Network Diagram

Transcript of red zuma

  • 5/21/2018 red zuma

    1/3

    SUBMITTED BY:-

    PROJECT MANAGEMENT

    RED ZUMA

    PROJECT

  • 5/21/2018 red zuma

    2/3

    TASK ID

    1 MARKET ANALYSIS

    2 PRODUCT DESIGN

    3 MANUFACTURING STUDY

    4 PRODUCT DESIGN SELECTION

    5 DETAILED MARKETING PLAN

    6 MANUFACTURING PROCESS

    7 DETAILED PRODUCT DESIGN

    8 BUILD PROTOTYPES

    9 LAB TEST PROTOTYPE

    10 FIELD TEST PROTOTYPE

    11 FINALIZED PRODUCT DESIGN

    12 FINAL MANUFACTURING PROCESS

    13 ORDER COMPONENTS

    14

    ORDER PRODUCTION EQUIPMENT

    15 INSTALL PRODUCTION EQUIPMENT

    16 CELEBRATE

    NETWORK SCHEDULE

    2

    3

    4

    5

    68

    9

    710

    11

    12

    13

    14

    15

    16

  • 5/21/2018 red zuma

    3/3

    TASK ID DURATION ES LS EF LF SLACK

    1 25 0 0 25 25 0

    2 30 25 25 55 55 0

    3 20 25 15 45 55 10

    4 10 55 55 65 65 0

    5 15 65 244 80 259 1796 30 65 120 95 150 55

    7 45 65 65 110 110 0

    8 25 110 110 135 135 0

    9 10 135 140 145 150 5

    10 15 135 135 150 150 0

    11 20 150 150 170 170 0

    12 10 170 170 180 180 0

    13 7 170 204 177 204 27

    14 14 180 194 194 194 0

    15 35 224 224 259 259 016 1 259 259 260 260 0

    The project is estimated to be completed in 260 days

    The critical path for the project is

    1 2 4 7 8 10 11 12 14 15 16

    Activity 5 i.e detailed marketing plan has highest amount of slack (179)