RANDOM BOULDER FIELDS {RBF} (For bank protection) 2 EXAMPLES.
-
Upload
bryan-weaver -
Category
Documents
-
view
213 -
download
0
Transcript of RANDOM BOULDER FIELDS {RBF} (For bank protection) 2 EXAMPLES.
Typically a Random Native Boulder Field is built in-channel adjacent to the bank of concern
to strengthen that area, increase hydraulic roughness, increase turbulence, partially block flow, decrease flow velocities, dissipate energy,
& shift velocities & the thalweg toward the center of the stream. RBF increase habitat
diversity, & can increase aeration & dissolved oxygen. Aesthetics can be anywhere from
natural appearing to soothing & stupendous!!
Taking the classic concept of making the bank of concern
hydraulically rougher & tougher, & the opposite bank smoother & weaker, the RBF
also increases the bed roughness near the bank of
concern!!!
POPLAR RIVER, LUTSEN, MN.
SEPARATING THE MEGA-SLIDE FROM
THE RIVER (AND MORE)
By the stream dream team
Stream stabilization/restoration: Conceptually we will separate the stream from the 90+ ft tall hill, & in the channel we will make the inside of the bend smoother & the outer section of the bend & bank hydraulically rougher & tougher.
Derrick-8-13-2007-lowest flow in 30 yrs
From top of mega slump looking US.
In some sections the
outer section of the
channel was smooth &
inner section boulder
strewn, that will be
reversed!!!
Stream Project Functions:
Bendway Weirs move scour & the thalweg away from attacked bank, with velocities reduced within weir field & on bank. Randomly placed native boulder field increases roughness, increases turbulence & complexity, & decreases flow velocities. Vegetation roughness reduces near-bank flow velocities. Roots strengthen bank & bind soil. Mini-swale captures colluvium.
Not shown on the next slide, but a Random Boulder Field (RBF)
will be installed within the Bendway Weir
field.
Mega- Slump Stream Project
Planform
Mega Slump
Bridge
Bendway Weir
Keys
Pre-dug Scour Holes
Boulder Revetment
Mini SwaleTransplanted Veg
A couple pebbles to be used for the keys & Bendway Weirs. Boulder specifications: D-100: max 54 inches, min 40 inches; D-50: max 38
inches, min 32 inches; D-35: max. 28 inches, min 22 inches.
CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008
Looking DS @ constructed mini-weir & Bendway Weir #1. Note constructed boulder field & pool riffle-pool complex on right side of channel
CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008
CONSTRUCTION PIX OF RANDOM
SCATTERING OF BOULDERS TO CREATE THE
BOULDER FIELDS BETWEEN THE
BENDWAY WEIRS
Looking DS @ boulder flying though air
CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008
Looking DS @ the big boulder splash
CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008
Looking DS @ 2 more boulders flying though air
CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008
Looking US @ completed boulder field & Bendway Weir & stone toe & Jay. Does it look natural???? I would say so… Smooth on inside of bend
CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008
Stream Project Functions::::::::• Longitudinal toe stone provides scour protection• Toe stone protection completely separates stream from Mega Slump• Willow poles provide vegetative roughness, increase height of “soft
protection”, shades stone & water, & has many wildlife functions {everything from carbon input to structure cover to insect production, beneficial to pollinators, etc.}
• Mini-Swale provides a storage area for colluvium from Mega Slump• Bendway Weirs increase stream roughness, reduce toe scour,
provide diversity & complexity of depth, velocity (horizontal & vertical) & substrate, plus they move the thalweg away from the toe of the eroding bank.
• The dug pools at the ends of the Bendway Weirs provide mini pool-riffle-pool sequences throughout the bend.
• Boulder fields provide additional roughness, plus a “natural” look
Looking DS. Boulder field to left, dug pools & riffles on right
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Looking DS @ constructed mini-weir & Bendway Weir #1. Note constructed boulder field & pool riffle-pool complex on right side of channel
CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Looking DS @ toe stone & Bendway Weirs 2 - 4.
BW#2
BW#3
BW#4
Looking DS @ Bendway Weirs # 4 & 5. Diversity & complexity of flow
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Looking at constructed natural appearing random boulder field (foreground) & random chaotic stone toe
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Looking US @ pool & colorful boulder assemblage.
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Watching the river flow, looking US @ Bendway Weir #5 & boulder field
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Watching the river flow, looking US @ BW #5 & boulder field, fantastic diversity of depth, velocity, turbulence, substrate, holding water (refugia)
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Looking US @ placed boulders dissipating stream energy
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Looking DS @ stone toe, boulder field, & Bendway Weirs 7 & 8.
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Looking US @ Bendway Weir #7 & stone toe, smooth on inside of bend, rough on outside of bend.
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Looking DS @ Key #8 (with veg) & BW #8. Note pools & flow at end of weir
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
Looking DS @ stone toe, boulder field, & Bendway Weirs 7 & 8.
CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008
SITE 4: MINIMAL BANK STABILIZATION TO REDUCE THE
SEDIMENT LOAD INTO DINGMANS CREEK FROM THE SMALL SLIDE
DELAWARE WATER GAP NATIONAL RECREATION AREA,
NATIONAL PARK SERVICE PROJECT CONSTRUCTED
SEPTEMBER 24, 2009
PROBLEMS• For approximately 200 ft Dingmans Creek is
flowing against & eroding the left valley wall (estimated height 35 ft). The amount of fine sediment delivered to the stream is significant. This entire colluvium slide is very unstable. If erosion progresses at this site it may kick the stream back toward the park road downstream and create a threat to road stability (Johnny B. Mountain Road).
• The point bar (right side) of the channel is very rough with a number of boulders increasing the hydraulic roughness & impeding flow.
• 35 Vegetated Traffic Control Stones (TCS)
• Every 4th TCS is keyed 10 ft into the bank (perpendicular) with rooted Black Willow whips & other live poles planted at a rate of 3 plants per ft.
• Every 4th TCS has a Single Stone Bendway Weir (SSBW) to move the thalweg away from the left bank & toward the center of the channel approximately 5-8 ft.
• The space between & behind the TCS is heavily vegetated with a variety of species of rooted-stock trees & shrubs.
• The loose eroding talus slope slide was heavily planted with several species of rooted-stock shrubs & trees
• Native boulders from the point bar were placed as a random boulder field streamward of the TCS & SSBW.
METHODS EMPLOYED
HIGH WATER-Looking DS @ fast water (smoother bed) near bank.
PRE-PROJECT DINGMANS CR-SITE 4 PIX BY DERRICK 7-24-2008
HIGH WATER-Looking DS @ smoother bed near bank, rougher toward inside of bend!!
PRE-PROJECT DINGMANS CR-SITE 4 PIX BY DERRICK 7-24-2008
HIGH WATER-Looking US @ project bank. Erosion of bank is contributing significant sediment to the system. Bed is rough
on the inside of the bend, but smooth near eroding bank
PRE-PROJECT DINGMANS CR-SITE 4 PIX BY DERRICK 12-15-2008
HIGH WATER-Looking DS toward DS end of project, smoother bed near bank, rougher toward inside of bend!!
PRE-PROJECT DINGMANS CR-SITE 4 PIX BY DERRICK 12-15-2008
SOLUTIONS (THE PLAN)• This project is designed to stabilize 200 ft of the bank at the
present location by increasing roughness of the entire bank with 3 gallon container rooted-stock trees & shrubs.
• Hard protection is limited to the toe & includes 35 vegetated Traffic Control Stones (TCS). TCS were typically 3 ft by 3 ft by 4 ft & spaced 3 to 6 ft apart. Every 4th TCS was keyed 8 to 10’ into the bank & had a Single-Stone Bendway Weir (SSBW) placed at the stream end. Live poles were placed in the key trench before stone was placed. Eight SSBW were built.
• A random natural bedload boulder field was placed around & in front of the SSBW & TCS’s.
Courtesy of Ecological
Restoration, Inc.
Correction: There should be 3 Traffic Control Stones between each Single Stone
Bendway Weir, not 2.
Two healthy Single Stone Bendway Weir (SSBW) stones.
CONSTRUCTION DINGMANS CR-SITE 4 PIX BY DERRICK 9-19-2009
PLANTS PLANTED
• Gray Birch 50 2 gallon pots • Gray Birch 200 unrooted poles• Buttonbush 25 bare root• Silky Dogwood 200 bare root• Ninebark 175 bare root • Rhododendron 50 3 gallon pots• White Pine 150 3 gallon pots
Common Name # Size
Traffic Control Stones (TCS) sized about 3 ft by 3 ft by 4 ft, dug into the bed & bank, designed to stabilize & roughen the bank, are spaced 3 to 6
ft apart. Every 4th TCS is keyed into the bank & has a Single Stone Bendway Weir attached. 8 SSBW total
Traffic Control Stones (TCS) with Single Stone
Bendway Weirs (SSBW) & vegged keys & pole
plantings
Key
Key
TCS
KeyTCS
SSBW
TCS
TCS
TCS
TCS
TCS
TCSTCS
SSB
W
SSB
W
Key
Key
Key
Thalweg
Key
Scoop a hole into the bed & bank for the Traffic Control Stone (TCS), then place live poles against
bank, push the TCS into position, then backfill. TCS were typically 3 ft by 3 ft by 4 ft & spaced 3 to 6 ft
apart. Every 4th TCS was keyed 8 to 10’ into the bank & had a Single-Stone Bendway Weir (SSBW) placed at the stream end. Live poles were placed in the key trench before stone was placed. A random natural
bedload boulder field was placed around & in front of the SSBW & TCS’s. All bare areas of the slide area were planted with 3 gallon container rooted-stock
trees & shrubs.
Rooted–stock container shrubs & trees added to Traffic Control Stones at toe & all bare
areas of the entire eroding bank
Key
Key
TCS
KeyTCS
SSBW
TCS
TCS
TCS
TCS
TCS
TCSTCS
SSB
W
SSB
W
Key
Key
Key
Thalweg
Looking across @ stone being placed in the key for Bendway Weir #4. Live poles have already been placed in the key trench.
CONSTRUCTION DINGMANS CR-SITE 4 PIX BY DERRICK 9-19-2009
Close-up of a Single Stone
Bendway Weir (SSBW) &
vegged key & pole plantings
Thalweg
Key
TCS
SSB
W
Key
Key
Looking DS @ many live pole plantings landward of the TCS.
CONSTRUCTION DINGMANS CR-SITE 4 PIX BY DERRICK 9-19-2009
Looking across @ live poles & key stones in BW #5.
CONSTRUCTION DINGMANS CR-SITE 4 PIX BY DERRICK 9-19-2009
Looking across @ Single Stone Bendway Weir #5.
CONSTRUCTION DINGMANS CR-SITE 4 PIX BY DERRICK 9-19-2009
Weir construction complete, looking across @ Bendway Weir #5.
CONSTRUCTION DINGMANS CR-SITE 4 PIX BY DERRICK 9-20-2009
Construction complete, looking across @ Bendway Weir #3, vegetated key, hillside plantings, TCS US & DS, & Random Boulder Field.
CONSTRUCTION COMPLETE DINGMANS CR-SITE 4 DERRICK 9-24-2009
Construction complete, looking across @ Bendway Weir #7, along with a vegetated key, hillside plantings, TCS, & Random Boulder Field.
CONSTRUCTION COMPLETE DINGMANS CR-SITE 4 DERRICK 9-24-2009
Construction complete, looking DS. Left side hydraulically rough (and will become rougher as plantings grow), right side smooth.
CONSTRUCTION COMPLETE DINGMANS CR-SITE 4 DERRICK 9-24-2009
Construction complete, looking US @ toe & bank roughness due to TCS, Single Stone Bendway Weirs, Random Boulder Field, many pole plantings & rooted-stock plants provide roughness
CONSTRUCTION COMPLETE DINGMANS CR-SITE 4 DERRICK 9-24-2009
Construction complete-Looking US. The secret to bank stabilization: smooth the opposite bank (point bar area), & roughen & toughen the eroding
bank (toe & entire slide area) & bed using a Random Boulder Field.
CONSTRUCTION COMPLETE DINGMANS CR-SITE 4 DERRICK 9-24-2009
1 YEAR LATER-Mid project Bendway Weirs, Traffic Control Stones, vegged floodplain bench, & Random Boulder Field.
1 YEAR LATER-DINGMANS CR.-SITE 4-PIX BY DERRICK 9-12-2010
1 YEAR LATER-Mid-project Bendway Weirs, Traffic Control Stones, vegged floodplain bench, & Random Boulder Field.
1 YEAR LATER-DINGMANS CR.-SITE 4-PIX BY DERRICK 9-12-2010
This PowerPoint presentation was developed & built by Dave Derrick.
Any questions or comments, call my personal cell @ 601-218-7717, or email @ [email protected]
Enjoy the information!!