Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel...

28
Reactor Economics 2008 Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC

Transcript of Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel...

Page 1: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Reactor Economics 2008 Reactor Economics 2008

Jim Harding

National Academy of Sciences/National Research Council Panel

January 22, 2008

Washington, DC

Page 2: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

How Do Current Estimates Compare? How Do Current Estimates Compare? What Factors Are Most Important?What Factors Are Most Important?

• Capital cost is most important• EIA - $2083/kW• MIT - $2000-2500/kW (2003)• Keystone - $3600-4000/kW (June 2007)• S&P - $4000/kW (May 2007)• Moody’s - $5000-6000/kW (October 2007)• FP&L - $5200-7800/kW (Fall 2007)

• Operating costs less important but not insignificant• Assumptions and methodology often opaque• Life cycle cost estimates range from 5-17 cents/kWh• Why is this so?

Page 3: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

The Easy Reasons – for all resourcesThe Easy Reasons – for all resources

• Lack of a consistent economic methodology• Capital cost usually stated in mixed current dollars at COD, rather

than discounted real dollars• Subsidies often included in cost estimates, though they affect price

not cost• Very important for long lead time, capital intensive units

• Example: Keystone high case for nuclear was $2950/kW overnight, $4650/kW mixed current dollars at COD, and $4000/kW in discounted 2007 dollars.

• All the same number!

Page 4: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Nuclear Power is TougherNuclear Power is Tougher• Lack of recent North American nuclear construction experience• Historical reliance on “studies” and vendor software

• Studies often reference each other• Software assumes Asian construction practices, and excludes owner’s costs –

contingency, escalation, interest during construction, land, transmission, and oversight. Long lead time for recalculating

• Little incentive to be accurate or up-to-date; no real money being spent• MIT chose actual Asian values, but assumed no real escalation

• Long lead time; licensing, siting, rate recovery and financing uncertainties. Very problematic in states with deregulated retail markets.

• Escalation during construction not considered; first of a kind premiums and learning curves instead

• Supply-chain imbalances not considered (skilled labor, sub-suppliers)• Transmission costs and lead time usually not considered

Page 5: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Recent Asian ExperienceRecent Asian ExperiencePlant MWe COD Yen@COD 2002$s/kW 2007$s/kW

Onagawa 3 825 Jan 2002 3.1 Billion 2409 3332

Genkai 3 1180 Feb 1994 4 Billion 2643 3656

Genkai 4 1180 Jul 1997 3.2 Billion 1960 2711

KK 3 1000 Jan 1993 3.2 Billion 2615 3617

KK 4 1000 Jan 1994 2.2 Billion 2609 3608

KK 6 1356 Jan 1996 4.2 Billion 2290 3167

KK 7 1356 Jan 1997 3.7 Billion 1957 2707

Y 5 (SK) 1000 Jan 2004 1700 2352

Y 6 (SK) 1000 Jan 2005 1656 2290

Average 2354 3257

Cost data from MIT 2003 Future of Nuclear Power study. Average does not include South Korean units, owing to labor rates. Real escalation from 2002-2007 at 4 percent/year.

Page 6: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Major Keystone AssumptionsMajor Keystone Assumptions• Take Asian experience at face value (important)• Escalate at EPRI estimate for heavy construction, 2002-2007 in low

case and through COD in high case (very important)• 5-6 year construction period and no major finance or regulatory issues;

conventional IOU financing (all very important)• Use current spot prices for uranium, and predicted enrichment prices

for long term fuel prices (not very important)• O&M and capacity factor at current fleet average; include

decommissioning, capital additions, and A&G; 30-40 year life (somewhat important)

• Life cycle cash flows discounted at weighted after tax cost of capital (somewhat important; first year cost – “rate shock” - can be twice as high as levelized life cycle cost)

• No major new transmission required (important, but site specific)

Page 7: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Real Escalation is the Biggest Real Escalation is the Biggest ProblemProblem

360

380

400

420

440

460

480

500

520

Jun-98 Jun-99 Jun-00 Jun-01 Jun-02 Jun-03 Jun-04 Jun-05 Jun-06

Ch

em

ica

l En

gin

ee

rin

g P

lan

t C

os

t In

de

x

950

1,000

1,050

1,100

1,150

1,200

1,250

1,300

1,350

Ma

rsh

all

& S

wif

t E

qu

ipm

en

t C

os

t In

de

x Chemical Engineering Plant Cost Index

Marshall & Swift Equipment Cost Index

Provided to Keystone panel by EPRI

Page 8: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Chemical Engineering Plant Cost Index

0.0

100.0

200.0

300.0

400.0

500.0

600.0

1950.00 1960.00 1970.00 1980.00 1990.00 2000.00 2010.00

Year

Ind

ex

avg. slope from 1959 - 2005 ~ 3.5 %/yravg. slope from 2002 - 2005 ~ 7.4 %/yr

Steeper Curve Than in the Mid 80s

Page 9: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Commodity Esc 86-03 Esc 03-07 Ratio vs. History

Nickel 3.8%/yr 60.3%/yr 15.9x

Copper 3.3%/yr 69.2%/yr 21x

Cement 2.7%/yr 11.6%/yr 4.3x

Iron/Steel 1.2%/yr 19.6%/yr 16.3x

Heavy construction

2.2%/yr 10.5%/yr 4.8x

Source: American Electric Power

Four Percent Real May Be Too Low

Page 10: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Escalation Likely Worse for Nuclear Escalation Likely Worse for Nuclear

• Industry moribund in Western Europe, US, and Russia since TMI and Chernobyl

• Twenty years ago (US): 400 suppliers, 900 N-Stamp holders; today 80 and 200

• Only one forge for large parts – Japan Steel Works; maybe Creusot Forge (France)

• Skilled labor and contractor limits• World uranium production well below current

consumption

Page 11: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Recent EstimatesRecent Estimates

• Keystone - $3600-4000/kW; 8-11 cents/kWh• Discounted real 2007 dollars; would be $5600/kW (16-

17 cents/kWh) at AEP escalation rate from 2002-COD• Standard & Poor’s - $4000/kW; 9-10 cents/kWh

• Basis not stated; levelized fixed charge rate• Life cycle costs reflect Keystone O&M and fuel costs

• Moody’s - $5000-6000/kW• Basis not stated; operating and fuel costs not estimated

• Florida Power & Light - $5200-7800/kW• Basis not stated; major transmission included

Page 12: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Keystone “Updated” Lifecycle Costs

Cost Category Low Case High Case

Capital Costs 6.0 7.9-10.5

Fuel 1.6 2.0

Fixed O&M 1.3 1.8

Variable O&M 0.5 0.5

Total (Levelized Cents/kWh) 9.4 12.2-14.8

Costs are in real discounted 2007 cents/kWh. Highest high case based on Moody’s capital cost. Low high and low case exclude South Korea.

Page 13: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Life Cycle and Operating Costs Also Life Cycle and Operating Costs Also VaryVary

• Nuclear O&M costs estimates often do not include• A&G costs• Net capital additions• Decommissioning

• Nuclear fuel cost estimates often do not include• Current spot prices for uranium• Likely increase in enrichment prices

• Life cycle cost estimates often use simplified levelized fixed charge rates rather than more complex discounted cash flows

Page 14: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Pulverized Coal

Gas (CCCT) Eastern IGCC

Wind Nuclear

Capital Cost ($/kW)

2438 700 2795 1700 4000

Total cost (cents/kWh)

5.8 6.8 6.8 7.1 8.9

CO2 Capture Cost ($/kW)

940 470 450 NA NA

Cost for CCS (cents/kWh)

6.2 2.8 3.4 NA NA

Cents/kWh 12.0 9.6 10.2 7.1 8.9-9.8

Cents/kWh (credits $10-30)

6.2-7.9 7-7.7 7.1-8.7 7.1 8.9-9.8

S & P Assessment - w/ carbon controls

Keystone operating costs are used instead of those estimated by S&)

Page 15: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

US Projections – Decades AgoUS Projections – Decades Ago

Construction start Estimated Overnight Actual Overnight % Over

1966-1967 $560/kW $1170/kW 209%

1968-1969 $679/kW $2000/kW 294%

1970-1971 $760/kW $2650/kW 348%

1972-1973 $1117/kW $3555/kW 318%

1974-1975 $1156/kW $4410/kW 381%

1976-1977 $1493/kW $4008/kW 269%

Mark Gielecki and James Hewlett, Commercial Nuclear Power in the United States: Problems and Prospects, US Energy Information Administration, August 1994. Data is in 2002 dollars.

Page 16: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

1970 1975 1980 1985 1990 1995 2000

Date of first operation

Inst

alle

d c

apit

al c

osts

in 2

004

$/k

W

Shoreham

Nine Mile Point 2 Watts Bar 1

Comanche Peak 2

Copyright Jonathan G. Koomey 2007

Comanche Peak 1

US Economics – Two Decades Ago

Koomey, Jonathan, and Nate Hultman. 2007. “A Reactor-Level Analysis of Busbar Costs for US nuclear plants,” 1970-2005, forthcoming in Energy Policy

Page 17: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.
Page 18: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.
Page 19: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Jeff Combs, President, Ux Consulting Company, Price Expectations and Price Formation, presentation to Nuclear Energy Institute International Uranium Fuel Seminar 2006

Page 20: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Fuel cycle steps MIT This analysis

Uranium $30/kg $300/kg

Enrichment $100/SWU $140-340/SWU

Fabrication $275/kg $275/kg

Disposal $400/kg $400/kg

Reprocessing $1000/kg $1500-2000/kg

Fuel cycle cost

Open 0.5 cents/kWh 1.6-2 cents/kWh

Closed 2 cents/kWh 3.4-4.3 cents/kWh

Differential 4x 2-3.5x

Reprocessing Is Still ExpensiveReprocessing Is Still Expensive

Approximately 5.25 kgs of spent fuel must be reprocessed to obtain 1 kg of MOX.

Page 21: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Supplemental SlidesSupplemental Slides

Page 22: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Efficiency and Renewables Can Be Efficiency and Renewables Can Be Disruptive TechnologiesDisruptive Technologies

A disruptive technology is often cheaper than the operating cost of the existing system

Demand is not limited to growth in serviceEfficiency resources cost less than operating costs for

existing gas (or coal with carbon taxes); they pay for themselves with +3x more carbon savings per dollar

Wind was disruptive from 2002-2005 and may be againPhotovoltaics may soon become oneOnly disruptive energy technologies can grow fast enough

to solve climate challenges

Page 23: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Rapid Worldwide Growth in Renewables

Page 24: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Technical Innovation Driven by Technical Innovation Driven by StandardsStandards

Page 25: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Figure 1 - Annual Lost-Opportunity Achievable Potential Supply Curve

0

10

20

30

40

50

60

70

80

90

100

$0 $10 $20 $30 $40 $50 $60 $70 $80 $90 $100 $110 $120

Levelized Cost (2004$/MWH)

Achi

evab

le P

oten

tial (

aMW

)

2005 (aMW/yr)

2007 (aMW/yr)

2009 (aMW/yr)

20011 (aMW/yr)

20013 (aMW/yr)

2015 - 2024 (aMW/yr)

Northwest Power Planning Council, Achievable Savings, August 2007

Utility Programs Are Also Important

Page 26: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

Figure 10 - Annual Utility Program Conservation Savings1980 - 2005

0

20

40

60

80

100

120

140

160

1980

1981

1982

1983

1984

1985

1986

1987

1988

1989

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

Year

Savi

ngs

(aM

W)

Historical Northwest Utility Programs

Northwest Power Planning Council, Achievable Savings, August 2007

Page 27: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

0%2%4%6%8%

10%12%14%16%18%20%22%24%26%28%30%32%34%

2000

Q4

2001

Q1

2001

Q2

2001

Q3

2001

Q4

2002

Q1

2002

Q2

2002

Q3

2002

Q4

2003

Q1

2003

Q2

2003

Q3

2003

Q4

2004

Q1

2004

Q2

2004

Q3

2004

Q4

2005

Q1

2005

Q2

2005

Q3

2005

Q4

2006

Q1

2006

Q2

2006

Q3

2006

Q4

NW CFL Market Shares

US CFL Market Shares

Figure 8 -Estimated ENERGY STAR CFL Market Share for the Northwest and U.S., 2000-2006

Sources: NW CFL sales 2000-2006: PECI and Fluid Market Strategies sales data reports; and NEEA estimate of an additional 1.5 million WAL-MART CFLs sold region-wide in 2006 (See Appendix A [Section 9.1.1] of MPER3 for more detail); U.S. and NW population estimates 2000-2006: U.S. Census 2004; U.S. market shares and non-CFL sales 2000-2005: Itron California Lamp Report (2006); U.S. market share 2006: D&R International (personal communication).

Compact Fluorescent Market Penetration

Page 28: Reactor Economics 2008 Jim Harding National Academy of Sciences/National Research Council Panel January 22, 2008 Washington, DC.

The Bottom LineThe Bottom Line

• Twenty years from light water reactor technology will be roughly the same as it is today

• Efficiency resources, wind turbine technology, and photovoltaics are improving rapidly

• Take one example --- Nanosolar• started by the Google founders, backed also by Swiss Re• Building two 430 MW/yr thin film PV production facilities this

year in Germany and California, using a technology they equate to printing newspapers

• Currently shipping and reportedly profitable at $0.99/watt (not including installation and balance of system)

• The cheapest, least risk strategy is rapid development of efficiency resources