Real Estate Development Key Steps Hotel Projects GESIIC, Pantheon-Sorbonne, Paris January 25 th,...
-
Upload
jasmin-vann -
Category
Documents
-
view
218 -
download
4
Transcript of Real Estate Development Key Steps Hotel Projects GESIIC, Pantheon-Sorbonne, Paris January 25 th,...
Real Estate DevelopmentKey Steps
Hotel Projects
GESIIC, Pantheon-Sorbonne, Paris
January 25th, 2013
Yilmaz KARAUCGlobal Project Management
2
REAL ESTATE DEVELOPMENT PROCESS – KEY STEPS
AGENDA
Key Points
Overview of a development project key steps as Developer
Existing & Take-over projects key steps as Developer
Project Structures in following cases:– Hotel Operator is the Developer
– Hotel Operator leases or acquires after Completion
– Hotel Operator is only Hotel Manager
Questions
3
Key Points
In Real Estate Development Process the followings are crucial:
– Sequential process
– Deliverables
– Internal Validations
– Accountability
– Program Optimization
– Cost Certainty
in order to ensure project completion:
– within the Budget & Time
– and in compliance with the Product and Technical Guidelines.
4
Overview Of A Development Project Key StepsS
tep
s’ C
on
ten
tK
ey S
tep
s
Project Detailed Program
& PreliminaryStudies
2
1. Program analysis & optimization
2. Detailed Hotel Program
3. Base building Schematic Design
4. Interior Design Brief
5. List of proposed interior designers
6. Project Structure
7. Updated project cost plan & time frame
Program Committee
1. Project Delivery validation
2. Pre-opening phase
3. Hotel opening
Project Delivery& Hotel
Opening
5
Hotel Opening
Project Works
Execution & Follow-up
4
1. Design Development
2. Tender file
3. Tender for works
4. Beginning of Works
5. Execution studies
6. Mock up room
7. Execution of works
8. FF&E integration
Mock up Room
Handover
Project Assessment & Feasibility Analysis
1. Pre feasibility & Market overview
2. Preliminary Cost Plan
3. Site identification
4. Concept Design
5. Techn. Feasibility & Constructability Study (Technical File)
6. Initial Cost Plan
7. Business Plan
1
Development / Investment Committee
Project Final
Program & Detailed
Studies
1. Final version of the Program
2. Detailed Interior Design & Landscape drawings
3. Final Project Budget
4. Project time schedule.
Program Committee
3
Tender
Existing & Take Over Project Key StepsS
tep
s’ C
on
ten
tK
ey S
tep
s
Project Detailed Program
& PreliminaryStudies
2
1. Agreement for Acquisition
2. Program analysis & optimization
3. Detailed Hotel Program
4. Base building Schematic Design
5. Interior Design Brief
6. List of proposed interior designers
7. Project Structure
8. Updated project cost plan & time frame
Program Committee
1. Project Delivery validation
2. Pre-opening phase
3. Hotel opening
Project Delivery& Hotel
Opening
5
Hotel Opening
Project Works
Execution & Follow-up
4
1. Design Development
2. Tender file
3. Tender for works
4. Beginning of Works
5. Execution studies
6. Contractor Mock up room
7. Execution of works
8. FF&E integration
Mock up Room
Handover
Project Assessment (DD & PIP) & Feasibility Analysis
1. Pre feasibility & Market overview
2. Site Identification
3. Preliminary Business Plan
4. MoU / Due Dilig.
5. Property Improvement Plan
6. Concept Design
7. Techn. Feasibility & Constructability Study (Tech. File)
8. Initial Cost Plan
9. Business Plan
1
Development / Investment Committee
Project Final
Program & Detailed
Studies
1. Work Permit & Acquisition
2. Final version of the Program
3. Detailed Interior Design & Landscape drawings
4. Concept Mock up Room
5. Final Project Budget
6. Project time schedule.
Program Committee
3
Tender
6
HOTEL OPERATOR IS THE DEVELOPPERProject Structure
OWNER’s Representative (Secondment Agreement)
Third PartyTechnical Inspection
Project Management Team
Project ManagerCommercial Manager
Design ManagerLogistics Manager
Time SchedulerH&S Manager
Document Controller
Civil Engineer
Main-Contractor
PROPERTY OWNERSHIPCOMPANY
Hotel Consultant
Suppliers
Assistant to Owner (AMO Contract)
TYPICAL PROJECT STRUCTURE / SUBSIDIARY or J.V.
Local Technical Department
Brand Standards
I&D Interior Design Validation
OperationsCoordinator
FF&EProcurement Agent
Sub-contractorsFF&E, EQT, OSE
Installation
Contractual only
Management only
Relational
Product Interior Designer
Interior DesignerDecoration
Architect
Fire Safety Consultant
MEP Engineers
IT/VDI Engineer
Kitchen Consultant
Lighting Designer
Elevator Consultant
Cost Consultant
Contractual & Management
Façade Consultant
Signage Consultant
Sub-contractorsTrade Package
Works
Technical Due Diligence
(if Renovation)
DiagnosticsAsbestos & Lead(if Renovation)
Waste & Rain waterpipes diagn. (if Renovation)
HotelBrand
HOTEL OPERATORBusiness Unit
Lease Contract
SteeringCommittee
HOTEL OPERATORInvestment Funds
THIRD PARTYInvestment Funds
F&B ConceptAssistance
Spa ConceptAssistance
IT SupportHES Coord
ProcurementProperty Mngr
Hotel Operator Involvement in Management
Hotel Operator Involvement in Management (Optional)
Surveyor / Geometre
Hotel Financing, Development & OperatingProposed International Scheme
HOTEL GROUP WORLDWIDE
LOCAL HOTEL INVEST. & OPERATING
CO.
100%
LOCAL HOTELOPERATING & DEVELOPMENT
JOINT-VENTURE CO.
LOCAL PARTNER INVEST. & DEVELOPMENT
CO.
51% 49%
HOTELProp Co
HOTELProp Co
HOTELProp Co
HOTELOp Co
HOTELOp Co
HOTELOp Co
100%
Lease Contracts
Management ContractLicencing AgreementTechnical Assistance
100%
LOCAL BANKLoans Agreement35 / 65 (equity / debt)
Construction ContractsAsset Management
8
HOTEL OPERATOR LEASES / ACQUIRES AFTER COMPLETIONProject Structure
OWNER’s Representative Program Manager
Third PartyTechnical Inspection
Project Management Team
Project ManagerCommercial Manager
Design ManagerLogistics Manager
Time SchedulerH&S Manager
Document Controller
Civil Engineer
Main-Contractor
PROPERTY OWNERSHIPCOMPANY (POC)
Hotel Consultant
Suppliers
Assistant to Owner (AMO Contract)
TYPICAL PROJECT STRUCTURE LEASE / ACQUISITION
Local Technical Department
Brand Standards
I&D Interior Design Validation
OperationsCoordinator
FF&EProcurement Agent
Sub-contractorsFF&E, EQT, OSE
Installation
Contractual only
Management only
Relational
Product Interior Designer
Interior DesignerDecoration
Architect
Fire Safety Consultant
MEP Engineers
IT/VDI Engineer
Kitchen Consultant
Lighting Designer
Elevator Consultant
Cost Consultant
Contractual & Management
Façade Consultant
Signage Consultant
Sub-contractorsTrade Package
Works
Technical Due Diligence
(if Renovation)
DiagnosticsAsbestos & Lead(if Renovation)
Waste & Rain waterpipes diagn. (if Renovation)
HotelBrand
HOTEL OPERATORBusiness Unit
Agreement for Lease
SteeringCommittee
THIRD PARTYInvestment Funds
Hotel Operator Involvement in Management
F&B ConceptAssistance
Spa ConceptAssistance
IT SupportHES Coord
ProcurementProperty Mngr
POC Acquisition Agreement
Hotel Operator Involvement in Management (Optional)
HOTEL OPERATORInvestment Funds
Surveyor / Geometre
9
HOTEL OPERATOR LEASES AFTER COMPLETIONProposed Lease Structure
Services
Fixed Rent
Opex by Tenant
Total Cost of Ownership
Proposed Lease Classic Lease End-User
Tenant Benefit Combined benefits
Saving share
Total Cost of Occupancy
Variable Rent
10
HOTEL OPERATOR IS ONLY HOTEL MANAGERProject Structure
OWNER’s Representative Program Manager
Third PartyTechnical Inspection
Project Management Team
Project ManagerCommercial Manager
Design ManagerLogistics ManagerTime SchedulerH&S Manager
Document Controller
Civil Engineer
Main-Contractor
PROPERTY OWNERSHIPCOMPANY
Hotel Consultant
Suppliers
Assistant to Owner (AMO Contract)
TYPICAL PROJECT STRUCTURE / HOTEL MANAGEMENT AGREEMENT
Local Technical Department
Brand Standards
I&D Interior Design Validation
OperationsCoordinator
FF&EProcurement Agent
Sub-contractorsFF&E, EQT, OSE
Installation
Contractual only
Management only
Relational
Product Interior Designer
Interior DesignerDecoration
Architect
Fire Safety Consultant
MEP Engineers
IT/VDI Engineer
Kitchen Consultant
Lighting Designer
Elevator Consultant
Cost Consultant
Contractual & Management
Façade Consultant
Signage Consultant
Sub-contractorsTrade Package
Works
Technical Due Diligence
(if Renovation)
DiagnosticsAsbestos & Lead(if Renovation)
Waste & Rain waterpipes diagn. (if Renovation)
HotelBrand
HOTEL OPERATORBusiness Unit
Lease Contract
SteeringCommittee
THIRD PARTYInvestment Funds
Hotel Operator Involvement in Management
F&B ConceptAssistance
Spa ConceptAssistance
IT SupportHES Coord
ProcurementProperty Mngr
HOTELTRADING CO.
Hotel Management Contract
Hotel Operator Involvement in Management (Optional)
Surveyor / Geometre