Simis scheme irrigation management information system formation
Rajivlift Irrigation Scheme Bhima
Transcript of Rajivlift Irrigation Scheme Bhima
1 Project Profile : Lifting of 20 tmc of water from foreshore of PJP and Ookachettivagu Project Pondage
2 Administrative Sanction :G. O. Ms. No. 166, I & CAD, Dt: 30-10-2003 for Rs. 1426.30 Crores
3 No. of EPC Packages : 13 Nos.4 Agt. Value of 13 Pkgs : Rs. 1417.92Crs.
5 Budget Provision for 2006-07 : Rs. 193.20 Crs.
6 Expenditure
2004-05 : Rs. 108.68 Crs. (Incl. Sangambanda BR)
2005-06 : Rs. 238.50 Crs.
TOTAL : Rs. 347.18 Crs.
7 Utilisation : 20 TMC8 Ayacut New Ayacut : 2,03,000 Acres
Stabilization : 4,000 Acres
RAJIV LIFT IRRIGATION SCHEME (BHIMA)
9 Lift-I
Lift Height : 67 M
No. of Pumps : 6 Nos.
Total pumps capacity : 48 MW
10 Lift-II
Lift Height : 61 M
No. of Pumps : 6 Nos.
Total pumps capacity : 48 MW
11 Total Power required : 96 MW
RAJIV LIFT IRRIGATION SCHEME (BHIMA)
12 Land Acquisition
Required : 21,641 acres
Acquired : 8,278 acres
Requisitioned : 13,000 acres
13 Est. Cost for LA : Rs. 120 Crs.
14 Est. Cost for R & R : Rs. 40 Crores
15 Mobilisation Advance : PaidRecovered
2004-05 : 62.57 Crs -
2005-06 : 22.10 Crs. 14.99 Crs.
Total : Rs. 84.78 Crs.Rs.14.99 Crs.
16 Target date for completion : 9/2007
RAJIV LIFT IRRIGATION SCHEME (BHIMA)
PKG No.
Description AwardedBid AmountRs. in Crs.
13Excavation of High level right main canal, distributary system including construction of CM & CD works from Sangambanda BR to feed ayacut of 18400 Acres.
M/s. R.M.M. & BRC (JV) 57.97
14Excavation of High level left main canal, distributary system including construction of CM & CD works etc. to feed an ayacut of 35,800 Ac. Under Sangambanda BR
M/s. VPR-Cromandal (JV) 68.94
15
Investigation, design, estimation and excavation of canal distributary system including construction of CM & CD works from Yenukunta BR, Waddewata (V), Kottakota (M), Mahabubnagar (D) to feed about 14,000 Acres upto Rangasamudram BR.
M/s. Prathibha-Ch MR (JV) 51.270
16Excavation of canal distributary system – including constrction of CM & CD works from Ranga Samudram to feed an ayacut of 21,000 Acres
M/s. RNS-GSR & CO (JV) 70.800
17
Investigation, design, estimation and execution for converting the existing Rangasamudram tank, near Sri Rangapuram (V) Pebbair (M), Mahabubnagar district as balancing reservoir under Bhima Lift Irrigation Project (Lift-II)
M/s. ALS-KVR (JV) 41.540
18
Investigation, design, estimation and execution for convesting the existing Shankarasamudram tank, near Knaipally (V) Kothakota (M), Mahabubnagar district as balancing reservoir under Bhima Lift Irrigation Project (Lift-II)
M/s. Sri Avanthi Saivenkata (JV) 42.100
CATEGORY-II
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Pkg No.
Description AwardedBid
AmountRs. in Crs.
19 Shankara Samudram Balancing Reservoir Right Main canal.M/s. G.H. Reddy &
Associate K.K.R & Co (JV)
36.90
20(i) Formation of Earth Dam with FRL +352m (ii) Construction of spillway, (iii) Construction of Head Regulator to let out into left and right main canals. Budpur Balancing Reservoir
M/s. KNR-SLEC (JV) 36.98
21
Investigation, Designs and excavation of left main canal, distributary system including construction of CM & CD works from budpur Balancing reservoir, Budpur (V), Atmakur (M), Mahabubnagar (D) to feed about 32,000 Acres
M/s. S.V.E.C. Co., 60.39
22Investigation, Designs and excavation of right main canal, distributary system including construction of CM & CD works from budpur Balancing reservoir, Budpur (V), Atmakur (M), Mahabubnagar (D) to feed about 32,000 Acres
M/s. S.V.E.C. Co., 26.73
27Investigation, Design, excavation of left main canal, distributary system including construction of CM & CD works from Sankarsamudam Balancing Reservoir .
M/s. KNR Const. Ltd. & BPL (JV) 149.40
OCLIFT-I : Design, manufacture, supplying & erection of pumps, motors, electro mechanical works, including tunnel, cistern and pump house etc.
M/s. Patel Engg. Ltd. 383.349
OCDesign and execution of Stage-I and stage-II pumping stations of LIFT-II at Thirumalayapalli & Kothakota (M), Mahabubnagar (D) on EPC basis.
M/s. NEC-NCC-MAYTAS (JV) 391.55
TOTAL 1417.919
CATEGORY-II
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Package No. 13/Cat-II : Excavation of
High level right main canal, distributary
system including construction of CM & CD
works from Sangambanda BR to feed ayacut
of 18400 Acres.
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s R.M.M &BRC
(JV)
Agreement Amount : Rs. 57.97Crs.
Agreement Date : 03-03-2005
Period of Completion : 24 Months (8 milestones)
Date of completion : 03-03-2007 Investigation completed : Completed
Designs : 9.2 KM approved against 24 KM
Execution (Main canal) : 15 KM length in progress against total length of 24.00KM
Qty. of earth work done : 6.00Lakh Cum against 37.32 Lakh Cum.
Qty. of concrete work done : 500 cum against 3500 cum
No. of Machinery : Deployed = 15Nos (Excavators =2 Nos.,Tipper-8Nos., T Roller- 2Nos., Dozers = 1 Nos., Water tank -1No.Crushing plant-1No.)
Land Acquisition : Required 1000 Acres, Requisition : 260 acres, Acquired – 81 acres
Expenditure : Rs. 14.90 Crs. against Rs. 57.97 Crs.,
Mob. Adv. Paid : Rs. 2.90 Crs.
Mob. Adv. Recovered : Rs. 2.90 Crs.
Bottlenecks : Land Acquisition
Package No. 14/Cat-II : Excavation of
High level left main canal, distributary system
including construction of CM & CD works etc.
to feed an ayacut of 35,800 Ac. Under
Sangambanda BR,
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s VPR–
Coromandal (JV)
Agreement Amount : Rs. 68.94Crs.
Agreement Date : 05-03-2005
Period of Completion : 24 Months (8 milestones)
Date of completion :24-02-2007 Investigation : Completed (40.645 KM)
Designs : Main canal completed (40.465 KM)
Execution (main canal) : 28.75KM length in progress against total length of 40.645 KM
Qty. of earth work done : 18 Lakh Cum against 26.20 Lakh Cum.
Qty. of concrete work done : 1500 cum
No. of Machinery : Deployed = 29Nos (Excavators = 6 Nos., Dozers = 2 Nos, Tippers = 21Nos. etc)
Expenditure : Rs. 29.88 Crs. against Rs. 68.94 Crs.,
Mob. Adv. Paid : Rs. 6.88 Crs.
Mob. Adv. Recovered : Rs. 1.68 Crs.
Land Acquisition : Required 1867 Acs, Requisition : 651 Acquired– 205.54 Acres
Package No. 15/Cat-II : Investigation,
design, estimation and excavation of canal distributary system including construction of CM & CD works from Yenukunta BR, Waddewata (V), Kottakota (M), Mahabubnagar (D) to feed about 14,000 Acres upto Rangasamudram BR.
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s Prathibha – Ch MR- (JV)
Agreement Amount : Rs. 51.27 Crs.
Agreement Date : 05-03-2005
Period of Completion : 24 Months (8 milestones)
Date of completion : 05-03-2007
Investigation : Completed (30.25 KM)
Design : 26.75 KM approved against 30.25 KM
Execution (main canal) : 13 KM length in progress against total length of 30.25
KM
Qty. of earth work done : 5,70,000 Cum against 20,00,000 Cum
No. of Machinery : Deployed = 28Ns (Excavators = 6 Nos., Tippers=20Nos,
Leveller =2No.)
Land Acquisition : Required 943 Acres, Requisition :407Acs. Acquired
– 218.71Acs.
Expenditure : Rs. 8.12 Crs. (Inc. Mob. Adv. Rs. 5.12 Crs.) against
Rs. 51.27 Crs.
Package No. 16/Cat-II : Excavation of
canal distributary system – including
construction of CM & CD works from Ranga
Samudram to feed an ayacut of 21,000 Acres.
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s RNS-GSR &
Co. (JV)
Agreement Amount : Rs. 70.80Crs
Agreement Date : 02-03-2005
Period of Completion : 24 Months (8 milestones)
Date of completion : 02-03-2007 Investigation (HPs) : Length 58Kms finalised against 81Kms
Execution : Excavation in 1.5 KM length in progress against total
length of 81.00 KM
Qty. of earth work done : 10,000 Cum against 16,00,000 Cum
No. of Machinery : Deployed = 15 Nos (JCB-1No.Excavators = 4 Nos, Tippers-2Nos,
S.Crushers- 2Nos, Hard top jeep-4Nos)
Expenditure : Rs. 3.54Crs. (Mob. Adv. Only) against Rs. 70.80
Crs.
Land Acquisition : Required 1415 Acres, Requisition: 162.34Acres Acquired –
Nil
Bottle Necks : Land Acquisition
Package No. 17/Cat-II : Investigation,
design, estimation and execution for
converting the existing Rangasamudram tank,
near Sri Rangapuram (V) Pebbair (M),
Mahabubnagar district as balancing reservoir
under Bhima Lift Irrigation Project (Lift-II)
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s A L S-KVR(JV)
Agreement Amount : Rs. 41.50 Crores
Agreement Date : 07-03-2005
Period of Completion : 24 Months (8 milestones)
Date of completion : 07-03-2007
Investigation : Completed
Designs (Earth Bund & Weir) : 80% approved
Execution : Started
Qty. of earth work done : Cut off trench excavated for a length of 1.50
KM
Expenditure : Rs. 2.08 Crs. (Mob. Adv. Only) against Rs.
41.50 Crs.
Land Acquisition : Required 2452.30Acres, Requi.: 2526.11Acrs
Acquired – Nil
Bottle Necks : Land Acquisition
Package No. 18/Cat- : Investigation,
design, estimation and execution for
convesting the existing Shankarasamudram
tank, near Knaipally (V) Kothakota (M),
Mahabubnagar district as balancing reservoir
under Bhima Lift Irrigation Project (Lift-II)
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s Sri Avanthika
Saivenkata (JV)
Agreement Amount : Rs. 42.10 Crores
Agreement Date : 14-03-2005
Period of Completion : 24 Months(8 Mile Stones)
Date of completion : 14-03-2007
Investigation : Completed (3.69 KM)
Designs (Earth bund & Weir) : 80% of designs approved.
Execution : Yet to start (Water in the Tank & objections of
Kanepally (V) for want of inclusion of village in R & R
Package.
Expenditure : Rs. 2.11 Crs. (Mob. Adv. only) against Rs. 42.10
Crs.
Land Acquisition : Required 2220 Acres, Requisitioned: 1491Ac.
Acquired – 1436 acres
Package No. 19/Cat-II : Shankara
Samudram Balancing Reservoir
Right Main canal.
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s G. H. Reddy &
Associates K.K.R & Co. (JV),
Agreement Amount : Rs. 36.90 Crores
Agreement Date : 19-02-2005
Period of Completion : 24 Months (Milestones : 8)
Investigation : Completed (39 KM)
Designs (HPs & Structures) : approved
Execution : 34 KM length in progress against total length of 39 KM
Qty. of earth work done : 5.5 Lakh Cum against 6 Lakh Cum.
Qty. of concrete work done: 2500 cum against 30,000 cum
Structure : 25 Nos. executed against 110 Nos.
Expenditure : Rs. 16.68 Crs. against 36.79Crores
Mob. Adv. Paid : Rs. 3.68 Crs.
Mob. Adv. Recovered : Rs. 0.70 Crs.
Land Acquisition : Required 800 Acres, Requisitioned 459 Acs Acquired – 236 acres
Package No. 20/Cat- : (i) Formation
of Earth Dam of Budpur with FRL
+352m (ii) Construction of spillway,
(iii) Construction of Head Regulator
to let out into left and right main
canals.
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s KNR-SLEC
(JV), Hyd.
Agreement Amount : Rs. 36.98Crs
Agreement Date : 07-03-2005
Period of Completion : 24 Months (8 milestones) Investigation : Completed (6.10 KM)
Designs : Approved
Execution : Qty. of earth work 5.64 Lakh cum completed.
Expenditure : Rs. 15.43 Crs. (Inc. Mob. Adv. Rs. 3.43 Crs.) against
Rs. 36.98Crs.
Mob. Adv. Recovered : Rs. 1.37 Crs.
Machinery deployed : Excavator-1No., Tippers-5No., Dozer-1No., Other
M/C-7Nos.
Land Acquisition : Required 2073.11 Acres, Requisitioned- 2073.11 Acs
Acquired – 358Acs.
Package No. 21/Cat-II : Investigation,
Designs and excavation of left main
canal, distributary system including
construction of CM & CD works from
budpur Balancing reservoir, Budpur (V),
Atmakur (M), Mahabubnagar (D) to feed
about 32,000 Acres
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s S.V.E.C Co.,
Hyd.
Agreement Amount : Rs. 60.39 Crores
Agreement Date : 25-02-2005
Period of Completion : 24 Months (milestones)
Investigation : completed (32 KM)
Designs (HPs & Structures) : Length 28.65 Km approved against 37.825Kms.
Execution (Canal) : 28.10 KM length in progress against total length of
37.825KM
Structures : 13 Nos. executed against 79 Nos.
Machinery deployed : 10Nos. (Tippers-4Nos, Poclains-4Nos, DRR-1No,Dozer-
1No.)
Land Acquisition : Required 1386 Acres, Requisitioned: 316Acs
Acquired – 98 Acs.
Expenditure : Rs. 18.04 Crs. (inc. mob. Adv. Rs. 6.04 Crs.)
against Rs. 60.39 Crs.
Bottle necks : Land acquisition – not handed over by Revenue
authorities
Package No. 22/Cat- : Investigation,
Designs and excavation of right main
canal, distributary system including
construction of CM & CD works from
budpur Balancing reservoir, Budpur (V),
Atmakur (M), Mahabubnagar (D) to feed
about 32,000 Acres
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s S.V.E.C
Co., Hyd.
Agreement Amount : Rs. 26.73 Crores
Agreement Date : 25-02-2005
Period of Completion : 24 Months (8
milestones) Investigation : Completed (15.025 KM)
Design (HPs) : Approved
Execution (Canal) : 14.50 KM length in progress against total length of 15.025KM
Qty. of earth work done : 2.86 Lakh cum against 2.95 Lakh cum
Qty. of concrete work done: 5200 cum
Structures : 23 Nos. executed against 54 Nos.
Expenditure : Rs. 14.68 Crs. (Inc. Mob. Adv. Rs. 2.68 Crs.) against Rs. 26.73 Crs.
Mod. Adv. Recovered : Rs. 0.73 Crs.
Machinery deployed : 13Nos. (Tippers-4Nos, Poclains-7Nos, DRR-1No,Dozer-1No.)
Land Acquisition : Required 354 Acres, Requisitioned: 212Acres Acquired – 128 Acs.
Bottlenecks : Land acquisition
Package No. OC (Pkg. 27):
Investigation, Design, excavation of left
main canal, distributary system including
construction of CM & CD works from
Sankarsamudam Balancing Reservoir .
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s KNR Const. Ltd. & BPL (JV)
Agreement Amount : Rs. 149.40Crs.
Agreement Date : 9/2005
INVESTIGATION and DESIGNS are in PROGRESSINVESTIGATION and DESIGNS are in PROGRESS
AGREEMENT DATE : 9/2005AGREEMENT DATE : 9/2005
Financial – Rs. 7.47 Crores (Mob. Adv. Only) against Rs. 149.40 Crores
Financial – Rs. 7.47 Crores (Mob. Adv. Only) against Rs. 149.40 Crores
Land Acquisition:
Required : 3,000 Acs.
Requisitioned : 169.95 Acs.
Acquired : Nil
Land Acquisition:
Required : 3,000 Acs.
Requisitioned : 169.95 Acs.
Acquired : Nil
Package No. EPC / OC- : LIFT-I :
Design, manufacture, supplying &
erection of pumps, motors, electro
mechanical works, including tunnel,
cistern and pump house etc.
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s Patel
Engineering Ltd.
Agreement Amount : Rs. 383.349Crores
Agreement Date : 07-03-2005
Period of Completion : 30 Months (10 milestones) Investigation :Completed (3.0725 KM)
Designs (Tunnel, Pump House, Surge pool, Cistern) : 2.70 KM approved against 3.0705
Execution : Excavation in progress (approach channel, tunnel, surge pool
& Pump house)
Qty. of earth work done : 5.50 Lakh Cum against 7.82 Lakh Cum.
No. of Machinery : Deployed = 8 Nos (Excavators = 6 Nos., Dozers = 2 Nos. etc)
Land Acquisition : Required 250 Acres, Requisitioned 218Acs Acquired – 111
Acs.
Expenditure : Rs. 52.16 Crs. against Rs. 383.34 Crs. (Mob. Adv
paid – Rs. 19.58 Crs.)
Mob Adv. Recovered : Rs. 1.61 Crs.
Bottlenecks : Land Acquisition
Package No. EPC / OC- : Design and
execution of Stage-I and stage-II
pumping stations of lift-II at
Thirumalayapalli & Kothakota (M),
Mahabubnagar (D) on EPC basis.
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor : M/s NEC – NCC –
MAYTAS (JV)
Agreement Amount : Rs. 391.55 Crores
Agreement Date : 14-03-2005
Period of Completion : 30 Months
Investigation : Completed (3.132 Kms)
Designs (Tunnel, Pump House, Surge pool, Cistern) : Approved
Execution : Excavation 0.383Km in progress (approach channel, tunnel, surge pool & Pump house)
Qty. of earth work done : 1,70,000 Cum against 5 Lakh Cum.
No. of Machinery : Deployed = 18 Nos (Excavators = 4 Nos., Dumpers = 12 Nos.,
Dozers = 2 Nos. etc)
Land Acquisition : Required 135 Acres, Requisitioned 67 Acs. Acquired – Nil
Expenditure : Rs. 71.58 Crs. against Rs. 391.55 Crs.
Mob. Adv. Paid : Rs. 19.58 Crores.
Mob. Adv. Recovered : Rs. 6.00 Crores.