RC-S CERP PROJECTsREPORTED IN CIDNE
IN THE LAST 12 MONTHS
From 31 July 2009 To 01 August 2010
![Page 2: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/2.jpg)
From 31 July 2009 To 01 August 2010
Kandahar Province – Projects Divided by MonthUNCLASSIFIED
Kandahar Province
CERP Project
Total number
98
![Page 3: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/3.jpg)
Kandahar Province – Projects Divided by District
From 31 July 2009 To 01 August 2010
UNCLASSIFIED
Kandahar Province
CERP Project
Total number
98
![Page 4: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/4.jpg)
From 31 July 2009 To 01 August 2010
Kandahar Province – Projects Divided by CategoryUNCLASSIFIED
Kandahar Province
CERP Project
Total number
98
![Page 5: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/5.jpg)
From 31 July 2009 To 01 August 2010
Zabul Province – Projects Divided by MonthUNCLASSIFIED
Zabul Province
CERP Project
Total number
149
![Page 6: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/6.jpg)
From 31 July 2009 To 01 August 2010
Zabul Province – Projects Divided by DistrictUNCLASSIFIED
Zabul Province
CERP Project
Total number
149
![Page 7: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/7.jpg)
From 31 July 2009 To 01 August 2010
Zabul Province – Projects Divided by MonthUNCLASSIFIED
Zabul Province
CERP Project
Total number
149
![Page 8: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/8.jpg)
From 31 July 2009 To 01 August 2010
Uruzgan Province – Projects Divided by Month
Uruzgan Province
CERP Project
Total number
105
UNCLASSIFIED
![Page 9: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/9.jpg)
From 31 July 2009 To 01 August 2010
Uruzgan Province – Projects Divided by District
Uruzgan Province
CERP Project
Total number
105
UNCLASSIFIED
![Page 10: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/10.jpg)
From 31 July 2009 To 01 August 2010
Uruzgan Province – Projects Divided by AIMS Category
Uruzgan Province
CERP Project
Total number
105
UNCLASSIFIED
![Page 11: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/11.jpg)
From 31 July 2009 To 01 August 2010
Daykundi Province – Projects Divided by Month
Daykundi Province
CERP Project
Total number
41
UNCLASSIFIED
![Page 12: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/12.jpg)
From 31 July 2009 To 01 August 2010
Daykundi Province – Projects Divided by District
Daykundi Province
CERP Project
Total number
41
UNCLASSIFIED
![Page 13: RC-S CERP PROJECTs REPORTED IN CIDNE IN THE LAST 12 MONTHS From 31 July 2009 To 01 August 2010.](https://reader035.fdocuments.us/reader035/viewer/2022062404/5514cff455034640138b6016/html5/thumbnails/13.jpg)
From 31 July 2009 To 01 August 2010
Daykundi Province – Projects Divided by AIMS Category
Daykundi Province
CERP Project
Total number
41