RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A...

download RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative Review

of 10

Transcript of RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A...

  • 7/31/2019 RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative

    1/10

    Talk given at the Researching Agile development of

    Information Systems (RAISE2012) conference

    11th October 2012

    held at the Inmarsat Centre, London

    Agile Project Management for GovernmentAgile Project Management for GovernmentAgile Project Management for GovernmentAgile Project Management for Government::::

    Agile adoption in the US and UKAgile adoption in the US and UKAgile adoption in the US and UKAgile adoption in the US and UKGovernments:Governments:Governments:Governments: aaaa briefbriefbriefbrief comparative reviewcomparative reviewcomparative reviewcomparative review

    Brian WernhamBrian WernhamBrian WernhamBrian Wernham

    Brian Wernham 2012 CC BY-NC-ND

  • 7/31/2019 RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative

    2/10

    2

    Introduction

    Good morning to you all!

    After many decades of run-away technology

    projects, where delivery has failed and

    benefits have not been achieved, both the US

    and the UK governments have said that they

    want to move to a more flexible approach to

    IT.

    Ten years on from the signing of the Agile

    Manifesto,1 we are seeing more than just an

    interest in Agile from leaders in Government,

    we have had clear statements of intent.

    Agile is no longer the ugly duckling spurned

    by the mainstream. Governments on both

    sides of the Atlantic wish to use it - and use it

    on large, critical projects.

    One of the objectives of this conference is to

    kick-off the "Agile Research Network" (ARN)

    which will initiate research projects under a

    jointly agreed research agenda.2

    What I will suggest today is a stream of work

    for the ARN to consider - a medium term

    goal, over the next 3-5 years, to assess how

    the switch to Agile in government is

    progressing, and whether it is delivering to

    the citizen and reducing the cost of project

    failures. This research will be helpful in

    identifying where the roll-out of Agile is

    faltering and why. We need to understand

    what barriers there are to the use of Agile ingovernment, and how to overcome those

    barriers.

    There have only been incomplete attempts to

    survey the progress of the adoption of Agile in

    government. A torrent of reports have been

    issued in the last two years, and their

    conclusions have been tentative and in each

    case they have noted that more research is

    needed. The general consensus is thatalthough targets for a move to Agile are

    broadly set, more robust measurement,

    monitoring and analysis is needed.

    So - here is the structure of this paper - both

    for the US and then for the UK we will

    explore:

    Firstly - some background: what is

    driving the need for new approaches?

    Secondly - What do these new IT

    strategies promise?

    Thirdly - What actions are underway?

    And Fourthly - I will assess the current

    status of Agile adoption - both for the US

    and the UK governments.

    The US Experience

    BackgroundBackgroundBackgroundBackground

    The US government has had its fair share of

    IT technology disasters. For example, the

    failure of a huge project that tried to

    integrate the personnel systems for the USArmy, Air force and Navy. In 2010, the project

    was cancelled, after 10 years and 850 million

    dollars thrown away.

    One of the problems is that so many

    regulations have built up over the years.

    These try to improve technical development

    in diverse government bodies, but often they

    have just ended up stifling effectiveness.

    A good example of how regulation has not

    improved project management is the series of

    regulations created over the years by the US

    Department of Defense. For example, to try

    and improve project management the DoD

    published the infamous 2167 standard. This

    was widely interpreted as mandating a

    waterfall approach. The department then

    tried to stress that modular development and

    incremental delivery was the preferredapproach - they issued the 2167A standard.

  • 7/31/2019 RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative

    3/10

    3

    But waterfall projects continued unabated.

    Efforts were made to sweep up all the

    regulations under one all-encompassing

    umbrella standard, DOD498.3

    IT disasters continued to plague the

    department, so-Congress got involved. The

    Clinger-Cohen Act of 1996 begat the 5000

    series of regulations. These tried to reinforce

    the need for evolutionary development.

    Unfortunately an inflexible approach to

    project management continued.

    The story is broadly similar in technology

    projects across all US public bodies. Each

    major project failure results in more

    regulations - more audit - and more

    centralised standards. These create a mirage

    of apparent control over projects by

    increasing the amount of detail in the

    management apparatus surrounding the

    development teams.

    The 25The 25The 25The 25----Point PlanPoint PlanPoint PlanPoint Plan

    In 2008, when Barack Obama put togetherhis team to prepare for his transition into

    office, he appointed a 34 year-old geek as his

    technology advisor. Vivek Kundra proposed a

    very different approach to running

    technology projects. Previously, there was

    little central oversight of IT - there was an

    "AdministratorforE-Government", but the

    position was little more than a placeholder.

    Kundra convinced the president elect that apowerful executive role was needed - and that

    he was the man for the job.

    When Obama took office in 2009, Kundra was

    appointed as Chief Information Officer with

    the power to review and cancel any project in

    the Federal government.

    Kundra inherited a legacy of 27 billion dollars

    of failing IT projects.

    Vivek Kundra - the first Federal CIO

    In the previous decade, IT spending had

    nearly doubled, growing at an annual rate of

    7 per cent. So Kundra immediately capped

    the IT Budget - saving over 25 billion dollars

    a year.

    He forced change to the running of

    technology projects by holding deep-dive

    project reviews. These reviews, Kundra called

    Technical Status, or TechStat reviews.

    Each TechStat review entailed a long,

    detailed, face-to-face meeting to inspect each

    yellow or red status project. These reviews

    were intended to delve deep into each project

    with a relentless pursuit of oversight to

    reshape projects, or to halt and terminate

    them.

    To kick off the initiative, Kundra attended

    more than three of these meetings a week,

    publically issuing memos to agencies where

    problems were found. At the Environmental

    Protection Agency, for example, one IT

    project was found to be one year late and 30

    million dollars over budget, so Kundra gave

    them a month to put a recovery strategy in

  • 7/31/2019 RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative

    4/10

    4

    place for the project. He was rolling up his

    shirt-sleeves and meeting each agency CIO in

    long and detailed meetings. If a project could

    not come up with a realistic improvement

    plan, it would be cancelled.

    Kundra reviewed 38 projects. He saved three

    billion dollars by cancelling four and

    drastically reducing the scope of 11 other. In

    12 cases he found ways to cut the time for

    delivery by more than half, from two to three

    years down to an average of 8 months by

    adopting a more agile approach.

    In 2010 he published a "25 Point Plan"

    intended to shock the system.4 It shook up

    the counterproductive processes that had led

    to so many project failures. Major initiatives

    were kicked off to put in place technologies to

    complement agile approaches. For example:

    Upgrading project management skills

    to include agile training

    Breaking down barriers to agile by

    requiring integrated project teams

    Making sure that procurement

    professionals took agile approaches

    Influencing Congress to change

    legislative frameworks such as the

    Clinger-Cohen Act that were anti-

    patterns to agile development.

    The current status in the USThe current status in the USThe current status in the USThe current status in the US

    So, what is the current status in the US?

    Yesterday at the Agile Business Conference I

    talked about the failure of the FBI Virtual

    Case File project, and how the subsequent

    Sentinel project initially faltered. It started

    with a massive Project Management Office

    (PMO). This goliath superstructure tried to

    control the supplier - over 100 million dollars

    was spent on management 1/4 of the whole

    budget - completely wasted until an Agile

    approach was adopted and the PMO was

    disbanded.

    The introduction of Agile at the FBI was

    initiated by Chad Fulgham, who came in

    from the private sector, reorganised the

    Sentinel project to use Agile and led the

    project to success. Fulgham left earlier this

    year to return to the private sector. And, last

    year, Vivek Kundra left his post as Federal

    CIO for a research position at Harvard.

    Whether the US government can maintain

    the momentum behind incremental,

    accelerated delivery and implement Agile

    remains to be seen.

    The Government Accountability Office (GAO),

    is the US equivalent to the UK National Audit

    Office (NAO). The GAO released a report in

    July charting progress in the adoption of

    Agile in the US government. They found

    pockets of excellence at various agencies:5

    The Department of Defense had a 190

    million dollar project developing a

    Combat Support System using Scrum

    A new 150 million dollar project to

    improve the management of the

    registration of Patents at the

    Department of Commerce was also

    using Scrum

    A 44 million dollar Agile project to

    create a system to manage tax

    payments on Branded Prescription

    Drugs

    However, despite the GAO's enthusiasm for

    Agile, the CIO Council, now without Vivek

    Kundra, has yet to supply any leadership with

    regard to the take-up of Agile specifically. The

    Council has released guidance on modular

    procurement and modular development but

    has not specifically addressed Agile practices.

    Vivek Kundra is a tough act to follow. We

    will have to wait to see whether the new

    Federal CIO, Steven Van Roekel, can keep up

    the pressure for reform.

  • 7/31/2019 RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative

    5/10

    5

    The UK Experience

    BackgroundBackgroundBackgroundBackground

    We are all familiar, I think, of waking up the

    news that yet another IT technology project

    has ended in disaster.

    Surely the most egregious example of project

    failure in the last few years was the

    Firecontrol project.

    The main contract to supply the Firecontrol

    system started late and took two years longerthan expected to sign. The relationships in

    the project between the IT supplier, EADS,

    and the government were painful to say the

    least. The Government and EADS failed to

    provide timely information to each other.

    A lack of interim milestones undermined the

    Departments ability to hold EADS to account

    for delivery and conversely the delays to

    delivery led to cash flow difficulties for EADS

    which created further strains in an alreadytense relationship.

    Both sides were locked into the deadly

    embrace of a non-agile contract. The

    Government took legal advice and found out

    that it was unable to terminate its contract

    with EADS without incurring substantial

    compensation payments provided for under

    the contract. And EADS in turn was unable to

    deliver against a final key milestone for mid-2011. In the end, the contract was terminated

    and the government received a settlement of

    22.5m from EADS little cheer considering

    that 469m was eventually written off.6

    Whereas the US government tried to regulate

    and legislate tighter control in an attempt to

    make Waterfall project management work,

    the UK tried 'softer' techniques based on

    best-practice guidance issued by the Office forGovernment Commerce such as PRINCE2,

    MSP (Managing Successful Programmes and

    the use of 'Gateway' peer-reviews. In the

    time available I will just focus on the latter:

    'Gateway peer-reviews.

    These short, sharp reviews produced reports

    at each Waterfall gate between stages of

    projects. These reviews pre-supposed a

    Waterfall approach with clear 'Gates' between

    each cataract of the Waterfall.

    This approach depended on a review of

    detailed BDUF documentation, with an

    assessment of likely success based on

    paperwork and interviews with project staff.

    No expectation existed of an iterative

    approach. There was no encouragement for

    the delivery of increments of working

    software or for real life deliveries of that

    software to users.

    These Gateway reports mirrored the

    assumption that Waterfall project

    management was necessary for large projects.

    They were confidential between the reviewing

    team and the project sponsor. Because of

    their secrecy they could not be even

    requested under the UK Freedom of

    Information (FOI) legislation.7.

    The original objective of this secrecy was to

    encourage robust criticism that might have

    been stifled if embarrassing facts were made

    public. However, the contents of each report

    were often widely distributed within the

    government, so the conclusions were often

    not clear and were usually overoptimistic.

    One report stated that the reports were

    ineffective because of this lack of robustness,

    and that they were considered unimportant

    by Senior Responsible Owners.8

    The findings of these Gateway reviews were

    invariably optimistic, and often had not

    impact on the likelihood of success.

  • 7/31/2019 RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative

    6/10

    6

    The new IT StrategyThe new IT StrategyThe new IT StrategyThe new IT Strategy

    The UK Institute for Government (IfG) has

    been pressing for a change of approach for

    several years. The IfG issued a report last

    March called, System Error - the sub-titlewas "Fixing the flaws in government IT". It

    recommended two major changes:9

    First, the need for a new IT Strategy to

    drive down costs and increase flexibility.

    Second, the rollout of agile project

    management throughout government.

    In the same month, influenced by both theIfG's lobbying and also the US 25-point Plan,

    Francis Maude published a new UK IT

    Strategy.10

    Francis Maude specifically declared a drive for

    the adoption of Agile project management.

    Five out of the 14 points in the UK IT

    Strategy specifically relate to the adoption of

    agile approaches.11

    The plan was for 19 separate strands of

    technological change, one of which was the

    adoption of an agile approach. For example,

    the use of flexible framework contracts. These

    would be used rather than large fixed price

    contracts that had so often ended up as

    anything but fixed in price and length.

    One influential paper from Emergn, put the

    suppliers point of view as a response to theUK Government IT Strategy - it stressed the

    need for agility could only be supported by

    more involvement of Small/Medium sized

    Enterprises (SMEs). Large project

    procurements often fail, the paper argues,

    because of inflexible use of standard forms

    and contracts which slow the agility of both

    suppliers and customers. Experts in the

    buying and negotiation of large contracts are

    too distant from the technology experts thepaper argues, and experts are so intimate

    with the detailed in contract specifications

    that they overlook the importance of

    flexibility.12

    Francis Maude - Minister for the Cabinet

    Office

    One important strand in the new

    Government IT Strategy to support the move

    to Agile, was to be major drive to end the use

    of massive contracts that were seen to favor

    the existence of an oligopoly of large

    suppliers.

    Most saliently, the IT Strategy set what

    seemed like a concrete target for half of all

    large IT developments in Government to be

    using Agile within two years - by April 2013 -

    next year.13

    The CThe CThe CThe Current Status in the UKurrent Status in the UKurrent Status in the UKurrent Status in the UK

    Later in 2011, the NAO investigated the

    activities that had been spawned in the first

    six months of the IT Strategy. Their report

    was optimistic, but found that there were no

    clear measurable targets in the strategy and

    no system to measure its impact. They

    warned that because there was no overall

    plan to support the strategy, progress could

    be hindered through lack of resources.14

  • 7/31/2019 RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative

    7/10

    7

    When the Government produced a statement

    on progress towards the IT Strategy in June

    2012, the only agile project cited as a success

    was the successful, but small-scale, e-

    Petitions project which, although it had

    collated 16,000 petitions successfully, was not

    really a large-scale delivery project.15

    However, one year later there was still little

    evidence of the promised increase in use of

    agile approaches. A Cabinet Office report

    admitted that 10 departments had not yet

    started any significant agile projects, and in

    those that had, agile adoption was patchy.

    Significant progress was reported in only

    three areas:16

    The massive Universal Credit project was

    underway using some agile techniques

    The Government Digital Service had

    released alpha.gov and beta.gov websites

    A lot of money had been spent on

    training staff in agile techniques at the

    Maritime and Coastguard Agency.

    The IFG published a report from their

    research into progress. They interviewed all

    significant Government CIOs and their

    procurements staff, and representatives of IT

    suppliers both large and small. They found

    that progress towards using agile approaches

    had been slow.17

    They noted that the US has effective directintervention from a strong Government Chief

    Information Officer (CIO). In the UK they

    found that the implementation of agile and

    the strategy overall was poorly coordinated,

    incoherent and still without clear objectives

    or success criteria, despite the warnings in

    the NAO report of the previous year. The IFG

    noted that although senior leaders in

    government and in technology suppliers

    supported the concepts proposed in the 19

    strands of the strategy, they were not

    convinced about the approach to

    implementing it:

    The IT strategy did not adopt the

    (previous IFG) recommendation that

    platform and agile should be driven by a

    strong, independent CIO instead (it relies on

    a) CIO delivery board. CIOs should question

    whether they are genuinely improving the

    ways that they are working in areas such as

    agile, or whether they are just attaching a

    label to projects to get a tick in the box. 18

    The IFG found that there were concerns that

    the agile projects that were underway were

    often very minor projects running on the

    fringe of the departments and that in some

    areas projects may be being labeled as agile

    without having really changed the way in

    which they were run. 19

    Two weeks ago, the NAO has issued a report

    surveying the use of Agile Project

    Management in the 17 central UK

    Government departments. The report was

    expressly NOT intended to analyse the

    economy, efficiency and effectiveness of these

    efforts such Value for Money (VFM)

    reports from the NAO are larger, usually

    focusing on one department or project. This

    recent report aims to identify elements of

    agile practices that are being used in central

    government departments, rather than analyse

    VFM. Although this report is just a warm-up

    for analytical VFM reports on Government

    technology projects, it does identify the

    problem that there is still no specific plan for

    tracking the adoption of Agile throughout

    Government, and it is unclear how many

    Agile projects are actually underway.

    Conclusions

    To conclude:

    What I have found fascinating in my researchare the similarities and the differences

  • 7/31/2019 RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative

    8/10

    8

    between the US and the UK.

    Both the Obama and the Cameron

    administrations have similar aims with

    regard to flexible IT development, but they

    have taken different approaches towards

    making the changes.

    On the one hand the US IT Strategy has

    measurable targets, but they mainly relate to

    deadlines for the production of

    yet more guidance material on modular

    development

    running training courses

    setting up clear project management

    career paths.

    On the other hand the UK IT Strategy has a

    vaguely defined target of half of major ICT-

    enabled change programmes being Agile by

    April next year - a great intent, but one that is

    difficult to measure.

    Certainly, even though both governments

    have the aim of moving away from Waterfall,the approach in each case is different. Vivek

    Kundra in the US used a hands-on approach

    to re-shape failing projects for faster, more

    incremental delivery. In the UK a consensual

    approach of management by committee has

    been adopted.

    This is a great area for potential research: the

    best estimates are that governments are

    responsible for about half of IT spend in boththe US and UK.

    One private sector Agilist that I spoke to in

    my researches thought that Agile in

    Government was an interesting niche for

    research.

    Well, half of all IT spend is a pretty big niche!

    There has been a spate of reports in the lasttwo years from the IfG, the GAO, the NAO

    and industry commentators, such as Ovum.

    DISA started GCSS-J in 1997 as a prototype.

    The system is being developed incrementally

    using Agile software development

    specifically, the Scrum methodology.20

    These reports have recognized that a move to

    Agile is a major policy shift, but that more

    research is needed into progress.

    For example: What is a 'major' programme?

    What is, and what is not an 'IT-enabled'

    programme? How can we be sure that a

    project really is using an Agile approach?

    A follow-up survey by the NAO, published justlast month, found it impossible to identify a

    consistent list of the Agile projects that are

    underway.

    There is a window of opportunity here, I

    suggest, to assess how the switch to Agile in

    the US and UK governments is progressing.

    To realise this goal of proving the benefits of

    Agile to government, we need research overthe next 3-5 years to show:

    How many projects are actually using

    Agile?

    Which strategies for making the switch

    have really worked?

    What evidence is there that a switch to

    Agile has brought an economic benefit?

    This is a fertile area in need of more research- perhaps some collaborative, trans-Atlantic

    work.

    Will the US resolve and clarify how 'modular'

    approaches relate to Agile approaches - are

    these terms synonymous? Is the new US

    guidance really any more than a new set of

    regulations - how can the culture change that

    is needed be enacted? And can the vigorous

    and decisive leadership during VivekKundra's term as Federal CIO be sustained

  • 7/31/2019 RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative

    9/10

    9

    now that he has moved on to fresh pastures?

    Finally - a unique opportunity for

    comparative research is offered by the

    existence of two similar Agile strategies,

    being enacted in two different countries in

    similar timeframes.

    It's up to us to take up this research

    opportunity, and run with it!

    Thank you!

    Brian Wernham's new book, "Agile Project Management for Government" was published thisBrian Wernham's new book, "Agile Project Management for Government" was published thisBrian Wernham's new book, "Agile Project Management for Government" was published thisBrian Wernham's new book, "Agile Project Management for Government" was published this

    summer by Maitland and Strong.summer by Maitland and Strong.summer by Maitland and Strong.summer by Maitland and Strong.

    [email protected]

    1 See http://agilemanifesto.org

    2 See http://www.agileconference.org/academic-conference

    3 Brian Wernham, Agile Project Management for Government: Leadership Skills for Implementation of Large-

    scale Public Sector Projects in Months, Not Years. (New York, London: Maitland and Strong, 2012), 24856

    4 Vivek Kundra, 25 point implementation plan to reform federal information technology management

    (Washington [D.C.]: The White House, 2010)

    5 Michael Azoff, Agile in the UK public sector (Ovum, 2012) unpublished manuscript, .

    6

    UK NAO, The failure of the FiReControl project, 2011,http://www.nao.org.uk/publications/1012/failure_of_firecontrol.aspx

    7 Agile for Universal Credit a good choice says report, Campaign for Change, 2011,

    http://ukcampaign4change.com/2011/10/05/agile-for-universal-credit-a-good-choice-says-report

    8 Tony Collins, Gateway reviews, Campaign for Change, 2012,

    http://ukcampaign4change.com/category/gateway-reviews/

    9 Justine Stephen et al., System Error: Fixing the flaws in government IT, Institute for Government UK,

    2011, http://bit.ly/PWNjCC

    10 UK Cabinet Office, Government ICT Strategy, 2011,

    http://www.cabinetoffice.gov.uk/sites/default/files/resources/uk-government-government-ict-strategy_0.pdf

    11

    UK Cabinet Office, Government ICT Strategy, 2011 and UK Cabinet Office, Government ICT Strategy,2011, http://www.cabinetoffice.gov.uk/sites/default/files/resources/uk-government-government-ict-

    strategy_0.pdf

    12 Emergn, Sourcing for Agile, 2012, 6, http://www.emergn.com/wp-content/uploads/2012/05/TP-Sourcing-

    for-Agile.pdf

    13 UK Cabinet Office, One Year On: Implementing the Government ICT Strategy, 2012, 9

    14 Implementing the Government ICT Strategy: six-month review of progress: NAO Report (HC 1594 2010-

    2012), UK NAO, 2011

    15 UK Cabinet Office, One Year On: Implementing the Government ICT Strategy, 2012, 9

    16 ibid

  • 7/31/2019 RAISE2012 - Brian Wernham - 11 October 2012 - Agile Adoption in the US and UK Governments - A Comparative

    10/10

    2

    17 Justine Stephen et al., System Error: Fixing the flaws in government IT, Institute for Government UK,

    2011, 14, 30, http://bit.ly/PWNjCC See Figure 1 for a diagram which illustrates the lack of clarity over co-

    ordination of the implementation of the strategy.

    18 ibid.

    19 Government Technology Opportunity in the 21st Century (GTO-21), TechAmerica Foundation, 2010, 18,

    http://www.techamerica.org/Docs/gwd4r5.pdf

    20 See also US GAO, GAO-12-7 Information Technology: Critical Factors Underlying Successful Major

    Acquisitions, 2011, 13, http://www.gao.gov/new.items/d127.pdfand Azoff, M, Agile in the UK public sector,

    Ovum, 2012