RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan,...
Transcript of RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan,...
![Page 1: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/1.jpg)
1
RAJASTHAN ELECTRICITY REGULATORY COMMISSION
JAIPUR Suo-Motu
In the matter of Rajasthan Electricity Regulatory Commission (Distribution
Licensee’s Standards of Performance) Regulations, 2012 Coram: Shri D.C. Samant, Chairman
Shri S. Dhawan, Member
Date of hearing: 18.06.2013
Date of Order: 17.02.2014
Memo on Statement of objects & reasons and consideration
of Comments / Suggestions, received from various stakeholders
1. The Rajasthan Electricity Regulatory Commission, in exercise of the powers
conferred on it by sections 57 to 59 read with sections 86(1)(i), 181(1) and
181(2)(za & zb) of the Electricity Act, 2003 (36 of 2003) and all other powers
enabling it in this behalf, prepared the draft Rajasthan Electricity
Regulatory Commission (Distribution Licensee’s Standards of Performance)
Regulations, 2012 (‘SOP Regulations’ in short) and invited suggestions /
comments from the stakeholders, by publishing Public Notice in following
news papers:
1) Dainik Bhaskar dated 03.11.2012
2) Dainik Navjyoti dated 03.11.2012
3) Times of India dated 03.11.2012
The draft Regulations, along with background note, was placed on the
Commission’s website. The last date for offering suggestions or comments
was kept as 30.11.2012.
2. The copies of draft Regulations were also sent to the members of the State
Advisory Committee of the Commission, for offering their suggestions.
3. On the request from the Members of the State Advisory Committee made
during its 14th meeting held on 23.11.2012, the last date for offering
suggestions or comments, was extended up to 21.12.2012 by publishing
Public Notice in the following news papers:
1) Rajasthan Patrika dated 28.11.2012
2) Rastradoot dated 28.11.2012
3) Times of India dated 29.11.2012.
![Page 2: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/2.jpg)
2
The Members were also intimated through letters, about such extension of
the last date for offering suggestions or comments.
4. The Commission received comments/ suggestions from the following
stakeholders within the due date of 21.12.2012:
1) Sh. Narendra Agarwal, Taranagar
2) Sh. D.P.Chirania, Retired CE, RVPNL, Jaipur
3) Sh. Rajendra Kumar Mehta, Bundi
4) Sh. B. M. Sanadhya, Director, Samta Power, Jaipur
5) Sh. Shanti Prasad, Jaipur
6) Sh. Y. K. Bolia, Director, Samta Power, Udaipur
7) Sh. G.L. Sharma, Jaipur
8) Sh. R.G. Gupta, Chief Executive, RVVS, Jaipur
9) Sh. B.L. Jat, Gen. Secy, RSEB Engineers Association, Jaipur
10) Sh. Rakesh Kumar Parmar, Samajik Vikas Samiti, Dholpur
11) Sh. Pramod Jhanwar, Maruti Sewa Samiti, Udaipur
12) Sh. S.C. Kothari, Member, Samta Power, Beawar
5. The Distribution l icensees, named as under, offered their
suggestions/ comments after the last date of 21.12.2012. However,
keeping in view the requirement under the Section 57(1) of the Act to
specify the Standards of Performance of the licensees after consultation
with them, the suggestions/ comments so received have also been
considered:
1) Jaipur Vidyut Vitran Nigam Ltd., Jaipur (JVVNL)
2) Jodhpur Vidyut Vitran Nigam Ltd., Jodhpur (JdVVNL)
3) Ajmer Vidyut Vitran Nigam Ltd., Ajmer (AVVNL)
6. The hearing in the matter was held on 18.06.2013, wherein the following
were present:
S. No. Name of Stakeholders
1. Sh. R.C. Jain, Dy. CE (HQ), JdVVNL
2. Sh. A.K. Mathur, S. E.(RA&C), JdVVNL
3. Sh. L.N. Soni, XEn (RA), JdVVNL
4. Sh. Arvind Jain, AEn (Comml.), JdVVNL
5. Sh. R. P. Agrawal, S.E. (Comml.), JVVNL
6. Sh. Ajeet Saxena, XEn (RA&R), JVVNL
7. Sh. S. T. Hussain, AEn (RA&R), JVVNL
8. Sh. V.K. Agrawal, XEn (Comml.), AVVNL
9. Sh. R.L. Chechani , Consultant, Rajasthan Discoms
10. Sh. R. G. Gupta, Chief Executive, RVVS, Jaipur
![Page 3: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/3.jpg)
3
11. Sh. R. Jhalani, Director, RVVS
12. Sh. Satish Sharma, Sr. Vice President (HQ), PEAR
13. Sh. Y. K. Bolia, Director, Samta Power, Udaipur
14. Sh. S. C. Kothari, Member, Samta Power, Beawar
15. Sh. D. P. Chirania, Retired CE, RVPNL, Jaipur
16. Sh. B. L. Jat, Gen. Secy, RSEB Engineers Association, Jaipur
17. Sh. G. L. Sharma, Jaipur
18. Sh. M. C. Agrawal, Retired S.E., JVVNL
19. Sh. Mohd. Wahid, CA.
20. Sh. B. M. Sanadhya, Director, Samta Power, Jaipur
7. All the three members of the Commission were present during the hearing
in the matter. However, one member namely Shri S. K. Mittal has demitted
office on completion of his tenure. This order, therefore, is being passed by
two members, including Chairman of the Commission.
Stakeholders’ Comments / suggestions and Commission’s
view & decision
8. The Commission has received a number of comments / suggestions from
the various stakeholders, listed above. These comments / suggestions,
being very useful, have been given due cognizance in finalising these SOP
Regulations for the Distribution licensees. The Stakeholders’ comments /
suggestions have been analysed as under along with the Commission’s
view and decision:
I. General comments on Discom’s staffing pattern and
requirements to meet standards
II. Other general comments
III. Comments/ suggestions on the draft Regulations
IV. Comments/ suggestions on the Schedules to the draft
Regulations
I. General Comments on Discoms’s staffing pattern and requirements to
meet standards
Shri Y. K. Bolia
1) During the hearing, Shri Bolia suggested that “Time-Motion Studies”
should be got conducted by the Discoms which would facilitate the
Commission to specify realistic Standards of Performance. He expressed
his concern as regards shortage of technical staff with Discoms
especially in Rural areas.
![Page 4: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/4.jpg)
4
2) He mentioned that at some places, for as many as 25 numbers of
villages, only 1 complaint- attendant is deployed, who, at times, is more
than 50 years old. He emphasized that there should be required staff
along with provision of accountability of Helper and above cadre. At
many places, particularly in rural sector, the staff deployed is illiterate,
with the result that whatever data is made available to the Commission
by Discoms, may not reflect the complete and correct picture. Shri
Bolia pointed out that the staffing pattern was set up way back in 1969
in the times of the then RSEB. Based on those norms, as per consumer–
employee ratio, the employee strength should now be around 1.0 Lac
against which it is only 36,000 and moreover most of these employees
are at the verge of retirement. At that time there was one technical
employee on an average for every 70 numbers of consumers, while
today, it is for around 250 consumers on an average. He expressed
concern on shortage of technical hands which affects the service
standards.
3) He voiced his concern that there are many Sub-divisions with as many
as 30,000 to 40,000 numbers of consumers but with no Accountant,
A.R.O., and Meter Reader etc.
4) Shri Bolia recalled that in RSEB time, there was one post of Chief
Engineer of protection, which has subsequently been abolished. Now a
days, the Discoms are involved in the metering process only with hardly
any care, time or resources, oriented to Protection side.
5) He wondered that on one hand, the complaints are proposed to be
entertained on SMS, mail or voice mail but on other hand, the technical
workers do not have even bare essential tools like torch or even hand
gloves or pliers. He mentioned that the limit of Rs.50/- per month,
towards petrol expenses, approved for the Junior Engineers of the field,
four decades back, has yet not been revised.
6) He said that the ‘RAPSAR’ Act is yet another handicap, in deploying the
staff. The manpower contract of a 33 kV GSS is awarded for as low an
amount as Rs.10,000/month, which hardly suffices even for 2 persons for
24 hours, resulting in shortage of staff at such places.
7) Further, during the RSEB days, an exhaustive training of the officers of
different wings was used to be conducted by the management for
almost 2 months period but these days, the training session lasts for only
4 days.
![Page 5: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/5.jpg)
5
Shri B. L. Jat
8) During the hearing, Shri Jat argued that in 1967, there was one Sub-
division after every 8000 number of consumers in rural and 12000 in
urban, but to-day the number of sub-stations are much short of the
required number. Till such time the resources are made available, the
SOP provisions should not be enforced.
9) He said that on one hand, there are provisions of penalty in the Public
Services Guarantee Rules, on other hand many Sub-divisions are devoid
of employees. In 1985 there were 25 consumers per employee and now
there are about 250 consumers per employee. The O&M safety
measures are very old. It is very difficult to handle above one crore of
consumers. Therefore, ground realities be seen before enforcing the
SOP Regulations.
Shri B. M. Sanadhya
10) Shri Sanadhya pointed out various norms being followed in the erstwhile
RSEB regime due to which the problems listed in the draft Regulations
were not appearing. These norms are not being followed now; for
example:
i. Provision of map indicating whole network.
ii. Indexing of poles, distribution Sub-stations and consumers.
iii. REC Register indicating details of infrastructure and progress of each
village and information about all types of assets.
iv. There were four documents relating to Meter Readings, mentioned in
the Revenue Manual– A-10: Meter Reading Binder, A-27:
Consumption Variation Register, A-30: Meter Reader Reports and A-
51: Meter Card put on the meter. Through these documents all the
problems relating to meter were monitored and redressed.
v. Provision of bill distribution receipt and getting consumer's receipt in
the book.
11) He advised the Discoms to adopt earlier procedure/norms so as to
reduce the consumer complaints.
12) Shri Sanadhya also advised that staffing pattern vis-a-vis work load
should be reviewed every year and ensured regular line patrolling &
sub-station inspection. The provision of R&D should also be
incorporated.
13) Before releasing connections, the Discoms should ensure the testing of
consumer’s installation specifically for proper earthling, ELCB, over load
protection, over voltage protection, short circuit protection etc.
14) During the hearing, Shri B. M. Sanadhya stressed the need of preventive
maintenance by the Discoms. He mentioned that the Regulations
![Page 6: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/6.jpg)
6
provide for “Symptomatic” treatment only and the provision of
compensation will not help. He stressed the need for review of staffing
pattern. The process of indexing should be there and any change
should first be in the map of the Sub-division, before any alteration is
made at site. He advised that the pole should bear its identity number,
after proper survey is conducted. He underlined the significance of
formation of sub-groups, comprising labour and consumers, so that
“Chaupal” concept may be implemented.
Shri R. G. Gupta
15) During hearing Shri R. G. Gupta said that there is vast gap between the
desired level of standards to be maintained by the licensees and their
capability to do so. He said that Discoms are short of required staff and
this adds to their difficulty. He argued that regulator can play an
important role in removing this difficulty, more so as licensees on their
own are not able to get the required staff sanctioned from the Govt.
He drew attention of the Commission towards Sec. 86 (1) (i) which reads
as “specify or enforce standards with respect to quality, continuity and
reliability of service by licensees” and contended that State
Commission is not only required to specify standards but even its
enforcement falls within its domain. He further stated that since
inadequate staff is also a constraint, the Commission can intervene and
pass appropriate order under this provision. He accordingly suggested
that Commission should engage itself and approve the requirement of
staff to enforce the standards of performance. He also suggested that
Board of Directors and the higher management should also be
responsible for enforcing standard of performance instead of leaving
that to concerned AEN and other lower levels.
Shri S. C. Kothari
16) During the hearing, Shri Kothari complained against the general
callousness of the Discoms’ response in respect of complaints and
mentioned that despite repeated complaints and suggestions, the
results were always missing.
Jaipur Discom
17) Shri Ajeet Saxena, Executive Engineer mentioned on behalf of Jaipur
Discom that it can be appreciated by one and all that despite
absence of provision of compensation so far, the Discoms’ officers are
working day and night to meet the consumers’ aspirations.
![Page 7: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/7.jpg)
7
Commission’s views
18) Commission has given careful consideration to the suggestion of Shri
R.G.Gupta as regards steps required to bridge the gap between
capabilities of the Discoms on the one hand and the responsibility of
them to maintain specific standards on the other. Commission has also
taken note of the strong comments of various stakeholders as regards
the necessity of removing the constraint of technical staff with Discoms
and their appropriate strengthening to meet with specified standards.
However, Commission believes that it is for the licensees to work out the
requirement and take up the matter with the Govt. at the appropriate
levels to see that staff related issues are suitably addressed. From the
presentation of various stakeholders it does appear that appropriate
strengthening of Discoms is required. Having said that Commission
would also like to clarify that it would not be appropriate for the
Commission to get involved in assessing the staff related requirement of
licensees, which better needs to be done by them.
19) In view of the above discussed position, the Commission is not inclined
to accept the suggestion of the stakeholder that Commission should
invoke its power under Sec. 86(1)(i) and approve requirement of staff
for enforcing SOP. However, Discoms must take necessary steps to
strength their field set up for meeting the Standards and for timely
redressal of consumers’ complaints.
II. Other General Comments
Shri R. G. Gupta
1) During the hearing, Shri Gupta said that the consumer indexing could
be enforced and regulated by the Regulatory intervention only. He
mentioned the independent performance audit, for which the Model
Regulations of the FOR can be considered.
Shri S.C. Kothari
2) A consumer advocacy cell may be instituted by the Commission to
provide the legal advice, support & assistance to complainant for
representing their case before the Ombudsman. Such a Cell should be
funded by the Commission. The Cell may also perform additional
functions as specified under Model Regulations as detailed below.
(i)Half Yearly review of grievances, representations & reports submitted
by the Forum & the Ombudsman in order to advice the Commission on
improvements to be made in the Regulations.
(ii) Analysis of reports submitted by the Licensees with regard to levels
of performance achieved on performance standards specified under
![Page 8: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/8.jpg)
8
section 57 (Consumer Protection Standards of Performance of
Licensee) of the Act.
(iii)Facilitate capacity building of consumer groups & ensure their
effective representation for enhancing the efficiency of regulatory
processes.
Commission’s views
3) The Commission noted the comments / suggestions furnished by the
Stakeholders.
III. Comments / suggestions on the draft Regulations
Shri D. P. Chirania
1) The Commission is in process of revising the already existing RERC
(Distribution Licensee’s Standards of Performance) Regulations, 2003.
The proper way of revision in any existing regulation is to state the
existing section, one by one, and if there is any proposed revision of the
same, than produce the revision by the side of the existing one with a
little commentary on the ground of the proposed revision so that a
clear picture is available to the commentator before he or she can
comment. The Commission has not followed this normal procedure of
inviting comments on the proposed revision and therefore, the
preliminary objection is that the Commission should follow proper
procedure of inviting comments on the revision of an existing
regulation. When it is a revision of an existing regulation, it cannot be
termed as draft Regulation. In fact, it is the case of proposed
amendments in an existing Regulation.
Shri R. G. Gupta
2) During the hearing, Shri Gupta advised that in the SOP Regulations,
2003, the provision for adjustment of the Security in case of reporting of
a burnt meter was in place and the same should be retained in the
following manner, in the proposed Regulations as well, :
“In case burning of the meter/metering system is due to causes
attributable to consumer (like tampering, defects in consumer’s
installation, excessive leakage to meter due to falling of water on
meter, unauthorized connection of additional load by the
consumer etc.), then meter security will be adjusted towards cost
and consumer shall be served notice to deposit meter security
amount afresh and cost of associated equipments/materials (e.g.
meter box, MCBs, and/or service line etc.)”
![Page 9: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/9.jpg)
9
Shri S.C. Kothari
3) The Commission should follow the normal procedure of inviting
comments on the proposed revision and therefore, the preliminary
objection is that the Commission should follow proper procedure of
inviting comments on the revision of an existing Regulation.
Shri G. L. Sharma
4) On 5.7.2011 the State Government has issued the Public Services
Guarantee Document and the Commission’s efforts should be such that
the various provisions of the SOP Regulations do not overlap with that
document.
Shri Rakesh Kumar Parmar
5) The draft Regulations were notified for previous publication in English
only. Rajasthan being a Hindi language State, the draft should also be
made available in Hindi.
6) Further, the Standards of Performance along-with admissible time limit
should also be printed on the back side of the consumers’ electricity
bills and also be indicated outside the Discoms’ Offices.
Commission’s views
7) The reasons for replacing the existing Regulations have already been
elaborated in the Background Note attached with the draft
Regulations. The Commission has initiated the process by way of
previous publication, which is as per the requirement of the Electricity
Act, 2003. The above observation is with respect to the comments of
Shri Chirania and Shri Kothari about the mechanism of framing the
revised SOP Regulations.
8) As regards the suggestion of Shri R. G. Gupta, Commission agrees with
the suggestion that the matter of charging meter cost and adjustment
of security relate to the Supply Code Regulations. Accordingly, the
Regulation 12(1) of the draft stands revised as under:
‘Save as otherwise provided in these regulations, the RERC
(Distribution Licensee’s Standards of Performance) Regulations,
2003 are hereby repealed on coming into force of these
regulations except the Regulation 9(iii) thereof so far as charging
of cost / security in case of burnt meters, is concerned which will
remain in force till it is incorporated in the RERC (Supply Code and
Connected Matters) Regulations, 2004.’
9) As regards the suggestion of Shri G. L. Sharma, it is stated that while
preparing the draft Regulations, the provisions appearing under the
Public Services Guarantee Act were kept in view. However, provisions
![Page 10: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/10.jpg)
10
relating to release of connections, meters etc. shall be as prevailing in
the RERC (Supply Code and connected matters) Regulations, 2004 and
RERC (Metering) Regulations, 2007; specified by the Commission under
the Electricity Act, 2003.
10) The requirement of Hindi version of the draft regulation, as sought by
Shri Rakesh Kumar Parmar, was met. The printing of the all SOP data at
the reverse side of the bill or indicating the same outside the Discoms’
offices is not feasible.
Background note
Shri D. P. Chirania and Shri S.C. Kothari
11) After examining / reviewing the position, the Commission should have
annexed the outcome of the findings so collected in r/o other SERC/
Forum of Regulators for proper examining of the parameters under
reference for thorough study of the terms & conditions prevailing in
other SERCs, so as to enable to submit comments more precisely.
Commission’s views
12) As regards the position prevailing in other SERCs and Report of Forum of
Regulators, the same are available on Internet. The Commission did not
find it appropriate to annex such studies with the draft regulations.
Preamble
Shri G.L. Sharma
13) In the opening para, the words appearing as “after previous
publication” may be deleted as the proposed Regulation 1(2) already
takes care in this respect and such wordings in opening para are not
required.
14) In place of words “after previous publication” the word “hereby” may
be placed.
Commission’s views
15) The suggestions of Shri G. L. Sharma and Shri S.C. Kothari are accepted
and accordingly the words “after previous publication” have been
replaced with the word “hereby”.
Regulation 1. Title and Commencement
Commission’s views
16) The words used in bracket in Regulation 1(1) i.e. ‘Distribution Licensee’s
Standards of Performance’ are being modified as ‘Standards of
Performance for Distribution Licensees’ as this gives a better expression
![Page 11: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/11.jpg)
11
for the title of SOP Regulations. Similarly, year in the title is being
changed from ‘2012’ to ‘2014’. Accordingly, the Regulation 1(1) shall
be as under:
‘(1) These Regulations shall be called the ‘Rajasthan Electricity
Regulatory Commission (Standards of Performance for Distribution
Licensees) Regulations, 2014.’
17) The Commission has given careful consideration to the position strongly
brought out and articulated a number of stakeholders as regards
inadequacy of staff and infrastructure to meet the standards envisaged
in the draft SoP Regulations. It has been said that there is vast gap
between the desired level of standards to be maintained by the
Licensees and their capability to do so. It has also been brought to our
notice that there is shortage of technical staff, particularly in remote
and rural areas and even the essential tools to maintain and operate
system are not available with field staff in such rural and remote areas.
The constraints of the licensees in induction of technical and other staff
due to applicability of RAPSAR Act and ageing of the existing field staff
has also been strongly highlighted.
18) However, the Commission is of the view that despite inadequacy and
shortcomings highlighted during hearing, specifications of revised
standards of performance by Distribution Licensees under Section 57 of
the Electricity Act need not be deferred or delayed. Standards of
Performance were earlier specified in the year 2003 and situation since
then has undergone considerably change.
19) In view of the discussed position, the new SOP Regulations based on
draft need to be finalised. The Distribution Licensees would need to
gear up to be able to meet the standards. The augmentation and
strengthening of system, wherever required, will have to be planned
and implemented. The field staff should be equipped with the required
tools and equipments for redressing consumers’ complaints and
grievances and shortage of technical and other staff would also have
to be appropriately addressed, and if required, the matter would need
to be taken up with the Government at appropriate level.
20) However, considering the said position, the Commission is of the view
that certain moratorium period should be allowed to the Discoms for
enforcing these regulations and the provision of compensation as
determined and specified in the regulations should be made effective
from a date to be notified separately. Accordingly, the proposed
Regulations 1(2) has been revised as under:
![Page 12: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/12.jpg)
12
‘(2) These Regulations shall come into force with effect from
1st October, 2014. However compensation amount for the non-
compliance of these Regulations by the licensees, shall be
payable to the affected persons, from the date(s) to be notified
separately by the Commission.’
Regulation 2. Scope of Application
Shri R. G. Gupta and Shri G. L. Sharma
21) Scope of application may be the same as contained at para 3.1 of the
Forum of Regulator which is re-produced below:
“These regulations shall be applicable to all the distribution licensee
including deemed licensee under section-14 of the Act and its
consumers in the State of Rajasthan.”
Commission’s views
22) The standards are for the Discoms to comply with therefore there is no
need to include ‘consumers’ in the Regulations. Similarly, there is no
need to refer the Section 14 of the Act, under which license is granted.
Hence, no change is required in the existing draft Regulation.
Regulation 3. Definitions
Shri D. P. Chirania
23) For serial numbers 6,7 and 9, a word ‘nominal’ may be added before
‘voltage’ because the system voltage is known by its nominal voltage
with a certain upper and lower limits.
24) The words ‘and panchayat Samities’ may be added at the end of
item (10)
Shri G.L. Sharma
25) In Reg. 3(2) the word “retail” may be deleted as licensee makes retail
and bulk both kind of supply.
26) In Reg. 3(3):
(a) The words “with adequate technology” is required to be
deleted as it is the responsibility of the licensee itself to do so. If
they do not do so, they will themselves bear the consequences.
Further by keeping these words, in the event that licensee does
not have such arrangement, should it be appropriate not to
consider such centres as “call centre” and any complaint
registered at such centre will not be considered as a legitimate
complaint etc.
(b) again the word “retail” in this regulation be deleted.
![Page 13: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/13.jpg)
13
(c) The words “round the clock throughout the year” appearing in
this regulation may be deleted. Once the complaint has been
registered it is the responsibility of the licensee to address the
same within the time specified in these Regulations.
(iii) At the end of the Regulation, between the words “not defined
in these regulations” and the words “but defined elsewhere,”
the following words may be added :-
“Or in the Electricity Act or in the rules and regulations made
there under”
27) Further the word “elsewhere” may also be replaced with the words “in
any law passed by a competent legislature and appropriate to
electricity entity in the State” as meaning of “elsewhere” could be
taken in some other way.
Shri R. G. Gupta
28) It is understood that ‘Rural area’ and ‘Urban area’ as defined,
completely covers the geographically jurisdiction of the licensee for
which the licence has been granted. However, it may be further
ensured that no area or consumer of licensee is left uncovered by these
regulations.
Shri S.C. Kothari
29) The words ‘and panchayat Samities’ may be added at the end of item
(10).
30) The word “Industrial estates of township” may be deleted in the item
no. 12 “Urban Area”.
Reply from Jaipur Discom:
31) The word nominal may be added before ‘voltage’ to maintain status
quo with the technical vocabulary.
32) The ‘panchayat samities’ may be added to add more clarity.
Commission’s views
33) The suggestions of Shri Chirania, as also agreed by the Jaipur Discom,
to replace the word “voltage” by the expression “nominal voltage” and
to add Panchayat Samities in Rural Areas, have been agreed to.
34) The suggestion of Shri G. L. Sharma to delete the word “retail” in
Regulation 3(2) and 3(3) has also been agreed to.
35) Considering the suggestion of Shri G. L. Sharma about definitions of
other words, the last para of the Regulation has been modified so as to
reworded as under:
![Page 14: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/14.jpg)
14
‘Words and expression used and not defined in these regulations but
defined in the Act shall have the meanings assigned to them in the
Act. Expressions used herein but not specifically defined in these
regulations or in the Acts but defined under any law passed by a
competent legislature and applicable to the electricity industry in the
state shall have the meaning assigned to them in such law.’
36) Other suggestions of the stakeholders have not been found
acceptable.
Regulation 4. Guaranteed Standards of Performance
Shri D. P. Chirania and Shri S.C. Kothari
37) 4 (1): In the first line, the word ‘possible’ need to be deleted as it is
making the things uncertain.
38) 4 (2) : It is irrelevant and confusing and thus be deleted.
39) Please include the clauses 3.i to 3. vi of the earlier Regulation as these
are very important and deletion of the same in the revised form dilutes
the things. The sanctity of the Regulation is getting lost in absence of
these. Salient part of these clauses with certain addition/deletion is
reproduced as under for appropriately including the same:
i. The licensee shall register every complaint made by a consumer
whether verbally or in writing regarding failure/interruption of power
supply, quality of power supply, meters/meter boxes/metering
system’s service line, payment of bills and other services relating to
power supply free of any charge.
ii. A unique number shall be allotted to each complaint. This complaint
number shall be conveyed to the consumer.
iii. Complaints in respect of supply of electricity, its metering, billing and
payment thereof, shall be made at specified offices and the Call-
center of the licensee.
iv. Licensee shall convey the name of office(s), its address(s), e-mail
address and telephone numbers where the consumer can lodge
complaints, at least once with the electricity bill and also display it at
the AEn’s office.
v. The office where a complaint is registered shall dispose of it and if any
instruction/sanction is to be obtained from a higher authority, it shall
be obtained by the complaint registering office.
vi. The complainant should not be required to approach such higher
authority.
vii. Complaints against non-registration of complaints and failure to
perform within the time limits and/or to meet the performance targets,
as specified in these regulations, shall be made to the concerned
![Page 15: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/15.jpg)
15
Executive Engineer and in case of unsatisfactory disposal of complaint
to Superintending Engineer (O&M).
viii. In case a consumer is not satisfied with the disposal of complaint even
after taking the issue at the level of Executive Engineer/
Superintending Engineer, he can approach the complaint redressal
committee.
ix. The licensee shall ensure holding of complaint redressal meetings
where entry shall be free and consumers will be able to file their
complaints. These meeting shall be held in the office of Assistant
Engineer on 10th of every month and in the office of the
Superintending Engineer on 20th of the same month. Minutes of the
Assistant Engineer level meeting and action taken report will be
available to the Superintending Engineer at the time of meeting to be
held by him on 20th of the same month. The redressal committee shall
dispose of the matter in not more than three meetings.
Shri G.L. Sharma, Jaipur
40) In first line of sub Reg. (1) the words “endeavor” may be replaced with
the words” be responsible”.
41) In first line of sub Reg. (1) the words “best possible” be replaced with
word “the best”
42) In third line of sub Reg. (1) before the words “guaranteed Standards of
service” the word “minimum” may be added.
43) Further after the words “guaranteed Standards of service” the words”
required to be achieved by the licensee” may also be added.
44) Sub Reg. (2) may be deleted. These guaranteed Standards of service
has to be performed and achieved by the licensee in all respect. The
standards prescribed herein have been after taking into considerations
all the provisions of relevant other regulations.
Shri R. G. Gupta
45) The monetary compensation prescribed in the schedule-I should be
considered as minimum monetary compensation. If the consumer is not
satisfied with amount of that compensation, he has legitimate right of
coming to the Commission under section-57(1). The facility provided in
the Act shall remain operative despite the monetary compensation as
per schedule-I.
Commission’s views
46) The suggestions, given by Shri Chirania and Shri Kothari are mostly
pertaining to and already existing in the RERC (Guidelines for Redressal
of Grievances) Regulations, 2008, as such, need not be incorporated in
![Page 16: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/16.jpg)
16
SOP Regulations. The matter relating to complaint handling mechanism
has been dealt hereinafter at appropriate place.
47) Looking to the suggestions of Shri G. L. Sharma the words ‘endeavor to’
and ‘possible’ shall be deleted. However, remaining suggestions about
the language of the draft Regulations have not been found
acceptable. Further, instead of deleting the proposed Regulation 4(2),
it has been slightly modified for more clarity, as under:
‘(2) These guaranteed standards shall be read with the provisions
specified under the RERC (Electricity Supply Code and Connected
Matters) Regulations – 2004 and other relevant regulations,
amended from time to time.’
48) The suggestion of Shri R. G. Gupta to treat the monetary compensation
as minimum compensation subject to right of consumer to approach
Commission for revision is neither desirable nor practicable.
Regulation 5. Complaint Handling Mechanism
Regulation 5(1)
Shri Y. K. Bolia & Shri B.L. Jat
49) It is a regular function of a licensee therefore it should be got
conducted from its own regular employees instead of on contract
basis. However till the regular employees are employed, the same can
be got conducted on contract basis but in that case tender should be
invited properly and orders be placed on competent contractor only.
Such centres can also be used for delivering consumer related
information and also for depositing the electricity bills.
Shri Pramod Jhanwar
50) The formation of Consumer Grievance Redressal Forum should be
made clear and should also include the representatives of Consumer
Forum.
Shri D. P. Chirania
51) Shri D. P. Chirania proposed to revise the provision as under:
‘The licensee shall publish a “Manual for Handling Consumer Complaints”
incorporating the details of call centres, toll free telephone numbers, email
address, for registering the complaints & to inform the status of its redressal,
details of concerned officers, guaranteed SOP, compensation & its payment
mechanism, application format and other relevant details, including that of
Sub-divisional level Consumer Grievance Redressal cum Settlement Forum
(CGRF) and Electricity Ombudsman.’
![Page 17: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/17.jpg)
17
Shri S.C. Kothari
52) The procedure followed in arriving at the decision including channels of
supervision & accountability is to be ensured in positive spirit within the
frame work of rules. The manual should contain the provisions for
providing correct information and not misleading, incomplete or false
information. The decision not given within the prescribed time limit, may
be deemed to be request refused. In case of failure to comply the
decision by a public authority within specified time limit, the information
to the applicant be provided free of charge.
53) The manual be updated every year, if required & monitoring should be
implemented under the Grievance Redressal Forums as per direction of
RERC. The Discom GRF associated with Monitoring Committee/ Member
nominated by RERC at all Forums, which, should contain members
having adequate experience of law, electricity handling engineering,
finance, & also having experience of VVNLs etc. such as retired
engineer etc. Such agency framed should be more effective with
powers to grant even relief(s) in case of failure to achieve the
guaranteed parameters.
54) The grievance may be prioritized for redressal based on the following
priority order:
a) Non- Supply
b) New Connection/Extension/Reduction/Deemed connection
c) Disconnection/Reconnection of supply
d) Meter related issues
e) Billing related issues
f) Other issues including functioning of VCR Monitoring Committee.
Reply from Jaipur Discom:
55) The points as specified may be included under the ‘Manual for
Handling Consumer Complaints’ of complaints handling mechanism as
per adequate technology, as per its appropriateness by the approval
authority.
Commission’s views
56) The suggestions pertaining to Discom’s functions, as furnished by the
stakeholders, need to be taken note of by Dicoms for taking required
actions and the suggestions relating to the manual should be given due
consideration while finalizing the Manual.
![Page 18: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/18.jpg)
18
57) The formation of CGRF is a matter of RERC (Guidelines for Redressal of
Grievances) Regulations, 2008, which cannot be incorporated in the
SOP Regulations, as suggested by Shri Pramod Jhanwar.
58) As regards priorities of the complaints, as suggested by Shri Kothari, it is
stated that the time frame for redressal of complaints have accordingly
been proposed in the SOP Regulations.
Regulation 5(2)
Shri G. L. Sharma
59) The words “the manual shall be prepared in English & Hindi “may be
worded as “the manual shall have language both English & Hindi and
shall also have the format prescribed by licensee for claiming the
compensation”.
Commission’s views
60) The suggestions furnished by the stakeholder have been accepted and
accordingly the Regulation 5(2) shall read as under:
‘(2) The manual shall be in both languages i.e. English & Hindi and shall
also have the format prescribed by licensee for claiming the
compensation. It shall be available at every sub-divisional office
for reference of general public as also for sale at nominal cost.’
Regulation 5(3)
Shri G.L. Sharma, Jaipur
61) The words “certified copy” are not clearly understood. It would be
suffice of only the word “a copy” is kept instead “certified copy”.
Shri R. G. Gupta
62) A copy of the manual may also be sent to the Members of the State
Advisory Committee.
Commission’s views
63) The suggestion furnished by Shri G. L. Sharma has been accepted and
accordingly the words ‘certified’ shall be deleted.
64) The suggestion of Shri R. G. Gupta does not need to be incorporated in
the Regulations. However, Distribution licensees shall provide a copy of
the Manual to a member of the State Advisory Committee if sought by
him.
Regulation 5(4)
Shri Narendra Agarwal
65) The concept of call centres was earlier envisaged & proposed by the
Discoms while finalising previous SOP regulations. In fact the Call centres
were proposed to be established by the Dec’06. Therefore, not more
![Page 19: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/19.jpg)
19
than 12 months time should be allowed irrespective of the class of cities.
It shall be obligation on Discom that centre must be functioning at least
sub-division level.
Shri D. P. Chirania & Shri S. C. Kothari
66) If the Commission is envisaging attending of all the complaints whether
it is relating to no current, metering, billing, quality of supply etc. through
Call centres and the efficiency of performance on name of minor
compensation; it has to come out with a complete design, that of the
Call-centres, the interface between Call-centers to Grid-sub-stations to
the complaints attending parties, the frequency of monitoring of the
calls, the monitoring mechanism, the feedback mechanism etc.
67) If on contract to establish & operate customer complaint center on
BOOM/BDDR basis, the Call-centre, having power back up UPS of
sufficient capacity/ time, Fault Rectification Team along with
appropriate infra structure, having, VTS services, Any time Payment
Kiosk, ATP Collection Centres for deposition of electricity bills/issue of
duplicate bills, Operation of spot billing Centres, Cash Collection
Centres for Energy Bills, etc.
68) If the infrastructure is created by the Licensee and operating services
are hired than it may become somewhat practical but up to supply
position. As far as metering and billing related problems are concerned,
direct contact between the consumer and the concerned Sub-division
is a must.
69) A detailed analysis on this aspect is a must otherwise the situation may
worsen in the name of compensation. Proper care & the safety
measures required to be taken in advance need to be ensured, so as
to avoid levy for minimal compensation.
Jodhpur Discom
70) Clause 5(4) (iii) may be deleted. It is difficult to establish call-centres in
Rural Areas. The prevailing practice is adequate i,e. the complainer
lodge their complaint with CCA of the rural area of nearby 33/11KV Sub
Station.
Shri Rakesh Kumar Parmar
71) The Discom should be allowed only one year period to establish the
Call Centres and their telephone numbers should be toll free.
Shri Pramod Jhanwar
72) It should be clear as to what action would be taken in case of failure in
establishing the Call Centres within the permissible time limit.
![Page 20: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/20.jpg)
20
Reply from Jaipur Discom:
73) The points as specified may be included under the ‘Manual for
Handling Consumer Complaints’ of complaints handling mechanism as
per adequate technology, as per its appropriateness by the approval
authority.
74) The time limit specified by the Commission should be looked as the
upper ceiling. Being a public sector entity, multiple approvals are
required to be taken prior to the execution of the scheme. The process
takes lots of time and input and therefore the time specified by the
Commission should not be revised considering the present intricacies of
the system.
75) In the recent tenders for establishing call centres in Jaipur & Kota City,
the response was not very encouraging and only 3 bids were qualified.
76) The additional means including email, website for receiving the
complaint could be added and it shall be included in the ‘manual for
handling consumer complaints’.
77) As specified in the regulations, there shall be one or more ‘Toll-free
number’ with sufficient lines to register the complaints.
Commission’s views
78) Some of the suggestions of Shri Chirania and Shri Kothari relating to
creation of Call Centres; shall be taken care in the Manual as agreed
by the Discoms while others can well be addressed during / after
creation of the Call Centres with step by step improvement in the
quality of services, in a phased manner.
79) Looking to the difficulties expressed by the Jodhpur Discom, the sub-
regulation (iii) shall be deleted and following sentence shall be added
at the end of last line:
‘The time limit for establishment of call centres in rural areas shall
be notified separately by the Commission.’
80) Other suggestions furnished by the stakeholders have not been found
acceptable.
Regulation 5(5)
Shri G. L. Sharma
81) The word “affected” may be replaced with the word “aggrieved”.
Further the words “to use” appearing in second line may be deleted.
![Page 21: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/21.jpg)
21
Shri Pramod Jhanwar
82) It is to be made clear that till the Call Centres are established in what
manner the complaints would be redressed under present channels.
Commission’s views
83) In the Section 57 of the Electricity Act, 2003, the term ‘person affected’
has been used, therefore the suggestion of Shri G. L. Sharma is not
acceptable.
84) It has already been made clear that till the establishment of call
centres, the existing channels for redressal of grievance would
continue.
Regulation 5(6)
Shri Y. K. Bolia & Shri B.L. Jat
85) Before imposing financial penalties, the Call Centres should be
strengthened with trained persons equipped with infrastructure and
necessary facilities. For monitoring of the working of these Call Centres
at Sub-divisional level and above, committees having retired
experienced persons should be constituted.
Shri D. P. Chirania & Shri S.C. Kothari
86) Add in end: ‘or e-mail’
87) Please consider the followings too:
a) The words such as ‘sufficient’ and ‘adequate’ are uncertain words
and their use may be avoided.
b) The things should be specified in certain form, say one telephone
line for 10000 consumers, one person for 10000 consumers etc.
c) When the Commission has got carried out study of other States, it
must have studied the bench-marked States with the infrastructure
they have created in this regard.
d) It is essential that the consumer should get immediate response
when called, and in case of traffic-congestion, the Call-centre
register the call as a missed call and automatically call back itself
without waiting repeated calls from the consumer.
e) Similarly there should be mechanism of automatically intimating the
reasons of no-current etc. complaints and periodically up-datation
of the status of the complaint.
Shri G.L. Sharma
88) At the end of this regulation words “or in writing” may be added.
![Page 22: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/22.jpg)
22
Commission’s views
89) As suggested by Shri G. L. Sharma, the words “or in writing” shall be
added at the end of the regulation.
90) Other suggestions furnished by the stakeholders have not been found
acceptable.
Regulation 5(7)
Jodhpur Discom
91) The Jodhpur Discom expressed the difficulty in printing the Toll-free
telephone number of the Call centre on the bills, so it was suggested
that the word “Printed” may be substituted by the word
“Communicate” and after the word “bills” the words “once in a year”
may be added.
Commission’s views
92) Looking to the difficulties expressed by the Jodhpur Discom, the
suggestion is accepted to the extent that instead of printing the Toll-
free telephone number the Discom shall indicate such number on the
bills. The Regulation has been modified accordingly.
Regulation 5(8)
Shri Narendra Agarwal
93) The complaint shall also be receiving/made in electronic mean such as
e-mail, web-portal etc.
Shri D. P. Chirania
94) He suggested to replace sub-para (iii) and (iv) as under:
iii. intimate the status of redressal of grievance as and when asked by the
complainant; Periodically automatic intimation including its automatic
passing to the higher authority after lapse of certain period.
iv. intimate the contact details of the next higher authority in case the
complainant is not satisfied with the redressal of his complaint
,automatic passing to the higher authority after lapse of certain
period.
95) Provision for automatically passing of the complaint to next higher
authority after a preset time limit, if the complaint is not redressed by
that time, need to be incorporated otherwise the system of call-centre
will remain ineffective.
Shri G.L. Sharma
96) He suggested to replace sub-para (i) and (ii) as under:
![Page 23: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/23.jpg)
23
(i) After the words “voice or SMS”, the words “or in writing in the
complaint registration register” may be added. Further between
the words “A model format” and “is enclosed” the words “of
compliant registration register” may be added.
(ii) In first line of sub Reg. (8) (ii) after the words “within 30 minutes” the
word “of registering the complaint” may be added.
97) During the hearing, Shri Sharma mentioned that the provision should be
in place, that for redressal of a complaint, if the approval / sanction of
next higher authority is required, the same shall be the responsibility of
the Call Centre, where the complaint has been lodged and the
complainant should not be asked to move to the next hierarchy.
98) He stated that if a complaint is not registered, the complainant may
send it by Registered Post as well, and he shall also be entitled for
payment of compensation, if the other conditions are met.
99) It is suggested that such form shall have the following details
a) Name of the consumer.
b) Address and contact number of the consumer.
c) Account Number.
d) Name of complaint centre where complaint was lodged.
e) Complaint number given by the complaint centre.
f) Date and time of lodging the complaint.
g) Date and time when the complaint has been redressed.
h) Total duration of time taken by the licensee in redressing the complaint.
i) Standard time period within which the complaint was required to be
redressed.
j) Amount of compensation claimed by the applicant consumer.
Shri R. G. Gupta
100) The Annexure-I should also include column of time of intimation to the
complainant about the nature of fault and status of complaint to
verify whether the status has been intimated within 30 minutes or not?
It is also suggested that the copy of the Annexure-I should be provided
to the complainant on demand for claiming the compensation. Such
copy should be provided within three days of making a request and
failure to do so should be considered as deficiency in the service and
should be included in the Schedule-II for compensation.
Shri S.C. Kothari
101) He suggested to amend sub-para (i), (iii) and (iv) as under:
![Page 24: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/24.jpg)
24
(i) The following words may be added in 2nd line after SMS – “fax or
email”.
(iii) The following words may be added in end – “Periodically
automatic intimation including its automatic passing to the higher
authority after lapse of certain period.”
(iv) The following words may be added in end – automatic passing
to the higher authority after lapse of certain period.
102) Provision for automatically passing of the complaint to next higher
authority after a present time limit, if it is complaint is not redressed by
that time, need to be incorporated otherwise the system of call-centre
will remain ineffective.
Shri Pramod Jhanwar
103) It is to be ensured that in case Call Centre does not attend a call for
certain time, then it should revert back to the consumer to attend the
complaint.
Reply from Jaipur Discom:
104) While addressing the above suggestions, the Jaipur Discom agreed to
that additional means of receiving the complaints including email,
website etc could be included in the ‘manual for handling consumer
complaints’.
Commission’s views
105) Following suggestions have been broadly accepted:
i. To elaborate the format in Regulation 5(8)(i) as ‘Model format for
registration of complaints’, as suggested by Shri G. L. Sharma.
ii. To elaborate the time in Regulation 5(8)(ii) as ‘within 30 minutes of
registering the complaint’, as suggested by Shri G. L. Sharma.
iii. To add a new sub-clause in the last, as suggested by Shri R. G.
Gupta with modification as under:
‘Provide a copy of the relevant extract of Annexure-I to the
complainant on demand, free of cost, for claiming the
compensation; within three days of receiving a request.’
106) The suggestions of Shri D. P. Chirania and Shri G. L. Sharma, relating to
requirement of sanction of higher authority as also relating to making
reference to higher officer in case of non-satisfaction, have been
addressed by incorporating new regulation 5(9&10).
![Page 25: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/25.jpg)
25
107) The suggestion of Shri G. L. Sharma, relating to details to be
incorporated in the format, has been addressed while revising the
format at Annexure -1.
Regulation 5(9 & 10) - now proposed:
Sh. G.L. Sharma, Jaipur
108) The following new sub Reg. may also be added after sub-Regulation
5(8) so as to complete the working:-
(9) The office where the complaint has been registered shall redress
the complaint within the time specified for the purpose. In case
any instructions/sanction is required to be obtained from a higher
authority, it shall be obtained by the complaint registering office.
The higher authority may also directly communicate the decision.
The complainant should not be required to approach such higher
authority.
(10) Complaint against non- registration of complaints and/ or failure
to perform/redress the complaint within specified time period,
shall be made to the concerned Executive Engineer/
Superintending Engineer. In the case the aggrieved person is not
satisfied with the disposal of such authorities; he may approach
sub-division level Consumer Grievance Redressal cum Settlement
Forum.”
Commission’s views
109) The Commission has accepted the suggestion with slight modification,
as under:
“(9) The office where the complaint has been registered shall redress
the complaint within the time specified for the purpose. In case
any instructions/sanction is required to be obtained from higher
authority, it shall be obtained by the complaint registering
office. The affected person shall not be required to approach
such higher authority.
(10) Complaint against non- registration of complaints and/ or failure
to perform/redress the complaint within specified time period,
may be brought to the notice of the concerned Assistant
Engineer /Executive Engineer by the affected person for
expediting the redressal of the complaint.”
Regulation 6. Payment of Compensation
Regulation 6(1)
Shri D. P. Chirania
110) In the 10th line after the word ‘application’ the words “free of charge,
personally or by registered post”, may be added:
![Page 26: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/26.jpg)
26
111) The clauses no. 4 and 5 of the existing regulation are very important
and these must be incorporated in the body of the present proposed
regulations, though the figures may be modified in accordance of the
proposed regulations.
Shri G.L. Sharma
112) He suggested to amend the provision as under:
i) The words “On violation of any guaranteed Standards as per
Schedule -1 “occurring in the beginning may be replaced as “In
the event of non-fulfilment of guaranteed standards by the
licensee within the time period prescribed under these
regulations”
ii) The words “standard time” occurring in 6th line may be reworded
as “specified time”
iii) The sentence starting as “However in case” and ending as “days
from the date of redressal of his complaint” needs to be deleted.
Shri R. G. Gupta
113) The two dispensation made in this para create a little bit of confusion
as to whether the complainant is authorized to file the claim for
compensation even before redressal of complaint or not. It should be
made categorical that application for compensation can be filed
before redressal of the grievances in case it is so opted by the
complainant after the expiry of the standard time of redressal
permitted as per schedule-I. It is also suggested that in normal course,
the licensee should pay the compensation and if aggrieved, the
consumer should go to Grievance Redressal Forum. It should not be
made the original jurisdiction for claiming the compensation.
Shri Y. K. Bolia & Shri B.L. Jat
114) The consumers are more interested in getting good quality of electric
supply rather to get compensation of small money. Therefore it is
necessary that the tenders are invited properly in two parts- technical
& financial bids and orders be placed on competent contractor only.
Presently the Electrical Inspectorate is not having proper infrastructure.
The Commission should direct the licensee to conduct necessary
testing of consumer’s installation before releasing connections. For
monitoring of such working at Sub-divisional level and above,
committees having retired experienced persons, should be
constituted.
![Page 27: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/27.jpg)
27
Shri Pramod Jhanwar
115) It is necessary to revise the name of Consumer Grievance Redressal
and settlement Forum because it infers as a court and consumers may
get confused.
Shri S.C. Kothari
116) In the 10th line after the word ‘application’ the words “free of charge,
personally or by registered or speed post” may be added.
117) The Scheme for payment of compensation in lieu of death caused to
the public/Animals due to electrocution, the Nigam is directly or
indirectly responsible for accident. The cause of accident & there
remedial measures are not being implemented/monitored at other
such locations, for which the Nigam earlier started to inspect the
installation prior to charging the lines & sub stations, which has been
dispensed with now & may be reviewed again.
Shri Rakesh Kumar Parmar
118) The amount of compensation should be deducted from the salary of
the defaulter employee / officer of the licensee.
Reply from Jaipur Discom:
119) The spirit of SOP regulations is to specify parameters and warning
signal on various parameters for any noted deviation as specified. The
actual impact of SOP may be observed after its implementation.
120) The regulations should be treated as a tool for measurement of
performance and it shall act as a deterrent for any deviation in
performance. The spirit of these regulations is to gradually improve the
performance of the system, culture and practice.
121) The term compensation payable by the licensee should not be looked
as the ‘opportunity of compensation’; otherwise it would be difficult to
quantify the opportunity and therefore the compensation amount.
122) It is suggested to the Commission to reword the ‘compensation’ as
symbolic ‘penalty’; as the whole spirit of SOP regulations would
foregone, if it is not treated as deterrent.
Commission’s views
123) The suggestion of Shri Chirania and Shri Kothari for lodging the
application for claiming the compensation, absolutely free of cost, has
already been incorporated under Reg. 6(4). However, the suggestion
of clarifying the process of filing of application has been accepted.
The other suggestion of Shri Kothari is not relevant here.
![Page 28: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/28.jpg)
28
124) The suggestion of Shri G. L. Sharma to mention ‘specified time’ in
place of ‘standard time’ has been accepted along with the
suggestion about the opening words of the provision.
125) In the Section 57 of the Electricity Act, 2003, the term ‘affected person’
has been used, therefore wherever, the words ‘aggrieved person’ has
been used, the same has been replaced with ‘affected person’.
126) The general suggestions of Shri Pramod Jhanwar, Shri Y. K. Bolia and
Shri B. L. Jat have already been addressed herein earlier.
127) The suggestion of Shri Rakesh Kumar Parmar that compensation
amount should be deducted from the wages of the defaulting
employees is within the domain of Discoms and provision for this is not
required in the SOP Regulations.
128) In reference to the comments of Shri R. G. Gupta, it is clarified that the
affected person may lodge the claim for compensation on non-
fulfilment of the specified standards by the Discom, irrespective of the
fact that the complaint was redressed subsequently.
129) The suggestion of Shri R. G. Gupta that in normal course, the licensee
should pay the compensation and if aggrieved, the consumer should
go to Grievance Redressal Forum; has been considered by the
Commission. However, the affected person has to lodge application
for the claim of compensation.
130) Considering the comments / suggestions of the stakeholders, as
discussed above, the Commission has decided to revise the
Regulation 6(1) as under:
‘(1) In the event of non-fulfilment of any Guaranteed Standards of
Performance, specified in Schedule – 1, the affected person may
file an application personally or by registered post to the
concerned Assistant Engineer, in the format prescribed by the
licensee, for the claim of compensation as specified in Schedule
– 2 of these Regulations. Such application can be filed within 30
days of expiry of the specified time. The licensee shall pay such
compensation, by way of adjustment through electricity bills, not
later than 90 days from the date of violation of the Guaranteed
Standard failing which an additional compensation @ 1% of the
compensation amount shall be payable to the affected
consumer for each week of delay or part thereof.’
![Page 29: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/29.jpg)
29
Regulation 6(2)
Shri R. G. Gupta
131) It has to be made clear that the Forum shall only examine the claim
with reference to the expiry of the standard time line of redressal.
Once the deviation from the standard time line is established, the
Forum should have no option except to award the compensation as
per schedule-II. However, if the Forum does not agree with the expiry
of the standard time line, then only the compensation will be denied.
The Forum should give a speaking order about acceptance or the
denial of the compensation.
Commission’s views
132) In reference to the comments / suggestion of Shri R. G. Gupta, it is
clarified that the Forum is required to function as per the RERC
(Guidelines for Redressal of Grievances) Regulations, 2008 and
required to decide the grievance within the time specified therein. In
case of non-settlement the Forum is required to record a speaking
order under the said regulations.
133) Keeping in view the revision in Regulation 6(1) as above, the
Regulation 6(2) shall now read as under:
‘(2) Failure by the licensee to pay the compensation as per Regulation
6(1) above, shall constitute a Grievance, which shall be dealt
and decided by the respective Consumer Grievance Redressal
Forum, in accordance with procedure set out in the RERC
(Guidelines for Redressal of Grievances) Regulations, 2008.’
Regulation 6(3)
Shri R. G. Gupta
134) The provision at para 6(3) is not consistent with the Act. Reference to
the ombudsman cannot arise in the matter of compensation. It will be
relevant to note that Grievance redressal Forum as envisaged in
section-42 of the Act is not empowered to determine compensation
which is the sole jurisdiction of Regulatory Commission under section-
57(1) of the Act. However, if the Commission so desires, it can
delegate this power of determination of compensation under section-
97 of the Act to any other person which can include the Sub Divisional
level Grievance Redressal Forum. In view of these legal provisions, the
act of determination of compensation by the Sub Divisional level
Grievance Redressal Forum shall not amount to the grievance
redressal as contemplated under section-42 of the Act. In the matter
of determination of compensation, the Sub Divisional level Grievance
![Page 30: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/30.jpg)
30
Redressal Forum will have separate identity which will work under
delegated authority of the Regulatory Commission under section-97 of
the Act. Hence, any person aggrieved with compensation of Sub
Divisional level Grievance Redressal Forum in the matter of award of
compensation is legally entitled to approach the Regulatory
Commission under section-57(1) and that door of Commission cannot
be closed to any consumer under Electricity Act. The provision of
appeal to the Ombudsman therefore, is not consistent with the Act
and should be dropped. It is therefore, requested that it may be
amply clarified by the regulator that the compensation as per
Schedule-II is not the same as the compensation as can be claimed
under section-57(1) of the Act. If it is so clarified, then the procedure as
envisaged in the proposed performance regulation can have legal
sanctity. Then non award of compensation would come into the
definition of grievance and accordingly be take care of by the
Grievance Redressal Forum and Ombudsman.
Commission’s views
135) Considering the suggestion of Shri R. G. Gupta, the procedure for
making the payment of compensation has already been revised as
above.
136) As regards delegation of powers, as suggested by Shri R. G. Gupta, it is
stated that the Commission itself has determined the amount of
compensation under Section 57(1) of the Act and incorporated in
these regulations made after previous publication wherein views of
licensees and stakeholders have been considered. Therefore, there is
no need to delegate its powers to any other person under section 97
of the Act. Non-payment of compensation by the licensee shall form a
grievance of the consumer which can be redressed by the Forum /
Ombudsman; as mentioned above.
Regulation 6(4)
Shri G.L. Sharma, Jaipur
137) The words “amount through” appearing in first line may be reworded
as “amount decided by the Forum/Ombudsman, as the Case may
be, through”
Shri R. G. Gupta
138) The mention of Ombudsman from this para should be dropped unless
clarification as sought above is made.
![Page 31: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/31.jpg)
31
Jaipur Discom & Jodhpur Discom
139) The rate of additional compensation 5% may be considered as 0.5%
per week or part thereof, as 5% rate seems to be very high side.
Commission’s views
140) The Commission has considered the above suggestion of the Discoms
and decided to specify the additional compensation as 1% per week
or part thereof for non-payment of compensation amount by the
licensees within the specified time under these regulations. The
provision specifying the period of payment along with additional
compensation, has been incorporated under Regulation 6(1) itself.
Therefore Regulation 6(4) of the draft is not required and hence
deleted.
Regulation 6(5)- now 6(4)
Shri G.L. Sharma
141) The word “a” appearing at the end of first line may be reworded as
“the”
Commission’s views
142) The Commission has decided to modify the regulation as under for
more clarity:
‘(4) The aggrieved consumer shall not be liable to pay any fee for
lodging a claim of compensation under these regulations before
the licensee, Forum or Electricity Ombudsman.’
Regulation 6(5) - New
Commission’s views
143) Keeping in view the provision appearing under the Section 57(2) of the
Act, the Commission has decided to add a new sub-regulation as
under:
‘(5) The payment of such compensation shall be without prejudice to
any penalty which may be imposed or prosecution be initiated
for the failure of the licensee in meeting the standards specified in
these Regulations.’
Regulation 7. Overall Standards of Performance
Regulation 7(1)
Shri Pramod Jhanwar
144) It is to be clarified as to what action would be taken in case of failure
in making compliance.
![Page 32: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/32.jpg)
32
Commission’s views
145) The failure in making compliance shall be considered as non-
compliance of the Commission’s Regulations.
Regulation 7(2 & 3)
Shri G.L. Sharma
146) The sub Reg. (2) and (3) of Reg.7 may be deleted. Sub Reg. (2) is
expenditure on account of failure of performance of standards and
compensation for the same is in the form of penal charges for not
performing their legitimate regular duties. For performing such duties
O&M expenses are allowed in ARR therefore no additional
consideration can be held for such expenses.
147) Similarly, for any expenditure required, for strengthening their system, it
is the duty of the licensee to prepare necessary estimates etc and to
obtain the sanction from the concerned authorities. It is not necessary
that provisions are made in the Regulations to suggest them for such
purposes.
148) During the hearing Shri Sharma mentioned that as per the Reg. 7(2)
the Commission is to allow in ARR, a part of the amount, paid as
compensation to the affected persons, based on the achievements of
the licensees, beyond the targets of overall standards. He mentioned
that it is deduced by this provision that though the compensation is
received by a few consumers, but in totality, the burden of the total
sum has to be borne by the consumers only, therefore it should be
avoided.
Commission’s views
149) The Commission is of the view that compensation to be paid may be
allowed in ARR based on assessment of licensee’s ability to achieve
overall standards. Other SERCs like HPERC, MPERC etc, are also
following this in ARR. Accordingly, Regulation 7(2) is being revised as
under:
‘(2) The compensation amount paid by the licensee, may be allowed
to be recovered partly or fully in the ARR, keeping in view the
extent to which the licensee is able to achieve the Overall
Standards as per the Schedule - 3.’
150) The Commission accepts the suggestion of the stakeholder and
Regulation 7(3) proposed in draft is being deleted.
![Page 33: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/33.jpg)
33
Regulation 8. Submission of SOP Reports
Regulation 8(1)
Sh. G.L. Sharma, Jaipur
151) In this regulation it may be added that besides submitting yearly
reports to the Commission it will be mandatory for the licensees that
they will invariably file such yearly reports with their ARR and Tariff
petitions as well.
Shri R. G. Gupta
152) The copy of the report should be made available to the Members of
the Advisory Committee.
Jodhpur Discom
153) It reveals that Discom shall have to furnish the sop reports on yearly
basis, whereas in the Formats it is indicated “for the 1st/2nd half year
ending” the Commission may clarify the matter.
Ajmer Discom
154) The 45 days should be replaced by 120 days for furnishing the yearly
reports in the formats SOP-1 to SOP-6 as collection of data from the
field & thereupon its compilation requires time.
Commission’s views
155) Jodhpur Discom has pointed out the mentioning of “Yearly Reports” in
the text of the Regulations while “First/Second half yearly ending” in
the format of the draft document. The matter has been examined and
it is decided that keeping in view the provision of half yearly reports in
the Rule 7 of the Electricity Rules, 2005, the Discoms shall be required
to furnish half yearly reports to the Commission as well as to the
Ombudsman, within 45 days. Accordingly, the words ‘The licensee
shall furnish the Commission, yearly reports within 45 days from the
close of each financial year’ shall be replaced with ‘The licensee shall
furnish the Commission as well as the Electricity Ombudsman, half
yearly reports within 45 days respectively from 30th September and 31st
March of each financial year’.
156) The suggestion of Shri G. L. Sharma that the Discom should invariably
file such reports with their ARR and Tariff petitions as well; is not
acceptable.
157) The request of the Ajmer Discom for a period of 120 days, instead of 45
days, for furnishing the yearly reports in the specified formats cannot
be agreed to.
![Page 34: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/34.jpg)
34
158) The request of Shri R. G. Gupta for providing copy of the Formats and
other relevant information to the members of SAC, need not to be
incorporated in the Regulations. However, the licensee shall provide a
copy of such reports to a member of State Advisory Committee if
sought by him.
Regulation 8(2)
Sh. G.L. Sharma, Jaipur
159) The words “and” occurring at the end of this Regulation may be
deleted.
Shri R. G. Gupta
160) The copy of the information/ report should be made available to the
Members of the Advisory Committee.
Commission’s views
161) As discussed above, the words ‘yearly reports’ shall be replaced with
‘half yearly reports’.
162) The suggestion of Shri G. L. Sharma to delete the word ‘and’ is
acceptable.
163) The request of Shri R. G. Gupta for providing copy of the reports to the
members of SAC, need not to be incorporated in the Regulations.
However, the licensee shall provide a copy of such reports to a
member of State Advisory Committee if sought by him.
Regulation 8(3) - new
Commission’s views
164) To have flexibility in revising the specified formats in future looking to
the practical difficulties in furnishing the information and also to get
certain additional information, a new sub-regulation shall be inserted
as follows:
‘(3) The Commission may revise the formats through separate orders,
as warranted necessary from time to time.’
Regulation 9. Information with respect to Levels of Performance
Shri R. G. Gupta
165) The copy of the information/ report should be made available to the
Members of the Advisory Committee.
![Page 35: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/35.jpg)
35
Commission’s views
166) As discussed above, the words ‘every year’ shall be replaced with
‘every half year’. Further, the words and figures ‘Regulation 8(1)’ shall
be read as ‘Regulation 8’.
167) The request of Shri R. G. Gupta for providing copy of the information/
reports to the members of SAC, need not to be incorporated in the
Regulations. However, the licensee shall provide a copy of such
reports to a member of State Advisory Committee if sought by him.
Regulation 10. Exclusions of Events
Regulation 10(i)
Shri R. G. Gupta
168) The mention of wind and rainy conditions should be excluded, at par
with model regulation, because such conditions always prevail to
some extent and that may give opportunity to licensee to escape the
responsibilities.
Commission’s view
169) Looking to the geographical conditions prevailing in the state, it would
be difficult for a licensee to maintain the required standards under
heavy wind and rainy conditions. As such, the suggestion of Shri R. G.
Gupta has not been agreed to.
Regulation 10(iii)
Shri R. G. Gupta
170) The provision should be that outages due to other reasons shall be
approved by the Commission after due notice and hearing, as also
provided in the model regulation.
Commission’s view
171) It would not be practicable for the licensee to seek Commission’s
approvals for the outages after the due notices and hearings.
However, the Commission has decided to revise the sub-Regulation
10(iii) as under:
‘iii. outages due to shut down required to carry out the work by /
for other agency.’
Regulation 15 (new)
Commission’s view
172) The Commission has decided to incorporate necessary provision so as
to enable the Commission to seek the power to relax any provision of
these regulations as and when the circumstances of the case warrant
such an action. The regulation is as under:
![Page 36: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/36.jpg)
36
‘15. Power to Relax
The Commission, may by general or special order, for reasons
to be recorded in writing, and after giving an opportunity of
hearing to the parties likely to be affected, relax any of the
provisions of these Regulations on its own motion or on an
application made before it by an interested person.’
IV. Comments / suggestions on the Schedules to the draft Regulations
Schedule - 1: Licensee’s Guaranteed Standards of Performance
1. Restoration of Supply
1.1 No Current Complaint
Shri Y. K. Bolia & Shri B.L. Jat
1) The period should be counted from the time of registering the
complaint.
Shri R. G. Gupta
2) It is not clear as to with reference to what, the time should be
reckoned, whether time of occurrence of fault recorded by the
licensee or time of reporting by the consumer.
3) Whether the exclusion of period 10 pm to 6 am would mean that no
complaint would be attended during this period.
Jaipur Discom
4) In the first line, the words “Prior to Meter” may be inserted after the
word “MCB”.
5) In sub-para (iii), specify “24 hrs.” In place of “12 hrs.” in Rural Areas. In
rural Areas, localities are scattered and resources are less. It will not be
possible to dispose off the complaints in 12 hrs.
Jodhpur Discom
6) The words “at consumer premises”, may be deleted.
7) As the Discom is responsible to maintain the supply of consumer up to
metering point only and there is no provision to provide fuses/MCBS/LT
Fuses before the metering point.
8) Looking to the scattered rural area of Discom, “12 Hrs.” may be
replaced by “24 hours” under item (iii).
9) Discom is of view that the complaint received during the period 08PM
to 06AM may be handled on next working day if the complaint is
individual nature therefore “10 PM” may be replaced by “08 PM”.
![Page 37: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/37.jpg)
37
Shri G.L. Sharma
10) The wordings “excluding the period from 10 pm to 6 am” appearing
are not appropriate which would mean giving an absolute power to
the licensee for not doing such works in any circumstances. These
words may be replaced as under:-
“However in case of any practical difficulties if such complaints are
not redressed during the period 10 PM to 6 AM, such period would
not be considered for above purpose.”
Commission’s views
11) Following suggestions furnished by the JVVNL and JdVVNL have been
found acceptable:
i. In the first line, the words “prior to Meter” may be inserted after
the word “MCB”.
ii. The words “at consumer premises”, may be deleted.
iii. “12 Hrs.” shall be replaced with “24 hours” under item (iii).
12) Considering the comments / suggestions of Shri R. G. Gupta and Shri
G. L. Sharma, the Commission has decided to elaborate the time of
commencement of specified period and also to revise the existing
words ‘excluding the period from 10 pm to 6 am’.
13) The revised Item 1.1 of Schedule -1 shall now be as under:
‘1.1 No Current Complaint
The licensee shall restore the supply in case of supply related
problem/ fault like blowing of HT/LT fuse/MCB prior to meter or at
distribution transformer or due to loose connections at meter or
service line; within
i. 4 hrs. in Class 1 Cities
ii. 6 hrs. in Urban Areas
iii. 24 hrs. in Rural Areas
from the time of reporting of fault by the consumer. However in
case of any practical difficulty if a complaint is not redressed
during the period 10 PM to 6 AM, it could be redressed later within
the time frame specified above, excluding such period in
reckoning of the said time frame.’
1.2 Overhead line / cable breakdowns
Shri Y. K. Bolia & Shri B.L. Jat
14) The period should be counted from the time of registering the
complaint.
![Page 38: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/38.jpg)
38
Jaipur Discom
15) “8 hrs.” In place of “6 hrs.” In Class 1 Cities. There may be possibility
that Manpower is engaged in another work under item (i).
Jodhpur Discom
16) Discom is of view that the complaint received during the period 08PM
to 06AM may be handled on next working day if the complaint is
individual nature therefore “10 PM” may be replaced by “08 PM”.
Shri G.L. Sharma
17) The wordings “excluding the period from 10 pm to 6 am” appearing
are not appropriate which would mean giving an absolute power to
the licensee for not doing such works in any circumstances. These
words may be replaced as under:-
“However in case of any practical difficulties if such complaints
are not redressed during the period 10 PM to 6 AM, such period
would not be considered for above purpose.”
Shri R. G. Gupta
18) Same clarification is required as in Item 1.1
Commission’s views
19) Considering the comments / suggestions of Shri R. G. Gupta and Shri
G. L. Sharma, the Commission has decided to elaborate the time of
commencement of specified period and also to revise the existing
words ‘excluding the period from 10 pm to 6 am’.
20) No other suggestion has been found acceptable. The revised Item 1.2
of Schedule -1 shall now be as under:
‘1.2 Overhead line/cable breakdowns
The licensee shall restore the supply in case of its overhead
line/cable breakdowns; within
i. 6 hrs. in Class 1 Cities
ii. 12 hrs. in Urban Areas
iii. 24 hrs. in Rural Areas
from occurrence of fault. However in case of any practical
difficulty if a complaint is not redressed during the period 10 PM to
6 AM, it could be redressed later within the time frame specified
above, excluding such period in reckoning of the said time
frame.’
![Page 39: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/39.jpg)
39
1.3 Underground Cable Breakdowns
Shri Y. K. Bolia & Shri B.L. Jat
21) The period should be counted from the time of registering the
complaint.
Jaipur Discom
22) Keeping in view, the complex nature of Underground Cable
Breakdowns and availability of Fault Locator Machines in inadequate
quantity, the time limit for restoration may be considered as under:
i 24 hrs. in Class 1 cities
ii. 36 hrs. In Urban Areas
iii. 72 hrs. in Rural Areas
Jodhpur Discom
23) Discom is of view that the complaint received during the period 08PM
to 06AM may be handled on next working day if the complaint is
individual nature therefore “10 PM” may be replaced by “08 PM”.
Shri G.L. Sharma
24) The wordings “excluding the period from 10 pm to 6 am” appearing
are not appropriate which would mean giving an absolute power to
the licensee for not doing such works in any circumstances. These
words may be replaced as under:-
“However in case of any practical difficulties if such complaints
are not redressed during the period 10 PM to 6 AM, such period
would not be considered for above purpose.”
Shri R. G. Gupta
25) Same clarification is required as in Item 1.1
Commission’s views
26) Considering the comments / suggestions of Shri R. G. Gupta and Shri
G. L. Sharma, the Commission has decided to elaborate the time of
commencement of specified period and also to revise the existing
words ‘excluding the period from 10 pm to 6 am’.
27) No other suggestion has been found acceptable. The revised Item 1.3
of Schedule -1 shall now be as under:
‘1.3 Underground cable breakdowns
The licensee shall restore the supply in case of breakdown of its
underground cable; within
i. 12 hrs. in Class 1 Cities
ii. 24 hrs. in Urban Areas
![Page 40: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/40.jpg)
40
iii. 36 hrs. in Rural Areas
from occurrence of fault. However in case of any practical
difficulty if a complaint is not redressed during the period 10 PM to
6 AM, it could be redressed later within the time frame specified
above, excluding such period in reckoning of the said time
frame.’
1.4 Transformer failure
Shri Y. K. Bolia & Shri B.L. Jat
28) The period should be counted from the time of registering the
complaint.
Shri Narendra Agarwal
29) The entry should be replaced by respectively 16hrs./24hrs./48hrs.
Shri G.L. Sharma
30) The words appearing as “time limits specified as under” may be
deleted otherwise under such item (i), (ii) and (iii) etc word “within”
has to be placed to start with to complete the sense.
Shri R. G. Gupta
31) Since in case of HT consumers normally the transformers belong to
consumers, it is not clear as to how nigam is responsible for
replacement of that transformer.
Jaipur Discom
32) The Discom suggested to make following changes:
i) “48 hrs” In place of “16 hrs” In class 1 city. There may be possibility
that transformer may not be available and it will take time to
arrange the same.
ii) “64 hrs” In place of “36 hrs” In Urban Areas, corresponding to i)
above and resources are less in Urban Area compared to Class-1
cities.
Jodhpur Discom
33) The Discom suggested to make following changes:
i. In (iii), “72 hrs.” should be replaced by “05 days”
ii. After the word “Rural Areas” following sentence may be added:
“From time of verification of failure of transformer”
![Page 41: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/41.jpg)
41
Reply from Jaipur Discom:
34) The time limit specified by the Commission ‘16/36/72 hrs’ should be
looked as the upper ceiling. The Discom may endeavour to restore the
supply through temporary restoration from alternative source,
wherever feasible before the specified time.
35) It is suggested that the Commission may add the below clause under
restoration of supply: ‘Temporary Restoration of supply from
alternative sources, wherever feasible within eight hours’
Commission’s views
36) The words appearing as “time limits specified as under” may be
deleted as suggested by Shri G. L. Sharma.
37) Restoration of supply from alternative sources is not barred wherever
feasible; as such it is not required to be mentioned specifically in the
regulations.
38) As regards comments of Shri R. G. Gupta about the fault on HT
transformers, it is clarified that here the failure of transformer refers to
the Power Transformer belonging to the licensee and through which
HT supply is provided to HT consumers.
39) Considering the comments / suggestions of the stakeholders, the
Commission has decided to specify the time of commencement of
specified period from the time of reporting of fault by the consumer, in
case of LT supply consumers and from occurrence of fault in case of
HT supply consumers.
40) The revised Item 1.4 of Schedule -1 shall now be as under:
‘1.4 Transformer failure
The licensee shall restore the supply in case of failure of its
transformer within:
a) Distribution Transformers
i. 16 hrs. in Class 1 Cities
ii. 36 hrs. in Urban Areas
iii. 72 hrs. in Rural Areas
from the time of reporting of fault by the consumer and
b) Power Transformers
3 working days from occurrence of fault.
![Page 42: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/42.jpg)
42
1.5 Scheduled outages
Shri Y. K. Bolia & Shri B.L. Jat
41) The provision of notifying the scheduled Load Shading Programme
should also be considered.
Shri Pramod Jhanwar
42) The action to be taken for non-compliance of prior notice, should also
be mentioned.
43) For scheduled outage of a long duration, the consumers should also
be allowed relaxation in paying rent.
Shri Narendra Agarwal
44) The long hunger for power may create chance of sudden over
loading on distribution network when supply is restored, which may
cause damage to the equipments. It would be a major drawback &
obstacle in achieving the SOP benchmark. Keeping in view of hard
ship of consumers, system related aspects, achieving SOP bench mark
target, as well shortage of power, the Scheduled cut shall not be
allowed more than 06 hours.
45) The scheduled outages of more than 06 hrs under specific
circumstances shall be undertaken with prior intimation to
SLDC/RDPPC cell, as both entities now a days play more important &
crucial role need close co-ordination with Discom.
Shri Shanti Prasad
46) The regulations do not indicate how such interruptions shall be
notified. Most common method presently in practice (e.g.
maintenance before Diwali) is notification through daily newspapers
of the day. Further, 24 hours advance notification, through
newspapers may not remain in public memory. It is suggested that
words ‘at least 24 hours’ may be deleted and mechanism of
notification may be decided by the Commission in consultation with
Discoms. It is suggested that it may be specified that notification for
interruption during specified supply hours shall be placed on the
notice Board of the concerned subdivision office and call centres of
the area at least 24 hours in advance and shall also be notified to
consumers as under;-
(i) In case of HT consumers, 24 hours in advance through fax at fax
number or e-mail at e-mail id conveyed by the consumer.
(ii) In case of other consumers in urban / semi urban areas, through
two (widely circulated) daily news papers of the day for
![Page 43: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/43.jpg)
43
shutdown between 6.00 A.M. to 24.00 hours of the day and 0.00
hours to 6.00 a.m of next day.
(iii) In case of consumers in rural area , through notice placed on
notice Board of Gram Pachayat Samiti(es).
47) There may be contingencies when shut down longer than 8 hours
may be required (e.g. to effect multiple EHV line crossings). The above
clause may have enabling provision that duration of shutdown
longer than 8 hours permitted by the Commission in specific cases will
not subject to compensation.
Shri G.L. Sharma
48) At the end of item 1.5, a sentence as “The supply should normally be
restored by 6 PM” may be added.
Shri R. G. Gupta
49) It should be clarified whether the load shedding would mean as
authorised by SLDC or any other load shedding which is done by the
sub-divisional officer without any authority.
Jaipur Discom
50) Sometimes, shutdowns have to be taken in emergent cases for which
it shall not be possible to notify 24 hours in advance. Further, it may
take up to 10 hrs. to complete any schedule work. Therefore, the
clause may be considered for replacement as under:
“Interruption in Power supply due to schedule outages, other than the
load-shedding, shall be notified by licensee at least 24 hours in
advance for planned shutdown and same day in emergent cases and
shall not exceed 10 hours in a day.”
Jodhpur Discom
51) The following sentence may be added after the word “day”
“except in extra ordinary circumstance”
Reply from Jaipur Discom
52) The scheduled outages are pre-dominantly due to maintenance
activity and the time limit specified by the Commission ‘not exceed 8
hours in a day’ should be looked as the upper ceiling. The Discom may
endeavour to restore the supply through temporary restoration from
alternative source, wherever feasible in case the maintenance activity
exceeds the specified time limit.
53) Further in view of hardship faced by the consumers, but the system
performance cannot be controlled beyond a limit i.e. system
breakdown; where it could be very difficult to restore the power. The
![Page 44: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/44.jpg)
44
sudden over loading of power system depends on various factors
including season, time of day etc.
54) The points suggested by Shri Shanti Prasad are of importance to us
and mechanism of notification may be included under the ‘Manual
for Handling Consumer Complaints’ of complaints handling
mechanism as per adequate technology, as per its appropriateness
by the approval authority.
Commission’s views
55) The suggestions of Shri Shanti Prasad merit consideration and as
suggested by him an effective mechanism of prior notification of the
load shedding or scheduled outages can be worked out and
incorporated in the Manual for Handling Consumer Complaints, as
also agreed by the Discoms. The queries of Shri Narendra Agarwal
have also been addressed to by the Nigam.
56) As suggested by Shri G. L. Sharma, the sentence ‘The supply should
normally be restored by 6 PM’ shall be added at the end of item 1.5.
57) As regards comments of Shri R. G. Gupta, it is clarified that here the
load shedding refers to any load shedding, required to be conducted
for any valid reason, which need not necessarily be authorised by the
SLDC.
58) The suggestions of Jaipur Discom is accepted and after incorporating
the suggestion of Shri G. L. Sharma, the revised Item 1.5 of Schedule -1
shall now be as under:
“1.5 Scheduled outages
Interruption in power supply due to schedule outages, other than
the load-shedding, shall be notified by licensee at least 24 hours
in advance for planned shutdown and same day in emergent
cases and shall not exceed 10 hours in a day. The supply should
normally be restored by 6 PM”
2. Quality of Supply
2.1 Voltage Variations
Shri Y. K. Bolia & Shri B.L. Jat
59) To avoid unnecessary disputes, it is necessary to clarify the term ‘Local
problem’
Shri D. P. Chirania & Shri S.C. Kothari
60) Please ensure that the limit is as per CEA’s Regulation
61) The condition ‘Subject to voltage availability at Transmission-
Distribution interface, within the specified limits’ is a vague condition
![Page 45: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/45.jpg)
45
and the distribution licensee will always evade its responsibility in name
of non availability of proper voltage at transmission-Distribution
interface. Provision of OLTC exists at transmission GSS and the
distribution licensee have to coordinate with transmission licensee for
maintaining of proper voltage at transmission-distribution interface.
62) The licensee shall resolve problem; within
i. 2 working days in case of local problem - How the
Commission is specifying a local problem?
ii. 1 month in case of transformer repair/ replacement - Too
much, it should not be more than a week.
iii. 4 months in case of substation augmentation
Why there should be a voltage problem in name of substation
augmentation? A Licensee has to supply electricity within
specified voltage limits as specified under CEA Regulations. The
Commission cannot specify any relaxation to these and therefore
review its proposal in consideration of the said regulations.
iv. 6 months in case of new substation - Comments as above
Shri Shanti Prasad
63) Voltage variation of Transmission system is +/- 10% (vide reg.6.6.4.2 of
REGC -2008). With this specified voltage variation for transmission,
voltage variation as specified at clause 2.1 of schedule -1, will not be
feasible to be met and besides this it will be too stringent. Negative
side voltage variation of LT supply (-6%), better than that on HT supply
(-9%), is inconceivable. As performance parameters, subject to
penalty, are introduced first time, it may not be specified too stringent
and specified considering present ground reality with trajectory of
improvement.
Shri G.L. Sharma
64) The words “subject to voltage availability at transmission-distribution
interface, within the specified limits, “may be deleted as to keep
proper voltages at such points is the responsibility of the concerned
utilities.
Shri R. G. Gupta
65) The time line for resolving the problem is highly consumer unfriendly. It
is suggested that in case it is found that the problem shall be removed
only after transformer repair / replacement / augmentation / erection
of new substation, then an intimation of the same should be sent to
the complainant within 7 days of the complaint and indicating that
![Page 46: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/46.jpg)
46
the time by which the voltage problem would be over. The time
should not be more than one month.
Reply from Jaipur Discom:
66) The limit specified is as per the regulations and is also followed by other
State Electricity Regulatory Commissions including Delhi.
67) Prayer: It is suggested to include the voltage variation in case of Extra
High Voltage: +10% and -12.5%
68) The spirit of SOP regulations is to specify parameters and warning
signal on various parameters for any noted deviation as specified. The
actual impact of SOP may be observed after its implementation.
69) The time limit specified by the Hon’ble Commission should be looked
as the upper ceiling. Being a public sector entity, multiple approvals
are required to be taken prior to the execution of the schemes
(especially in case of transformer repair/replacement, substation
augmentation and new substation and simultaneously the finalization
of cost effective means of executing the scheme. The process takes
lots of time and input and therefore the time specified by the Hon’ble
Commission should not be revised considering the present intricacies
of the system.
70) However, the discom may endeavor to restore the supply through
temporary restoration from alternative source or mobile transformer,
wherever feasible before the specified time.
71) It is suggested that the Commission may add the below clause under
restoration of supply:
‘Temporary Restoration of supply from alternative sources, wherever
feasible within eight hours’ in case the time estimated to resolve the
problem is higher than the specified limit under SOP.
Commission’s views
72) The words ‘in case of local problem’ shall be replaced with ‘in
general’.
73) The Discoms are on receiving side of the Transmission system,
therefore, they should not be penalised for the variation in the
voltage they are getting from RVPN system.
74) The CEA has specified the variation band for 33 kV and above only
therefore the variation band specified in the Indian Electricity Rules,
1956 has been adopted in the Regulations, which is also as suggested
by the Forum of Regulators in the model SOP Regulations and
![Page 47: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/47.jpg)
47
adopted by other SERCs like APERC, DERC, MERC, HERC etc. As such
any need for giving a second look by the Commission on these
standards is not warranted.
75) The voltage variation for EHV system is beyond the jurisdiction of the
Discoms, as such, the same has not been incorporated in the
Schedule.
76) Restoration of supply from alternative sources is not barred wherever
feasible; as such it is not required to be mentioned specifically in the
regulations; as proposed by JVVNL.
77) However, the draft Schedule has been reworded as under for better
clarity:
‘2.1 Voltage Variations
The licensee shall maintain voltages at the point of
commencement of the supply to a consumer within the limits as
under subject to voltage availability within the specified limits at
incoming point of the distribution system:
i. +6% and -6% in case of LT supply
ii. +6% and -9% in case of HT supply
and in case of variation, the problem shall be resolved within the
time frame as given below:
i. 2 working days in general
ii. 1 month in case of transformer repair/ replacement
iii. 4 months in case of substation augmentation
iv. 6 months in case of new substation’
from the time of reporting by the consumer.
3. Meter Complaints
Shri Y. K. Bolia & Shri B.L. Jat
78) The Discom should purchase meters of specified standards and also
keep 25% of consumer meters reserved in the store for replacement of
defective meters immediately. Presently meters are not available for
replacement. In Ajmer Discom 3.78 lakh single phase and 1 lakh three
phase meters are lying defective whereas only 10000 single phase and
33000 three phase meters are available in the stores.
Shri Narendra Agarwal
79) Keeping in view of Meters related scenario & rising consumer
complaints about cease to function of meters, the provisions for
Licensee shall be laid down that % age of defective meter’s to the
total Nos. in service of meter not greater than 5 %.
![Page 48: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/48.jpg)
48
Reply from Jaipur Discom:
80) The Commission has already specified the desired level of minimum
standards (95% of correct meters to the total numbers of meters in
service) in the SOP parameters under system reliability mentioned
under Minimum overall standards of performance to be achieved by
a licensee.
3.1 Testing of Meter
Shri D. P. Chirania & Shri S.C. Kothari
81) Too high a limit, especially when it is found that meter is not
functioning properly. Correct meter recording is essence of EA 2003
and it cannot be diluted by specifying such a high limit.
Shri G.L. Sharma
82) The words “suspects” appearing in first line as item 3.1 may be
replaced as “reports”.
83) During the hearing he mentioned that the Discoms’ bye-passing the
meter, in case of its burning is not appropriate.
Shri R. G. Gupta
84) It should be clarified that meter shall be replaced within 2 months of
the date of notice by the consumers, including the time taken by the
licensee to verify the correctness of meter.
Reply from Jaipur Discom:
85) The time specified for replacement is the upper limit. The problems
related to meters are directly linked with the inventory and stores.
There were also issues related to non-availability of required meter to
be made available by the concerned manufacturer. However the
Discom may endeavour to restore the supply through temporary
restoration from alternative source wherever feasible before the
specified time.
86) It is suggested to the Commission may add the below clause under
restoration of supply:
‘Temporary Restoration of supply by bypassing the burnt/damaged/stopped
meter within 24 hours in case of no current complaint’ in urban area and 48
hours in rural area.
Commission’s views
87) The suggestion of Shri G. L. Sharma is acceptable and accordingly the
word “suspects” appearing in first line as item 3.1 shall be replaced
with the word “reports”.
![Page 49: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/49.jpg)
49
88) The suggestion of Shri R. G. Gupta is acceptable and accordingly the
words ‘of the date of notice by the consumer’ be added at the end.
89) The suggestion of Jaipur Discom is not acceptable as the Commission
cannot allow the Discoms to restore the supply without meter. The
other suggestions are also not found acceptable.
3.2 Replacement of stopped /damaged /burnt Meter
Shri D.P.Chirania
90) The limit is too high. If a burnt meter will not be replaced immediately,
how the consumer will get electricity supply? Restoration of electricity
supply must be a paramount requirement and the Licensee must
restore the supply within 6 hours in case of burnt meter.
91) For proviso: It should be the same as that for no current case
Sh. G.L. Sharma, Jaipur
92) In the first line of item 3.2 after the word “burnt meter” and before the
word “noticed”, the words “is reported/”may be added. Further in the
third line of this item after the word “months” and before the word “of
such detection” the words “from the date of” may be added.
93) Further the second sentence/para of this item has been started with
the words “provided that” it would be better that these words are
deleted so as to make full meaning of this para.
Shri R. G. Gupta
94) Where incidence is attributable to the licensee, the meter should be
replaced within one month without charging any price. However,
where incidence is attributable to the consumer, the licensee should
send notice to the consumer indicating the reason of considering the
incidence attributable to the consumer. The meter in that case should
be replaced within 15 days of the deposit of the price demanded.
Jaipur Discom
95) The 2nd paragraph may be replaced as under:
“provided that in case of no current complaint on account of stopped /
damaged / burnt meter, the licensee shall replace the meter within 48 hrs of
reporting by the consumer or detection by the licensee, as the case may be,
unless it is established that the meter has been tempered or damage in any
way including excess load by the consumer, in which case, the licensee shall
replace the meter within 48 hours after depositing the Amount of Security of
Meter towards cost of Meter by the consumer”.
![Page 50: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/50.jpg)
50
Jodhpur Discom
96) As the rural areas of Jodhpur Discom is widely scattered, after the
word “48 hours”, following sentence may be added:
“48 hours in City & Urban Area” and 04 days in rural areas”.
Shri S.C. Kothari
97) The limit is too high. If a burnt meter will not be replaced immediately,
how the consumer will get electricity supply? Restoration of electricity
supply must be a paramount requirement and the Licensee must
restore the supply within 6 hours in case of burnt meter. Replacement
of stopped Meter beyond prescribed time limit be given credit as per
rules approved by RERC without waiting for its representation in
forthcoming bill & be got mentioned in writing in SOP booklet.
Reply from Jaipur Discom
98) The time specified for replacement is the upper limit;
99) The points as specified may be included under the ‘Manual for
Handling Consumer Complaints’ of complaints handling mechanism
as per adequate technology, as per its appropriateness by the
approval authority.
100) It is suggested that the Commission should understand the
practicalities involved in addressing such consumer complaints where
the time specified failed in the following cases and take a practical
view while specifying the time limit and compensation:
Absence of adequate resources including manpower,
equipments, wire, meter, etc.
Absence of funds to resolve the complaints
Absence of required documentation to address the consumer
complaints
Absence of approvals of final authority
Most of the times the work entirely depends on actual site
situation including right of way, moreover at times various
agencies like municipality, UIT etc, are also involved;
Proper protection devices are not installed by the consumer for
electrical installation or there are cases where tempering is
involved;
Jurisdiction of consumer and licensee;
Rural and Urban areas are widely scattered.
![Page 51: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/51.jpg)
51
Commission’s views
101) Considering the suggestion of Shri G. L. Sharma, the words ‘burnt
meter noticed by the consumer or by the licensee’ shall be replaced
with the words ‘burnt meter reported by the consumer or noticed by
the licensee’.
102) The suggestion from JVVNL as also from Shri R. G. Gupta, Is
acceptable and accordingly the proviso appearing in the draft shall
now be replaced as under:
“Provided that in case of no current complaint on account of
stopped / damaged / burnt meter, the licensee shall replace the
meter within 48 hrs of reporting by the consumer or detection by
the licensee, as the case may be, unless it is established that the
meter has been tempered or damage in any way including
excess load by the consumer, in which case, the licensee shall
replace the meter within 48 hours after depositing the amount of
security of meter towards cost of meter by the consumer”.
4. Shifting of Meters/Service Lines
4.2 Shifting of Meter
Shri G.L. Sharma
103) The words “in case of L T.” and “in case of H T” have been mentioned.
Both these words do not give full meaning. Therefore it would be
better if these words are mentioned as “in case of L T consumers” and
“in case of H.T. consumers”.
Jaipur Discom
104) The Discom suggested that in (ii), “30 working days” be specified In
place of “15 working days” In case of HT, as it involves multi wing
activates.
Commission’s views
105) The words “in case of L T.” and “in case of H T” shall be replaced with
“in case of L T consumers” and “in case of HT consumers” respectively,
as suggested by Shri G. L. Sharma.
106) The suggestions from the JVVNL have not been found acceptable.
4.3 Shifting of Service Line
Jaipur Discom
107) ii) “2 months” In place of “1 month” In case of HT, as shifting of HT line
may affect large number of consumers as such it requires to choose
appropriate time for shifting,
![Page 52: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/52.jpg)
52
Jodhpur Discom
108) Following sentence may be added after the word “Within”:
“Subject to condition that it will not affect any other
consumer/persons and right of way shall be provided by the
consumer. This provision shall not be applicable for agriculture
consumers”.
Ajmer Discom
109) The Discom suggested as under:
(i) Instead of 15 working days it should be one month for LT.
(ii) Instead of one month it should be three months for HT.
110) It has been proposed as the work entirely depend on actual site
situation including Right of Way. Moreover at times various agencies
like Municipality, UIT etc. are also involved.
Shri G.L. Sharma
111) The words “in case of L T.” and “in case of H T” has been mentioned.
both these words do not give full meaning. Therefore it would be
better if these words are mentioned as “in case of L T consumers” and
“in case of H.T. consumers”.
Shri Y. K. Bolia & Shri B.L. Jat
112) Necessary provision should be incorporated that In case of damage
of service line the shifting should be immediate.
Shri S.C. Kothari
113) Shri Kothari’s comments are meter related grievances, which are not
within purview of these draft Regulations.
Commission’s views
114) The words “in case of L T.” and “in case of H T” shall be replaced with
“in case of L T consumers” and “in case of HT consumers” respectively,
as suggested by Shri G. L. Sharma.
115) The other suggestions from the stakeholders have not been found
acceptable.
5. Release of New Connections or additional power
Shri D. P. Chirania
116) Reproduce the Supply Code norms here too. These Regulations should
be self-contained one.
![Page 53: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/53.jpg)
53
Shri S.C. Kothari
117) Shri Kothari’s has furnished comments related to Supply Code
Regulations / TCS.
Commission’s views
118) The suggestion of Shri Chirania to reproduce the Supply Code norms
here does not seem required.
119) Shri Kothari’s has furnished comments related to Supply Code
Regulations / TCS, which are not within the purview of these draft
Regulations.
120) However, for more clarity, a new sub-para shall be added at the end,
as under:
‘5.2 In case of any delay in release of new connection or
additional power, the consumer should first approach the
concerned sub-divisional officer who shall appraise him the
factual status in the matter and expected date / period of
completion of work. In case of un-satisfactory response, the
consumer may get the complaint lodged in Call centre.’
6. Transfer of ownership and change of category
Shri S.C. Kothari
121) The licensee should make available in r/o all such activates as
mentioned in SOP- indicating a clear check list of requisite documents
normally required to be furnished, in absence of the same, the field
officers are demanding unnecessary documents.
Reply from Jaipur Discom
122) The checklist of documents required to address such issues may be
suitably notified in the Manual.
Commission’s views
123) These issues can be addressed in the proposed Manual for Handling
Consumer Complaints.
7. Consumer bill complaint
Shri Y. K. Bolia & Shri B.L. Jat
124) The billing authority should be empowered to revise the wrong bills.
Shri D.P.Chirania & Shri S.C. Kothari
125) It is not clear where the billing problem is to be lodged, whether at the
call centres or otherwise.
![Page 54: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/54.jpg)
54
126) Generally, the billing complaints are attended by the sub-division
concerned, and in most of the cases, consumers visit the concerned
office. The existing regulations covering the redressal mechanism in its
clause no. 11 and these provisions are better than the proposed one.
127) The existing provisions are also incorporating mechanism of periodical
inspection/testing of meters under its clause no. 9 which is missing in
the present provisions. The reasons of deleting the same need to be
specified or these may be retained.
Shri Shanti Prasad
128) Billing complaints may also include non-payment of interest charges
as per section 47(4) of the Electricity Act 2003 (of the Electricity
charges) on security deposits of consumer by the dates specified by
the Commission.
Reply from Jaipur Discom:
129) The billing related problems shall be transferred to the concerned
officer within the specified time and will be dealt by the concerned
officer. The call centres shall act as a medium for attending such
complaints and passing to the appropriate authority to resolve such
complaints.
Commission’s views
130) Considering the suggestion of S/Shri Y. K. Bolia, Shri B.L. Jat and D. P.
Chirania, the schedule has been revised as under, for more clarity:
‘7. Consumer bill complaint
7.1 In case of any billing problem, the consumer should first
approach the concerned Sub-divisional officer or Billing officer
who shall resolve the problem. However, in case of un-satisfactory
response, the consumer may get his complaint lodged in Call
centre. The licensee shall resolve the billing problem within
i. 3 working days, in case no information is required to be
collected
ii. 7 working days, in case some information is required to be
collected by the billing authority.
In case the complaint is genuine, the licensee shall extend the
due date for payment of bill so as to allow at least 7 working days
for making payment by the consumer.’
131) As regards periodical inspection / testing of meters, it is stated that the
licensee is required to follow the mechanism of periodical inspection /
testing of meter as incorporated in the RERC (Metering) Regulations,
![Page 55: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/55.jpg)
55
2007, failing which action could be taken against the licensee for
violation of the Commission’s regulations. Therefore separate provision
in these SOP regulation is not required.
132) The suggestion of Shri Bolia and Shri Jat, about the Public Service
Provider Guarantee Act, has already been addressed herein above.
8. Disconnection of supply
8.1
Jodhpur Discom
133) After the word “within” following sentence may added:
“After getting disconnection fees, as prescribed by the Commission”
134) Presently, no such fee has been prescribed for disconnection of supply
on the request of consumer. It is requested the Commission to
prescribe the disconnection fee, which is in consonance with Section
56(1) of I.A.-03.
Shri S.C. Kothari
135) The D.C. of electric supply on non payment / on demand be done
timely as per the requirements.
Commission’s views
136) The Commission has agreed to add after the words “dues from the
consumer” the words “along with disconnection fee, if any, prescribed
by the Commission”
8.2
Shri G.L. Sharma
137) In item 8.2 the words appearing as “any money payable” may be
replaced with the words “the amount refundable” further the words
appearing as “payable to the licensee” may also be deleted.
Shri R. G. Gupta
138) There is no need to wait for the clearance of dues. The available
security should be enough to adjust the dues.
Commission’s views
139) The suggestion from the stakeholder has not been found acceptable.
However, for better expression, the words ‘any money’ shall be
replaced with the words ‘all the money’.
![Page 56: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/56.jpg)
56
10. System reliability to avoid heavy fluctuations or short circuiting of lines
Shri Y. K. Bolia & Shri B.L. Jat
140) They have suggested the measures to be taken for avoiding the
heavy fluctuations and short circuiting of lines which are not within
purview of these draft Regulations.
Shri D. P. Chirania and Shri S.C. Kothari
141) Shri Chirania and Shri Kothari suggested specifying adherence of CEA
Regulations by the Licensee and specifying a mechanism to monitor
their compliance.
Commission’s views
142) The CEA Regulations are required to be followed by the licensees and
need not be specified in these SoP regulations separately. Therefore,
the Commission does not require any change in the draft provision.
Schedule-2: Compensation Payable by the Licensee
Shri Rakesh Kumar Parmar
143) The minimum compensation should be Rs 500 along with a surcharge
of Rs 50 per day for the delay after the permissible time period.
Shri Pramod Jhanwar
144) There should be time limit for the payment of compensation.
Shri S.C. Kothari
145) These should be time linked; otherwise the distribution Licensee will not
be serious in attending the complaint once the specified initial time is
crossed.
146) The proposed compensation should be for each day of delay
otherwise it will have no meaning and would result in harassment of
the consumer as he/she will have to incur much more expenditure
and time in lodging the complaint, appearing before the Forum,
making appeal etc.
Shri Y. K. Bolia & Shri B.L. Jat
147) Before specifying the compensation, the availability of proper
infrastructure and its operation and maintenance should be ensured
along with a committee to be appointed with experienced persons to
monitor the activities.
![Page 57: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/57.jpg)
57
Shri Narendra Agarwal
148) The amount has been fixed irrespective of actual hardship borne by
the consumer. Actual compensation may be prescribed by
considering following factors
(a) hardship beared
(b) average monthly bill of aggrieved consumer
Shri Rajendra Kumar Mehta
149) For purpose of compensation, no distinction has been made with
regard to urban / non agriculture rural and agriculture consumers. It is
not very important what compensation one gets in urban / non
agriculture rural, because it is a matter of their inconvenience only.
Beside compensation for their damage have been taken care of in
schedule -2 S.no.10. 18, 19, 20.On the contrary for damage/ crop loss
of agriculture consumer has not been addressed in proposed draft
Regulations. Shri Mehta narrated the facts and submitted the
suggestions, as under:
Facts:
i. In urban area more than 200 consumers are affected if any
transformer is failed / burnt. And the local staff of Licensee is
under pressure to repair the failed / burnt transformer as soon
as possible. And in most cases it takes less than 16 hrs. to
replace the transformer. Because after in proposed draft
Regulation delay in repairing any Transformer will cost the
licensee at least Rs. 20000 (200 consumers x@ 100) if all the
consumers apply for compensation. Now because of this the
repair of transformer will be made in the stipulated time.
ii. In rural non agriculture more than 25 consumers are affected if
any transformer is failed / brunt. And the local staff of Licensee
is not so insensitive in case of rural non agriculture category
and it take not more than the stipulated period of 25 hrs.
Because after proposed draft Regulations delay in repairing of
transformer will cost the Licensee at least Rs. 2500 (25
consumers x@ 100), if all the consumers apply for
compensation.
iii. For urban / non agriculture rural, provision for compensation for
damage to their mix, fan, washing machine, friz, TV, Computer
etc have been made in the proposed draft Regulations. But no
provision for damage (crop loss) of agriculture consumer has
![Page 58: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/58.jpg)
58
been made. Person who gives “roti “to whole nation has been
blatantly forgotten.
iv But in agriculture category specially after FRP work only 1 or 2
consumers are affected if any transformer is failed / burnt. This
is not a matter of inconvenience for him, it is a matter of
national importance because it causes “crop loss – a national
loss”. From here the plight of the poor consumer starts. When
he goes to Grid station only to be told to report this to JEN. Now
where to find the Jen. Suppose one is lucky to find the JEN,
who will never act as per JPR 5-596, and ask the consumer to
take the failed / burnt transformer to store. He does this also by
spending lot of money otherwise he has to listen that DP is not
available, indent has been sent to higher authority and shall be
given on its receipt; in case of any complaint, go to XEN.
v. This situation is most likely to be worsened, because after this
proposed draft Regulations any days’ delay in repairing
transformer will cost the Licensee a meagre amount of RS. 100 /
200 (1 or 2 consumers x@ 100), if the poor and already
harassed consumer dares to apply for compensation and
apply for this paltry money, he will have to spend his whole
day+ Rs. 100 for going to the AEN office. there cannot be any
agonizing situation than this. Because it will add more
corruption. Already everything is “fixed” and if need be to save
whole year’s ROTI, he can get transformer “out of turn”.
Suggestions:
i. During month of ‘April/May/June/July/ August and Sept. for full
six months agriculture consumer can accept delay without any
complaint.
ii. But in months of October delay of 3+3 days, he can accept.
But more delay will cause delay in pre-irrigation resulting
delayed sowing of main crop like wheat and sarson
compensation of Rs. 500 per day for 5 days after 3+3 days and
Rs. 1000 per day thereafter should be provided in proposed
draft Regulation.
iii. But during months of November to February, delay after
stipulated period of 3 days causes loss to his already sown crop
and the compensation of Rs. 1000 per day for 3 days after 3+3
days and Rs. 2000 per day after 3+ 3+3 days should provided in
proposed draft Regulation. His loss is loss for the whole nation.
![Page 59: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/59.jpg)
59
Shri Shanti Prasad
150) The standard of parameters which will be subject to compensation
and specified at schedule -2 can be broadly classified into (i) those for
which either a single consumer or only a few consumers are normally
involved and (ii) those for which large number of consumers are likely
to be involved (viz. 2, 3, 4, 5 and 6 and also billing complaints as
suggested above).Complaints under later categories are required to
be dealt by separate mechanism. For example, Failure to notify in
advance the interruptions in supply as per sr.no. 1.5 (due to
maintenance outage) may involve thousands of consumers. Same
may be the case with voltage variations. It may not be feasible and
also time consuming to deal with such individual complaints and there
may be high financial liability of discoms. It will be appropriate that in
such cases (where complaints of single event exceeds specified
number (say 10-12), there may be a lump sum penalty (of say Rs.
12,500 to 25,000/-) on discom payable to a pool and out of the sum
available in the pool, for each item, compensation is paid equally to
complainants subject to ceiling per consumer as specified by the
Commission. For complaints under these category, there be a shorter
time limit of say 7 days.
Shri D. P. Chirania
151) During the hearing Shri Chirania mentioned that the time limit for many
activities proposed by the Commission, is two to three days but he
wondered that even if the particular tasks is not executed by the
Discom for as long as three months, why the penalty should be same.
Shri G.L. Sharma
152) In respect of schedule -2 it is stated that the amount of compensation
may be indicated in slabs relating to some fixed days viz. for so much
delay of days, a certain amount would be payable and beyond that
such and such amount would be paid which should be on increase
side. However after third slab a maximum limit could be prescribed.
Otherwise the licensee will become careless for a longer time when
they knew that even for such a longer time nothing extra is to be paid
to the consumer.
153) Further, in the note under this schedule it has been stated that
compensation for damages on account of heavy fluctuations in
supply or short circuiting of lines shall be payable only when event
affects more than five consumers on a feeder. This is injustice. There
![Page 60: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/60.jpg)
60
should be no bar like this specifically when it is to be paid only after
physical verification.
Shri R. G. Gupta
154) Shri Gupta mentioned that various elements of compensation,
proposed in the document should indicate only the minimum
amount and the actual amount (more than the minimum), if so
claimed by the applicant, should be determined by the Commission
only.
155) Further, in all the cases, only a flat rate of compensation for non-
performance, within the scheduled time period, has been provided.
But this should be in slabs.
Jodhpur Discom
156) Discom is not agreed with the amount of compensation to the
consumer, as indicated in Schedule-2 of draft regulations. Discom is of
view that compensation is to be allowed to the consumers on the
deficiencies of activities as prescribed in Schedule-2. But the amount
of compensation should be allowed on pro-rata basis to the
applicable fixed charges for particular category of consumers only for
the period when the services could not be provided.
Ajmer Discom
157) Compensation for damages for protected system on account of
heavy fluctuations in supply or short circuiting of lines.
158) Justification: Discom may not be made liable for compensation in
case consumer has not installed proper protection system for its
electrical installation, therefore ‘for protected system’ should be
inserted as above.
Reply from Jaipur Discom:
159) The term compensation payable by the licensee should not be looked
as the ‘compensation of opportunity loss’, otherwise it would be
difficult to quantify the opportunity and therefore the compensation
amount. It is a deterrent and should be treated as a signal of deviation
from performance standards.
160) It is suggested to the Commission to reword the ‘compensation’ as
symbolic ‘penalty’; as the whole spirit of SOP regulations would
foregone, if it is not treated as deterrent.
![Page 61: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/61.jpg)
61
Commission’s views
161) The Commission has gone through various suggestions as furnished by
various stakeholders. In fact the Commission is specifying for the first
time, the compensation to be paid by the Discom on not-achieving of
certain standards in supply of electricity to the consumers. It is
mentioned that the SOP provisions can be made more stringent after
review by the Commission, keeping in view the improvement in the
infrastructure by the Discoms with the passage of time.
162) As regards the suggestion of Shri Rajendra Kumar Mehta, the
Commission is of the view that it would not be desirable to incorporate
separate sector specific compensation amount in these SOP
Regulations.
163) As regards the suggestion of Shri Shanti Prasad, the Commission is of
the view that the amount of compensation payable to an individual
consumer cannot be reduced on the ground of involvement of large
number of consumers.
164) However, considering suggestions of stakeholders brought out above
relating to delay in payment once the specified period is over, the
Commission has decided to add following new foot-note:
‘ii. The above mentioned amount of compensation shall remain
the same if time taken by licensee is up to double the specified
period; thereafter the amount of compensation shall be double
the amount specified above.’
165) As regards time limit for making payment of compensation, the same
has already been specified under Regulation 6 of these SOP
Regulations.
166) The suggestions of Shri Bolia relating to improvement of infrastructure
and the suggestion of Shri R. G. Gupta relating to payment
mechanism of compensation; have already been addressed to in the
foregoing paras.
1. Restoration of supply
Shri D. P. Chirania & Shri S.C. Kothari
167) These should be time linked; otherwise the distribution Licensee will not
be serious in attending the complaint once the specified initial time is
crossed. The proposed compensation should be for each day of delay
otherwise it has no meaning but result in harassment to consumer as
he/she has to incur much more expenditure and time in lodging the
complaint, appearing before the Forum, making appeal etc. There
must be sufficient detrimental action on the licensee. No eye-wash
![Page 62: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/62.jpg)
62
please. The Commission has to protect the consumer’s interest, not to
throw salt on its wounds.
Commission’s views
168) The suggestion has already been addressed in foregoing paras.
169) Looking to the fact that EHV system is beyond the purview of the
distribution licensees, the provision of paying compensation to EHT
consumers for no current complaints and overhead / underground
line /cable breakdowns in case of EHV system, has been deleted
under sub-clause 1.1, 1.2 and 1.3 of the schedule.
2. Quality of Supply
Shri D. P. Chirania & Shri S.C. Kothari
170) The Commission has not specified the Quality of Supply parameters in
the proposed Regulations though the same is available in the existing
regulations.
171) As far as the compensation amount is concerned it must be time
linked, as discussed in case of no-current, as above.
Commission’s views
172) The parameter relating to Quality of Supply appearing under the draft
Schedule has been deleted as discussed above.
173) With the deletion of Item number 2 as above, the subsequent Item
numbers of the Schedule and formats have been revised accordingly.
3. Meter Complaints
Shri D.P.Chirania & Shri S.C. Kothari
174) For replacement of stopped /defective /burnt Meter, instead of
making reference of other code, please specify the amount.
175) For no-current complaint it should be time based
Commission’s views
176) The matter relating to reproducing of Supply code provisions, have
already been dealt in foregoing paras.
177) The Commission has also decided that the words ‘(for delay per
month or part thereof)’ may be deleted in view of new foot-note
mentioned above.
4. Shifting of Meter / Service line
Shri D.P.Chirania & Shri S.C. Kothari
178) It should be time based
![Page 63: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/63.jpg)
63
Commission’s views
179) The matter relating to time limit has already been dealt in foregoing
paras.
5. Release of new connection/additional power
Shri D.P.Chirania & Shri S.C. Kothari
180) It should be time based
Commission’s views
181) The matter relating to time limit has already been dealt in foregoing
paras.
6. Transfer of ownership or change of category
Shri D.P.Chirania & Shri S.C. Kothari
182) It should be time based
Commission’s views
183) The matter relating to time limit has already been dealt in foregoing
paras.
7. Consumer bill complaint
Shri D.P.Chirania & Shri S.C. Kothari
184) It should be time based
Commission’s views
185) The matter relating to time limit has already been dealt in foregoing
paras.
9. Restoration of a disconnected consumer
Shri D.P.Chirania & Shri S.C. Kothari
186) It should be time based
Commission’s views
187) The matter relating to time limit has already been dealt in foregoing
paras.
10. Compensation for damages on account of heavy fluctuations in supply or
short circuiting of lines
Shri D. P. Chirania & Shri S.C. Kothari
188) How the Forum will decide whether it was a case of heavy fluctuation
or not? When there is damage to house hold equipments, it is a sure
case of high voltage than the nominal voltage of the supply to which
the consumer belongs. These events should be clearly defined.
![Page 64: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/64.jpg)
64
Commission’s views
189) The matter has already been dealt in foot-note and would further be
elaborated in the Manual. As such, no change in the existing provision
is required.
Schedule-3 Overall Standards of Performance for a Licensee:
Shri D.P.Chirania
190) All these indices in the schedule should be sub-division level based
and based on sub-division’s performance, the overall performance of
the Licensee should be adjudged.
191) There should be a provision of scaling fine and that fine should not be
recovered from tariff.
192) There should be a provision of prudent check at the level of the State
Commission or some empowered committee constituted by the
Commission otherwise there will be ample chance of manipulation
and thus there will be no material improvement in the performance of
the Licensee.
Commission’s views
193) It would not be practicable for the Commission to monitor the
standards of performance at sub-divisional level.
194) The matter relating to allow in ARR, the compensation amount paid by
the Discoms to the consumers, has already been dealt herein above,
at appropriate place.
195) As regards checking at the level of the State Commission or some
empowered committee constituted by the Commission has noted the
suggestion.
3.1 Consumer Satisfaction
Shri Y. K. Bolia & Shri B.L. Jat
196) Consumer satisfaction should be got examined from an outer agency
consisting of experienced persons. The Commission should get
feedback from such agency.
Commission’s views
197) As regards checking by an outer agency, the Commission would take
action at appropriate time.
![Page 65: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/65.jpg)
65
3.2 Replacement of incorrect meters
Shri Y. K. Bolia & Shri B.L. Jat
198) The Discom should purchase meters of specified standards and also
keep 25% of consumer meters reserved in the store out of which 10%
be kept duly tested for immediate use. Further distribution at
corporate level, Circle level and District level may be 5&2, 10&4 and
40&4 respectively.
Shri G.L. Sharma and Shri D. P. Chirania
199) The words “try to” may be deleted. Keeping such words would defeat
the very purpose of prescribing the standards of Performance. Similarly
also the words “try to” appearing in first line in item 3.3 under this
schedule should also be deleted.
Commission’s views
200) The Commission feels that it is for the Discom to manage their affairs so
as to meet the required standards.
201) The Commission does not find the suggestion of Shri G. L. Sharma and
Shri D. P. Chirania, as acceptable.
3.3 Replacement of Transformers
Shri Y. K. Bolia & Shri B.L. Jat
202) The Discom should purchase sufficient numbers of transformers and
also keep some transformers reserved in the store for replacement of
defective transformers immediately. Presently transformers are not
available for replacement. In Ajmer Discom 7000 single phase and
16000 three phase transformers are lying defective whereas only 1000
transformers are available in the stores.
Shri D. P. Chirania
203) The use of word “try” is totally diluting the things. It must be a very
specific with certain punishment measures.
204) The term ‘working condition’of the transformer is also a vague term.
Most of the transformers are not checked for years, oil leaks, dust
accumulation on the insulators are very common. The Commission
should specify maximum damage rate for the power and distribution
transformers, capacity wise.
Commission’s views
205) In reference to the suggestion of Shri Bolia and Shri Jat, it is stated that
it is for the Discom to manage their affairs so as to meet the required
standards.
![Page 66: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/66.jpg)
66
206) In reference to the suggestion of Shri Chirania, it is stated that the
Commission has already specified the minimum standards to be
achieved in the matter of transformer failure, separately for Distribution
and Power Transformers.
3.4 Reliability Indices
Shri Y. K. Bolia & Shri B.L. Jat
207) The Discoms are not having proper infrastructures for collecting the
required data. The statistical structure of the Discoms is detoriating day
by day. Therefore it is necessary to rebuild such structure for which
services of retired persons of power sector may be obtained.
208) During the hearing Shri Bolia complained that the format of reliability
indices was too complicated to be filled- in by the illiterate/semi-
literate staff.
Shri G.L. Sharma
209) It is submitted that the reliability indices should have been specified
with these standards to complete matter instead of keeping it for
future.
Shri D. P. Chirania
210) During the hearing Shri Chirania argued that the SoP were in place in
2003, and these stipulated that the Commission shall specify the
benchmarks after one year. He said that the indices mentioned were
impossible to apprehend or compile and impressed that non realistic
data should be removed.
Shri Narendra Agarwal
211) It is observed that interruptions within 05 minutes occur more
predominantly on 11KV/LT network, the major causes of which is
frequent tripping on faults, heavy loading, frequent shut downs taken
by staff to facilitate small works/other similar type reasons. It shall not
be prudent to ignore such type practical situation of field area in
isolation
212) Keeping in view of above facts of field, it will be prejudice with “Judge
the reliability” of system, the following amendment shall be laid down
in formula of calculation to indices SAIDI, SAIFI & MAIFI.
A1 = Total number’s of sustained interruption each longer than 05
minutes.
C1 = Total numbers of momentary interruptions each less than 05
minutes.
![Page 67: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/67.jpg)
67
213) To serve better & achieving SoP benchmark, the necessary provision
shall be laid down in SoP regulation
214) Total numbers of scheduled outages for 11 KV feeder shall not be
exceeds more than 12/18 in a year.
Shri R.G.Gupta
215) The Commission shall appreciate that SAIFI, SAIDI and MAIFI were not
mentioned by the Commission even in the earlier performance of
regulation. It is high time that these three parameters which is
important yardstick for ensuring supply reliability should now be
specified in these regulations, if necessary, some more time can be
taken. The regulation which are now being issued should be complete
in all respect.
216) It is also very important that these three parameters should be feeder
wise and not for Discoms area as a whole to be fair with consumers.
Jodhpur Discom
217) Since supply of rural areas is being fed from single phase transformer,
hence, Jodhpur Discom is of view that Rural Area may be deleted.
Reply from Jaipur Discom:
218) The time specified by the Commission is prudent and hence the
method of reliability indices is self-sufficient to measure the
contingencies in the system and measure the performance. The spirit
of SOP is to gradually improve the system performance and to remove
the contingencies. Strict levels of performance would be proving to be
back-burner of various initiatives; which Discoms cannot achieve in
the present scenario.
Commission’s views
219) Looking to the practical difficulties of the Discoms in working out the
Reliability Indices even specified under the existing regulations for the
want of reliable data, as brought out by the Discoms during the
hearing as well as by various stakeholders; the Commission has
decided to retain the existing provisions of Reliability Indices, for the
time being.
220) Commission shall notify benchmarks of the reliability indices through a
separate order. These benchmarks as suggested by Shri R. G. Gupta,
cannot be specified in these regulations,. Further, it would not be
practicable to have benchmark for each feeder, as suggested by Shri
R. G. Gupta.
![Page 68: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/68.jpg)
68
221) With regards to other suggestions, it is mentioned that the SOP
provisions can be made more stringent after review by the
Commission, keeping in view the improvement in the infrastructure by
the Discoms with the passage of time.
Schedule -4: Minimum Overall Standards of Performance to be achieved by
a Licensee
Shri G.L. Sharma,
222) It has been mentioned that Commission would separately specify the
overall reliability indices standards required to be achieved by each
licensee. It is submitted that such reliability indices should have been
specified with these standards to complete matter instead of keeping
it for future
223) At S.no 2 under item B- system Reliability the words “meters in service”
may be replaced with the word “meters installed”. Similar correction is
also required in Form SoP-2.
Jaipur Discom
224) Consumer Satisfaction: The Minimum Standards figures 98% and 95%
may be considered 95% and 90% respectively.
225) System Reliability: The Minimum Standards figures 95% may be
considered 90%.
226) Beside above, formats prescribed with the Draft Regulations for
seeking information from field officers are bulky and considering past
experience, it seems that most probably, the field officers will not be
able to furnish the information incorporated in the formats. The
Commission is requested to take a practical view in this regard.
Commission’s views
227) As already mentioned above, the Commission shall consider to lay-
down benchmarks of the reliability indices through a separate
administrative order.
228) As suggested by Shri G. L. Sharma, the words “meters in service” shall
be replaced with the word “meters installed” at S.no 2 under item B-
system Reliability. Similar correction shall also be done in Form SoP-2.
229) As requested by the Jaipur Discom, the Minimum Standards figures
98% and 95% shall be revised to 95% and 90% respectively under the
item ‘A. Consumer Satisfaction’ and the Minimum Standards figures
95% shall be revised to 90% under the item ‘B. System Reliability’.
![Page 69: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/69.jpg)
69
9. Further, the formats have been suitably modified. Moreover, to have
flexibility in slight modifications in the existing formats, the Commission has
decided to insert a new sub-regulation 8(3) as mentioned above.
10. Accordingly, the ‘Rajasthan Electricity Regulatory Commission (Standards
of Performance for Distribution Licensees) Regulations, 2014, finalized as
above with minor other changes, wherever required, as placed below
duly authenticated, may be got published in official Gazette.
11. The copy of this Memo, along-with the finalized regulations, may be sent to
the State Government, concerned utilities and other Stakeholders.
(S. Dhawan) (D.C. Samant)
Member (T) Chairman
![Page 70: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/70.jpg)
70
RAJASTHAN ELECTRICITY REGULATORY COMMISSION
JAIPUR
--- February, 2014
No. RERC/ Secy / Regulation -- In exercise of the powers conferred on it by
sections 57 to 59 read with sections 86(1)(i), 181(1) and 181(2)(za & zb) of the
Electricity Act, 2003 (36 of 2003) and all other powers enabling it in this behalf,
the Rajasthan Electricity Regulatory Commission hereby makes following
regulations, namely:
1. Title and Commencement
(1) These Regulations shall be called the ‘Rajasthan Electricity Regulatory
Commission (Standards of Performance for Distribution Licensees)
Regulations, 2014.
(2) These Regulations shall come into force with effect from 1st October,
2014. However compensation amount for the non-compliance of these
Regulations by the licensees, shall be payable to the affected persons,
from the date(s) to be notified separately by the Commission.
2. Scope of Application
These regulations shall be applicable to all the Distribution Licensees
including Deemed Licensees in the state of Rajasthan.
3. Definitions
In these Regulations, unless the context otherwise requires:
(1) “Act” means the Electricity Act, 2003;
(2) “Area of Supply” means the area within which a licensee is authorized by
his license for supply of electricity;
(3) “Call-centre” means the office set-up by the licensee with adequate
technology to register and process the complaints against the supply of
electricity, round the clock throughout the year;
(4) “Commission” means the Rajasthan State Electricity Regulatory
Commission;
(5) “Class-1 Cities” means the cities with population of more than 2,00,000
as per census of India 2011;
(6) “Extra High Tension” (EHT) means the nominal voltage exceeding 33kV
between the phases;
![Page 71: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/71.jpg)
71
(7) “High Tension” (HT) means the nominal voltage exceeding 440 volts but
not exceeding 33kV, between the phases;
(8) “Licensee” means the Distribution Licensee, including Deemed
Distribution Licensee;
(9) “Low Tension” (LT) means the nominal voltage not exceeding 440 volts
between the phases;
(10) “Rural Areas” means the areas covered by Gram Panchayats and
Panchayat Samities;
(11) “SOP” means standard of performance;
(12) “Urban Areas” means the areas covered by Municipal Corporations and
Municipalities including the areas falling under the various Urban
Development Authorities, Cantonment Authorities and Industrial estates
or townships, excluding the areas covered under Class-1 Cities.
Words and expression used and not defined in these regulations but
defined in the Act shall have the meanings assigned to them in the Act.
Expressions used herein but not specifically defined in these regulations
or in the Acts but defined under any law passed by a competent
legislature and applicable to the electricity industry in the state shall
have the meaning assigned to them in such law.
4. Guaranteed Standards of Performance
(1) The licensee shall provide best services well within time limits specified in
Schedule-1 of these regulations, which are the guaranteed standards of
service for its consumers. The failure of licensee to achieve these
guaranteed standards shall entail payment of monetary compensation
to the affected persons as per these regulations.
(2) These guaranteed standards shall be read with the provisions specified
under the RERC (Electricity Supply Code and Connected Matters)
Regulations – 2004 and other relevant regulations, amended from time
to time.
5. Complaint Handling Mechanism
(1) The licensee shall publish a “Manual for Handling Consumer Complaints”
incorporating the details of call centres, toll free telephone numbers for
registering the complaints & to inform the status of its redressal, details of
concerned officers, guaranteed SOP, compensation & its payment
mechanism, application format and other relevant details, including
that of Consumer Grievance Redressal Forum (CGRF) and Electricity
Ombudsman.
![Page 72: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/72.jpg)
72
(2) The manual shall be in both languages i.e. English & Hindi and shall also
have the format prescribed by licensee for claiming the compensation.
It shall be available at every sub-divisional office for reference of general
public as also for sale at nominal cost.
(3) A copy of the Manual shall be filed with the Commission within three
months from the date of commencement of these regulations.
(4) The licensee shall establish Call-centres, easily accessible to its
consumers, within
i. 12 months in Class-1 Cities
ii. 18 months in Urban Areas
from the date of commencement of these regulations. The time
limit for establishment of call centres in rural areas shall be notified
separately by the Commission.
(5) The affected person shall lodge the complaint with the respective Call
centre. However, the licensee shall continue to use the existing channels
for recording and redressal of the consumer complaints till the
establishment of Call centres.
(6) The licensee shall depute sufficient staff at its Call centres, set-up with
adequate technology. It shall provide one or more ‘Toll-free number’
with sufficient lines to register and process the complaints against the
licensee’s services, round the clock throughout the year. The complaints
may be received in person or through telephonic voice or SMS or in
writing.
(7) The licensee, immediately upon establishment of its Call centres with toll-
free telephone number, shall advertise through a public notice in
newspapers in circulation in the area of supply. Such toll free numbers
shall also be indicated on the electricity bills.
(8) The Call-centre shall
i. register the complaint received in person or through telephonic
voice or SMS or in writing and allot a complaint number which shall
be communicated to the complainant for further reference. A
model format for registration of the complaints is enclosed at
Annexure – I;
ii. within 30 minutes of registering the complaint, intimate to the
complainant through telephone or otherwise, the nature of fault
and status of the complaint;
iii. intimate the status of redressal of grievance as and when asked by
the complainant;
iv. intimate the contact details of the next higher authority in case the
complainant is not satisfied with the redressal of his complaint.
![Page 73: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/73.jpg)
73
v. provide a copy of the relevant extract of Annexure-I to the
complainant on demand, free of cost, for claiming the
compensation; within three days of receiving a request.
(9) The office where the complaint has been registered shall redress the
complaint within the time specified for the purpose. In case any
instructions/sanction is required to be obtained from higher authority, it
shall be obtained by the complaint registering office. The affected
person shall not be required to approach such higher authority.
(10) Complaint against non- registration of complaints and/ or failure to
perform/redress the complaint within specified time period, may be
brought to the notice of the concerned Assistant Engineer /Executive
Engineer by the affected person for expediting the redressal of the
complaint.
6. Payment of Compensation
(1) In the event of non-fulfilment of any Guaranteed Standards of
Performance, specified in Schedule – 1, the affected person may file an
application personally or by registered post to the concerned Assistant
Engineer, in the format prescribed by the licensee, for the claim of
compensation as specified in Schedule – 2 of these Regulations. Such
application can be filed within 30 days of expiry of the specified time.
The licensee shall pay such compensation, by way of adjustment
through electricity bills, not later than 90 days from the date of violation
of the Guaranteed Standard failing which an additional compensation
@ 1% of the compensation amount shall be payable to the affected
consumer for each week of delay or part thereof.
(2) Failure by the licensee to pay the compensation as per Regulation 6(1)
above shall constitute a Grievance, which shall be dealt and decided
by the respective Consumer Grievance Redressal Forum, in
accordance with procedure set out in the RERC (Guidelines for
Redressal of Grievances) Regulations, 2008.
(3) In case the Forum does not decide the amount of compensation within
the specified time or the aggrieved consumer is not satisfied with the
decision of the Forum, he will be free to approach the Electricity
Ombudsman, who shall deal and decide the case under RERC
(Settlement of Disputes by Electricity Ombudsman) Regulations, 2010.
(4) The aggrieved consumer shall not be liable to pay any fee for lodging a
claim of compensation under these regulations before the licensee,
Forum or Electricity Ombudsman.
![Page 74: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/74.jpg)
74
(5) The payment of such compensation shall be without prejudice to any
penalty which may be imposed or prosecution be initiated for the failure
of the licensee in meeting the standards specified in these Regulations.
7. Overall Standards of Performance
(1) The licensee shall achieve the Overall Standards of Performance in the
discharge of its obligations towards the various standards specified in
Schedule-3. The minimum Overall Standards of Performance to be
achieved by a licensee during the year shall be as specified in
Schedule-4.
(2) The compensation amount paid by the licensee, may be allowed to be
recovered partly or fully in the ARR, keeping in view the extent to which
the licensee is able to achieve the Overall Standards as per the
Schedule - 3.’
8. Submission of SOP Reports
(1) The licensee shall furnish the Commission as well as the Electricity
Ombudsman, half yearly reports within 45 days respectively from 30th
September and 31st March of each financial year, indicating its actual
performance in the formats SOP-1 to SOP- 5, attached to these
regulations. These formats are as listed below;
SoP 1: Establishment of Call Centers
SoP 2: Redressal of Consumer Complaints
SoP 3: Compensation Information
SoP 4: SAIFI
SoP 5: SAIDI
(2) The licensee shall also furnish a report along with the half yearly reports
as per (1) above, indicating
i. the measures taken to improve performance,
ii. the reasons for not achieving the specified targets, if any.
(3) The Commission may revise the formats through separate orders, as
warranted necessary from time to time.’
9. Information with respect to Levels of Performance
The Commission shall once in every half year arrange for the publication,
in such form and manner as it considers appropriate, of such of the
information furnished to it under Regulation 8 above, by each licensee.
![Page 75: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/75.jpg)
75
10. Exclusions of Events
The application of the standard of performance specified in these
regulations shall remain suspended in case of force majeure
i. events such as war, mutiny, civil commotion, riots, flood,
cyclone, lightning, earthquake, fire etc. affecting licensee’s
installations and also under wind or rainy conditions affecting
safety of electrical equipment and personnel,
ii. activities like strike, lockout, outages of generation or
transmission lines, instructions of SLDC for shut down, any act of
law beyond the control of the licensee, and
iii. outages due to shut down required to carry out the work by /
for other agency.
11. Protection of Consumer Rights
Nothing contained in these regulations, shall in any way, prejudice or
affect the rights & privileges of the consumers under other laws including
the Consumer Protection Act, 1986 (Central Act of 68 of 1986).
12. Repeal and Saving
1) Save as otherwise provided in these regulations, the RERC (Distribution
Licensee’s Standards of Performance) Regulations, 2003 are hereby
repealed on coming into force of these regulations except the
Regulation 9(iii) thereof so far as charging of cost / security in case of
burnt meters, is concerned which will remain in force till it is
incorporated in the RERC (Supply Code and Connected Matters)
Regulations, 2004.
2) Notwithstanding such repeal anything done or action taken or
purported to have been done for the purpose of meeting SoP
obligation shall be deemed to have been done or taken under the
corresponding provisions of these Regulations.
3) Any rights and liabilities arising out of the Regulation so repealed shall
be settled within the framework of the repealed Regulations.
13. Power to remove difficulties
If any difficulty arises in giving effect to the provisions of these Regulations,
the Commission may Suo-motu or on a petition, by general or specific
order, makes such provisions not inconsistent with the provisions of the
Act, as may appear to be necessary for removing the difficulty.
![Page 76: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/76.jpg)
76
14. Power to amend
The Commission may, at any time, vary, alter, modify or amend any
provision of these Regulations, with reasons to be recorded in writing.
15. Power to Relax
The Commission, may by general or special order, for reasons to be
recorded in writing, and after giving an opportunity of hearing to the
parties likely to be affected, relax any of the provisions of these
Regulations on its own motion or on an application made before it by an
interested person.
By order of the Commission,
(G. K. Sharma)
Secretary
RERC, Jaipur
![Page 77: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/77.jpg)
77
Schedule - 1
Licensee’s Guaranteed Standards of Performance
1. Restoration of Supply:
1.1 No Current Complaint
The licensee shall restore the supply in case of supply related problem/
fault like blowing of HT/LT fuse/MCB prior to meter or at distribution
transformer or due to loose connections at meter or service line within:
i. 4 hrs. in Class 1 Cities
ii. 6 hrs. in Urban Areas
iii. 24 hrs. in Rural Areas
from the time of reporting of fault by the consumer. However in
case of any practical difficulty if a complaint is not redressed during
the period 10 PM to 6 AM, it could be redressed later within the time
frame specified above, excluding such period in reckoning of the
said time frame.’
1.2 Overhead line/cable breakdowns
The licensee shall restore the supply in case of its overhead line/cable
breakdowns within:
iv. 6 hrs. in Class 1 Cities
v. 12 hrs. in Urban Areas
vi. 24 hrs. in Rural Areas
from occurrence of fault. However in case of any practical difficulty
if a complaint is not redressed during the period 10 PM to 6 AM, it
could be redressed later within the time frame specified above,
excluding such period in reckoning of the said time frame.’
1.3 Underground cable breakdowns
The licensee shall restore the supply in case of breakdown of its
underground cable within:
iv. 12 hrs. in Class 1 Cities
v. 24 hrs. in Urban Areas
vi. 36 hrs. in Rural Areas
from occurrence of fault. However in case of any practical difficulty
if a complaint is not redressed during the period 10 PM to 6 AM, it
could be redressed later within the time frame specified above,
excluding such period in reckoning of the said time frame.’
1.4 Transformer failure
The licensee shall restore the supply in case of failure of its transformer
within:
a) Distribution Transformers
iv. 16 hrs. in Class 1 Cities
v. 36 hrs. in Urban Areas
vi. 72 hrs. in Rural Areas
from the time of reporting of fault by the consumer and
b) Power Transformers
![Page 78: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/78.jpg)
78
3 working days from occurrence of fault.
1.5 Scheduled outages
Interruption in power supply due to schedule outages, other than the
load-shedding, shall be notified by licensee at least 24 hours in advance
for planned shutdown and same day in emergent cases and shall not
exceed 10 hours in a day. The supply should normally be restored by 6 PM
2. Quality of Supply
2.1 Voltage Variations
The licensee shall maintain voltages at the point of commencement of
the supply to a consumer within the limits as under subject to voltage
availability within the specified limits at incoming point of the distribution
system:
iii. +6% and -6% in case of LT supply
iv. +6% and -9% in case of HT supply
and in case of variation, the problem shall be resolved within the time
frame as given below:
v. 2 working days in general
vi. 1 month in case of transformer repair/ replacement
vii. 4 months in case of substation augmentation
viii. 6 months in case of new substation
from the time of reporting by the consumer.
3. Meter Complaints
3.1 Testing of Meter
In case a consumer reports that meter is not functioning properly, a
notice can be given to the licensee, who shall verify the correctness of
meter at site and if required replace the meter within 2 months of the
date of notice by the consumer.
3.2 Replacement of stopped / damaged / burnt Meter
In case of stopped / damaged / burnt meter reported by the consumer
or noticed by the licensee, the meter shall be replaced by the licensee,
within 2 months of such detection.
Provided that in case of no current complaint on account of stopped /
damaged / burnt meter, the licensee shall replace the meter within 48 hrs
of reporting by the consumer or detection by the licensee, as the case
may be, unless it is established that the meter has been tempered or
damage in any way including excess load by the consumer, in which
case, the licensee shall replace the meter within 48 hours after depositing
the amount of security of meter towards cost of meter by the consumer.
4. Shifting of Meters/Service Lines
![Page 79: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/79.jpg)
79
4.1 Demand Note
The licensee shall inspect and inform the estimated cost to the consumer
within 15 days of receipt of application.
4.2 Shifting of Meter
The licensee, on receipt of amount of demand note and necessary
clearances / no-objection, shall shift the meter within:
i. 7 working days in case of LT consumers
ii. 15 working days in case of HT consumers
4.3 Shifting of Service Line
The licensee, on receipt of amount of demand note and necessary
clearances / no-objection, shall shift the service line within:
i. 15 working days in case of LT consumers
ii. 1 month in case of HT consumers
5. Release of New Connections or additional power
5.1 The licensee shall release new connections to different categories of
consumers under different situations, as per the norms specified in the
RERC Supply Code Regulations.
5.2 In case of any delay in release of new connection or additional
power, the consumer should first approach the concerned sub-divisional
officer who shall appraise him the factual status in the matter and
expected date / period of completion of work. In case of un-satisfactory
response, the consumer may get the complaint lodged in Call centre.’
6. Transfer of ownership and change of category
6.1 The licensee, on receipt of necessary documents certifying the transfer
of ownership or change of category, as the case may be, shall transfer
the ownership of the connection or change of category on the existing
system, within 2 months.
7. Consumer bill complaint
7.1 In case of any billing problem, the consumer should first approach the
concerned Sub-divisional officer or Billing officer who shall resolve the
problem. However, in case of un-satisfactory response, the consumer may
get his complaint lodged in Call centre. The licensee shall resolve the
billing problem within:
iii. 3 working days, in case no information is required to be collected
iv. 7 working days, in case some information is required to be collected
by the billing authority.
In case the complaint is genuine, the licensee shall extend the due date
for payment of bill so as to allow at least 7 working days for making
payment by the consumer.
![Page 80: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/80.jpg)
80
8. Disconnection of supply
8.1 The licensee, on receipt of a request and clearance of dues from the
consumer along with disconnection fee, if any, prescribed by the
Commission, shall disconnect the supply within:
i. 3 working days in Class 1 Cities
ii. 7 working days in Urban Areas
iii. 10 working days in Rural Areas
8.2 In case of permanent disconnection, the licensee shall refund all the
money payable to the consumer such as security etc and issue a “No-
Dues Certificate” within 2 months from the date of disconnection or from
the date of clearing the dues by the consumer payable to the licensee;
whichever is later.
9. Restoration of a disconnected consumer
9.1 The licensee, on clearing the dues by a disconnected consumer, shall
restore supply as envisaged under RERC Supply Code Regulations.
10. System reliability to avoid heavy fluctuations or short circuiting of lines
10.1 The Licensee shall erect and keep the system so reliable to avoid any
damage to electrical equipments of the consumers on account of heavy
fluctuations in supply voltage or short circuiting of lines.
-------------
![Page 81: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/81.jpg)
81
Schedule-2
Compensation Payable by the Licensee
In case of failure of a licensee to meet the Guaranteed Standards of
Performance as specified in Schedule – 1 of these regulations, the following
compensation shall be payable to the consumer by the licensee-
S. No.
Ref no. of Sch.- 1
SOP Parameters Compensation to individual
1. Restoration of supply
1 1.1 No current complaint Rs. 50 for LT Rs. 100 for HT
2 1.2 Overhead Line / Cable breakdowns Rs. 50 for LT
Rs. 100 for HT
3 1.3 Under ground cable break down Rs. 50 for LT
Rs. 100 for HT
4 1.4 Transformer Failure Rs. 100 for LT
Rs. 300 for HT
5 1.5 Scheduled outage Rs. 50 for LT
Rs. 100 for HT
2. Quality of supply
6 2.1 Voltage variations Rs. 100 for LT
Rs. 300 for HT
3. Meter Complaints
7 3.1 Testing of meter Rs. 200 for LT
Rs. 500 for HT Rs. 1000 for EHT
8 3.2 Replacement of stopped /defective /burnt Meter As per Supply Code
Regulations
9 3.2 For no-current complaint due to meter Rs. 200 for LT
Rs. 500 for HT Rs. 1000 for EHT
4. Shifting of Meter / Service line
10 4.1 Demand note Rs. 50 for LT
Rs. 100 for HT Rs. 200 for EHT
11 4.2 Shifting of Meter Rs. 50 for LT
Rs. 100 for HT Rs. 200 for EHT
12 4.3 Shifting of Service line Rs. 50 for LT
Rs. 100 for HT
5. Release of new connection/additional power
13 5.1 Release of new connection/additional power Rs. 200 for LT
Rs. 500 for HT Rs. 1000 for EHT
6. Transfer of ownership or change of category
![Page 82: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/82.jpg)
82
S.
No.
Ref no. of
Sch.- 1
SOP Parameters Compensation to
individual
14 6.1 Transfer of ownership or change of category Rs. 50 for LT
Rs. 100 for HT Rs. 200 for EHT
7. Consumer bill complaint
15 7.1 Billing complaint resolution Rs. 50 for LT
Rs. 100 for HT Rs. 200 for EHT
8. Disconnection of supply
16 8.1 Disconnection of supply Rs. 50 for LT
Rs. 100 for HT Rs. 200 for EHT
17 8.2 Issue of no dues certificate Rs. 50 for LT
Rs. 100 for HT Rs. 200 for EHT
9. Restoration of a disconnected consumer
18 9.1 Restoration of a disconnected consumer Rs. 50 for LT
Rs. 100 for HT Rs. 200 for EHT
10. Compensation for damages on account of heavy fluctuations in supply or short circuiting of lines
19 10.1 Fan, B&W TV, Mixy Rs 500
20 10.1 Color TV, Semi-auto Washing m/c, Fridge Rs 1000
21 10.1 Full auto Washing m/c, Computer, A/C Rs 2000
Note
i. Compensation for damages on account of heavy fluctuations in supply or short
circuiting of lines shall be payable to individuals when event affects more than five
consumers on a feeder and subject to physical verification of the damaged
equipments by the licensee.
ii. The above mentioned amount of compensation shall remain the same if
time taken by licensee is up to double the specified period; thereafter the
amount of compensation shall be double the amount specified above.
![Page 83: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/83.jpg)
83
Schedule -3
Overall Standards of Performance for a Licensee:
3.1 Consumer Satisfaction
The licensee shall redress the consumer complaints within the time limit
specified in Schedule – 1. The licensee shall maintain the minimum
overall consumer satisfaction level as specified in Schedule– 4.
3.2 Replacement of incorrect meters
The licensee shall try to replace the incorrect meters at the earliest and
keep all the consumer meters correct. The licensee shall maintain the
minimum percentage of correct meters to the total number of meters in
service as specified in Schedule– 4.
3.3 Replacement of transformers
The licensee shall try to replace the burnt or defective transformers at
the earliest and keep all the transformers in working condition. The
licensee shall maintain the minimum percentage of working
transformers to the total number of transformers connected for service,
separately for Distribution and Power Transformers, as specified in
Schedule– 4.
3.4 Reliability Indices
3.4.1 Reliability of the distribution system operated by the licensee shall be
computed on the basis of number and duration of sustained interruptions
in each half year. In a power delivery system, it may take a few minutes to
restore power after transient faults or to reroute power in the network to
restore supply to the affected area where a large number of customers
are involved. Such momentary interruptions of up to ten minutes shall not
be considered but sustained interruptions of more than ten minutes
duration shall be considered for judging the reliability of the system.
3.4.2 Reliability standards of the licensee shall be judged by the following two
indices:
a) System Average Interruption Frequency Index (SAIFI), which shall be
calculated by dividing the total number of sustained interruptions to
consumers in each half year by the total number of consumers
served. An interruption in supply to a consumer shall be considered
as one interruption to one consumer. In case of failure of a line or
transformer, number of interruptions shall be equal to the number of
consumers affected. The index shall be expressed as number of
interruptions per consumer per half year.
![Page 84: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/84.jpg)
84
b) System Average Interruption Duration Index (SAIDI), which shall be
calculated by dividing the total minutes of sustained interruption in
supply to consumers in each half year by the total number of
consumers served. The index shall be expressed as number of minutes
of interruption per consumer per half year.
3.4.3 While calculating the above indices, the following types of interruptions
shall not be taken into account:
a) Planned outages
b) Momentary outages of ten minutes or less
c) Outages due to failure of upstream power system including
generation and transmission network.
d) Outages due to reasons allowed in these Regulations under
‘Exclusions of Events’.
3.4.4 For calculating reliability indices, licensee shall maintain data at each sub-
station and compile monthly data for each Circle to ascertain Circle wise
reliability indices of the system. The licensee shall workout each Reliability
Index as above and calculate circle wise SAIFI and SAIDI in the formats
SOP-4 and SOP-5 respectively.
3.4.5 The Commission shall separately notify the overall reliability indices
standards required to be achieved by each licensee.
![Page 85: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/85.jpg)
85
Schedule -4
Minimum Overall Standards of Performance to be achieved by a Licensee
A. Consumer Satisfaction
S. No.
Ref no. of Sch.- 1
SOP Parameters Minimum Standards for redressal of
consumer grievances to be achieved during each year
1 1.1 No current complaint 95%
2 1.2 Overhead Line / Cable breakdowns 90%
3 1.3 Underground cable break down 90%
4 1.4 Transformer Failure(separately for LT & HT
supply consumers)
90%
5 1.5 Scheduled outage 90%
6 2.1 Voltage variation 90%
7 3.1 Testing of Meter 90%
8 3.2 Replacement of stopped/defective Meter 90%
9 3.2 For no-current complaint due to meter 90%
10 4.1 Demand note 90%
11 4.2 Shifting of Meter 90%
12 4.3 Shifting of Service line 90%
13 5.1 Release of new connection/additional
power
90%
14 6.1 Transfer of ownership or change of category 90%
15 7.1 Billing complaint resolution 95%
16 8.1 Disconnection of supply 90%
17 8.2 Issue of no dues certificate & refund of security
95%
18 9.1 Restoration of a disconnected consumer 90%
19 10.1 System reliability to avoid heavy fluctuations or short circuiting of lines
90%
![Page 86: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/86.jpg)
86
B. System Reliability
S. No.
Ref no. of Sch.- 3
SOP Parameters Minimum Standards to be achieved during each year
1 3.2 Correct meters to the total number of
meters installed
90%
2 3.3 Transformers in working condition to
the total number of transformers connected in service
i. Distribution Transformer
ii. Power Transformer
90%
90%
3 3.4 SAIFI The Commission shall separately notify
the overall reliability indices standards
required to be achieved by each
licensee.
4 3.4 SAIDI
![Page 87: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/87.jpg)
87
![Page 88: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/88.jpg)
88
Distribution SOP Reporting Formats
Establishment of Call - Centres
SOP - 1
Name of Licensee:
For the 1st/ 2nd Half Year ending: ________
S. No.
Name of circle
Total No. of Call Centres to be established
No. of Call Centres previously established
No. of Call Centres established during the period
Total No. of Call Centres established
Call centres yet to be established
No. of consumers connected with Call centres
Total No. of consumers in the area
1
2
3
Total
(Signatures with Designation)
![Page 89: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/89.jpg)
89
Distribution SOP Reporting Formats
Redressal of Consumer Complaints
SOP – 2
Name of Licensee:
For the 1st/ 2nd Half Year ending _______
A. Consumer Satisfaction
S. No. Ref no.
of
Sch.- 1
SOP Parameters Complaints
brought
forward
Received
during
period
Total
complai
nts
Redressed
in time
Redress
al in
time (%)
Redressed
beyond
time
Total
complain
ts
redressed
Compla
ints
pending
Total
Redressal
(%)
Target
fixed
1 1.1 No current complaint 95%
2 1.2 Overhead Line / Cable
breakdowns
90%
3 1.3 Under ground cable break down 90%
4 1.4 Transformer Failure 90%
5 1.5 Scheduled outage 90%
6 2.1 Voltage variation 90%
7 3.1 Testing of Meter 90%
8 3.2 Replacement of stopped/defective Meter
90%
9 3.2 No-current complaint due to meter 90%
10 4.1 Demand note 90%
11 4.2 Shifting of Meter 90%
12 4.3 Shifting of Service line 90%
13 5.1 Release of new
connection/additional power
90%
14 6.1 Transfer of ownership or change of
category
90%
15 7.1 Billing complaint resolution 95%
16 8.1 Disconnection of supply 90%
![Page 90: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/90.jpg)
90
S. No. Ref no.
of
Sch.- 1
SOP Parameters Complaints
brought
forward
Received
during
period
Total
complai
nts
Redressed
in time
Redress
al in
time (%)
Redressed
beyond
time
Total
complain
ts
redressed
Compla
ints
pending
Total
Redressal
(%)
Target
fixed
17 8.2 Issue of no dues certificate 95%
18 9.1 Restoration of DC consumers 90%
19 10.1 System reliability to avoid heavy
fluctuations or short circuiting of lines
90%
B. System Reliability
S. No. Ref no.
of
Sch.- 3
SOP Parameters Complaints
brought
forward
Received
during
period
Total
complai
nts
Redressed
in time
Redress
al in
time (%)
Redressed
beyond
time
Total
complain
ts
redressed
Compla
ints
pending
Total
Redressal
(%)
Target
fixed
1 3.2 Correct meters to the total number
of meters installed
90%
2 3.3 Transformers in working condition
to the total number of transformers connected in service
i. Distribution Transformers
ii. Power Transformers
90% 90%
(Signatures with Designation)
![Page 91: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/91.jpg)
91
Distribution SOP Reporting Formats
Details of Compensation Paid
SOP - 3
Name of Licensee:
For the 1st/ 2nd Half Year ending: ________
S. No.
Name of circle
No. of consumers in the circle
No. of complaints received during the Half Year
Compensation Complaints lodged
Compensation paid
No. of consumers
Amount (Rs)
No. of consumers
Amount (Rs)
1
2
3
Total
(Signatures with Designation)
![Page 92: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/92.jpg)
92
Distribution SOP Reporting Formats
Reliability Indices
System Average Interruption Frequency Index (SAIFI)
SOP - 4
Name of Licensee:
For the 1st/ 2nd Half Year ending ________
S. No.
Name of circle Total number of consumers served (1)
Total number of sustained interruptions to consumers (2)
SAIFI= (2) / (1) (Number of interruptions/ consumer)
Target specified by the Commission
1
2
3
4
5
6
Total
Note:
An interruption in supply to a consumer shall be considered as one interruption to one consumer. In case of
failure of a line or transformer, number of interruptions shall be equal to the number of consumers affected.
(Signatures with Designation)
![Page 93: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/93.jpg)
93
Distribution SOP Reporting Formats
Reliability Indices
System Average Interruption Duration Index (SAIDI)
SoP - 5
Name of Licensee:
For the 1st/ 2nd Half Year ending ________
S. No.
Name of circle Total number of consumers served (1)
Total minutes of sustained interruptions to consumers (2)
SAIFI= (2) / (1) (Minutes/consumer)
Target specified by the Commission
1
2
3
4
5
6
Total
Note:
An interruption in supply to a consumer shall be considered as one interruption to one consumer. In case of
failure of a line or transformer, number of interruptions shall be equal to the number of consumers affected.
(Signatures with Designation)
![Page 94: RAJASTHAN ELECTRICITY REGULATORY · PDF fileCoram: Shri D.C. Samant, Chairman Shri S. Dhawan, ... The manpower contract of a 33 kV GSS is awarded for as low an ... an exhaustive training](https://reader034.fdocuments.us/reader034/viewer/2022042801/5aa0416e7f8b9a8e178dbd13/html5/thumbnails/94.jpg)
94
Model format for registering a complaint
Annexure -I
Name of Complaint Centre:
Name of circle:
Month ________
S. No
Time & Date of receiving complaint
Mode of receiving complaint
Name, Address, contact no. of complainant
A/c No.
Nature of complaint
Complaint number
Name of Sub Div & Division
Reference Guaranteed Standard
Time & Date of intimating status
Time & Date of redressal of complaint
Total time taken for complaint redressal (in Days/Hrs)
Redressal of grievance within / beyond Std time
(Signatures with Designation)