Reconstruction of the Saint-Jacques overpass
Presentation of mitigation measuresMay 15, 2014
![Page 2: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/2.jpg)
2
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
PRESENTATION PLANNING
![Page 3: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/3.jpg)
3
COMPLETE CLOSURE OF ST-JACQUES BETWEEN GIROUARD AND DÉCARIE
ONE (1) LANE IN EACH DIRECTION ON BOULEVARD DÉCARIE BETWEENDE MAISONNEUVE AND ST-JACQUES (EXPECTED COMPLETION TIME: MID-JUNE)
RUE ST-JACQUES BETWEEN DÉCARIE AND ST-RÉMI: ONE (1) LANE IN EACH DIRECTION
WORK ON RUE SHERBROOKE OUEST, BETWEEN DÉCARIE AND GREY, WITH ONE (1) LANE AVAILABLE WESTBOUND (DURATION: 6 TO 8 WEEKS)
ROADWORK ZONE
COMPLETE CLOSURE OF THE ST-JACQUES ONRAMP TO THE A-720 EASTBOUND
![Page 4: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/4.jpg)
4
PERMANENT RESERVED LANE ON SHERBROOKE EST & OUEST BETWEEN GIROUARD AND TRENHOLME
OPENING OF THE DE MAISONNEUVE EXIT ON THE A-15 SOUTHBOUND
TEMPORARY RESERVED LANE ON SHERBROOKE EST
OPENING OF THE SHERBROOKE U-TURN AREA
TEMPORARY RESERVED LANE ON UPPER-LACHINE
LEFT-TURN LANE ON SHERBROOKE EST FOR THE A-15 NORTHBOUND
MITIGATION MEASURES
![Page 5: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/5.jpg)
5
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians• Detour - network for trucks and automobiles• Review• Noise management• Communications media
PRESENTATION PLANNING
![Page 6: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/6.jpg)
6
MITIGATION MEASURESOpening of the Girouard onramp to the A-15 southboun d
![Page 7: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/7.jpg)
7
MITIGATION MEASURESAddition of a right-turn lane on chemin de la Côte-S t-Luc
![Page 8: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/8.jpg)
8
MITIGATION MEASURESOpening of the De Maisonneuve exit on the A-15 south bound
![Page 9: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/9.jpg)
9
MITIGATION MEASURESOpening of the Sherbrooke U-turn
![Page 10: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/10.jpg)
10
MITIGATION MEASURESModification of signage in the roadwork area
![Page 11: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/11.jpg)
11
MESURES D’ATTÉNUATIONModification des feux de circulation du secteur
MODIFICATION OF TRAFFIC LIGHTS IN THE ROADWORK AREA
![Page 12: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/12.jpg)
12
MITIGATION MEASURESAddition of permanent and temporary reserved lanes on rue Sherbrooke
PERMANENT RESERVED LANE ON SHERBROOKE EST & OUEST BETWEEN GIROUARD AND TRENHOLME
TEMPORARY RESERVED LANE ON SHERBROOKE EST
LEFT-TURN LANE ON SHERBROOKE EST FOR THE A-15 NORTHBOUND
![Page 13: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/13.jpg)
13
MITIGATION MEASURESImplementation of a temporary reserved lane on chem in Upper-Lachine
![Page 14: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/14.jpg)
14
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
PRESENTATION PLANNING
![Page 15: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/15.jpg)
15
BICYCLE NETWORK AND DETOUR FOR PEDESTRIANS
![Page 16: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/16.jpg)
16
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound
• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound • Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area
• Implementation of a reserved lane on rue Sherbrooke• Implementation of a temporary reserved lane on chemin Upper-
Lachine• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
PRESENTATION PLANNING
![Page 17: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/17.jpg)
17
DETOURNetwork for trucks and automobiles
![Page 18: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/18.jpg)
18
PRESENTATION PLANNING• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn• Modification of signage and traffic lights in the roadwork area
• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
![Page 19: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/19.jpg)
19
• Mitigation measures offer :• More route flexibility over the road network;• Improved capacity on rue Sherbrooke Est at the onramp to the A-
15 northbound;• More efficient public transportation service thanks to additional
reserved lanes.
• All the preferential measures for buses will favour modal transfer.
• Simulations indicate that the impacts on the Sud-Ouest borough are minor.
REVIEW
![Page 20: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/20.jpg)
20
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
PRESENTATION PLANNING
![Page 21: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/21.jpg)
21
NOISE BARRIER
![Page 22: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/22.jpg)
22
NOISE BARRIER
![Page 23: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/23.jpg)
23
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
PRESENTATION PLANNING
![Page 24: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/24.jpg)
• Neighbourhood committees• Leaflets distributed door-to-door• Website dedicated to the project www.turcot.gouv.qc.ca• Dedicated telephone line 514 873-1372• Turcot email: [email protected]• Twitter @MTQ_Turcot• Monthly electronic bulletins (subscribe via the Turcot website)• Advertising and notices in newspapers• Radio circulation 730 AM and traffic columnists• Ambient noise monitoring system accessible through the website
COMMUNICATIONS MEDIA
![Page 25: Reconstruction of the Saint-Jacques overpass Presentation ... · • Opening of the Girouard onramp to the A-15 southbound ... • Communications media PRESENTATION PLANNING. 3 COMPLETE](https://reader034.fdocuments.us/reader034/viewer/2022050214/5f6032059d54384c6f71eb8f/html5/thumbnails/25.jpg)