Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR...

49
Redditch Branch Enhancement

Transcript of Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR...

Page 1: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Redditch Branch Enhancement

Page 2: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Introduction

• Roger Clarke – NWR Project Manager• Bob Aldridge – NWR Scheme Project Mgr• Marc Riley – BGCL Contracts Manager• Dominic Eldridge – BGCL Project Manager• Susan Fisher – LM Estates Manager• Karen Allington – LM Bus Replacement

Page 3: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Focus of Presentation

• Provide information on forthcoming works (4x29hr weekend possessions & 8 week blockade).

• Advise what alternative transport arrangements are proposed whilst the train service is disrupted.

• Meeting will not centre on previous complaints – purpose is to be “informative”.

Page 4: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Scheme Details• Install a 3km length of passing loop between Alvechurch and Redditch• Aim to increase capacity on the Redditch Branch Line from 2 to 3 trains per

hour

Main Lines

Redditch Branch

Page 5: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.
Page 6: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Existing LayoutNorth to Barnt Green Station South to Redditch Station

Alvechurch Station O/Br. 12 Grange Lane

O/Br.10 Station RoadCutting

Embankment

54 MP53 ¼ MP 55 MP 55 ¼ MP

Page 7: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Proposed Layout

North to Barnt Green Station South to Redditch Station

Alvechurch Station

New Up Line

Down Line

New Platform & Footbridge

54 MP53 ¼ MP 55 MP 55 ¼ MP

Page 8: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Existing Arrangement

Page 9: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Proposed Arrangement

Page 10: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Alvechurch Station 1950s

Page 11: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Alvechurch Station Existing

Looking South towards Redditch

Page 12: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Alvechurch Station Proposed

New Up Line

New Footbridge & LiftsNew OLE

Looking South towards Redditch

Page 13: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Grange Lane Existing

Looking North towards Alvechurch

Page 14: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Grange Lane Proposed

Looking North towards Alvechurch

New Up Line

New OLE

Page 15: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

29 Hour Possessions• Week 11 – 00:10 Sun 8th June to 05:30 Mon 9th June

• Installation of OLE gantries to South• Delivery of points to Alvechurch• Installation of track drainage through station• Placement of bottom ballast • Installation of OLE foundations

• Week 12 - 00:10 Sun 15th June to 05:30 Mon 16th June• Installation of OLE gantries to South to mid-point• Delivery of points to Weights Lane• Installation of track drainage south of station• Placement of bottom ballast • Delivery of station footbridge• Installation of OLE foundations

Page 16: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

29 Hour Possessions• Week 13 – 00:10 Sun 22nd June to 05:30 Mon 23rd June

• Installation of OLE gantries to Mid-point to north of Grange Lane• Placement of bottom ballast • Installation of OLE foundations• Wingwall retaining wall to Overbridge at Station Road

• Week 14 - 00:10 Sun 29th June to 05:30 Mon 30th June• Installation of OLE gantries to Grange Lane to Alvechurch• Placement of bottom ballast • Wingwall retaining wall to Overbridge at Station Road

Page 17: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Blockade Works• Install new signal panel at Saltley PSB• Removal of 72 no. OLE gantries & cantilevers• Removal of 85 no. existing OLE foundations• Relay 1500m of existing track on Down Line• Slew 1700m of existing track on Down Line• Install new 3000m track.• Install S&C (2no.) • 10 no. engineering trains• 12 no. tamping shifts• Install 116 no. OLE gantries - 7900m of wire runs• Install signalling equipment • Install CCTV, PA systems, CIS etc at Station• Testing & commissioning• Open Line & Station

Page 18: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Working next to Existing Line

Existing Track

Existing OLE Gantries

NewOLE Gantries

Foundation Excavation Exclusion Zone

Bottom ballast installed prior to blockade

Page 19: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Redditch Branch Enhancement

Blockade Works

Page 20: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Alvechurch53.40

Kings Norton46.59

Longbridge49.12

Northfield48.12

Barnt Green51.67

Redditch56.60

Five Ways43.18

University 44.73

Selly Oak45.50

Bournville46.58

Hazelwell45.07

Stage 2b – Blockade WorksMain Blockade Works

• Blockade Shortened back to Redditch Branch Only.

52.40

Area affected by works

Page 21: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Blockade Overview

Page 22: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Week 1 & 2 of the Blockade

03:45 Mon – 03:45 Wed

03:45 Wed – 03:45 Sun

00:45 Sun – 05:45 Mon

03:45 Wed – 03:45 Fri

19:45 Fri – 04:15 Sat

04:15 Sat – 04:15 Tue

04:15 Sat – 18:15 Sat

04:15 Tue– 18:15 Sat

Page 23: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Week 3 to 6 of the Blockade

13:15 Sun– 12:00 Thu

04:00 Sat – 12:00 Fri

Page 24: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Weeks 7 to 8 of the Blockade

04:45 Mon – 04:00 Mon

Page 25: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Remove OLE8 Week Blockade

• Isolation to include Barnt Green Station – first 27hrs only• Install Earth Section & Remove OLE (2 Days)

Week 1

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 26: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Gantry Removal8 Week Blockade

Week 1 - 2

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 27: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Thimble North Rails (570m)

8 Week Blockade

Week 1

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 28: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Remove North Sleepers8 Week Blockade

Week 1

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 29: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Excavate to Formation8 Week Blockade

Week 2

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 30: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Place Bottom Ballast8 Week Blockade

Week 2

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 31: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Install S&C via PEMS8 Week Blockade

Week 2

South to Redditch Station

North to Barnt Green Station

UPSIDE

DOWNSIDE

54 MP53 ¼ MP 55 MP 55 ¼ MP

Page 32: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Install North Sleepers8 Week Blockade

Week 2

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 33: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Install North Rails8 Week Blockade

Week 2

South to Redditch Station

North to Barnt Green Station

UPSIDE

DOWNSIDE54 MP53 ¼ MP 55 MP 55 ¼ MP

Page 34: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Install S&C via PEMs8 Week Blockade

Week 2

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 35: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Install South Sleepers8 Week Blockade

Week 2

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 36: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Install South Rails8 Week Blockade

Week 2

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 37: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

1 of 2 No. Autoballasters8 Week Blockade

Week 3

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 38: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Tamp Down Line incl. S&C8 Week Blockade

Week 3

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 39: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Rail Drop

8 Week Blockade

Week 3

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 40: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

1 of 2 Sleeper Trains

8 Week Blockade

Week 3

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 41: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Thimble Rail to Up Line

8 Week Blockade

Week 3

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 42: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

1 of 3 Ballast Trains

8 Week Blockade

Week 3

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 43: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Tamp Up Line

Week 3

South to Redditch Station

North to Barnt Green Station

8 Week Blockade

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 44: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Install Cantilevers & RC

Week 4 & 5

South to Redditch Station

North to Barnt Green Station

8 Week Blockade

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 45: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Install Catenary & Contact

8 Week Blockade

Week 5 & 6

South to Redditch Station

North to Barnt Green Station

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 46: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Autoballasters

Week 6

South to Redditch Station

North to Barnt Green Station

8 Week Blockade

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 47: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Final Tamp

Week 6

South to Redditch Station

North to Barnt Green Station

8 Week Blockade

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 48: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Final OLE Adjustments

Week 6

South to Redditch Station

North to Barnt Green Station

8 Week Blockade

54 MP53 ¼ MP 55 MP 55 ¼ MP

UPSIDE

DOWNSIDE

Page 49: Redditch Branch Enhancement. Introduction Roger Clarke – NWR Project Manager Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr.

Communications with NWR

• All communications will be via the help line:-

08457 11 4141

Public Relations team have been advised of forthcoming works and will be able to provide updated information.