RAJASTHAN CO-OPERATIVE DAIRY FEDERATION LIMITED · RCDF Ltd., payable at Jaipur. The detailed terms...
Transcript of RAJASTHAN CO-OPERATIVE DAIRY FEDERATION LIMITED · RCDF Ltd., payable at Jaipur. The detailed terms...
1
Rajasthan Co-operative Dairy Federation Limited
“Saras Sankul” J.L.N. Marg, Jaipur-302 017 Phone No. 0141-2702501-508 : Telefax 0141-2702135 : Website : sarasmilkfed.rajasthan.gov.in
E-mail : [email protected]
No. RCDF/DPM& Proj./(P-2901)/2012-13 Dated 16.07.2012
TENDER NOTICE
Sealed tenders are invited from experienced bonafide manufacturers of Cattle Feed Plant and its
equipments for “Design, Supply, Installation, Testing and Commissioning of 150 TPD cattle
feed plant (expandable up to 300 TPD) on Turnkey Basis” each at Lambiyankalan District
Bhilwara & proposed site at village Hathalai (Gundoge) District Pali (Raj). Tender form with
terms and conditions can be obtained from RCDF by depositing Cash/Demand Draft of Rs.
10,000/- only (Rs. 100 extra if desired by post) in favour of RCDF Ltd., payable at Jaipur up to
3.00 PM on dated 16.08.2012. Further details can be obtained from our website
sarasmilkfed.rajasthan.gov.in.
General Manager (DPM & Proj.)
1. LAST DATE AND TIME OF
SALE OF TENDER FORM : 16.08.2012 Upto 3.00 PM
2. DATE & TIME OF PRE-BID MEETING : 09.08.2012 AT 11.00 AM AT
RCDF, JAIPUR
3. LAST DATE & TIME FOR SUBMISSION
OF DULY FILLED TENDER FORM
(Technical & Financial bid in separate envelopes) : 17.08.2012 Upto 2.30 PM
4. DATE & TIME FOR OPENING OF
THE TENDER (Technical bid only) : 17.08.2012 AT 3.00 PM
5. EMD (to be deposited with the tender in
the technical bid) : Rs. 36,00,000/- (Rs. Thirty Six Lac
only) by Demand draft only in favour of
RCDF Ltd., payable at Jaipur.
The detailed terms and conditions of the tender are contained in the Tender document.
General Manager (DPM & Proj.)
Note: The Tender form is also available on web site www.sarasmilkfed.rajasthan.gov.in and may
be downloaded from the website. In case of downloaded document a demand draft of Rs. 10,000/-
(Ten Thousand only) should be enclosed with the tender document.
2
RAJASTHAN CO-OPERATIVE DAIRY FEDERATION LIMITED
“SARAS SANKUL”, J.L.N. MARG, JAIPUR – 302 017. Phone No.2702501 : Fax 2710209 : Website : www.sarasmilkfed.coop : E-mail: [email protected]
No. RCDF/DPM& Proj./(P-2901)/2012-13 Dated 16.07.2012
ONLY THROUGH SPEED POST
M/s. _______________________,
___________________________,
___________________________,
___________________________.
Sub: Tender document for “DESIGN, SUPPLY, INSTALLATION, TESTING AND
COMMISSIONING OF 150 TPD CATTLE FEED PLANT (EXPANDABLE UP TO 300
TPD) ON TURNKEY BASIS” EACH AT LAMBIYANKALAN DISTRICT BHILWARA &
PROPOSED SITE AT VILLAGE HATHALAI (GUNDOGE) DISTRICT PALI (RAJ).
Ref.: Your request letter No. _____________ dated ____________ for issue of tender
document.
Dear Sir,
We thank you for evincing interest in the tender floated by us. The tender document along with
technical specification is enclosed which is to be returned duly sealed and signed on each page. We wish to
emphasize few pertinent points concerning the tender:-
1. There is an Eligibility and Qualification Criterion prescribed in the tender document . Tenders from firms
fulfilling the Eligibility and Qualification Criterion will only be considered for price bidding. It is,
therefore, of utmost importance that all documents establishing your eligibility are submitted as per the
check list given. Non receipt of the documents with the tender would be construed as you are not
fulfilling the eligibility criterion and such tenders are liable for no further consideration / evaluation.
2. All the terms & conditions, Special as well as General are important.
3. Each tenderer is required to provide complete address, phone no. etc. against General Condition No.2.8 of
the tender document failing which the tender is liable to be treated as incomplete.
4. The tender must be submitted in three envelopes method as specified in special note i.e. :-
(i) The first envelope of part –I : This shall contain “EMD” Demand Draft.
(ii) The Second envelope of part-I – This shall contain :-
A. Sealed & signed complete tender document (except Page No.29 to 40 which is for Price
Bid) along with specifications.
B. Required documents/papers towards eligibility & qualifications criterion.
C. All other requirements as mentioned in the tender document.
(iii) The third envelope (Part-II)
This shall contain only Price Bid of the quoted item in the prescribed proforma given in the
tender document. Kindly refer page no 29 to 40 of tender document for quoting rates)
3
Thanking you,
Yours faithfully,
Encl.: As above
General Manager (DPM & Proj.)
4
FOR
“DESIGN, SUPPLY, INSTALLATION, TESTING AND
COMMISSIONING OF 150 TPD CATTLE FEED PLANT
(EXPANDABLE UP TO 300 TPD) ON TURNKEY BASIS”
AT
LAMBIYANKALAN DISTRICT BHILWARA & PROPOSED SITE
AT VILLAGE HATHALAI (GUNDOGE) DISTRICT PALI (RAJ).
(Bid to be submitted in Two envelop technical & commercial)
RAJASTHAN COOPERATIVE DAIRY FEDERATION LIMITED
SARAS SANKUL, JAWAHARWAL NEHRU MARG, JAIPUR
Phone No: 0141-2702501-508, Telefax: 0141-2710209, 0141-2702135
Website: www.sarasmilkfed.coop, E-mail: [email protected]
TENDER FORM
5
Rajasthan Co-operative Dairy Federation Limited
“Saras Sankul” J.L.N. Marg, Jaipur-302 017 Phone No. 0141-2702501-508 : Telefax 0141-2702135 : Website : sarasmilkfed.rajasthan.gov.in
E-mail : [email protected]
No. RCDF/DPM& Proj./(P-2901)/2011-12 Dated 16.07.2012
TENDER NOTICE
Sealed tenders are invited from experienced bonafide manufacturers of Cattle Feed Plant and its
equipments for “Design, Supply, Installation, Testing and Commissioning of 150 TPD cattle
feed plant (expandable up to 300 TPD) on Turnkey Basis” each at Lambiyankalan District
Bhilwara & proposed site at village Hathalai (Gundoge) District Pali (Raj). Tender form with
terms and conditions can be obtained from RCDF by depositing Cash/Demand Draft of Rs.
10,000/- only (Rs. 100 extra if desired by post) in favour of RCDF Ltd., payable at Jaipur up to
3.00 PM on dated 16.08.2012. Further details can be obtained from our website
sarasmilkfed.rajasthan.gov.in.
General Manager (DPM & Proj.)
4. LAST DATE AND TIME OF
SALE OF TENDER FORM : 16.08.2012 Upto 3.00 PM
5. DATE & TIME OF PRE-BID MEETING : 09.08.2012 AT 11.00 AM AT
RCDF, JAIPUR
6. LAST DATE & TIME FOR SUBMISSION
OF DULY FILLED TENDER FORM
(Technical & Financial bid in separate envelopes) : 17.08.2012 Upto 2.30 PM
4. DATE & TIME FOR OPENING OF
THE TENDER (Technical bid only) : 17.08.2012 AT 3.00 PM
5. EMD (to be deposited with the tender in
the technical bid) : Rs. 36,00,000/- (Rs. Thirty Six Lac
only) by Demand draft only in
favour of RCDF Ltd., payable at Jaipur.
The detailed terms and conditions of the tender are contained in the Tender document.
1. Name and full address of the firm
Submitting the tender (In block letters) ___________________________________
___________________________________
___________________________________
Phone No. ……………………. Mobile No. ……………………. Fax No. …………………………
6
2. Addressed to : R.C.D.F. Ltd.,
Saras Sankul
J. L. N. Marg
JAIPUR-17
3. Income tax PAN no. : ________________________________
4. Last 3 years Income Tax clearance : Either in original or photocopy
or returns certificates duly attested are to be
enclosed.
5. Status of tenderer (tick mark only) : Individual/ HUF/ firm/ company (Specify the
details in enclosed section– I)
6. Earlier experience in this field (if any) : Enclose the document/s.
7. Name of the person/s authorized to : An attested photocopy of power of
negotiate and sign the contract attorney issued by all partners/director
(Designation / status in the firm) in favor of nominated person to be encl.
8. Before making any change in constitution of the firm will be intimated to the R.C.D.F. LTD.,
Jaipur for their approval.
9. The tender fee of Rs. 10,000/= ( Rs Ten Thousand only ) cash / DD has been deposited vide
cash receipt no._________dated___________.
10. I / We agree to abide by all the terms & conditions mentioned in the Tender Notice issued by
the General Manager (DPM),RCDF Ltd., Jaipur and the other conditions annexed with the
tender form, all the pages of which have been signed by me / us in token of my / our
acceptance of the terms & conditions mentioned therein.
11. The EMD deposited vide demand draft no.______________dated__________ issued by
bank______________________________________of Rs. 18,00,000/= (Rs. Eighteen Lac
only) in favor of R.C.D.F. Ltd., Jaipur to cover earnest money (No interest will be payable on
EMD).
12. Details of the Bankers:
13. VALIDITY: The validity of offered rate will be 120 days from the date of opening / final
bid (withdrawal of offer with in which by me / us shall to be forfeiture of the EMD).
14. COMPANY PROFILE: The tenderer must enclose their company profile and financial
status (Enclose latest balance sheet, current assets / liabilities, working capital) along with
tender form. It should also include details like location of production unit, make & capacity
of production and service equipments, technical manpower and other facilities available.
7
Notes:
1. Please do not change the format/language and cut/add any items otherwise the
tender would be rejected.
2. Proofs and supporting documents of all the points must be enclosed and filled in the
checklist.
3. Any clarification w.r.t. tender‟s terms & conditions can be obtained during office
hours on all working days from this office prior to submission date of tender
4. All rates quoted must be FOR destination. IF RST/CST / excise is/are exempted,
than exemption certificate (s) is/are to be enclosed.
5. Rates in “Price Bid” as per Annexure-1 shall be written both in words and in
figures. There should not be errors and or overwriting. Correction if any, should be
made clearly and initialed with dates.
6. Tenderer has to submit the Technical Bid and Price Bid Separately in sealed
envelopes super scribing with Technical Bid and Price Bid.
a. EMD and all required enclosures along with duly signed General Terms &
Special Terms & Conditions should be submitted along with “Pre-
Qualification Bid”.
General Manager (Proj. & DPM)
8
(i)
SPECIAL NOTES – Section - I
1. EARNEST MONEY :
The tenderer is required to submit EMD as mentioned in the tender document in a
separate envelop only in form of Demand Draft in favour of Rajasthan Cooperative
Dairy Federation Limited, Jaipur.
2. BIDS IN TWO PARTS :
Bids are required to be submitted in two parts - Part-I & Part-II as described below:
2.1 The first part (Part-I) of the bid shall contain 2 separate sealed envelopes. In one
envelope EMD in form of DD/Bankers cheque as specified shall be placed. This
envelope should be super-scribed as “Part-I EMD only”. The second envelope of
the first part shall contain technical bid only. The envelope should be duly sealed
and super-scribed as “Part-I Technical Bid only”. At the time of the opening of the
tender first EMD DD envelope shall be opened and EMD shall be verified in
accordance to tender If EMD DD is not enclosed in a separate envelope and not
found in accordance to tender document the tender of such party shall be
rejected summarily.
2.2 The second part (Part-II) shall be placed in third separate envelope. It shall contain
financial bid/price bid. The envelope should be duly sealed and super-scribed as
“Part-II Price Bid only”
2.3 After verification of EMD DD deposit Technical bids shall be opened and EMD
details & technical details read out to the bidder‟s representatives. Price bids shall
not be opened immediately. After scrutiny of the technical bids, the clarifications, if
any, will be obtained from the bidders during the technical discussions. In case it is
necessary to obtain revised prices from the bidders the same shall be done by
asking all the concern bidders to submit the revised price bids in sealed covers, and
the earlier price bids will become invalid. In case all the tenderers submit the price
bids on the same day after freezing of technical requirements the bids shall be
opened on the same day. In case one or more of the eligible tenderers, consequent
to technical discussions and technical details frozen, desire to revise their price bid,
they can do so on the same day or at the most the next working day of the technical
discussions and the bids in such event shall be opened on the next day in the
presence of such representative of the tenderers who wish to be present. Normally
one representative of participating bidder will be allowed.
9
3. ELIGIBILITY & QUALIFICATION CRITERION:
The information required for Eligibility & Qualification Criterion should be provided
by the tenderer in the Criterion sheet at Page No. (iii) of Special Note and formats
(ii) prescribed under Section I, Section II (Schedule I and Schedule II), Section III by
enclosing order copies, performance certificates and other relevant documents in
support of their version. Incomplete information & documents or information not
furnished in the prescribed formats will make the tender liable for rejection
without any further reference to the tenderer. It is therefore enjoined upon all
tenderers to furnish complete information in the prescribed formats with supporting
documents in the very first instance.
4. The tenderers are advised to depute their authorized representative for the technical
discussions on the date and time as informed by the RCDF. The bids of the tenderers,
who fail to depute their representative as above shall be liable for rejection.
5. PRE BID CONFERENCE:
Pre bid conference dates as notified in tender document. The tenderers can seek any
clarifications in the Pre-bid conference.
10
(iii) COMPARATIVE STATEMENT OF ELIGIBILITY & QUALIFICATIONS
CRITERION
SPECIAL NOTES – Section - II
Statement/Check List of important documents to be submitted by each tenderer
(Each tenderer is required to fill up the form and enclose the required document failing which
the tender will become liable for no further consideration/evaluation) Sr.
no.
Particulars YES
or
NO
If yes please
indicate
page no
1 Power of attorney
2 Whether manufacturer (Yes/No)
If no, whether manufacturer‟s authorization form enclosed as per Section I.
3 Whether experience in past performance on works of similar nature within
the past five years submitted as per Schedule-I of Section-II. (Attach copies of
purchase order and performance certificates)
4 Whether details of current work in hand and other contractual commitments
submitted as per Schedule-II of Section-II. (Attach copies of purchase order)
5 Whether P&L statement and balance sheet and auditor‟s report submitted for
last three years.
6 Whether information regarding current litigation submitted.
7 Is the bidder in business of the jobs tendered for a minimum period of five
years at the time of bid opening? (Attach copy of registration of the firm.)
8 What is the bidders annual financial turn over during last three years?
1st preceding year
2nd
preceding year
3rd
preceding year.
9 Has the bidder completed / having in hand, three projects or above of similar
nature during the last five years.
10 Whether a copy of IT clearance/returns submitted for the previous three years.
11 Whether a copy of valid Sales Tax Registration for the tendered item
submitted.
12 Whether a copy of Sales Tax clearance/returns submitted for the previous three
years.
13 Whether Solvency Certificate equal to three months requirement of cash flow
at the peak execution period for the project submitted.
14 Payment terms accepted (Yes/No).
15 Sealed and signed tender document & specifications in original enclosed
(Yes/No).
16 EMD Details:
DD No…………………. dated ………………. For Rs. ……………..
17 Correspondence address ________________________________________
____________________________________________________________
____________________________________________________________
Ph. No. ……………… Fax No. …………. Mobile No. …………………
Signature of tenderer
11
Rajasthan Co-operative Dairy Federation Limited “Saras Sankul” J.L.N. Marg, Jaipur-302 017
Phone No.2702501 : Fax 2710209 : Website : www.sarasmilkfed.coop : E-mail: [email protected]
No. RCDF/DPM& Proj./(P-2901)/2011-12 Dated 04.01.2012
INDEX
1. SCHEDULE-I PAGE NO.
1.1 SPECIAL NOTES 6-7
1.2 ELIGIBILITY & QUALIFICATIONS CRITERION SHEET 8
1.3 SYNOPSIS OF TENDER 11-12
1.4 GENERAL TERMS & CONDITIONS 13-28
1.5 ANNEXURE – I : Form of Tender for quoting rates.
Part A 29-34
Part B 35-40
1.6 ANNEXURE – II : Form of Bank Guarantee for 30% 41-42
advance payment.
1.7 ANNEXURE – III : Form of agreement required to be 43-45
submitted by the supplier
1.8 ANNEXURE – IV : General terms & conditions which 46-49
will form an integral part of
Purchase Order.
1.9 ANNEXURE – VI : Performa of Bank Guarantee for 50-51
releasing 10% balance payment.
1.10 ANNEXURE – VII : Eligibility & Qualifications Criterion 52-58
2. SCHEDULE – II : Detailed technical specification. 59-155
Sub Section – I : Project Information
Sub Section – II : Basis of Design and Design Data
Sub Section – III : Process Flow Description
Sub Section – IV : Technical Data & Information to be Provided by the Bidder
Sub Section – V : Project Management
Sub Section – VI : Scope of Work
3. SCHEDULE – III : General Terms and Conditions of
Erection Testing & Commissioning 156-195
7. SCHEDULED – IV : Site Layout, Equipment Layout 196-200
and Flow Diagram
8. LAST DATE & TIME OF ISSUE OF TENDER As per NIT published in
newspaper / Website
12
9. LAST DATE & TIMEOF RECEIVING TENDER: As per NIT published in
newspaper / Website
10. DATE & TIME OF OPENING TENDERS As per NIT published in
newspaper / Website
11. ADDRESS FOR COMMUNICATION : As given above
12. PLACE OF OPENING : HEAD OFFICE,
Rajasthan Co-operative Dairy
Federation Ltd,(Purchase Cell)
“Saras Sankul”, J.L.N. Marg,
JAIPUR – 302 017.
9. TENDER ISSUE TO : M/s.____________________,
________________________,
________________________.
13
SYNOPSIS OF THE TENDER
1.0 Purchaser : The Rajasthan Co-operative Dairy Federation Ltd., Jaipur
Saras Sankul, Jawaharlal Nehru Marg, Jaipur
2.0 Contact : Phone No: 0141-2702501-508, Telefax: 0141-2710209, 0141
2702135 Website: www.sarasmilkfed.coop,
E-mail: [email protected]
3.0 Job : “Design, Supply, Installation, Testing and Commissioning of 150
TPD cattle feed plant (expandable up to 300 TPD) on Turnkey
Basis” each at Lambiyankalan District Bhilwara & proposed site
at village Hathalai (Gundoge) District Pali (Raj).
4.0 Exclusions : All Civil works, Workshop Tools & Machines, Sanitary
Installation, Water Disposal, Fire Extinguishers, Water Hydrants ,
Environmental Works, Access Roads, Overhead tank for raw water,
Laboratory Glassware, Chemicals & Equipment, Workshop tools,
furniture, Telephone & Intercom Systems, HT Electricals,
D.G. Sets, Steam generation plant, HP steam piping, PRS, By-
pass protein plant, Water Handling equipment, piping , Water
Softener, Electronic weighbridge
5.0 Eligibility : i. The bidder should have completed/ having in hand at least three
projects of similar nature capacity 150 TPD or above cattle feed
plants in the last five years.
ii. The bidder‟s annual financial turnover in the same name and style
during the last three years shall not be less than Rs. 20 crores in
each year. iii. The bidder should have in house manufacturing setup for the
Cattle Feed plant & machineries and their spare parts.
6.0 Completion : Supply, Erection Testing & Commissioning within Six months 7.0 Automation : Automation scope starts from the dumping of Raw material in Raw material godown and till bagging conveyer 8.0 Payment : For Supply of equipment
30% advance against Bank guarantee 60% after supply of equipment and inspection at site. 10% after completion of job & against performance BG
For Erection & Commissioning
10% advance against Bank guarantee 80 % after erection, commissioning & completion of trial runs 10% after completion of job & against performance BG
14
9.0 Liquidated damages : 0.5% per week beyond the contract period & maximum
upto 5% of the contract value.
10.0 Bid submission : In Two Parts –
Technical Bid in Envelope No. 1 which shall include
i. Earnest Money deposit
ii. All technical details of equipment to be supplied, literature,
job completion certificates, tax clearance / returns filed and
other documents as per the requirements given in the tender
iii. All other qualifying documents
Commercial Bid in Envelope No. 2 which shall include
i. Tender Form ( as given on page) giving full details of prices of
supply and erection including all taxes & duties.
ii. Terms and conditions
iii. Price break up of all the equipment to be supplied as per Annexure - I.
Both Envelopes to be placed in separate envelope clearly Indicating Technical bid & Price bid
11.0 Bid validity : 120 days from the date of opening of bids
15
GENERAL TERMS AND CONDITIONS
PREFACE:
The Rajasthan Co-Operative Dairy Federation Limited, Jaipur hence forth termed as
R.C.D.F. LTD., invites the sealed competitive bids from the technically & financially sound
individual / HUF / firm / Company for “DESIGN, SUPPLY, INSTALLATION, TESTING
AND COMMISSIONING OF 150 TPD CATTLE FEED PLANT (EXPANDABLE UP TO
300 TPD) ON TURNKEY BASIS” EACH AT LAMBIYANKALAN DISTRICT BHILWARA
& PROPOSED SITE AT VILLAGE HATHALAI (GUNDOGE) DISTRICT PALI (RAJ
The Managing Director, Rajasthan Co-operative Dairy Federation reserves the right to reject
any or all the tenders in full or part thereof, which in his opinion justifies such action without
further explanation to the tenderers.
SPECIAL TERMS & CONDITIONS OF TENDER AND CONTRACT:
1. SUBMISSION OF TENDER:
The tenders should be sent by Registered post with acknowledgement due so as to reach the
Managing Director, Rajasthan Co-operative Dairy Federation Ltd., “Saras Sankul”, J.L.N.
Marg, Jaipur-302 017 not later than the time and date mentioned in the NIT published.
Alternatively the tenderers or their agents can also submit their tenders personally at the office
of the Managing Director, Rajasthan Co-operative Dairy Federation Ltd., “Saras Sankul”,
J.L.N. Marg, Jaipur-302 017 and obtain the acknowledgement latest by the time and date
mentioned in the NIT published.
1.1 Technical & Financial bids to be submitted in two separate properly sealed envelopes
marked Technical & Financial as the case may be on the left corner of the envelopes
Tender for “DESIGN, SUPPLY, INSTALLATION, TESTING AND
COMMISSIONING OF 150 TPD CATTLE FEED PLANT (EXPANDABLE UP TO
300 TPD) ON TURNKEY BASIS” EACH AT LAMBIYANKALAN DISTRICT
BHILWARA & PROPOSED SITE AT VILLAGE HATHALAI (GUNDOGE)
DISTRICT PALI (RAJ). The technical bids should contain the DD for EMD and
photocopies of work orders executed by tenderers in the past five year, in absence of
which tender should be technically disqualified. The financial bids should be given in
sealed separate envelope and also marked financial on the envelope. Financial bids
shall be opened only after due evaluation of the technical bids.
1.2 No responsibility shall be taken for premature opening of the tender, which is not
properly addressed and identified.
1.3 The tenderer whose tender is accepted (hereinafter called the supplier/contractor) will
be required to furnish security for the due fulfillment of his contract in the form of a
bank demand draft of 5% of the contracted value (F.O.R. site). This bank Demand Draft
of Nationalized / Scheduled Bank drawn in favour of Managing Director, RCDF Ltd,
Jaipur is to be submitted within a period of 10 to 15 days from the date of placement of
Purchase Order. The EMD amount shall be adjusted in the aforesaid security. No
interest shall be paid for the security money deposit for the period during which it (the
security money) lies in deposit with the RCDF Ltd.
16
In case the contractor/ supplier complete it contractual obligations expect for
performance of equipment for which 10% amount is deducted / retained while
processing payment against supply or erection. The security deposit can be refund at
such point of time as may be decided by the Purchase section at its sole discretion.
All compension or other sums of money payable by the contractor to Rajasthan
Cooperative Dairy Federation Ltd, Jaipur under the terms of this contract may be
deducted from, or paid by the sale of a sufficient part of his security deposit or from
any sums which may be due or may become due to contractor by the Rajasthan
Cooperative Dairy Federation Ltd, on any account whatsoever, and in the event of his
security deposit being reduced by reason of any such deduction or sale as aforesaid,
the contractor shall within ten days thereafter make good in case endorsed as
aforesaid any sum of sums which may have been deducted from or raised by sale of
his security deposit or any part thereof.
1.4 The counter terms & Conditions will not be accepted and as such no additions/
deletions or alternation in the tender form should be done. In such case tender document
may be liable to reject.
1.5 The tenderer shall be deemed to have carefully examined the terms & conditions,
specifications, size, make and drawing etc. In case of any doubts as to the meaning of
any portion of these conditions or of the specification, drawing etc. he shall before
filling the tender form and signing the contract, refer to the competent authority and get
clarifications.
1.6 The tenderer shall, invariably, furnish complete address of the premises of his office,
godown and workshop together with full name and complete address, telephone no.,
FAX no., Mobile no. of the person/s who is to contacted for the purpose. All
correspondence sent on the given address shall be deemed to be properly served.
1.7 The contractor shall not sublet his contract or any substantial part thereof to any other
agency/ person / firm/ establishment.
1.8 The contractor shall have to submit all related formalities in case of firm/ company like
partnership deed / memorandum and articles of association, registration certificate, bank
guarantee, PAN no. etc along with this tender-form. Any change in constitution of the
firm shall be intimated to RCDF Ltd., for approval.
1.9 The tenderer should sign the tender form at each page at the end in token of the
acceptance of all the terms & conditions of the tender.
1.10 The RCDF Ltd., reserves the right to accept any tender and reject any tender in whole or
part without assigning any reason thereof. Order can be placed for whole or part of the
job to the tenderer at the absolute discretion of the RCDF Ltd.
1.11 Any discrepancy in filling the tender/ incomplete tender form shall make the tender
liable to be rejected.
1.12 General Terms & Conditions for contract are annexed with the tender document which
forms as integral part of the contract.
17
2.0 GENERAL TERMS AND CONDITIONS
2.1 The tender thus prepared should be put in properly sealed double cover in two separate
envelopes marking clearly technical bid and financial bid and super scribed giving
the tender reference number and date of opening. The covers should bear address of
Rajasthan Co-operative Dairy Federation, “SARAS SANKUL”, Jawahar Lal Nehru
Marg, JAIPUR – 302017. Only one tender should be kept in cover. In case more than
one tender is kept in a cover, all the tenders thus kept shall be liable to be ignored.
2.2 The tender must be submitted in the three envelopes method as specified in
special notes.
2.3 The tender thus prepared should be put in properly sealed cover and super-
scribed giving the tender reference number and date of opening. The covers
should bear address of Rajasthan Co-operative Dairy Federation Ltd;
Jaipur. Only one tender should be kept in one cover. In case more than one
tender is kept in a cover, all the tenders thus kept shall be liable to be
ignored.
2.4 No responsibility shall be taken for the premature opening of the tender which is
not properly addressed and identified.
2.5 No telegraphic/telephonic/telex/Fax tenders shall be considered. However, any
amendment sent by telegram/telex/Fax to the tender already submitted shall be
considered, provided it is received before the due date and time for opening of the
tender and it is confirmed in writing by post.
2.6 LEGAL COMPETENCY OF SIGNING THE TENDER
Individual signing the tender or other documents connected with this tender must
specify whether he signs as:
a) “Sole Proprietor” of the firm or constituted attorney of such proprietor.
b) The partner of the firm, if it is a partnership firm in which case, he must have
authority to refer to arbitration disputes pertaining to business of the partnership
either by virtue of the partnership deed or by holding the power of attorney.
c) Constituted attorney of the firm, if it is a Company.
NOTE:
1) In case of (b) above, a copy of the partnership deed or general power of attorney duly
attested by a notary public should be furnished or any affidavit on stamp paper of all the
partners admitting execution of the partnership deed or the general power of attorney
should be furnished.
18
2) In case of partnership firms, where no authority to refer disputes concerning to the
business of the partnership has been conferred on any partner, the tender and all other
related documents must be signed by every partner of the firm.
3) A person, signing the tender form or any documents constituting an integral part of the
contract, on behalf of another shall be deemed to warranty that he has authority to bind
such other and if, on enquiry it appears that the person so signing has no authority to do so,
the buyer may without prejudice to other civil remedies, terminate the contract and hold
the signatory liable for all costs and damages.
2.7 EARNEST MONEY DEPOSIT
2.7.1 Earnest money amounting to Rs. 36,00,000/- (Rupees Thirty Six Lacs only) must
accompany the tender. The earnest money shall be required to be paid by a crossed
demand draft in favour of Managing Director, Rajasthan Co-operative Dairy Federation
Ltd., drawn on any scheduled or Nationalized bank in India, payable at Jaipur. The
tenders accompanied by cheques instead of demand draft towards earnest money will
not be considered. Earnest money shall have to be paid according to the items offered
by tenderers covering the total quantity required for all the projects.
2.7.2 Any tender which is not accompanied by earnest money deposit will be summarily
rejected. Earnest money of unsuccessful tenderer will be returned within 120 clear days
from the date of opening of the tender.
2.7.3 No interest shall be paid for the earnest money deposit for the period during which it
(the earnest money) lies in deposit with the Rajasthan Co-operative Dairy Federation
Ltd.
2.8 The tenderers should state herein the complete address to which the orders, notices and
further correspondence pertaining to the tender and agreements are to be sent. Any
correspondence made by the RCDF/milk union at the address given herein shall be
deemed to have been delivered to the party notwithstanding that such correspondence
may not in fact have been delivered. Any change in the address thereafter must be
notified to the Managing Director, Rajasthan Co-operative Dairy Federation Ltd., Jaipur
and the concerned milk unions and a copy in confirmation of RCDF/milk union having
recorded change in address be obtained in writing from RCDF/milk union. In absence
of such confirmation the correspondence made on the address given herein shall be
valid once the confirmation is issued by RCDF/milk union subsequent correspondence
shall be sent to the new notified address.
Address_______________________ Telegraphic Address_________________
_____________________________
Phone No./ _________________________
Mobile no.____________ Fax No.__________ E-mail________________
Name of contact Person:_______________________.
19
2.9 The tenders received shall be opened on the date and time given in the N.I.T. at the
Office of the Managing Director, Rajasthan Co-operative Dairy Federation Ltd., Jaipur.
The tenderers or their accredited agents will be allowed to be present at the time of
opening of the tender.
2.10 Negligence on the part of tenderer in preparing the tender confers no right to withdraw
the tender after it has been opened.
2.11 The specifications, conditions, schedules drawing of the tender constitute an integral
part of the tender.
2.12 All tenders in which any of the prescribed conditions are not fulfilled or which have
been vitiated by errors in calculations totaling, or other discrepancies or which contain
overwriting in figures or words or corrections not initialed and dated will be rejected.
2.13 In the place of substantial non conformity with the specifications or if it contains any
inadmissible reservations seen or otherwise, in contravention to the sprit and latter of
the tender documents, such tenders shall be summarily rejected.
All compensation or other sums of money payable by the contractor to Rajasthan Co-
operative Dairy Federation Ltd. under the terms of this contract may be deducted from, or paid
by the sale of a sufficient part of his security deposit or from any sums which may be due or
may become due to the contractor by the Rajasthan Co-operative Dairy Federation Ltd. on any
account whatsoever, and in the event of his security deposit being reduced by reason of any
such deduction or sale as aforesaid, the contractor shall within ten days thereafter make good in
cash endorsed as aforesaid any sum or sums which may have been deducted from or raised by
sale of his security deposit or any part thereof.
2.14 No refund of tender fee is claimable for tenders not accepted or Forms returned or
tenders not submitted.
1.0 SCOPE OF TENDER.
3.1 Supply :
1. The scope of this tender shall include only the design, fabrication, supply, erection,
testing & commissioning of the cattle feed manufacturing plant required for producing
150 Tons per day balanced cattle feed with a provision to expand the plant to 300 TPD.
The equipment shall include mainly intake conveyors, storage bins, auto batching,
grinding, molasses storage tanks, silos, mineral mix plant, molasses mixing, pelleting,
bagging, aspiration systems, air compressor and LT electrical. The scope of the bidder
shall necessarily include the supply as well as erection and commissioning. Any bid for
part job will be summarily rejected.
2. The plant will be installed on the fabricated MS structure and covered with the pre-
coated sheets and fitted with lighting and lightening arrestor by the bidder.
3. All the civil works, foundations, water, steam, molasses and electrical power shall be
provided by the Rajasthan Cooperative Dairy Federation Ltd., Jaipur.
4. The Tenderer shall be responsible for developing the conceptual layout and flow
diagram to ensure automatic operation of the plant with minimum investment.
5. Since this will be Turnkey Job it will be the full responsibility of the Tenderer to carry
20
out all minor works necessary to achieve the rated capacity of the plant even though
they might not have been expressly mentioned in the tender document.
6. All the equipment to be supplied will have to be manufactured as per the standard
specifications adopted by the cattle feed industry in the country.
7. This contract will be “Fixed Rate Contract” and the contractor will have to supply the
equipment and complete the erection and commissioning within the agreed contract
value and no escalation of prices will be allowed.
8. It is absolutely essential to complete the job of design, fabrication, supply, erection and
commissioning of cattle feed plant within six months from the date of signing the
contract and receipt of advance.
9. The tenderer is advised to visit to site so as to apprise himself of actual site condition
and quantum of work involved. Civil work at site already commenced and tenderer
should plan with consideration of actual site condition.
3.1.1 Erection, Testing & Commissioning:
The tenders shall erect/install the equipment in accordance with the General terms &
Conditions, special terms and conditions, specifications stipulated in Schedules of the tender.
4.0 TURN – KEY CONTRACT This is a turn - key project. All necessary material which may be required for the successful completion of the project falls in the scope of the work. Cost of installation for any addition or deletion in quantities will be calculated based on the unit prices indicated. If any extra quantities of quoted items are needed then the tenderer shall supply those at the quoted unit price. If any extra item (s), not included in the tender but required for successful completion of the work, the same will be either supplied by the RCDF/Milk Union and erected by the tenderer or supplied and erected both by the tenderer at mutually agreed rates considering purchase price, taxes and handling charges etc. Necessary ESI/PF deductions, wherever applicable shall be borne by the tenderer.
The requisite approval form Chief Electrical Inspectorate, Government of Rajasthan must be
obtained by the tenderer and the actual payment shall be reimbursed by RCDF/Milk Union
against production of original documents.
The tenderers are required to give the price bid for all items section-wise in the same faction as
of Part – A showing the F.O.R. unit rate for supply as well F.O.R. unit rate installation, testing
& commissioning as well the total cost.
In addition to the standers mentioned, all works shall also conform to the requirements of the
following for which necessary certifications of the concerned departments are to be obtained
and submitted to the concerned Milk Union/RCDF:-
a. Indian Electricity Act and rules framed there under.
b. Fire, Insurance and Regulations Act.
c. Regulations laid down by the Chief Electrical Inspector of the State/State Electricity
Board.
21
d. Regulations laid down by the Chief Inspector of the Factories & Boilers of the State.
e. Regulations laid down under the Explosive Act.
f. Regulations as per Weight and Measure Act.
g. Pollution Control Board of Rajasthan.
h. Bureau of Indian Standards
i. Any other regulations laid down by the local authorities.
Applications under various Acts should be moved through MD, Union well in advance so that
operation of the plant could be started as per rules and regulations from the day one after
handing over the plant. However, actual fee and other charges deposited with the government
authorities will be reimbursed to the Contractor after production of receipt.
5.0 BID PRICES
5.1 The price should be quoted on the basis of F.O.R. site inclusive of all taxes. All taxes are to
be built up in the financial bid part as on 09.02.2012 and are to be shown separately. Any
addition/deletion/variation in taxation or future taxes leveled by the State or Central Govt.
beyond this date shall be born by RCDF/Concerned Unions. It should be absolutely clear
that any tax applicable as on 09.02.2012 but not considered by the tenderer while
submitting financial bid shall be deemed to have included in the rate offered by the
tenderer.
The bidder shall quote for the total package of Design, Fabrication, Supply, Erection,
Testing & Commissioning on the Turn key basis. The prices quoted under different heads
should be grouped as under. Supply - Including packing, forwarding, taxes & duties, freight, loading & unloading at site
and insurance etc. Detailed price break and list of equipment as given under Annexure – I
should be submitted in Commercial Bid, i.e. Envelope – 2 Erection & commissioning – Labour charges including service tax should be given for all the
equipment and the steel structure as per the list given under Annexure – I should be submitted
in Commercial Bid, Envelope - 2 Discount if any should also be indicated separately. The bidders‟ separation of price
components as above will be solely for the purpose of facilitating the comparison of bids by the
purchaser and will not in any way limit the purchasers right to contract on any of the terms
offered.
5.2 FIXED PRICE:
Prices quoted by the bidder shall be fixed during the bidder‟s performance of the contract and not subject to variation on any account .
5.3 PRICE OF SPARE PARTS:
All the bidders are required to submit the list of spares with rates. In case of bought out
22
items a list giving full particulars, including available sources and current prices, of all
spare parts, special tools, etc. which are necessary for the proper and continuing
functioning of the plant for a period of two years should be furnished. These prices should
be valid, for acceptance by the purchaser and placement of orders, for one year from the
date of bid opening.
5.4 The prices thus quoted by firm, free from all escalations and valid for a period of 120 clear
days from the closing date of the tender.
5.5 All the tenderers should quote for supply of equipment in fully fabricated and
assembled condition.
5.6 BREAK – UP PRICES All the bidders shall furnish the cost separately for the supply and
installation/commissioning along with detailed cost break-up (item-wise), which will be
applicable for progressive payments. Items and works for which no break-up price is
furnished by the bidder will not be paid for by the purchaser when supplied/executed and
shall be deemed covered by other break-up prices. Such break up cost should be based on
ex-works cost and percentage of ex-works cost should be indicated separately for packing
and forwarding, transportation, insurance and other incidental charges, erection and
commissioning on percentage basis for each item.
5.7 Sales Tax/Entry Tax :
The Sales Tax, Entry Tax, Surcharge and any other type of taxes prevailing upto date of
submission of the rates must be included in the net rate. This however should be shown
separately, so that in the event of any subsequent change in these charges by the Government
(State or Central), the same will be considered for increase/decrease over the net rates.
Wherever possible C/D forms shall be issued to avail concessional rates of the Central/State
Tax. The Entry Tax, if applicable, should be included where the supplier belongs to outside
Rajasthan and Purchase Order/RAL placed on outside Rajasthan. The tenderer must also
indicate the details of Sales Tax Registration and the number allotted to them by Sales Tax
authorities.
5.8 Octroi :
Octroi duty, if applicable at the destination shall be paid extra on all dispatches made from
the suppliers works/warehouses to the point of destination.
5.9 Excise Duty :
Excise duty or surcharge prevailing upto the date of submission of the rates must be included
in the net rate. This however, should be shown separately, so that in the event of any
subsequent change in these charges by the Government (State or Central), the same will be
considered for increase/decrease over the net rates. However, the increased excise duty due
to change in slab on higher turnover shall be payable by the tenderer.
23
5.10 Service Tax:
The Service Tax and Surcharge prevailing upto date of submission of the rates must be
included in the net rate. This however should be shown separately, so that in the event of any
subsequent change in these charges by the Government (State or Central), the same will be
considered for increase/decrease over the net rates.
5.11 Unloading charges at site –
For supply order the price should exclude unloading charges. However for installation
contract the price must include these charges.
5.12 If the price for reasons of change in statutory taxes and duties by Government taking place
during the period of bid finalisation or during the normal delivery period envisaged in the
Purchase Order/Contract.
6.0 (a) The material/equipment/machinery offered must be securely packed at the cost of the
suppliers to withstand tough handling enroute by road/rail/air. Packing should be
provided with protective lining to avoid damage to the surface of the packing and the
items packed inside.
(b) Marking :
Each package delivered under this tender shall be marked by the suppliers at their own
expenses. Such markings shall be distinct and should bear the following:
(i) Name of the supplier.
(ii) Details of the items in the package.
(iii) Weight gross, net and tare.
(iv) Name and address of the consignees as mentioned in the Purchase Order.
Marking shall be carried out with such a material as may be considered necessary as
regards quickness of drying, fastness and indelibility.
7.0 Insurance :-
The supplier shall arrange insurance coverage, according to the dispatch instructions
issued by Rajasthan Co-operative Dairy Federation Ltd., Jaipur and the supplier should
cover all dispatches. However, to avoid any complications that may arise at the time of
settlement of claims by the underwriters for the transit losses it is proposed that the
insurance coverage shall be arranged by the supplier as under :
(a) The insurance coverage shall have to be arranged commencing from their
warehouse/works to the warehouse of the buyer (All Transit risks).
(b) Suppliers are requested to take insurance with any Nationalised Insurance
Company.
(c) The cover provided by the insurance shall be in such amount so as to allow
complete replacement for any item lost or damaged.
24
8.0 Guarantee :-
The supply of equipment as well as installation, if entrusted shall have to be carried out by the
supplier to the entire satisfaction of the buyer. The supplier shall also guarantee to
repair/replace without any extra cost, the items or parts there of if found defective due to
defective design, workmanship or substandard material brought to the attention within 12
calendar months from the date of satisfactory commissioning or within 24 months from the
date of receipt of material at site, whichever is earlier. If it is necessary to send the defective
equipment or parts thereof for repair/replacement the cost of loading, unloading, repacking
and transportation from the site to works and back to site shall have to be borne by the
supplier. The guarantee however does not cover any damage resulting from normal wear and
tear or improper attendance or mishandling of the equipment by the buyer/his authorised
representatives.
The contractor shall have to guarantee the complete installation for satisfactory performance
for a minimum period of one year from the date of commissioning of the plant. Any defect
arising out of faulty erection/installation or use of substandard material or workmanship shall
have to be rectified by the contractor at his own cost.
8.1 Warranty :
All the suppliers shall provide a warranty for a minimum period of 12 months from the date
of commissioning of the equipment for the satisfactory performance of the equipment
supplied to the designed/rated/installed capacity or any other norms fixed by the buyer.
Also, they should provide a warranty for the period as stated above to the effect that
supplier shall alone be responsible for all the litigations/disputes/claims and other legal
complications that may arise in connection with the patent rights design rights and the
rights of ownership of the materials.
8.2 Right to operate & use unsatisfactory material or equipment :
If after delivery, acceptance and installations and within the guarantee period, the operation
of use of materials or equipment proves to be unsatisfactory to the buyer, he shall have the
right to continue to operate or use such materials or equipment until rectifications of defect,
errors or omissions by repair or by partial replacement can be made without interfering with
the buyer‟s operation.
9.0 Terms of Payment :
Following terms of payment would be applicable to this order subject to supplier/ contractor
having furnished security deposit for 5% of the F.O.R. order value for the due fulfillment of
this contract in form of cash/DD in accordance with the Clause No.1.3 of the tender
document. In case the contractor/supplier completes its contractual obligations before 12
months the cash/DD deposit can be refunded before 12 months at the sole discretion of RCDF
before aforesaid period of 12 months.
25
9.1 For supply of material :-
30% of the ex-works order value (basic cost) shall be paid on acceptance of the order subject
to the supplier furnishing a Bank Guarantee valid for 12 calendar months from the date of
guarantee for an equivalent amount from a scheduled or Nationalised Bank in the enclosed
proforma given at Annexure-II. The Bank Guarantee can be released by RCDF once the
advance is fully recovered/adjusted. The execution of agreement in the format at Annexure-
III is also a precondition for clearing advance.
60% (90% in case of the supplier/contractor who has not taken advance) on safe receipt of
the equipment ordered at site but not later than 45 days from the date of receipt of the
equipment at site.
The 10% of the FOR site value shall be paid within 12 calendar months from the date of
commissioning or 24 months from the date of receipt of the same at site, whichever is
earlier. However the balance 10% will also be released, if so desired by the supplier,
provided the supplier furnishes a Bank Guarantee from a Scheduled or Nationalised Bank for
the 10% value valid for a period of 12 calendar months from the date of issue of Bank
Guarantee in the proforma enclosed.
9.2 For Erection :-
90% on submission of progressive bills duly certified by the authorised representatives/Site
Engineer of RCDF and balance 10% within 12 months from satisfactory commissioning of
the equipment. However, the balance 10% will also be released, if so desired by the supplier,
provided the supplier furnishes a Bank Guarantee from a Scheduled or Nationalised Bank for
the 10% value valid for a period of 12 calendar months from the date of issue of Bank
Guarantee in the proforma enclosed.
10.0 DELIVERY SCHEDULE OF ITEMS
(a) Bidders should submit a detailed item wise delivery schedule keeping in view the
completion period of the contract. Such items shall be grouped under monthly
delivery schedule with total value of such items. This will facilitate for ensuring the
cash flow requirement for the project.
(b) The delivery time given in the contract is to be adhered to strictly. For this purpose the
supplier has to inform RCDF the progress made towards fabrication of the items ordered
from time to time during the delivery period. The supplier has to maintain good
progress of work during the delivery period so as to deliver the items ordered in time. It
is essential that RCDF is informed of the quantified progress made by the supplier by
Registered Post once after 1/3rd
of delivery time elapses and again after 2/3rd
of
delivery time elapses. In case RCDF does not receive such progress reports it will
presume that the work has not been taken up by the supplier in the right earnest and that
RCDF in such a situation will be at liberty to withdraw the work order and forfeit the
earnest money as well as security deposit simultaneously. The supplier is therefore
advised strictly to follow this essential condition of the contract.
26
(c) It may be noted that delay/time taken in release of advance payment whether for
reasons of supplier not furnishing the Bank Guarantee exactly in the proforma given
in this tender document or any other reasons whatsoever, will not affect the
delivery period. Similarly delay in execution of the agreement will also not affect the
delivery period. The tenderer is therefore advised to take note of this important
condition. The successful tenderer should therefore take immediate action for execution
of agreement and submission of bank guarantee of advance, if desired, within 10 to 15
days of placement of purchase order. It normally takes 30 days to release the advance,
subject to submission of B.G. as per our format.
(d) In case of failure by supplier in making deliveries within the time specified, the
Rajasthan Co-operative Dairy Federation Ltd. may procure the materials supplies and
services from any other sources and hold the suppliers responsible for any losses
occurred thereby. Further the Rajasthan Co-operative Dairy Federation Ltd. reserves the
right to terminate the services of such suppliers in such case without assigning any
reasons thereof.
(e) In case supplier fails to supply machinery/equipment in delivery period, interest at the
rate of 19% per annum will be charged on the advance amount from the date by which
delivery fails due to the actual date of supply unless an extension in delivery period is
mutually agreed to by the supplier and RCDF.
11.0 Completion of work :
The entire job of “DESIGN, SUPPLY, INSTALLATION, TESTING AND
COMMISSIONING OF 150 TPD CATTLE FEED PLANT (EXPANDABLE UP TO
300 TPD) ON TURNKEY BASIS” EACH AT LAMBIYANKALAN DISTRICT
BHILWARA & PROPOSED SITE AT VILLAGE HATHALAI (GUNDOGE)
DISTRICT PALI (RAJ).
is to be completed within 6 months from the date of issuing the work order.
It may be noted that delay/time taken in release of advance payment whether for
reasons of supplier not furnishing the Bank Guarantee exactly in the proforma given in
this tender document or any other reasons whatsoever, will not affect the completion
period. Similarly delay in execution of the agreement will also not affect the completion
period. The tenderer is therefore advised to take note of this important condition. The
successful tenderer should therefore take immediate action for execution of agreement
and submission of bank guarantee of advance, if desired, within 10 to 15 days of
placement of purchase order.
In case of failure by contractor in completing the job within the time specified, the
Rajasthan Co-operative Dairy Federation Ltd. Will have liberty to get the job completed
from any other sources and hold the contractor responsible for any losses occurred
thereby. Further the Rajasthan Co-operative Dairy Federation Ltd. reserves the right to
terminate the services of such contractor in such case without assigning any reasons
thereof.
27
12.0 Compensation for delay :
Clause 1 : The time allowed for carrying out the work as entered in the tender shall be strictly
observed by the contractor and shall be reckoned from the 15th
day after the date of
written order to commence the work as given to the contractor. The work shall
throughout the stipulated period of the contract be proceeded with all due diligence,
time being deemed to be the essence of the contract on the part of the contractor and the
contractor shall pay as compensation an amount equal to half percent or such smaller
amount as the Managing Director, RCDF Ltd. (whose decision shall be final) may
decide on the tendered amount for every week that the work remains un-commenced or
unfinished after the proper date subject to a maximum of 5% of the net value of the
accepted order which remains unexecuted or partially executed.
Clause 2 :-
The Managing Director, RCDF Ltd. may without prejudice to his right against the
contractor in respect of any delay or inferior workmanship or otherwise or any claims
for damage in respect of any breaches of the contract and without prejudice to any
rights or remedies under any provisions of this contract or otherwise and whether the
date for completion has or has not elapsed by notice in writing absolutely determine the
contract in any of the following cases :-
(i) If the contractor having been given by the Officer-in-charge or authorised representative,
a notice in writing to rectify, reconstruct or replace any defective work or that the work is
being performed in an inefficient or otherwise improper or unworkman like manner shall
omit to comply with the requirements of such notice for a period of seven days thereafter
or if the contractor shall delay or suspend the execution of the work so that either in the
judgment of the Officer-in-charge or authorised Engineer (which shall be final and
binding) he will be unable to secure completion or he has already failed to complete the
work by that date.
(ii) If the contractor being a company shall pass a resolution or the court shall make an order
that the company shall be wound up or if a receiver or a manager on behalf of a creditor
shall be appointed or if circumstance shall arise which entitle the court or creditor to
appoint a receiver or a manager or which entitle the court to make a winding up order.
(iii) If the contractor commits breach of any of the terms and conditions of the contract.
(iv) If the contractor commits any acts mentioned in clause 19 hereof.
When the contractor has made himself liable for action under any of the cases aforesaid,
the Managing Director, Rajasthan Co-operative Dairy Federation Ltd. shall have powers :-
a. To determine or rescind the contract as aforesaid (of which termination or rescission
notice in writing to the contractor under the hand of the Managing Director, RCDF Ltd.
shall be conclusive evidence). Upon such determination or rescission the full security
28
deposit of the contractor calculated on the tendered amount shall be liable to be forfeited
and shall absolutely be at the disposal of Rajasthan Co-operative Dairy Federation Ltd.
b. To employ labour paid by the Federation and to supply materials to carry out the work or
any part of the work debiting the contractor with the cost of the labour and the price of the
materials (of the amount of which cost and price certified by the Officer-in-charge shall
be final and conclusive) and crediting him with the value of the work done in all respects
in the same manner and at the same rates as if it has been carried out by the contractor
under the terms of his contract. The certificate of the Officer-in-charge as to the value of
work done shall be final and conclusive against the contractor provided always that action
under the sub-clause shall only be taken after giving notice in writing to the contractor.
Provided also that if the expenses incurred by the Federation are less than the amount
payable to the contractor at his agreement rates, the difference shall not be payable to the
contractor.
c. After giving notice to the contractors on measure up the work of the contractor and to
take such part there of as shall be unexecuted out of his hands and to give it to another
contractor to complete in which case any expenses which may be incurred in excess of the
sum which would have been paid to the original contractor if the whole work had been
executed by him (of the amount of which excess, the certificate in writing of the Officer-
in-charge shall be final and conclusive) shall be borne and paid by the original contractor
and may be deducted from any money due to him by Rajasthan Co-operative Dairy
Federation Ltd. under this contract or on any other account whatsoever or from his
security deposit or the proceeds of sales thereof or a sufficient part thereof as the case
may be.
In the event of any one or more of the above courses as may be deemed best suited to
the interest of the Federation being adopted by the Managing Director, Rajasthan Co-operative
Dairy Federation Ltd., the contractor shall have no claim to compensation for any loss
sustained by him by reason of his having purchased or procured by him by reason of his having
purchased or procured any materials or entered into any engagements, or made any advances
on account of or with a view to execution of the work or the performance of the contract. And
in case action is taken under any of the provisions aforesaid, the contractor shall not be entitled
to recover or be paid any sum for any work there for actually performed under this contract
unless and until the Officer-in-charge has certified in writing the performance of such work and
the value payable in respect thereof and he shall only be entitled to be paid the value as
certified.
Contractor remains liable to pay compensation if action not taken under Clause 3.
Clause 3 :-
In any case in which any of the powers conferred by Clause 3 hereof shall have become
exercisable and the same shall have not been exercised, the non-exercise thereof shall not
constitute waiver of any of the conditions hereof, and such power shall notwithstanding be
exercisable in the event of any future case of default the contractor for which by any clause or
clauses hereof he is declared the contractor for which by any clause or clauses hereof he is
declared liable to pay compensation amounting to the whole of his security deposit and the
liability of the contractor for past and future compensation shall remain unaffected.
29
13.0 Force Majeure Clause :-
The terms and conditions mutually agreed shall be subject to the Force Majeure Clause. Neither
the supplier nor the buyer shall be considered in default in performance of its obligations
hereunder, if such performance is prevented or delayed because of war, hostilities, revolutions,
civil commotion, strike, epidemic, accident, fire, wind, flood, earthquake or because of any
law, order, proclamation, regulation, or ordinance of any Government or any act of God or any
other cause whether of similar or dissimilar nature, beyond the reasonable control of the party
affected should one or both of the parties be prevented from fulfilling his/their contractual
obligations by a state of Force Majeure lasting continuously for a period of six months, the two
parties should consult with each other regarding the future implementation of the
agreement/purchase order.
14.0 Settlement of disputes :
In the event of any dispute in the interpretation of the terms of this agreement/ Purchase Order
or difference of opinion between the parties on any point in the Purchase Order arising out of,
or in connection with the agreement/accepted purchase order or with regard to performance of
any obligations hereunder by the either party, the parties hereto shall use their best efforts to
settle such disputes or difference of opinion amicable by mutual negotiations.
In case, no agreement is reached between the two parties in respect of or concerning any of the
provisions herein contained or arising out of this supply order/ tender/ agreement as to the
rights, liabilities or duties of the said parties hereunder or as to the recovery of any amount, the
same shall be referred to the Sole Arbitrator M.D., RCDF who in turn may refer the dispute to
any officer of RCDF for adjudication. The arbitration shall be in accordance to the law of
Arbitration & Conciliation Act, 1996. The decision of the Sole Arbitrator shall be final and
binding on both the parties.
All the disputes pertaining to the said contract shall vest to the jurisdiction of Courts at Jaipur.
15.0 Right to Acceptance:
The Rajasthan Co-operative Dairy Federation Ltd. Does not pledge itself to accept the lowest or
any tender and reserves to itself the right to accept the whole or any part of the tender or portion
of the quantity offered. The tenderer is at liberty to tender for whole or any portion or to state
in the tender that the rates quoted shall apply only if the entire quantity is taken from them.
16.0 IMPORTANT NOTES :
16.1 TIMELY DELIVERY, OF SPECIFIED QUALITY OF MATERIAL, PLANT &
MACHINERY SATISFYING ALL DESIGN AND FUNCTIONAL
REQUIREMENTS ORDERED, IS THE ESSENCE OF THE CONTRACT.
THEREFORE, FAILURE TO DELIVER IN TIME OR NOT CONFORMING TO
PRESCRIBED SPECIFICATIONS & QUALITY WILL MAKE THE SUPPLIER
LIABLE FOR BLACKLISTING THE FIRM AND THEREBY DEBARRING
THE SUPPLIER FROM PARTICIPATION IN FUTURE TENDERS BY RCDF,
MILK UNIONS & OTHER AFFILIATED UNITS. AS FOR THE PRESENT
30
CONTRACT PENALTIES, COMPENSATION AND OTHER PROVISIONS AS
GIVEN IN THE TENDER DOCUMENT SHALL BE INVOKED ON FAILURE
OF THE PARTY.
16.2 RCDF and milk unions shall have the fullest liberty to notify the defaulting firm to
Business/Trade Associations/Public Sector undertakings/autonomous bodies and the like
about the default and breach of contract committed by a firm giving out names of the
partners of the firm. A register is intended to be maintained for such defaulting firms and
their partners.
16.3 RCDF will not consider the tender of such firms who has earlier been
debarred/censured/black listed or even those firms who have on their role key
employees/ key executives/ proprietors/ partners of another already debarred/censured/
black listed firms in one or the other capacity.
16.4 All the tenderers without fail, should furnish full technical details about tendered
project.
1.1 The quantities mentioned in the tender are tentative and the actual quantities to be
procured may vary upward or downward suiting to the actual requirements.
18.0 Supplier will execute agreement on non-judicial stamp paper of Rs.100/- (Rupees
One Hundred only) before 30% advance can be released to him. Format of the
agreement is given at Annexure-III.
19.0 If the Managing Director shall at any time, and for any reasons whatever, think
any portion of the work should not be executed or should be withdrawn from the
contractor he may, by notice in writing to that effect, require the contractor not to
execute the portion of the work specified in the notice or may withdraw from the
contractor the portion of the work so specified and the contractor shall not be
entitled to any compensation by reason of such portion of the work having been
executed by him, and the value (i.e. cost at tendered rates) of the portion of work so
omitted or withdrawn shall in cases where the contractor has for any reason already
received payment for it or in the cases of lump-sum contracts be deducted from any
sum them due or thereafter to become due under the contract or otherwise against
or from the security deposit or the proceeds of sale thereof.
20.0 No term or condition in addition to those mentioned above will be agreed to.
31
ANNEXURE-I (Part – A)
CFP LAMBIYAKALAN DISTRICT BHILWARA
FORM OF TENDER FOR PRICE FOR (TO BE SUBMITTED IN FINANCIAL BID ENVELOPE)
Time & Date of opening of Tender :
Description of goods :
S.No. Particulars Amount (Rs.) Remarks, if any.
1. Design & supply charges for 150 TPD Cattle
Feed Plant (Expandable upto 300 TPD
equipment and utilities as per the technical
specification & drawings enclosed.
2. Packing & forwarding charges
3. Excise Duty @______
4. Sales Tax (RST/CST/VAT) @______ (see note
no.1given below)
5. Entry Tax if any @________
6. Transportation including Insurance charges
7. Any other charges (if any)
8. Total FOR site price (1 to 7)
9. Installation, testing & commissioning charges for
150 TPD Cattle Feed Plant (Expandable upto
300 TPD equipment and utilities as per the
technical specification & drawings enclosed.
10. Service Tax @_____
11. Total FOR Unit Price (9 to 10)
12. Total Net FOR Unit Price for supply, installation &
commissioning (8+11)
(in figures and in words)
*The FOR rates indicated at sr. no. 8, 11 & 12 includes all duties & taxes even if not
explicitly mentioned here but in vogue/applicable at the time furnishing rates.
Note :
(i) Tenderer should indicate clearly whether the sales tax mentioned above is against any concessional
form. In case the concessional form is not provided, the rate of tax should be mentioned.
(ii) Price negotiations shall be discouraged bidders should therefore quote their most competitive rates
(with conformity to the specifications and commercial stipulations given in the tender) in the very
instance least they run the risk of losing out in absence of negotiations.
(iii) The rate must be written both in words and figures. There should be no erasures and or over
writings, corrections, if any, should be made clearly and initiated with date. In case if there is
variation observed in the rates in between words & figures, the lowest rate shall be considered.
(iv) The conditional offer which affect the rate of the quoted item shall be liable for rejection even
the quoted rate is lowest.
(Signed & sealed by the tenderer
in token of acceptance of above)
32
ANNEXURE – I (Part – A)
CFP LAMBIYAKALAN DISTRICT BHILWARA
PART 1. : DESIGN, FABRICATION, SUPPLY OF MAJOR EQUIPMENTS, FOR 150 TPD
CATTLE FEED PLANT (EXPANDABLE UP TO 300 TPD) ON TURNKEY BASIS.
LIST OF MAJOR EQUIPMENT
S.
No.
Description Capacity/Size
(cm=Cubic
Meter)
Quantity Unit Price
Rs.
Amount
Rs.
1 RAW MATERIALS STORAGE EQUIPMENTS
1.01 Silo System for DORB/Grain Storage with
handling & Transferring system. 500 MT
2
1.02 Complete Unloading, Cleaning System of 50
TPH with Three Truck at a time and Shed 50 TPH 1
2 RAW MATERIALS INTAKE EQUIPMENT
2.01 INTAKE CHAIN CONVEYOR IN RMG
WITH PNEUMATIC SLIDE GATES 40TPH 55RM 2
2.02 DUMPING HOPPERS FOR INTAKE
CONVEYORS IN RMG 2 M x 1 M 10
2.03 ASPIRATION UNIT FOR DUMP HOPPERS
IN RMG -- 10
2.04 ELEVATOR FOR BATCH PRE-MIXER 10 TPH 1
2.05 HOPPER ABOVE BATCH MIXER WITH
PN. GATE 1 MT 1
2.06 BATCH MIXER FOR PREMIX DUTY WITH
PNEUMATIC OUTLET GATE 1 MT 1
2.07 HOPPER BELOW BATCH MIXER 1 MT 1
2.08 ELECTRONIC PLATFORM WEIGHSCALE 200 KGS 2
2.09 PORTABLE BAG STACK CONVEYORS 250 BAGS/HR;
10 M 3
2.10 INTAKE BUCKET ELEVATOR 40 TPH 2
2.11 ASPIRATION UNITS FOR INTAKE
ELEVATORS -- 2
2.12 CASCADE MAGNET 40 TPH 2
2.13 JUTE TWINE REMOVER 40 TPH 2
2.14 CROSS CONVEYOR 40 TPH 1
2.15 DISTRIBUTION CONVEYORS 40 TPH 2
3 BATCHING EQUIPMENT
3.01 PROPORTIONATE BIN WITH OUTLET
GATE 20 MT 16
3.02 ASPIRATION UNITS FOR
PROPORTIONATE BINS 1 SET
3.03 GRAVITY FEEDERS FOR BIN DISCHARGE 16
3.04 REDLER CHAIN CONVRYOR FOR BIN
DISCHARGE 250 MM 16
3.05 BATCH WEIGH HOPPER ( MAJOR 3 MT 1
33
INGREDIENTS)
3.06 BATCH WEIGH HOPPER(MINOR INGREDIENTS) 1 MT 1
3.07 PNEUMATIC GATE BELOW WEIGH
HOPPER -- 2
3.08 SURGE HOPPER BELOW BATCH
WEIGHER -- 2
3.09 BATCH CHAIN CONVEYOR 30 TPH 1
3.10 BATCH BUCKET ELEVATOR 30 TPH 1
3.11 ASPIRATION UNITS FOR BATCH
ELEVATOR -- 1
4 GRINDING, MIXING EQUIPMENT
4.01 GRINDING BIN WITH PN. GATE 3 MT 2
4.02 FEEDER ABOVE HAMMER MILL 15 TPH 2
4.03 HAMMER MILL WITH 6 or 8 MM SIEVE 15 TPH 2
4.04 HOPPER BELOW HAMMER MILLS -- 2
4.05 ASPIRATION UNIT FOR HAMMER MILLS -- 2
4.06 BIN ABOVE BATCH MIXER 3 MT 2
4.07 PNEUMATIC GATE ABOVE BATCH
MIXER -- 1 SET
4.08 BATCH MIXER ( RIBBON TYPE) 3 MT 1
4.09 PNEUMATIC GATE BELOW BATCH
MIXER -- 1 SET
4.10 HOPPER BELOW BATCH MIXER 10 MT 1
4.11 CONVEYOR BELOW MIXER 30 TPH 1
4.12 MIXED FEED ELEVATOR 30 TPH 1
4.13 ASPIRATION UNIT FOR MIXED FEED
ELEVATOR -- 1 1
5 PELLETTING EQUIPMENT
5.01 MIXED FEED TRANSFER ELEVATOR
WITH OUTLET CASCAD MAGNET. 30 TPH 1
5.02 PELLETING BIN WITH BIN ACTIVATOR 10 MT 1
5.03 VARIABLE SPEED LOSS IN WEIGHT
FEEDER WITH HOPPER 10 TPH 1
5.04 PELLET MILL WITH CONDITIONER AND
MOLASSES MIXER 10 TPH 1
5.05 ROTARY AIR LOCK FOR PELLET COOLER 10PH 1
5.06 COUNTER CURRENT PELLET COOLER 10 TPH 1
5.07 PELLET COOLER CYCLONE (SS 304) WITH
PN.HAMMERS. -- 1
5.08 ROTARY AIR LOCK FOR CYCLONE (SS ) 10 TPH 1
5.09 PELLET COOLER FAN -- 1
5.10 ASPIRATION DUCTING FOR PELLET
COOLER (SS 304) -- 1 SETS
5.11 PELLET ELEVATOR 30 TPH 1
5.12 PELLET SIEVE 30 TPH 2
34
5.13 SPARE MOTOR FOR PALLET MILL -- 1
5.14 SPARE MOTOR FOR CYCLONE BLOWER -- 1
6 MOLASSES STORAGE / HANDLING EQUIPMENT
6.01 Molasses Storage Tank 400 MT 2
6.02 MOLASSES UNLOADING TANK (WITH
HOSE)
6.03 MOLASSES UNLOADING PUMP (1 Working
+ 1 Standby) 15 KLPH 2
6.04 MOLASSES PRE-HEATER 1 1
6.05 MOLASSES FEEDING PUMP (1 Working + 1
Standby) 3 KLPH 2
6.06 MOLASSES FLOW METER 3 KLPH 1
6.07 MOLASSES PIPING, CONTROL
VALVES,FITTINGS -- 1 LOT
7 BAGGING EQUIPMENT
7.01 BAGGING BIN (SS LINED) 20 MT 2
7.02 PNEUMATIC SLIDE GATE -- 2
7.03
AUTOMATIC BAG PLACING,
WEIGHING,FILLING, STITCHING
MACHINE WITH CONVEYOR &
CONTROLLER
250 BAGS/HR 1 SET.
704 SLAT CONVEYOR - With WOODEN slats. 250 BAGS / HR;
25 M 1 SET
7.05 PORTABLE BAG STICHING MACHINE -- 2
7.06 ELECTRONIC WEIGH SCALE 200 KG 2
7.07 PORTABLE BAG STACK CONVEYOR 250 BAGS / HR;
10 M 2
8 FEED MILL HOUSING
8.01 MS STRUCTURAL STEEL FOR MAIN
PLANT AND PIPE BRIDGE 240 MT Approx.
8.02 MILD STEEL CHEQUERED PLATE
PLATFORM,TRENCH COVERS ETC 60 MT Approx.
8.03 WINDOWS As per Design
8.04 ROOF SHEETING As per Design 0
8.05 CLADDING SHEETS As per Design 0
8.06 LIGHT FITTINGS & LAMPS ( MAIN
PLANT) -- 75 SETS
9 PRODUCT PIPING/ ACCESSORIES
9.01 PRODUCT PIPING/DUCTING, FLEX.
CONNECTIONS -- 1 LOT
9.02 SMALL HOPPERS/TRANSITION PIECE -- 1 LOT
9.03 PNEUMATIC GATES FOR PROP. BINS
FILLING -- 1 LOT
9.04 PNEUMATIC PIPE FLAPS -- 4
9.05 SIGHT GLASS FOR AIR LOCK -- 2 SETS
35
10 AUTOMATION EQUIPMENT
10.01 LOAD CELL WITH WEIGHING SYSTEM
FOR BATCH WEIGHER EACH 1 MT; 1 MT 1 SET
10.02 LOAD CELL FOR LOSS-IN-WEIGHT
FEEDER -- 2 SETS.
10.03 PROGRAM SOFTWARE FOR THE ENTIRE
PLANT -- 1 SET
10.04 PLC PANEL , HMI , SENSORS,
COMMUNICATION & DATA CABLES -- 1 LOT.
10.05 MIMIC PANEL, COMPUTER FOR
CONTROL ROOM -- 1 SET
10.06 COMPUTER FURNITURE (MODULAR) -- 1 LOT
10.07 UPS FOR CONTROLS & PLC -- 1 SET
10.08 COMPUTER WITH MIS OF PLANT
INFORMATION IN ENGG. OFFICE -- 1 SET
10.09 INSTRUMENT EARTHING ( CU PLATE)
FOR PLC LOT PANEL ETC -- 1
10.10 SPLIT TYPE AIR CONDITIONING UNIT
FOR CONTROL ROOM -- 1 SET.
SERVICE EQUIPMENTS
11 ELECTRICAL EQUIPMENT (LT)
11.01 MAIN LT PANEL
11.02 MCC FOR MAIN PLANT -- 1
11.03 REMOTE PANELS FOR FEED MILL
EQPTS -- 1 LOT
11.04 AUTOMATIC POWER FACTOR
CORRECTION PANEL -- 1
11.05 MCC FOR RAW MATERIAL INTAKE,
SILO SYSTEM, BOILER , PUMP HOUSE &
MOLASSES UNLOADING TANK
-- 1each
11.06 MCC FOR SILO SYSTEM -- 1
11.07 SOFT-STARTER PANEL -- 1
11.08 POWER CABLES -- 1 LOT
11.09 CONTROL & SIGNAL CABLES -- 1 LOT
11.10 ELECTRICAL ACCESSORIES (CABLE
TRAYS, GI CONDUITS, CABLE GLANDS,
CABLE LUGS, ISOLATORS, PUSH
BUTTONS, RUBBER MATS,FUSE
PULLER, RUBBER GLOVES ETC)
-- 1 LOT
11.11 IN MAIN PLANT BUILDING – LIGHTING
PANEL, LIGHTING DBS, CONDUITS ,SET
WIRING, EMERGENCY LIGHTS FOR
CONTROL ROOM (Excluding RMG & FPG)
-- 1
11.12 EARTH PITS AND NETWORK FOR
PANELS, DB ETC -- 1 LOT
36
11.13
LIGHTENING ARRESTOR WITH CU
EARTH CONDUCTOR, GI EARTH PITS,
AVIATION LIGHTS
-- 1 SET
12 STEAM DISTRIBUTION & CONDENSATE RECOVERY
12.01
LOW PRESSURE STEAM PIPES WITH
INSULATION LOT & CLADDING,
VALVES, FITTINGS, FLOW
CONTROLLERS
-- 1
12.02 CONDENSATE RECOVERY SYSTEM -- 1 SET
12.03 CONDENSATE PIPES, VALVES, AND
FITTINGS -- -- 1 LOT
13 COMPRESSED AIR GENERATION & HANDLING EQUIPMENT
13.01 AIR COMPRESSOR (SCREW) PNEU.
FLAPS, GATES, ASPIRATION UNITS 60 CUM/HR 2
13.02 REFRIGERATED AIR DRYER 60 CUM/HR 1
13.03 AIR RECEIVER WITH AUTO DRAIN 1000 LITRE 1
13.04 COMPRESSED AIR PIPES, VALVES ,
FITTINGS -- 1 LOT
13.05 Mineral Mixture Plant 1 LOT
Total of Part – I.
14 PART – II ERECTION & COMMISSIONING
14.01 Erection, testing & commissioning of
equipment as per the above list. 1 LOT 1
14.02 Erection & commissioning of steel structure
sheeting and internal lighting etc. 1 LOT 1
Total of Part – II.
Total of Part – I & II. (In figures)
Total of Part – I & II. (In words)
Note:- The above list of equipment is as per preliminary design of the plant. The final list of
equipment & their individual capacity may vary as per detailed engineering of the bidder to
achieve the MINIMUM rated capacity of 150 TPD and further provision for expansion of
capacity up to 300 TPD. It is required to keep a provision for adding of all the equipments that
will be needed in future for achieving a capacity of 300 TPD on 20 hrs per day of working. All
suitable structure, cables and relevant works for the same are required to be done in first phase
along with ordered execution. It is also required that the design be made on a basis that capacity
can be increased to 300 TPD in future without any shut down needed in running plant of first
150 TPD. However capacities mentioned above for individual equipment can not be increased
to achieve overall plant capacity.
37
ANNEXURE-I (Part – B)
PROPOSED SITE AT VILLAGE HATHALAI (GUNDOGE) DISTRICT PALI FORM OF TENDER FOR PRICE
(TO BE SUBMITTED IN FINANCIAL BID ENVELOPE)
Time & Date of opening of Tender :
Description of goods :
S.No. Particulars Amount (Rs.) Remarks, if any.
1. Design & supply charges for 150 TPD Cattle
Feed Plant (Expandable upto 300 TPD
equipment and utilities as per the technical
specification & drawings enclosed.
2. Packing & forwarding charges
3. Excise Duty @______
4. Sales Tax (RST/CST/VAT) @______ (see note
no.1given below)
5. Entry Tax if any @________
6. Transportation including Insurance charges
7. Any other charges (if any)
8. Total FOR site price (1 to 7)
9. Installation, testing & commissioning charges for
150 TPD Cattle Feed Plant (Expandable upto
300 TPD equipment and utilities as per the
technical specification & drawings enclosed.
10. Service Tax @_____
11. Total FOR Unit Price (9 to 10)
12. Total Net FOR Unit Price for supply, installation &
commissioning (8+11)
(in figures and in words)
*The FOR rates indicated at sr. no. 8, 11 & 12 includes all duties & taxes even if not
explicitly mentioned here but in vogue/applicable at the time furnishing rates.
Note :
(v) Tenderer should indicate clearly whether the sales tax mentioned above is against any concessional
form. In case the concessional form is not provided, the rate of tax should be mentioned.
(vi) Price negotiations shall be discouraged bidders should therefore quote their most competitive rates
(with conformity to the specifications and commercial stipulations given in the tender) in the very
instance least they run the risk of losing out in absence of negotiations.
(vii) The rate must be written both in words and figures. There should be no erasures and or over
writings, corrections, if any, should be made clearly and initiated with date. In case if there is
variation observed in the rates in between words & figures, the lowest rate shall be considered.
(viii) The conditional offer which affect the rate of the quoted item shall be liable for rejection even
the quoted rate is lowest.
(Signed & sealed by the tenderer
in token of acceptance of above)
38
ANNEXURE – I (Part – B)
PROPOSED SITE AT VILLAGE HATHALAI (GUNDOGE) DISTRICT PALI PART 1. : DESIGN, FABRICATION, SUPPLY OF MAJOR EQUIPMENTS, FOR 150 TPD
CATTLE FEED PLANT (EXPANDABLE UP TO 300 TPD) ON TURNKEY BASIS
LIST OF MAJOR EQUIPMENT
S.
No.
Description Capacity/Size
(cm=Cubic
Meter)
Quantity Unit Price
Rs.
Amount
Rs.
1 RAW MATERIALS STORAGE EQUIPMENTS
1.01 Silo System for DORB/Grain Storage with
handling & Transferring system. 500 MT
2
1.02 Complete Unloading, Cleaning System of 50
TPH with Three Truck at a time and Shed 50 TPH 1
2 RAW MATERIALS INTAKE EQUIPMENT
2.01 INTAKE CHAIN CONVEYOR IN RMG
WITH PNEUMATIC SLIDE GATES 40TPH 55RM 2
2.02 DUMPING HOPPERS FOR INTAKE
CONVEYORS IN RMG 2 M x 1 M 10
2.03 ASPIRATION UNIT FOR DUMP HOPPERS
IN RMG -- 10
2.04 ELEVATOR FOR BATCH PRE-MIXER 10 TPH 1
2.05 HOPPER ABOVE BATCH MIXER WITH
PN. GATE 1 MT 1
2.06 BATCH MIXER FOR PREMIX DUTY WITH
PNEUMATIC OUTLET GATE 1 MT 1
2.07 HOPPER BELOW BATCH MIXER 1 MT 1
2.08 ELECTRONIC PLATFORM WEIGHSCALE 200 KGS 2
2.09 PORTABLE BAG STACK CONVEYORS 250 BAGS/HR;
10 M 3
2.10 INTAKE BUCKET ELEVATOR 40 TPH 2
2.11 ASPIRATION UNITS FOR INTAKE
ELEVATORS -- 2
2.12 CASCADE MAGNET 40 TPH 2
2.13 JUTE TWINE REMOVER 40 TPH 2
2.14 CROSS CONVEYOR 40 TPH 1
2.15 DISTRIBUTION CONVEYORS 40 TPH 2
3 BATCHING EQUIPMENT
3.01 PROPORTIONATE BIN WITH OUTLET
GATE 20 MT 16
3.02 ASPIRATION UNITS FOR
PROPORTIONATE BINS 1 SET
3.03 GRAVITY FEEDERS FOR BIN DISCHARGE 16
3.04 REDLER CHAIN CONVRYOR FOR BIN
DISCHARGE 250 MM 16
3.05 BATCH WEIGH HOPPER ( MAJOR 3 MT 1
39
INGREDIENTS)
3.06 BATCH WEIGH HOPPER(MINOR INGREDIENTS) 1 MT 1
3.07 PNEUMATIC GATE BELOW WEIGH
HOPPER -- 2
3.08 SURGE HOPPER BELOW BATCH
WEIGHER -- 2
3.09 BATCH CHAIN CONVEYOR 30 TPH 1
3.10 BATCH BUCKET ELEVATOR 30 TPH 1
3.11 ASPIRATION UNITS FOR BATCH
ELEVATOR -- 1
4 GRINDING, MIXING EQUIPMENT
4.01 GRINDING BIN WITH PN. GATE 3 MT 2
4.02 FEEDER ABOVE HAMMER MILL 15 TPH 2
4.03 HAMMER MILL WITH 6 or 8 MM SIEVE 15 TPH 2
4.04 HOPPER BELOW HAMMER MILLS -- 2
4.05 ASPIRATION UNIT FOR HAMMER MILLS -- 2
4.06 BIN ABOVE BATCH MIXER 3 MT 2
4.07 PNEUMATIC GATE ABOVE BATCH
MIXER -- 1 SET
4.08 BATCH MIXER ( RIBBON TYPE) 3 MT 1
4.09 PNEUMATIC GATE BELOW BATCH
MIXER -- 1 SET
4.10 HOPPER BELOW BATCH MIXER 10 MT 1
4.11 CONVEYOR BELOW MIXER 30 TPH 1
4.12 MIXED FEED ELEVATOR 30 TPH 1
4.13 ASPIRATION UNIT FOR MIXED FEED
ELEVATOR -- 1 1
5 PELLETTING EQUIPMENT
5.01 MIXED FEED TRANSFER ELEVATOR
WITH OUTLET CASCAD MAGNET. 30 TPH 1
5.02 PELLETING BIN WITH BIN ACTIVATOR 10 MT 1
5.03 VARIABLE SPEED LOSS IN WEIGHT
FEEDER WITH HOPPER 10 TPH 1
5.04 PELLET MILL WITH CONDITIONER AND
MOLASSES MIXER 10 TPH 1
5.05 ROTARY AIR LOCK FOR PELLET COOLER 10PH 1
5.06 COUNTER CURRENT PELLET COOLER 10 TPH 1
5.07 PELLET COOLER CYCLONE (SS 304) WITH
PN.HAMMERS. -- 1
5.08 ROTARY AIR LOCK FOR CYCLONE (SS ) 10 TPH 1
5.09 PELLET COOLER FAN -- 1
5.10 ASPIRATION DUCTING FOR PELLET
COOLER (SS 304) -- 1 SETS
5.11 PELLET ELEVATOR 30 TPH 1
5.12 PELLET SIEVE 30 TPH 2
40
5.13 SPARE MOTOR FOR PALLET MILL -- 1
5.14 SPARE MOTOR FOR CYCLONE BLOWER -- 1
6 MOLASSES STORAGE / HANDLING EQUIPMENT
6.01 Molasses Storage Tank 400 MT 2
6.02 MOLASSES UNLOADING TANK (WITH
HOSE)
6.03 MOLASSES UNLOADING PUMP (1 Working
+ 1 Standby) 15 KLPH 2
6.04 MOLASSES PRE-HEATER 1 1
6.05 MOLASSES FEEDING PUMP (1 Working + 1
Standby) 3 KLPH 2
6.06 MOLASSES FLOW METER 3 KLPH 1
6.07 MOLASSES PIPING, CONTROL
VALVES,FITTINGS -- 1 LOT
7 BAGGING EQUIPMENT
7.01 BAGGING BIN (SS LINED) 20 MT 2
7.02 PNEUMATIC SLIDE GATE -- 2
7.03
AUTOMATIC BAG PLACING,
WEIGHING,FILLING, STITCHING
MACHINE WITH CONVEYOR &
CONTROLLER
250 BAGS/HR 1 SET.
704 SLAT CONVEYOR - With WOODEN slats. 250 BAGS / HR;
25 M 1 SET
7.05 PORTABLE BAG STICHING MACHINE -- 2
7.06 ELECTRONIC WEIGH SCALE 200 KG 2
7.07 PORTABLE BAG STACK CONVEYOR 250 BAGS / HR;
10 M 2
8 FEED MILL HOUSING
8.01 MS STRUCTURAL STEEL FOR MAIN
PLANT AND PIPE BRIDGE 240 MT Approx.
8.02 MILD STEEL CHEQUERED PLATE
PLATFORM,TRENCH COVERS ETC 60 MT Approx.
8.03 WINDOWS As per Design
8.04 ROOF SHEETING As per Design 0
8.05 CLADDING SHEETS As per Design 0
8.06 LIGHT FITTINGS & LAMPS ( MAIN
PLANT) -- 75 SETS
9 PRODUCT PIPING/ ACCESSORIES
9.01 PRODUCT PIPING/DUCTING, FLEX.
CONNECTIONS -- 1 LOT
9.02 SMALL HOPPERS/TRANSITION PIECE -- 1 LOT
9.03 PNEUMATIC GATES FOR PROP. BINS
FILLING -- 1 LOT
9.04 PNEUMATIC PIPE FLAPS -- 4
9.05 SIGHT GLASS FOR AIR LOCK -- 2 SETS
41
10 AUTOMATION EQUIPMENT
10.01 LOAD CELL WITH WEIGHING SYSTEM
FOR BATCH WEIGHER EACH 1 MT; 1 MT 1 SET
10.02 LOAD CELL FOR LOSS-IN-WEIGHT
FEEDER -- 2 SETS.
10.03 PROGRAM SOFTWARE FOR THE ENTIRE
PLANT -- 1 SET
10.04 PLC PANEL , HMI , SENSORS,
COMMUNICATION & DATA CABLES -- 1 LOT.
10.05 MIMIC PANEL, COMPUTER FOR
CONTROL ROOM -- 1 SET
10.06 COMPUTER FURNITURE (MODULAR) -- 1 LOT
10.07 UPS FOR CONTROLS & PLC -- 1 SET
10.08 COMPUTER WITH MIS OF PLANT
INFORMATION IN ENGG. OFFICE -- 1 SET
10.09 INSTRUMENT EARTHING ( CU PLATE)
FOR PLC LOT PANEL ETC -- 1
10.10 SPLIT TYPE AIR CONDITIONING UNIT
FOR CONTROL ROOM -- 1 SET.
SERVICE EQUIPMENTS
11 ELECTRICAL EQUIPMENT (LT)
11.01 MAIN LT PANEL
11.02 MCC FOR MAIN PLANT -- 1
11.03 REMOTE PANELS FOR FEED MILL
EQPTS -- 1 LOT
11.04 AUTOMATIC POWER FACTOR
CORRECTION PANEL -- 1
11.05 MCC FOR RAW MATERIAL INTAKE,
SILO SYSTEM, BOILER , PUMP HOUSE &
MOLASSES UNLOADING TANK
-- 1each
11.06 MCC FOR SILO SYSTEM -- 1
11.07 SOFT-STARTER PANEL -- 1
11.08 POWER CABLES -- 1 LOT
11.09 CONTROL & SIGNAL CABLES -- 1 LOT
11.10 ELECTRICAL ACCESSORIES (CABLE
TRAYS, GI CONDUITS, CABLE GLANDS,
CABLE LUGS, ISOLATORS, PUSH
BUTTONS, RUBBER MATS,FUSE
PULLER, RUBBER GLOVES ETC)
-- 1 LOT
11.11 IN MAIN PLANT BUILDING – LIGHTING
PANEL, LIGHTING DBS, CONDUITS ,SET
WIRING, EMERGENCY LIGHTS FOR
CONTROL ROOM (Excluding RMG & FPG)
-- 1
11.12 EARTH PITS AND NETWORK FOR
PANELS, DB ETC -- 1 LOT
42
11.13
LIGHTENING ARRESTOR WITH CU
EARTH CONDUCTOR, GI EARTH PITS,
AVIATION LIGHTS
-- 1 SET
12 STEAM DISTRIBUTION & CONDENSATE RECOVERY
12.01
LOW PRESSURE STEAM PIPES WITH
INSULATION LOT & CLADDING,
VALVES, FITTINGS, FLOW
CONTROLLERS
-- 1
12.02 CONDENSATE RECOVERY SYSTEM -- 1 SET
12.03 CONDENSATE PIPES, VALVES, AND
FITTINGS -- -- 1 LOT
13 COMPRESSED AIR GENERATION & HANDLING EQUIPMENT
13.01 AIR COMPRESSOR (SCREW) PNEU.
FLAPS, GATES, ASPIRATION UNITS 60 CUM/HR 2
13.02 REFRIGERATED AIR DRYER 60 CUM/HR 1
13.03 AIR RECEIVER WITH AUTO DRAIN 1000 LITRE 1
13.04 COMPRESSED AIR PIPES, VALVES ,
FITTINGS -- 1 LOT
13.05 Mineral Mixture Plant 1 LOT
Total of Part – I.
14 PART – II ERECTION & COMMISSIONING
14.01 Erection, testing & commissioning of
equipment as per the above list. 1 LOT 1
14.02 Erection & commissioning of steel structure
sheeting and internal lighting etc. 1 LOT 1
Total of Part – II.
Total of Part – I & II. (In figures)
Total of Part – I & II. (In words)
Note:- The above list of equipment is as per preliminary design of the plant. The final list of
equipment & their individual capacity may vary as per detailed engineering of the bidder to
achieve the MINIMUM rated capacity of 150 TPD and further provision for expansion of
capacity up to 300 TPD. It is required to keep a provision for adding of all the equipments that
will be needed in future for achieving a capacity of 300 TPD on 20 hrs per day of working. All
suitable structure, cables and relevant works for the same are required to be done in first phase
along with ordered execution. It is also required that the design be made on a basis that capacity
can be increased to 300 TPD in future without any shut down needed in running plant of first
150 TPD. However capacities mentioned above for individual equipment can not be increased
to achieve overall plant capacity.
43
ANNEXURE-II
(Form of Bank Guarantee against 30% advance sought from the Dugdh Sanghs for
supply/erection contracts)
1. In consideration of the ______________ ZILA DUGDH UTPADAK SAHAKARI SANGH
LTD.,_______________ (hereinafter called “The SANGH”) having agreed to grant an
advance of Rs.___________________(Rupees___________________________________
only) to M/s.________________________ (hereinafter called the said supplier(s) under the
terms and conditions of an agreement /Purchase Order No._________________ dated
_____________ made between the Rajasthan Co-operative Dairy Federation Ltd., Jaipur
and / or SANGH and M/s.______________________ for supply/erection and
commissioning (hereinafter called the said agreement/purchase order) on production of a
Bank Guarantee for Rs.________________ (Rupees ___________________________
only). We _______________________(hereinafter called “The Bank”) do hereby undertake
to pay the SANGH an amount not exceeding
Rs.______________(Rupees________________________ only) against any loss/damage
caused to or suffered or would be caused to or suffered by the SANGH by reasons of any
breach by the said supplier(s) or any of the terms and conditions mentioned in the said
agreement/Purchase Order.
2. We ________________________ (Name of the Bank) do hereby undertake to pay the amount
due and payable under this guarantee without any demur, merely on a demand from the
SANGH stating that the amount claimed is due by way of loss or damage caused to or would
be caused to or suffered by the SANGH by reasons of any breach by the said supplier(s) or
any of the terms and conditions contained in the said agreement/Purchase Order, or by reason
of the supplier(s), failure to perform the said agreement/purchase order, or by reasons of the
supplier‟s failure to perform the said agreement/purchase order. Any such demand made on
the Bank shall be conclusive as regards the amount due and payable by the Bank under this
guarantee. However our liability under this guarantee shall be restricted to an amount not
exceeding Rs.___________ (Rupees ____________ only).
3. We _______________ (Name of the Bank) further agree that the guarantee herein contained
shall remain in full force and effect during the period that would be taken for the
performance of the said agreement/purchase order and that it shall continue to be
enforceable till all the dues of the SANGH, under or by virtue of the said
agreement/purchase order have been fully paid and its claims satisfied or discharged or till
the SANGH certifies that the terms and conditions of the said agreement/purchase order
have been fully and properly carried out by the said supplier(s) and accordingly discharge
the guarantee unless a demand of claim under this guarantee made on us in writing on or
before _______________. We shall be discharged from all liabilities under this guarantee
thereafter.
4. We _______________ (Name of the Bank) further agree with the SANGH that the SANGH
shall have the fullest liberty without our consent and without affecting in any manner our
obligations hereunder to vary any of the terms and conditions of the said agreement/purchase
order to extended the time of performance by the said supplier (s) from time to time or to
postpone for any time or from the time to time any of the power exercisable by the SANGH
44
against the said supplier(s) and to forbear or endorse any of the terms and conditions relating
to the said agreement/purchase order and we shall not be relived from our liability by reason
of any such variation of extension or for any forbearance, act or omission on the part of the
SANGH or any indulgence by the SANGH to the said supplier(s) or by any such matter or
thing whatsoever which under the law relating to sureties would but for this provision have
effect of so relieving us.
5. We _________________ (Name of the Bank) lastly undertake not to revoke this guarantee
during its currency except with the previous consent of the SANGH in writing.
6. Notwithstanding anything stated above our liability under this guarantee is restricted to
Rs.________________(Rupees __________________________ only). Our guarantee shall
remain in force until unless a suit or an action to enforce a claim under this guarantee is filed
against us before that date, i.e. on or before ____________ all your rights under the said
guarantee shall be forfeited and we shall be released and discharged from all liability
thereunder.
The Bank agrees that the amount hereby guaranteed shall be due and payable to the SANGH
on SANGH‟s serving a notice requiring the payment of the amount and such notice shall be
served on the Bank either by actual delivery thereof to the Bank or by despatch thereof to the
Bank by registered post at the address of the said Bank. Any notice sent to the Bank at its
address by Registered Post shall be deemed to have been duly served on the Bank
notwithstanding that the notice may not in fact have been delivered.
NOTWITHSTANDING – anything contained herein :
i) Our liability under this Bank Guarantee shall not exceed
Rs.____________(Rupees__________________________________________only).
ii) This Bank Guarantee shall be valid upto _________________ and,
(iii)We are liable to pay the guaranteed amount under this Bank Guarantee only and only if you
serve upon us a written claim or demand in the manner specified above on or before
______________.
7. Notwithstanding anything stated above the Bank Guarantee shall be discharged by the
SANGH once the advance amount released against the Bank Guarantee along with interest or
penalty if any payable on such advance has been fully recovered/adjusted.
Place :
Date :
Signature & Seal
45
ANNEXURE – III
AGREEMENT
(On non judicial stamped paper of value Rs.100/-)
1. An agreement made this ___________ day of ____________ between
M/s.____________________ hereinafter called “approved supplier” which expression
shall where the context so admits, be deemed to include his heirs, successors, executors
and administrators of the one part and the Rajasthan Cooperative Dairy Federation Ltd.
(hereinafter called “the Federation” which expression shall, where the context so admits,
be deemed to include his successors in office and assigns) of the other part.
2. Whereas the approved supplier has agreed with the Federation for supply,
installation, testing and commissioning of & all those articles set forth in the
supply order/work order issued vide No._________ and in the manner set forth in
the aforesaid order.
3(a) And whereas the approved supplier has deposited a sum of Rs._______ in form of
Demand Draft as security for the due performance of the agreement.
3(b) And whereas the approved tenderer/supplier has agreed :
(i) to keep the security deposit with the Federation in form of demand draft for an initial
period of 12 months or such extended period so as to cover the period of performance of
contract i.e. supply/erection/commissioning as per purchase order. In case the
contractor/supplier completes its contractual obligations before 12 months the deposit
can be refunded before 12 months at the sole discretion of RCDF before aforesaid
period of 12 months.
(ii) that no interest shall be paid by the Federation on the security deposit.
(iii) that in case of breach of any terms & conditions of the aforesaid supply order of
this agreement by the contractor/supplier the amount of security deposit shall be
liable to forfeiture in full or part by the Federation.
NOW THESE PRESENT WITNESS
1. In consideration of the payment to be made by the Federation at the rates setforth in the
aforesaid supply order/work order, the approved supplier will duly supply the articles
setforth/execute the work in the aforesaid supply order/work order and in the manner
setforth and within the period stipulated in the conditions of the tender and order.
46
2. The conditions of the tender as given in the tender document for the work,
conditions of the aforesaid supply order/work order and also any subsequent
amendment as may be issued by the Federation will be deemed to be taken as part
of this agreement and are binding on the parties executing this agreement.
3(a) The Federation do hereby agree that if the approved supplier shall duly supply the
said articles/execute the work in the time and manner aforesaid, observe and keep
the said terms & conditions, the Federation shall pay or cause to be paid to the
approved supplier, at the time and in manner set forth in the said conditions, the
amount payable for each and every consignment/work executed on supplier‟s
raising bills.
3(b) The mode of payment will be as specified in the supply order/work order.
4. Delivery shall be effected and completed in the manner and time specified in the
supply order.
5. In case the approved supplier fails to deliver the goods/execute the work within the
time specified in the aforesaid supply order/work order, the conditions of
liquidated damages clause and penalty those for late deliveries as stipulated in the
aforesaid tender/supply order/contract shall be enforced.
6. In case of any doubt or question arising on the interpretation pertaining to the supply
order/tender the terms of the contract shall be binding, override and final over the supply
order/tender.
7. If any dispute or difference shall at any time arise between the two parties in
respect of or concerning any of this herein contained or arising out of this supply
order/tender/agreement as to the rights, liabilities or duties of the said parties
hereunder or as to the recovery of any amount, the same shall be referred to the
sole arbitrator M.D., RCDF who in turn may refer the dispute to any officer of
RCDF for adjudication. The arbitration shall be in accordance to the law of
Arbitration and Conciliation Act, 1996. The decision of the Sole Arbitrator shall be
final and binding on both the parties.
8. All the disputes pertaining to the said contract shall vest to the jurisdiction of
Courts at Jaipur.
In witness whereof the parties hereto have set their hands on the _____________ day
______________________.
SIGNATURE OF THE SIGNATURE FOR AND ON
APPROVED SUPPLIER: BEHALF OF the Federation :
47
Witness No.1 Witness No.1
Signature :______________________ Signature :_________________
Name :______________________ Name :_________________
Address :______________________ Address :_________________
______________________ _________________
______________________ _________________
Witness No.2 Witness No.2
Signature :______________________ Signature :_________________
Name :______________________ Name :_________________
Address :______________________ Address :_________________
______________________ _________________
______________________ _________________
48
ANNEXURE – IV
RAJASTHAN CO-OPERATIVE DAIRY FEDERATION LTD.,
JAIPUR : 302 017.
General Terms and Conditions form an integral part of Purchase Order
1. INSPECTION :
The equipment under the purview of your supply should be inspected by your own
technical experts at your works and such inspection report should be forwarded to
us in triplicate along with despatch documents. However, the RCDF, reserves its
right of inspection at any stage of fabrication manufacture of the
equipment/material. The final inspection if any case will be carried out at RCDF
project site.
You should forward to us the test certificate, wherever applicable, obtained from
the concerned authorities/principal manufacturers either regarding quality or any
other details of the items utilised in the process of manufacture/fabrication.
2. DESPATCH INSTRUCTIONS :
The material are to be despatched to the project site by the mode of transport
specified in the order under intimation to us. Depending on the type of material,
you shall have to carryout proper packing/creating to avoid breakage in transit.
Other details of despatch such as marking, consignee a particulars etc. are given
under clause No.4 of this purchase order. For using any mode of transport other
than the specified one prior concurrence from us in writing should be obtained. All
consignments should be despatched on freight paid basis irrespective of price basis.
In the event of freight paid basis irrespective of price basis. In the event of freight
payable by us, you shall have to obtain our prior approval and produce necessary
documentary evidence in support of your claims. Unless otherwise stated, the
original RR/LR should be sent by registered post directly to the consignee
alongwith a copy of invoice and two copies of delivery challan/packing list.
3. INSURANCE :
You shall have to arrange all transit risk insurance on warehouse basis for the items
to be supplied by you. In the cases, where orders are placed on ex-works basis, the
premium shall be paid by us at actual to you against production of documentary
evidence. In the event of any damage to /loss of consignment in transit, it will be
your responsibility to lodge necessary claims with the carriers/underwriters and
pursue them till settlement. Since insurance policy will be taken in our name, if
required, we shall give you necessary authorisation letter, authorising you to lodge
and pursue claims on your behalf with the carriers/underwriters. Also you shall
have to make good the losses/damages occurred in transit by making
replacement/payment to us in the first instance and if claims are settled by the
49
underwriters and any amounts are released by us, the amount thus realised in
settlement of claims shall be reimbursed to you.
In other words, the prime facie responsibility rests on you for getting compensation
of the damages/losses incurred if any, due to all transit hazards.
In the case, when order is placed on „free delivery at site‟ basis, no insurance
premium will be paid by us. However, in such case also, all transit risk insurance
policy must be taken to safeguard your own interest and to protect the material
against transit hazards.
4. DELIVERY CLAUSE :
The stipulated delivery time given in the order is the essence of this contract. You
must, therefore, strictly adhere to the delivery schedule mentioned in the order.
5. DEMURRAGE :
You shall bear and reimburse to useful demurrage charges, if any paid by reason of
delay on your part in forwarding the original despatch documents to destination
given in the purchase order.
6. REJECTION :
We reserve the right to reject the goods either in part or full if at the time of
delivery, it is noticed that the goods supplied do not conform to the
specifications/description given in the order. The rejection, if any, will intimated to
you in writing within a reasonable time. You will be liable to repair/replace the
rejected goods within the stipulated time. Till the repair/replacement is done, the
rejected goods shall be lying at your risk, cost and responsibility. If you do not
arrange to repair/replace the rejected goods within a period stipulated by us, we
may dispose of such goods at your risk and in the manner which we think fit. We
shall be entitled to retain the incurred on storage, handling and disposal of the
rejected goods. We shall also be entitled to recover the expenses made by us on
storage land handling of such rejected goods till the goods are removed from our
premises/stores.
7. COMPENSATION FOR DELAY :
The accepted delivery schedule of supply and/or installation shall be governed by
the compensation for delay clause as given in the tender. Under the clause, if the
delivery or installation of the equipment is not made by the stipulated date, you
shall have to pay a penalty @ half percent the value of each item per week subject
to a maximum of five percent of the net value of the unexecuted part of the
accepted order. Alternatively in the event of non delivery of the materials or non
completion of installation within the stipulated time, we reserve the right to cancel
the order and procure the material/get installed from any other the order land the
party.
50
8.0 GUARANTEE :
The supply of equipment as well as installation, if entrusted, shall have to be
carried out by you to the entire satisfaction of RCDF.
You shall also guarantee to repair/replace without any extra cost, the items or parts
thereof, if found defective due to bad designing, workmanship or substandard
material, within 12 months from the date of commissioning or 24 months from the
date of receipt of material at site whichever is earlier. If it is necessary to send the
defective equipment or parts thereof to your works for repair/replacement, without
forming any precedence the cost of repacking, loading, unloading, transportation
from the site to your works and back to site shall have to be borne by you. The
guarantee however, does not cover any damage resulting from normal wear and
tear or improper attendance or mishandling of the equipment during repair by
personnel other than the supplier or their authorised agents.
9. WARRANTY :
You must provide a warranty for a minimum period of one year from the date of
commissioning of the equipment for satisfactory performance of the supplied
equipment according to the designed/rated/installed capacity or any other norms
fixed by RCDF.
10. DRAWINGS, SPECIFICATIONS & MANUALS :
10.1 Prior to commencement of fabrication, you shall have to submit for our approval,
two sets of drawings of all the items ordered for supply showing overall
dimensions with typical sections, details of service connection and their
requirement, details of drive units etc. The drawing should also show a complete
bill of material, wherever applicable.
10.2 Three copies of each operation and maintenance manuals and service instructions
alongwith the drawings showing details of part list, against each item of your
supply should be sent to us. You should also furnish us service requirements like
water (hot water, chilled water and main‟s water), electricity, lubricant air etc. for
each equipment, wherever applicable.
10.3 You shall provide a list of spare parts, which will be required for the plants and
equipments supplied by you for atleast two years of normal operation with the
names and the addresses of the manufacturers from whom they can be procured.
The list should contain the code numbers of the parts, which are required to be
procured in addition to the machine number and model etc.
10.4 In case, any documents, drawings are supplied to you by RCDF the same must be
treated as confidential, must not be copies, reproduced, transmitted or disclosed
otherwise in whole or part, not duplicated, modified, divulged or discussed to any
third party nor misused in any other way without the consent of the RCDF in
writing. All such documents, and drawings shall be the property of RCDF and they
must be returned to RCDF after done with.
11. SUBMISSION OF BILLS :
51
Bills in triplicate under registered post, stating therein our purchase order reference
along with necessary inspection certificates from your inspector in respect of the
material supplied and copies of despatch documents should be sent to our Head
Office at Jaipur/ Concern Milk Union/ Units. Unless otherwise state, the payment
shall be made to you by Crossed Account Payee Cheque by post according to the
terms of payment mentioned in the Purchase Order.
12. CANCELLATION OF CONTRACT AND REFUND OF ADVANCES :
We shall be free to cancel our order in part or full, in the case of non-delivery of
material/non-completion of installation within the stipulated delivery period or
breach of any one of the clauses mentioned herein. Consequential losses, if any, on
account of our getting installation done or obtaining supplies from alternative
sources besides payment of higher price shall be recovered from you. In the event
of cancellation of the order, you will be liable to refund the advance amount, if
any, to the RCDF in full. Suppliers will have no right to forfeit the advance amount
received by them.
13. SUB-CONTRACT :
In the event of awarding sub-contract to any of the parties by you for the
manufacture/supply/erection of any parts/spares/components that will be used in
the ordered equipment, you must furnish us details about your sub-contractors,
their experience, specification etc. The sub-contract can be awarded by you only
after obtaining written approval from us. In the event of sub-contract also the prime
facie responsibility rests on you regarding quality, quantity, guarantee/warranty of
the materials supplied by the sub-contractors.
14. FORCE MAJEURE CLAUSE :
The terms and conditions mutually agreed upon shall be subject to For Majeure
Clause. Neither the supplier nor the purchaser shall be considered in default in
performance of its obligations hereunder, if such performance is prevented or
delayed because of war hostilities, revolution, civil commotion, strike, epidemic,
order, proclamation, regulation, or ordinance of any Government or of any act of
God or of any other cause whether of similar or dissimilar nature, beyond the
reasonable control of the party affected. Should one or both the parties be
prevented from fulfilling his/their contractual obligations by a state of Force
Majeure lasting continuously for a period of six months, the two parties should
consult each other regarding the future implementation of the contract.
15. ARBITRATION CLAUSE :
For settlement of any dispute arising out of this order, Jaipur shall be the
jurisdiction irrespective of any jurisdiction clause mentioned in your
correspondence. The arbitration proceedings shall be governed by the provisions of
the Indian Arbitration Act, 1940 and the rules made thereunder or any enactment or
statutory modifications thereof for the time being in force subject to condition
No.13 of General Terms & Conditions Schedule – I of the tender document.
52
ANNEXURE-VI
(Proforma Bank Guarante against 10% balance)
(On Non-judicial stamp paper)
This deed of Guarantee made this __________ day of ____________ 200 (Two
thousand___________________) by _____________ (Name and address of the Bank)
(hereinafter referred to as “The Bank”) which expression shall be here the context or
meaning so requires, includes the successors and assignees of the Bank and the Rajasthan
Co-operative Dairy Federation Ltd., Jaipur, Rajasthan, (hereinafter referred to as “The
Federation which expression shall unless repugnant to the context or the meaning there of
include its legal representatives, successors and assignees.
WHEREAS the Federation has placed its purchase order bearing No._________
dated ________ (Name and address of the party) (Hereinafter called “The supplier”) for
supply of ________________ and WHEREAS the Federation has agreed to pay to the
supplier final 10% of the value of the equipment on submission of a Bank Guarantee of
equal amount, which will be kept valid upto ________ from the date of despatch/receipt
of material at site.
In consideration of the Federation having agreed to pay to the supplier
Rs.___________(Rupees_______________only) being the last 10% of the value of the
equipment, we__________(Name of the Bank) hereby undertake and guarantee to make
repayment to the Federation of the said 10% amount or any part thereof which does not
become payable to the supplier by the Federation in accordance with the terms and
conditions of the said purchase order within _____ days from the date of despatch/ receipt
of material at site. The Bank further undertakes not to revoke this guarantee during its
currency except with the previous consent of the Federation in writing and this guarantee
shall be a continuous and irrevocable guarantee upto a sum of Rs.______
(Rupees___________only). The Bank shall not be discharged or released from this
guarantee by any arrangement between the supplier and the Federation with or without the
consent of the Bank or any alterations in the obligations of the parties or by any
indulgence, forbearance shown by the Federation to the supplier and that the same shall
not prejudice or restrict remedies against the Bank nor shall the same in any event be a
ground of defense by the Bank against the Federation. We_________ (Name of the Bank)
do hereby undertake to pay an amount due and payable under this guarantee without any
demur, merely or demand from the Federation stating that the amount claimed is due to
the Federation. In case the Federation puts forth a demand in writing on the Bank for the
payment of the amount in full or in part against this guarantee, the Bank shall consider
that such demand by itself is a conclusive evidence and proof that the supplier has failed
in complying with the terms and conditions stipulated by the Federation without raising
any dispute regarding the reasons for any such lapse/failure on the part or the supplier.
53
This guarantee shall be in addition to and without prejudice to any other securities
or remedies which the Federation may have or hereafter possess against the
supplier/tenderer and the Federation shall be under no obligation to marshal in favour of
the Bank any such securities or fund or assets that the Federation may be entitled to
receiving or have a claim upon and the Federation at its absolute discretion may vary,
exchange, renew, modify or refuse to complete or enforce or assign any security or
instrument.
The Bank agrees that the amount hereby guaranteed shall be due and payable to the
Federation on Federation‟s serving a notice requiring the payment of the amount and such
notice shall be served on the Bank either by actual delivery thereof to the Bank or by
despatch thereof to the Bank by registered post at the address of the said Bank. Any notice
set to the Bank at its address by Registered Post shall be deemed to have been duly served
on the Bank notwithstanding that the notice may not in fact have been delivered to the
Bank.
In order to give full effect to the provisions of this guarantee the Bank hereby
waives all rights inconsistent with the above provisions and which the Bank might
otherwise as a guarantor be entitled to claim and enforce.
Notwithstanding anything contained here in before, our liability under this
guarantee is restricted to Rs.____________(Rupees_______________________only) and
it shall remain in force until __________, unless a suit or action is filed against us enforce
such claims, within three months from the aforesaid date, all the Federation‟s rights under
this guarantee shall be forfeited and we shall be relieved and discharged from all liabilities
thereunder.
Place :
Date :
(SIGNATURE)
Seal
54
ANNEXURE – VII
Eligibility & Qualifications Criterion
1. The bidder shall furnish, as Part-I of its bid, documents establishing the bidder‟s
eligibility to bid and its qualifications to perform the contract if its bid is accepted.
The bidder should also give information in the format attached to the bid
document.
2. The documentary evidence of the bidder‟s qualification to perform the contract if
its bid is accepted shall establish to the purchaser‟s satisfaction :
(a) that in the case of a bidder offering to supply goods under the contract
which the bidder did not manufacture or otherwise produce the bidder has
been duly authorised by the goods manufacturer or producer to supply the
goods. The bid shall include Manufacturers Authorisation Form given under
Section-I. Offers from other agents, brokers & middlemen shall not be
accepted.
(b) that the bidder has the financial, technical and production capability
necessary to perform the contract. To this end, all bids submitted shall
include the following information under Section – II :
(i) Copies of original documents defining the constitution or legal status,
place of registration and principal place of business of the company or
firm or partnership etc.
(ii) Power of Attorney or a true copy thereof duly attested by a Gazetted
Officer in case an authorised representative has signed the bid.
(iii) Details of experience and past performance of the bidder (or each party
to a joint venture) on works of similar nature within the past five years,
and details of current works in hand and other contractual
commitments shall be submitted as per Schedule-I and Schedule-II
given in Section-II respectively of this bidding document.
(iv) Reports on financial standing of the bidder such as profit and loss
statements, balance sheets and auditors report of the past three years,
bankers certificates etc.
(v) Information regarding any current litigation in which the bidder is
involved.
3. For the purpose of this particular contract, bidders shall meet the following criteria
as minimum :
55
(a) The bidder should be in business of the jobs tendered for a minimum period
of five years at the time of bid opening in the same name and style.
(b) The bidder‟s annual financial turnover in the same name and style during the
last three years shall not be less than Rs. 20 crores in each year.
(c) The bidder in the same name and style shall have completed / having in hand,
the three projects of similar nature or above i.e. cattle feed plant capacity
150TPD or above.
(d) The bidder shall furnish a copy of the Income Tax Returns and the Income
Tax Clearance Certificates for the previous three years in original certified
true copies.
(e) Solvency certificate equal to 3 months requirements of cash flow at the peak
execution period for the project.
(f) Major items of plant and equipment available/installed in the bidders factory
premises.
(g) The bidder should have in house manufacturing setup for the Cattle Feed
plant & machineries and their spare parts to ensure proper support of spares
and services after successful execution of the project..
4. Bid submitted by a joint venture of two or more firms as partners shall comply
with the following requirements :
(a) the bid and in case of a successful bid, the form of agreement shall be signed so
as to be legally binding on all the partners; This parternership or association or
alliance or JV should have completed / having in hand, in the same form 3 or
more successful projects.
(b) one of the partners shall be nominated as being incharge and this authorisation
shall be evidenced by submitted a power of attorney signed by legally authorised
signatories of all the partners;
(c) the partner incharge shall be authorised to incur liabilities and received
instructions for an on behalf of any and all the partners of the joint venture and
the entire execution of the contract including payment shall be done exclusively
with the partner incharge;
(d) all the partners of the joint venture shall be liable jointly and severally for the
execution of the contract in accordance with the contract terms and a relevant
statement to this effect shall be included in the authorisation mentioned (b)
above as well as in the form of bid and the form of agreement (in case of the
successful bid) and
(e) a copy of the agreement entered into by the joint venture partners shall be
submitted with the bid;
(f) experience, resources, men and machinery of each party to the joint venture will
be taken into account only to the extent of their participation for performing
tasks under the joint venture agreement.
56
(g) A newly formed JV or partenership or alliance of any sort will not be eligible for
this project unless they have executed successfully / having in hand, at least
three similar feed plant turnkey projects.
5. Documents Establishing Goods – Eligibility and Conformity to Bidding
Documents
5.1 The bidder shall furnish as part of its bid, documents establishing the eligibility and
conformity to the bidding documents of all goods and services which the bidder
proposes to supply under the contract.
5.2 The documentary evidence of the goods and services eligibility shall consist of a
statement in the price schedule on the country of origin of the goods and services
offered which shall be confirmed by a certificate of origin issued at the time of
shipment.
5.3 The documentary evidence of the goods and services conformity to the bidding
documents may be in the form of literature, drawing and data and shall furnish :
(a) a detailed description of the goods essential technical and performance
characteristics;
(b) a list giving full particulars, including available sources and current prices of all
spare parts, special tools etc. necessary for the proper and continuing
functioning of the goods for a period of two years, following commencement of
the goods use by the purchaser ; and
(c) a statement of deviations and exceptions to the provisions of the technical
specifications demonstrating the goods and services substantial responsiveness
to those specifications in the form provided under Section-III.
5.4 The bidder should clearly confirm that all the facilities exist for inspection and
shall be made available to the inspecting authority.
5.5 Pursuant to Clause-5.3(c) above, the bidder shall note that standards for
workmanship, material and equipment, and references to brand names of catalogue
numbers designated by the purchaser in its technical specifications are intended to
be descriptive only and not restrictive. The bidder may substitute alternative
standards, brand names and/or catalogue numbers in its bid, provided that it
demonstrates to the purchaser‟s satisfaction that the substitutions are substantially
equivalent or superior to those designated in the technical specifications.
57
SECTION-I
MANUFACTURERS’ AUTHORISATION FORM
(Please see Clause 2(a) of Eligibility Criterion)
No.__________________________________Dated___________________________
To,
RAJASTHAN CO-OPERATIVE DAIRY FEDERATION
“SARAS SANKUL”, J.L.N. MARG,
JAIPUR – 302 017.
Sub : - Tender reference No._______________________________________.
Dear Sir,
We________________________________________ an established and reputable
manufacturers of ______________________________________________ having factories at
________________ and _______________________ do hereby authorise
M/s._____________________________________________ (Name and address of Agents) to
bid, negotiate and conclude the contract with you against tender reference
No.__________________________________ for the above said goods manufactured by us.
No company or firm or individual other than
M/s._________________________ ________________________________ are
authorise to bid, negotiate and conclude the contract in regard to this business against
this specific tender.
We hereby extend our full guarantee and warranty for the goods offered for supply
against your tender.
Yours faithfully,
(NAME)
for and on behalf of M/s.
(Name of Manufacturers)
Note : This letter of authority should be on the Letter Head of the manufacturing concern and
should be signed by a person competent and having the power of attorney to bind the
manufacturer.
58
SECTION-II – SCHEDULE-I
(Refer clause No.2(b) of Eligibility Criterion)
Major works successfully completed during the past five years
Sr. Name of Place Contract Name of Value of Time of Date
No. Work Reference Client work Completion of
Completion
Note : Indicae plant capacity and major parameters handled.
Completion Certificate from Clients should be enclosed with the bid.
59
SECTION-II – SCHEDULE-II
(Refer clause No.2(b) (iii) of Eligibility Criterion)
WORKS IN HAND DURING THE CURRENT FINANCIAL YEAR
______________________________________________________________________ Sr. Name Work Name Place Value Completion
No. of work order of client of work Order of Period Date
reference Work Order
Note : Indicate plant capacity and major parameters handled.
60
SECTION – III
TECHNICAL DEVIATION STATEMENT FORM
(Refer Clause 5 of Eligibility Criterion)
The following are the particulars of deviations from the requirements of the tender
specifications :
CLAUSE DEVIATION REMARKS
(Including justification)
Dated Signature and seal of
the Manufacturer/Bidder
NOTE :
(1) Where there is no deviation, the statement should be returned duly signed with an
endorsement indicating “No Deviations”.
(2) The technical specifications furnished in the bidding document shall prevail over
those of any other document forming a part of our bid, except only to the extent of
deviation furnished in the statement.
61
SCHEDULE - II
TECHNICAL SPECIFICATION
PROJECT INFORMATION (SUB SECTION – 1.)
BASIS OF DESIGN AND DESIGN DATA (SUB SECTION – 2.)
PROCESS FLOW DESCRIPTION (SUB SECTION – 3)
TECHNICAL DATA & INFORMATION TO BE
PROVIDED BY THE BIDDER (SUB SECTION – 4.)
PROJECT MANAGEMENT (SUB SECTION – 5.)
SCOPE OF WORK (SUB SECTION – 6.)
62
(SUB SECTION – 1.)
PROJECT INFORMATION
63
Project Information
“DESIGN, SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF 150 TPD
CATTLE FEED PLANT (EXPANDABLE UP TO 300 TPD) ON TURNKEY BASIS” EACH
AT LAMBIYANKALAN DISTRICT BHILWARA & PROPOSED SITE AT VILLAGE
HATHALAI (GUNDOGE) DISTRICT PALI (RAJ).
Introduction
1. The scope of this tender shall include only the design, fabrication, supply, erection,
testing & commissioning of the cattle feed manufacturing plant required for producing
150 Tons per day balanced cattle feed with a provision to expand the plant to 300 TPD.
The equipment shall include mainly intake conveyors, storage bins, auto batching,
grinding, molasses storage tanks, silos, mineral mix plant, molasses mixing, pelleting,
bagging, aspiration systems, air compressor and LT electrical. The scope of the bidder
shall necessarily include the supply as well as erection and commissioning. Any bid for
part job will be summarily rejected.
2. The plant will be installed on the fabricated MS structure and covered with the pre-
coated sheets and fitted with lighting and lightening arrestor by the bidder.
3. All the civil works, foundations, water, steam, molasses and electrical power shall be
provided by the Rajasthan Cooperative Dairy Federation Ltd., Jaipur.
4. The Tenderer shall be responsible for developing the conceptual layout and flow
diagram to ensure automatic operation of the plant with minimum investment.
5. Since this will be Turnkey Job it will be the full responsibility of the Tenderer to carry
out all minor works necessary to achieve the rated capacity of the plant even though
they might not have been expressly mentioned in the tender document.
6. All the equipment to be supplied will have to be manufactured as per the standard
specifications adopted by the cattle feed industry in the country.
7. This contract will be “Fixed Rate Contract” and the contractor will have to supply the
equipment and complete the erection and commissioning within the agreed contract
value and no escalation of prices will be allowed.
8. It is absolutely essential to complete the job of design, fabrication, supply, erection and
commissioning of cattle feed plant within six months from the date of signing the
contract and receipt of advance.
9. The tenderer is advised to visit to site so as to apprise himself of actual site condition
and quantum of work involved. Civil work at site already commenced and tenderer
should plan with consideration of actual site condition.
64
Instructions to Bidder
This section of the bidding document defines the way that bidders are required to structure the
presentation of the technical section of the bids. All technical data are to be provided in the
format given in this section. Any bidder not following the bid format structure or providing
insufficient technical data/information or presenting data that is not in the required format is
liable to be deemed non-responsive.
Introduction:
The bidder is to take note of the various points listed in the introduction and they are to describe
their technical proposal and systems, which they have applied in designing the plant. Also to
highlight any special technical innovation that the bidder proposes to include in the plant that
will improve the performance, reduce operating costs, reduce maintenance or improve product
quality.
The preamble should commence at the start of the process and work logically through the
process. Any such highlights should be cross referenced with the Bid Schedule, Annexure and
paragraph number to which they apply.
Technical Specification – Schedule – II.
Design Data and Design Basis
This sub-section gives in brief the design basis to be followed and gives the basic design data
like operating/storage capacities and special requirements for major equipment/system, the
typical ingredient types which will be used, required type and quality parameters of the feed
etc.
The bidder is required to follow the Basis of design given in the bidding document, and indicate
clearly where additional processes or alternative processes or equipment are considered to be
necessary or desirable to achieve optimum plant operating efficiency, optimum product quality
etc., within the standards specified, and optimum plant operating convenience and maintenance.
These additional items/sections & processes may be included as optional.
Process Flow Description
The tentative process description is detailed in this sub-section, which is also shown in the
tentative flow diagram enclosed with the bidding document, the preliminary site plan indicating
the proposed area of the feed plant is also enclosed.
It may please be noted that these drawings are only a tentative one to give an idea of buildings,
process and equipment required. It can be developed further as per the process flow and
equipment layout designed by the bidder to improve the operating flexibility and efficiency,
reducing maintenance, easier expansion in future, less investment etc. Additional or alternate
process or sections must be clearly detailed if proposed.
65
Technical Information and Data to be provided by the bidder with
Bids
This sub-section specifies the various technical drawings, data and information, which each
bidder has to provide along with their bid, without which the bid shall be considered incomplete
and will be liable for rejection.
Deviations from Technical Requirement
All technical deviations are to be stated. If there is no deviation, nil is to be recorded. This is
mandatory and failure to comply will make the bid liable to be deemed non-responsive.
Optional Items
Optional items, which the bidder proposes, shall be included in this sub-section. Items that the
bidder includes in this section shall be used if considered during the evaluation to be essential
for the satisfactory operation of the plant and shall not be included in the overall techno
commercial evaluation of the bid. All break-up prices for all such optional items to be given.
Major responsibilities of Bidder/Purchaser
Responsibilities of bidder: The bidder is required to specifically state his acceptance or non-
acceptance of each clause in this Sub-section. Non- acceptance shall be deemed as a deviation
from the bidding document, and should be mentioned in deviations.
Responsibilities of Purchaser: The bidder is required to state here any additional responsibilities
that they consider to be borne by Purchaser besides those described in the bidding document.
Project Management
Time Schedule: The bidder is to state the proposed schedule of execution from receipt of
order to commencement of product trials and handing over of the project. Bar Chart or PERT
network shall be provided.
Management Team: The bidder is to detail the make-up of the project management team in
terms of designation, qualifications and their role /function in accordance with this section of
the bidding document.
The bidder is to ensure that the following sections are fully detailed and quantify the duration
and manpower applied to each:
Commissioning, Product Trials & warranty runs
Training
Standby Technical Supervisory Support
Drawings and Documentation
In this section, list of drawings enclosed with bidding documents have been indicated.
Drawings and documentation to be submitted by bidders with their bid for technical evaluation
of the bids are explained (technical information and data to be provided by the bidder). Bidder
66
to indicate and list out in this section the drawings, data and documents provided for technical
portion of their bid.
Battery Limits
The battery limits of the various utilities and Engineering services are clearly given in this
subsection.
Performance Guarantees
The bidder is to take note of the various performance tests and guarantees stated in this sub-
section and confirm the same being given.
SCOPE OF WORKS
LIST OF EQUIPMENTS TO BE SUPPLIED, INSTALLED & COMMSSIONED
Design & Supply, Installation, Testing and Commissioning
In this section, a consolidated list of all major equipment to be supplied and installed as per
preliminary design of the plant by purchaser are indicated with capacity and quantities. The
bidder has to provide in this section a consolidated list of all major equipment being supplied
and installed as per their design and detailing along with quantity, capacity, size, length, height
etc. of each item. The bidder is required to follow the sequence in their list as followed in
purchaser‟s list as far as possible to enable purchaser to compare the bids for evaluation. New
items, if required, can be added section wise by bidder.
Technical Specifications for Feed Milling Equipment
It provides the brief general technical specification of each important feed milling equipment.
Lengths, heights, capacities, inlet, outlet, driving motor HP and drive parts etc. may be worked
out by the bidder to meet the overall capacities of section and complete plant as specified in
design data and process flow. It may be noted that specification of the equipment mentioned in
this section is very brief, but the bidders should ensure that all equipments are designed and
manufactured to ensure the best performance of the individual equipment / system. The
technical specifications of equipment are generally based on a particular design, but bidders can
supply equipment, as per their design, to meet the functional requirement of equipment
specified in these technical specifications.
Technical Specifications for Utilities/Services
This sub-section provides the brief technical specifications for the various utilities / services
including supply of its main equipment wherever required. The controlling and distribution
piping network with valves, fittings and all required accessories for utilities like LP steam,
Compressed air up-to each of the equipment where these are required is to be provided and
clearly indicated in the bid.
This sub-section also includes brief technical specification of electrical substation, all main
electrical equipment for receiving and distribution of electrical power in the plant and utilizing
it for control and monitoring of equipment / process. Though the prices of motors and geared
motors etc. may be included with the machines, the specifications of these are mentioned in this
section.
67
Technical Specifications of Production Block Housing
Under this sub-section technical specification of the production block housing steel structure,
side and roof sheeting, windows etc. shall be provided.
Technical Specifications for Erection, testing & commissioning
The bidder is to note carefully the specifications in the scope of erection, testing and
commissioning.
Technical details to be submitted by the bidder:
Under this section, the bidder has to furnish all the technical details for equipment, items under
the scope of supply for technical evaluation of the bid.
Preferred makes of bought out items Multiple makes for the bought items have been given,
category-wise. The bidder may choose the make of the bought items from the list provided.
68
(SUB SECTION – 2.)
BASIS OF DESIGN AND DESIGN DATA
69
Basis of Design
Design Data and Design basis of Cattle Feed Plant 150 MTPD, expandable to 300 MTPD Cattle
feed would be formulated by using various ingredients such as: Maize, Groundnut De-oiled
cake, De-oiled Rice Bran, Broken Rice, Rice Polish, De-Oiled Cotton Seed Cake, Molasses,
mineral mixture, common salt, urea, Wheat Br. Jawar, Bajra , Gur cake, Gur k., Rape, Ext.,
mus. cake, soya DOC, GNEXP, Barley, Dal Chura, D.Wheat, Calcite. etc.
Other Details
Capacity 10 TPH (Minimum) of pelletized feed for milk cattle (150 MTPD minimum with 20
hours operation)
Size of
pellets 4-10 mm diameter & 15 mm long
Formulated
System
Generally manual formulation is done by trial and error & method by combining
various cattle feed ingredients in different proportion by working out crude protein,
crude fat, crude fiber, ash, and energy content. The tenderer should provide software for
least cost formulation. The formulation will be done through the computer on the basis
of least cost formulation. The feed prepared shall be as per BIS standards.
Feed Standards
Proximate Composition of Cattle Feeds of BIS Standards
Type – II Type – I Special Feed for High
Milk Yielders
Crude Protein 20% Min 22% Min 24% Min
Ether Extract 2.5% Min 3% Min 4% Min
AI Ash 4% Max 3% Max 2.5% Max
Fiber 12% Max 7% Max 6% Max
Moisture 11% Max 11% Max 11% Max
ME 2200 Kcal/Kg Min 2500Kcal/Kg Min 3000Kcal/Kg Min
Urea 1% Max 1% Max 1% Max
Salt by Mass 1.5% Max 1.5% Max 1% Max
Calcium by mass 0.5% Min 0.8% Min 1% Min
Phosphorous by mass 0.5% Min 0.8% Min 1% Min
Vitamin A 5000 IU/Kg Min 7000 IU/Kg Min 7000 IU/Kg Min
Vitamin D3 1000 IU/Kg Min 1200 IU/Kg Min 1200 IU/Kg Min
Vitamin E 30 IU/Kg Min 30 IU/Kg 30 IU/Kg Min
Formula for Type II BIS Standard Feed
Ingredients Proportions
Rice Bran 14%
Rice Bran Extn. 42%
Mustard Oil Cake 3%
70
Mustard de-oiled cake 14%
Wheat/Maize/Barley 5%
Guar Korma 3%
Calcite Powder 1.5%
Urea 1%
Salt 1.5%
Molasses 8%
Malt Sprout 6%
Mineral Mixture 1%
Vitamin AD3 100 gram per ton
Total cost per Qtl. 100%
Typical Feed Formula used in Cattle Feed Plants of RCDF
(Tentative figures and can change with seasons/costing etc.)
Percentage Basis of Dry Matter
Existing Percentage Limit
D,R,BRAB 45 Minimum
R,BRAB 11 Minimum
R.KANI 5 Minimum
GUAR C. 14 Minimum
GAUR K. 38 Minimum
RAPE, EXT 10 Minimum
MAIZE 5 Minimum
MOLASSES 5.62 Minimum
CALCITE 1.5 Minimum
MINMIX 1 Minimum
SALT 1.5 Minimum
Note: A premix shall be made for mineral mixture, calcite, common salt, urea, with 2-3%
carrier DORB.
Typical Raw Materials
Maize, Groundnut De-oiled cake, De-oiled Rice Bran, Broken Rice, Rice Polish, De-Oiled
Cotton Seed Cake, Molasses, mineral mixture, common salt, urea, Wheat Br. Jawar, Bajra , Gur
cake, Gur k., Rape, Ext., mus.cake, soya DOC, GNEXP, Barley, Dal Chura, D.Wheat, Calcite.
etc.
Raw Material Storage
Raw Material Storage Description
In gunny bags, Roofed Godown
Enough built space is available for powder, oil
cakes, DORB & meals etc.
Bulk Storage silo Capacity 500 MT , Qty. 2 Nos. for DORB / Grain.
Average bulk density of solid raw materials 600 KG/CUM to 700 KG/CUM (Grains)
Cleaning, Unloading System Complete Unloading, Cleaning System of 50 TPH
with three trucks at a time & shed
71
Intake of Raw Materials
Premix batch mixer, horizontal, paddle type capacity (in Raw Material Godown).
Pre-weighed ingredients shall be dumped through a mechanized system of conveyor,
elevator in pre-mixer
1000 Kg – 1 No
Intake line to have PLC operated cascade type magnet, jute twine remover before
feeding to any of the proportionate bin. For feeding to proportionate bins, two sets of
distribution conveyors with PLC operated pneumatic slide gates to be used.
2 line of 40 TPH
Portable bag stack conveyor required for conveying / stacking DORB Bags/Other
Material etc. in RMG
2 set of 250
bags/ hr
Cascade Magnet, & Jute twine remover for each intake line. 2 set each of 30
TPH
SILO FOR GRAIN/ DORB STORAGE : Design, fabrication, supply , installation
and commissioning of DORB Silo System of 1000 MT (2x500 MT) capacity
complete with supporting steel structure and platforms as required for 150 MTPD
cattle feed plant as per technical specifications, scope of works, battery limits etc.
(Complete with required conveying system i.e. feeding & transferring system to the
plant)
One Job
Batching
Modular type Steel proportionate bins – (Total 16 Nos.) Level sensors
(2 nos.) shall be placed for each of the silos, to give indicative
information of levels and control of the filling and emptying operations.
One of the proportionate bins for premix shall be fabricated with 1 mm
thick SS 304 sheet inner lining. All bins shall have manual outlet gates.
16 Bin of 20 MT each.
Outlet Feeders from Proportionate bins. Gravity type & 250 mm screw
type (controlled by common VFD). : 16 Nos.
Automatic Batch weighment in two separate hoppers to get a composite
batch of 2 MT with load cells & display in Control Room & Mimic
panel
3 MT Hopper 1 No
Batch Chain conveyor 30 TPH 1 Set
Batch Elevator (Bucket Type) 30 TPH 1 Set
Grinding & Mixing
100 % Post Grinding ( Entire Batch is ground)
(One working & One Standby) (8 to 10 TPH) x 2
Maximum grindables in formulation 60%
Bin above Hammer Mill 3 MT – 2 No
Feeder for Hammer Mill ( Rotary vane type) (15 TPH) x 2 Nos
Hammer Mill ( Full circle type, Horizontal) with 4 mm Sieve (15 TPH) x 2 Nos
Hopper below Hammer Mill 2 Nos.
Bin above Batch Mixer with outlet gates 3 MT – 1 No
Batch Mixer with inlet & outlet gates 3 MT – 1 No
Surge Bin Below Batch Mixer 10 MT, 1 No.
72
Mixed Feed Chain conveyor 30 TPH – 1 Set
Mixed Feed Elevator (Bucket) 30 TPH – 1 Set
Pelleting
100 % pelleting of Mixed mash feed
Pelleting lines with provision of Second Line for future expansion. 1 lines of 10 TPH
capacity
Bins above Pellet mill 10 MT – 1 No
Loss in weight Feeders for proportioning the Feed & Molasses for a set
formulation 10 TPH – 1 Nos
Pellet Mill with conditioner & Molasses Mixer (Twin Paddle – Adjustable) 10 TPH – 1 No
Rotary Air lock ( SS 304) 10 TPH – 1 No
Pellet Cooler (vertical, Induced draft type) with ambient air 10 TPH – 1 Nos
SS 304 Cyclone separator for Fines with Aspiration ducting complete with
Sight Glass, Rotary Air Lock 1 set
Pellet Cooler fan (Exhaust type) 1 No
Pellet Feed Transfer conveyor 30 TPH 1 Nos.
Pellet Elevators ( Bucket Type) 30 TPH 1 Nos.
Pellet Sieve 10 TPH – 1 No
Molasses Handling
Molasses Storage Tank 400 MT 02 Nos.
Maximum Molasses to be added in the formulation 10 % Maximum
Molasses Pre-heater (Indirect Type; Horizontal insulated steel tank) 1 Job
Tanker unloading pumps ( Shuttle Block type , Motor with gearbox) (1
working + 1 standby ) 15 KLPH – 2 No
Molasses Feed pumps to plant ( Shuttle Block type , Motor with gearbox) -(2
working + 1 standby ) 3 KLPH – 3 No
Molasses Flow Meter for flow measurement (PID Controller type) 3 KLPH – 2 Nos
Molasses pipes , valves & fittings (Insulated) 1 Lot
Finished Feed Handling
CYLINDRICAL Bagging bins with 1 mm thick, SS 304 Lining
with outlet pneumatic Gates 20 MT 2 Nos.
Automatic Bagging System complete with placer, filler, weigher,
stitching with conveyor machine (with manual bagging system) 250 Bags/Hr set, 1 Set for 70
kg baqs
Bag Capacity (HDPE/Gunny Bags) 50 kg for HDPE &
70 kg for Gunny Bags
Electronic weighing machine check weighers 200 kg 2 No.
Slat conveyor to FPG with wooden slates. 250 bags/hr 1 SET 15 mtrs.
Portable Bag stack conveyor (2 Working + 1 Standby) 250 Bags/hr 3 sets
73
Automation
Automation for the main plant shall include controlled operation of electrically driven units,
with sensors / meters etc, with a predetermined logic to produce pellets from dumping of raw
materials in the godown, upto Bagging operation in the production plant. The Automation shall
optimise the power utilization and improve the overall operational efficiency of the plant. The
system also envisages collection of information from various points and shall collate such data
to determine losses, utility consumption/ unit of production and shall generate plant reports with
all necessary data.
Aspiration system with compressed Air generation
Few decentralized, modular type rather than one centralized. All dust producing
equipment/hoppers/bins to be connected to aspiration systems.
Dust collected to be reused.
Automatic compressed air operated compact units.
Feed Mill Housing, platforms, Pipe Bridge, trench covers.
RCC columns foundation excluding foundation bolts upto plinth, shall be provided by
purchaser & steel structure including structural platforms, staircase shall be in bidder's
scope.
Separate structure with the Main plant would be required for hammer mills and would not
be connected to the main plant structure.
Basement to be avoided to the extent possible. Limited basements or pits can be provided
for elevators legs and Freight/passenger elevators, and trenches for intake conveyors.
Wall cladding and roofing with GALVALUME (AL-ZINC) profile rib sheets. Minimum
thickness of Sheet 0.5 MM
Feed mill housing to have windows, regular industrial staircase, railing, steel chequered
plate flooring and artificial electric lighting. Provision of 1 MT capacity industrial Elevator
(Lift) to be made in the Main plant structure.
Pipe bridge between Boiler house and Main plant shall be executed as per site requirement.
Steam Distribution Condensate recovery
Low pressure steam piping from outlet of PRS to Main plant, in Pipe Bridge, for pellet mill
conditioner in feed mill, Molasses pre-heater etc shall be in the scope of work. Condensate
generated from Molasses pre-heating sections shall be returned to Boiler feed water tank.
Electrical Distribution
Electrical Power distribution for plant requirement 3 phase, 415 V, 50 Hz
Electrical panel for Main plant, Raw material Intake Equipments, Silo
System Equipments. 1 each
74
APFC panel with capacitors. 1 No.
Power cables for Main plant MCC shall be drawn from LT Panel
located in substation room. Raw material intake, Silo system shall be
drawn from Main Plant MCC.
1 Lot
Power & Control Cables, Signal cables , cable trays 1 Lot
Lighting Distribution Boards, Light fittings, cables 1 Lot
Lightening Arrestor with Earth-pits, Earthing Network 1 Set
Compressed Air Handling System
Generation of Compressed Air & its distribution, to meet requirement of complete plant for
pneumatic cylinders, cleaning and aspiration units is included in the scope.
Screw Air compressor (1 working + 1 standby) 60 CUM/Hr.
Refrigerated Air drier 60 CUM/Hr.
Air Receiver 1000 KL
Compressed Air pipes, valves , fittings including FRL etc.
General Requirements for Equipments
2 Nos. portable filled bag conveyor for mechanised conveying of bags to be provided for
transferring bags from Bagging System to the godown for stacking / upto point of loading in
trucks.
All bolted type drag chain conveyors shall have following:
Maximum linear speed 0.5 meter/second
Minimum cover plate thickness 2 mm
Minimum side plate thickness 4 mm
Minimum bottom plate thickness 4 mm
Minimum intermediate plate thickness 3 mm
All belt bucket elevator with flanged double trough shall have following
Maximum liner belt speed 2 meter/second
Minimum trough plate thickness 2 mm
Minimum head and bottom plate thickness 4 mm
All screw conveyers shall have the following Minimum trough plate thickness 3 mm
Minimum flight screw plate thickness 3 mm
Minimum too cover plate thickness 2 mm
Wear Parts
Following wear parts are to be supplied with the plant and their cost shall be considered in the
technical and financial evaluation: Pellet Mill die 5 Nos
Pellet Mill roller Shell 5 sets
Hammers for hammer mill 5 sets
75
Sieve for hammer mill 5 sets
Beaters and knives for molasses mixer 5 sets
Filter bags for aspiration unit 1 set for each unit
Flexible canvass/rubber sleeves 1 set for complete plant
Spare Jute twine remover rotor 4 sets
Spare parts
For one year operation of plant, spare parts to be indicated and quoted item wise separately, as
these shall be ordered separately as per the plants requirements.
Future Expansion
Plant to be designed for future expansion up to 300 MTPD capacity
Not in Scope of Supplier
Following shall be arranged by the purchaser and is not included in scope of supplier.
All building works for offices, godown, roads, service block etc., feed production block up
to plinth, molasses tanks foundation, foundation and building for silo system.
Fire fighting and detection wherever required.
Laboratory equipment
Workshop m/c and tools for feed plant operation.
Lighting for all buildings except production block of feed mill.
Internal Communication system.
Note:
Wherever there is a discrepancy with the technical specification of services utility in General
Terms of Contract – General, Electrical, Mechanical and Installation, specifications i.e.
Schedule – III, its interpretation in this section shall prevail.
The responsibility of design, performance of the proprietary equipment performance of bought
out equipment shall be with the bidder.
76
SUB SECTION – 3
PROCESS FLOW DESCRIPTION
77
Process Flow Description
Raw Material Intake
All the solid ingredients packed in bags for feed production would be received at the plant by
road. These shall be first weighed at Road Weigh Bridge (not in scope) and then samples will
be drawn for testing for acceptance. Acceptable ingredients in trucks shall then be directed to
either to Raw Material Godown or to Raw Material Silo system for its storage. At the Raw
Material Godown, the bags will be manually unloaded from the Trucks and stacked in the
Godown.
Trucks of DORB / grains / similar raw materials diverted to silo storage system, where raw
materials either in bags or bulk are unloaded manually & then dumped manually in dumping
hoppers and conveyed to any one of the bulk storage silos through a mechanised conveying
system.
As per the requirement of production, there are two sets of intake chain conveyors (30 TPH) in
the RMG for transferring ingredients to Main production plant. Ingredient bags are brought
manually to various dumping hoppers located suitably in the RMG, where the bags will be
opened manually and contents dumped. One cross conveyor in the RAW MATERIAL Godown
can be use for either pre-mix or RAW MATERIAL, as per requirement.
Ingredients such as salt, urea, and mineral mixture etc are to be added in batch in very small
quantity and hence a premix is prepared. The Mineral Mixture in prepared in a plant located in
the Godown. Pre-weighed quantities of mineral mixture per formulation for a batch are
manually dumped along with a pre-weighed carrier ingredient. Mineral mix & carrier ingredient
is mixed in a 500 Kg batch pre-mixer installed in Godown, installed on one of the cross
conveyors. After mixing, pre-mixed batch is conveyed to the 20 MT storage Bin.
Main intake conveyors transfer ingredients, to the adjoining Main production plant through set
of elevators. Raw materials from grain/DORB silos are also conveyed to production block
though a mechanised conveying system.
Ingredients on reaching the production block are directed to proportionate bins for storage
before batching. Before filling proportionate bins, the ingredients shall pass through Cascade
magnet (Hump back) and Jute twine remover, to remove ferrous impurities and other foreign
materials such as stems, jute fibre etc. Two intake lines from RMG & One intake line from Silo
system above proportionate bins, a set of cross conveyors & distribution conveyors are
provided to direct raw materials automatically to a pre-decided proportionate bin. Operation
and selection of Proportionate bin is done from control room through PLC logic.
Batching
Formulae containing various available ingredients in the plant based on least cost to produce a
specific type of balance concentrate feed are made available by quality control officer of the
plant for production. All the major & minor ingredients of these formulae are stored in 16 nos
proportionate bins. Plant is provided with two automatic microprocessor controlled batching
plants, one for major (1 MT) & other for minor (1 MT) ingredients, by which the desired
quantity of each ingredient and premix is discharged from proportionate bins into one main
hopper (for main ingredients) and other small hopper (for minor ingredients) to make a
78
composite batch of 2 MT (maximum). Once the batch is prepared, it is conveyed mechanically
to a 2 MT Bin above Hammer Mills.
Grinding & Mixing
Ingredients of one batch of 2 MT can be transferred into two Hammer mills from their
respective bins located above. The feeders for the hammer Mills regulates the flow of
ingredients to the Hammer Mill. Permanent magnet in feeder of Hammer mill separates ferrous
material from the ingredients before the batch is ground. Feeders of Hammer mills shall also
have provision to separate big size stone or lump of material in the feed before the batch is
ground. In the Hammer mill, the coarse material is broken into powder till they pass through the
sieve of the grinder. The operation of the Hammer mills and their feeders should be automated
& controlled by a VFD, based on the preset electrical load of the Hammer Mill.
Powdered ingredients are conveyed to the Bin above Batch Mixer. Powdered batch is fed into a
Ribbon type batch mixer through a set of pneumatic gates. Mixing of batch in batch mixer is
done generally for 2 to 3 minutes. Interlocks shall be provided to ensure exclusivity of batches.
Molassing
Molasses is an important source of energy and hence is generally included in the feed
formulation. Molasses is received at plant through road tankers and these after weighment on
Road weigh bridge , it is unloaded through a intermediate underground tank, & pumped to
vertical steel storage tanks. As per the requirement of production, molasses is drawn from the
storage tank by the feed pump. Molasses pumped to the plant, is pre-heated in a molasses pre-
heater before being fed to molasses mixer and feeder conditioners of pellet mills, in a controlled
manner for mixing with feed. The feed from the pelleting bin is drawn by a Loss–in-weight
feeder which regulates the flow of feed to the Pellet Mill. A fixed % of molasses is mixed to the
feed in the Molasses mixer. Molasses is metered before being sprayed within the molasses
mixer (major percentage) as well as in conditioner of pellet mills. Molassing of the feed shall be
automatically controlled (coarse controlled) by the speed of the feeder and fine control of the
molasses shall be done by the field operator, if required.
Pelleting
Feed is converted from mash form to pellet form by pelleting machines. In pellet mill, the
mixed molasses mash after being cooked with steam, is pressed between die & press rolls
resulting into formation of pellets, which are cut to required length by pre-adjusted knife of the
mill. Feeder for pellet mill shall control the feed to the Pellet Mill in the same way as feeder to
the Hammer mill. The pellet Mill shall be controlled for parameters such as constant electrical
load based on amperage of pellet mill and conditioning temperature in conditioner based on
PID loop. Steam controller shall control the steam inlet to the conditioner so as to achieve a
preset cooking temperature. Immediately after discharged from pellet mills, pellets are cooled
in counter current pellet coolers by flow of ambient air across column of pellets through a
suitable capacity Exhaust fan. Cooled pellets from the cooler are directed to the elevator by
gravity. These pellets are directed to respective pellet sieve for separation of crumbles from
79
pellets. The crumbles from the Pellet sieve is returned to the Pellet Mill conditioner and fines
from the cyclone shall be returned to feeder of pellet Mill for re-pelleting. Good pellets are
directed to any of the four Bagging bins for bagging.
Bagging & Dispatch
Finished product from one of the SS Bagging bins selected weighed, filled in Gunny / HDPE
bags in automatic bagging system, which shall place, fill, weigh, & stitch the bags
automatically for a pre-decided quantity. Filled bags are then conveyed to Finished Product
Godown on a slat conveyor. From the Finished product Godown, bags are conveyed to the
trucks for dispatch, through manual Bag stack conveyors.
Aspiration System
To minimize the generation of dust in the plant, all dust-generating points are identified and a
few small aspiration systems operating with compressed air and having filters and blower etc.
are provided which serve to a limited area. Aspiration connection is given to all major
conveying equipment. Dust Powder collected by aspiration system is put back to the system for
minimizing product losses.
Services
For supplying electric power to all the equipment, Motor Control Centre (MCC) for Main plant
is installed in the Electrical panel room of the Main plant, to which cables are connected to all
machines, control equipment like PLC panel, Mimic panel and remote control panels. Separate
panels for Raw material intake section & soft-starters shall be supplied to cater to RMG &
DORB load requirements. For operating the plant, the remote control panels / local control
panels shall be provided in each section for intake, grinding, molassing, pelletting and bagging.
For all automatic operations for the running of the plant, a PLC based system shall be provided
in the control room. The PLC and its computer, shall be located in the control room, are used
for automation of the plant operation.
Steam at 10.5 kg/sq.cm is generated in boilers located in the Boiler house. LP Steam is received
at the outlet of PRS and is piped through Pipe Bridge to the pellet mill area, where it is mainly
used to cook the molassed feed, in conditioner of pellet mills at a desired cooking temperature.
Steam line is traced along with the molasses feeding line to the molasses mixer with a common
insulation. All steam/condensate lines, valves & fittings shall be insulated & cladded to prevent
heat loss in piping.
There are number of pneumatic flaps and slide gates in the plant for diverting and controlling
the flow of material as per requirement of plant operation. For operation of these flaps and slide
gates, compressed air generated by Air Compressors, is fed to an Air receiver, before
distribution to various consumption points through pipes. Moisture is removed from
compressed air by a Refrigerated Air dryer before it is received in an Air receiver. Compressed
air is also used for purging operation of jet filters of aspiration systems.
80
Automation
Objective
Automation for this plant shall be intended to ensure uniform & preset parameters for quality in
production, uninterrupted operation of equipments, optimally run equipments and reduce
manual involvement & errors. PLC with SCADA shall be used to automate various operations
by sequencing the activities of the system, as per flow logic.
Raw Material Intake
The control panel operator with the information of level in proportionate bins in Main plant and
requirement, shall decide, which ingredients are required and information on the requirement
shall be flashed on the operator panel in the RMG/ DORB Godown for loading operation.
Ingredients on reaching the production block are directed to preset proportionate bin for storage
before batching. The operation of cross conveyor, respective distribution conveyor and
pneumatic gate for the proportionate bin shall be activated by the software logic of the PLC
depending on type of ingredient. Interlocks shall be made such that ingredients from different
intake lines do not fall into same distribution conveyor. Each proportionate bin shall have two
level probes to provide feedback on the status of bin and further loading /unloading operations
to the control room operator.
Batching
PLC based batching operation as per formulation arrived by QC officer, shall automatically
prepare batch from the ingredients available in proportionate bins. The outlet feeders (gravity &
screw) from the proportionate bins shall control discharge of all ingredients for a batch through
the software program specific for the recipe. The flow of minor ingredients shall be controlled
through a common VFD for accurate material dosage in the weigh Hopper. Batching is done in
two weigh hoppers, with a set of load cells of 750 Kgs capacity each, to prepare a composite
batch of 2 MT.
Grinding & Mixing
Probes shall be placed on the Grinding bin. Ingredients of one batch of 2 MT can be transferred
into two Hammer mills from their respective bins located above with Low and high level
indications for control of feed to the Hammer Mill Feeder. These feeders control the feed to the
Hammer mill, through a VFD through a PID loop. The current drawn by the respective grinding
hammer mill in turn controls the speed of the feeder. The batch is conveyed mechanically to the
bin above batch mixer. This bin has a low and high level sensor to avoid accidental mixing of
successive batches. The entire batch is mixed in batch mixer with timer controlled operation for
2 to 3 minutes. Interlocks are provided to ensure exclusivity of batches. For this level probes are
placed on the bin above Mixer.
Molassing
After grinding & mixing, the powdered feed is conveyed to pelleting bins. For a particular flow
rate of the Feed, a fixed % of Molasses by weight is measured for blending with the feed in the
Molasses mixer. The Molasses mixer shall be capable of mixing about 10 to 13% by weight of
Molasses to the mixed feed and is controlled by the speed of the loss-in-weight feeder. To
81
achieve this, a pneumatically /electrically operated control valve for Molasses is installed to
regulate Molasses feed to Mixer & conditioner to control molasses in coarse adjustment.
However, Final correction of Molasses if required can be done by the operator, near pellet mill.
Pelleting
Feeder for pellet mill shall control the feed to the Pellet Mill in the same way as feeder to the
Hammer mill. Pelleting bins, shall have High and Low level probes to control the operations of
the equipments before and after bin. The pellet Mill shall be controlled for parameters such as
constant electrical load based on amperage of pellet mill and conditioning temperature in
conditioner based on PID loop. The temperature of conditioned feed shall be set in the PLC, as
per requirement and the flow of steam regulated through a control valve and temperature sensor
with transmitter. Steam controller shall control the steam inlet to the conditioner so as to
achieve a preset cooking temperature.
Bagging & Dispatch
Pellets from vibro-sieve are directly discharged into any of the two bagging bins, through a set
of pneumatic flaps before being bagged. High and low level probes in this bin shall control the
operation of upstream and downstream equipment. Pellets from the bagging bin are discharged
to Automatic bagging system wherein bags are automatically placed, filled, prefixed quantity of
pellets is filled & stitched in a sequence. PLC shall keep track of the no. of bags bagged for
particular formulae and data shall be used to compile the production figures and in a shift /
day/month/year and overall losses. There should be the provision for Manually Bagging system,
in case of any failure in automatic bagging system.
General Requirement:
The system shall be used to automate and co-ordinate, monitor the plant operations for
production, to ensure smooth and continuous operations.
All idle machinery shall be put off when not in use.
Systematic and regular report generation for shift, day, month, year to be made available.
Various recipes for formulation shall be created as per Least Cost Formula & provision for
changing the recipe from time to time by Quality control officer shall be included feature in
the scope.
Production reports for shift, day, month, year shall be generated and hence loss report shall
be prepared.
Operating loads of Hammer Mill & Pellet Mill motors shall be tracked and recorded.
Inputs for Steam flowmeter in Boiler house shall be picked up & recorded and consumption
of utility/ton of production shall be calculated.
The density variation with temperature for Molasses along with Flow rate shall together be
computed in the PLC to arrive at the mass of Molasses being fed in the Molasses Mixer.
All hardware for dynamic and static panel, PLC, panels shall be supplied.
PLC for the Main plant shall communicate with the PLC for the silo system. Main PLC
shall receive data and instruction from Silo PLC for loading, unloading/transfer operations.
The control room shall house the PLC panel, Control system for SCADA shall be dust free
& air conditioned. For this a suitable capacity split type air conditioning unit shall be
supplied and installed.
82
SUB SECTION – 4
TECHNICAL DATA & INFORMATION TO BE
PROVIDED BY THE BIDDER
83
Technical Data & Information to be Provided by the Bidder
Flow Diagram
This shall be for the complete plant being offered similar to one prepared by purchaser and
attached with bidding document, starting from receipt of material from godown / silos,
production and conveying of finished product to godown. Flow diagram also to include raw
material storage silo system. All sections of feed mill including aspiration, utilities, pre-mix etc.
have to be indicated.
Equipment Layout
The scaled layouts shall be in the form of plans (for each floor), sections and elevations with
major dimensions of the equipment as well as that of the building for production block
suggested by the bidder.
Modular Layout of Production Area
Layout similar to one prepared by purchaser and attached with bidding document shall be
shown in one drawing (plan) the overall relative locations of RMG, FPG, Production Block,
Mineral Mixture Plant, By-pass Protein Plant, Raw Material Storage Silo System, Molasses
Tanks, Boiler House, Electric Sub-station, Engineering Workshop and Store. The design of the
plant building shall take into account of wind loading (maximum as per historical data), seismic
zone of the area.
Services Schematics
For all the services like air, LP steam, Molasses, separate single line schematic diagram
indicating piping with valves, fittings etc., up to utility points to be provided.
Electricals
1. Consolidated List of Motors ( equipment-wise), with drive mechanism, connected KW/HP,
RPM of Motor, Type of Geared motor/Gear box, RPM of driven parts, Full Load amperes
of drives
2. Consolidated single line power diagram of electrical installation showing Motor Control
Centres, PLC Control panels, Remote panels, APFC Panel, Electric motors
3. The total capacity of capacitors considered in KVAR for APFC panel for total load and
their quantity and individual ratings.
84
Equipment
List of equipment (Section-wise) with adequate brief specification of each item including
construction material, critical thickness, length/height/ capacity, drive details, make/model etc.
Additional technical details of following main machine:
Machine / Technical Detail Unit Detail
Pellet mill Die
Inner Diameter mm
Overall width mm
Working width mm
Working Area Sq.mm
Effective length mm
Total Thickness mm
MOC
Expected Life MT
Press Roller shell
Inner Diameter mm
Overall Diameter mm
Pad width mm
Pattern of outside of shell
MOC
Expected life MT
Motor HP
Driven pulley size:
Motor pulley size :
No of belts :
Conditioner
Diameter mm
Length mm
Steam requirement at full capacity Kg/hr
Cooking time at full capacity sec
MOC
Motor HP
Hammer Mill
Screen area sq.m
Size of the beater (LXBXT)
Tip speed m/min
Open screen Area / HP sq.cm
Open screen area %
85
MOC & No. of beaters in one set no.
Distance between Hammer & screen mm
Expected life of beaters MT
Batch Mixer ( 2 MT & 0.5 MT )
Main body thickness mm
Size L X B x H
Air Cylinder dia and stoke in mm
No. of paddles
RPM after speed reduction rpm
Motor HP
Molasses Mixer
Main body thickness mm
Size L X B x H
No. of paddles
RPM after speed reduction rpm
Motor HP
Mineral mixture plant
Pellet cooler Blower: Air flow rate : ________ cum/hr at ______ static pressure differential
Chain Conveyor
General arrangement drawing of a typical chain conveyor showing thickness of various plates,
detail of wear plates, detail of chain, designed breaking load, chain speed, type of bearing, drive
arrangement, etc.
Bucket Elevator
General arrangement drawing of a typical belt bucket elevator showing thickness of various
plates, size, type and thickness of buckets, size and type of belt, type of bearings, belt speed,
drive arrangements, head and tail pulley etc.
Screw Conveyors
General arrangement drawing of a typical screw conveyor showing thickness of various plates,
size and type of main shaft, pitch of screw, type of bearing, screw speed, drive arrangement,
drive parts etc.
Proportionate Bins and Big Bins / Hoppers
General arrangement drawing of a typical proportionate bin and a big hoppers, molasses tanks,
showing thickness of various plates, height and diameter, flange joints, slops and construction
material, inspection window, sight glass etc.
Feed Mill Housing Structure
General arrangement drawing of elevation and section showing columns, beams, side cladding,
roof cladding, windows, flooring etc.
86
Approx. quantity of following to be provided for technical evaluation:
Item Quantity Other Details
Structural steel for Main plant, pipe bridge In MT
Chequered plate flooring material In MT
Side cladding In Sq.mts Thickness & profile
Roof Sheeting In Sq.mts Thickness & profile
Windows In Sq.mts
Bidder shall quote for a minimum quantity of 250 MT of Structural steel for plant Main
structure, pipe bridge including platform, trench covers based on which the bids would be
assessed.
Automation System and PLC Panel
Details of the Automation scheme, network diagram, type & model of the PLC offered
Technical detail of Raw material loading in bins, auto-batching, Hammer Mills load
controlling, Molasses dozing, feed conditioning & computer system with a write-up
describing the process controls, type of reports that can be printed and provision for future
expansion. Detail of input/ output ports and other technical details of the PLC panel &
hardware of computer systems.
87
Make/Model Specific Important Details of Following Equipment/Items – 1
Description Make of Items
1st Preference 2
nd Preference
Screw Discharger
Chain Conveyors
Screw Discharger
Bucket Elevators
Paddle Batch Mixer
Hammer Mill
Molasses Mixer
Bin Activators
Pellet Mill
Rotary Air-locks
Bagging of Weigher
Bin Discharger
Counter Current Pellet Cooler
Aspiration Filter
Centrifugal Fans
Air-compressors
Air dryer
Molasses Flow meter
Load cells for Weighing System
Computer System
PLC
Software for Plant operations
Electric Motors
Geared Motors
Gearboxes
Molasses Pumps
Motor Control Centre (MCC)
Power and control cable
Pneumatic cylinders and solenoid valves
Structural Steel
Light fittings
Loss-in-weight Feeder
Air Conditioner
Utility Pipes
Condensate rec. system
88
Make/Model Specific Important Details of Following Equipment/Items – 2
S. No. Name of Items Makes of Items
1st Preference 2
nd Preference
1 ACB and its relays
2 Moulded Case Circuit Breaker (MCCB)
3 Motor Protection Circuit Breaker (MPCB)
4 Switch Disconnector Fuse Unit
5 HRC Fuse Links
6 Miniature Circuit Breaker (MCB)
7 Soft-starter
8 Variable Frequency Drive (VFD)
9 Contactors
10 Starter Relays
11 Electronic Timers
12 Push Buttons
13 Indicating Lamps
14 Current Transformers
15 Measuring Instruments
16 PVC Insulated Control wires
17 PVC Insulated Power wires
18 Terminal Blocks
19 Junction Box
20 Power Isolator
21 Power Capacitor
Deviations From Technical Requirement
This bidding document provides guidelines for the processes and equipment to be used for the
cattle feed plant and the „Design data and Design basis‟ and „Technical Specifications‟ define
the qualitative parameters and frame work against which equipment will be required to perform.
It is imperative on bidders to provide the fully detailed technical specification of the equipment
and services, which they intend to provide, to fully execute the contract in line with the bidding
document. Items, which deviate from the bidding proposal, shall be as per design specifications
of the bidder and shall be treated as a deviation from the text of this bidding document.
Deviated items should fulfil the minimum performance parameters as specified in this bidding
document. This bidding document does not allow bidders to make exclusions from any part of
the bid and an incomplete list of equipment or an incomplete schedule of service utilities to be
provided would be considered as a non-responsive bid.
89
Optional Items
There may be items or sections offered as „OPTIONAL‟ by the bidder. The entire system shall
be designed with all provisions to include the optional items in such a way that no major
changes would be required in the system. The specifications of `Optional‟ items shall be the
same as that of similar items in the tender.
The cost of `Optional‟ items shall not be included in the calculation of total bid price for
evaluation. In the event that the optional items are selected by the purchaser for supply, these
shall be in addition to evaluated price. The quoted price for the “optional” item shall include all
incidental costs of installing that item as part of the contract.
Break Up Price
For all items including LOT or SET items, which are detailed in the bidding document, break-
up price whether in Nos., RM or Sq. meters, Kilograms or MT is to be provided. unless
specifically asked under technical information and data, which is meant only for technical
evaluation and not for the commercial evaluation of the bid. The bidding document will be
evaluated on a total lump-sum basis as specified price schedule.
90
SUB SECTION – V
PROJECT MANAGEMENT
91
Project Management
Major Responsibilities of Bidder & Purchaser
Major responsibilities of Bidder
1. Developing the process design, complete engineering design supply of all equipment and
systems, ensuring best performance of individual equipment/system, for which bidder shall
avail the assistance of reputed specialists in their respective fields, wherever required, as per
the details given in the bidding document and as per battery limits.
2. Performance and suitability of the total system: Performance tests should be carried out by
the bidder in the presence of and to the satisfaction of Purchaser.
3. Arranging and obtaining approvals from various statutory authorities on behalf of the
Purchaser. The statutory fees shall be reimbursed by the Purchaser on production of
receipts.
4. Ensuring satisfactory performance, training of operating staff, stand by services after
commissioning and after sales services of the complete plant supplied and installed.
5. First charge of oil, lubricants and consumables. “First charges” means that these items shall
be replenished whenever and wherever required till the successful completion of product
trials. However, supply of electricity, water, petrol and diesel etc. is not covered in bidder‟s
scope.
6. Test kits required for establishing performance parameters.
7. Necessary manpower and tools for installation, testing and commissioning
8. Performance guarantees with regards to the following:
a. Rated performance of individual equipment and complete system.
b. Product quality standards conforming to the prevailing Standards.
c. Three sets of installation, operation and maintenance manuals of all machines should
be supplied. Two sets should be handed over to Site while handing over the plant to
Site Engineer/Project Authority along with the equipment while the third set is to be
handed over to the RCDF controlling office. As built drawings in soft i.e. in CD
(AUTOCAD) with manuals to be handed over to purchaser.
9. The Bidder shall furnish to the Purchaser, the total load on each of the foundations to enable
the purchaser to design & arrive at the footing/pedestal details.
10. The Bidder shall furnish all equipment details as indicated in Technical Data & information
to be provided by Bidder
Major responsibilities of Purchaser
1. Temporary store at site.
2. Details of civil design, building layout and drainage and sewage details.
3. Adequate labour force with operators/supervisors and engineers for trial, testing and
commissioning at no charge.
4. All buildings including roads, drainage and minor civil works during plant and pipe work
installation.
5. Provision of services, Raw material, packaging material etc.
6. Fire fighting system.
7. Lighting distribution system in RMG and FPG and non-plant areas.
92
8. Internal telephone system.
9. Engineering personnel to liase with the supplier, Project Manager and the execution team.
10. Provision of personnel for training and on going jobs supervision.
11. Telephone facility on chargeable basis.
12. Permanent water and power supply at the time of testing and commissioning of the plant,
including petrol and diesel etc.
Project Management
1. The project execution shall be time-bound as per the mutually agreed time schedule.
Supplier shall nominate an experienced project engineer who shall be responsible for
activities of project in office and site. A competent execution team shall be deputed at site
by supplier who shall be stationed at site and adequately experienced in Project
Management of such magnitude and type.
The Project Engineer shall avail assistance wherever required from reputed experts in
various fields who shall be directly responsible for satisfactory execution. The Project
Engineer shall be responsible for overall implementation of the entire project, from
commencement to the final take over of the plant. The services of the Project Engineer shall
be ensured for the day to day operations and coordination to ensure successful and
satisfactory design, procurement, manufacture, inspection, erection, testing and
commissioning of all the equipment/ facilities/systems within the time-bound schedule. He
shall be assisted by a Site Engineer to take care of all site activities.
The Project Engineer and Site Engineer shall attend all technical and review meetings
between various parties involved in the project and ensure implementation of all decisions
taken in the meetings. The Site Engineer shall be responsible for detailed material
accounting at site and management of the store maintained at site.
2. The purchaser shall also nominate a Project In-charge with whom the supplier shall
communicate/coordinate. The purchaser shall also post a Site Engineer at project site for
supervision and coordination with Site Engineer of the supplier. Approval on technical
documentation (with or without specified amendments) shall be given by purchaser within
ten working days after submission. The amendments which are not in the original scope of
work or due to changes in concept, shall be taken-up by the supplier as per mutually agreed
rates (decided either before or after execution), and shall be binding on the supplier.
3. Supplier shall obtain approval for purchase of specific makes of equipment whose makes
are not mentioned in his offer. If two or more makes of the same equipment are mentioned
in the form of alternatives, the supplier shall seek approval for choosing one make over
another. All the detailed design calculations regarding the selection of equipment sizes,
system types, etc. shall be submitted to Purchaser for their specific observation and record
whenever asked for.
4. The supplier‟s Project Engineer will provide to the purchaser‟s Project In-charge with
monthly progress reports which clearly indicate the actual vis-à-vis planned progress and
the new likely completion date of supply, erection and commissioning of the plant.
5. For indigenous items, the supplier shall invite Purchaser for inspection and preliminary
testing. The inspection may be required at various stages of manufacture/assembly for some
items.
93
6. Details of documentation to be submitted shall be according to the overall project
programme. The Project / Site Engineer of supplier shall be fully authorised to take on the
spot decision with regard to:
a. Modification in layout and execution programme to suit local conditions.
b. To purchase essential materials from local market to avoid delays.
7. For smooth execution of the project, the supplier‟s team of Project Engineer, Site Engineer
and key Personnel shall remain consistent throughout the execution period.
8. After satisfactory erection and testing, competent commissioning team shall be deputed to
establish the performance parameters for a specific period.
Testing & Commissioning
After installation of all equipment and completion of product piping and connection of all
utilities including electrical, all major equipment shall be tested at no load after checking all
alignments. On completion of satisfactory no load test, section-wise testing at no load shall be
carried out. Any defect notice during no load shall be attended to. After testing of all sections
on no load, the plant as a whole shall be tested with raw material for trial run and ultimately
commissioning the complete plant to the satisfaction of purchase/project authority.
Establishing Performance Guarantees
On completion of supply, erection, testing and commissioning of the plant, the plant has to be
operated at full capacity continuously in 3 shifts of 8 hours basis for seven days to the
satisfaction of the Purchaser/Project Authority, to establish performance guarantees provided by
the bidder. However if purchaser/client is unable to provide operating staff for three shifts,
number of days can be increased with mutual discussions.
Performance Guarantees
If the plant or any part thereof does not give the offered process performance, capacities and
consumption guarantees as confirmed in design data and technical data and information, during
the commissioning due to reasons attributable to the supplier, suitable recovery shall be made
by purchaser from supplier‟s bill.
Training
Training of plant personnel in the operation and maintenance of the various equipment of the
plant shall form an important component of Project Management. Training shall be imparted by
the bidder for a period of two weeks during which the contractor should guide and train the
staff of the client in operation and maintenance of the plant equipment to achieve the optimum
plant efficiency and product quality. Training should commence during the testing/
commissioning period and shall include:
1. Familiarization with all major feed milling equipment of all sections of the feed plant and
utilities etc. including the operation of the computer/PLC based auto batch weigher and
other systems.
2. Procedure for attaining the rated output and optimum product quality.
94
3. Familiarization with the basic principle of Electronic/Electrical control systems, including
faultfinding.
4. Familiarization with start-up procedures, regular maintenance and operational procedures
including dismantling of machine parts, replacement of spares/components, preventive
maintenance etc.
5. Condition monitoring of equipments.
6. Generating production and maintenance log sheets of important equipment and systems.
Training shall be given to all the personnel required to operate the plant, and their immediate
Supervisors/ Engineers.
The training schedule should be proposed by the bidder together with the content of training
programmes, their duration etc.
Standby Services after Commissioning
Once the commissioning and warranty runs are over and the plant is taken over by
Purchaser/Project Authority, the supplier shall provide to the plant standby technical
supervisory support as follows:
1. For one week after warranty runs in which further training of the Purchaser/Project
Authority's operating staff shall be done and equipment/system still needing finer
adjustment/changes shall be carried out.
2. For two days after 4 months, 8 months and 1 year from warranty runs, to have discussions
with plant staff and assistance to review the correctness of operations / maintenance
procedures and necessary corrections.
3. These visits of the Supplier are other than those covered under guarantee/warranty clause,
which shall be undertaken whenever required separately.
The bidder shall provide drawing/data and technical details with their bid as specified in tender.
After commissioning and during handing over of the plant by Supplier to Purchaser/Project
Authority, the contractor to provide the following:
1. As executed final drawings and technical data of the complete plant for operation,
maintenance and permanent record in soft and hard copies.
2. The final software and source codes of the systems.
3. A consolidated operation and maintenance manual of the complete plant along with
operation and maintenance of each key equipment as provided by manufacturer.
95
SUB SECTION – VI
SCOPE OF WORK
96
Scope of Work
List of Major Equipment to be Supplied and Commissioned
The list given below of equipment is as per preliminary design of the plant by Purchaser. The
detail list of equipment & their individual capacity may vary as per design and detailed
engineering by the bidder to achieve the minimum plant‟s rated capacity of minimum 7.5
MT/Hr ( 150 TPD for 20 operating hours) or as specified in design data & battery limits. If
required, the bidder can break-up an item into further detail, but wherever purchaser has
indicated quantity as one lot, no further detail is required. Bidders may add additional items
section wise if these are required as per their detail engineering.
These additional / optional / alternatives items offered by the bidder will be considered during
technical evaluation of the bids and would be subjected to acceptance by the purchaser.
Schedule of Quantities for Design, Supply, Installation, Testing and Commissioning of Equipment
Part - A
CFP LAMBIYAKALAN DISTRICT BHILWARA
PART 1. : DESIGN, FABRICATION, SUPPLY OF MAJOR EQUIPMENTS, FOR 150
TPD CATTLE FEED PLANT (EXPANDABLE UP TO 300 TPD) ON TURNKEY BASIS.
LIST OF MAJOR EQUIPMENT
S. No. Description Capacity/Size
(cm=Cubic
Meter)
Quantity Unit Price
Rs.
Amount
Rs.
1 RAW MATERIALS STORAGE EQUIPMENTS
1.1 Silo System for DORB/Grain Storage
with handling & Transferring system. 500 MT
2
1.2
Complete Unloading, Cleaning System
of 50 TPH with Three Truck at a time
and Shed -- 1
2 RAW MATERIALS INTAKE
EQUIPMENT
2.01
INTAKE CHAIN CONVEYOR IN
RMG WITH PNEUMATIC SLIDE
GATES
40TPH 55RM 2
2.02 DUMPING HOPPERS FOR INTAKE
CONVEYORS IN RMG 2 M x 1 M 10
2.03 ASPIRATION UNIT FOR DUMP
HOPPERS IN RMG -- 10
2.04 ELEVATOR FOR BATCH PRE-
MIXER 10 TPH 1
2.05 HOPPER ABOVE BATCH MIXER
WITH PN. GATE 1 MT 1
2.06 BATCH MIXER FOR PREMIX DUTY
WITH PNEUMATIC OUTLET GATE 1 MT 1
2.07 HOPPER BELOW BATCH MIXER 1 MT 1
97
2.08 ELECTRONIC PLATFORM
WEIGHSCALE 200 KGS 2
2.09 PORTABLE BAG STACK
CONVEYORS
250 BAGS/HR;
10 M 3
2.10 INTAKE BUCKET ELEVATOR 40 TPH 2
2.11 ASPIRATION UNITS FOR INTAKE
ELEVATORS -- 2
2.12 CASCADE MAGNET 40 TPH 2
2.13 JUTE TWINE REMOVER 40 TPH 2
2.14 CROSS CONVEYOR 40 TPH 1
2.15 DISTRIBUTION CONVEYORS 40 TPH 2
3 BATCHING EQUIPMENT
2.01 PROPORTIONATE BIN WITH
OUTLET GATE 20 MT 16
3.02 ASPIRATION UNITS FOR
PROPORTIONATE BINS 1 SET
3.03 GRAVITY FEEDERS FOR BIN
DISCHARGE 16
3.04 REDLER CHAIN CONVRYOR FOR
BIN DISCHARGE 250 MM 16
3.05 BATCH WEIGH HOPPER ( MAJOR
INGREDIENTS) 3 MT 1
3.06 BATCH WEIGH HOPPER( MINOR
INGREDIENTS) 1 MT 1
3.07 PNEUMATIC GATE BELOW WEIGH
HOPPER -- 2
3.08 SURGE HOPPER BELOW BATCH
WEIGHER -- 2
3.09 BATCH CHAIN CONVEYOR 30 TPH 1
3.10 BATCH BUCKET ELEVATOR 30 TPH 1
3.11 ASPIRATION UNITS FOR BATCH
ELEVATOR -- 1
4 GRINDING, MIXING EQUIPMENT
4.01 GRINDING BIN WITH PN. GATE 3 MT 2
4.02 FEEDER ABOVE HAMMER MILL 15 TPH 2
4.03 HAMMER MILL WITH 6 or 8 MM
SIEVE 15 TPH 2
4.04 HOPPER BELOW HAMMER MILLS -- 2
4.05 ASPIRATION UNIT FOR HAMMER
MILLS -- 2
4.06 BIN ABOVE BATCH MIXER 3 MT 2
4.07 PNEUMATIC GATE ABOVE BATCH
MIXER -- 1 SET
4.08 BATCH MIXER ( RIBBON TYPE) 3 MT 1
4.09 PNEUMATIC GATE BELOW BATCH
MIXER -- 1 SET
4.10 HOPPER BELOW BATCH MIXER 10 MT 1
98
4.11 CONVEYOR BELOW MIXER 30 TPH 1
4.12 MIXED FEED ELEVATOR 30 TPH 1
4.13 ASPIRATION UNIT FOR MIXED
FEED ELEVATOR -- 1 1
5 PELLETTING EQUIPMENT
5.01
MIXED FEED TRANSFER
ELEVATOR WITH OUTLET CASCAD
MAGNET.
30 TPH 1
5.02 PELLETING BIN WITH BIN
ACTIVATOR 10 MT 1
5.03 VARIABLE SPEED LOSS IN WEIGHT
FEEDER WITH HOPPER 10 TPH 1
5.04 PELLET MILL WITH CONDITIONER
AND MOLASSES MIXER 10 TPH 1
5.05 ROTARY AIR LOCK FOR PELLET
COOLER 10PH 1
5.06 COUNTER CURRENT PELLET
COOLER 10 TPH 1
5.07 PELLET COOLER CYCLONE (SS 304)
WITH PN.HAMMERS. -- 1
5.08 ROTARY AIR LOCK FOR CYCLONE
(SS ) 10 TPH 1
5.09 PELLET COOLER FAN -- 1
5.10 ASPIRATION DUCTING FOR
PELLET COOLER (SS 304) -- 1 SETS
5.11 PELLET ELEVATOR 30 TPH 1
5.12 PELLET SIEVE 30 TPH 2
5.13 SPARE MOTOR FOR PALLET MILL -- 1
5.14 SPARE MOTOR FOR CYCLONE
BLOWER -- 1
6 MOLASSES STORAGE / HANDLING EQUIPMENT
6.01 MOLASSES STORAGE TANK 400 MT 2
6.02 MOLASSES UNLOADING TANK
(WITH HOSE)
6.03 MOLASSES UNLOADING PUMP (1
Working + 1 Standby) 15 KLPH 2
6.04 MOLASSES PRE-HEATER 1 1
6.05 MOLASSES FEEDING PUMP (1
Working + 1 Standby) 3 KLPH 2
6.06 MOLASSES FLOW METER 3 KLPH 1
6.07 MOLASSES PIPING, CONTROL
VALVES,FITTINGS -- 1 LOT
7 BAGGING EQUIPMENT
7.01 BAGGING BIN (SS LINED) 20 MT 2
99
7.02 PNEUMATIC SLIDE GATE -- 2
7.03
AUTOMATIC BAG PLACING,
WEIGHING,FILLING, STITCHING
MACHINE WITH CONVEYOR &
CONTROLLER
250 BAGS/HR 1 SET.
7.04 SLAT CONVEYOR - With WOODEN
slats.
250 BAGS / HR;
25 M 1 SET
7.05 PORTABLE BAG STICHING
MACHINE -- 2
7.06 ELECTRONIC WEIGH SCALE 200 KG 2
7.07 PORTABLE BAG STACK
CONVEYOR
250 BAGS / HR;
10 M 2
8 FEED MILL HOUSING
8.01 MS STRUCTURAL STEEL FOR MAIN
PLANT AND PIPE BRIDGE 240 MT Approx.
8.02 MILD STEEL CHEQUERED PLATE
PLATFORM,TRENCH COVERS ETC 60 MT Approx.
8.03 WINDOWS As per Design
8.04 ROOF SHEETING As per Design 0
8.05 CLADDING SHEETS As per Design 0
8.06 LIGHT FITTINGS & LAMPS ( MAIN
PLANT) -- 75 SETS
9 PRODUCT PIPING/ ACCESSORIES
9.01 PRODUCT PIPING/DUCTING, FLEX.
CONNECTIONS -- 1 LOT
9.02 SMALL HOPPERS/TRANSITION
PIECE -- 1 LOT
9.03 PNEUMATIC GATES FOR PROP.
BINS FILLING -- 1 LOT
9.04 PNEUMATIC PIPE FLAPS -- 4
9.05 SIGHT GLASS FOR AIR LOCK -- 2 SETS
10 AUTOMATION EQUIPMENT
10.1
LOAD CELL WITH WEIGHING
SYSTEM FOR BATCH WEIGHER
EACH
1 MT; 1 MT 1 SET
10.2 LOAD CELL FOR LOSS-IN-WEIGHT
FEEDER -- 2 SETS.
10.3 PROGRAM SOFTWARE FOR THE
ENTIRE PLANT -- 1 SET
10.4
PLC PANEL , HMI , SENSORS,
COMMUNICATION & DATA
CABLES
-- 1 LOT.
10.5 MIMIC PANEL, COMPUTER FOR
CONTROL ROOM -- 1 SET
10.6 COMPUTER FURNITURE
(MODULAR) -- 1 LOT
10.7 UPS FOR CONTROLS & PLC -- 1 SET
100
10.8 COMPUTER WITH MIS OF PLANT
INFORMATION IN ENGG. OFFICE -- 1 SET
10.9 INSTRUMENT EARTHING ( CU
PLATE) FOR PLC LOT PANEL ETC -- 1
10.10 SPLIT TYPE AIR CONDITIONING
UNIT FOR CONTROL ROOM -- 1 SET.
SERVICE EQUIPMENTS
11 ELECTRICAL EQUIPMENT (LT)
11.01 Main LT Panel
11.02 MCC FOR MAIN PLANT -- 1
11.03 REMOTE PANELS FOR FEED MILL
EQPTS -- 1 LOT
11.04 AUTOMATIC POWER FACTOR
CORRECTION PANEL -- 1
11.05
MCC FOR RAW MATERIAL
INTAKE, SILO SYSTEM, BOILER ,
PUMP HOUSE & MOLASSES
UNLOADING TANK
-- 1each
11.06 MCC FOR SILO SYSTEM -- 1
11.07 SOFT-STARTER PANEL -- 1
11.08 POWER CABLES -- 1 LOT
11.09 CONTROL & SIGNAL CABLES -- 1 LOT
11.10
ELECTRICAL ACCESSORIES
(CABLE TRAYS, GI CONDUITS,
CABLE GLANDS, CABLE LUGS,
ISOLATORS, PUSH BUTTONS,
RUBBER MATS,FUSE PULLER,
RUBBER GLOVES ETC)
-- 1 LOT
11.11
IN MAIN PLANT BUILDING –
LIGHTING PANEL, LIGHTING DBS,
CONDUITS ,SET WIRING,
EMERGENCY LIGHTS FOR
CONTROL ROOM (Excluding RMG &
FPG)
-- 1
11.12 EARTH PITS AND NETWORK FOR
PANELS, DB ETC -- 1 LOT
11.13
LIGHTENING ARRESTOR WITH CU
EARTH CONDUCTOR, GI EARTH
PITS, AVIATION LIGHTS
-- 1 SET
12 STEAM DISTRIBUTION & CONDENSATE RECOVERY
12.01
LOW PRESSURE STEAM PIPES
WITH INSULATION LOT &
CLADDING, VALVES, FITTINGS,
FLOW CONTROLLERS
-- 1
12.02 CONDENSATE RECOVERY SYSTEM -- 1 SET
12.03 CONDENSATE PIPES, VALVES, -- 1 LOT
101
AND FITTINGS --
13 COMPRESSED AIR GENERATION & HANDLING EQUIPMENT
13.01 AIR COMPRESSOR (SCREW) PNEU.
FLAPS, GATES, ASPIRATION UNITS 60 CUM/HR 2
13.02 REFRIGERATED AIR DRYER 60 CUM/HR 1
13.03 AIR RECEIVER WITH AUTO DRAIN 1000 LITRE 1
13.04 COMPRESSED AIR PIPES, VALVES ,
FITTINGS -- 1 LOT
13.05 Mineral Mixture Plant 1 LOT
Total of Part – I.
14 PART – II ERECTION & COMMISSIONING
14.01 Erection, testing & commissioning of
equipment as per the above list. 1 LOT 1
14.02
Erection & commissioning of steel
structure sheeting and internal lighting
etc.
1 LOT 1
Total of Part – II.
Total of Part – I & II. (In figures)
Total of Part – I & II. (In words)
102
Part - B
PROPOSED SITE AT VILLAGE HATHALAI (GUNDOGE) DISTRICT PALI
PART 1. : DESIGN, FABRICATION, SUPPLY OF MAJOR EQUIPMENTS, FOR 150
TPD CATTLE FEED PLANT (EXPANDABLE UP TO 300 TPD) ON TURNKEY BASIS.
LIST OF MAJOR EQUIPMENT
S. No. Description Capacity/Size
(cm=Cubic
Meter)
Quantity Unit Price
Rs.
Amount
Rs.
1 RAW MATERIALS STORAGE EQUIPMENTS
1.1 Silo System for DORB/Grain Storage
with handling & Transferring system. 500 MT
2
1.2
Complete Unloading, Cleaning System
of 50 TPH with Three Truck at a time
and Shed -- 1
2 RAW MATERIALS INTAKE
EQUIPMENT
2.01
INTAKE CHAIN CONVEYOR IN
RMG WITH PNEUMATIC SLIDE
GATES
40TPH 55RM 2
2.02 DUMPING HOPPERS FOR INTAKE
CONVEYORS IN RMG 2 M x 1 M 10
2.03 ASPIRATION UNIT FOR DUMP
HOPPERS IN RMG -- 10
2.04 ELEVATOR FOR BATCH PRE-
MIXER 10 TPH 1
2.05 HOPPER ABOVE BATCH MIXER
WITH PN. GATE 1 MT 1
2.06 BATCH MIXER FOR PREMIX DUTY
WITH PNEUMATIC OUTLET GATE 1 MT 1
2.07 HOPPER BELOW BATCH MIXER 1 MT 1
2.08 ELECTRONIC PLATFORM
WEIGHSCALE 200 KGS 2
2.09 PORTABLE BAG STACK
CONVEYORS
250 BAGS/HR;
10 M 3
2.10 INTAKE BUCKET ELEVATOR 40 TPH 2
2.11 ASPIRATION UNITS FOR INTAKE
ELEVATORS -- 2
2.12 CASCADE MAGNET 40 TPH 2
2.13 JUTE TWINE REMOVER 40 TPH 2
2.14 CROSS CONVEYOR 40 TPH 1
2.15 DISTRIBUTION CONVEYORS 40 TPH 2
3 BATCHING EQUIPMENT
2.01 PROPORTIONATE BIN WITH
OUTLET GATE 20 MT 16
3.02 ASPIRATION UNITS FOR
PROPORTIONATE BINS 1 SET
103
3.03 GRAVITY FEEDERS FOR BIN
DISCHARGE 16
3.04 REDLER CHAIN CONVRYOR FOR
BIN DISCHARGE 250 MM 16
3.05 BATCH WEIGH HOPPER ( MAJOR
INGREDIENTS) 3 MT 1
3.06 BATCH WEIGH HOPPER( MINOR
INGREDIENTS) 1 MT 1
3.07 PNEUMATIC GATE BELOW WEIGH
HOPPER -- 2
3.08 SURGE HOPPER BELOW BATCH
WEIGHER -- 2
3.09 BATCH CHAIN CONVEYOR 30 TPH 1
3.10 BATCH BUCKET ELEVATOR 30 TPH 1
3.11 ASPIRATION UNITS FOR BATCH
ELEVATOR -- 1
4 GRINDING, MIXING EQUIPMENT
4.01 GRINDING BIN WITH PN. GATE 3 MT 2
4.02 FEEDER ABOVE HAMMER MILL 15 TPH 2
4.03 HAMMER MILL WITH 6 or 8 MM
SIEVE 15 TPH 2
4.04 HOPPER BELOW HAMMER MILLS -- 2
4.05 ASPIRATION UNIT FOR HAMMER
MILLS -- 2
4.06 BIN ABOVE BATCH MIXER 3 MT 2
4.07 PNEUMATIC GATE ABOVE BATCH
MIXER -- 1 SET
4.08 BATCH MIXER ( RIBBON TYPE) 3 MT 1
4.09 PNEUMATIC GATE BELOW BATCH
MIXER -- 1 SET
4.10 HOPPER BELOW BATCH MIXER 10 MT 1
4.11 CONVEYOR BELOW MIXER 30 TPH 1
4.12 MIXED FEED ELEVATOR 30 TPH 1
4.13 ASPIRATION UNIT FOR MIXED
FEED ELEVATOR -- 1 1
5 PELLETTING EQUIPMENT
5.01
MIXED FEED TRANSFER
ELEVATOR WITH OUTLET CASCAD
MAGNET.
30 TPH 1
5.02 PELLETING BIN WITH BIN
ACTIVATOR 10 MT 1
5.03 VARIABLE SPEED LOSS IN WEIGHT
FEEDER WITH HOPPER 10 TPH 1
5.04 PELLET MILL WITH CONDITIONER
AND MOLASSES MIXER 10 TPH 1
5.05 ROTARY AIR LOCK FOR PELLET
COOLER 10PH 1
104
5.06 COUNTER CURRENT PELLET
COOLER 10 TPH 1
5.07 PELLET COOLER CYCLONE (SS 304)
WITH PN.HAMMERS. -- 1
5.08 ROTARY AIR LOCK FOR CYCLONE
(SS ) 10 TPH 1
5.09 PELLET COOLER FAN -- 1
5.10 ASPIRATION DUCTING FOR
PELLET COOLER (SS 304) -- 1 SETS
5.11 PELLET ELEVATOR 30 TPH 1
5.12 PELLET SIEVE 30 TPH 2
5.13 SPARE MOTOR FOR PALLET MILL -- 1
5.14 SPARE MOTOR FOR CYCLONE
BLOWER -- 1
6 MOLASSES STORAGE / HANDLING EQUIPMENT
6.01 MOLASSES STORAGE TANK 400 MT 2
6.02 MOLASSES UNLOADING TANK
(WITH HOSE)
6.03 MOLASSES UNLOADING PUMP (1
Working + 1 Standby) 15 KLPH 2
6.04 MOLASSES PRE-HEATER 1 1
6.05 MOLASSES FEEDING PUMP (1
Working + 1 Standby) 3 KLPH 2
6.06 MOLASSES FLOW METER 3 KLPH 1
6.07 MOLASSES PIPING, CONTROL
VALVES,FITTINGS -- 1 LOT
7 BAGGING EQUIPMENT
7.01 BAGGING BIN (SS LINED) 20 MT 2
7.02 PNEUMATIC SLIDE GATE -- 2
7.03
AUTOMATIC BAG PLACING,
WEIGHING,FILLING, STITCHING
MACHINE WITH CONVEYOR &
CONTROLLER
250 BAGS/HR 1 SET.
7.04 SLAT CONVEYOR - With WOODEN
slats.
250 BAGS / HR;
25 M 1 SET
7.05 PORTABLE BAG STICHING
MACHINE -- 2
7.06 ELECTRONIC WEIGH SCALE 200 KG 2
7.07 PORTABLE BAG STACK
CONVEYOR
250 BAGS / HR;
10 M 2
8 FEED MILL HOUSING
8.01 MS STRUCTURAL STEEL FOR MAIN
PLANT AND PIPE BRIDGE 240 MT Approx.
105
8.02 MILD STEEL CHEQUERED PLATE
PLATFORM,TRENCH COVERS ETC 60 MT Approx.
8.03 WINDOWS As per Design
8.04 ROOF SHEETING As per Design 0
8.05 CLADDING SHEETS As per Design 0
8.06 LIGHT FITTINGS & LAMPS ( MAIN
PLANT) -- 75 SETS
9 PRODUCT PIPING/ ACCESSORIES
9.01 PRODUCT PIPING/DUCTING, FLEX.
CONNECTIONS -- 1 LOT
9.02 SMALL HOPPERS/TRANSITION
PIECE -- 1 LOT
9.03 PNEUMATIC GATES FOR PROP.
BINS FILLING -- 1 LOT
9.04 PNEUMATIC PIPE FLAPS -- 4
9.05 SIGHT GLASS FOR AIR LOCK -- 2 SETS
10 AUTOMATION EQUIPMENT
10.1
LOAD CELL WITH WEIGHING
SYSTEM FOR BATCH WEIGHER
EACH
1 MT; 1 MT 1 SET
10.2 LOAD CELL FOR LOSS-IN-WEIGHT
FEEDER -- 2 SETS.
10.3 PROGRAM SOFTWARE FOR THE
ENTIRE PLANT -- 1 SET
10.4
PLC PANEL , HMI , SENSORS,
COMMUNICATION & DATA
CABLES
-- 1 LOT.
10.5 MIMIC PANEL, COMPUTER FOR
CONTROL ROOM -- 1 SET
10.6 COMPUTER FURNITURE
(MODULAR) -- 1 LOT
10.7 UPS FOR CONTROLS & PLC -- 1 SET
10.8 COMPUTER WITH MIS OF PLANT
INFORMATION IN ENGG. OFFICE -- 1 SET
10.9 INSTRUMENT EARTHING ( CU
PLATE) FOR PLC LOT PANEL ETC -- 1
10.10 SPLIT TYPE AIR CONDITIONING
UNIT FOR CONTROL ROOM -- 1 SET.
SERVICE EQUIPMENTS
11 ELECTRICAL EQUIPMENT (LT)
11.01 Main LT Panel
11.02 MCC FOR MAIN PLANT -- 1
11.03 REMOTE PANELS FOR FEED MILL
EQPTS -- 1 LOT
106
11.04 AUTOMATIC POWER FACTOR
CORRECTION PANEL -- 1
11.05
MCC FOR RAW MATERIAL
INTAKE, SILO SYSTEM, BOILER ,
PUMP HOUSE & MOLASSES
UNLOADING TANK
-- 1each
11.06 MCC FOR SILO SYSTEM -- 1
11.07 SOFT-STARTER PANEL -- 1
11.08 POWER CABLES -- 1 LOT
11.09 CONTROL & SIGNAL CABLES -- 1 LOT
11.10
ELECTRICAL ACCESSORIES
(CABLE TRAYS, GI CONDUITS,
CABLE GLANDS, CABLE LUGS,
ISOLATORS, PUSH BUTTONS,
RUBBER MATS,FUSE PULLER,
RUBBER GLOVES ETC)
-- 1 LOT
11.11
IN MAIN PLANT BUILDING –
LIGHTING PANEL, LIGHTING DBS,
CONDUITS ,SET WIRING,
EMERGENCY LIGHTS FOR
CONTROL ROOM (Excluding RMG &
FPG)
-- 1
11.12 EARTH PITS AND NETWORK FOR
PANELS, DB ETC -- 1 LOT
11.13
LIGHTENING ARRESTOR WITH CU
EARTH CONDUCTOR, GI EARTH
PITS, AVIATION LIGHTS
-- 1 SET
12 STEAM DISTRIBUTION & CONDENSATE RECOVERY
12.01
LOW PRESSURE STEAM PIPES
WITH INSULATION LOT &
CLADDING, VALVES, FITTINGS,
FLOW CONTROLLERS
-- 1
12.02 CONDENSATE RECOVERY SYSTEM -- 1 SET
12.03 CONDENSATE PIPES, VALVES,
AND FITTINGS -- -- 1 LOT
13 COMPRESSED AIR GENERATION & HANDLING EQUIPMENT
13.01 AIR COMPRESSOR (SCREW) PNEU.
FLAPS, GATES, ASPIRATION UNITS 60 CUM/HR 2
13.02 REFRIGERATED AIR DRYER 60 CUM/HR 1
13.03 AIR RECEIVER WITH AUTO DRAIN 1000 LITRE 1
13.04 COMPRESSED AIR PIPES, VALVES ,
FITTINGS -- 1 LOT
13.05 Mineral Mixture Plant 1 LOT
Total of Part – I.
14 PART – II ERECTION & COMMISSIONING
107
14.01 Erection, testing & commissioning of
equipment as per the above list. 1 LOT 1
14.02
Erection & commissioning of steel
structure sheeting and internal lighting
etc.
1 LOT 1
Total of Part – II.
Total of Part – I & II. (In figures)
Total of Part – I & II. (In words)
Note:- The above list of equipment is as per preliminary design of the plant. The final list of
equipment & their individual capacity may vary as per detailed engineering of the bidder to
achieve the MINIMUM rated capacity of 150 TPD and further provision for expansion of
capacity up to 300 TPD. It is required to keep a provision for adding of all the equipments
that will be needed in future for achieving a capacity of 300 TPD on 20 hrs per day of
working. All suitable structure, cables and relevant works for the same are required to be
done in first phase along with ordered execution. It is also required that the design be made
on a basis that capacity can be increased to 300 TPD in future without any shut down
needed in running plant of first 150 TPD. However capacities mentioned above for
individual equipment can not be increased to achieve overall plant capacity.
108
Important Note for Bidder
a. The unit rates to be quoted by bidder shall include Packing & forwarding, insurance,
freight, taxes, Duties etc on FOR site basis.
b. As stated above, this requirement is for design, supply, labour job for installation, testing
and commissioning of Cattle Feed Plant equipments & service equipments, as per schedule
of quantities.
c. All minor works, which may be necessary to achieve the rated capacity of the plant, is
included in the scope of work, though not specifically mentioned.
d. Bidder shall include the cost of all the wear parts indicated at page no. 68.
e. Bidder will have to indicate and quote separately equipment wise spare parts for one-year
operation.
f. All equipments indicated above shall include suitable rated drives.
g. The quantities indicated for intake conveyors are approximate as per attached drawings &
for tender purpose only. However supply & payment shall be made as per site requirement.
Mode of Measurement for Payment
Payment for items shall be aid as below interpretation:
S.
No
Description of
Unit of Payment
Paid as
1 No./Number Number
2 Set Complete Set as per work scope
3 Lot Lot as per specific clause mentioned in terms of payment
4
Structural steel
Shall be paid on actual weight in MT received for supplies. Final payment of
steel shall be based on theoretical sp. weights of total steel erected in MT
after reconciliation. Loss/ wastages shall be to the account of the bidder.
5
Cladding sheets,
windows
Shall be paid on actual quantity in sq.m received for supplies. Final payment
shall be based on actual measurement of total area of sheets/windows erected
in sq.m after reconciliation. Loss/ wastages shall be to the account of the
bidder.
General Requirements
Feed milling equipment The following may be noted in general with respect to the technical specifications of the supply
of Feed milling equipment.
1. Capacities of all machines and hoppers etc. as specified in the tentative list of equipment to
be supplied are based on raw material of 600 gs cum bulk density unless otherwise
specified.
2. All machines are to be provided with motor/geared motor/motor-gear box and drive parts.
The term drive parts cover the supply of items as follows:
3. Chain drive: Driving and driven sprockets, required length of simplex/duplex chain with
closing links and key in the driven shaft. All the sprockets should be of MS and flame
hardened.
4. V belt drive: Driving and driven pulleys, required no., type and length of V belts of
polyester reinforced type, key in driven shaft and side rails for motor.
5. Direct coupled drives: Suitable chain type coupling with accessories and key in driven
shaft unless specified otherwise.
6. As per details specified in individual equipments specification / design data.
109
7. Apart from the above, the supply of steel base frame for motor/geared motor and guard for
drive parts of minimum 2 mm thick MS sheet is also included in drive parts.
8. Packing for flanged joints of machines/hoppers/bins etc. should be felt or rubber depending
on the application. Packing shall be fixed with glue rather than simple grease. If equipment
is being dispatched in dismantled condition, necessary packing materials along with glue
shall be sent separately.
9. Discharging angle of raw material in pipes/transition pieces/hopper bottoms etc., in general
should be min. 55 degree from horizontal for meals and 45 degree for pellet and grains.
10. All equipment should have suitable provision for inspection, lubrication and maintenance.
11. All equipment in general should have dust-proofing arrangement.
12. All equipment should be supplied with first charge of lubricant (grease/gear oil) etc. either
filled in equipment or supplied loose and to be filled before testing and commissioning.
13. All weld joints for fabricated equipment/hoppers/bins/piping etc. should be ground smooth
from inside to facilitate easy and free flow of material.
14. In detail specification of equipment/hoppers and accessories etc., the thicknesses of
construction material have been specified wherever required. It has to be noticed that these
are the minimum but the supplier may provide these thicknesses more than these if required
by their design/detailing of the equipment.
15. Painting: All bought out standard manufactured equipment may be supplied as per
manufacturer's standard painting practice. However, all fabricated equipments shall be
provided with standard cleaning, degreasing practice before painting, then primer coating
before applying one coat of approved shade of synthetic enamel paint. Second coat of
synthetic enamel paint shall be provided at site after installation and before commissioning.
Supporting steel structure, transition pieces & piping etc. being fabricated at site should be
applied with corrosion resistant zinc oxide primer before erecting/installing and then
applying one coat of synthetic enamel paint after erection. Approved colour shades for
equipments are as follow unless otherwise specified in equipment specifications or agreed
during execution of contract. However, final decision on colour shade shall be confirmed
with the engineer -in-charge before commencement of painting.
Colour Shades for Equipments
Equipment Approved Colour Shades
Conveyors and elevators
Machines
Hoppers
Proportionate bins/storage bins
Steel structure
Manual/ pneumatic flaps
Product piping
Aspiration piping
Inspection door of machines/hoppers/bins
Inside of machine/hopper/bins
All supports, stands and frame of machine
All equipments bins in the scope shall be lettered in English (in capital) with black (Description
Capacity 6”size) at observable height.
110
Conveying and Handling System
Chain Conveyors
Chain conveyors are required to transfer all types of solid feed ingredients for the Feed plant
horizontally or at an inclination not exceeding 10 degree. These shall be of dust proof and
bolted design, having steel plate thickness as follow:
Item Description
casing bottom minimum 4 mm
casing side minimum 4 mm
casing partition minimum 3 mm
casing top cover minimum 2 mm
end plates minimum 8 mm
Note: CHAIN'S LINEAR SPEED NOT TO EXCEED 0.5 M/SEC.
Conveying chain shall be Drag Bush Chain type of sufficient breaking load with special forged
steel & case hardened parts along with special nylon wear pads. Screw type chain tensioning
device, conveying chain wheel of hardened special steel, shaft supported on both sides in pillow
block self aligned ball bearings, exchangeable wear rail of TISCRAL (Wear resistant Abrasion
Resistance Steel Plates) or equivalent material to be provided at trough top & bottom for chain
guide. Cleaning strips of UHMW to be provided after a few links. Spring loaded safety device
at tail end with limit switch for protection of chain against overloading, necessary inlets &
outlets to be provided. Conveyor to be run by horizontal foot mounted geared motor with
chain/direct coupled drive parts etc. as per requirement. Wipers for the conveyors shall be
provided for Distribution conveyors.
Screw Paddle Conveyors
Screw Conveyors are required to convey/distribute all types of solid feed ingredients
horizontally or at inclination (maximum 10 Deg.) for lengths not exceeding 15 M. Maximum
length of screw trough shall not exceed 2.8 M.
These shall be of constant / variable pitch, as per requirement and dust-proof design, having
steel construction, flanged bearing with stuffing boxes, intermediate hanger bearings with
maintenance ¬free, self lubricated special nylon bushes, screw or paddle flights of steel of
uniform / variable pitch welded on screw shaft, necessary inlet & outlet. Overflow flap at
discharge end with limit switch to be provided. Conveyor to be run by foot mounted horizontal
geared motor and chain type direct coupling. Construction detail of various major items shall be
as follows.
Item Construction Details
Trough minimum 3 mm thick MS sheet
Flight minimum 3 mm thick MS sheet
Saddles minimum 5 mm thick MS late
Main shaft Heavy Duty C class MS ERW pipe
End plates minimum 8 mm thick MS late
Top cover minimum 2 mm thick MS sheet
111
Bucket Elevators
Bucket Elevators are required to convey all solid feed ingredients vertically at the rated
capacity. These shall be of dust-proof design, having steel construction, two leg bolted trough
type, food and oil resistant antistatic belting of PVC - lined fabric, (M-24 grade 3 ply nylon
fabric), pressed steel buckets, Elevators boot with two inlets, screw type belt tightening device
and cage type pulley. Elevator head with rubber lagged crown pulley and wear resistant guide
plate. Elevator to be provided with necessary clean out slides, inspection windows, steel back
stop, special bolts for fixing buckets on belt, casing retention frame and leg spacers. Elevator
shall be driven by a foot mounted horizontal geared motor, and chain type direct coupling drive
parts. Elevators shall have provision of mounting Aspiration units. All Elevators shall be
provided with air breather arrangement at suitable locations, to enable effective air movement
& quick replacement, wherever aspiration units are not specified. Belt speed sensors for
stopping the elevator motor not required.
Construction details of materials shall be as follows: Item Construction Details
Trough Minimum 2 mm thick MS sheet
Buckets Minimum 2 mm thick MS sheet
Top Head Minimum 4 mm thick MS plate
Cover of Top Head Minimum 2 mm thick MS sheet
Bottom Head Minimum 4 mm thick MS plate
Foundation Plate Minimum 12 mm thick MS plate
Slat Conveyor
These conveyors are used for transfer of filled bags from production area to finished product
Godown on an inclination up to 10 degree. Conveyor is designed for moving of filled bags on
number of steel slats linked with each other with fabricated steel chain and malleable cast steel
wheels. Conveyor is having steel plate body with stiffeners and steel guide plates for wheels
and pipe railing for bags. 2 Nos. hardened (EN-8) sprockets wheels with suitable sealed
bearings are to be provided at feed end and discharged end to facilitate movement of chain. MS
heavy duty ERW pipes are provided for support of conveyor. Conveyor is run by horizontal
foot mounted electric geared motor with chain-type direct coupling drive parts. The conveyor
shall also have a tilting device, so that the bags can be directly received by loaders on their
backs.
Cascade Type Magnetic Separator
Cascade Magnets are used to effectively remove the ferrous impurities from raw materials feed
flow.
The unit is fabricated from stainless steel plates in Diamond shaped chute. On each section of
Diamond shaped chute, a permanent ferrite magnet (with high remanence after magnetization)
is housed in stainless steel 304 enclosure with heavy duty hinges and magnet to be swing away
from the body of chute by pneumatic air cylinder after a pre-determined time through signal
from a PLC. Cleaning cycle of magnet shall be fully automatic. Ferrous impurities shall be
collected in a separate steel hopper and regular material to be guided to a different chute.
112
Jute Twine Remover
Jute Twine removers are required as a pre-cleaning machine to remove jute strings, in the intake
section before ingredients are stored in bins. The machine shall consist of MS enclosed housing
with double rotor arrangement with extended spike like attachments to entwine jute fibre and
also break loose lumps. The end plates of the rotor shall be machined 8 mm thick MS plates
with suitable end bearings fitted on the shaft. Both rotors shall be of removable type with quick
opening access door with locking arrangement. The drive shall be of horizontal foot mounted
geared motor mounted on a common base frame with the remover. Main body - 3 mm thick MS
sheet
Dumping Hoppers
Hoppers are required in Godown for dumping of ingredients from bags to conveyor running
below.
These shall be fabricated from steel plates for sufficient holding capacity, with removable
Galvanized M.S. grill on top. MS angle frame for installation of these hoppers in RCC opening
shall also be supplied with the dumping hoppers. These grills shall be magnetic and shall attract
ferrous materials during dumping operation. Construction detail of dumping hoppers shall be as
follows:
Main body minimum 3 mm thick MS sheet
Grill 15 mm MS square bar
Frame 65 x 65 x 6 mm MS angle
Hoppers and Storage Bins
Bins are required for temporarily storing solid feed ingredients materials as per the Design data.
These shall be fabricated from mild steel plates /profile ribbed steel sheets with welded/bolted
joints wherever required for required holding capacity with stiffening arrangements. However,
main body shall be fabricated from minimum 3 mm thick MS sheets. Proportionate Bins shall
be rectangular /square cross-section, modular type with bolted segments complete with
stiffeners, with air equalizing connections within the bins. All bins shall have discharge hoppers
with inspection window to view ingredient flow. All bins supplied shall have proximity level
sensors (non-contact type) to ensure continuous operation with feedback indication. All Bins
shall have manual discharge gates & suitable sized Air breathers. SS Lined bins in the Main
plant shall be fabricated from 1 mm thick SS 304 sheet. The discharge angle for the Hoppers &
Bins shall be 55 Deg (minimum). Air equalizing duct shall be supplied as a part of scope,
between successive bin/hopper and hopper separated by a pneumatic gate, apart from suitably
sized Air breathers, to facilitate air exchange within & outside the system.
Portable Bag Stack Conveyors
These portable conveyors are used in godown for stacking of filled raw material and finished
bags mechanically or dispatch to trucks rather than manually.
The stacker to be mounted on chassis fabricated from ISMC/C Class heavy duty MS ERW pipe
with castor wheels and pneumatic ADV tyres for easy movement. Delivery height of stacker
shall be adjustable by suitable winch assembly. Stacker shall be fabricated from suitable MS
angle and flats. Bags shall be transferred on MS slats fitted with bushed chain with K1
113
attachment and malleable cast steel wheels. Bags shall move on slats with suitable electric
motor, gear box, tyre type flexible coupling between motor and gear box and chain type drive
parts and bearings. Stacker shall be provided with a DOL starter (near the drive) and copper
wiring between this starter and electric motor. Bag stacker shall be complete in all respect,
ready to use. Feeders (MPCB) for the starter shall be located in the relevant MCC.
Pellet Cooler Cyclone
Cyclone for separation of fines from cooling ambient air shall be designed & selected for most
efficient operation suitable for the required Air flow rate for cooling of the pellets. The Cyclone
shall be fabricated from 3 mm thick SS 304 sheet with a fines discharge size of 200 mm & shall
have provision for lifting, supporting etc. The cyclone shall have SS pads for 3 nos. pneumatic
hammers, at suitable locations in the conical portion, for removal of fines when necessary &
provisions for installing these hammers.
Air Lock
Airlocks are required to air seal the cyclones, pellet Mill cooler & dust collectors etc. Air
lock shall have stainless steel (SS 304) fabricated body. Rotor shall be wane type, fabricated
from stainless steel (SS 304) plate & shall rotate within the housing with very close tolerance
with self-lubricating bearings. Nylon wire cleaning brush shall be provided for each Airlock.
Air locks shall be driven by suitably rated horizontal foot mounted geared motor and coupling.
If function desires, adjustable UHMW wear pads to be used in rotor.
Batch Mixer
Batch mixer is required to improve the homogeneity of a batch consisting of dry solids e.g.
flours, meals and fine powders to achieve a set Co-efficient of Variance. Provision of
vitamin/liquid dozing in the mixer shall be considered while designing the mixer.
The Mixer shall be horizontal, Double Helical design, Ribbon Mixer and shall be designed to
achieve mixing by turning of rotor in the mixing chamber. The Mixer is to be designed to
operate efficiently even for 50% of full capacity filling. The Mixer is to be dust-tight, single
shaft with cylindrical mixing trough, of sturdy steel construction, rotor supported by two
outboard pillow blocks, heavy duty ball bearings and fitted with sturdy paddles. Quick
emptying of the mixer to be ensured through a full length bottom opening pneumatically
operated gate. There should not be any product leakage through this gate when mixer is being
charged. The Mixer is to be complete with Manhole, safeties, shaft seals, limit switches for gate
position, duplex chain drive between gear box and motor shaft, drive guard, air balancing ducts
with above & below hoppers, horizontal foot mounted geared motor, Air breathers, pneumatic
cylinders and solenoid valves etc. Geared motor shall be coupled through tyre type flexible
direct coupling.
Main body: 6 mm thk.MS plate minimum.
Air cylinder: 150 mm diameter ; 150 mm stroke (min)
Control panel for the mixer shall have ammeter, ON-OFF indicative type push buttons for
operation & safeties for related position of pneumatic gates etc.
114
Batch Mixer for pre mix duty shall be horizontal type with paddle design, based on the average
density of the premix for the rated capacity.
Molasses Mixer
Molasses mixers are required to prepare a homogeneous dispersion of heated molasses
throughout the incoming powdered mixed feed. The Mixer shall be horizontal in construction
with twin intermeshing rotor with paddles in low speed beating action. All plates touching the
feed shall be of AISI 304. Design shall ensure that there is very little sticking of molasses on
inside surface of stator and it can run continuously without cleaning. For this purpose, the mixer
is to be provided with Teflon or equivalent coating on inside surface of the stator. The design
shall ensure that no molasses is dozed, when the feeder /feeding is stopped. The Mixer shall be
complete with 4 nos. of swing type cleaning doors, all safeties, driving geared motor, direct tyre
type coupling arrangement with separate MS base frame and anti-vibration pads. Rotors shall
be statically and dynamically balanced with adjustable SS 304 paddles.
Body thickness: 4 mm thick SS 304 plate (minimum)
Side plate: 8 mm MS plate with 4 mm thick AISI 304 lining.
Pellet Mill
Pellet mills are required for the pelleting of conditioned Molassed feed, by forcing the feed
between rotating die and press rolls.
Pellet Mill shall be vertical type with pulley & "V" belt drive arrangement. Pellet mill to have
the following specific features:
Solidly constructed and welded steel frame for mill.
Die chamber casing in corrosion resistant stainless steel. (AISI 304)
Quick release knife assemblies for regulating the pellets length.
Servicing hoist mounted on the pellet mill to facilitate changing of dies and press rolls.
A shear pin and limit switch device, mounted on the main support shaft, to protect the
mechanical press components, drive belts and main drive motor from overloading.
Die fixing arrangement mounted on the die holder body for quick die changing.
Digital type thermometer with sensor for measuring the temperature of mash feed entering
the mill.
Powerful permanent magnet in pellet mill inlet to eliminate ferrous foreign particles.
Main drive motor (IP 55) of RPM not exceeding 1500 with additional pillow block bearing
and extra shaft for motor.
V belts & pulleys
Anti-vibration mountings.
Die of 8 mm dia. holes.
Distributor for uniform delivery of mash to rolls.
Hand tools for maintenance, adjustable torque wrench and hydraulic press for removing
shells from press rolls.
Feeder and Conditioner
Feeder & conditioners are to be two separate units installed on either side of Molasses
Mixer.
115
Feeder shall be continuous loss-in-weight type with hopper, load cell etc. The feedback
from load cell of this feeder, shall determine control the dozing of Molasses in the Molasses
Mixer, through the PLC logic and PID controller in Molasses.
Feeder to be driven by an infinitely variable speed motor, variable frequency drive type.
Double conditioner required to condition the mash feed with steam. All parts of the
adjustable twin paddle conditioners coming in contact with the feed are to be of stainless
steel (AISI 304) and the unit should be suitable for direct mounting over pellet mill.
Conditioner to have arrangement for electric heat shield for body for sanitary feed
production.
Conditioners to have arrangement of injecting and mixing steam and molasses liquids
(minimum 3% of each) by the help of adjustable pitch paddles .Design shall be such that the
cooking time of the feed, shall be at least 30 seconds.
Conditioner‟s drive motor and drive parts for both conditioners shall be supplied.
Control panel for complete automatic operation and safeties of the pelleting plant for
controlled feed flow, steam injection, molasses, interlocking with various units, with
ammeter, ON-OFF indicator type push buttons for manual operations etc.
Hammer Mill
Hammer mill shall grind coarse ingredients, such as cereals, oil meals etc, to obtain a more
uniform & desired particle size of the batched ingredients. The design of the Hammer Mill shall
be horizontal & full circle type with bottom discharge. Machine shall grind batched ingredients,
on a single pass and to reduce particle size of desired mesh size, according to the sieve fitted.
The sieve is fitted all around the rotor to give maximum sieving area. The open screen area
shall not be lesser than 1.15 sq.m. The Hammer Mill shall have air assisted system for efficient
removal of ground particles across the sieve. Hammer mill shall be directly coupled to the drive
IP 55 Motor of 2880 rpm. Grinding in hammer mill shall be obtained by mechanical impact of a
set of free swinging rotating “M” type hammers (mounted on rods) on individual ingredient
particle, till it is small enough to pass through the 4.0 mm screen, along with aspiration air. The
screen of the Hammer Mill shall be placed around the grinding chamber to maximize the
screening area. Control panel for complete automatic operation and safeties of the Hammer
Mill to control feeding operation with manual intervention, ammeter, ON-OFF indicator type
push buttons etc.
The machine to have the following general & special features :
Large Hinged Doors for Quick opening & changing /interchanging of Grinding screen &
Reversibility & replacability of hammers.
Directional reversal for grinding shall be possible for increased life of the Hammers.
Long life & dustproof bearings for the Hammer Mill. All protection/safety devices for the
Mill.
Statically & dynamically balanced for Low noise & vibration. The composite unit of
Hammer Mill & Motor shall be mounted on a common base frame with heavy duty
Vibration dampers.
Control panel for automatic controlled operation of hammer mill, its feeder and to ensure
operation safeties.
Design of the screen perforations shall be to maximize the open screen area.
116
Feeder for Hammer Mill
The Feeder for the Hammer mill shall control the Feeding rate of batched ingredients flowing
across to the Grinding equipment. The design of the feeder shall be rotary, vane type controlled
through a variable speed drive for continuous & controlled feeding of batch material to hammer
mill. The variable speed drive shall be slaved by a Controller in PLC, so that feed to Hammer
mill could be automatically regulated depending upon electric load of hammer mill motor for
most efficient operation for the desired throughput of the mill. The Feeder shall have strong
permanent Ferrite magnet at its inlet to protect the Hammer Mill from iron parts/particles by
separating them, before the batched feed enters the grinding chamber.
Pellet Cooler (Vertical)
Pellet Cooler is required to cool hot and moist pellets by drawing ambient air, immediately after
discharge from Pellet Mills. Pellet cooler shall be vertical box type, bolted construction of
counter current design, using ambient air for cooling. The discharge arrangement shall be of
oscillating top grill with eccentric mechanism.
Product inlet, holding and exhaust place shall be of non-rusting material (SS 304) whereas
collection hopper from mild steel sheets. All interior parts not made of non rusting material
shall have anticorrosion painting. Cooler should be complete with geared motor, pellet
discharger, hinged type inspector door with sight glass, air inlet and discharge connections,
uniform and regular distribution of the air across the complete cross section of cooler should be
ensured to permit optimum utilisation of the air. The pellet discharge from the cooler shall be
automatic based on level sensor. Coolers to have arrangement for manual and automatic
adjustment of discharge rate for pellets, after getting cooled. Major construction materials shall
be as follows:
Top conical pellet inlet and air outlet minimum 2 mm thick SS 304
Box type cooling column minimum 2 mm thick SS 304
Collection hopper below tray minimum 5 mm thick steel plates
Stator and rotor of air lock minimum 5 mm thick SS 304
Grill type trays Mild steel plate / flat, hot -dip galvanised
Aspiration Filter Unit
This unit shall be modular in construction & is used for cleaning of dust laden air or the
separation of solids from gas/ solids mixes from connected equipment, in order to recover
materials and clean the exhaust air. Dust laden air enters in aspiration filter and then air escapes
through filter bags and dust is deposited on the outside of filter bags. For removing the dust
retained on the outside of filter bags, high pressure reverse air shocks are provided at regular
intervals to the inside of the filter bags through an automatic electronic/pneumatic control
system for sequential air release for a set of filter bag rows. Dust shall be collected in a bottom
cone and discharged through an airlock.
Aspiration filter to consist of sheet steel bag housing fabricated from minimum 3 mm thick
mild steel sheet with inlet spout and dust collecting cone. Filter to be provided with sheet steel
hinged covers with integral filter-row purge system in IP-65 protection class. Filter bags to be
provided with suitable GI cage and fastening system. It should be ensured that bags and cages
can be easily removed for cleaning in position by special annular brush. The unit to be complete
with electronic/ pneumatic control apparatus having provision for adjustable bag cleaning cycle
117
and the length of the cleaning pulses, pressure reducing station for air supply to control system,
steel supporting legs, etc. as per requirement.
Pellet Sieve
Pellet sieve is used to separate pellets from pellet crumbles & fines through a vibratory
mechanism of the sieve and directs pellets & crumbles for further operations. The sieve shall be
mounted on a sturdy MS frame work and shall be of totally enclosed construction. The sieve
shall be of SS 304 MOC. The design considerations of size & pattern of the perforations on the
sieve shall be as per the throughput mentioned in Design data. Vibrations produced by
unbalanced motors attached to the inclined sieve housing mounted on helical springs shall be
designed for quick & efficient separation. Adjustable moving flap Counter weights shall be
used for retaining pellets. The sieve shall have arrangement for quick opening & replacement of
sieves. The Pellet sieve shall be complete with anti-vibration & canvas cloth joints at inlet &
outlet.
Pellet Cooler Fan
Pellet Cooler Fans are required for creating low pressure in Pellet cooler to facilitate flow of
ambient air across pellets and reduce the moisture in pellets before bagging. The sheet steel
construction housing and the SS 304 impeller of the centrifugal fans shall be mounted on a
sturdy steel base. Motor & the Fan shall be mounted on a common structural steel base frame
with heavy-duty vibration dampeners. The impeller to be fitted with special blades and
designed for high-speed service, statically and dynamically balanced for minimum vibrations.
Casing shall be provided with anti-noise coating for silent operation. Preference shall be given
for direct coupled motor drive. Fan shall be selected to have highest efficiency for the required
pressure differential and air throughput. Main body of centrifugal fans should be made from
minimum 3 mm thick mild steel sheet. The selection of the capacity of the Fan shall be such
that, it shall cater to rated capacity of the Pellet Mill.
Stitching Machine (part of automatic bagging system)
These machines are required in feed plant for stitching of gunny/polyester bags after filling of
the finished feed. These shall be mounted on a steel column, completely automatic, suitable for
two-thread double chain stitch and adjustable stitch length. Column shall have arrangement for
fixing sewing head at any height and also for fixing other accessories such as bag feed-in and
labelling device. Machine shall be complete with feed-in device, labelling device and switch
box containing all necessary switching and protecting elements including conveyor. One
sewing head has to be fixed on the vertical steel column and one loose sewing head to be
supplied.
Molasses Handling
Molasses Pre-Heater
Molasses Pre-Heater of suitable capacity is required
118
Molasses Pumps
These are used for transferring molasses from tanker to vertical storage tanks and for onward
use to mix Molasses with feed in Molasses mixers & conditioners. These CI construction
pumps shall be horizontal, foot mounted, positive displacement (shuttle block only) with gear
box arrangement, capable of handling molasses having viscosity of 2000 seconds red wood 1 at
20 Deg. C. and specific gravity 1.4. Pumps to be complete with common steel frame for pump
& motor, gland packing, coupling and guard, foundation bolt, coupled with gearbox and drive
with TEFC motor IP 55.
For Unloading Molasses: 15 KLPH @ 30 mWc
For Feeding Molasses to plant: 3 KLPH @ 30 mWc
External electrical Heating tape arrangement with temperature controller are required for the
unloading pumps only. GI shroud (18 G) for the unloading and feed pumps are included in the
scope.
Molasses Flow Meter
This is used to measure the total molasses being added in molasses mixers and conditioner.
The flow meter shall be of electro-magnetic induction type, suitable for measuring the flow of
pre-heated molasses having viscosity of 2000 seconds Red wood 1 at 20 Deg. C and specific
gravity of 1.4. The Flowmeter shall display the flow rate in digits & the cumulative quantity,
and should be resettable. Necessary air eliminator and other accessories are to be provided with
flowmeter. Electro-magnetic induction type flowmeter shall be provided with material
measuring tube of SS 316 and the liner of PTFE whereas electrode shall be of HASTELLOY–C
or as per standard design of the manufacturer.
Molasses :
The Purchaser shall provide the underground RCC reservoir, pump house and Molasses storage
steel tanks for storing the liquid molasses received by road tankers and unloaded by gravity to
the reservoir. The bidder‟s scope of works starts from transferring molasses s from the RCC
reservoir to MS molasses storage tanks through pump and then from outlet of molasses storage
tank to stream heated molasses day tanks and from day tanks up to mixers through molasses
feeding pumps with inlet and outlet headers, flow meters, control valves, isolation valves,
filters, non return valves etc. All piping beyond this reservoir for storing, feeding & return
piping for conveying back surplus molasses from mixers to the steel day tank/between the day
tanks is in the bidder‟s scope. Piping for inter transfer of molasses from one molasses storage
tank to other storage tank shall be in bidder‟s scope of works.
Molasses day tank :
This is required for heating and intermediate storage of molasses before feeding to molasses
mixers through loss in weight type feeder or similar arrangement. Molasses day tank is to be
welded type, horizontal and cylindrical shape, plate steel construction and heavy duty mild steel
pipes. For heating of molasses by circulation of steam. Complete tank to be provided with
50mm glass wool insulation and mild steel sheet 2mm (minimum) thick cladding. Tank to be
complete with inlet, outlet, manholes, steam inlet-outlet, pressure release valve etc. Inside of the
119
tank to be cleaned by sand blasting and then epoxy painting. All outside surfaces are to be
provided with two coats of head resistance primer prior to insulation. Tank to be preferably
fabricated at site and to be tested with water prior to applying primer.
DESIGN REQUIREMENTS :
Capacity of tank – 400 MT x 2 Nos. (Molasses specific gravity of 1.4 MT Per Cu.Mtr. Upto
Overflow of tank.
Material of construction – Mild steel structural steel as per IS 2062 Grade A; IS 808 for Rolled
Steel for beams, Channels, Angles, IS 1730 for plates, trips, flats; IS `1239 for MS Pipes.
Tank to be fabricated at project site on foundation.
Molasses storage tank to be welded type, vertical and cylindrical shape, milk steel structural
member like cross bracings, central kind post, circumferential stiffener rings etc. Each tank to
be provided with standard accessories such as staircase, rung ladder (welded inside the shell),
safety railing on top, manholes (at bottom and top), inlet, outlet, air vents float type level
indicators, drain etc. three adjoining tanks to be connected with working platform on top. Tanks
to be fabricated at site on civil foundation (1M above ground),. Civil foundation shall be
provided by the purchaser. After fabrication ,the tanks are to be tested with water for leakages
and then all internal surfaces are to be cleaned by sand blasting and then provided with epoxy
painint. All outside su4rfaces are to be sand blasted and provided with enamel primer and paint.
After testing, all the three tanks to be calibrated.
SCOPE OF SUPPLY
Bottom plate : MINIMUM 12MM Thick with lap Joint welding with 75mm Overlap.
VERTICAL SHELL :
Bottom 3.00m Min. 12mm thick
Intermediate 1.50m Min. 10mm thick
Next 1.50m Min. 8mm thick
Top 3.75m Min. 6mm thick
Double “V” groove welding on both sides.
Roof : Conical type with 5mm thick plates having slope of 5 degree from horizontal.
Tank Accessories :-
Inlet 100mm NB MS “C” class pipe (2 Nos.) with F table flange on roof of the tank. One inlet
to be closed with blind flange and for other, counter flange to be provided.
Manhole in shell near bottom (1 No.) of 600mm dia, made from 12mm thick MS plate and
cover plate from 16mm thick complete with bolts, nuts and packing etc.
Manhole on roof (`1 No.) of 600 mm dia. Made from 8 mm thick plates, complete with flanged
bolted rain hat and wire mesh.
Float type level indicator complete with SS304 float, 14 gauge SS guide wires, pulleys, ss wire
ropes (14 gg) scale with marking in litres after proper calibration.
120
Air vent at roof (min. 8 Nos.) from minimum 450mm dia and 450mm height with 50x6mm MS
flat, SS wire mesh, rain hat.
Drain near bottom plate (2 Nos.) from 150mm NB MS “C” class pipe complete with flanged
type butterfly valve, blind flange F table, bolts nuts and packing.
Outlet near bottom (2 Nos) from 150mm NB MS “C” class pipe with flanged type butterfly
valve counter flange, H table for one outlet and blind flange of table “H” for 2nd
outlet bolts,
nuts and packing. The provision for 2nd
outlet is meant for electronic level indicator electronic
level indicator is included in the scope of supply.
IMPORTANT NOTES :-
The load details on the foundations shall have to be provided to be purchasers to design the
foundation.
The steel structure for the bulk molasses storage tanks shall be as per the design of the bidder.
The tanks shall be designed for wind load (Heights as per historical records) and for seismic
stability as per seismic zone stability certificate for the tankj and structure shall be submitted
by the successful bidder. Design calculations for the structure shall be shared with the purchaser
without any exta cost. Purchaser shall suggest the bidder, for alteration ,wherever found
required.
Silo System
In this silo system, flat bottom silos 4 Nos. Of minimum 500 MT (2 in use & 2 for future)
capacity each of GI corrugated (Imported) sheet (Min.zinc deposition 450 gm/sq.mtr) bolted
type flat bottom with hydraulically operated serew (imported) for discharging left out materials
from bottom of silo, complete with aeration system and temperature monitoring system for
storage of DORB RCC foundation for silo above ground by purchaser. Each silo to be provided
with automatic sampler. Discharge from each silo to common chain conveyor through
pneumatic slide. Additional emergency gate in the bottom of silos.
All other details of this system for storing DORB shall be similar to that for grains as
mentioned point given below.
This silo system shall be installed in separate location as shown in Production Block Layout
drawing.
FLAT BOTTOM SILOS : 2 Nos. Of minimum 500 MT capacity each of GI corrugated
imported sheet (Min. Zinc deposition 450 gm/sq.mt.) bolted type flat bottom with electrically
operated sweep auger (Imported) for discharging left out materials from bottom of silo,
complete with aeration system and temperature monitoring system for storage of grains. RCC
foundation for silo above ground by purchaser. Each silo to be provided with automatic
sampler. Discharge from each silo to common chain conveyor through pneumatic slide gate.
Input feeding capacity to silos and discharge capacity from silo to feed mill to be 30 TPH.
Distribution for material for feeding to silos and discharge from silos through chain conveyors
121
& pneumatic slide gates/flaps. Material discharge from silos to pre-weighing bns of plant
through intake elevator automatically through plant PLC.
Twin rotor jute twine remover and diamond shaped cascade magnet to be provided in intake
line prior to store material in silos. No weighing facility to be provided in silo storage system.
Permanent magnet erequired in inlet spout of bucket elevator. Provision to be gthere in system
for recirculation of material mechanically from one silo to other using feeding conveyor and
elevator with a separate discharge conveyor so as to facilitate simultaneous operation of transfer
of material from one silo to production block and recirculation of material from another SILO.
MCC cum mimic panel for the system with necessary earthing grid, pits.
Weigh Scales
Batch Weigher With Hopper
This weigher is required to accurately weigh solid ingredients being discharged from
proportionate bins in a hopper for making a batch. The operation of the weighing system shall
be automated & controlled through the Centralized PLC, to prepare a predefined composition
batch. This weigh shall have a set of load cells on which the batch weigher hopper is mounted.
The load cell for 1 MT weigh hopper for minor ingredients, shall have load cell capacity of 1
MT.
Weigher shall be designed for stationary execution. Weighing capacity to be as per the design
requirement of the plant, load cells capacity to be approximately 3 times of weighing capacity
and digital graduation shall be minimum 0.05% of the weighing capacity. Load cells shall be
completely hermitically sealed type in dust-proof enclosure. The weigh hopper shall be
supported on load cells and retained in its position by transverse links/stoppers. The indication
of weight shall be digitally displayed on Mimic panel and simultaneously displayed on the
monitor of the Control room. The Central PLC shall arrange to log all the data of batches in
shift /day. Air equalizing line (with flexible connection) from weigh hopper to the hopper
below the pneumatic gate shall be included in the supply scope. Apart from air equalizing duct,
air breathers of sufficient quantity & size shall be supplied to equalize excess pressure.
The weigh hopper to be made of sheet steel minimum 3 mm thick with necessary steel
stiffeners, flexible connection, inspection windows etc. Weigh hopper to have arrangement for
putting standard weights on outside for calibration purpose.
Platform Scales
These are used in feed plants for weighing the bags containing ingredients or for checking the
weight of filled bags. These shall be electronic type with digital indicator for weight and
platform to keep the bags. Minimum capacity - 200 Kgs Platform size 635 x 560 mm.
(minimum)
Automatic Bag Placing, Filling, Weighing, Stitching Machine
These machines shall be used for Automatic bag placing, filling, weighing, and stitching of
finished feed in HDPE bags, as per the rated capacity indicated in the design Data.
122
The machine shall automatically place bags, fill, weigh & stitch the bags and convey them
towards the Finished Product Godown. This machine shall be fully automatic in its operation
through pneumatic cylinders, sensors, stoppers etc. & shall have a Local & remote display in
monitor, near the central PLC. The Central PLC shall also log no. of bags, weight of bags for
formulations in each shift, day etc. The weighing system shall be load cell operated having
arrangement for dribble and fast filling to achieve high accuracy of filling. Machines shall be
complete in all respects including its own control panel & system for indicating the no. of bags
filled, quantity of material being filled in each bag etc. This shall be nett ware type along with
pneumatic bag closing device.
Miscellaneous
Aspiration Ducts
Ducts are used for interconnecting dust producing centres such as hoppers/bins/machines etc.
with aspiration filters, blowers etc. These also shall help in pressure equalization between
successive bins /hoppers across pn. gate.
MINIMUM SIZE OF ANY PIPE SHALL BE 220 MM (NOMINAL DIA.)
All pipes, pipe accessories such as bends, spout branches, segments, elbows, transition pieces,
Y joints, exhaust pipes and chimney, throttle valves, etc. to be manufactured from sheets.
Minimum thickness of mild steel sheet for pipes shall be 2.5 mm. However, aspiration piping
from pellet cooler to pellet cooler blower via cyclone shall be of SS 304 of minimum 1.25 mm
(18 gauge) thickness.
Sight Glass for Air Lock
FUNCTIONAL REQUIREMENTS : To observe flow of material in product line.
DESIGN REQUIREMENTS : MOC frame -Aluminium; Sight glass - Acrylic
Scope of Supply
Acrylic cylinder of 200 mm height and 200 mm internal diameter and of 6 mm thickness with
chrome plated fixing clamps of 18 gauge plate at top and bottom with felt packing 5 mm thick.
Frame for glass fixing with top and bottom flanges of 10 mm thick Aluminium, anodized and
15 mm dia. fixing rods with counter-sunk screws with bolts, nuts, washers and felt packing 5
mm thick at top and bottom.
Gravity Spouting
Spouts are used for connecting different machines, hoppers, etc. for conveying various
ingredients and finished feed. These can be in the form of circular pipe or rectangular/square
shape with flanges only, no cufflink is allowed.
MINIMUM SIZE OF ANY CIRCULAR PIPE SHALL BE 300 MM. (NOMINAL DIA.) OR
700 SQ CM FOR RECTANGULAR /SQUARE DUCTS.
123
All spouting & accessories such as bends, spout branches, segments, elbows, transition pieces,
flaps etc. to be manufactured from minimum 3.15 mm thick mild steel sheets. Pipes &
accessories shall have non-porous & no projection on internal surfaces and having excellent
protection against rust.
Two / Three Way Flaps
Two/ Three way pneumatic flaps are required for diverting the flow of material in a gravity
flow line. Flaps shall be fabricated from sheet steel with inlet & outlet having flanges. These
shall be pneumatic type. Flaps to be complete with inspection windows, limit switches solenoid
valves, pneumatic cylinders (double acting) & operating handles etc. The main body of flaps
should be made from 2.5 mm (minimum) mild steel sheet and solenoid valves suitable for 230
V, 4 ports.
Pneumatic Gates
Pneumatic gates are required for discharging/accumulating solid ingredients in the
hopper/bin/mixer. These shall be pneumatically operated, & shall be complete with limit
switches to indicate the position of the gate to centrally located PLC in control room. For
pneumatic gates suitable size, air cylinder (double acting) & rating solenoid valve shall be
provided. The design of the gates shall be approved by the purchaser before supply. Wherever
required, pneumatic gate shall be provided with slots/stoppers and control mechanism to control
the flow rate of material rather then only open and close.
Automation Equipment &Accessories
Dynamic screen for monitoring and operation with IBM compatible personal computer
(minimum specification given in Appendix) with centralized data and status collection.
Automation system including latest version of PLC, SCADA system for real time control
system, UPS, Remote I/O panels, sensors, limit switches Ethernet cables, signal cables,
Operator‟s panel (HMI) for programmed process operation for optimal power utilization
with WINDOWS compatible software.
One additional computer (minimum specification given in Appendix) for Plant in-charge
with IBM compatible personal computer
Laser Printer (HP/Canon)
Modular type Furniture for computers/operator (Tables, chairs)
PC Specification
Particulars Minimum Specification
Motherboard Intel original
Processor Intel(R) Core(TM)2 Duo Processor E7500 (2.93GHz, 1066FSB, 3MB)
Operating System
Genuine Windows Vista(R) Business 32 bit / equivalent Window 7 OEM
Edition (English)
Preloaded Software As per requirement
Hardware Maintenance Atleast one year on-site support
Monitor 19" inch TFT Monitor
Memory 4 GB DDR2 800 MHz SDRAM Memory
Hard Drive 320 GB SATA 3.0 GB/s Hard Drive with Native Command Queuing
124
Optical Drive DVD Writer
Video Card Intel GMA 3100 graphics
Sound card/Audio
Solution Inbuilt sound card only, speakers not required
Wireless Solution Not required
IEEE 1394 Firewire Not required
Speaker Not required
Keyboard USB entry keyboard
Mouse USB mouse
Others Integrated 10/100/1000 Base Eathernet, Basic System installation, Power
cord, System Drive DVD Kit
Function:
Programmed operation through PLC logic, for Process monitoring, recording of data, report
generation from Raw material dumping in RMG, batching operation, Hammer mill, Pellet
mill operation, bagging upto dispatch to trucks after bagging shall be included.
Inputs from Raw Material silo storage and handling system panel.
125
Mineral Mixture
The proposed cattle feed plant would have provision of manufacturing various types of mineral
mixtures the can be added directly to the feed as well as sold separately. Ingredients used for
manufacturing mineral mixture are: magnesium oxide, zinc sulphate, ferrous sulphate,
manganese sulphate, copper sulphate, cobalt sulphate, potassium iodide, di-calcium phosphate,
sodium thio-sulphate etc.
Machinery for Mineral Mixture Unit
Dump feeder with elevator of 1 Ton per hour capacity for feeding the raw material to inlet
hopper of Ball Mill Grinder.
Ball Mill Grinding unit: Capacity 750 Kg/hour – 1no.
Ball Mill is an efficient tool for grinding many mineral material in to fine powder. We shall be
going for dry process. Bal Mill (Grinding Mill, Grinder) is made up of feeding part, discharge
parts, gyre parts, transmission parts etc.
It will comprise of Ball Mill Grinder with necessary provision of lifting the material from
Dump Hopper through elevator to the inlet hopper of Grinding Mill with suitable aspiration
system for air assisted & dust free operations complete with high efficiency electric motors of
suitable size.
Elevator of 1T/hour capacity for conveying grinded material in to Mixer complete with motor,
Drive & driven parts.
Mixer: 250 KG per batch
The design of the Mixer should be such so that it should ensure uniform mixing of various
mineral material for ensuring least coefficient of variance. Double ribbon type rotor with
pneumatically operated outlet flap, air cylinder & solenoid valve & air balancing duct. All the
internal contact parts should be of Stainless steel where as outer body should be of MS. The
Mixer should have necessary provision of Inlet, outlet, air aspiration facility. It should be
completed with suitable size energy efficient motor coupled with Gear Box.
Suitable elevator & conveying equipment for storing the mixed minerals in to storage Bin of
500 Kg capacity.
Hopper of 200 Kg capacity with Bagging Machine: For packing Mineral Mixture in various
sizes I.e. 35Kg, 25Kg, 10Kg.
Platform Electronic weighing Scale of 50Kg capacity with digital display -1no
Electronic weighing scale of 5Kg capacity with digital disply-1no.
Packing table with SS top for smaller packing. Heat Sealer
It is proposed to pack 1Kg, 500gram packing manually at the initial stage.
126
Technical Specifications for Utilities/Services General Requirements
The service pipe headers for steam, Molasses shall be designed for 450 TPD production
capacity. The supply of pipes, valves, fittings and accessories for utilities and services includes
but not limited to that for Molasses, LP steam, condensate, Compressed air. The following may
specially be noted.
For pipe sizing the following flow rates is to be considered.
– LP Steam 25 m/sec ;
– Condensate 2 m/sec
– Compressed Air 30m/sec
– Molasses 1 m/ sec
All valves for above services are to be flanged type except those below 25 mm.
The supply of above service pipes should be inclusive of same quality bends, tees, flanges
and with necessary gaskets, bolts, nuts etc
Flanges/Counter flanges shall be as per BS Tables:
– Table E for LP Steam
– Table D for Condensate
– Table F for Molasses
– Table E for Compressed Air
The bidder has to refer to the Special conditions of contract for erection of mechanical
works for details on Mechanical /Service piping installation and Special conditions of
contract for erection of electrical works for the Electrical installation.
Painting of pipelines with anti corrosive primer and paint of approved shade including,
lettering, marking, flow directions etc., shall be as per the special conditions of contract for
erection of mechanical works
Expansion bend for LP steam line to be provided at every 30 mts straight line piping
complete with Air vent and condensate drain arrangements as per standard practice.
Molasses
Molasses Distribution and Molasses Piping
Piping shall be electric arc welded type with MS Class „C‟ ERW pipes (shall conform to IS
1239) complete with pipes, bends, flanges etc. Molasses supply lines from the outlet of
Molasses Storage tanks upto molasses mixer/ feeder conditioner of pellet mill shall be traced
along with LP steam piping duly insulated with resin bonded mineral wool of minimum 50 mm
thickness complete with 22 SWG Al sheet cladding.
Molasses Valves and Fittings
Flanged type Duplex filters before pumps are required. The following type of valves and
fittings for the molasses lines between pump and at molasses utility points is required as per
requirement: Pressure relief valve, Glycerine filled Pressure gauges, Butterfly ball valves, etc
shall be supplied. For accurate dozing of Molasses in the Molasses mixer, pneumatically
operated flow control valve shall receive input form PID controller, based on the Feed rate
measured in loss in weight feeder. By-pass of the pneumatic control valve shall be provided.
Pipes shall be rigidly supported by shoe & guide.
127
Compressed Air
Compressed Air Equipment and Distribution
AIR COMPRESSOR CAPACITY: 60 CUM/HR
This is required for producing compressed air required for operation of pneumatic flaps gates
and aspiration filters of feed mill, etc.
This shall be air-cooled, screw two stage compressor, lubricated type, to generate compressed
air at suitable pressure and required free air delivery. Compressor shall be complete with intake
filters, un-loader, inter cooler between two stage and all standard accessories such as service
valve, safety valve, auto drain valve, pressure gauge, drive motor & drive parts etc.
Compressor shall be provided with a pressure switch for auto operation. The capacity of
receiver shall be sufficient to meet sudden large requirement of compressed air and to avoid
frequent ON/OFF of compressor. For removal of bulk of moisture from receivers, automatic
drain valve with solenoid etc. To be provided.
REFRIGERATED AIR DRYER CAPACITY: 60 CUM/HR
Functional Requirements
Air drier would be required to provide moisture free compressed air for use in various
equipment, controls & instruments.
Design Requirement
The Air Dryer shall be refrigerated type, air cooled type and capable of handling upto 60
CUM/HR (Cubic meter per hour) of air at a maximum pressure of 16 kg/sq cm.
Operating Conditions Desired Maximum
Inlet Temperature 35 0C 55
0 C
Ambient Temperature 25 0 C 43
0 C
Inlet Pressure 7 bar (gauge) 16 bar (gauge)
Pressure Dew Point 3 0 C NIL
Scope of Supply
The Air drier should be provided with the following:
Air inlet connection
Air outlet connection
Refrigerant separator
Pressure dew point meter
Air-drying unit insulating block housing Air-to-Air heat exchanger, air to refrigerant heat
exchanger/evaporator, cyclone condensate separator, liquid separator, refrigerant
distributor, refrigeration injection restrictor, hot gas by-pass.
Condensate trap with automatic discharge
128
Manual drain valve for condensate & auto drain valve (timer based)
Air cooled condenser
Safety switch, High & Low pressure
Liquid refrigerant dryer
Liquid shut off valve
Liquid refrigerant receiver
Liquid separator
Sight glass with moisture indicator
Refrigerant expansion valve
Refrigerant circuit access connection
Hose, automatic condensate discharge
Air Receiver
Capacity: 1000 litres
Function:
Air receiver shall store compressed air, help equalize pressure variation in pipes, & prevent
short cycle loading and unloading of compressor.
Design Requirement:
Receiver shall be vertical type with dished ends and shall meet the statutory requirement of
pressure vessels. Receiver shall be designed conforming to IS 7983 and the material of
construction shall conform to the relevant IS in Mild steel. The receiver shall be complete with
safety valve, service valves, pressure gauge, fusible plug, hand holes, drain valve with
automatic drain arrangement Timer based) to remove moisture. The air receiver shall be
designed for Design pressure of 12 Kg/sq.cm & should be Hydro-tested at 18 Kg/sq.cm.
Compressed Air Piping and Valves
Air filter cum moisture separator is required to remove moisture, oil fog lubricator for
lubricating and pressure regulator to regulate the pressure. Heavy duty, mild steel ERW piping
“C” class (shall conform to IS 1239), only welded or flanged installation, complete with SS
ball valves, flexible metal braided hoses & brass nipples, 4 port, 3 way Solenoid valves etc as
per requirement. Pipes shall be rigidly supported on CI clamps.
Steam & Condensate
LP Steam Piping
LP steam piping should be non-IBR type and MS „C” class ERW pipes (shall conform to IS
1239), with shoe, guide arrangement shall be used. Expansion bends shall be provided at every
30 m straight line pipe, with Air vent & drain trap arrangement. These lines shall be traces with
Molasses pipelines.
129
Insulation
Thermal insulation of steam lines with resin-bonded mineral wool in pipe form including
cladding with 22 G Al. Sheet as per IS 737-1900 (amended as on date) should be provided.
Valves & fittings shall also be insulated.
Steam Valves and Fittings
The following shall be provided wherever required between PRS outlet and steam utility points
: Cast steel flanged glandless piston/ball valves with SS working parts, CI strainer with brass
screen, thermodynamic steam traps (for pipelines, headers only), angle needle valve, moisture
separators, safety valves, non return valves (wafer type), dial type pressure gauges etc. Steam
trap assembly shall be complete with by-pass valves. A pneumatically operated steam control
valve shall automatically control the feed rate of steam to the conditioner, regulated by the
feedback received from the temperature sensor in the conditioner. By-pass of the pneumatic
control valve shall be provided. Air vent shall be provided at the highest point in the steam
piping & on the expansion bend, if any. Condensate drain trap assembly on the LP steam shall
be located just before the expansion bend & Pellet mill conditioner.
Condensate Pipes, Valves and Fittings
Type:
ERW MS `C‟ class (shall conform to IS 1239) welded type heavy duty piping with CS body
ball valves, NRVs (wafer) in flange/screwed execution. Supporting: MS shoe, guide, roller
support, in mild steel painted execution generally as per bidding document and meeting with
IBR requirements. Accessories: Pipe sleeves, roller supports, flow measurement at the entry
point to the plant.
Pipe Insulation:
50 mm Thick insulation mineral wool, with 22 G aluminium sheet cladding. Condensate
Recovery system shall consist of pressurized recovery of condensate generated during
preheating of molasses in the shell & tube heat exchanger. The recovery system shall make use
of steam pressure rather than electrically operated arrangement to transfer condensate to Feed
water tank in Boiler House. The specification of condensate piping, valves shall be similar to
LP steam.
130
Electrical
Design, Manufacture supplier, erection testing & commissioning of compartmentalized
cubical type Panel Board with incoming feeders, ACB 4 pole Air Circuit Breaker,
Aluminium bus bars design 1600amps with Volt meter, Ammeter, 3 phase energy meter, set
of CT‟s, Phase indicating lamps etc. outgoing feeders (a) 4 pole micro processer based
MCCB 800amps with inbuilt release for short circuit, overload protection for Cattle Feed
Plant (b) Boiler House – 4 pole 160amp. MCCB (c) By-pass Protein Unit, MCCB Unit
200amp (d) 160amps. For weigh bridge (e) Godown lighting (f) External lighting (g) Spare
MCCB 160amps. 3 nos.
LT cables from LT Panel located in the substation room to the Main plant MCC & Raw
water pumps are included in the scope of work. Interconnecting LT power/ Control Cables
from Main plant MCC to Boiler House MCC, Raw material Intake MCC, Silo System,
APFC panel are included in the scope of work.
Standard Motor Control Centre (MCC) for the Main plant for incoming & outgoing
electrical feeders (in cubicles) described in the work scope shall be supplied.
Separate MCC for Silo System equipments, the Raw material loading into proportionate
Bins in the Main plant. This panel shall be suitably located near silo and shall be receive
power from the Main plant MCC
Separate Soft-starter panel for motors above 20 HP, shall draw power from the Main plant
MCC & shall be located in the plant electrical room. VFDs shall also be installed in the
soft-starter panel. This panel shall be located in the Main Plant electrical room.
One MCC in Boiler House for electrical loads in Boiler House for Boilers panel, water
softener, Molasses unloading pumps, Air compressor etc is included in the scope. One
feeder of 63 amps shall be provided for welding purpose in the Boiler House MCC.
Outdoor type panel for Raw water pumps near the water pumps is included in the scope.
One number Power Factor Correction panel with capacitor banks to improve PF for Main
plant, Boiler panel with interconnecting cables shall be placed near the Main Plant MCC.
Lighting panel for the Main plant, including Distribution Boards, trays, conduits, Light
fittings are included in the scope. Power for Lighting panel shall be drawn from an outgoing
feeder in the Main lighting panel in Substation room. The lighting loads shall be equally
distributed in three phases.
Remote Push button stations, isolators, junction boxes etc for control, isolation etc included.
The entire Earthing network for the equipments shall be in the scope of work.
One Lightening arrestor for the Main plant with GI earth-pits shall be included in the scope.
MCC/ Electrical panel for the following shall be supplied;
1. LT Panel.
2. Main plant MCC.
3. MCC for Silo System Equipments
4. Soft-starter panel.
5. Boiler House MCC.
6. Panel for Raw Water pumps.
7. APFC panel.
8. Lighting panel for Main plant
131
Following are the feeder details to be considered for following panels, apart from the electrical
loads in the scope of work for each site
S. No Description Feeder detail Qty
Main LT Panel
1 Incoming Feeder
Air Circuit Breaker 1200amps 1 No.
2 Outgoing Feeder
Air Circuit Breaker 800amps 1 No.
Main Plant MCC
1 Boiler House MCC 250 A MCCB 1 No.
2 Welding Feeder 63 A MCCB 1 No.
MCC for Raw material Intake
1 Mineral Mix plant 100 A MCCB 1 No.
3 Raw material silo storage system 200 A MCCB 1 No.
4 Welding Feeder 63 A MCCB 1 No.
From Boiler House MCC
1 Softener pump 3 HP DOL starter 1 No.
2 Boiler Control Panel 63 A MCCB 2 Nos.
3 Welding Feeder 63 A MCCB 1 No.
4 Air Compressor 63 A MCCB 1 No.
5 Feeder for Air dryer 6 A DPMCB 1 No.
Outdoor panel for Raw water pumps
1 Raw water pumps 7.5 HP DOL starter 2 Nos.
2 Spare Feeder 3 HP DOL starter 2 Nos.
Outdoor type panel for Raw water pumps is to be supplied. Outdoor panel shall have incoming
and outgoing feeders with push buttons for electrical equipment such as motors/pumps, spare
feeders. The bidder shall confirm with the purchaser, the rating of the outgoing feeder for Raw
water pumps, as per actual electrical load requirement.
Boiler House MCC shall have starters for Molasses unloading pumps & electrical heaters for
the unloading pumps. Remote Push button stations for these pumps, shall be provided in Cast
aluminium IP 55 protected housing near these pumps. However, starters for the Molasses feed
pumps (for the plant) shall be located in the Main Plant MCC.
Instruments & Protective Relays to be provided in MCC/Panel as below details;
S. No. Components Incomer Outgoing Feeder
1 RYB LED Indication Lamps YES NO
2 Voltmeter with selector switch YES NO
132
3 Ammeter with selector switch YES YES
4 Over & under voltage protection YES NO
5 Over Current Protection YES YES
6 Inst. Earth Fault YES NO
7 Energy Meter YES NO
8 ON-OFF LED Indication lamps YES YES
9 Power Factor Meter YES NO
Motor Control Centre (Sheet Steel Enclosure)
Functional Requirement
Panels shall receive, control and distribute electrical power at 440 V, 50 Hz, AC in sheet steel
housing.
Design Requirement and Scope of Supply
Statutory Requirements:
Motor control centre is to be manufactured /assembled as per the latest ISI Specification, Indian
Electricity Rules, including special requirements of concerned State Electricity Inspectorate and
the detailed specification mentioned below.
Housing Details:
The switchboard shall be fabricated using pressed and shaped cold rolled steel sections
structure of adequate thickness. The sheet steel used for panel shall be minimum 14 SWG
sheet except that the partition plates, inter-panel barriers which shall be made of 16 SWG.
The switchboard shall consist of free standing front open able panels arranged to form a
continuous line-up of uniform height. Cold rolled sheets shall be used for doors and front
covers. Front doors shall be hinged type and bus bars and cable alleys covers shall be bolted
type with thumb screws.
Switch Board shall be extensible at both the ends by addition of vertical sections. Ends of
the bus bars shall be suitably drilled for this purpose. Panels at extreme ends shall have
openings, which shall be covered with plates screwed to the panel. The switchboard shall be
provided with integral base frame. The panel base plate/cable gland plate shall be 2.5 mm
thick.
The switchboard shall be totally enclosed, dust, weather and vermin proof. The switchboard
shall conform to degree of protection not less than IP 44. Gaskets of durable material shall
be provided for doors and other openings. Suitable hooks shall be provided for lifting the
boards. These hooks when removed shall suitably plugged in the board.
All hardware shall be corrosion resistant. All joints and connections shall be made by
galvanised zinc passivated or cadmium plated high tensile strength steel bolts and nuts.
Spring washers shall be provided to secure against loosening.
The switchboard shall be in cubicle design (each feeder components are housed in
individual cubicle) suitable for indoor installation. Suitable cable & bus bar alleys shall be
provided. In case plant room dimensions prohibit provision of cable/bus alleys in front,
panel depth may be increased suitably to accommodate cables/buses on back of MCC. All
133
components of the switchboard shall generally be approachable from front. However, MCC
can be in double front execution also if specifically asked for, or space restriction.
The maximum and minimum operating handle/push button height of any feeder shall be
approximately 1900 mm and 300 mm respectively with reference to panel bottom. The total
height of panel shall generally not exceed 2300 mm. Supporting arrangement for dressing of
power and control cables in cable alleys also shall be provided. Maximum shipping length
of MCC shall be 2500 mm.
Motor HP Cubicle for DOL starter Cubicle for Star-Delta starter
Width (mm) Height( mm) Width (mm) Height( mm)
Up to 10 HP 450 275 -- --
12.5 & 15 HP -- -- 450 550
Note: The size of feeders with soft starters, variable frequency drives (VFD) shall be decided
as per the size of the soft starters, its switching device and the type of connection for the
application.
Current Rating of
SFU/MPCB/MCCB
Cubicle for SFU/MPCB/MCCB
Width mm Height mm
Upto 63 A 450 275
100 A to 250 A 450 550
400 A and above 500 825
Minimum depth of cubicle for ACB shall be 1000 mm.
Minimum depth of panel shall be 350 mm.
Minimum width of cable and bus bar alleys shall be 300 mm
Painting:
All metal surfaces shall be thoroughly cleaned and degreased to remove all scales, rust, grease
and dirt. Fabricated panels shall be pickled and treated to remove any trace of acid. The under-
surface shall be prepared by applying a coat of phosphate paint and a coat of yellow zinc
chromate primer. The under surface shall be made free from all imperfections before
undertaking the final coat. After preparation of the under surfaces, the panel shall be spray
painted with two coats of approved shade of po der coating. The finished panels shall be dried
in stoving ovens in dust free atmosphere. Panel finish shall be free from imperfections like pin
holes, orange peels, run-off paint, etc. All unpainted steel parts shall be cadmium plated or
suitably treated to prevent rust, corrosion, etc.
Nameplates:
Nameplates for all incoming and outgoing feeders shall be provided on doors of each
compartment. Nameplates shall be fixed by screws only and not by adhesives. Engraved
nameplates shall preferably be of 3-ply (Black-White-Black) acrylic sheets or anodized
aluminium. Special danger plates shall be provided as per requirement.
Inside the panels, stickers should be provided for all components giving identification no. as per
detailed wiring diagram.
Bus bar Sizing Connection and Supports:
134
The bus bars shall be made from high conductivity electrolytic aluminium conforming to
grade E91 E of IS 5082. The bus bars and supports shall be capable of withstanding the
rated and short circuit current stated in the single line diagram/feeder details. Minimum size
of power bus bars shall be 200 Amps. rating. Maximum current density permissible for
Aluminium bus bars shall be 0.8 Amps./Sq. mm for bus bar area above 500 Sq. mm & 1.0
Amp/Sq. mm for bus bar area below 500 Sq. mm. An earthing bus bar of minimum 150 Sq.
mm section aluminium shall be provided outside panel at bottom throughout the length of
the panel. Provision shall be made to connect the earthing bus bar to the plant earthing grid
at two ends. All doors shall be earthed using flexible copper connections to the fixed frame
of the switchboard.
Maximum current density permissible for Copper bus bars shall be 1.5 Amps./mm2
The bus bars hall be provided with heat shrinkable PVC insulating sleeves of 1100V grade.
Red, yellow and blue colour shall be used for phase bus bars and black colour shall be used
for neutral bus bars. Joints shall be shrouded suitably. Supports for bus bars shall be made
of suitable size non-hygroscopic and non-inflammable epoxy compound SMC/DMC blocks
and these should be adequate in number so as to avoid any sag in the bus bars.
Minimum clearance between phase to phase shall be 25 mm and that between phase to
neutral/earth shall be 20 mm
Power Connection:
For power interconnection within the panel board:
Copper stranded conductor PVC insulated cables suitable for 1100 volts, of adequate cross
section shall be used. FOR CURRENT RATING ABOVE 63 AMPS ALUMINIUM
BUSBAR STRIPS OF ADEQUATE RATING SHALL BE USED. MINIMUM SIZE OF
COPPER CONDUCTOR TO BE USED SHALL BE 4.0 SQ.MM. Cable lugs/ sockets of
suitable size and type shall be used for all interconnections wherever required.
For all Aluminium to Copper connections: - The Copper surface will be silver plated and
the aluminium surface will be properly cleaned and supplied with oxide inhibiting grease.
For all outgoing motor feeders, the suitable size terminal blocks shall be provided in cable
alleys near feeder‟s cubicle and wiring upto these from contactors shall be done by panel
supplier. These terminal blocks shall be heavy duty type to withstand high starting currents.
For incoming and outgoing feeders of the MCC, copper/aluminium conductor cable will be
used and hence the panel is to be designed for receiving these and wherever required cable
boxes with bus bar extensions for receiving more no. of cables, shall be provided in panel
by supplier. Removable gland plates of 12 gauge thickness shall be provided on top/ bottom
of panel, for cable entries. Supplier to check with purchaser whether incoming/outgoing
cables are to enter MCC from bottom or top.
To prevent accidental contacts, all interconnecting cables/bus bars and all terminals also
shall be shrouded.
Standard colour code of red, yellow and blue for phases and black for Neutral to be
followed for all bus bars/conductors.
Auxiliary wiring and Terminals:
Wiring for all controls, protection, metering, signalling etc. inside the switchboard shall be
done with 1100 volts grey colour PVC insulated stranded copper conductors. Minimum size
135
of these conductors shall be 1.5 Sq.mm. CT circuit wiring shall be done with 2.5 Sq.mm.
Control wiring to components fixed on doors shall be flexible type.
The complete panel would be sub-divided into different sections if required by purchaser.
Each cubical shall have its own control circuit with MCB and indication. Terminal block
(Minimum 3-ways) for control wiring shall be provided for each outgoing Motor feeder in
its cubical near cable alley. 10% spare (minimum one) terminals shall always be available
in each terminal block. Control wiring up to these terminal blocks shall be done by supplier.
All control wiring should be provided with necessary cable sockets/lugs at both ends.
Separate cubicle can be provided in the panel to enable termination of multi-core control
cables.
Conductors shall be terminated using compression type lugs. Each termination shall be
identified at both the ends by PVC ferrules. The identification termination numbers should
match with those on drawings.
Control wiring for motor feeders should be such that the "green" light of motor feeder is
"ON" only when control as well as power circuit of feeders is "ON" and it shall have its
own MCB.
For all motor starter feeders, provision for control wiring to remote ON/OFF control is to be
made. The auxiliary wiring for the same shall be brought up to terminal block in the feeder's
cubicle.
Switchgears:
Air Circuit Breakers (ACBs)
These shall be manually operated, fully draw out type, 4 pole type with built-in microprocessor
based programmable protection suitable for 415 V, 50 Hz. supply. Microprocessor based
programmable protection unit shall have settings for overload, short circuit, instantaneous and
earth fault currents with time delay and LED indicators to show various conditions such as
Power ON, Overload, Short-circuit, Instantaneous Earth fault, Percentage load, Self Diagnostic
Test etc. Mechanical spring charging mechanism stored energy type shall be provided with
mechanical indicators to show 'Open', 'Closed', 'Service' & 'Test' positions. The circuit breaker
shall be provided with mechanically operated emergency tripping device. This device shall be
available on the front of the panel. Mechanical interlock shall be provided such that the ACB
feeder cubical door cannot be opened when ACB is "ON". However, it shall be possible to
defeat this interlock for inspection purpose. Trip coil shall work under the following voltage
variation conditions:
Trip coils: 50 % to 130 % of rated voltage
The circuit breaker shall be provided with mechanically operated emergency tripping device.
This device shall be available on the front of the panel. The circuit breaker position shall be
indicated electrically. The following indicating colours shall be used: BREAKER CLOSE RED
BREAKER OPEN GREEN
BREAKER AUTO TRIP AMBER
Note: The air circuit breaker for incoming feeder shall be of 4 pole construction, unless stated
otherwise. It shall also be provided with under voltage coil and single phase protection
relay.
136
Moulded Case Circuit Breakers (MCCB)
MCCBs shall always be provided with separate operating handle mechanism with door
interlocking. The MCCBs for motor feeders shall be of triple pole construction arranged for
simultaneous three pole manual closing or opening and automatic instantaneous tripping on
short circuits. MCCB used for incoming feeder or for non-motor outgoing feeder, shall be of 4
pole type. MCCBs shall be provided with adjustable type tripping device with inverse time
characteristics for over load protection. All motor feeders MCCBs shall be provided with
neutral link complete with isolating link.
Closing mechanism shall be quick make, quick break and trip free type. Operating handle shall
give a clear 'ON' 'OFF' & 'TRIP' indication. Control voltage for MCCB shall be 240 volts. The
ratings shall be as specified in feeder details or approved drawings.
Minimum rated breaking capacities shall be as under: MCCBs up to 100 Amps 135 KA
MCCBs above 100 Amps 150 KA
Note: All feeders having MCCB shall be provided with neutral link complete with isolating
link. However, the MCCBs for incoming and non-motor feeders shall be of 4 pole
construction, unless stated otherwise.
Motor Protection Circuit Breaker (MPCB)
These shall be used along with conjunction with power contactor as specified in special
requirement of this project/drawings. MPCB shall be selected for motor protection tripping
characteristics, current limiting and shall have low let through energy. MPCB shall have inbuilt
bimetal for overload protection and Electro-magnetic release for short circuit protection.
MPCB shall have adjustable overload settings, single phase protection & auxiliary
switches/contacts for indications, interlocks etc. It shall comply with latest standard and provide
short circuit coordination TYPE “2” in accordance with IEC 947-4-1 with contactors. The
Contractor and MPCB shall be of same make. MPCB should give indication for ON/OFF and
tripping on fault. The minimum breaking capacity of the MPCB shall be 50 KA. MPCB shall
have door interlocking with cubicle feeder door by suitable extensions.
Switch & fuse switches
Switches or fuse switches shall be load break, heavy duty, air break having continuous
maximum rating type with manual quick make/break mechanism. Mechanical interlock shall
be provided to prevent opening of door in switch „closed‟ position and prevent closing of
switch in door „open‟ position. However, it should be possible to defeat this arrangement for
testing purpose.
Fuses
These shall be non-deteriorating HRC cartridge link type with operation indicator which will be
visible without removing fuses for the service. These shall be complete with moulded phenolic
fuse base and cover. The fuse base shall be so located in the modules to permit insertion of fuse
pullers and removal of fuse links without any problem.
137
Contactors
The rating of the power contactors shall be as required depending upon the feeder rating
indicated in the specifications and as per the table provided in this specification below.
Contactors coils shall be suitable for 240 volts, 50 Hz. unless otherwise specified. All
contactors shall be supplied with minimum 2NO + 2NC auxiliary contacts. Additional contacts
if required for interlocking etc. shall also be provided. All contactors of motor starters shall be
suitable for AC 3 duty unless specified otherwise. Auxiliary contactors for controls shall have
minimum 2NO + 2NC auxiliary contacts.
Protective Devices
Bimetal overload relays with inbuilt single phase protection shall be adjustable and self reset
type. Alternatively, electronic relay with LCD display and annunciation with trip reasons may
also be provided. Heavy duty starters shall be provided with saturable type current transformer
operated overload relays only, which shall be suitable for motor starting time of 15-60 seconds.
Any other relays, if required for incoming & outgoing feeders shall be specified in the feeder
details.
Timers
The timers shall be continuously adjustable and electronic type, suitable for 240 V, 50 Hz
supply. The timers for Star Delta automatic starters shall have time delay of 0 to 60 seconds
between changeovers of contacts.
Push Buttons (PBs)
Push buttons shall be complete with actuator and contact block & LED indicator type. These
shall be generally mounted on doors of the cubicles. Colours shall be as follows: Stop/open/emergency Red
Start/close Green
It should have minimum 1 NO + 1NC contacts. Push buttons shall conform to IP-65 protection
against dust and water ingress.
Indication Lamps
All outgoing motor feeder shall be provided with „ON‟ indication lamps. For all incoming and
non motor outgoing feeders shall be provided “ON” indication lamps for all three phases.
Colours shall be as under: Phases Red, Yellow & Blue
ON Red
OFF Green (Only for ACB Feeder)
TRIPPED Yellow (Only for ACB Feeder)
Indication lamps shall be in the form of cluster of high intensity light emitting diodes (LED) to
give bright indication. These lamps shall be of 22.5 mm dia and having operating voltage of
240 V, AC.
138
Current Transformers (CTs)
CTs shall be cast resin insulated type. Primary and secondary terminals shall be marked
indelibly. CTs shall preferably be mounted on stationery parts. These shall be capable of
withstanding momentary short circuit and symmetrical short circuit current for 1 second and
shall have a minimum rating of 10 VA. Neutral side of CTs shall be earthed. Protection CTs
shall be of low reactance, accuracy class "SP" and an accuracy limit factor greater than "10".
Instrument CTs shall be of accuracy class "1.0" and accuracy limit factor less than "5.0".
Separate CTs to be provided for protection and metering purpose.
Measuring Instruments
These shall be of square pattern having approximate dimensions 96 mm x 96 mm, flush
mounting type. Necessary auxiliary instruments like CTs, VTs, etc. are also included in the
scope of supply. All AC meters shall be of Digital type for displaying three phases reading.
Suitable selector switch shall be provided if the digital meter does not have provision for
simultaneous display of three phase readings. Voltmeter shall be suitable for direct line
connection. Voltmeters shall be connected through MCBs only.
General Requirements
All non-motor outgoing feeders shall have ammeter with selector switch to indicate current in
all three phases. Ammeter shall always be CT operated. The following selection table shall be
followed for switches & contactors of motor feeders unless otherwise specified :
S. No 415 V Motor
rating (HP)
Contactors
Rating (amps)
MCCB Rating
(amps)
MPCB Rating
(amps)
Type of Starter
1 Up to 7.5 HP 25 ---- 16 DOL
2 10 & 15 HP 32 ---- 25 STAR-DELTA
3 20 to 25 HP ---- 40 ----
SOFT
STARTER
4 30 to 35 HP ---- 50 ----
SOFT
STARTER
5 40 HP ---- 63 ----
SOFT
STARTER
6 45 HP ---- 100 ----
SOFT
STARTER
7 50 to 60 HP ---- 100 ----
SOFT
STARTER
8 65 to 70 HP ---- 200 ----
SOFT
STARTER
9 75 to 90 HP ---- 200 ----
SOFT
STARTER
10 100 to 125 HP ---- 250 ----
SOFT
STARTER
11 150 to 180 HP ---- 400 ----
SOFT
STARTER
12 200 to 250 HP ---- 400 ----
SOFT
STARTER
139
Special requirements
1. For capacitors, rating of contactors switch shall be double of rated current of capacitor.
2. All motors upto 7.5 HP feeders shall have DOL starter for motors of 10 HP 15 HP shall
have star delta starter, motor feeders above 20 HP shall have soft starters.
3. All motor feeder rating of 20 HP above shall have ammeter with selector switches.
4. Motor feeders upto 15 HP shall be provided with MPCB for feeders 20 HP above shall be
provided with MCCB of specified minimum breaking capacity.
5. If the total operating load on MCC is more than 600 KW, MCC shall have t 0 incoming
feeders with a bus coupler (similar to incoming feeder without protection and metering
provisions). Each incoming feeder shall have independent instrumentation and protection.
6. For incoming feeder of rating up to 600 Amps, MCCB (4 Pole type) and for rating 600
Amps and above ACB (4 Pole type) shall be provided. Each incoming feeders to be
complete with earth leakage relay. For incoming feeder for the Main plant, a
microprocessor based data logger to be provided to indicate and store 3 phase voltages, 3
phase current power factor, energy consumed in Hand VAR etc.
7. For High electrical loads like Batch mixers, Hammer Mills, Pellet Mills, Pellet cooler fans,
capacitors shall be placed in the Main plant MCC shall be directly connected, once the
respective feeder is put ON.
8. If the non motor outgoing feeder rating is 100 Amps and above, MCCB (4 Pole type) shall
be provided.
9. All control wiring in feeders, instrument connections shall be wired through 2 Amp
DPMCB.
10. Electrical interlocking shall be provided between various feeders as required by the process
or specified in special requirement for this project or approved drawings.
11. Induction motors (above 10 KW) with 3000 RPM shall require higher rating for MPCB
MCCB, contactors and electronic timers due to very high starting current. MCC supplier to
specially check this requirement from purchaser before preparing the drawings.
12. Feeder details for incoming and outgoing for this project as per battery limit to be worked
out by the supplier as per the design and requirement of the plant.
13. Motors for Hammer Mills pellet Mills with common base frame, the final termination at the
motors end, shall be with copper conductor cable.
14. In addition to the connected load to MCC, at least 10 (rating) spare outgoing feeders
complete with starters shall be provided. These spare feeders shall cover as far as possible
more or less all sizes of starters.
15. VFDs provided in the panel for plant equipment shall be interfaced to the Central PLC
through Ethernet or similar type of communication cable. The VFD shall be dynamically
controlled from the PLC depending on the program and feedback system from field. These
VFD shall have Battery back- up and communication port.
16. Rubber mats, 12 mm thick suitable for 11 V to be provided in front of operating side of
MCC for full length of MCC.
17. All the ma or components of an MCC shall be of same Make
Soft Starter Panel
Panel for Soft-starter shall have specifications similar to that of MCC with suitable sized
cubicles for outgoing feeders. This panel shall have ON, OFF, TRIP indications, with ammeter
& provision for cooling arrangement like fan & louvers. VFDs for feeders for Pellet Mill &
140
Hammer mill shall also be installed in this panel. Soft-starters are required for Heavy-duty start
applications for motor ratings above 20 HP & shall be used in conjunction with MCCB (with
tripping arrangement) in a panel feeder. The selection of the soft-starter shall be based on the
application, ambient temperature, no. of start & stops/hr & rating of the motor. Standard
features like Ramp-up time, Ramp-down time, % starting voltage, LED indications etc shall be
available in the unit. For Hammer Mill & Pellet Mill motors, the soft-starter shall have
additional features like adjustable current limiting, thermister protection for motor, built-in CT
& PLC communication port. All soft-starters shall have electronic overload relay & for motors
above 50 HP the starter shall have inbuilt electronic overload relay with a trip class 30 & fan
cooling arrangement. In most cases, soft-starter shall be in-line connected. However, if
required, for specific application, an inside delta connected soft-starter with suitably rated
contactor, can be considered.
Automatic Power Factor Correction Panel With Capacitors
The capacitor requirement shall be calculated considering the overall inductive loads of Main
plant equipments under the scope of supply. Power factor correction for electrical loads of other
associated plants need not be considered. The calculation of capacitor requirement shall be
shared with purchaser and approval of the final requirement shall be taken from purchaser
before supply. This panel shall be located near Main plant MCC & for the design purpose an
initial power factor of 0.8 shall be assumed. CT for PF relay shall be located on the load side of
the incoming feeder of the LT PANEL.
Automatic Power Factor Correction Panel
Automatic Power factor Correction panel is required to continuously measure and monitor the
power factor of a system and switch ON/OFF bank of power capacitors to bring the power
factor of the system to a preset value. This shall be a separate panel which shall receive input
from LT PANEL. The panel is to be fabricated with 14 SWG thick cold-rolled sheet steel
enclosure, indoor type, floor mounted, weather and vermin proof with similar specifications of
a Motor Control Centre with provisions for heat dissipation (louver with mesh) & suitable for
415 V, 50 Hz, 3 phase supply.
It would consist of -
An automatic power factor correction relay, microprocessor based, with arrangement for
sensing the power factor of the inductive load and giving signal to 16 feeders (min) of power
capacitors, as per the setting of P. F. and electronic circuit to ensure that once a capacitor gets
cut off, it is not put on at least for a minute. The relay should automatically manage capacitor
banks. The capacitors must be turned "on" and "off' according to the reactive power required to
correct the power factor of the load to the power factor set on the relay. The relay should have
automatic and manual mode of operation with a LED to indicate the operating mode. The
auto/manual function makes it possible to turn the capacitor banks on and off manually
regardless of the line value measured.
APFC panel shall have the following;
141
Description Unit Required
Suitable rating SF unit/MCCB, contactor, pair of ON/OFF LED indication type push
button for each outgoing capacitor feeder
1 set
Flush mounted 96 mm x 96 mm square digital power factor meter having 4 digits
LCD or LED display
1 set for the
incomer
Selector switch and CT operated digital ammeter of size 96 mm x 96 mm 1 set for the
incomer
Selector switch and digital voltmeter of size 96 mm x 96 mm 1 set for the
incomer
Auto manual switch and connected circuit to ensure that in manual mode each
capacitor can be put ON/OFF manually
1 set for the
incomer
Incoming feeder with suitable rating MCCB/ACB to feed power to switchgears of
capacitor bank
1 set for the
incomer
Suitable 3 phase and neutral bus bars 1 set
Wiring for all above accessories/functions should be complete and ready for use. The details of
each capacitor bank rating, no. of capacitor banks and rating of incoming switchgear for power
factor improvement cubicle shall be as per details given in the data sheet and schedule of
quantities.
Power Capacitors Banks
The power capacitor banks shall be used to improve the power factor of an electrical system
and shall be housed in the power factor correction panel separated from the feeder cubicle.
Design Requirements
Each basic unit is to be built up with a number of elements. These elements shall be All
Polypropylene film (Super Heavy duty), non-self healing type with low watt loss. Capacitor
element must be completely sealed with epoxy resins to provide maximum humidity protection
and highest insulation. The capacitor elements are to be given adequate outside insulation and
should be put in all welded surface treated MS containers. The outer surface shall be provided
with a coat of protective primer followed by two coats of synthetic enamel paint of approved
shade. These capacitors shall be Non PCB oil impregnated under high vacuum. The metal case
shall be equipped with porcelain bushings to permit connection between power lines and active
capacitors. The unit shall have built-in internal individual fuses.
Externally each capacitor unit shall have two separate earthing points, name plate confirming to
the requirements of IS-2834 (amended up to date), discharge resistances etc. Each capacitor
should be suitable for operation on 440 V, 3 Phase, 50 Hz AC power supply for 25 KVAR
rating.
142
Geared Motors & Gear Boxes
Gear Boxes are required for torque transmission & speed reduction for plant equipments. Speed
reduction for machines shall be through geared motors only unless gear boxes have been
specified in individual machine's specification. The geared motor should use helical gears. The
electric motor and helical gear box should be built as one unit. The geared motors gear boxes
shall be selected for minimum 15 start stops per hour, for moderate shock load for continuous
operational requirement with a minimum mechanical service factor of 1.5, without undue
heating of gear oil. The load factor for overhang shall also be considered for gearbox selection.
Geared motors / boxes shall be complete including key in the driven shaft, oil level indicator,
oil filling plug, oil breather and drain plug. Suitable grade gear oil for first charge of geared
motor / boxes should not be filled but should be packed separately in a drum and sent along
with geared motor/boxes. Suitable grade Gear oil for the gear box /geared motor shall be filled
at site before testing. The electric motors used for geared motors / gear boxes should be TEFC,
degree of protection IP¬ 54/55, squirrel cage, induction type, with class 'F' insulation suitable
for 415 V, 50 Hz, 3 phase AC supply. Electric motors performance in general should confirm to
IS-325-1996.
Electric Motors
These are required for driving various machines of the plant. All motors should be TEFC
(Totally Enclosed Fan Cooled), squirrel cage, degree of protection IP-54/55, horizontal foot
mounted, induction type, rated for continuous duty, with class 'F' insulation suitable for
operation on 415 volts (+/_ 5% ), 50 Hz, 3 phase AC supply. All motors to be supplied shall be
"Energy Efficient" type and shall confirm to the latest relevant IS and shall comply with the
following:
1. All poly-phase motors of 0.375 kW or more shall have a minimum acceptable nominal full
load motor efficiency not less than shown in table below or as per the IS 12615 2004 Eft 1
for energy efficient motors.
2. Motor nameplates shall list the nominal full-load motor efficiencies and the full-load power
factor.
3. Certificates shall be obtained and kept on record indicating the motor efficiency. Whenever
a motor is rewound, appropriate measures shall be taken so that the core characteristics of
the motor is not lost due to thermal and mechanical stress during removal of damaged parts.
After rewinding, a new efficiency test shall be performed and a similar record shall be
maintained.
143
Minimum acceptable nominal full load motor efficiency
(For all poly-phase motors of 0.375 kW or more)
Motor Power Efficiency
KW HP 2 Pole 4 Pole
1.1 1.5 82.2 83.8
1.5 2 84.1 85
2.2 3 85.6 86.4
3 4 86.7 87.4
4 5.5 87.6 88.3
5.5 7.5 88.5 89.2
7.5 10 89.5 90.1
11 15 90.6 91
15 20 91.3 91.8
18.5 25 91.8 92.2
22 30 92.2 92.6
30 40 92.9 93.2
37 50 93.3 93.6
45 60 93.7 93.9
55 75 94 94.2
75 100 94.6 94.7
90 120 95 95
110 150 95 95
132 180 95.3 95.5
160 215 95.5 95.8
180 240 95.5 95.8
200 270 95.8 95.8
All motors to have at least class 'F' insulation. The performance of the motors should conform
to Indian Standard IS-325- 1996. The starting torque of the motors shall be at least 2.5 times of
the rated torque. All motors above 60 HP shall be provided with bigger terminal box to
accommodate AI cables. Thermistor shall be provided in motor windings of 60 HP & above &
shall be of two ranges, one being for the warning and the other for tripping the motor if the fault
persists.
Remote Control Panels
These shall be floor/wall-mounted type as per site requirement. These shall be made of SS 304
housing. Front cover shall be removable type with suitable rubber gaskets to make them dust,
vermin and moisture proof. Degree of protection for housing shall be IP - 54/55.
Each feeder of station shall be provided with nameplate (white bakelite), LED type indication
lamp with pushbuttons i.e. one 'ON' (Green) push button and one 'OFF' (Red) push button with
144
latch to prevent accidental starting. Green and Red push buttons shall have contact elements
having 1 NO + 1 NC.
Heavy duty connector shall be used in RCP for internal wiring. Indication lamps shall be LED
type to give bright indication. Push Buttons shall be indicator type with LED lamps & shall be
of 22.5 mm dia and having operating voltage of 240 V AC. The panels shall have ammeter for
critical equipments to monitor motor load. Localised control panels to be provided, as per the
requirement, near the special machines such as Pellet mills, Hammer mills, Mixers and
Automatic bagging system etc. These can be floor/wall-mounted type and made from SS 304
sheet with suitable supporting arrangements. These can be as per the standard design of the
manufacturer of the related machine.
Push Button Stations / Isolators /Junction Boxes etc.
Push button stations and isolators are required for emergency operation of the equipment and
installed near it. All Push buttons shall be indicative type with LED. All DOL started motors
shall have power isolators near the motors and Star-Delta started motors shall have ON and stay
put on type red OFF Push button stations near the motors. Junction boxes are required on floors
near equipment for bringing multi-core control cables up to floor and distribution to individual
control switches such as limit switches, isolators, push buttons, solenoid valve etc. These push
button stations/isolators/junction boxes etc. shall be housed in aluminium cast housing and to
have IP-54/55 protection so that these are robust and no dust could enter into them.
Mimic Panel
This panel is used for operating the feed mill equipment on manual mode when PLC is not in
operation & not controlled by the remote control panels provided in the individual sections of
the plant, for operating various pneumatic flaps/slide gates and for housing indicator for auto-
batching plant. The complete installation to be shown by a painted multi- colour mimic
diagram. The mimic diagram shall be housed in a SS enclosure & shall have LED indicators for
status of motors, slide gate, level sensors etc. The general specification of this panel would be
similar to that of motor control centre specified elsewhere in the bidding document. All the
necessary operating, indicating and signal elements shall be located on the fixed front panel
with desk, in functional manner so as to facilitate comfort of operation.
Production Block Lighting
Lighting of entire production block (except wherever R.C.C. roof is provided by the purchaser)
is to be carried out by the bidder. Lighting work scope starts from the outlet feeder of the Main
lighting panel in the LT Panel room of the Substation block to the light fittings in the main
plant. The specification of the Lighting panel shall be similar to that of MCC, excepting that the
outgoing feeders shall be with suitable rating TPN MCB for the Distribution Boards in the
Main plant.
Lighting shall be carried out as per equipment and general lighting requirement. Light fittings
are to be wired via Distribution Board to a centralised lighting panel for the main plant in the
Electrical room which are to be supplied by the bidder. This centralized lighting panel shall be
cabled to respective Distribution Boards located on respective floors. Various switchgears such
as miniature circuit breakers & earth leakage circuit breakers etc. of the distribution Board shall
be integrated in this Lighting panel. Light fittings control may be for individual or group of
light fittings depending upon the locations by miniature circuit breakers. For wiring PVC
145
insulated armoured cable with copper stranded conductor, shall be used for sub-main wiring
upto Distribution Board in each floor. From each Distribution Board to individual fixtures shall
be through Copper point wiring (min 2.5sq.mm) in 25 mm MS conduit to be provided. All
Light fitting shall be Dust & Jet proof, (similar to IDJ 1124 EB of Crompton) with electronic
ballast. Fluorescent tubes of 36 W cool Day light shall be used for the fittings. Emergency
lights for indication of the emergency exits to be provided complete with centralised inverter in
control room. For production block roof, twin obstructers marking light for aviation purpose to
be provided.
On each floor of the production block, one distribution board shall be provided with at least one
25A universal single phase metallic plug and socket power point in cast Al. dust proof
enclosure. Copper lightning arrestor with connected GI earthing strip and earthing pits shall be
provided for lightening protection of the plant. Separate earthing system with pits to be
provided for industrial power system, computer systems, lighting system and lightening
arrester. Power for Air conditioner with voltage stabilizer, emergency lights for Control room
shall be drawn from nearest lighting distribution board. Distribution Boards shall be
prefabricated type with I6 /18 G MS sheet housing suitable quantity of MCBs, with suitable
nos. of knockouts for incoming cable & outgoing cables & conduits. The box shall be hinge
type with only the MCBs operating knob visible. These boards shall have 2 mm thick gland
plate.
Power Cables (LT)
Power cables for use on 415 V system shall be of 1100 volt grade, copper conductor (upto 50
Sq.mm) & aluminium conductor (above 50 Sq.mm), XLPE insulated, PVC sheathed, armoured
and overall PVC sheathed strictly as per IS : 7098 PART 1/1988. Unarmoured cable shall be
used only for specifically requirements as per directions of Engineer-in-charge. The size of
these cables shall be as per approved erection drawings. NO COPPER CABLE OF SIZE LESS
THAN 2.5 SQ. MM SHALL BE USED. The following selection table shall be followed for
cables of motors unless otherwise specified:
3 Phase 415 V Motor H.P. Direct-on-line Star-Delta Starter
Supply side Motor side Supply side Motor side
Copper Conductor Cable Size : Sq mm
Up to 7.5 2.5 2.5 2.5 2 X 2.5
10 4 4 4 2 X 2.5
15 6 6 6 2 X 2.5
20 10 10 10 2 X 4
25 16 16 16 2 X 6
30 16 16 16 2 X 6
40 25 25 25 2 X 10
50 35 35 35 2 X 16
Aluminium conductor Cable Size : Sq mm
60 70 70 70 2 X 35
75 95 95 95 2 X 50
100 120 120 120 2 X 70
146
125 185 185 185 2 X 95
150 240 240 240 2 X 120
180 - - 300 2 X 150
200 - - 2 X 150 2 X150
250 - - 2 X 185 2 X 185
275 - - 2 X 240 2 X 240
300 - - 2 X 240 2 X 240
Note: Cables indicated above in the table shall be only armoured copper conductor cable for
motors 50 HP. For motors rating 60 HP and above, armoured aluminium cable should
be used.
Control Cables
Control cables for use on 415/230 V systems shall be of 1100 V grade, copper conductor, PVC
insulated, PVC sheathed, armoured and overall PVC sheathed, strictly as per IS: 1554 (Part I) -
1988, read with latest revisions, if any. Unarmoured control cable to be used only if
specifically indicated in approved drawings or specially approved by site in-charge. The size of
these cables shall be as per approved erection drawings. NO CABLE OF SIZE LESS THAN
2.5 SQ. MM SHALL BE USED.
Screened Control Cable for Analogue Signals
These shall be used for carrying out analogue signals. Multi-standard base annealed copper
conductor, PVC insulated, cores colour coded, laid up screened by braiding with ATC copper
wire and finally over all PVC sheathed, complete as per British Standard Code 5308. Sizes of
these cables shall be specified in schedule of quantities/approved drawings. As a standard
practice, these cables shall be of conductor dia 1.0 sq. mm and number of cores as per
requirement. These cables shall be with armouring unless specified otherwise in schedule of
quantities/approved drawings.
Earthing System
Earth Pit
1. Plate type earth electrode with earth pit shall be provided for this work unless otherwise
advised by site engineer due to typical site conditions. Earthing electrode and pit shall be as
per IS: 3043-1987 the latest revision (code of practices for Earthing).
2. For ready reference, sketches for pipe and plate type earth electrode earthing pit have been
shown in the attached sketch no. SK-25. All earth electrodes shall preferably be driven to a
sufficient depth to reach permanent moist soil.
3. Earth pit centre shall be at a minimum distance of 3 M from nearest building, unless
otherwise advised. The minimum 3 M distance shall be maintained between centres of 2
earth pits.
4. Earth electrode for PLC, instrumentation earthing shall be of copper, whereas the same for
all other application (LT MCC /Electrical panels) shall be of GI.
5. Earthing electrodes for Main plant Lighting panel shall be plate type with double earthing.
147
Earth Bus, Earthing Lead & Earth Wire/Strip
1. All electrical equipment is to be doubly earthed by connecting two-earth strip/ wire
conductor from the frame of the equipment to an earthing pit/ main earthing ring. The
earthing ring will be connected via links to several earth electrodes. The cable armoured
will be earthed through the cable glands. Conductor size for connection to various
equipments shall be as specified in the drawing or as instructed by the Engineer-in-charge.
However, the length of the branch leads from equipment to earthing grid/ ring shall not be
more than 10 to 15 meters.
2. All hardware for earthing installation shall be hot dip galvanized. Spring washers shall be
used for all earthing connections of equipment having vibrations.
3. Size of earthing lead/ wire shall be as specified in schedule of quantities/drawings. Below
Table may be considered as general guidelines.
4. However, while deciding type & size of earth lead, the resistance between the earthing
system and the general mass of the earth shall be as per IS code of practice. The earth loop
impedance to any point in the electrical system shall not be in excess of 1.0 ? in Contract to
ensure satisfactory operation of protective devices.
5. G.I. wire/ Copper wire shall be connected to the equipment by providing crimping type
socket/ lug.
6. Wherever earthing strip to be provided in cable tray, it shall be suitably bolted on cable tray
and electrically bonded to the cable tray at regular interval.
7. Excavating & refilling of earth, necessary for laying underground earth bus loops shall be
the responsibility of the Supplier.
8. Wherever earth leads/ strips/ wire are laid in cable trenches, these shall be firmly and
suitably cleared to the walls/ supporting steel structure on which cable is clamped.
9. All LT Electrical panels shall be double earthed i.e. connected to earth pit independently
and earth pit shall have GI earth plate. Earth strips for panels shall be interconnected
wherever possible.
10. Long runs of GI strip shall be connected at each end with lap type welding to ensure
continuity.
Sizing of Earthing Lead Wire
S. No Item Size
1 Control Switches / glands Copper wire 14 SWG
2 Motor / Isolators upto 40 HP Copper wire upto the Cable tray & GI strip 25x3 mm
3 Motor above 40/50 HP upto 125 HP GI strip 40x3 mm
4 Motor above 125 HP GI strip 25x6 mm
5 Switch Board/Motor Control Center GI strip 50x6 mm
6 Earthing main in trenches GI strip 50x6 mm
Other Electrical Items
1. Control circuit junction boxes
2. Cable tray and GI conduits
3. LT Control wires and cables for instrumentation, and interlock along with sensors probes,
limit switches, HG switch etc
4. Cable glands, lugs, route markers
5. Earth pits with electrodes
148
6. Complete double earthing for all electrical equipment with suitable size earth conductors
7. LT power capacitors for PF correction
8. Rubber mats, fuse puller, hand gloves
The specifications for above items are available in the Special Condition of Contract –
Electrical Section
149
Technical Specification of Production Block Housing
Structural steel is required to house complete feed mill equipment in the production block
except for exclusion mentioned in the bidding document elsewhere.
All general purpose steel
Shall be conform for physical and chemical composition as per IS 2062 Grade A (of latest
version)
Nominal Dimension of rolled steel
Shall conform to IS 808 for Beams, columns, Channels, Angels
Shall conform to IS 1730 for plates, strips, flats
Shall confirm to IS 3954 for channel sections
Shall conform to IS 1239 for pipes
The Production Block structure shall be bolted/welded type consisting of suitable steel structure
having columns, „I‟ channels, angels, plates, foundation bolts etc. All platforms fabricated from
5 mm thick steel chequered plates, suitably supported to avoid deflection or vibration.
All necessary MS purlins and roof trusses shall be supplied & installed for the sheeting work.
Suitable steel staircase is also required. Necessary MS „B‟ class pipe NB 32 mm railing to be
provided whenever required. Complete steel structure to be painted with two coats of Red-
Oxide Zinc Chromate primer and then 2 coats of synthetic enamel paint. For production block
(main plant) required quantity per unit area of windows to allow natural light and ventilation to
equipments shall be provided with press steel frame, welded mesh for protection from birds and
4 mm minimum thick wired glass. The size, design of windows & colour shall be approved
before supply.
On sided and roof, ALVALUME (AL ZINC) pre-coated profiled rib sheets as per below
specification shall be fixed. Necessary pre-coated Galvalume sheet flashing pieces for
windows, corner pieces shall be fixed to avoid rainwater entry. Profile and colour shade of
sheets shall be approved before supply.
Technical Specification for GALVALUME Colour Coated Roofing / Cladding Sheets
S. No Description Specification
1 Base Metal High Tensile Cold rolled steel AS 1397
2 Al-Zn Alloy
Coating
55 % Aluminium & 43 % Zinc (approx) 1.5 % Silicon (approx);
Minimum 150 GSM coating mass ,total of both sides
3 Colour coating 20 microns on top with Silicon Modified Polyester paint & 5 - 7 Micron
back-up epoxy coating at Bottom
4 Total Coated
thickness
0.50 mm
5 Yield strength 550 Mpa
6 Approx mass per
unit area
4.24 kg /sq.m
7 Approx. Coverage 235 sq.m/ton
150
8 Fasteners
Imported galvanized carbon steel, self-drilling & self-tapping hexagonal
head screws of HILTI/ BOSCH)
Note: The make of fasteners should be HILTI /BOSCH with EPDM sealing washers.
Important Notes:
The steel housing shall house all the feed plant equipments required for the pellet production.
The foundation location, layout of plant, load details on the foundations shall have to be
provided to the purchaser to design the foundation. Foundation bolts for the structure shall be in
the scope of the bidder. The structure for the Main plant shall be of welded construction of steel
members.
The structure housing shall be designed for facilitating future expansion of the plant by
replacing with higher capacity pellet Mills or by adding an additional pelleting line.
The steel structural housing shall be designed using economical sections, so as to reduce the
overall steel requirement, keeping the minimum safety standards as indicated.
The Hammer Mill, Batch Mixer, Pellet Mills, gravity feeder, screw feeder for bin discharger
shall be located in the same platform level. The bidder shall place batch weighers, pellet
coolers, bagging bins such that they are placed in the same platform level. Hence bidder shall
restrict the number of access equipment platforms for equipments to the minimum.
The steel structure framework for housing feed plant equipments shall be designed and checked
by the reputed structural engineer by the bidder. The framework shall be designed for wind load
(highest as per historical records) and for seismic stability as per seismic zone. Stability
certificate for the structure shall be submitted by the successful bidder. Design calculations for
the structure shall be shared with the purchaser and who shall suggest the bidder, for alteration,
wherever found required.
The bidder shall quote for 250 (200 + 50) MT for the plant structure, steel platforms, trench
covers, Pipe Bridge in the bidding document. The bidder shall however economize requirement,
wherever possible without reducing stability of the structure.
The steel sheeting work for Main plant shall eliminate unwanted opening and shall be no
leakage into the plant during rains. All unwanted opening in the joint between inclined and
vertical sheets shall be suitably sealed/ closed. Holes on the sheets shall be made only by
drilling and only self tapping fasteners (as described above) shall be used.
To the extent possible cutting of cladding/Roofing sheets shall be avoided and proper selection
of sheet sizes is to be made. If opening are made in the sheets, they shall be properly sealed to
stop bird /dust entry.
Staircase shall be suitably located so that quick approach to working platforms and shall be
1.2m wide with 32 mm pipe hand railing (double braced).
Platforms, railing shall be extended to all working equipment to facilitate inspection, operation
and maintenance.
Windows for the plant shall be located at suitable height above each platform near equipments
for natural ventilation, lighting and for external views. The quantity of windows, design for the
plant shall be approved by the purchaser.
Elevation (all sides) drawings for the plant shall be furnished to the purchaser to decide on the
requirement of windows.
Proper sized sheet canopy or flashing for the windows shall be used to prevent water entry.
The sheet skirting at the lowest level shall be a part of the required of the sheeting.
151
Technical Specification for Erection, Testing and Commissioning
General technical specification for erection, testing and commissioning is included under special
condition of contract of bidding document. Erection, testing and commissioning is inclusive but not
limited to the following: Positioning of all the feed plant equipment in the approved locations,
including grouting, anchoring etc as per requirement.
Laying of product, aspiration and Service pipelines inclusive of the necessary valves, fittings
etc including the necessary accessories if any.
Anchoring of the pipelines on necessary supports - for all products, aspiration and Service
pipelines.
Insulation of Steam and molasses pipe lines.
Erection/Welding/Grouting into place necessary structural platforms, walkways, handrails etc.,
as per requirement.
Name of all important machines to be written on them after final installation but before
commissioning by a painter. Necessary aero marks and other identification by painting to be
provided on piping as required.
Laying of LT Power cables in conduit pipes, Cable trays, underground (including excavation
etc) as per specifications, including supporting of cable trays/conduits, isolators, junction boxes,
remote push button stations etc. are in scope of tenderar.
Termination of Power cables on MCC and on Motor starters, Capacitors, isolators etc. with
suitable cable glands, lugs etc.
Termination of control cables/sensor wires on RCPs, control panels, limit switches, indicators,
controllers etc
Earthpit installation complete including excavation, installation, refilling etc.
Earthing of all electrical equipment with two runs of earth electrode of appropriate size from
earthpits, Panel board trenches etc.
Approval of Electrical installation executed by the bidder by the Electrical Inspectorate of the
state where the plant is located.
Testing and commissioning procedure have been detailed separately as per the „Project
Management‟
Supply of Wear Parts and Spare Parts (TO BE CONFIRMED FOR SUPPLY)
Wear Parts for each site:
Following wear parts are to be supplied with the plant and their cost shall be considered in
technical and financial evaluation: Pellet Mill die 5 Nos
Pellet Mill roller Shell 5 sets
Hammers for hammer mill 5 sets
Sieve for hammer mill 5 sets
Beaters and knives for molasses mixer 5 sets
Filter bags for aspiration unit 1 set for each unit
Flexible canvass/rubber sleeves 1 set for complete plant
Spare Jute twine remover rotor 4 sets
152
Spare parts
For one year operation of plant, the Bidder shall furnish a list of all essential spare parts for items in
the scope with their item rates. Purchaser shall order spare parts separately as per the plant‟s
requirements.
List of preferred Makes of Bought out Items
Description Makes
Electronic Weighing Machine
Platform Type
METTLER TOLEDO / SARTORIUS / ESSAE TERRAOKE /
JAY INSTRUMENTS/ REIL / ATCO
Centrifugal fans ABB / FLAKT WOODS /AEROTECH / DUVENT/ ENGICON
/ RITZ / TLT / NADI / AIR CONTROL
Automatic Bag placing, Filling,
Weighing, stitching system
IIM /CRONOS RICHARDSON / BOSCH / AVATON/ EEL
/TECHNO-WEIGH/ AUTOWEIGH SERVICES/ SARTORIUS
Galvalume steel Pre-coated Profiled
sheets
METACOLOUR / ISPAT / INTERARCH/
POLYSTEEL(DENDRO) UNIMETAL /
Soft Starter (Electronic) L&T/ ABB /SIEMENS / ALLEN BRADLEY / DANFOSS
Programmable Protection Relay MINILEC
VFD ABB / L&T / SIEMENS / ALLEN BRADLEY / DANFOSS /
YASOKAWA
Level Transmitter & indicator E&H / ROSEMOUNT
Temperature / Pressure Transmitter E&H / ROSEMOUNT
RTD RADIX /PYROELETRIC / ALTOP / GIC / TOSHNIWAL
PID Controller YOKAGAVA / CHINO / FOXBORO / TATA
HONEYWELL/SIEMENS / ROSEMOUNT
Level Switch (float type for liquid &
vibrating fork type for powder)
E&H / ROSEMOUNT / P&F / HONEYWELL / TECHROL /
SB ELECTRONICS
Vortex / Magnetic Flow meter FORBES MARSHALL / E&H / ROSEMOUNT /
YOKAGAWA / MANAS MICROSYSTEMS
Process Control Valve FORBS MARSHALL /SAMSON / ROSEMOUNT
Valve SAMSON /DANFOSS / DEMBLA / AVCON / TOSHBRO /
FISHER XOMOX / MASONEILAN
Pressure switch / temp switch/
Pressure transmitter / temperature
transmitter / Thermostat
DANFOSS / ALCO / HANSEN / PARKER / E&H/ SWITZER /
CHINO / PYROTECH / ALTOP / GIC/ WIKA / AMERICAN
SPECIALITIES, USA
Pressure & Temperature Gauge FIEBIG / H GURU / PRICOL / WAREE / WIKA
Dual type Pressure / temp. gauges FIEBIG / H GURU / PRICOL / WARREE
Temperature sensors / digital
indicator/ controller / recorder
YOKOGAWA / CHINO / TATA HONEYWELL / RADIX /
PYROTECH
Energy Monitor L&T / SIEMENS / ABB / ALLEN BRADLEY
Voltage / Current / Energy /
Power/factor Transducer
RISHABH / ENERCON
PC (Personal Computer) IBM LENEVO/ DELL / ACER/ WIPRO/ COMPAQ/HP
PLC System SIEMENS / ALLEN BRADLEY / HONEYWELL/
SCHNEIDER / L&T QUANTUM / EMERSION
Printer HP/Canon
Automation System IIM / SIEMENS / ROCKWELL/ TATA HONEYWELL/
INVENSYS / EMERSION/ MELSS / TECHNOWEIGH
153
Electric Motors ABB / KIRLOSKAR / BHARAT BIJLEE / SIEMENS / NGEF /
CROMPTON GREAVES
Air Circuit Breaker L&T / SIEMENS / ABB / SCHNEIDER
MCCB, MPCB L&T / MDS-LEGRAND / SIEMENS / ABB / MERLIN GERIN
/ GE / CROMPTON GREAVES
Contactors L&T / SIEMENS / ABB / SCHNEIDER
Starter, Overload Relays L&T / SIEMENS / ABB / SCHNEIDER
Timers (Electronic) L&T / SIEMENS / BCH / GE
Fuse Switch Units L&T / SIEMENS / ABB / SCHNEIDER / C&S/ GE
MCBs L&T-HAGER /SIEMENS/ MDS-LEGRAND / GE
Push Buttons TEKNIC / ESBEE / SIEMENS / GE / VAISHNO /
Indicating Lamps L&T / SIEMENS / VAISHNO / TEKNIC / BINAY
Digital Ammeter & Voltmeter L&T /ANERCON / HPL SOCOMEC / MECO
Analog Ammeter & Voltmeter RISHABH / IMP / MECO / AE
Digital Energy Meter L&T / ENERCON / HPL SOCOMEC / CADEL / AE
Analog Energy Meter GEC / UNIVERSAL / HAVE / JAIPUR
Power Factor Meter RISHABH / IMP / MECO / AE
Current Transformer KAPPA / MECO / AE / IMP / INDCOIL
LT Power Cables FINOLEX / FORT GLOSTER / CCI / RPG ASIAN / INCAB /
UNIVERSAL / NICCO
LT Copper Control Cables FINOLEX / FORT GLOSTER /CCI / RPG ASIAN / RR
KABELS (UNILAY) / LAPP KABEL
Signal & Instrument cable POLYCAB / LAPP KABEL / THERMOPAD
Power Capacitors EPCOS / MOMAYA / MEHER / KHATAU JANKAR /
SIEMENS / UNISTAR
APFC Relay L&T / BELUKE / EPCOS / PHASITRON / MECO
Cable Tray INDIANA / MEK / SUNRISE / SUPER / PILCO
Isolating Switches L&T / SIEMENS / ABB / SCHNEIDER / C&S
HRC fuses L&T / SIEMENS / EE / C&S
IP 55 boxes for motor isolators, push
buttons, junction boxes etc.
HENSEL / HANSU
Terminal Blocks WAGO / LAPP INDIA / CONNECT WELL / ELMEX
Electronic Load Manager L&T / ENERCON / KRYKARD /
Selector Switch L&T / KAYCEE / SALZER /
Cable Glands COMET / EX-PROTECTA / DOWELS / LAPP KABEL /
BRACKO
Programmable Protection Relay MINILEC
Servo Voltage Stabilizer SUVIK / APLAB / NEEL / KRYKARD
UPS NUMERIC / EMERSION / APC / HI-REL / DB
ELECTRONICS / APLAB
SMF Battery EXIDE / AMCO / YUASA / FURUKAWA / PANASONIC /
MS Pipes TATA / JINDAL / KALYANI / MST / ISMT
LP Steam / condensate Valves AUDCO / CRESCENT / LEADER / THERMAX / BDK
Steam relief valve, traps & strainers SPIRAX / MAZDA / SAMSON / THERMAX
Expansion bend for steam line JN MARSHALL / MAZDA
Steam Pressure Reducing Valve SPIRAX / MAZDA
Air Compressor (Reciprocating) CHICAGO PNEUMATIC / INGERSOLL RAND / ELGI /
KIRLOSKAR / KHOSLA
154
Refrigerated Air Dryer CHICAGO PNEUMATIC / GEM EQUIPMENTS / SABROE /
HIRAS/ INGERSOLL RAND/ ATLAS COPCO
Air lines accessories SHAVO NORGEN / FESTO / AIRMATIC / LEGRIS / NUCON
NRV for Air Line FORBES MARSHALL/INTERVALVE / AUDCO / LEADER
Air Line valves (Ball) AUDCO/ LEADER/ CRESCENT/ HAWA
Auto Drain Valve ULTRA FILTER / ZANDER
Molasses Pumps JOHNSON / DELTA / ROTODEL / TUSHACO
Duplex filer for molasses line INTERVEST
Resin bonded mineral wool ROCKWOOL / LLOYD / UP TWIGA / MINWOOL /
Geared Motor / Gear Box PBEGL / POWER MASTER / RADICON/ SHANTHIGEARS /
IC BAUER / BON FIGOLI / EURO DRIVES
Structural Steel SAIL / ESSAR / TISCO / RINL / IISCO
Air Conditioner (Split) LG/ BLUE STAR/ CARRIER / VOLTAS / HITACHI /
GODREJ
155
Battery Limits
Electrical
The bidder‟s scope of works include all the works related to LT electrical distribution to all the
equipment mentioned under the scope of this bidding document, supply of LT main panel and
same to be design with consideration of extended plant capacity from the outgoing feeders of
the Power Control Centre / Main LT panel (in substation), upto all electrical loads, through
panels. Scope includes supply of Main plant MCC, Soft-starter panel ,MCC for Raw material
Intake Equipment., Silo System, Boiler MCC, Raw water pump panel, APFC panel and their
interconnecting cables on trays/pipes/trenches, earthing networks & earth-pits. Cables to weigh-
scales, portable conveyors from relevant MCCs are included in the scope. The scope includes
obtaining approval for electrical installation executed by the bidder from the Electrical
Inspectorate.
Steam
The bidder‟s scope of works includes all the equipment, piping, traps assemblies, air vents etc.
for distribution of LP steam from the outlet of PRS, through LP steam header to all
consumption points with condensate recovery system, necessary piping, valves etc. Obtaining
statutory approval, from the local Boiler Inspectorate for LP steam piping is in the bidder‟s
scope of works. Any modifications or changes, if suggested by local Boiler Inspectorate, shall
be in the scope of bidder.
Condensate
All condensate recovered from various sources shall be returned to the Feed water tank in the
Boiler House, through a pressurized recovery system. Bidder‟s scope shall start from
condensate outlet from the molasses pre-heaters (near Pellet mills & near Molasses storage
tanks) to Boiler feed water tank in the boiler house.
Compressed Air
Bidder is required to generate compressed air at required pressure, remove moisture, store and
distribute compressed air to all consumption points in the scope of supply for cleaning i.e. for
all pneumatic flaps / gates operation & air jet filters etc. Drain from the Air compressor, dryer,
receiver shall be taken outside the plant building.
Molasses
Molasses received in tankers shall be unloaded with unloading pumps & directed to any of the
two Molasses storage tank. The bidder's scope of work starts from the outlet of the Road Tanker
upto inlet of Molasses storage tanks and from outlet of Molasses storage Tank upto Molasses
mixers through feed pumps, flow meters, control valves are included in the bidder's scope.
Molasses line from the outlet of Molasses storage Tanks up the plant shall be insulated & traced
with LP steam line.
156
Silo System
In this silo system, flat bottom silos 4 Nos. Of minimum 500 MT (2 in use & 2 for future)
capacity each of GI corrugated (Imported) sheet (Min.zinc deposition 450 gm/sq.mtr) bolted
type flat bottom with hydraulically operated serew (imported) for discharging left out materials
from bottom of silo, complete with aeration system and temperature monitoring system for
storage of DORB RCC foundation for silo above ground by purchaser. Each silo to be provided
with automatic sampler. Discharge from each silo to common chain conveyor through
pneumatic slide. Additional emergency gate in the bottom of silos.
All other details of this system for storing DORB shall be similar to that for grains as
mentioned point given below.
This silo system shall be installed in separate location as shown in Production Block Layout
drawing.
Lighting & Earthing System
Electric power, 415 V, 3 phase & neutral shall be made available from Main Lighting panel
located near LT PANEL in the substation room. Cables form this Main Lighting panel,
distribution boards for the Main plant lighting shall be in the scope of the Bidder. Distribution
of lighting within the complete steel structure of production plant area including supply &
installation of light fittings, aviation light with wiring, lightening arrester, lightening conductor
and necessary earth pits & earthing electrodes are in the bidder's scope.
Feed Mill Housing Structure and Civil Works
The Purchaser shall provide production block foundation and all RCC works including
pedestals up to plinth. However, the bidder shall provide the locations of the foundations with
respect to the RMG & FPG to enable construction of the foundations.
All steel structure of feed mill above plinth including side and roof sheeting, windows etc. in
steel structure is in the bidder‟s scope. The bidder shall optimally design the steel structure &
shall get this cross checked which his structural designer before forwarding the drawing to
purchaser. The purchaser shall in-turn check the design from an approved structural consultant
before clearing the drawing. Any changes so recommended shall be incorporated in the steel
structure for the Main plant. Details of load on foundation for the structure shall be furnished to
the purchaser.
All building works of control room, MCC room, offices and links between production block
and godown will have RCC roof and connected civil work shall be provided by the Purchaser.
For feed mill structure, enclosure walls up to 2.5 M from plinth shall be provided by Purchaser.
Trench covers, angle nosing for trenches, platforms, staircase, railing, ladders, etc as required
for equipment approach & maintenance shall be in the scope of the bidder. All frames,
foundation bolts for steel structure and equipments, supports for steel
structure/equipment/piping/cables etc. to be provided by bidder and these shall be only grouted
by the Purchaser /Project Authority once these are fixed/aligned by the bidder.
157
Equipment
All equipment in Raw Material Godown, Finished Product Godown, Molasses
storage/handling, DORB Storage in Silo/handling & production block to be supplied & erected
by the Bidder. Scope of the bidder starts from the dumping hoppers of intake conveyor and
ends at the outlet of slat conveyor of finished feed. Bidder shall arrange the inlet to the third
cross conveyor (from silo system) above the Proportionate bins. Bypass protein & Mineral mix
plant equipments are not in scope.
Automation
Automation scope starts from the dumping of Raw materials in Raw material Godown & Silo
System till bagging conveyor.
Consumables
All raw materials for production of feed, operating staff for commercial production shall be
provided by purchaser/ project authority. All consumables like Gear oils, lubricants, packing for
flanged joints, flexible joints for vibrating equipments etc. and commissioning spares required
if any, for installation, testing & commissioning till taking over the plant by the purchaser, shall
be provided by bidder and the same after taking over the plant shall be provided by purchaser /
project authority.
Exclusions :
Description
1. All Civil works
2. Workshop Tools & Machines
3. Sanitary Installation, Water Disposal
4. Fire Extinguishers, Water Hydrants etc.,
5. Environmental Works, Access Roads,
6. Overhead tank for raw water,
7. Laboratory Glassware, Chemicals & Equipment,
8. Maintenance workshop and furniture for engineering Store,
9. Telephone & Intercom Systems,
10. HT Electricals, DG Set
11. Steam generation plant, HP steam piping, PRS,
12. By-pass protein plant,
13. Water Handling equipment, piping, water softener
14. Electronic weighbridge
158
SCHEDULE-III
TERMS & CONDITIONS
FOR
ERECTION/TESTING/
COMMISSIONING
OF
CATTLE FEED PLANT &
MACHINERY
RAJASTHAN COOPERATIVE DAIRY FEDERATION LIMITED SARAS SANKUL, JAWAHARWAL NEHRU MARG, JAIPUR Phone No.2702501-508/2710209 : Telefax: Fax : 2710209/2702537 Website : www.sarasmilkfed.coop : E-mail: [email protected]
159
SCHEDULE-III
GENERAL TERMS AND CONDITIONS FOR ERECTION CONTRACT
1.O Material drawings etc.
1.1 All goods or materials shall be erected/supplied under the scope of erection with the
specifications stated herein, and those covered under scope of work.
1.2 All goods or materials supplied or used shall be unused, new and of first quality. Where
foreign or partly foreign goods or material are to be used, this must be specifically stated
and brought to the notice of RCDF.
1.3 Wherever necessary or required by RCDF, the erector shall furnish the necessary test
and/or inspection certificate etc. from the appropriate authorities as per IBR, IER and
other statutory regulations at no extra cost.
1.4 All remarks, suggestions and modifications as suggested by the authorities mentioned in
1.3 above, shall be carried out by the erector to the entire satisfaction of the referred
authorities and no extra cost shall be payable in this regard to the erector by the RCDF.
1.5 The supplier shall furnish the necessary foundation drawings with all pertinent details for
each of the equipment under the purview of the supply alongwith the sets of drawings for
approval.
2.0 Assigning & Subletting :
Assigning or subletting the contract shall not be done by the party unless written
permission is obtained from RCDF. Written permission if given shall not relieve erector
from his obligations under the contract and he shall take full responsibility for all the
works carried out by the Sub-vendor.
3.0 Purchaser’s comments :
Erector shall not be relieved of his obligations under the order including but not limited to
his warranty obligations stated herein merely by incorporating the purchaser‟s design and
fabrication comments on the goods hereunder.
4.0 Secrecy Clause :
4.1 The technical information, drawings, specifications and other related documents forming
part of purchase order are the property of Purchaser and shall not be used for any other
purpose, except for the execution of the order. All rights, including rights in the event of
grant of a patent and registration of designs are reserved. The technical information,
drawings, specifications, records and other documents shall not be copied, transcribed,
traced or reproduced in any other form or otherwise, in whole or part and/or duplicated,
modified, divulged and/or disclosed to a third party nor misused in any other form
whatsoever without Owner‟s or his collaborators previous consent in writing, except to
the extent required for the execution of this order. This technical information, drawings,
160
specifications and other related documents shall be returned to owner with all approved
copies and duplicate, if any, immediately after they have been used for the agreed
purpose.
4.2 In the event of any breach of this provision, erector shall indemnify the owner from any
loss, cost or damage or any other claim whatsoever from his collaborator and or any other
parties claiming from or through them or from any other party in respect of such a breach.
5.0 Scope of Contract for Erection :
The erection would comprise of positioning and installing all CFP, miscellaneous and
service equipments under the purview of his supply and those mentioned herein as per the
approved machinery layout drawings. The scope of mechanical erection involves access
preparation for moving of the plant and equipment including their fittings, from the work
site godown(s) or from the place within the site where they have been unloaded, to the
place of erection, decorating, placing on foundation wherever specified or required;
erection of pipes and connections of necessary services to the main or ancillary branch of
the service lines, but all within the battery limits, specified starting up and successful
commissioning to get the specified rated output for each equipment. The installation
should be carried out as per the drawing(s) submitted by the erector and approved by
RCDF. Necessary Pipes fittings and valves etc. for interconnecting the equipment would
be installed by the erector and it would generally be done according to the piping layout to
be prepared by the erector and approved by RCDF. All the serviced pipes, fittings and
valves etc. shall be supplied and installed by the erector and this should be carried out as
per service piping drawings prepared by the erector and approved by RCDF.
All necessary foundation bolts and their grouting on floor, walls, etc. as per the
requirement, are included in the scope of erection & installation. All the supply covered in
this part shall be governed by the same general terms and conditions given in the tender
document against which the offer was made. Further the specifications of the contract are
intended to describe and provide for a finished piece of work. They are intended to be
complementary and what is equired by either shall be as if required by all. It is to be
understood and agreed by erector that the work described shall be complete in every
details even though every item necessarily involved is not particularly mentioned herein.
Erector shall be required to provide all Labour materials and equipments necessary for the
entire completion of the work describe and shall not avail himself of any manifesting or
unintentional error, omission or inconsistency that may exist. Erector shall carry out and
complete the work in every respect in accordance with the contract and accordance with
the directions and to the entire satisfaction of RCDF and the manufacture‟s
representatives.
6.0 Engineer’s Instructions :
RCDF may in his absolute discretion, from time to time issue further drawings and/or
written instructions, details directions and explanations which are collectively referred to
as „Engineer‟s instructions‟ in regard to :
161
6.1 Any additional drawings and explanations to exhibit or illustrate details.
6.2 The variation or modifications of the design, quality or quantity of work or the additional
or omissions or substitutions of any works.]
6.3 Any discrepancy in the drawings or between the schedule of quantities and/or
specifications.
6.4 The removal from the site of any material brought thereon by erector and the substitution
of any other material thereof.
6.5 The removal and/or re-execution of any work executed by the erector.
6.6 The dismissal from the work of any persons employed thereupon.
6.7 The opening up for inspection of any work covered up.
6.8 The amending and making good of any defects.
7.0 Right of RCDF :
7.1 The various parts of the contract are intended to be complementary to each other but
should any discrepancy appear or any misunderstandings arises as to the interpretations of
anything contained therein, the explanation of RCDF shall be final and binding.
7.2 Right to direct work :
7.2.1 RCDF shall have the right to direct the manner in which all work under this contract shall
be conducted in so far as it may be necessary to secure the safe and proper progress and
specified quality of the work, all work shall be done and all materials shall be furnished to
the satisfaction and approval of RCDF.
7.2.2 Whenever, in the opinion of the RCDF, erector has made marked departures from the
schedule of the completion laid down in the agreement or when untoward circumstances
force a such departure from the said schedule, RCDF in order to assure the compliance
with the schedule and the provisions of the agreement, shall direct the order, pace and
method of conducting the work, which shall be adhered to by the erector.
7.2.3 If, in the judgement of RCDF, it become necessary at any time to accelerate the over all
pace of the plant erection work erector when, ordered and directed by RCDF shall cease
work at any particular point and transfer his men to such other point or points and execute
such portion of his work, as may be required, to enable RCDF to hasten and properly
engage and carry on their work, all directed by the RCDF.
7.2.4 Night work will be permitted only with prior approval of RCDF, RCDF may also direct
erector to operate extra shifts over and above normal day shift to ensure completion of
162
contract as scheduled or due to exigent circumstances, if in his opinion, such work is
required.
7.3 Right to order Modifications of Methods & Equipment:
If at any time the erectors methods, materials or equipment appear to RCDF to be unsafe,
inefficient or inadequate for securing the safety of workmen or the public, the quality of
work or the rate of progress required, he may order erector to ensure their safety, and
increase their efficiency and adequacy and the erector shall promptly comply with such
orders. If at any time erectors working force and equipment are in the opinion of RCDF is
inadequate for securing the necessary progress as herein stipulated erector shall if so
directed increase the working force and equipment to such an extent as to give reasonable
assurance of compliance with the schedule of completion. The absence of such demands
from RCDF shall not relieve erector of his obligations to secure the quality, the safe
conducting of the work and the rate of progress required by the contract the erector alone
shall be and remain liable and responsible for the safety, efficiency and adequacy of his
methods, materials, working force and equipment, irrespective of whether or not he makes
any changes as a result or any order or orders received from RCDF.
8 Changes/ Variation in the work :
8.1 If it becomes necessary or desirable to modify the contract and the specifications therein
contained and the drawings, in a manner not materially affecting the substance thereof, or
to make changes by altering, adding to or deducting from the work, or to add correlated
work not now covered by the contract to the work to be done under his contract RCDF
may, without invalidating the contract, direct such changes increase the cost of work and
payment therefore is not covered by the prices bid for the various items, erector shall be
reimbursed for such changes under a supplementary contract. In case such changes shall
diminish the cost of the work, appropriate deductions towards such reduction in cost shall
be made from the contract price.
8.2 Erector when requested in writing by RCDF shall perform extra work and furnish extra
material not covered by the specifications but forming an inseparable part of the work
contracted for and shall be paid extra for all such work at rates and terms mutually agreed
upon.
8.3 Extra items, if any, shall be paid on the basis of vouchers of cost of materials and labour
procured by erector. Erector shall be paid 15% of the cost of material and labour towards
his profit, supervision and overhead charges.
8.4 Items not covered by the schedule of quantities but similar in nature to the items already
covered shall be paid for, the rates being worked out on the basis of rates quoted for
similar items.
8.5 The purchaser shall make any variation of the form, quality or quantity of the works or any
part there of that may. In his opinion, be necessary and for that purpose, or if for any other
163
reason it shall, in his opinion be desirable, he shall have power to order the supplier to do
and the supplier shall do any of the following:
a. Increase or decrease the quantity of any work included in the contract,
b. Omit any such work, c. Change the character or quality or kind of any such work, d. Change the levels, lines, position and dimension of any part of the works, and e. Execute additional work of any kind necessary for the works and no such variation
shall in any way vitiate or invalidate the contract, but the value, if any, of all such
variations shall be taken into account in ascertaining the amount of the contract price. 8.6 The supplier shall make no such variations without an order in writing of the purchaser.
8.7 Provided that no order in writing shall be required for increase or decrease in the
quantity of any work where such increase or decrease is not the result of an order given
under this clause, butis the result of an order given under this clause, but is the result of
the quantities exceeding or being less than those stated in the contract/bill of quantities.
Provided also that if for any such order verbally, the supplier shall comply with such
verbal order given by the purchaser, whether before or after the carrying out of the order,
shall be deemed to be an order in writing within the meaning of this clause. Provided
further that if the supplier shall within seven days confirm in writing to the purchaser
and in writing within 14 days, it shall be deemed to be an order in writing by the
purchaser.
8.8 All extra or additional work done or work omitted by order of the purchaser shall be
valued at the rates and prices set out in the contract if in the opinion of the purchaser, the
same shall be applicable. If the contract does not contain any rates or prices applicable to
the extra or additional work, then suitable rates or prices shall be agreed upon between
the purchaser and the supplier. In the event of disagreement the purchaser shall fix such
rates or prices as shall, in his opinion, be reasonable and proper.
8.9 Provided that if the nature or amount of any omission or addition relative to the nature or
amount of the whole of the works or to any part thereof shall be such that, in the opinion
of the contract for any item of the works, is by reason of such omission or addition,
rendered unreasonable or inapplicable, then a suitable rate or price shall be agreed upon
between the purchaser and the supplier. In the event of disagreement the purchaser shall
fix such other rate or price as shall, in his opinion, be reasonable and proper having
regard to the circumstances.
8.10 Provided also that no increase or decrease mentioned above or variation of rate or price
shall be made unless, as soon after the date of the order as is practicable and, in the case
of extra or additional work before the commencement of the work or as soon thereafter
as is practicable, notice shall have been given in writing:
a. By the supplier to the purchaser of his intension to claim extra payment or a varied
rate or price, or b. By the purchaser to the supplier of is intension to vary a rate or price.
164
8.11 If, on certified completion of the whole of the works, it shall be found that a reduction
or increase greater than 15 percent of the sum named in the letter of acceptance results
from the aggregate effect of all variation orders but not from any other cause, the
amount of the contract price shall be adjusted by such sum as may be greed between the
supplier and the purchaser or, failing agreement, fixed by the purchaser having regard
to all material and relevant factors, including the suppliers site and general overhead
costs of the contract.
8.12 The supplier shall send to the purchasers representative once in every month an account
giving particulars, as full and detailed as possible, of all claims for any additional
payment to which ordered by the supplier may consider himself entitled and of all extra
or additional work ordered by the purchaser which he has executed during the
preceding month.
8.13 No final or interim claim for payment for any such work or expense will be considered
which has not been included in such particulars. Provided always that the purchaser
shall be entitled to authorize payment to be made for any such work or expense,
notwithstanding the suppliers failure to comply with this condition, if the supplier has,
at the earliest practicable opportunity, notified the purchaser in writing that he intends
to make a claim for such work.
8.14 The work shall be carried out as approved by the purchaser or his authorized
representative/s from time to time, keeping in view the overall schedule of completion
of the project. The suppliers job schedule must not disturb or interfere with purchasers
or the other suppliers schedules of day-to-day work. The purchaser will provide all
reasonable assistance for carrying out the jobs.
8.15 Night work will be permitted only with prior approval of the purchaser. The purchaser
may also direct the supplier to operate extra shifts over and above per schedule.
Adequate lighting wherever required should be provided by the supplier at no extra
cost. The supplier should employ qualified electricians and wiremen for these facilities.
8.16 In-case of suppliers failure to provide these facilities. in case of suppliers failure to
provide these facilities and personnel, the purchaser has the right to arrange such
facilities and personnel and to change the cost thereof to the supplier.
8.17 In order to enable the purchaser to arrange for insurance of all items received at the site
including the items of supply covered under this contract, the supplier shall furnish
necessary details of all the equipment immediately on its receipt at site, to the
purchaser. Any default on the part of the supplier due to which any item does not get
covered under the insurance of the purchaser; the consequential losses shall be charged
to the supplier.
8.18 The purchaser shall not be liable for or in respect of any damages or compensation
payable at law in respect or in consequence of any accident or injury to any workman or
other person in the employment of the supplier or any sub-supplier, save and except an
165
accident or injury resulting from any act or default of the purchaser, his agents,
servants. The supplier shall indemnify and keep indemnified the purchaser against all
such damages and compensation, save and except as aforesaid and against all claims,
proceedings, costs, charges and expenses whatsoever in respect thereof or in relation
thereto.
8.19 The supplier shall ensure against such liability with as insurer during the whole of the
time that any persons are employed by him on the works shall, when required, produced
to the purchaser or purchasers representative such policy of insurance and the receipt
for payment of the current premium. Provided always that, in respect of any persons
employed by any sub-supplier, the suppliers obligations to ensure as aforesaid under
this sub-clause shall be satisfied if the sub-supplier shall have insured against the
liability in respect of such persons in such manner that the purchaser is indemnified
under the policy, but the supplier shall require such sub-supplier to produce to the
purchaser or purchasers representatives, when required such policy of insurance and the
receipt for the payment of the current premium
8.20 Whenever proper execution of the work under the contract depends on the jobs carried
out by some other supplier, the supplier should inspect all such erection and installation
jobs and report to the purchaser regarding any defects or discrepancies. The suppliers
failure to do so shall constitute as acceptance of the other suppliers installation/jobs as
fit and proper for reception of suppliers works except those defects which may develop
after execution. Supplier should also report any discrepancy between the executed work
and the drawings. The supplier shall extend all necessary help/cooperation to other
suppliers working at the site in the interest of the work.
8.21 Supplier shall carryout final adjustments of foundations, leveling and dressing of
foundation surfaces, bedding and grouting of anchor bolts, bedplates etc. required for
seating of equipment in proper position. The supplier shall be responsible for the
reference lines and proper alignment of the equipment. However, all civil works like
making cutouts in walls, floors and ceilings for pipelines shall be done by the
purchaser. Adjustment & leveling are to be carried out by the supplier at no extra cost.
The purchaser shall arrange the necessary refilling/repairs of these cutouts and pockets.
The supplier should arrange for laying the supports, cutouts, grouting of bolts, etc.
when the civil works are in progress, so as to avoid refilling/repair works. The
purchaser at suppliers costs shall make the damages occurring to civil and other works
good. For fixing of piping/equipment supports on wall/beams/roof floor etc. preferably
anchor bolts shall be used by the supplier. Drilling of holes for fixing anchor bolts is in
the scope of supplier without any extra cost.
8.22 The supplier shall keep a check on deliveries of the equipment covered in the scope of
erection work and shall advise the purchaser well in advance regarding possible hold-
up in suppliers work due to the likely delay in delivery of such equipment/components
to enable him to take remedial actions.
166
DUTIES OF THE SUPPLIER VIS-À-VIS THE PURCHASER.
The equipment and the items, if any, to be supplied by the purchaser for erection, testing
and commissioning shall be as listed in the contract.
Besides the utilities/services as specified in battery limits the following
assistance/facilities shall also be provided to the supplier by the purchaser for carrying
out the installation work.
Plant building ready for installation of equipment/items.
Necessary temporary water for carrying out the installation shall be supplied at only one
point within the project site by the purchaser free of charge. All necessary distribution
tapings from this point onwards shall be the suppliers responsibility.
Necessary temporary power is provided by the purchaser, the recovery @1% of total
installation charges will be recovered. However, the supplier shall supply all the items
such as energy meter, switchgear etc. required for getting temporary power.
The details of temporary water and power requirements shall be furnished seven days in
advance by the supplier to enable the purchaser to make timely arrangement.
If the supplier suffers delay and/or incurs costs from failure on the part of the purchaser
to give possession of the civil works in accordance with mutually agreed schedule, the
purchaser shall determine:
Any extension of time to which the supplier is entitled under the contract
The amount of such costs, which shall be added to the contract price, and shall notify the
supplier accordingly.
9 Erector’s functions :
9.1 Erector shall provide everything necessary for the proper execution of the works,
according to the patent and meaning of the drawings, schedule of quantities and
specifications taken together whether the same may or may not be particularly shown or
described therein provided that the same can reasonably be inferred there from and if the
erector finds any discrepancy therein, he shall immediately and in writing refer the same
to RCDF where decision shall be final and binding on all the parties.
9.2 It is not expected that the work under contract will be subcontracted. However, in case
erector desires to subcontract a part of the work in the interest of the project, he shall
request in writing to RCDF for approval for the same giving full and complete details
regarding the proposed subcontractor, his experience and the terms of subcontract.
Approval from RCDF for subcontracting part of the work shall not relieve the erector
from any of his obligations and responsibilities under this contract.
9.3 Erector shall proceed with the work to be performed under this contract and each and
every part and details thereof, in the best and most workman like manner by engaging
qualified, careful and efficient workers, and do the several parts thereof at such time and
in such order as RCDF may direct and finish such work in strict conformance with the
167
plans, drawing and/or specifications, and any changes, modifications thereof made by
RCDF.
9.4 The supplier shall provide everything necessary for proper execution of the works,
according to the drawings, schedule of quantities and specifications taken together
whether the same may or may not be particularly shown or described therein, provided
that the same can reasonably be inferred there from and if the supplier finds any
discrepancy therein, supplier shall immediately refer the same to the purchaser whose
decision shall be final and binding on the supplier.
9.5 The supplier shall proceed with the work to be performed under this contract in the best
and workman like manner by engaging qualified and efficient workers and finish the work
in strict conformance with the drawings and specifications and any changes/modifications
thereof made by the purchaser.
9.6 Any work is to be done at place other than the site of the works erector shall obtain the
written permission of RCDF for doing so.
10 Unloading, Inspection & Storing :
10.1 Erector shall promptly unload from the carriers all the materials/equipment covered under
this contract. It is the erectors sole responsibility to keep in touch with the RCDF and
others to inform himself on the expected date and time or arrival of carriers at site and
ensure that his men aids are available in time to unload the material/equipment and
promptly release the carriers. Any demurrage charges incurred due to the delay in
unloading the materials/equipment and releasing the carriers shall be changed to the
erector‟s account. Erector shall plan in advance his requirements of jacks, cranes, sleepers
etc. including those not specified here in but required to unload the material/equipment
promptly and efficiently.
10.2 Unless excluded in the specifications, erector shall safety transport the material/equipment
to the storage area and store the same in systematic manner with tags for easy
identification and retrieval. He shall also maintain all required stores records and furnish
all required reports. If in the opinion of RCDF the erector is not taking any action to
unload and transport the material to site. RCDF reserves the right to arrange for the same
through alternative agencies, entirely at the cost of the erector. It is further clarified that
even in the event RCDF arranges for the unloading, transportation storage space etc.
under the circumstances described above, the liability and responsibility will rest with the
erector.
10.3 All materials and equipment received at site, before erector arrives at site, shall be
unloaded and stored by RCDF at the risk responsibility and cost of the erector. These
materials shall be handed over to the erector and there upon the erector shall inspect the
same and furnish the receipt to the RCDF. The protection safety and security of the
material so taken over shall be the responsibility of the erector until it is handed over to
the RCDF after erection and/or commissioning. Any and all the material/equipment
168
covered under the scope of this contract, received at site after erector arrives at a site shall
be unpacked, inspected and checked and against invoices by the erector. He shall furnish
shortage and damages reports to RCDF within a week of the receipt of material and assist
the RCDF in lodging claims with the Insurance Companies. In case RCDF incurs a loss
due to the delay in lodging insurance claims, which are attributable to erector all such
losses shall be deducted from erector‟s bills. Erector shall repack materials/equipments as
required and store the same in an orderly manner.
10.4 Erector shall also inform RCDF in right time regarding the repairs/replacement required
towards the items damages/lost in order to enable the RCDF to arrange for
repairs/replacement well in time and avoid delays due to non availability of equipment
and part at the time of their actual need.
10.5 Erector shall arrange for periodical inspection of material equipment in his custody until
taken over by the RCDF and shall carry out all protective and preservative measures
thereupon.
10.6 Erector shall also keep a check on the deliveries of the equipment/material covered in his
scope of erection and shall advise RCDF well in advance regarding possible hod ups in
his work due to expected delays in delivery of equipment, to enable RCDF to expedite the
deliveries and take other remedial action.
11 Other Contractors/Erector’s Work :
If any part of Erector‟s work depends, for proper execution, upon the work of any other
erector, the erector shall inspect and promptly report to RCDF any defect in such work of
other contractors that render it unsuitable for use. Failure to do so shall be deemed as an
acceptance of the other erector‟s work as fit and proper for the erection of his work except
as to defects which may develop in the work of other contractors after the proper
execution of the work. To ensure proper execution of his subsequent work, erector shall
measure work already in place and shall at once report to RCDF and discrepancy between
the executed work and the drawings.
12 Supply of Tools, Tackles & Materials :
12.1 For full completion of the work, erector shall at his own expense furnish all necessary
erection tools, machine tools, power tools, tackles, hoists, cranes, derricks, cables, slings,
skids scaffolding work benches, tools for rigging, cribbing and blocking, welding
machines and all other associated protective equipment, instruments, appliances, materials
and supplies required for unloading, transporting, storing, erecting, testing and
commissioning all the equipment of the plant that may be required to accomplish the work
under the contract unless otherwise provided for. Adequacy of such tools will be subject
to final determination by RCDF.
12.2 Erector shall also furnish all necessary expandable device like anchors, grinding and
abrasive wheels, raw plugs hacksaw blades, tape, dyes, drills, reamers, chisels, files
carborundum stones, oil stones, wire brushes, necessary bamboo scaffolding, ladders
wooden planks timers, sleeper and consumable material like oxygen, acetylene, argon,
169
lubricating, oils, greases, cleaning fluids, welding rods cylinder oils, graphite powder and
flakes fasteners, gaskets temporary supports stainless steel shims of various thickness as
required, cotton waste, cheese cloth and all other miscellaneous supplies of every kind not
necessarily listed above but required for carrying out the work under contract.
12.3 Erector shall provide all reasonable facilities including tools personnel etc. and ensure
coordination with RCDF and erection supervisors of other equipment suppliers to enable
them to carry out all supervision measurements checks etc. in a satisfactory manner.
12.4 Erector shall not dispose off transport or withdraw any tools, tackles, equipments and
material provided by him for the execution of the work without taking prior written
approval from RCDF at all times shall have right to refuse permission for disposal,
transport or withdraw all of tools, tackles, equipment and material which in the opinion of
RCDF will adversely affect the efficient and expeditious completion of the project.
12.5 Machinery Foundation :
All the civil foundations as per the drawings furnished by the manufactures/suppliers shall
be arranged by RCDF. The erector shall place the equipment on the foundations and carry
out final adjustment of the foundations alignment dressing of foundation surface,
providing and grouting of anchor bolts pockets etc. and set the equipment properly as per
approved layout drawing and manufacture instructions.
12.6 Structural Platform :
Supply of all necessary materials and installation of structural platforms, structural
supports and access arrangement required for the various equipment is included within the
scope of mechanical installation and should be so carried out that all operation can be
easily manoeuvred.
The details and drawings in regard of the platforms shall be worked out/prepared by the
erector and submitted to the RCDF for approval. The items should be executed as per the
approval details drawing. The payment will be made on the basis of cost per unit weight
as offered by erector and accepted by RCDF.
13 For Erection & Commissioning :
The erector will be required to take a „storage-cum-erection‟ insurance for the items to be
erected and commissioned by him. For this insurance premium shall however be
reimbursed to him by the buyer. In case, the erector is not able to arrange insurance at
reasonable rates acceptable to the buyer, the buyer shall arrange the same on behalf of the
erector. However, in the event of any loss/damage to the equipment during storage or
erection and commissioning, the erector alone shall have to lodge the claims with
underwriters and pursue the same till settlement irrespective of the fact whether the
insurance policy is taken by the erector or arranged by the buyer on his behalf. Further, it
shall be sole responsibility of the erector to make good the losses/damages expeditiously
without any extra cost to the buyer.
170
14. All the equipment/machineries including motors, pumps, starters, junction boxes,
isolators, and boxes, tanks supporting structures, pipe supports and brackets of MS, GI,
Pipes which are not insulated and all exposed and visible cost Iron parts shall be given a
double coat of anticorrosive primers. MS and GI parts (within the building) should be
given a final coat of paint of approved shade. However, if so instructed by RCDF in
respect of certain particular items/equipments, the erect should touch up breaches in the
paintings. All surfaces must be properly cleaned and all scale, dirt and grease should be
removed prior to painting. Spray painting must preferably be used on all the equipment,
machineries and wherever else practicable. Suitable and necessary cleaning/wiping of
slight/dial glasses, other non-metallic parts, flooring, walls and other surfaces which have
been spoiled by paint during painting must also be carried out by the erector. Lettering
and other markings, including capacity and flow direction markings, shall also be carried
out by the tenderer on the tanks, pipe lines, starters, motors, isolators and wherever else
necessary as directed and as per the standard practice of installation. The scope of paining
includes a double steel primer under coat and a top coat of paint of approved shade and
quality, wherever possible ISI colour codes and colour charts must be adhered to.
However, the final colour code shall have to be got approved from RCDF and any
changes suggested thereby should be carried out.
15.0 Cleaning Chemicals & Lubricants :
The necessary quantities of cleaning chemicals, make-up lubricants, etc. required for the
installation, commissioning, testing and start-up all the equipments are to be supplied by
the erector free of cost.
16.0 Access preparation :
In case access preparation is required to be made for shifting the equipment the erector
shall bring to the notice of RCDF, the quantity of work involved for making such a
preparation. Consequently RCDF would review the matter in consultation with the erector
and decide the course of action.
17.0 Setting put works, lines & Grades :
17.1 Building, foundation and other civil works shall be provided by RCDF unless indicated
otherwise. Erector shall carry out all adjustments of foundations, levels, dressing of
foundation surfaces, bedding and grouting of anchor bolts and bed plate etc. as may be
required for seating of the equipment in proper position. Erector shall be responsible for
obtaining correct reference lines for purposes of fixing the alignment of various
equipments from master bench marks furnished by RCDF. Any minor alternation required
in rectifying the anchor bolts pockets, anchor bolts, etc. shall be carried out by erector at
no extra cost. The erector shall supply all the necessary foundation and anchor bolts, bed
plates etc. without any extra cost.
17.2 Erector shall supply, fix and maintain at his cost during the execution of any work, all the
necessary centring, scaffolding, staging, planking, timbering, strutting, shorting pumping,
171
fencing boarding guarding and lighting by night as well as by day, required not only for
the proper execution and protection of the said work, but also for the protection of the
pumping station and of the safety of any adjacent roads, streets, cellars, vaults ovens,
walls, houses, buildings and all other erections, matters or things. Erector shall take out
and remove any or all such centring, scaffolding, staging, planking timbering, strutting,
shorting etc. as occasion shall require or when ordered to do so and shall fully reinstalled
and make good all matters and things disturbed during execution of the work, to the
satisfaction of RCDF. Erector shall be paid no additional amount for the above.
18.0 Erection & Inspection :
18.1 Erector shall prepare a detailed and comprehensive erection schedule for review and
approval of RCDF‟s site Engineer and supplier‟s erection supervisors. This „Approved‟
erection schedule shall form the basis for evaluating the pace of all the erection works to
be performed by erector.
18.2 The schedule shall show approximately the date on which each part of divisions of the
work is expected to begin based on his knowledge of the works of the other contractors
and the date when the work is schedules to be finished. Upon the request of RCDF erector
should be prepared to discuss his schedule in relation to the master schedule and shall co-
ordinate his work with that of the other erectors/contractors as determined by RCDF.
18.3 The work so far as it is carried out on RCDF‟s promised shall be carried out at such time
as RCDF may approve consistent with the construction schedule and so as not to interfere
unnecessarily with the conduct of RCDF‟s business and RCDF will give erector all
reasonable assistance for carrying out the work.
18.4 Erector shall revise and up date his erection schedule periodically (atleast once every
calendar month) to indicate actual progress of works, in relation to scheduled progress.
Erector shall also submit monthly progress reports indicating progress work giving
scheduled and actual percentage completions, causes for delay etc. as well as such other
reasonable reports RCDF may request from time to time.
18.5 Adherence to the instructions of supervisory engineers of manufacturers, where provided
by RCDF is compulsory. Erector shall work as per the procedure suggested by
manufacturer and shall complete erection of equipment in such a way so as not to interfere
with or prevent equipment from functioning as intended, as well as to the entire
satisfaction of the manufacturer‟s supervisor/RCDF. Erector shall also permit and provide
all facilities for manufacturer‟s erection super visors to carry out all checks that they may
wish to and approve any erection procedure and/or final setting and alignment of
components, in order to satisfy themselves that erection has been carried out as intended
by them. This shall, however, in no way relieve erector of his responsibility for providing
adequate and competent supervision and quality workmanship. In case of any dispute, the
decision of the RCDF/Manufacturer‟s erection supervisor shall be final and binding on the
erector.
172
18.6 Erector shall haul materials and equipment furnished at RCDF‟s storage or unloading
areas to the points where they are to be used, in the construction work, install the
materials and equipment in their final location and classify and store all surplus and
auxiliary parts in a systematic manner in the warehouse, where they can be readily
identified and located when needed at a later date.
18.7 In the execution of the work no person other than erector or his duly appointed
representatives, his subcontractors and their workman shall be allowed to do work at the
site except by the special permission, in writing of RCDF or their representatives, but
access to everywhere in the site at all times shall be accorded to RCDF and their
representatives and other authorized officials and statutory public authorities.
Nevertheless, erector shall not object to the execution of the work by other
erector/contractor or tradesman whose names shall have been previously communicated in
every facility for the execution of their several functions simultaneously with his own.
18.8 Erector shall carry out the required „minor modification work‟ at site as required to
efficiently complete the work covered in this contract at no extra cost over his contracted
sum. However „minor modifications‟ shall not involve more than 24 man hours per each
item of such work. However, in case of „major modifications‟ which are required to be
done on the equipment, for no fault of erector he shall be compensated on the basis of
man day rates. It is the responsibility of the erector to get the prior approval for such
„major modifications work‟ from RCDF before such works are taken up. Erector shall
also get the estimates and the actual time sheets certified by RCDF and these certified
time sheets will be the basis for processing his bills for the „Major modifications‟.
18.9 If the work or any portion thereof shall be damaged in any way excepting by the acts of
RCDF, or if defects not readily detected on prior inspection and which shall develop
before the final completion and acceptance of the whole work, erector shall forthwith
make good, without compensation, such damage or defects in a manner satisfactory to
RCDF. In no case shall defective or imperfect work will be retained.
18.10 Erector at all times shall work in co-ordination with RCDF‟s engineering staff and after
them all reasonable facilities to become familiar with the erection, operation and
maintenance of the equipments.
18.11 In respect of observation of local rules, administrative orders, working staff and the like,
erector and his personnel shall co-operate with the RCDF.
18.12 Erector shall not sell, assign, mortgage, hypothecate or remove equipment or materials
which have been installed or which may be necessary for the completion of the contract
without the consent of RCDF in writing.
18.13 Inspection of work : RCDF of any person appointed by them shall have access and right to inspect the work, or
any part thereof at all times and places during the progress of the work. The inspection
and supervision is for the purpose of assuring RCDF that the plans and specifications are
173
being properly executed and while RCDF and their representatives will extend to the
erector all desired assistance in interpreting the plan and specifications, such assistance
shall not relieve erector of any responsibility for the work. Any work which proves faulty
shall be corrected by erector without delay. The fact that RCDF or their representatives
have not pointed out faulty work or work which is not in accordance with plans and
specifications shall not relieve the erector from correcting such work as directed by RCDF
without additional compensation. RCDF their representatives and the employees shall at
all reasonable times have free access to the works and/or to the workshop factories or
other places where materials are being prepared or constructed or fabricated for the
contract and also to any place where the materials are lying or from where they are being
obtained and erector shall give every facility to RCDF and his representative for
inspection examination and test of the materials and workmanship even to the extent of
discontinuing portion of the work temporarily or of uncovering or taking down portion of
finished work.
19.0 Protection to Plant :
19.1 Except in case where RCDF‟s express permission, is applied for and received in writing
no use of RCDF‟s plant facilities such as cranes, passenger elevator, toilets showers or
machine shop etc. shall be made by erector or his employees.
19.2 RCDF shall not be responsible or held liable for any damage to person or properly
consequent upon the use, misuse or failure of any construction tools and equipment used
by erector of any of his subcontractors, even though such constructions tools and
equipment may be furnished rented or loaned to erector or any of this contractors. The
acceptance and/or use of any such constructions tools and equipment by erector or his
subcontractor shall be constructed to mean that erector accepts all responsibility for and
agrees to indemnify and save harmless RCDF from any and all claims for said damages
resulting from said use, misuse or failure of such construction tools and equipments.
19.3 Erector and his subcontractors shall be responsible during work for protection of the work
which has been completed by other contractors/suppliers. Necessary care shall be taken to
see that no damage to the same is caused by his own men during the course of execution
of their work.
19.4 All other work completed or in progress as well as machinery and equipment that are
liable to be damaged by erector‟s work shall be protected by erector and such protection
shall remain and be maintained until its removal is directed by RCDF.
19.5 Erector shall effectively protect all the works from action of weather and from damages or
defacement and shall cover finished parts wherever required for their through protection.
Face work shall be perfectly clean and free from defects.
19.6 The work shall be carried out to completion without damage to any work and properly
adjacent to the area of his work to whom so ever it may belong, without interference with
the operation of their existing machines or equipment.
174
19.7 Adequate lighting at and near all the shortage, handling, fabrication, preassembly and
erection sites for properly carrying out the work and for safety and security shall be
provided by erector. Erector should adequately light the work area during night time also.
Erector should also engage adequate electricians/wireman, helpers etc. to carry out and
maintain these lighting facilities. RCDF may provide such facilities as he may deem
necessary and charge the cost thereof to the erector. In any case, erector shall be liable for
all damages and consequences arising out of his neglect in this regard.
20.0 Clean up of work site
20.1 All soils, filth or other matter of an offensive nature taken out of any trench, sewer,
drain, cesspool or other place shall not be deposited on the surface, but shall at once be
carted away by the erector from the site of work for suitable and proper disposal.
20.2 Erector shall not store or place the equipment, materials or erection tools on the drive
ways and streets and shall take care that his work in no way restricts or impedes traffic or
passage of men and material. During erection, erector shall, without any additional
payment, at all times, keep the working and storage area used by him free from
accumulation of dust or combustile material, waste materials or rubbish, to avoid fire
hazards and hindrance to other works, of RCDF.
20.3 If erector fails to comply with these requirements inspite of written instructions from
RCDF, RCDF will proceed to clear these areas and the expenses incurred by the RCDF in
this regard shall be payable by erector. Erector shall remove or dispose off in a
satisfactory manner all scaffoldings, temporary structures, waste and debris and leave the
premised in a conditions satisfactory to RCDF. Any packing materials received with the
equipment shall remain as the property of RCDF and may be used by erector on payment
of standard charges to RCDF and with prior approval of RCDF. At the completion of his
work and before final payment, erector shall remove and shall restore the site to a neat
workman like conditions, at his cost.
21.0 Erector’s Personnel :
Erector shall function as on erection organisation and furnish adequate courteous and
competent labour (unskilled, semiskilled and skilled, watchman, supervisors, and
engineers of all classes for the duration of the work to maintain the rate of erection in
accordance with the requirement of the schedule of completion, and shall be in the work
included in the contract at such times as will ensure its completion as specified and shall
complete the same force of all lines and charged, at or before the time specified for
completion. Erector shall make available qualified engineers for placing the equipment in
operation and carrying out the necessary tests and trials. Conducts required of erector‟s
men are specified below :
21.1 It is important that erector shall employ men known to be reliable and competent for the
work in general and it shall be requirement of the contract that men used on special
works shall be competent, well trained and trusted employees.
175
21.2 Erector shall furnish details of the qualifications and experience of his senior supervisors
and engineers assigned to the work including their experience in supervising erection and
commissioning of plant and equipment of comparable capacity.
21.3 Erector shall be personally present or employ at least one competent representative
(whose name shall have previously been communicated in writing to RCDF to supervise
the erection of the equipment and carrying out the work under the contract. This
representative shall have full technical capability and complete administrative and
financial powers to expeditiously and efficiently execute the work under the contract.
Erector or his representative or if more than one be employed, one of the representative
shall be present at the site at all times when work is in progress, and any written orders or
instructions which RCDF may give to the said representative of erector shall deemed to
have been given to the erector. He shall maintain an office near/or adjacent to the site of
the work, and shall at all times keep in office a complete set of specifications and
drawings. RCDF shall normally communicate directly with the said representative at site.
21.4 Erector‟s representative at the site shall be posted and be available at site within a
reasonable time after RCDF shall inform erector in writing to the effect. The service of
erector‟s representatives shall be made available during the progress of the work for such
periods during the working days as RCDF may require.
21.5 When erector or his representative is not present on any part of the work where it may be
desired to give directions in the event of emergencies, orders may be given by RCDF and
shall be received and obeyed by the supervisors or foreman who may have charge of the
particular part of the work in reference to which order given. If requested to do so, RCDF
shall confirm such orders in writing. Any such instruction, direction or notices given by
RCDF shall be held to have been given to the erector.
21.6 Erector shall furnish RCDF a fortnightly labour force report showing by classifications
the number of employees engaged in the work. Erector‟s employment records shall
include any reasonable information as may be required by RCDF. The erector should also
display necessary information as may be required by statutory regulations.
21.7 None of the erector‟s superintendents, supervisors, engineers, or labour may be withdrawn
from the work without the notice given to RCDF and further no such withdrawals shall be
made if in the opinion of RCDF, it will jeopardise the required pace of progress and/or the
successful completion of the work.
21.8 RCDF shall be at liberty to object to any representatives or person or skilled, semiskilled
or unskilled worker employed by the erector in the execution, or otherwise, of the worker
who shall misconduct himself, or be incompetent, or negligent or unsuitable and erector
shall remove the person so objected to upon receipt of notice in writing from RCDF
requiring him to do so and shall provide in his place a competent representative at his own
expense within reasonable time.
176
22.0 Construction, Electric Power & Water :
Electric power and water will be made available for use by RCDF free of cost. These
supplies will be made, where available at one central point in the site convenient to RCDF
and all piping for service water to work area shall be furnished, installed and maintained
by erector at his own expense. He shall also furnish, install and maintain at his cost the
power lines, junction boxes and any other electrical receptacles, apparatus or equipment
from the central point of his work area.
23.0 Drawings :
23.1 Within three weeks from the date of receipt of the order, erector shall submit list of
necessary drawings as mentioned in 1.5, that he proposes to submit for approval,
identifying each by a serial number and descriptive, title and giving the expected date of
submission. This list shall be revised and extended, as necessary during the progress of
work.
23.2 Erector shall also submit copies of design calculations, material specification and detailed
drawings as called for in the equipment specifications for RCDF review. Erector must
satisfy RCDF as to the validity of his design with reference to the requirement of statutory
Code Authorities.
23.3 Drawings submitted for approval shall be signed by responsible representatives of erector
and shall be to any one of the following sizes in accordance with
Indian Standards :
A0, A1, A2, A3, or A4
23.4 All drawings shall show the following particulars in the lower right hand corner in
addition to Vendor‟s name :-
a) Name of RCDF
b) Project Title
c) Title of Drawing
d) Scale
e) Date of drawing
f) Drawing number
g) Space for RCDF drawing number.
23.5 In addition to the information provided on drawings, each drawing shall carry a revision
number, date of revision and brief of revision carried out. Whenever any revision is
carried out, correspondingly revision must be up dated.
23.6 All dimensions on drawings shall be in metric units, unless otherwise, specified.
177
23.7 Drawings submitted by erector for approval will be checked reviewed by RCDF and
comments, if any, on the same will be conveyed to erector. It is the responsibility of the
rector to incorporate correctly all the comments conveyed by RCDF on erector‟s
drawings. The drawings which are approved with comments are to be resubmitted to
RCDF for purpose of records. Such drawings will not be checked/reviewed by RCDF to
verify whether all the comments have been incorporated by the erector. If erector is
unable to incorporate certain comments in his drawings, he shall clearly state in his
forwarding letter such non-compliance along with the valid reasons.
23.8 Upon completion of the installation, erector shall make in a neat and accurate manner, a
complete record of all changes and revision to the original design, as installed in the
complete work. Six copies of these drawings shall be submitted to RCDF for records and
these becomes the property of RCDF.
23.9 Drawings prepared by erector and approved by RCDF shall be considered as a part of the
specifications. However, the examination and approval of the drawings by RCDF shall
not relieve erector of his responsibility for engineering, design, workmanship and material
under the contract.
23.10 If, at any time before the completion of the work, changes are made necessitating revision
of approved drawings, erector shall make such revision and proceed in the same routine as
for the original approval.
24.0 Inspection Right & Privileges :
24.1 RCDF reserves the right to inspect any machinery or material or equipment furnished or
used by erector under the contract, and to project any, which is found defective in
workmanship or otherwise unsuitable for the use and purpose intended, or which is not
in accordance with the intent of the contract.
24.2 Should RCDF waive the right to inspect any equipment, such waiver shall not relieve
erector in anyway of his obligation under the contract.
24.3 RCDF representatives shall be permitted free access to erector‟s or his subcontractor‟s
shop at all working hours for the purpose of inspecting work at all stages of progress.
24.4 RCDF representatives shall be given full assistance in the form of necessary tools,
instruments, equipment and qualified operations to facilitate inspection.
24.5 RCDF reserves the right to call for certificate of origin and test certificates for all raw
material and equipment at any stage of manufacture.
24.6 In the event of RCDF inspection reveals poor quality of goods RCDF shall be at liberty to
specify additional inspection procedures, if required, to ascertain Vendor‟s compliance
with the equipment specifications.
178
24.7 Even though inspection is carried out by RCDF or his representatives, such inspection
shall not however, relieve Vendor of all responsibility for furnishing equipment
conforming to the requirements of the contract, nor prejudice any claim right or privilege
which RCDF may have because of the use of defective or unsatisfactory equipment.
24.8 A set of latest prints of the approved drawings shall be kept available by the controller, in
the shop floor for reference of RCDF representative during inspection.
25.0 Storage of equipment :
25.1 In general, erector is responsible for the proper storage and maintenance of all
materials/equipments entrusted to him. He shall take all required steps to carry out
frequent inspection of equipment/materials/stores as well as erected equipments until the
same is taken over by the RCDF. The following procedure shall apply for the same.
25.2 Erector‟s inspector shall check stored and installed equipments/materials to observe signs
of corrosion, damage to protective coating, to parts, open ends in pipes, vessels and
equipment, insulation resistance of electrical equipment etc. In case open ends are noticed,
he shall immediately get them capped. In case signs of wear damage to protective coating
are noticed, he shall immediately arrange a coat of protective painting. A clean record of
all observations made on equipments, defects noticed shall be promptly communicated to
RCDF and his advise taken regarding the repairs/rectification erector shall thereupon
carryout such repairs rectifications at his own cost. In case erector is not competent to
carry out such repairs/rectification, RCDF reserves the right to get this done by other
competent agencies at the erectors responsibility and risk and the entire cost for the same
shall be recovered from erectors bill.
25.3 Erector‟s inspectors shall also inspect and provide lubrication to the assembled pumps etc.
The shafts of such equipment shall be periodically rotated to prevent rusting in certain
zones as well as to check freeness of the same.
25.4 Inspectors shall check for any sign of ingress or moisture of rusting in any equipment.
25.5 If the commissioning of the equipment is delayed after installation of the equipment,
erector shall carry out all protective measures suggested by the Manufacturer RCDF
during such period.
25.6 Adequate security measures shall be taken by erector to prevent theft and loss of material
entrusted to him by RCDF shall carry out periodical inventory of the material received
stored and installed by him and any loss noticed shall be immediately reported to RCDF.
A proper record of these inventories shall be maintained by the erector.
25.7 A suitable grease recommended for protection of surface against rusting (refined from
petroleum oil with lanclin mincu, 70 C and water in traces) shall be applied over all
equipment every six months.
179
25.8 These equipments shall be stored inside a closed shed or in the open depending upon
whether they are of indoor or outdoors design. However, in case of equipment stored in
the open, suitable protective measures including covering with tarpaulin must be carried
out by the erector. The space heaters, where provided in the electrical equipment shall be
kept connected with power supply irrespective of their type of storage. Where space
heaters are not provided adequate heating with bulb is recommended. In LT. motors a low
voltage current flow through the windings is recommended. Frequent checks on insulation
resistance is essential for all electrical equipments. A records of the inspection reports and
megger readings shall be maintained equipment wise. Such records shall be presented to
RCDF whenever demanded.
25.9 All the necessary items/goods required for the protection as described above shall be
arranged by the erector and no extra cost is payable in this regard by RCDF.
26.0 Deployment of erection team to site and Co-ordination meetings :
The erector shall depute a qualified and experienced engineers together with a adequate
skilled and unskilled labourers for carrying out the installation and commissioning. All
necessary staff shall be at the site till the completion of all works, commissioning/start-up,
trial runs and handling over of the plant. No member of the staff deputed to site shall be
withdrawn unless agreed to by RCDF. The erector shall depute a senior personnel to
attend the site co-ordination meeting that would generally be held at the site every month.
The erector shall take necessary action to implement the decision arrived at such meetings
and shall also update the schedule. In case of lag in the progress the erector shall act
suitably to make up for the lag. RCDF shall be at liberty to object to any representative or
person or skilled, semiskilled or unskilled worker employed by the erector in the
execution or otherwise of the work, who shall misconduct himself or be incompetent, or
negligent or unsuitable and the erector shall remove the persons so objected to, upon
receipt of notice in writing from RCDF requiring him to do so and shall provide in his
place a competent representative at his own expense within reasonable time.
27.0 Programme of Installation & Commissioning :
The successful erector should submit a scheduled programme for carrying out the work.
The erection schedule should describe the estimated time of installation of each of each
item against each section of the project and should also clarify when each of the item to be
supplied by RCDF should be made available to the erector in order to adhere to the
schedule.
The schedule should be so prepared that the erection, commissioning, testing and start-up
is completed in all respect, within _________________________ from the date of
placement of order.
RCDF shall have the right to direct the manner in which all work covered under the scope
of this contract shall be conducted by the erector in so far as it may be necessary to secure
the safe and proper progress and the specified quality of the work and all work shall be
180
carried out and all material shall be furnished to the satisfaction and approval of RCDF
whenever, in the opinion of RCDF, the erector has made departures from the schedule of
completion of work submitted by him and approved by RCDF or when untoward
circumstances force a departure from the said schedule or if in the judgment of RCDF, if
becomes necessary at any time to accelerate pace of erection work, then RCDF shall
direct the order pace and method of conducting the work and erector shall fully comply
with all such directions.
If erector doesn‟t comply with the direction as described above or complete the erection
and commissioning by the end of 4th
week after programmed completion, RCDF will
operate the penalty clause and shall also have the option to deploy their own staff/other
agencies to complete the job at the erectors risk, responsibility and cost.
It is however, clarified that the above or any such directions from RCDF or abstinence of
RCDF in deploying their own staff/other agencies as described above shall not relieve the
erector of his obligations to secure the quality, the safe conduction of work, rate of
progress required and adherence to scheduled programme.
IF THE ERECTOR FAILES TO COMPLETE ERECTION IN ALL ASPECTS WITHIN
THE STIPULATED PERIOD & TIME. THE ERECTOR SHALL HAVE TO PAY
RUPES @ ½% PER WEEK AS PENALTY FOR THE PERIOD FOR WHICH THE
WORK REMAINS INCOMPLETE.
28.0 Approvals :
The erector shall obtain the necessary approval of the factory Inspector, Boiler Inspector,
Electrical Inspector weights & Measures Inspector, Explosives Inspector, and any other
state and local authorities as may be required. All the necessary details, drawings,
submission of application and proformas will be furnished by the Erector to RCDF for
rectification/signature.
The necessary application duly filled in, together with the prescribed fees shall be
submitted to the authorities by the erector on behalf of the RCDF. However all the actual
prescribed fees paid by the erector shall be reimbursed by RCDF upon production of the
receipt/vouchers of the above said authorities.
RCDF shall, however, extend all possible assistance to the erector for obtaining the
necessary approvals. Nevertheless the ultimate responsibility for obtaining the necessary
approvals lies with the erector.
29.0 Final Drawings & Manuals :
The erector shall, upon completion of the job, submit six complete sets of final drawings
towards the equipment layout different pipe lines, cables, conduits, layout drawings and
other necessary drawings. All the drawings must conform to actual executing carried out.
181
30.0 Progress of Work :
If the erector does not commence/complete the entire job or sections of the job within four
weeks from programme schedule of commencement/completion, the RCDF shall be free
to deploy their own staff/agencies to commence/complete the job entirely at the risk,
responsibility and cost of the erector.
30.1 Start-up of manufacturer‟s representatives during commissioning/trial runs.
30.2 In the following cases the RCDF reserves the right to invite the representative(s) of the
original manufacturer and/or supplier at the cost of the erector for start by help, assistance
and guidance during commissioning and start-up.
a) The erector has no previous experience of commissioning and starting-up of the
similar equipment.
b) The RCDF is of the opinion that the erector is incompetent to commission and start-up
of certain specific equipment.
31.0 Commissioning :
The erector shall operate, maintain and give satisfactory trial run of the plant satisfactory
for a period of continuous one month at the rated output. All rectifications of
damages/defects and routine troubles shooting should be carried out by the erector to
achieve aforesaid satisfactory running of the plant. The erector shall incorporate/execute
necessary minor modification during the trial period for maximising operational
efficiency. The erector should also execute miner modification as may be suggested by
RCDF. The erector shall suggest recommended log sheet proformas for recording
necessary operating data and pass it on to RCDF in proof of satisfactory rated output and
performance of the equipment/plant.
The commissioning shall also include the following for each equipment :
a) Field disassembly and assembly.
b) Cleaning of lubrication system including chemicals cleaning and passivation wherever
required.
c) Circulation of lubricant to check flow.
d) Cleaning and checking of all the service lines.
e) Checking and commissioning of instruments, equipment and plants, filtering of
transformer, and other oils so that if deteriorated, they shall attain the required
properties/standard, specified tests in this regard must be carried out by approved
authorities and their satisfactory reports submitted to RCDF before start-up.
f) Recharging or make-up filling of lubricant oil up to the desired level in the lubrication
system of individual machine.
g) Operation in empty condition to check general operation details wherever required,
and wherever possible.
h) Closed loop dynamic testing with water wherever required.
182
i) Operation under load and gradual load increase to attain maximum rated output.
j) Trouble shooting during the trial period.
k) Guarantee of installation.
32.0 Guarantee :
The supply of equipment as well as installation shall have to be carried out by the erector
to the entire satisfaction of the RCDF. The erector shall also guarantee to repair/replace,
without any extra cost, the items or parts thereof, if found defective due to bad design,
workmanship or substandard material within 12 months from the date of commissioning
or 36 months from the date of receipt of material at site whichever is earlier. If it is
necessary to send the defective equipment or parts thereof for repair/replacement, cost of
transportation including package, insurance etc. from the site to works and back to site
shall have to be borne by the erector. The guarantee does not cover any damage resulting
from normal wear and tear or improper attendance or mishandling of the equipment by the
RCDF.
33.0 Training of personnel :
Necessary staff as may be deputed by RCDF shall be trained by the erector for operating
the plant. The personnel will be associated for the training during the installation, testing,
commissioning and start-up period and training tenure shall be minimum for a period of
one month from the date of commissioning and start-up.
34.0 Outline of the scope of duties of the Contractor Viz-a-viz RCDF :
34.1 The equipment and items as specified in purchase order shall be supplied by RCDF for
erection, installation, commissioning by the erector.
34.2 Besides the utilities/services as specified in battery limits the following shall also be
provided to the erector by RCDF for carrying out the installation/erection.
a) Suitable lockable space for storage of tools, tackles and erection materials (No
accommodation for erectors personnel will be provided under any circumstances) the
security of these materials will be the responsibility of the erector.
b) Plant building ready for installation/erection of all the equipment/items (flooring will
generally be carried out after positioning of main equipment and laying of necessary
conduits).
c) Necessary temporary power for carrying out the installation (the power shall be
supplied at only one point within the dairy site). All necessary tapping from this point
onwards shall be erector‟s responsibility.
d) Temporary water at one point within the site for the water required for testing etc. The
erector shall arrange on his own to tap and transfer the water to the points required.
183
34.3 Prior Information :
a) The details of temporary water and power requirements shall be furnished one month
in advance by the erector to enable RCDF to make timely arrangement.
b) Detailed drawings of the required main cut-outs must be supplied by the erector in
advance to RCDF to provide the same at the time of civil construction. The cutting in
the walls, floors etc. which are not informed earlier and required for erection work
will be done by the erector and to repair the same will also be the responsibility of the
erector.
c) Detailed drawings and other specifications of foundation and any other special
structure must be submitted by the erector within one month after award of contract to
RCDF.
35.0 Damage :
If the work or any portion thereof shall be damaged in any way excepting by the acts of
RCDF or if defects not readily detected by prior inspection shall develop before the final
completion and acceptance of the whole work. Erector shall forthwith make good, without
compensation, such damage or defects in a manner satisfactory to the RCDF. In no case
shall defective or imperfect work be retained.
36.0 Observation of local rules etc.
In respect of observation of local rules, administrative orders, working hours, labour
compensation act, applicable labour laws and the like erector and his personnel shall
strictly abide by the same.
37.0 Stand by manufacturer’s representative :
In the following cases the RCDF reserves the right to invite the representative(s) of the
original manufacturer and/or supplier at the cost of erector for stand by them, assistance
and guidance during the commissioning and start-up.
a) The erector has no previous experience of commissioning and start-up of the similar
equipments.
b) The RCDF is of the opinion that the erector is not competent to commission and start-
up of certain specific equipment, the opinion of RCDF shall be final and binding.
38.0 Inspection & test reports :
The equipment and items supplied under the purview of erector shall be inspected by the
inspector at works and copies of inspection test reports shall be forwarded to RCDF.
184
39.0 Terms of payment for erection work :
1) 10% of the order value of acceptance of the order subject to the supplier furnishing
Bank Guarantee from a National Bank or Scheduled Bank in India for an equivalent
amount valid for a period of 12 calendar months.
2) 80% against monthly progress bills duly certified by RCDF‟s Site Engineer/In-charge.
3) 10% balance within 12 calendar months from the date of satisfactory commissioning
of the plant.
40.0 Battery Limits :
The services/utilities will be made available at battery limits specified in the job
description and it will be the erectors responsibility to transmit them to the various points
required in the project. All the necessary fittings tappings, that would be required to tap
the utility at battery limits for onward transmission shall be supplied and installed by the
erector.
41.0 GENERAL GUIDELINES FOR ELECTRICAL INSTALLATION :
41.1 a) The specifications detail the broad guide lines for erection, testing and commissioning
of electrical equipment. The work shall however, at all times be carried out strictly as
per the instructions of RCDF and in accordance with latest IER.
b) The installation would also comprise for the supply laying and inter connecting, cables
form the battery limits of the power supply to the various switchboards controls and
electrical equipments.
c) The cable of electric power should be of PVC armoured type approved from ISI
unless otherwise specified and with sufficient cross section depending on the feeder.
d) The cable for control and flexible connection should be unarmoured type with copper
conductors. Wherever required, multicore copper cable should be used.
e) Wherever necessary drip proof junction boxes and isolators, cable carrying trays,
necessary clamps etc. shall be provided.
f) Necessary isolators of appropriate sizes are to be provided near the motors as per IER.
All the involved supply included within the scope of electrical installation and
erection should be approved type and make and conform to ISI standard.
g) Detailed electrical diagrams and cable layout should be prepared by the erector
according to the specifications and the same should be approved by RCDF before the
execution.
185
41.2 Electrical installation work shall comply with all currently applicable statues, regulations
and safety codes in the locality where the equipment will be installed. Nothing in this
specifications shall be construed to relieve erector of his responsibility.
41.3 Unless otherwise specified installation work shall comply with the requirements of latest
additions of applicable Indian standards.
41.4 In accordance with the specific installation instructions, as shown on manufacturer‟s
drawings or as directed by Site Engineer of RCDF, the erector shall unload, erect, install
wire test and put into commercial use all the electrical equipment included in the contract.
Equipment shall be installed in neat workman like manner so that if is in level and plumb,
properly aligned and oriented. Tolerance shall be established in manufacturer‟s drawings
or as stipulated by an Engineer. No equipment shall be permanently bolted down to
foundation or structure until the alignment has been checked.
41.5 Erector shall furnish all supervision, labour, tools, equipment, ribbing, materials and
incidental materials such as holts, wedges, anchors, concrete, inserts etc. required to
completely install test and adjust the equipment.
41.6 Where assemblies are supplied is more than one section erector shall make all necessary
mechanical and electrical connections between sections including the connection between
buses. Erector shall also do necessary adjustment/alignments necessary for proper
operations of circuit breakers isolators, and their operating mechanism. All insulators and
bushings chipped, cracked or damaged due to negligence or carelessness of erector shall
be replaced by him at his own expense.
41.7 Switchgear and control panels/desks shall be installed in accordance with Indian Standard
Code of Practice IS:3072 and manufacturer‟s instructions. The switch gears panels shall
be installed on finished surfaces or concrete or steel sills. Erector shall be required to
install align any channel sills which from part of the foundations. In joining shipping
suctions of the switch gears/panels/control centres together, adjacent housing or panel
section or flanged throat sections provided shall be bolted together after alignment has
been completed. Power bus, enclosures, ground and control splices of conventional nature
shall be cleaned and bolted together, being drawn up with torque wrench of proper size or
by other approved means. Tapes or compounds shall be applied where called for as per
manufacturer‟s drawings. Base of outdoor type units shall be sealed in an approved
manner to prevent ingress of moisture.
41.8 All switch gear, control panels, desks etc. shall be made absolutely vermin proof.
41.9 Induction motors shall be installed and commissioned as per IS Code of Practice ISS 900
and manufacturer‟s instructions.
41.10 After installation of all power and control wiring, erector shall perform operating test on
all switch gear and panels to verify proper operation of switch gear/panels and correctness
of the interconnections between the various items or equipment. This shall be done by
186
applying normal AC or DC voltage to the circuit and operating the equipment. Megger
tests for insulations, polarity checks on the instruments transformers, operation tests shall
be carried out by erector, who shall also make all necessary adjustments as specified by
the manufacturer for the proper functioning of equipment.
41.11 Installation and testing of battery and battery charges shall be in strict compliance with the
manufacturer‟s instructions. Each cell shall be inspected for breakage and conditions of
the cover seals as soon as received at site. Each cell shall be filled with electrolyte in
accordance with the manufacturer‟s instructions. Battery shall be set up on racks as soon
as possible after receipt, utilizing lifting devices supplied by manufacturer. The cells shall
not be lifted by terminals. Contact surfaces of battery terminals and intercell connections
shall be cleaned, coated with protective grease and assembled. Each connection shall be
properly tightened. Each cell shall be tested with by hydrometer and thermometer and
result logged. Freshening charge, if required, shall be provided. When turned over to
RCDF the battery shall be fully charged and electrolyte shall be at full level and of
specified specific gravity.
42.0 Cable Installation :
42.1 Erector shall install, test and commission the suitable cables. Cables shall be laid
directly buried in earth on cable racks, in built up trenches, on cable trays and supports,
in conduits, and ducts or bare on walls, ceiling etc. as follows :
a) Outside the building premises :
The scope of installation of underground cables includes digging necessary trenches,
laying of the cables in the trench, covering them with sand and bricks and then
refilling the trenches. Necessary cable markers at appropriate points to indicate the
path of under ground cable should also be supplied and installed by the erector.
b) With in the building :
Under ground cables will be laid in GI light duty class pipes of not less than 37 mm.
dia.
c) Cables above ground :
Cables above the ground shall be fixed either on wall or in cable trays of slotted
angle with necessary clamps, bolts etc. as directed by RCDF.
d) The main cables inside the building should be laid in hume pipes wherever provided
by RCDF. At the places where hume pipes have not provided the main cables shall
be laid as per 40.1 (c).
42.2 Installation and testing of proper insulated cables shall be in accordance with Indian
Standard Code of Practice IS:1255.
187
42.3 Inspection on receipt unloading, storage and handling of cables shall be in accordance
with IS:1255 and other Indian Standards Code of Practice.
42.4 Sharp bending and kinking of cables shall be avoided. The bending radius for various
types of cables shall not be less than those specified below unless specifically approved
by the Site Engineer of RCDF.
Type of Cable Minimum bending radius
Voltage grade Single Multi Core
Core Unarmoured Armoured
Paper insulated upto 11 kv 25 D* 20 D 15 D
Paper insulated upto 22 kv 32 D 25 D 20 D
Paper insulated upto 33 kv 38 D 32 D 25 D
PVC insulated 650/1100 V 10 D 10 D 10 D
Rubber insulated 600 V - 8 D 15 D
Mineral insulated 300 V - - 8 D
* ( D – OVER ALL DIAMETER OF THE CABLE)
If shorter radius appears necessary, no bend shall be made until clearance and instructions
have been received from Engineer.
42.5 Where cables cross roads and water, oil, gas or sewage pipes, the cables shall be laid in
reinforced upon concrete or steel pipes to be supplied and laid by the erector. For road
crossing, the pipes for the cables shall be buried at not less than one meter depth. Cables
laid below railway tracks should be at a depth not less than 180 mm. unless otherwise
approved by the Engineer.
42.6 In each cables run some extra length shall be kept at a suitable point to enable one or two
straight through joints to be made should be the cable develop fault at a later date.
42.7 Control cable terminations shall be made in accordance with wiring diagrams, using
colour codes established by Engineer for the various control circuits, by code marked
wiring diagrams furnished to the erector for this purpose or other approved means of
identification. It is the intent that erector shall terminate the cables which he installs.
Additional work of testing and reconnecting and connected, but where on further testing
reversal or other rearrangement of load turns out to be necessary. Additional work of
testing and reconnecting shall be performed by erector at no extra cost of RCDF.
188
42.8 Special tools, clips and saddles, glands, seals, PVC sealing compound, locknut etc.
required for the connection and termination of insulated cables shall be supplied by
erector. During installation, connection and termination of insulated cables, care shall be
exercised to ensure that aluminium sheet is not damaged. Groups of mineral insulated
cables shall be bent neatly around the corners by using inner most cables as a form
around, which to bend the next cable. Cables shall not be fastened or clamped close to the
point of entry of the equipment which may vibrate severely. Special instructions furnished
by the manufacturer shall be strictly followed.
42.9 After installation and alignment of motors, erector shall complete the conduit installation,
including a section of flexible conduit between the motor terminal box and cable
trench/tray. Erector shall install and connect the power, control and heater supply cables.
Erector shall be responsible for correct phasing of the motor power connections and shall
interchange connections at the motor terminals box if necessary, after each motor is test
run.
42.10 Connections shall be made to small electrically operated device on equipment installed as
accessories to or assembled with other equipment and requiring two wire or three wire
connection. Connections to recording instruments, float switches, limit switches, pressure
switches, thermocouples, thermostats and other miscellaneous equipment shall be done as
per Manufacturer‟s drawing and instructions.
42.11 Metal sheets and armour of the cable shall be bonded to the earthing system.
42.12 All new cables shall be megger tested before jointing. After jointing is completed all LT.
cables shall be megger tested and HT. Cables (3.3 KV to 11 KV) pressure tested before
commissioning. The test voltage for pressure testing shall be as per Appendix-F of
IS:1255. 1100/650 Volt grade cable shall be tested by 1000 Volt Megger.
Cables cores shall be tested for :
a) Continuity
b) Absence of cross phasing
c) Insulation resistance to earth
d) Insulating resistance between conductors.
Erector shall furnish all testing kit and instruments required for field testing.
43.0 Cable Trays, Accessories and Tray Supports :
43.1 Cable trays shall either be run in concrete trenches or run overhead supported from
building steel, floor slab etc.
43.2 Cables shall be clamped to the cable trays in the horizontal runs and vertical runs.
189
43.3 All cable trays including perforated sheet trays and vertical raceways shall be hot dip
galvanized or primed with red lead and oil primer followed by a finish coat of grey
lacquer paint or aluminium paint as specified.
44.0 Conduits, Pipes & Ducts :
44.1 Erector shall supply and install G.I. light duty conduits, pipes and ducts. All
accessories/fittings required for making installation complete, including but not limited to
ordinary and inspection tees and elbows, check nuts, male and female reducers and
enlargers, wooden plugs, caps square headed male plugs, nipples, gland sealing fittings,
pull boxes, conduits, outlet boxes, splice boxes terminal boxes, glands gaskets and box
covers, saddles and all steel supporting work shall be supplied by Erector. Conduit fittings
shall be of same material as conduits.
44.2 Conduits or pipes shall run along walls, floors and ceilings, on steel supports, embedded
in soil, floor, wall or foundation, in accordance with relevant layout drawings, under
ground portions of conduit installation to be embedded in the foundation or structural
concrete shall be installed in close co-ordination with collateral work. Exposed conduit
shall be neatly run and evenly spaced, with conduits parallel when in racks or in banks.
Conduits embedded in foundation or structural concrete shall be run as directly as possible
among with generally indicated route between two points with a minimum length and
with a minimum of crossing bending and cutting but without creating interferences with
other installations.
44.3 When two lengths of conduits are joined together through a coupling, running threads
equal to twice the length of coupling shall be provided on any one length to facilitate easy
dismantling of the two conduits whenever required.
44.4 When one or more cables are drawing through a conduit, cross sectional area of the cables
shall be 40% of the internal cross sectional area of the conduit.
44.5 Conduits and accessories shall be adequately protected against mechanical damage as well
as corrosion.
45.0 Earthing :
45.1 The scope of supply and installation should also include absolutely independent double
earthing of individual electric motors, control gears and switchboards, complete with
necessary copper/GI wire, copper strip, earthing plate, top funnel, salt, cola etc. The
earthing process include digging of earthing pit, filling the same with alternative layers
of coal and salt, refilling the pit and providing perforated GI pipe making housing pit
and cover as per IER & ISI code of practice No. ISI:3034-1966.
45.2 Erector shall install bare/insulated aluminium/GI Cables and strips, etc. required for
system and individual equipment earthing. All work such as cutting, bending, supporting
soldering, coating drilling, brazing, clamping, bolting and connecting into structures,
190
pipes, equipment frames, terminals, rails or other devices shall be in Erector‟s scope of
work. Unless otherwise specified, the excavation and trenching shall be done by Erector.
Erector shall also backfill and reinstate the trenches after installation of earthing
conductors.
45.3 Earthing shall conform to the Indian Standard Code of practice IS:3043 and Indian
Electricity Rules, 1956. All materials and fittings used in the earthing installation shall
conform to the relevant Indian Standards or approved by RCDF‟s Engineer. Any change
in routing, size of conductors etc. shall be subject to the prior approval of RCDF
Engineers.
45.4 Metallic frame of all electrical equipment shall be earthed by two separate and district
connections with earthing system.
45.5 All underground connections for the earthing system shall be brazed/welded. Connections
to equipment and devices shall be normally of the bolted type.
45.6 On completion of the installation, continuity of all conductors and efficiency of all bends
and joints shall be tested. The earth resistance shall be tested in the presence of RCDF
Engineer‟s/representative. All equipment necessary for the test shall be furnished by
Erector.
45.7 EARTHING NETWORK
The entire ear thing installation shall be done in accordance with the ear thing drawings,
specifications and instructions of the Engineer-in-charge. The entire ear thing system
shall fully comply with the Indian electricity act and rules framed there under. The
supplier shall carry out any changes desired by the electrical inspector or the owner in
order to make the installation conform to the Indian electricity rules, at no extra cost.
The exact location of the earth pits, earth electrode and conductors and ear thing points
of the equipments shall be determined at site, in consultation with the engineer-in-
charge. Any change in the methods, routing, size of conductor etc. shall be subject to
approval of the owner/engineer-in-charge before execution.
45.8 Earth Pit with Electrode
1. Plate or pipe type earth electrode with earth pit shall be provided for this work
unless otherwise advised and pit shall be as per IS:3043 – 1966 (code of practices
for ear thing). All earth electrodes shall preferably be driven to a sufficient depth
to reach permanent.
2. Earth pit centre shall be at a minimum distance of 2m distance shall be maintained
between centres of 2 earth pits.
191
45.9 Earth Bus. Ear thing Lead & Earth wire /strip
All electrical equipment is to be doubly earthed by connecting two earth strips / wire
conductor from the frame of the equipment to a ear thing pit / main ear thing ring. The
ear thing ring will be connected via. Links to several earth electrodes. The cable armored
will be earthed through the cable glands. Conductor size for connection to various
equipment shall be as specified in the drawing or as instructed by the engineer-in charge.
However the length of the branch leads from equipment to ear thing grid/ring shall not
be more than 10 to 15 meters.
All hardware for ear thing installation shall be hot dip galvanized. Spring washers shall
be used for all ear thing connections of equipment having vibrations.
Size of earthing lead/wire shall be as specified in schedule of quantities/drawings.
Following may be considered as general guidelines:
Sr. No
Item Size
Control switches G.I. wire 14 SWG
Motor upto 10 HP G.I. wire 8 SWG
Motor above 10 HP upto 125 HP G.I. strip 25 x 3mm
Motor above 125 HP G.I. strip 25 x 6mm
Switch Board G.I. strip 25 x 6mm
Power control centre / LT panel of sub-station G.I. strip 40 x 6mm
When ear thing wire is to be drawn under floor / in underground, aluminium wire
10mm dia. With PVC insulation shall be used. Instead of GI wire, PVC insulated
copper conductor wires can also be used. However, while deciding type & size of earth lead the resistance between the ear thing
system and the general mass of the earth shall be as per IS code of practice. The earth
loop impedance to any point in the electrical system shall not be in excess of 1.0 ohm in
order to ensure satisfactory operation of protective devices. G.I. wire/aluminium wire shall be connected to the equipment by providing
crimping type socket/lug. Wherever ear thing strip to be provided in cable tray, it shall be suitably bolted on cable tray and electrically bonded to the cable tray at regular interval. Excavating & refilling of earth, necessary for laying underground earth bus loops shall be the responsibility of the supplier. Wherever earth leads/strips/wire are laid in cable trenches, these shall be firmly and suitably cleaned to the walls/supporting steel structure on which cable is clamped. The neutral of the transformer shall be connected to earth pit independently and earth
192
pit shall have copper earth plate. Long runs of GI strip shall be connected at each end with lap type welding to ensure continuity.
Bureau of Indian Standards to be Followed for Electrical Erection
1. PVC insulated cables (light duty) for working voltage upto 1100 volts 694-1990 Part I & II
2. PVC insulated cables (heavy duty) for voltage upto 1100 volts 1554-1988 Part I
3. PVC insulated cables (heavy duty) for voltage 3.3 KV to 11 KV 1554-1988 Part II
4. Specification for polyethylene insulated PVC sheathed heavy duty
electric cables for voltage not exceeding 1100 V
5959-1970 Part I
5. Specification for polyethylene insulated PVC sheathed heavy duty
electric cables for voltage 3.3 KV to 11 KV
5959-1970 Part II
6. Guide for marking of insulated conductors 5578-1970 or 5575
7. Code of practice for installation and maintenance of power cables upto
33 kV
1255-1983
8. Code of practice for earthing 3043-1987
9. Guide for safety procedures and practices in electrical work 5216-1982
10. Code of practice for installation and maintenance of AC induction motor
starters
5214-1969
11. Code of practice for installation and maintenance of induction motors 900-1992
12. Code of practice for installation and maintenance of switchgears 10118 - 1982
Part I, II, III, IV
13. Code of practice for installation and maintenance of transformers 10028 – 1981 Part I
14. Code of practice for electrical wiring installation, voltage not exceeding
650 V
732-1989
15. Code of practice for electrical wiring installation (system voltage
exceeding 650 V)
2274-1963
16. Guide for testing three-phase induction motor 4029-1967
17. Guide for safety Procedures & Practices in electrical works 5316
18. XLPE Cables for working voltage upto and including 1100 Volts 7098 – 1988 Part I
19. XLPE Cables for working voltage upto 33 kV 7098 – 1988 Part II
20. Boxes for enclosures of electrical accessories 5133
21. Electric Power connectors 5561
22. HRC Cartridge Fuse Link up to 650 V 2208
23. Code of Practice for Selection, Installation & Maintenance of Fuse up to
650 V
3108
24. Cables methods of testing 10810
25. Danger / Lattice Boards 3551
26. National Electric Code SP :30
193
Recommended Cable Size for Industrial Wiring
The following selection table shall be followed for cables of motors unless otherwise specified:
3 Phase 415 V
Motor H.P.
Direct-on-line Star-Delta Starter
Supply side Motor side Supply side Motor side
Copper conductor Cable Size : Sq mm
Up to 7.5 2.5 2.5 2.5 2 X 2.5
10 4 4 4 2 X 2.5
15 6 6 6 2 X 2.5
20 10 10 10 2 X 4
25 16 16 16 2 X 6
30 16 16 16 2 X 6
40 25 25 25 2 X 10
50 35 35 35 2 X 16
Aluminium conductor Cable Size: Sq mm
60 70 70 70 2 X 35
75 95 95 95 2 X 50
100 120 120 120 2 X 70
125 185 185 185 2 X 95
150 240 240 240 2 X 120
180 - - 300 2 X 150
200 - - 2 X 150 2 X150
250 - - 2 X 185 2 X 185
275 - - 2 X 240 2 X 240
300 - - 2 X 240 2 X 240
Note: Cables indicated above in the table shall be only armoured copper conductor cable for
DOL starter upto 50 HP motor. For motors rating 60 HP and above, armoured aluminium
cable should be used.
46.0 Supply, Fabrication, Erection and Testing of Piping :
46.1 Codes and standards :
All piping system including sub-contracted materials shall comply with the latest
editions of the following wherever applicable :
a) Indian Boiler Regulation
b) Regulation of Inspector of Explosives
c) All applicable Indian Standards
d) All applicable State Laws.
194
46.2 Scope of Supply :
Erector shall supply all piping materials like pipes, fittings, flanges and other items as
shown in his scope in the flow diagrams/specifications.
46.3 Scope of erection to be performed by Erector is outlined below :
a) The scope of erection for piping includes all system covered under his scope of work
in the flow diagram/specification.
b) Erector shall also install small accessory, piping an any specialities furnished with or
for equipment such as relief valves, built is bypass, and other items of this type.
c) Erector‟s work terminates at the final tube or pipe connection at pumps, including the
final connection.
d) Erector shall install primary elements for flow measurement, control valves, and on
line metering equipment.
e) Erector shall perform necessary internal machining of pipe for installing crevices,
flow nozzles, straightening vances, control valves.
f) Erector shall install all valves and specialities being procured from others.
g) Erector shall hydrostatically test all piping systems including valves and specialities &
instrument impulse line at suitable pressures.
h) All piping shall be internally cleaned and flushed by Erector before and after erection
in a manner suited to the service as directed by RCDF.
i) For hydrostatic testing and water flushing, erector shall furnish necessary pumps,
equipment and instruments, piping etc. Purchase will provide water at available points
of supply to which Erector‟s temporary piping will be connected.
46.4 Colour code shall be used to identify pipe material. Erector shall be able to identify on
request all random piping prior to any field fabrication.
46.5 All steam piping shall be fabricated in complete accordance with Indian Boiler Code and
all approval required shall be obtained by Erector from the inspecting authority.
46.6 Erector shall be responsible for the quality of welding done by his organisation and shall
conduct tests to determine the suitability of the welding procedure used by him.
46.7 Erector shall employ welded construction for all black steel piping. All black steel pipes
50 mm. and below shall have socket welded joints unless otherwise specified.
46.8 All piping supports, guides, anchors, rod hangers, spring hangers, rollers with incidental
structural sub framing shall be furnished and erected by Erector.
46.9 All piping shall be suspended, guided and anchored with due regard to general
requirements and to avoid interference with other pipes, hangers, electrical conduits and
their supports, structural members and equipment and to accommodate insulation to
conform to purchaser‟s loading limitation. It is the responsibility of the piping Erector to
avoid all interferences while locating hangers and supports.
195
46.10 Anchors and/or guides for pipe lines or for other purpose shall be furnished when
specified for holding the pipe line in position or alignment. Hangers shall be designed
fabricated and assembled in such a manner that they cannot become disengaged by any
movement of the support pipe.
46.11 All piping shall be wire brushed and purged with air blast to remove all dust, mill scale
from inner surface. The method of cleaning shall be such that no material is left on the
inner or outer surfaces which will affect the serviceability of the pipe.
46.12 Effective precaution such as capping and sealing shall be taken to protect all pipes ends
against ingress of dirt and damage during transit or storage. The outside of the carbon
steel pipe (black) shall receive two coats of red lead paint.
47.0 Testing for :
1. HP Steam 4. Soft and Raw Water
2. LP Steam 5. Air
3. Glycol 6. SS Piping
7. Insulation 8. Electricals
9. Motors 10. Equipments.
Should conform to the latest ISI standards.
48.0 Service piping Installation guide lines :
48.1 Chilled water & Glycol piping (if mentioned in purchase order)
The scope of erection and installation if mentioned, comprises a set of GI „B‟ class pipes
and fittings for chilled water and glycol including supports, isolation and non-return
valves etc. for providing chilled water or glycol to all the equipment which would
require chilled water or glycol. All the necessary headers for interconnecting all the
chilled water and glycol pumps and auxiliary materials like adapters, reducers, flanges,
union, valves/cocks/ (of gun-metal/brass for valves upto 100 mm. dia), strainers,
gaskets, packing etc. required for the pipe should also be supplied and installed by the
erector. The pipeline should be insulated as per the specification detailed.
48.2 Steam & Hot Water and molasses Piping (if mentioned in purchase order)
The scope of supply and installation of mentioned, comprises the following set of steam
pipes and fittings for providing steam connections from the indicated battery point to all
the equipments requiring steam in accordance with IBR, MS Class „C‟ pipes, fittings and
auxiliary items. The scope of supply and installation includes the necessary pipes
supports, isolation supports, isolation valves, nonreturn valves, safety valves, check
valves, pressure reducing valves steam traps, strainers, expanders, bends, gaskets,
packing, sight glasses, pressure gauges etc. The manufacturer‟s certificates that the
material conforms to IBR duly attested by concerned authority should be furnished for all
196
items as per requirements. The necessary check valves(s) and other fittings required at the
sources of tapping at the battery point should also be supplied and installed by the erector.
Set of condensate pipes and fittings of MS Class „C‟ to interconnect the condensate return
line. The supply is inclusive of necessary pipe supports isolation valves, check valves,
bends, gaskets, packing etc.
48.3 Soft well water piping (if mentioned in purchase order)
The scope of installation comprises (if mentioned) a set of well water pipes and fittings
including supports, isolation and non-return valves etc. Pipes of GI Class „B‟ for
providing well water to sterlizer would be required. All the necessary headers for inter-
connecting the water pumps and auxiliary material like adopters reducers, flanges, union
valves/checks (of gun metal/brass for valve upto 100 mm dia), bends, strainers, gaskets,
packing etc. required for the pipe should also be supplied and installed by the erector.
48.4 Water distribution (if mentioned in purchase order)
The scope of supply and installation if mentioned comprises of the following:
Set of water pipes and fittings of GI Class „B‟ for providing water connection to the
various equipment/items and points requiring water (raw and soft water) from battery
limits. The scope is also inclusive of the necessary pipes and fittings, GI Class „B‟ for the
soft water from the softening plant to soft water overhead tank if specifically mentioned
and further to all the equipments requiring soft water and interconnections with suitable
valves etc. from all the compartments of the overhead tank. The supply and installation is
inclusive of necessary pipe supports, isolated valves, strainers, bends gaskets, packing,
polythene/copper tubes and all other necessary auxiliary items.
48.5 Air requirement (if mentioned in purchase order)
The scope of supply and installation if mentioned comprise of the following:
Set of air pipes and fittings in accordance with MS „C‟ Class for providing air to the
various equipments/items and controls and points requiring the same. The scope of supply
and installation is inclusive of necessary pipe supports, valves, filters, bends, gaskets,
packing, polythene, copper tubes and all other necessary auxiliary items.
48.6 All the above referred piping should generally be of welded execution and must be
removed of mill scales and properly cleaned before installation.
49.0 Important Note :
49.1 All the necessary materials, of a quality and make approved by RCDF required for
carrying out the installation mentioned in 46.2 shall be supplied by the Erector.
197
49.2 Piping (SS) (if mentioned in Purchase Order)
The scope includes the installation and inter connection of a set of SS Pipes and fittings,
including cocks, valves, Tees, flanges, unions, bends, reducers, liners and other necessary
fittings SMS/IDF standards, for inter connecting all the equipment listed. Necessary pipe
supports shall be also installed by the Erector.
49.3 Pipe fittings at connection points
All the required fittings that would be needed in the piping at all the tapping, termination,
connection and intermediate points must be installed by the Erector.
49.4 The erector shall prepare and submit the piping layout drawing, details of supports, details
of tapping, termination interconnection etc. for approval. All the piping work shall be
carried out strictly in accordance with the approved drawings/details. The respective milk
flow diagram to which the piping layout correspondence must also be furnished by the
erector.
50.0 Insulation (if mentioned in Purchase Order)
50.2 Insulation of Steam condensate & Hot water pipe lines :
All the steam and hot water pipes shall be insulated with 50 mm. thick mineral wool or
equivalent. The insulation shall be carried out in the following manner:
1) Cleaning of surface to be insulated. Applying a coat of red oxide primer and fixing
glass wool/mineral wool of suitable thickness tightly to the pipe, butting all joints to
be tied with lacking wire.
2) The insulation should be covered with GI wire netting.
3) The steam and hot water lines, after insulation must be covered with 22 gauge
aluminium sheet with proper grooves and overlaps and secured in position with 12
mm. self tapping Parker screws.
4) In case the insulation does not have the desired insulation properties, the entire
insulation will have to be redone at the erector‟s cost to give the desired results.
5) In case of condensate return piping, all the steps mentioned above shall be executed
except that the thickness of insulation shall be 30 mm.
All the necessary materials of quality and make approved by RCDF required for
carrying out the insulation mentioned in 50.2 shall be supplied by the erector.
198
SCHEDULE - IV
SITE LAYOUT
EQUIPMENT LAYOUT
FLOW DIAGRAM
199
200
201
202
203
Following amendments/clarifications/elaborations have been finalised during
the pre-bid meeting held on 09-08-2012 regarding the tender for both
cattle feed plants at lambia Kalan and Pali. The tender is for design, supply,
installation and testing of two cattle feed plants of 150 TPD and expandable
to 300 TPD on turnkey basis. The amendments and clarifications finalised
today will have a superseding effect on all the corresponding technical
specifications given in the tender document.
This has reference to the tender notice No. RCDF/DPM& PROJ/ (P-2901)/2012-
13 Dated 16th july, 2012. In reference to the tender following points have been
clarified as under:
1. The earnest money amount of 36.00 Lakhs mentioned in tender to be
deposited in the form of DD payable at Jaipur only.
2. The earnest money is mentioned for both the projects. This is a single
tender for installation of two plants at different locations
3. There is a mention of security deposit of 5% of the bid value to be
submitted in the event of a bidder being awarded the order on successful bidding.
This will also be in form of a DD payable at Jaipur.
4. The bids are being called from bonafide manufacturers of cattle feed plants,
machineries and spare parts. As such, there is no provision for subletting the
tender.
5. The bids are called for two separate locations but it remains a single tender
for two plants. As such, the bids will be evaluated on the basis of lowest bidder in
the combined bid for both projects. The total of both projects will be evaluated for
finalisation. The tender will be awarded to a single party capable of doing both
the projects in the same awarded time frame as per details mentioned in the
tender.
6. It will not be allowed to bid for single project.
7. The meaning of the fixed price contract is that there will be no provision
for price escalation. Any increase in the quoted unit prices will not be allowed.
8. Already there is a provision of Force Majeure clause for delay. Further
clarification in regards to impact of force majeure clause in delay of project, shall
be conveyed after due consideration at appropriate time.
9. Please refer page number 19 and point number 5.1. The date of 09-02-2012
will be considered as 17th Aug, 2012 which is the last date of opening of the
tender.
10. The JV, if any, should also meet the qualification criteria in the same name
and style. Similarly, the turnover criteria must also be met to fulfil condition
mentioned in tender in the same name and style. As regards to the orders on
204
hand, only those orders on hand will be considered which are almost near
completion. Only such projects will be considered which are near trials at the time
of submission of tender. All such order should be of at least 150 TPD capacities
on pelleted feed or above.
11. At the time of handing over of the plant both individual capacities of each
machine and over all capacity of the plant will be considered. The bidder does not
have any liberty to down size capacity of any equipment. However, he may up
size for the betterment of the plant. In nut shell, all machines should perform at
their respective capacities as mentioned and the project should give 150 TPD or
above in all the situations. The bidder should plan sufficient factors of safety in
designing of the plant at every stage to cover all aspects and requirements of
production of cattle feed with all possible die sizes and all possible formulation
combinations.
12. It has been clearly mentioned on the tender that pelleting capacity is
needed at 10 TPH which should be easily realised on all formulations using any
die size from 4mm to 10mm. That means, bidder should plan for 10 TPH on
4mm. It is understood that capacity on 8 -10 mm will be higher.
13. There will be bagging equipment set required on both the bins of finished
product. As such, one will be working and other will be standby. The bidder is
required to offer for two sets.
14. All pumps and pipelines should be as per capacities required for 300 TPD.
Similar approach is required at all places where expansion in capacity is planned
for 300 TPD.
15. The provision and supplying of fire stairs and lifts for passenger and
material shall be considered in the scope of bidder as per statutory norms.
16. The bidder should give a break up of prices on all individual supplies
along with erection and commissioning charges. The bidder is required to mention
the same individually (Item Wise) in the price bid. Bidder should supply a
separate annexure along with his bid mentioning prices of all items to be supplied
and erection & commissioning charges of every individual item in front of its
price. Kindly see the enclosed format as under for this purpose: S
L
DESCRIPTION CAPACITY
/SIZE
CU=CUBIC
MTR)
QTY Unit of
measurement Unit
cost of
Supply
AMOUNT of
Supply in
Rs.
E&C
Per
unit
Total
Value
of E&C
in(Rs)
Total
Value of
Supply
and
E&C
In(Rs)
17. The duration of all price validities of all machineries and spares shall be
considered from the date of awarding of the tender. It will be binding on all
bidders as per the terms and conditions mentioned in the tender documents.
205
18. The layout of Pali will be mostly on the basis of what has been finalised in
Lambia kalan. However, there may be changes as per site conditions and
requirements arising for betterment of the same. As such, the bidder is required to
consider all these aspects while making the bid for Pali.
19. The tender date will not be extended and the schedule for the submission of
bids remain as mentioned on tender document.