Redditch Branch Enhancement
Introduction
• Roger Clarke – NWR Project Manager• Bob Aldridge – NWR Scheme Project Mgr• Marc Riley – BGCL Contracts Manager• Dominic Eldridge – BGCL Project Manager• Susan Fisher – LM Estates Manager• Karen Allington – LM Bus Replacement
Focus of Presentation
• Provide information on forthcoming works (4x29hr weekend possessions & 8 week blockade).
• Advise what alternative transport arrangements are proposed whilst the train service is disrupted.
• Meeting will not centre on previous complaints – purpose is to be “informative”.
Scheme Details• Install a 3km length of passing loop between Alvechurch and Redditch• Aim to increase capacity on the Redditch Branch Line from 2 to 3 trains per
hour
Main Lines
Redditch Branch
Existing LayoutNorth to Barnt Green Station South to Redditch Station
Alvechurch Station O/Br. 12 Grange Lane
O/Br.10 Station RoadCutting
Embankment
54 MP53 ¼ MP 55 MP 55 ¼ MP
Proposed Layout
North to Barnt Green Station South to Redditch Station
Alvechurch Station
New Up Line
Down Line
New Platform & Footbridge
54 MP53 ¼ MP 55 MP 55 ¼ MP
Existing Arrangement
Proposed Arrangement
Alvechurch Station 1950s
Alvechurch Station Existing
Looking South towards Redditch
Alvechurch Station Proposed
New Up Line
New Footbridge & LiftsNew OLE
Looking South towards Redditch
Grange Lane Existing
Looking North towards Alvechurch
Grange Lane Proposed
Looking North towards Alvechurch
New Up Line
New OLE
29 Hour Possessions• Week 11 – 00:10 Sun 8th June to 05:30 Mon 9th June
• Installation of OLE gantries to South• Delivery of points to Alvechurch• Installation of track drainage through station• Placement of bottom ballast • Installation of OLE foundations
• Week 12 - 00:10 Sun 15th June to 05:30 Mon 16th June• Installation of OLE gantries to South to mid-point• Delivery of points to Weights Lane• Installation of track drainage south of station• Placement of bottom ballast • Delivery of station footbridge• Installation of OLE foundations
29 Hour Possessions• Week 13 – 00:10 Sun 22nd June to 05:30 Mon 23rd June
• Installation of OLE gantries to Mid-point to north of Grange Lane• Placement of bottom ballast • Installation of OLE foundations• Wingwall retaining wall to Overbridge at Station Road
• Week 14 - 00:10 Sun 29th June to 05:30 Mon 30th June• Installation of OLE gantries to Grange Lane to Alvechurch• Placement of bottom ballast • Wingwall retaining wall to Overbridge at Station Road
Blockade Works• Install new signal panel at Saltley PSB• Removal of 72 no. OLE gantries & cantilevers• Removal of 85 no. existing OLE foundations• Relay 1500m of existing track on Down Line• Slew 1700m of existing track on Down Line• Install new 3000m track.• Install S&C (2no.) • 10 no. engineering trains• 12 no. tamping shifts• Install 116 no. OLE gantries - 7900m of wire runs• Install signalling equipment • Install CCTV, PA systems, CIS etc at Station• Testing & commissioning• Open Line & Station
Working next to Existing Line
Existing Track
Existing OLE Gantries
NewOLE Gantries
Foundation Excavation Exclusion Zone
Bottom ballast installed prior to blockade
Redditch Branch Enhancement
Blockade Works
Alvechurch53.40
Kings Norton46.59
Longbridge49.12
Northfield48.12
Barnt Green51.67
Redditch56.60
Five Ways43.18
University 44.73
Selly Oak45.50
Bournville46.58
Hazelwell45.07
Stage 2b – Blockade WorksMain Blockade Works
• Blockade Shortened back to Redditch Branch Only.
52.40
Area affected by works
Blockade Overview
Week 1 & 2 of the Blockade
03:45 Mon – 03:45 Wed
03:45 Wed – 03:45 Sun
00:45 Sun – 05:45 Mon
03:45 Wed – 03:45 Fri
19:45 Fri – 04:15 Sat
04:15 Sat – 04:15 Tue
04:15 Sat – 18:15 Sat
04:15 Tue– 18:15 Sat
Week 3 to 6 of the Blockade
13:15 Sun– 12:00 Thu
04:00 Sat – 12:00 Fri
Weeks 7 to 8 of the Blockade
04:45 Mon – 04:00 Mon
Remove OLE8 Week Blockade
• Isolation to include Barnt Green Station – first 27hrs only• Install Earth Section & Remove OLE (2 Days)
Week 1
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Gantry Removal8 Week Blockade
Week 1 - 2
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Thimble North Rails (570m)
8 Week Blockade
Week 1
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Remove North Sleepers8 Week Blockade
Week 1
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Excavate to Formation8 Week Blockade
Week 2
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Place Bottom Ballast8 Week Blockade
Week 2
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Install S&C via PEMS8 Week Blockade
Week 2
South to Redditch Station
North to Barnt Green Station
UPSIDE
DOWNSIDE
54 MP53 ¼ MP 55 MP 55 ¼ MP
Install North Sleepers8 Week Blockade
Week 2
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Install North Rails8 Week Blockade
Week 2
South to Redditch Station
North to Barnt Green Station
UPSIDE
DOWNSIDE54 MP53 ¼ MP 55 MP 55 ¼ MP
Install S&C via PEMs8 Week Blockade
Week 2
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Install South Sleepers8 Week Blockade
Week 2
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Install South Rails8 Week Blockade
Week 2
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
1 of 2 No. Autoballasters8 Week Blockade
Week 3
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Tamp Down Line incl. S&C8 Week Blockade
Week 3
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Rail Drop
8 Week Blockade
Week 3
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
1 of 2 Sleeper Trains
8 Week Blockade
Week 3
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Thimble Rail to Up Line
8 Week Blockade
Week 3
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
1 of 3 Ballast Trains
8 Week Blockade
Week 3
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Tamp Up Line
Week 3
South to Redditch Station
North to Barnt Green Station
8 Week Blockade
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Install Cantilevers & RC
Week 4 & 5
South to Redditch Station
North to Barnt Green Station
8 Week Blockade
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Install Catenary & Contact
8 Week Blockade
Week 5 & 6
South to Redditch Station
North to Barnt Green Station
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Autoballasters
Week 6
South to Redditch Station
North to Barnt Green Station
8 Week Blockade
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Final Tamp
Week 6
South to Redditch Station
North to Barnt Green Station
8 Week Blockade
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Final OLE Adjustments
Week 6
South to Redditch Station
North to Barnt Green Station
8 Week Blockade
54 MP53 ¼ MP 55 MP 55 ¼ MP
UPSIDE
DOWNSIDE
Communications with NWR
• All communications will be via the help line:-
08457 11 4141
Public Relations team have been advised of forthcoming works and will be able to provide updated information.