Reducing Costs by Streamlining the Selection and Bidding of...
Transcript of Reducing Costs by Streamlining the Selection and Bidding of...
Reducing Costs by Streamlining the Selection and Bidding of Alternative Highway Drainage Pipe Systems
Michael Maher, Greg Hebeler (Golder), John Schuler (VDOT), Leslie McCarthy (Villanova) Moderators: Dr. Ed Harrigan (NCHRP), Colby Caywood (Golder Associates)
NCHRP 10-86 Team
Project Team, Partners, and Stakeholders
Golder Associates Bergmann Associates Dr. Ian Moore – Queen’s University NCHRP 10-86 Panel Members
State Agency Representatives (CA, MO, NE, PA, VA) AASHTO, FHWA, & TRB Representatives Pipe Industry Representatives (ACPA, NCSPA, PPI) Academic Researchers (U of Arkansas, Villanova) Consulting Engineer
All State Agencies
2
Presentation Outline
Introduction to Alternative Pipe Bidding Highlights from NCHRP 10-86 An Agency’s Perspective – VDOT Software as a Teaching Tool – An Academic Perspective
3
3
Introduction to Alternative Pipe Bidding Michael Maher
Infrastructure deficit is real and growing Agencies expected to do more with less Greater appreciation of life cycle costing – longer service
lives are less disruptive and save money More recognition of contractor innovation, e.g. greater use
of alternative project delivery
Realities
5
Increased competition will reduce cost If
• Product A has 5 suppliers • Product B has 8 suppliers • Product C has 7 suppliers
If project bid with Product A exclusively – 5 bidders If project bid allows Products A, B and C as alternatives, now opened up
to 20 bidders
Increased Competition
6
Increases competition (and reduces cost) within product supply industry but also may reduce construction costs, e.g. Product B may be quicker/cheaper to install at a particular site
Alternative Bidding
7
Difficulty of levelling the playing field for alternatives Push-back from some manufacturers/suppliers Increased engineering and design effort Increased performance risks Poor historic performance of particular product Failure to recognize/accept that different products may need different
construction or installation techniques Additional complexity with bid preparation Maybe only Product A is available in a market so why bother? Lack of familiarity with alternatives
Barriers to Alternative Bidding
8
“Alternate design/alternate bidding (ADAB) is a contracting process used in an increasing number of
state departments of transportation (DOTs). The process gives the contractor a choice to bid on either a concrete or an asphalt option, thereby increasing the number of
bidders on each job enhancing competition.”
Alternative Bidding for Pavements
9
Concrete vs. Asphalt as alternatives – well established Frequently strong agency preference for one or other Significant differences in service life, design details and costs – need
complex and controversial bid price adjustments Real differences in performance and economic comparisons based on
geography, climate, etc. – not always a straightforward comparison
Challenges to Implementation
10
Louisiana and Missouri: ⅓ more bids Kentucky: average 4.6 bids vs 2 bids Across states: 10% to 24% below engineer’s estimates vs 14% above to
17% below In individual states average winning bid was 5% to 24% below non AB
bid Indiana, Missouri, and Louisiana: average saving $2M per project Michigan: average $2M net savings after considering costs to
implement
Has it worked?
11
Ohio: In 2010, the average winning bid price for AB projects was 15%
below the engineer’s estimate By allowing bidders this tool, MoDOT has seen a 25 percent increase in
the number of bidders and cost savings of between 9-10%
Has it worked?
Ref: Alternative Design / Alternative Bid: A Survey of the Evidence www.leg.state.nv.us, ATRANS973L, 2013
12
“Economists and business professionals agree – competition is good for the consumer. When
consumers are presented with choices, they can select the product or service of preference, evaluating
their decision based on a number of factors, chiefly quality and value.”
Verdict
13
“This process allows the bidding contractors to select the pavement type to be constructed, rather than a DOT.
This not only eliminates any bias in the selection process, but also increases competition between paving industries. The end result is greater choice, lower costs, and enhanced innovation. In short, the competition that
ADAB fosters provides much better value for the taxpayer.”
14
Pipes are low cost items but very large design effort
• Structural design, hydraulic design, durability checks Pavements: 2 alternatives - Pipes: 50 - 100 alternatives How can equivalent service and value for money be evaluated and
compared easily? One pipe will last 20 years and another 100 years! Can market fairness for suppliers be achieved? Can performance and installation quality be achieved across the board? There are some bad products out there – can they be excluded? “Our jurisdiction has unique problems with abrasion – alternative bidding
won’t work for us.”
But will it work for drainage pipes?
15
Sound and robust engineering basis for design and performance
comparisons – AASHTO Concept of Design Service Life introduced to level playing field Must be automated by use of user-friendly software Must include engineering oversight Needs minimum product performance standards Must recognize product differences as well as installation differences Must incorporate post installation inspection as standard Needs support form pipe supply industry
Basic Principles
16
Comprehensive Alternative Pipe Selection Procedure implemented in 2007
First drainage projects through the system in 2009
Estimate drainage component costs reduced by ~10%
Positive feedback from contractors – product codes easy to understand
Negative feedback from one pipe supply sector
Minor increase in consulting engineering design charges
Reduction in design charges anticipated with future introduction of HiDISCD
Case Study – Ontario, Canada
Information provided by Mr. Art Groenveld, Senior Engineer, Drainage Design, MTO
17
The engineer must take into account these differences when designing a pipe
system using corrugated HDPE pipe. Failing to take these differences into account when designing and specifying products places the engineer at risk. Even if ultimately settled, engineers suffer great loss in the course of litigation—to their professional reputations, as well as to their pocketbooks. Engineers have a sworn duty to protect the health, safety and welfare of the public. Failure to heed this duty may result in an engineer being the responsible party with all the associated risk, liability and consequences.
This could result in not only monetary damages, but ultimately in the loss of the engineer’s license. Additionally, the engineer may be criminally responsible for any death(s) caused by poor engineering.
Challenges to Implementation: Scare Mongering
Ref: Read Between the Pipes, P.D. Galloway, Nielsen-Wurster Group, http://www.estormwater.com/read-between-pipes
18
A bill to ensure that all proven and acceptable piping materials be
included in bids for water and wastewater utility service improvement projects.
"Acceptable piping material" means piping material that meets the current recognized standards issued by ASTM international and the American Waterworks Association, or their successor organizations.
Ohio House Bill No. 417 (2014)
19
When contracting for a water or wastewater utility service improvement project, a governmental agency shall: (1) Procure only acceptable piping material; (2) Consider the quality, sustainability, durability, and corrosion resistance
of the acceptable piping materials in relation to the project requirements;
(3) Consider the up-front cost of installation of the acceptable piping materials;
(4) Consider acceptable piping material to be suitable for the project only if the use of that material is commensurate with sound engineering practices and the project requirements.
Intent of Bill
20
H.B. 417 defines "acceptable piping material" to mean “piping material that meets the current recognized standards issued
by ASTM international and the American Waterworks Association.” This language restricts water and wastewater utilities from developing and /or utilizing pipe specifications that are tailored to local and project specific needs and that
may not meet both AWWA and ASTM standards.
Concerns Raised
21
With regard to the municipal water and wastewater utility members of AWWA, H.B. 417 constitutes a significant
intrusion upon the powers of local self-government protected under the Home Rule and Municipal Utility Provisions of the
Ohio Constitution.
Bill Defeated
22
Act Concerning Specifications for Pipes Used by the Department of Transportation To expand the list of acceptable materials used by the Department of
Transportation All technically qualified pipes must be competitively bid. The Department must use established national standards to qualify the
design and construction of pipes. The design service life for storm drain and cross drain applications shall
be seventy-five years, and the design service life for side drain applications shall be fifty years.
House Bill No. 6739, State of Connecticut (2015)
23
Reduction in costs Improve quality Foster innovation, spurring economic growth Consolidation in the industry has reduced competition where single pipe
types are bid In CT in 2015:
90 highway projects - $525 M Drainage ~1% = $5 M Expect ~ $1M/year in savings
Perceived benefits of New Bill
Ref: Testimony in Support of House Bill 6739, by John Stelmokas, Advanced Drainage Systems Inc. , Hartfort, CT, Feb. 23, 2015
24
NCHRP Project 10-86 Highlights Greg Hebeler
Objective of NCHRP 10-86
Objective of NCHRP 10-86 is to develop a procedure suitable for adoption by AASHTO to guide owner-agencies in selecting drainage systems for highway projects.
This streamlined procedure, called the Recommended Practice, assists in design and selection of drainage pipe systems for highways.
Facilitate the selection of a wide range of technically suitable pipe options from a comprehensive list of available pipe systems.
Selection based on: Site characteristics Suitable hydraulic performance Adequate strength to resist deflection Appropriate Service life for application Constructability and performance
26
Specific Objectives and Tasks
Develop a highway drainage system evaluation and selection process that encompasses key factors: Technically Rational and Robust
Hydraulic, Structural, and Durability Incorporates Site Specific Conditions Mindful of Constructability & Operation & Maintenance Requirements Allows Confidence in and Tracking of Post-Construction Performance
Applying the process to field pilot projects in cooperation with DOTs Incorporate lessons learned into the Recommended Practice Develop an Implementation Plan for Adoption by AASHTO Map-21 Eliminated Previous Federal Mandate for Drainage System
Competition on Federal Aid Projects and Provided Agencies Autonomy
27
Benefits of Alternative Pipe Bidding
Highway drainage systems account for a significant portion of roadway infrastructure: 22% of bridge inventory, smaller culverts ~ every ¼ mile
Drainage Systems and Products are Rapidly Evolving with Innovative Research and Product Solutions National Standardization can reduce the burden on individual agencies to separately evaluate and approve each new technology integration with NTPEP, etc.
Increased Efficiency and Competition Reduced Costs Improved Reliability Encourages Innovation and Research
Facilitates Tracking of Infrastructure Inventory and Condition integrates with data management initiatives of SHRP2 and MAP-21
Possible to Maintain Agency Specific Flexibility and Autonomy, but Encourages Competition and Use of all Technically Sound Solutions
28
Identification of Gaps
Resources: NCHRP 20-07 Task 264, State DOT Survey, Literature Review, Other References / Discussions
Knowledge Gaps Design Service Life Consistency – Current NCHRP Synthesis Project Service Life Prediction and Evaluation –Durability Methods not Fully Mature Pipe Joint Evaluation – NCHRP 15-38 Installation Quality Assessment – Innovative Tech., Ongoing Research
Implementation Gaps Out of Date / Inconsistent Fill Height Tables Consideration of Entire Drainage System (Pipe, Backfill, Installation, etc.) Site Specific Consideration of Durability Not Common Practice Consistent and Timely Evaluation of New Pipe Products Unwarranted Exclusion of Pipe Systems (Historical or other Bias) Lack of Agreed National Standards Prevent Use of National Tools / System
29
Flowchart of Recommended Practice
30
Phase 1 Project
Definition
Phase 2 Technical Evaluation
Phase 3 Final
Checks
Roadway & Geometrical
Hydrology & Waterway
Geotechnical & Environmental
Inventory of Available Pipe
Systems
Hydraulic
Structural
Durability
Agency Policies
Phase 4 Results & Bidding
Results Matrix
Bid Documents
Inventory Results
Phase 5 Installation, Maintenance & Tracking
Material & Construction QA
Post-Installation Inspection
Maintenance & Tracking
Final Design A
B
C
D Performance
Feedback System Feedback
30
NCHRP PROJECT 10-86 WEBINAR
NCHRP 10-86 Select DOT Survey Results
31
Current Practice DOT Survey
No Response from DOT
32
DOT Survey – Alternative Bidding
33
‘Guesstimate’ of Pipe Type Usage
34
Diversity Among States
35
DOT Survey - Fill Height Tables
36
Inconsistency in Fill Height Tables
37
24” 36” 36” 48” 2-2/3 x ½ Inch Corrugations
2-2/3 x ½ Inch Corrugations
3 x 1 Inch Corrugations
3 x 1 Inch Corrugations
Mean 90 69 74 67
Max 191 127 147 110
Min 20 14 27 23
Range 171 113 120 87
Maximum Fill Height: Galvanized CMP,
12 gauge
24” 36” 48” Low Quality
Bedding High Quality
Bedding Low Quality
Bedding High Quality
Bedding Low Quality
Bedding High Quality
Bedding
Mean 14.7 18 14.4 18 14.5 18
Max 27 39 26 35 26 35
Min 7.9 10 7.9 10 7.9 10
Range 19.1 29 18.1 25 18.1 25
Maximum Fill Height RCP, Class III (1350D)
HDPE (Type S) PVC (Profile Wall)
24” 36” 48” 24” 36” 48”
Mean 19.6 18.6 17 29.9 28.5 21.5
Max 40 40 40 58 56 40
Min 10 10 10 15 15 15
Range 30 30 30 43 41 25
Maximum Fill Height Thermoplastic Pipes
Example Range of Fill Heights - CMP
38
Example Range of Fill Heights - RCP
39
Example Range of Fill Heights - HDPE
40
NCHRP PROJECT 10-86 WEBINAR
NCHRP 10-86 Select Pilot Project Results
41
Pilot Projects
During the pilot process, we implemented the RP across 9 Agency policies (CalTrans, FDOT, MDOT, MoDOT, MTO, NDOR, NYSDOT, PennDOT, and VDOT). MoDOT and PennDOT supplied real-life current projects for study and comparison.
RP was simple to apply across this range of Agency policies provides confidence in the broad flexibility and applicability of the proposed process.
Results were easily incorporated into current bidding processes. Process uses existing design tools and processes as the base –
comfortable for designers to implement hydraulic and structural evaluation phases.
Durability evaluation will likely be new to most designers and will take more adjustment period to gain comfort and design feel.
Manual implementation of alternative bidding was achievable but cumbersome.
42
Pilot Projects – Structural Comparison
43
Pipe Material CalTrans FDOT MDOT MoDOT MTO NDOR NYSDOT PennDOT VDOT RCP 24 24 24 24 24 24 24 24 24 Metal (Corrugated or Spiral Rib) 24 24 24 24 24 24 24 24 24
Polyethylene (HDPE) 24 24 24 24 24 24 24 24 24
Polyvinyl-Chloride (PVC) 24 24 24 24 24 24 N/A 24 24
Pipe Material CalTrans FDOT MDOT MoDOT MTO NDOR NYSDOT PennDOT VDOT
RCP 24 24 24 24 24 24 24 24 24 Metal (Corrugated or Spiral Rib) X X X X 24 X X 24 24
Polyethylene (HDPE) X X X X 24 X X 24 24
Polyvinyl-Chloride (PVC) X X X X 24 X N/A 24 24
Pipe Material CalTrans FDOT MDOT MoDOT MTO NDOR NYSDOT PennDOT VDOT
RCP 24 24 24 24 24 24 24 24 24 Metal (Corrugated or Spiral Rib) 24 24 24 24 24 24 24 24 24
Polyethylene (HDPE) X X X X 24 24 X X X
Polyvinyl-Chloride (PVC) 24 X X 24 24 24 NA X X
Average Fill 10 ft
Low Fill 2.5 ft
Moderate Fill 22 ft
Pilot Projects – Durability Comparison
44
Condition pH Resistivity (ohms-cm)
Sulfates (ppm)
Chlorides (ppm)
Design Value 7.5 2000 250 25 “Moderate” 6.5 1000 500 50 “Aggressive” 4.5 500 1000 100
Environmental parameters varied to more thoroughly trial the DRP Two additional hypothetical cases introduced (moderate and aggressive)
Typical Soil and Water Values
Soil Corrosiveness and Resistivity
Pilot Projects – Metal Durability
45
Condition CALTRANS Polymer +30 Polymer +40 Polymer +50 Design Value 54 84 94 104 Moderate 19 49 59 69 Aggressive 0 30 40 50
Steel – Plain Galvanized and Polymer Coated
Condition FDOT Design Value 78 Moderate 43 Aggressive 0
Aluminized Type 2 Durability is key aspect in pipe selection
Definition of failure not standardized Polymer coatings contribute
significantly to service life
All values shown are EMSL (years)
Pilot Projects – Concrete Durability
46
Condition Hurd Hadipriono ODOT Florida Design Value > 500 96 > 500 113 Moderate > 500 86 > 500 88 Aggressive > 500 60 153 58
Wide variation between methods Local calibration of methods suggested Engineering judgment must be applied
Table of Predicted Estimated Material Service Life (years)
Key Findings of Pilot Projects
Widespread adoption of alternative bidding will likely require automation of some kind, either industry developed or nationally/agency funded Existing automated routines, e.g. CalTrans, FDOT and MTO, etc.
each have some good features but none is completely flexible or adaptable to all agencies.
Widespread and standardized adoption would be aided by further national standardization of design criteria and pipe system requirements Development and Maintenance of a National Pipe Product Inventory Harmonized and Standardized Backfill Requirements Harmonized and Standardized Installation Requirements Development of Structural Thermoplastic Pipe Classes Standardized Design Service Life Criteria
47
Technical Evaluation Commentary
Hydraulic Design Discussion
49
Hydraulic Design Methods are fundamentally standard across Agencies. RP proposes to utilize generic roughness categories to streamline
design, one potential choice of categories is: Default Smooth n (e.g. 0.012) Default Corrugated n (e.g. 0.024)
If a different or more rigorous category classification scheme is desired, more categories can be used based on Agency guidelines.
The use of hydraulic equivalency charts is recommended for consideration of individual pipe system roughness values if desired.
Structural Design Discussion
50
Use of fill height tables is universal SOP across Agencies. Significant variation in structural design assumptions and incorporation of
LRFD still exist. Application of RP would help to standardize designs.
Durability Design Discussion
51
Durability design is not fully mature, some ongoing research but a lack of in-service performance databases may be limiting progress. RP recommends service life tracking to promote advances in EMSL methods. RP is intended to allow for easy incorporation of advances in
abrasion/corrosion evaluation methods.
RP Encourages site specific measurement of environmental conditions and use of site specific performance information.
RP recommends incorporate abrasion into EMSL evaluations. Currently recommends use of CALTRANS abrasion method
RP currently does not provide recommendations for default durability methods, as SOP has not identified universally preferred methods.
NCHRP 10-86 Conclusion and Acknowledgements
52
Concluding Thoughts
Pilot Projects Provided Significant Additional Insight into the Current State of Practice to Guide Finalization of the DRP and Aid Implementation.
The DRP was comprehensive yet flexible and adaptable framework able to work across all piloted agency standards.
Encourage, streamlined, technically sound, and consistent approach to pipe system selection. Integrated use of best available practices.
Flexible and expandable framework enabling modification as new methods and materials are developed and customization to address individual agency needs.
Greater national standardization would reduce redundant efforts across agencies and aid implementation of RP.
Several agencies remain interested in project and alternative bidding following removal of federal mandate in MAP-21.
53
Acknowledgements
We would like to thank all participating agencies (California, Florida,
Michigan, Missouri, Nebraska, New York, Pennsylvania, and Virginia) for their time and willing partnership during the pilot project phase of the project.
In particular, MoDOT and PennDOT for making actual projects available for pilot project process.
NCHRP 10-86 Panel Members for their time, encouragement, and feedback.
Ed Harrigan, Anthony Avery and the entire NCHRP Staff! The role of federal and state agencies in developing much of the
knowledge related to alternative pipe system selection is gratefully acknowledged.
54
General Software Commentary
Software Design Guiding Principles
The software should: Be simple and clean to the extent possible Be visually appealing and intuitive Be technically accurate (with admitted simplifications for certain
design elements) Provide unbiased (apples to apples) comparisons / evaluations. Provide a useful tool to fill a needed gap in the industry Minimize the number of screens required to complete each
module and the entire design process Make all non-critical entries optional Move meta-data / non-critical data and entries to secondary
screens as needed for de-cluttering Be useful and “fun” (or at least “not painful”) to use
56
Software Mock-Up Demonstration
Current Mock-Up Theme
These slides demonstrate the current version of the software status – will evolve with the project and after Alpha and Beta testing.
57
Software Navigation Bar Features
Completed Module
Active Module
Pending Module
PREV NCHRP ADPS Software Start Hydraulic Final Structural
NEXT Durability
Active Multi-Step Module
Access to Admin, Login/Logout, Help and Home Buttons Available Throughout
User Selection or Required Field
Software Calculated Value
User Entry Field
? Logout Admin
? Logout Admin
The header / navigation bar maintains form throughout the software application. It is intended to easily allow users to jump between / directly to desired individual modules while providing a visual tracking display of progress and easy access to key administrative pages (e.g. help, login/out, etc.)
58
Design Module Panel Layout
Functional Pane
Functional Pane Occupies
Left 60% of Screen for Technical Modules Entire Screen for Administrative Modules
Area for User Entries, Calculated Outputs
& Other Software Functional Elements
Functional Pane Header
Information
Pane
User selects visible information via button
selection
Additional information / help available via “?” Button
Schematic Background Results Matrix
PREV Module Header Project: Culvert:
Final Structural NEXT
Durability Start Hydraulic
? Logout Admin
59
Highway 101
Small Creek Crossing
Highway 101Highway 101
Small Creek Crossing
Highway 101Highway 101
Small Creek Crossing
Highway 101Highway 101Highway 101
Small Creek Crossing
Highway 101Highway 101Highway 101
Small Creek Crossing
Highway 101
Example Design Module Page In
clud
ed
Pipe Roughness
Class
Default Manning’s
Value
User Calculated Min. Pipe Diameter C
alcu
late
Eq
uiva
lenc
y
Inlet or Outlet Controlled
User Defined
Maximum Diameter
Corrugated 0.024 Inlet Outlet
Smooth 0.012 Inlet Outlet
Ultra Smooth 0.009 Inlet Outlet
Steel Plate 0.032 Inlet Outlet
User Defined Inlet Outlet
Hydraulic Design Inputs
Add Hydraulic Schematics
Schematic Background Results Matrix US (Inches) Metric (mm)
Please note that the software does NOT perform hydraulic analysis, rather it simply compares the hydraulic capacity (via diameter and roughness) of each available pipe system based upon the design information entered.
PREV Hydraulic Design Final Structural
NEXT Durability Start Hydraulic
? Logout Admin
Project: Culvert:
60
Enter Hydrologic Metadata
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40 40
40
40
40
40
40
40
40
40
40
40
Enter Hydraulic Design Metadata
Use Manning's Equation Calculator
Small Creek Crossing
Highway 101
Simple Manning’s Calculator
61
Additional Considerations:
Slope (ft./ft.):
Design Inflow cfs:
Wetted Perimeter (feet):
Hydraulic Radius (feet):
Area (feet2):
Calculated Diameter (inches):
Manning’s n value:
Imperial Metric
Hydrologic Design Metadata
Drainage Area (mi2)
Design Inflow (ft3)/s
Design Storm (years)
Check Storm (years)
Allowable Headwater (H/D)
Maximum Allowable
Velocity (fps) Minimum Allowable
Velocity (fps) Minimum Regulated
Diameter
Manning’s Calculator
**Assumes full pipe flow and does not consider end treatments. Refer to HY-8 for full hydraulic design
Hydrology Manning’s Agency Criteria
The calculation of the diameter assumes full pipe flow. The Manning’s equation is generally given as a function of roughness, slope, and geometry, and is described in greater detail in : http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_801.pdf.
PREV Final Structural
NEXT Durability Start Hydraulic
? Logout Admin
Project: Culvert:
Hydraulic Design
Schematic Background Results Matrix
Future Watershed Changes
Aquatic Organism Passage
Return to Design M odule
Hydraulic M etadata 2/2
Calculate Diameter
Manning's Equation
Small Creek Crossing
Highway 101
Durability Design Module – Abrasion
62
Durability Data Inputs
Abrasion Data Select Design Conditions Bed Load None or
Silt/Clay Moderate to Gravel
Moderate to Cobble
Moderate Angular
Heavy Rounded
Heavy Angular
Flow
Ve
loci
ty
(ft/s
)
Smooth n = 0.12 < 5 5 to 8 8 to 12 12 to 15 15 to 20 < 20
Corrug. n = 0.24 < 5 5 to 8 8 to 12 12 to 15 15 to 20 < 20
User n --- < 5 5 to 8 8 to 12 12 to 15 15 to 20 < 20
CALTRANS Level I II III IV V VI
FHWA Abrasion Level I II III IV
Coating
PREV
? Start Hydraulic Final Structural
NEXT Durability
Caltrans Level FHWA Coating
Schematic Information Results Matrix
The CALTRANS abrasion evaluation methodology is considered to be the most comprehensive. CALTRANS defines six levels of abrasion for preliminary estimation of abrasion potential based on flow velocities and bed load characteristics. Recommended abrasion guidance in regards to the CALTRANS methodology can be found in more detail in: http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_801.pdf.
Project: Culvert:
Durability Design
Asphalt Coated
Caltrans Level
Small Creek Crossing
Highway 101
Example Results Matrix
63
An Agency’s Perspective – VDOT John Schuler
VDOT Pipe Selection Experience (Contractor selection of Engineer determined alternates)
October 22, 2015 John Schuler, PE
Materials Program Manager, CO Materials
804.328.3140, [email protected]
VDOT Pipe Selection Experience
Agenda • Brief Overview • Selection Process
• Standard Drawing Requirements • Typical Plan Sheet for Pipe Alternates
• 2014-2015 Re-evaluation of Selection Process • Pros and Cons of Contractor Selection of Engineer Determined
Alternates • Participation in 10-86A Software Evaluation
66
Brief Overview
For over 12 years VDOT has been allowing the Contractor to choose from Engineer determined alternates.
• In project design, Engineer determines ALL allowable pipe types for
given location (concrete, corrugated metal, plastic).
• Selection criteria and process documented in our Standard Drawings to give a specified service life (50 or 75 yrs). Mostly concerned with pH, resistivity, and abrasion.
67
Selection Process
Bridge size culverts handled by Bridge Division/District Bridge Section
Concrete or Plastic Pipe – All Locations, 75-yr Service Life
Metal Pipe – Determine Location and Service Life
Table B of PC-1 for local exclusions check
Table C of PC-1 for velocity check (2” rock abrasion estimate)
Table D of PC-1 for gauge thickness for required service life
Table C of PC-1 for pH and resistivity check
Check Hydraulics
Check Cover Fills in PC-1
Select Joint Type from Approved List 14
Obtain Local OK
Notify Bridge Section if >7 ft diameter pipe replaced
Contractor selects pipe type if more than one allowed option
Engineer determines Allowable Pipe Types
68
Standard Drawing Requirements
69
Standard Drawing Requirements
70
Standard Drawing Requirements
71
Typical Plan Sheet for Pipe Alternates
72
VDOT is just completing a 2-year re-evaluation of our selection process. We looked at changing from Contractor selection of Engineer determined alternates to Engineer selection of just 1 pipe type per location.
We decided to stay with our current Contractor selection of Engineer determined alternates process, but did make several revisions. Most notably:
Allow local-decision making at Residency/Locality level. Engineer will also select joint types from an Approved List using
AASHTO PP-63 categories, update Specifications to reflect this. Revisions to pH, resistivity, abrasion. Defined service life and how to obtain. Updated cover tables from ASD to LRFD.
2014-2015 Re-evaluation of Selection Process
73
Pros and Cons of Contractor Selection of Engineer Determined Alternates VDOT is staying with Contractor selection of Engineer determined
alternates.
Pros: Engineer selection of 1-3 pipe types per location assures best material
type and service life for the location. Contractor selection from among these alternates assures best price. Service life determination straightforward. Life cycle costing not required. Joints, a significant element to achieving functionality and service life,
are addressed. Locality selection in line with other infrastructure decisions on local
assistance jobs. Documented residency selection allowed.
74
Pros and Cons of Contractor Selection of Engineer Determined Alternates
VDOT is staying with Contractor selection of Engineer determined alternates.
Cons: Cannot track bid prices of individual pipe types. Difficult to track pipe type usage.
75
Participation in 10-86A Software Evaluation
VDOT will participate in evaluating the 10-86A project software.
Experienced drainage engineer will evaluate.
VDOT may find beneficial use of the software.
76
An Academic Perspective Leslie McCarthy
NCHRP Project 10-86A: Software for Bidding Alternative Drainage Pipe Systems Reducing Costs by Streamlining the Selection and Bidding of Alternative Highway Drainage Pipe Systems: Educational Perspective Leslie McCarthy, Ph.D., P.E. Associate Professor Civil & Environmental Engineering
Outline of Webinar Presentation
Objectives Commitment from Academia Curricular Strategies Educational Application of NCHRP
Project 10-86A: Software for Bidding Alternative Drainage Pipe Systems
Closing Remarks
79
Objectives
To educate engineering students in recognizing and embracing the idea of pipe systems as a critical part of our nation’s transportation infrastructure
Photo courtesy of Michael Pluimer
Introduce the concept and need for fiscal responsibility and life cycle considerations in design of pipe systems for highways
80
How to go about it?
One university’s approach…
81
Commitment from academia
Need support from the Department of Civil Engineering
Latitude to incorporate real issues such as pipe selection into curriculum in a meaningful way Sponsorship for field trips in which students are able to see the real impacts
Need engagement from the College of Engineering
Foster network of employers in highway design-related sectors
Encourage student placement in internships
82
Commitment from academia
GET FACULTY EDUCATED! Attend ASCE, State DOT, or TRB-sponsored training Participate in regional and national conferences related to the design
and construction of pipe systems Join committees at ASTM or TRB that deal with pipe issues
Photo courtesy of Michael Pluim
83
Curricular Strategies
1. Engineering Economics- - required course for juniors Introduces calculation of benefits/costs of infrastructure components - - uses CalTrans cost data for real-life projects 2. Transportation Facilities Design - - design elective for seniors Includes design of highways and pipe systems - - uses CalTrans Alt-Pipe software 3. Senior Capstone Design in Transportation - - design elective for seniors Includes semester-long design project that includes a large portion related to highway design 4. Design of Sustainable Transportation Systems - - graduate level course More in-depth course which challenges graduate students with incorporation of sustainable practices in design of highways and passenger rail systems 5. Civil Engineering Materials - - graduate level course Introduces graduate students to material properties of various types of pipes
Opportunities for Use of NCHRP Project 10-86A: Software for Bidding Alternative Drainage Pipe Systems
84
Curricular Strategies
Example: Undergraduate Senior-Level Facilities Design Course
85
Curricular Strategies
Overview of pipe applications Factors in Selecting Pipes Pipe Selection Process Types of drainage pipes
Reinforced Concrete Pipe Corrugated Metal Pipe Plastic Pipe (PVC and HDPE)
Caltrans Alt-Pipe Trials
Outline of What’s Currently Covered
86
Highway Pipe Applications
Culverts Storm Drains
Photos courtesy of Michael Pluimer
87
Factors in Selecting Drainage Pipes
Cost Materials
Pipe, soils
Installation Service conditions
Soil properties / depth Water properties / depth
Durability / Service life Joint performance
Structural capacity Cover depth Minimum and maximum
Hydraulic capacity Roughness of inner wall
of pipe surface Availability
Related to cost (shipping) Ease of installation
Slide courtesy of Michael Pluim
88
Types of Highway Drainage Pipe
Reinforced Concrete Pipe Corrugated Metal Pipe
Several different types and alternatives Plastic Pipe
Corrugated HDPE Corrugated PVC Corrugated PP Solid wall HDPE and PVC
Slide courtesy of Michael Pluimer
89
Process for Selecting Pipes
Review requirements of application Hydraulic analysis Structural requirements – minimum /
maximum cover Soil type and characteristics
Review available pipe types Tools for selecting pipe for design in highways e.g., NCHRP Project 10-86A; Caltrans Alt-Pipe
Slide courtesy of Michael Pluimer
90
Educational Application of NCHRP 10-86A: Software for Bidding Alternative Drainage Pipe Systems NCHRP 10-86 – Bidding Alternative Drainage Pipe Systems
Outcomes of the Research Developed guide to identify potential pipe systems that meet criteria
for design Pipe systems evaluated based on hydraulic and structural capacity
as well as durability (estimated service life) Software tool
91
Process for Alternate Pipe Bidding using NCHRP Project 10-86 Approach
Slide courtesy of Michael Pluimer
92
NCHRP Project 10-86
Establishes final matrix showing pipe types that meet all criteria for a given design
Slide courtesy of Michael Pluimer
93
NCHRP Project 10-86
94
Class Exercise: Caltrans Alt-Pipe Trials
95
Take Home: Caltrans Alt-Pipe Trials
96
Create active learning opportunities for students to apply the 10-86A tool Coordinate with State DOT or Consultants on providing real-life project info
on which to base the educational assignments
Educational Application of NCHRP 10-86A: Software
Image courtesy of Golder Assoc.
97
Closing Remarks
Create active learning opportunities in multiple courses in order to best facilitate retention of use of the NCHRP 10-86A new tool
Seek opportunities not only at 4-year universities, but focus also on curricular development at 2-year technical colleges and community colleges
Increase success by supplementing coursework with real-world opportunities and eventual job placement
98
THANK YOU FOR YOUR ATTENTION
CONTACT INFORMATION
Leslie McCarthy, Ph.D., P.E. Associate Professor, Civil & Enviro. Engineering Villanova University PH: 610-519-7917 Email: [email protected]
99
Thank You Q&A Session
100