Presentation Outline
Integrated Sustainability corporate profile and experience
Reservoir design and construction
SCRD Raw Water Reservoir Project
Project Drivers
Design Concepts
Site Selection and Desktop Study Results
Next Steps
Questions
![Page 3: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/3.jpg)
Sustainability Data Management
Environmental and Regulatory
WasteWaste Management,
Wastewater
Renewable EnergySolar, Wind,
Geothermal, Efficiency
Water Source, Containment,
Distribution, Infrastructure
WasteWaste Management,
Wastewater
Environmental and Regulatoryry Was
Renewable EnergySolar, Wind,
Geothermal, Efficiencyt,
Re
Geo
Sustainability Data Managementnt
EnanMa
Water Source, Containment,
Distribution, Infrastructurt,
ture
Integrated Sustainability Services
![Page 4: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/4.jpg)
Water Storage Infrastructure
Services
Our team has designed more than 70 water storage reservoirs in western Canada, and have completed full design and construction of more than 35 water storage reservoir projects
• Desktop studies and siting
• Regulatory and environmental support
• Engineering design
• Construction
![Page 5: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/5.jpg)
Reservoir Design Examples
![Page 6: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/6.jpg)
Reservoir Project Examples
![Page 7: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/7.jpg)
Reservoir Project Examples
![Page 8: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/8.jpg)
Reservoir Project Examples
![Page 9: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/9.jpg)
Reservoir Project Examples
![Page 10: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/10.jpg)
Reservoir Project Examples
![Page 11: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/11.jpg)
SCRD Raw Water Reservoir Project
![Page 12: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/12.jpg)
Project Drivers
§ Diversion of water to a reservoir during periods of high precipitation and high creek flow (wet season)
§ Use of reservoir water during periods of low precipitation (dry season)
Sunshine Coast Tourism 2014
![Page 13: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/13.jpg)
Project Stages
Phase 1:
§ Water Demand Analysis
§ Site identification and preliminary desktop evaluation
§ Preliminary Multi-Criteria Analysis (MCA)
Phase 2:
§ Detailed site evaluation (desktop and field assessment)
§ Conceptual design
§ Class D cost estimates
§ Detailed MCA Completed to date
![Page 14: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/14.jpg)
Water Demand Analysis
Demand Reduction Factor from 2010 Supply Deficit (m3)
Demand Reduction 2025 2035 2050
Population 26,000 32,000 43,000
0% (zero reduction) 2,454,000 3,392,000 5,114,000
10% (minimal reduction) 2,002,000 2,837,000 4,366,000
20% (moderate reduction) 1,640,000 2,391,000 3,770,000
33% (high reduction) 1,245,000 1,811,000 2,988,000
Target reservoir volume: 900,000 m3 - 1,300,000 m3
![Page 15: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/15.jpg)
Study Areas for Site Selection
Low elevation reservoirs
High elevation reservoirs
Reservoirs created by enlarging existing alpine lake
![Page 16: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/16.jpg)
Desktop Study Results - Site Options
Sites A and B
Sites C3 and C4
Site C1 (eliminated during desktop)
![Page 17: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/17.jpg)
Site A Conceptual Design
Excavation Stockpiles
Reservoir
![Page 18: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/18.jpg)
Site B Conceptual Design
Excavation Stockpiles
Reservoir
![Page 19: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/19.jpg)
Sites C3 and C4 Conceptual Designs
Site C3 Site C4
Reservoir
Reservoir
Dam
Dam
![Page 20: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/20.jpg)
Estimated Reservoir Costs
Site Volume (m3) Site Area (ha.)
Total Installed Cost (incl. Contingency)
($ CAD)
Total Estimated Construction
Duration (months)
A 1,180,300 45 $ 23,764,000 15
B 1,291,600 46 $ 23,575,000 15
C3 781,900 41 $ 9,411,000 5
C4 856,000 35 $ 8,698,000 5
Class D Cost Estimate (+/- 50% accuracy):
![Page 21: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/21.jpg)
Raw Water Reservoir Project - Next Steps
§ Regulatory permitting, land acquisition, stakeholder engagement
§ Preliminary design
§ Preliminary cost estimates (Class C)
§ Detailed design
§ Detailed cost estimates (Class B, Class A)
§ Reservoir construction and commissioning
![Page 22: Raw Water Reservoir - SCRD...Raw Water Reservoir Project - Next Steps Regulatory permitting, land acquisition, stakeholder engagement Preliminary design Preliminary cost estimates](https://reader035.fdocuments.us/reader035/viewer/2022062303/5fc87a01327ef8614f1597fe/html5/thumbnails/22.jpg)
Questions? Thank you