Presented To:
Presented by : Dr. Anamaria Popescu, PE, PSP, PMP
March 19, 2015
Recovery Schedules: Practical Considerations in Their Development & Approval AACE International Rocky Mountain Section Denver, CO
![Page 2: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/2.jpg)
Bio: Anamaria Popescu
Senior Director- FTI Consulting, Construction Solutions 19 Years Experience: Project Management Construction Advisory Services Expert Witness Long Time Member of AACE-Forensic Schedule Analysis (Co-Author of 29R-03) Industries: Oil and Gas Production (On-shore and Off-shore) Pipelines Petrochemical and Process Plants University of Texas at Austin Civil Engineering/CEPM Program PhD in Schedule Analysis PM at Enron Youngest Scheduler- Primavera DOS Avid Sailor and Racer Since Age 10
![Page 3: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/3.jpg)
Definition: Recovery Schedule
“A specialized schedule showing special efforts to recover time lost compared to the master schedule…often a contract requirement when the project finish date is no longer projecting contractual completion” - AACE International RP 10S-90
![Page 4: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/4.jpg)
Schedule Evolution
Baseline Schedule
Schedule Updates
Recovery Schedule
Revised Baseline
Schedule Updates
As-Built Schedule
![Page 5: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/5.jpg)
Actual Dates Actual Logic % Complete
Actual Man-hours Delays/Impacts
Change Logic & Lags Change Duration
Delete/Add Activities Change Resources Change Calendars
“Time Now” (Data Date)
Forms Basis for Recovery Schedule
Development
Revising Statusing
Schedule Updates-Two Elements
![Page 6: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/6.jpg)
Contractor’s Response Options
Options
Ignore
“No”
Submit Full Submit
Partial
Submit + $$$
![Page 7: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/7.jpg)
Recovery Plan Continuum Ac
cele
ratio
n Co
st
The Time vs. Cost Tradeoff
EOT / Acceleration
EOT Only
Acceleration Only
$0
0 Days Time Extension (Days) Max Delay
Max Cost
![Page 8: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/8.jpg)
Development Process: Considerations
Identify critical milestones Cost/Time recovery tradeoffs (Acceleration) Identify owner requirements Be realistic Involve ALL the team (e.g. subs): “BUY-IN” Critical Document Assumptions When Done-Monitor Progress Against Recovery Schedule
![Page 9: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/9.jpg)
Recovery Schedule Development: Strategies
![Page 10: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/10.jpg)
Schedule Update: 8 Weeks Behind
![Page 11: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/11.jpg)
Reduce “G”
![Page 12: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/12.jpg)
Reduce “A”
![Page 13: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/13.jpg)
Reduce “J & K”
![Page 14: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/14.jpg)
Reduce “C, F, M”
![Page 15: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/15.jpg)
Reduce “F, L, M”
![Page 16: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/16.jpg)
“That’s All Folks…”
![Page 17: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/17.jpg)
The Price Tag…
![Page 18: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/18.jpg)
Verification Of the Adequacy and Legitimacy
![Page 19: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/19.jpg)
Owner Verification: Considerations
• Correct Schedule Update • Critical and near Critical Paths • Specific Activities identified? • Manpower Allocation • Historical Productivity Rates • Electronic Version (not PDF) • Schedule Diagnostic Report • Schedule changes valid & supportable? • Require a “Recovery Worksheet”
![Page 20: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/20.jpg)
Owner Verification: Next Steps
• Collaborating Meeting • Schedule Review Live • Grouped by Critical Paths • Agree on Activities and $$$ • Monitoring Plan • Output Signed C.O.
![Page 21: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/21.jpg)
Collaborative Review:
Critical Path Verification
![Page 22: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/22.jpg)
Owner Verification:
Recovery Worksheet
![Page 23: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/23.jpg)
Risks in Accepting/Implementing
• Acceleration efforts not always effective: Excusable (and potentially compensable)
delays Responsibility for delays to Recovery
Schedule Cost recovery under directed
acceleration
![Page 24: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/24.jpg)
Conclusions
• Good scheduling: foundational element • Contract provisions • Early identification of impacts • Compliance with notice requirements • Recovery schedule coordination • “Buy In” crucial • Cost/Schedule tradeoffs • Closely monitor progress
![Page 25: Recovery Schedules: Practical Considerations in Their Development ...aacerms.org/archive/presentations/2015-03_RecoverySchedules.pdf · Recovery Schedules: Practical Considerations](https://reader036.fdocuments.us/reader036/viewer/2022081515/5a716d007f8b9aa2538ce05a/html5/thumbnails/25.jpg)