Sentença procedente Elenstil excl ICMS da contrib previdenciaria
Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection...
Transcript of Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection...
![Page 1: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/1.jpg)
![Page 2: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/2.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 2 of 64
TABLE OF CONTENTS
1 INTRODUCTION.................................................................................................................... 5
1.1 DOCUMENTS RELATED TO THE REPORT ............................................................................ 6
2 SUMMARY OF HISTORY ...................................................................................................... 7
3 EXECUTIVE SUMMARY ....................................................................................................... 8
3.1 SCOPE OF PRESENT STUDY............................................................................................. 8
3.2 SELECTION OF THE AREA OF INTEREST (AOI) ................................................................... 8
3.3 ALIGNMENT STUDIES ON DEM ....................................................................................... 11
3.4 SELECTION OF THE ALIGNMENT...................................................................................... 13
3.5 ALT-3: DN TRACK SIDE WITH RULING GRADIENT OF 1 IN 125: ........................................... 14
3.6 FUTURE SCOPE OF WORK .............................................................................................. 15
4 DESCRIPTION OF THE AREA ........................... ................................................................. 16
4.1 EXISTING MEANS OF TRANSPORT .................................................................................. 16
4.2 CLIMATE & RAINFALL ..................................................................................................... 16
4.3 GEOLOGICAL SETTING OF THE AREA .............................................................................. 16
4.4 GEOTECTONIC SETTING OF THE AREA ............................................................................ 17
4.5 ENVIRONMENTAL INTERFERENCES ................................................................................. 19
4.5.1 Forest areas ......................................................................................................... 19
4.5.2 Wild life Sanctuary ................................................................................................ 20
4.5.3 Effects on Choice of Alignment ............................................................................. 21
5 COMMENTS ON PRELIMINARY ALIGNMENT SUGGESTED BY RAIL WAYS .................. 23
5.1 GENERAL DESCRIPTION ................................................................................................ 23
5.2 SEALIENT FEATURES OF FINAL LOCATION SURVEY ALIGNMENT PREPARED BY WCR ......... 23
5.3 REVIEW OF FINAL LOCATION SURVEY ALIGNMENT PREPARED BY WCR ............................ 24
5.3.1 Geometry of Paper Alignment (Budni - Barkhera Section) .................................... 24
5.3.2 Station location in Paper Alignment (Budni - Barkhera Section)............................ 25
5.3.3 General comments ............................................................................................... 25
5.4 CONCLUSION ................................................................................................................ 26
6 TERMS OF REFERENCE FOR PRESENT STUDY ............................................................. 27
6.1 OTHER CRITERIA .......................................................................................................... 30
6.2 CRITERIA OF SELECTION ................................................................................................ 31
6.3 DESIGN CODES AND STANDARDS .................................................................................... 31
![Page 3: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/3.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 3 of 64
7 DEVELOPMENT OF DIFFERENT VIABLE ALIGNMENT OPTIONS . ................................. 32
7.1 DESCRIPTION OF ALIGNMENTS ....................................................................................... 32
7.1.1 ALT-1: West side and Detour with ruling gradient of 1 in 170: .............................. 32
7.1.2 ALT-2: West side and Detour with ruling gradient of 1 in 125: .............................. 32
7.1.3 ALT-3: DN track side with ruling gradient of 1 in 125: ........................................... 33
7.1.4 Discussion on Critical Aspects .............................................................................. 36
7.1.5 Discussion on the alternatives and preliminary assessment ................................. 39
8 PRELIMINARY COST ESTIMATE ......................... .............................................................. 43
8.1 TUNNELS ...................................................................................................................... 43
8.2 CUTTINGS & EMBANKMENTS .......................................................................................... 45
8.3 BRIDGES ...................................................................................................................... 46
8.4 APPROACH ROADS CHECK ............................................................................................. 47
8.5 SETTLEMENT ................................................................................................................ 47
8.6 COST OF ALIGNMENT OPTIONS ...................................................................................... 47
9 CONCLUSIONS................................................................................................................... 49
9.1 SUMMARY ..................................................................................................................... 49
9.2 TECHNICAL DATA ABOUT THE SELECTED ALIGNMENT ....................................................... 49
10 REFERENCE ....................................................................................................................... 52
10.1 DESIGN CODES AND STANDARDS .................................................................................... 52
10.2 OTHER INTERNATIONAL TECHNICAL DOCUMENTS ............................................................. 54
![Page 4: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/4.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 4 of 64
![Page 5: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/5.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 5 of 64
1 INTRODUCTION
RAIL VIKAS NIGAM LIMITED (RVNL), a Government of India Undertaking, has been entrusted
with the work of detailed construction survey, Geotechnical investigations, design, engineering and
construction of 3rd Line of Barkhera – Budni (33KMs) Project on Bhopal-Itarsi route of Bhopal
Division of West Central Railway in the State of Madhya Pradesh. West Central Railways (WCR)
has already carried out a Reconnaissance Engineering-cum-Traffic Survey for the alignment.
This is a BG line conforming to the standards of a Group A line with speed potential of 160 KMPH.
This entire line will be in Raisen and Sehore districts (Obedullaganj forest div) of Madhya Pradesh.
Bhopal - Itarsi is a very important section of Indian Railway in Central India carrying enormous
passenger & goods traffic. It is a central link connecting North & South India. Bhopal is a junction
station with lines going towards Delhi & Ujjain. Itarsi is a very important junction station for lines
coming from Nagpur, Khandwa & Jabalpur i.e. from Central Railways & West Central Railway.
The area from Barkhera to Budni through which the 3rd railway line (between Bhopal and Itarsi)
has been proposed lies in the Aravali range. The entire length of this alignment falls in the Deccan
plateau with steep Ghat area. This involves the necessity of construction of a number of tunnels
and bridges/viaducts.
The preliminary alignment design carried out by WCR on the basis of topographical maps (referred
as WCR/Paper Alignment in the report), is used as the reference for further studies. The present
study aims at refining Paper Alignment /finding altogether new alternative which is most suitable
from Railway’s Operational point of view using advanced tools and softwares.
The study uses Digital Elevation Model and Trimble Quantm system to comprehensively assess
alignment options across the terrain. A GIS model consisting of topographical, geological,
environmental, wildlife and land use data shall be used at various stages during the design to
refine the alignment further.
The technical criterion on which the design has been based is detailed in Section 6 of this report.
The Alignment Design Report Stage I covers (based on TOR):
i) Comments on paper alignment suggested by Railway on areas such as Identification of
critical locations /sections such as Portal locations, Bridges, Height of cuts and retaining
structures and Location of Railway Stations
ii) Finalization of basic parameters for the Railway project from Construction and
Operational view point.
iii) Development of different viable alignment options from Budni to Barkhera based on the
geo-referenced cartography.
iv) Advantages and disadvantages on issues related to technical, financial, operational,
time line etc with comparative study in tabular form.
![Page 6: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/6.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 6 of 64
1.1 DOCUMENTS RELATED TO THE REPORT
The report should be read along with the drawings and documents listed in Table 1.1 which are inherent part of this report
Table 1.1: List of documents/drawings related to th e report
S.No Doc. No. Title 1 Title 2 Title 3 Scale Rev.
1 P-1-GW-1 ALIGNMENT REPORT
STAGE-I Design Report 1
2 P-1-AL-2 ALIGNMENT REPORT
STAGE-I General Plan Alignment
Alternatives Plan 1:25000 0
![Page 7: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/7.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 7 of 64
2 SUMMARY OF HISTORY
On Delhi-Chennai route, Bina-Bhopal-Itarsi section is extremely congested. This problem of
congestion is most critical in morning and evening hours when most of the mail/express long
distance trains cross the capital city of MP. This route is also negotiated by many goods trains. The
traffic is increasing year by year leading to slowing down of speeds & thoughput.
On this route, Barkhera-Budni is a ghat section with reduced capacity on which only a limited
number of trains per day can be run due to geometrical constraints like steep curves (leading to
reduction on max. Permissible speed) & steep gradients (leading to slowing down of goods trains
based on locomotive power). As such, a third line between Barkhera & Budni is required to ease
the traffic load on the existing two lines between these stations.
The first survey for the construction of the 3rd line Bhopal-Itarsi section was done in 2004. The
Railway board, vide letter no - 2004/W-I/Fenl/Survey dated Nov 2004, had sanctioned
Reconnaissance Engineering-cum-Traffic Survey for 3rd line between Bhopal and Itarsi Section.
The Survey work was awarded to M/S Elite Consulting Engineers, Pune by Deputy Chief Engineer
(Construction) West Central Railway Bhopal. This report has been duly prepared by M/s Elite
Consulting Engineers and submitted to WCR in Oct 2005.
The work of construction of third line across ghat between Budni and Barkhera was sanctioned by
Railway Board vide Pink Book 2011-12 at a total cost of Rs. 287.35 Cr. The work of final location
survey/detailed engineering construction survey for awarded to M/s Sipra Systems in 2011.
In 2012 (vide letter No. 2011/W-1/RVNL/1, dated 26/04/2012), Railway Board transferred the work
to RVNL for designing the alignment and constructing the line on fast-track basis. M/s Geodata
(GD) was awarded the work of alignment design (using DEM prepared from satellite imagery &
field surveys) and conducting Final Location Survey including preparation of detailed plans &
sections and detailed estimates, Marking Centre Line, Geotechnical Investigations and Detailed
Design Engineering in connection with Electrified 3rd Line between Barkhera & Budni (vide letter
No. 12.2 BKA-BNI/FLS & DDE).
![Page 8: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/8.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 8 of 64
3 EXECUTIVE SUMMARY
3.1 SCOPE OF PRESENT STUDY
The scope of the Present study consists of development of alignment including review and
refinement of preliminary paper alignment based on geological considerations & constructability
considerations using Satellite Imageries, Staking of final alignment, design of structures, land
acquisition, forest & environmental clearances, preparation of detailed estimate and BOQ etc
The present report, includes the study of alignments based on geometry, topography, operational,
wildlife & technical aspects finalised in consultation with RVNL. The report recommends the best-
suited alignment based on above criterion.
Prior to this report, the Inception Report detailed the process of selection of corridor for the study.
The process of preparation of DEM for the project area (project corridor), on which the studies are
based, was also described in the DEM Generation Report.
The recommended alignment is to be further studied in detail and refined in Alignment Report
Stage-II based on the geological studies to effect local changes to the alignment for avoiding
critical areas.
Pre-construction activities for the alignment including, preliminary design, abstract/detailed cost
estimates, planning of access roads & muck dumping areas and construction programme &
scheduling will be detailed in Draft Final Alignment Report/Final Alignment Report.
Apart from the desk studies, the consultancy work includes execution of geological surveys,
topographical surveys, geotechnical investigations (including borehole drilling) and the staking of
alignment on the ground at appropriate stages of the study.
3.2 SELECTION OF THE AREA OF INTEREST (AOI)
The AOI includes all the possible alignment options fulfilling the design criteria defined in the TOR
as well as those communicated afterwards. The difference in elevation between Barkhera & Budni
stations is 161m. The criteria for ruling gradient was defined as 1 in 170 . However, RVNL modified
the criteria to select a broader corridor covering alignments with gradients varying from 1 in 170 to
1 in 125. Thus, to incorporate all the alignments with ruling gradient varying between 1 in 125 and
1 in 170, an enlarged area was considered as the project AOI.
At present, there are two existing railway tracks in this section. The existing Up track travels
downhill from Barkhera to Budni with a gradient of 1 in 80 whereas the existing Down track travels
uphill from Budni to Barkhera at a gradient of 1 in 125. The Barkhera station is situated inside the
revenue area of Ratapani Wildlife Reserve Forest and Budni station is situated within 10 kms of the
Wildlife Reserve boundary (i.e. within eco-sensitive zone) – as such any new alignment connecting
Barkhera and Budni has to pass through the Wildlife Reserve Forest.
![Page 9: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/9.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
Figure 3.1 Map of project area showing existing inf rastructure
Ideally, the alignment should have a gradient of around 1 in 170 for operational efficiency and
degree of curvature less than 1.2 degrees to enable a maximum permissible speed of 160 kmph.
To match the geometric constraints (for a design Speed 160 KMPH), the proposed alignment
should ideally take a longer length route round the plateau enabling provision of smooth curve of
not greater than 1.2 degrees. This would allow the proposed 3rd track to function as DOWN track
(uphill) and the existing DOWN track to function as bidirectional middle line. This 3rd line will
connect at existing Barkhera and Budni stations on Bhopal-Itarsi section. This will be a BG line
conforming to the standards of a Group A route for sanctioned speed of 160 KMPH.
In case of operational requirements governing the design, the prime factors to be considered in
selecting the new alignment would be to enhance standards of construction - ruling gradient and
the degree of curvature. However, apart from the operational requirements, due importance has
also to be given to the consideration of wildlife and environment as a considerable part of the
Barkhera
Existing Railway Up Track
NH-69
Choka
Water pipeline
Budni
Existing Railway Down Track
Gadaria River
Midghat
![Page 10: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/10.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
alignment will have to traverse through the core area of Ratapani Wildlife Sanctuary Reserve and
remaining alignment will be in a zone of 10 km from the Ratapani Wildlife Reserve i.e. Eco-
sensitive/Buffer zone. Yet another important deciding factor would be the cost of the construction
of the new line which in turn will necessitate adoption of the option with smallest possible length
(while conforming to the specifications) & avoiding/minimizing tunnels and bridges.
Figure 3.2: General Plan view of Project Area
(Area of Interest, Existing main lines, studied alignments for 3 rd line & Survey Network)
As regards to the accessibility of the project area, NH-69 provides road access along the existing
railway lines. There also are village/forest roads and state roads in the project area. The passenger
road services in this area are operated by the Madhya Pradesh State Road Transport Corporation
AOI/Corridor
Barkhera
Budni
Mid Ghat
Choka
![Page 11: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/11.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 11 of 64
as well as private transporters. Figure 3.1 shows a map of the project area and existing
infrastructure in the area.
Figure 3.2 shows the various possible alignment options that were used to fix the AOI for the
present study and also shows the network of survey points used in the preparation of DEM. These
options, numbering in hundreds, shown in green colour, were studied based on the technical
parameters defined in the TOR, with the help of Quantm software on Aster and Cartosat DEM.
Alignment options were also drawn manually to add to the options already generated by Quantm.
3.3 ALIGNMENT STUDIES ON DEM
Following the demarcation of AOI for the project, DEM was prepared for the project area from the
satellite images made available by RVNL. Limited surveys were conducted to caliberate the DEM
to make it suitable for all further studies.
The alignment options provided by Quantm as shown in Figure 3.2 can be grouped into three broad
categories/corridors:.
• Corridor 1: Options traversing the area to the west of existing Down track and keeping
away from the existing track beyond the platue
• Corridor 2: Options following the existing Down track and passing as close as possible to
the Down track.(refer Figure 3.3.Figure 3.4)
The project area along with the arrangement of existing infrastructure and the three broad corridors
have been presented in the schematic diagram below (Figure 3.4). The topography of the area has
been shown in Figure 3.3.
For generating alignment alternatives in each of the three categories/corridors, the first step was
the finalisation of obligatory points, i.e. the block stations. The existing block stations were fixed as
obligatory points for the options close to existing tracks. Obligatory points for the option keeping
away from the existing tracks were fixed along the alignment, keeping in mind a block length of 10-
13 kms.
In corridor 1 , the alignment alternatives drift away from the existing Down Railway track
necessitating two new Railway stations (obligatory points). One new station was selected near
Jhajjargiri village (NS1) with block section length of 12 km. Between NS-1 and Barkhera, there is
no population at suitable block section length distance. Accordingly, long and flat area facilitating
location of new station (NS2) has been selected. The block section length between NS1 and NS2
is 13 km and the block section length between NS2 and Barkhera is 12.5 kms.
In corridor 2, the alignment alternatives closely follow the existing Railway tracks. Accordingly,
existing block stations at Choka and Midghat have been selected as obligatory points to reduce
recurring costs.
![Page 12: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/12.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 12 of 64
Figure 3.3: DEM snapshot showing topography of the project area
Figure 3.4: Schematic diagram of the project area
The station locations adopted for the study are summarised in Table 3.1 .
Table 3.1: List of possible locations for stations
ID Village/City Corridor 1 Corridor 2
BNI Budni Existing station Existing station
MID Midghat Existing station Existing station
NS-1 New Station 1 New Station 1 -
NS-2 New Station 2 New Station 2 -
CHQ Choka Existing station Existing station
BKA Barkhera Existing station Existing station
![Page 13: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/13.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 13 of 64
Alignment alternatives were developed to connect these obligatory points. All the alternatives
between obligatory points in each of the corridors were compared to select most preferred
connections. Finally, based on the above study, three alignments were shortlisted between Budni
and Barkhera for detailed study – ALT-1 in corridor 1, ALT-3 in corridor 2 & ALT-2 is combination
of both corridor , which are discussed in Section 3.4.
3.4 SELECTION OF THE ALIGNMENT
After having determined the possible locations for the various stations and after having determined
the revised technical parameters (see Table 6.1) in consultation with RVNL, various possible
connections between the stations have been evaluated and compared based on criteria for
selection of alignment. Finally, based on the above study, three alignments were shortlisted for
detailed study – ALT-1 in corridor 1, ALT-3 in corridor 2 & ALT-2 combination of both corridor. The
General plan showing alignment alternatives (Drawing Nos. P-1-AL-001 & P-1-AL-002) and
detailed plan and L section of the alignments (Drawing Nos. P-1-AL-5 to P-1-AL-09) are presented.
The key aspects and comparison of alignments is presented in Table 7.1.
Alignment option Alt-1 is the longest alignment option with a ruling gradient of around 1 in 170
and degree of curvature limited to 1.2 degrees resulting in a design speed of 160 kmph. Alt-1 takes
a longer length route around the plateau away from the existing Down line and allows the proposed
3rd track to function as Down track (uphill) & the existing Down track to function as bidirectional
middle line. This allows all the trains travelling in the uphill direction to climb a maximum gradient of
1 in 125 on the existing Down line (or 1 in 170 on the proposed 3rd line) increasing operating
efficiency. However, this is the longest and costliest alignment option along with being hugely
disruptive to the flora and fauna of the Ratapani Wildlife Reserve area. Since the Alt-1 option would
need to traverse through virgin forests inside the Ratapani Wildlife Reserve Forest, it has the
maximum risk of not getting an environmental clearance and would in any case involve
complications related to construction clearances.
Alignment option Alt-2 is take off from Budni station and turn left, passing between the Talpura
Lake & Vardhaman factory and reach proposed NS1. The ruling gradient for this section is 1 in
213 and maximum Degree of curvature is 1.2 degrees. This alignment have 1 new station, and
after that it is passing near the Yaar nagar village reaches existing Choka station. The ruling
gradient is 1 in 130 and and the maximum Degree of curvature is 1.2 degrees. The next block
Connects the Choka and Barkhera stations. This section is designed for a ruling gradient of 1 in
125 (Compensated) and a maximum Degree of curvature of 4 deg. This section can be refined
further with a reduced degree of curvature (approx. 1.2 degrees) but in such a case will involve
some additional tunnels (approx additional tunnel length of less than 1 km). This alignment is also
would need to traverse through virgin forests inside the Ratapani Wildlife Reserve Forest between
the New Station-1 and Choka station and after choka station it is running parallal to the existing
track. Howerver it is less (but not least) distrupted to the wildlife as compare to Alt-1.
![Page 14: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/14.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 14 of 64
Alignment Alt-3 follows the existing Down track and travels close to the existing line on the west.
The Alt-3 allows the proposed 3rd track to function as Down track (uphill) & the existing Down track
to function as bidirectional middle line allowing trains to climb at a gradient of 1 in 125 on both
existing Down line & proposed 3rd line. The maximum curvature on Alt-3 is 4 degrees near Budni,
restricting the design speed to 90 kmph in this curve. This option fulfils the environmental criteria
by being very close to the existing Down line all along its length thus causing very less disturbance
to the Ratapani Wildlife Reserve. Most of the 3rd line in this option would be constructed inside the
existing Railway boundary thus necessary approvals for construction may be easier. In this option
there is a risk of disturbance in the service on the existing down line due to construction work being
carried out in close proximity, however this can be mitigated by adopting suitable measures.
Based on a preliminary study of alignment alternatives on DEM, many alignments were studied in
detail and presented to WCR (presentation to GM and PHOD’s on 25/3/2014, 15/5/2014 &
26/6/2014). WCR has conveyed its approval for adoption of 1 in 125 as design gradient vide letter
no WCR-JBP/T-1272 dated 30.06.2014.The proposed alignment should be parallel to the existing
Down line.
In view of Alt-3 being a good balance between all the requirements and its suitability to WCR, it
has been selected for further study.
Tabulated comparision of all the alignment is mantioned in Table 7.1: Key aspects and comparison
of alignments
3.5 ALT-3: DN TRACK SIDE WITH RULING GRADIENT OF 1 IN 125:
The alignment is divided into three blocks and utilises the existing stations of Midghat and Choka
as block stations, avoiding the need of establishing new stations. This option traverses through the
Ratapani Wildlife Reserve almost hugging the existing infrastructure and remaining mostly inside
the existing Railway boundary. The alignment consists of six tunnels with a total length of 1705m
and Eight major bridges with total length of around 820m.
The alignment leaves Budni besides the Down track and navigates a sharp 4 degree (approx)
curve which is unavoidable due to the sudden rise in topography after the Budni station. Following
this, the alignment stays along the existing Down track at a slightly higher elevation and forms a
bulb over the existing bulb with a 3.5 degree curve. This bulb section includes one tunnel of length
1080m (approx) and high embankment. The design speed in this curve is limited to 95 kmph for a
length of 1751 m (approx). The alignment manages to achieve a gradient of 1 in 125
(compensated) up to Midghat station due to the increase in length in the bulb section. The bulb
section is a critical area for the design as construction of the line at this location would necessitate
construction of a tunnel. Provision of IBH is also possible in this section between KM 6.000 and KM
8.113 (2113 m) with a gradient of 1 in 200. The station yard at Midghat is proposed at a gradient of
1 in 125. The gradient in Midghat station is 1 in 125.
![Page 15: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/15.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 15 of 64
After Midghat, the alignment follows the existing Down track as much as possible within the
restrictions of design criterion. The alignment has a gradient of 1 in 380 (compensated) between
the two stations and has 4 degree curves which limit the design speed to 90 kmph in a length of
1287 m (approx). The station yard at Choka is at a gradient of 1 in 125 due to topography. The
existing station yard at Choka also has a steep gradient of about 1 in 125.
After Choka, the alignment keeps along the existing DOWN line up to Barkhera with a ruling
gradient of 1 in 125 (compensated. One tunnel is proposed in this section with a total length of 540
m and four bridges with a total length of 135 m (max 80m length). The Steepest gradient in this
block section is 1 in 125.
.
3.6 FUTURE SCOPE OF WORK
Alignment Alt-3 will be further studied in detail and refined in Alignment Report Stage-II based on
the geological constiderations. These refinements would be carried out for avoiding critical areas or
developing technical/constructional solutions to mitigate the risks at unavoidable critical areas.
Further the pre-construction activities for the alignment design including, preliminary design of
structures, abstract/detailed cost estimates, planning of access roads & muck dumping areas and
construction programme & scheduling will be detailed in Draft Final Alignment Report/Final
Alignment Report.
![Page 16: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/16.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 16 of 64
4 DESCRIPTION OF THE AREA
The project area lies in Raisen and Sehore Districts in the state of Madhya Pradesh, between
N22.90 - N22.77 and E77.50 - E77.71 (Lat/Long) and falls under the Survey of India toposheet
No. 55(F-9). The entire length of this alignment falls in the Vindhyanchal range in the Deccan
plateau with steep Ghat area and an undulating topography. The height of project area is between
300m to 560m above Average Mean Sea Level.
The town of Budni is situated at a distance of 10 km from Hoshangabad and is coming up as an
important Textile industry centre. The Central Farm Machinery Training & Testing Institute is also
located in Budni.
4.1 EXISTING MEANS OF TRANSPORT
The main points of this link, i.e. Budni and Barkhera are connected to Bhopal & Hoshangabad by
double line electrified railway line (Bhopal-Itarsi line) and by road (through NH-69). This road, NH-
69 runs along the existing UP track and at most places is not farther than 1km from the track.
Access to project site, for construction purposes can be easily provided through the NH-69. MP
State Highway – 22 can also provide access to the project area which traverses from the east of
the project area and joins NH-69 at Budni.
4.2 CLIMATE & RAINFALL
The Climate of the project area has a humid subtropical climate, with cool, dry winters, a hot
summer and a humid monsoon season. The winter season commences from end of November
and lasts till the end of February. The average normal minimum temperature during this period is
about 19o C. The individual day temperature comes as low as 10o C. From March onwards, the
temperature starts rising and maximum temperature is observed during the month of May. The
average normal maximum temperature is around 400 C. The individual day during summers can go
to around 46o C. With the arrival of monsoon the weather becomes pleasant. The monsoon starts
in late June and ends in late September. These months see about 40 inches (1020 mm) of
precipitation, frequent thunderstorms and flooding. The average temperature during this season is
around 25°C and the humidity is quite high. In October, with the retreating of monsoon, the
temperature rises slightly during the day time but the nights continue to remain pleasant.
4.3 GEOLOGICAL SETTING OF THE AREA
The predominant rock formations in the area are Sandstones and Shales belonging to the Upper
Vindhyan System (Bhander Series). These sedimentary rocks have retained their original
horizontality and they do not show any signs of metamorphism or deformation or any tectonic
activity. They are very stable, hard to very hard having a high degree of resistance to weathering
and erosion. Their texture is medium to coarse and sometimes fine. The bedding is clearly sub
![Page 17: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/17.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 17 of 64
horizontal without any exceptions and there are some minor vertical rough discontinuities/joints,
which most of them can be characterized as sun-cracked surfaces.
From a geological point of view, along the project area, there will not be much of a problem as the
local geological conditions are rather favourable. The horizontal bedding and the hardness of these
rocks can allow:
a. To create high cuts with almost vertical stable slopes,
b. To excavate the tunnels and develop the tunnel portals without many difficulties; to
minimize overbreaks, smooth blasting will be required. The tunnel support system will
consist of shotcrete and rock bolts and might also require provision of steel ribs in low cover
areas;
c. To construct bridge foundations and/or high embankments without specific problems of
bearing capacity & issues related to slope stability.
Locally, some weak formations may be found like weathered shales and siltstones or colluviums
with small to medium sandstone boulders. In case that these weak formations cannot be avoided,
special protection or supporting measures would be required.
4.4 GEOTECTONIC SETTING OF THE AREA
As per IS 1893: 2002, the area lies in Seismic Zone 3. The Seismic risk Map of Madhya Pradesh,
showing the study area in SEISMIC ZONE 3, Moderate damage corresponding to intensity VII of
MM scale ( MM = Modified Mercalli Intensity Scale) has been presented in Figure 4.1.
However, very close to the study area there exists a very big and well known Fault System, namely
the SONATA Fault System, which poses a great seismic threat to the surrounding area. The
SONATA fault system (North Sonata and South Sonata Faults) is – according to many researchers
- an active boundary and is responsible for seismic activities in and around Madhya Pradesh
(Figure 4.2 & Figure 4.3).
![Page 18: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/18.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 18 of 64
Figure 4.1 : Seismic Risk Map of Madhya Pradesh.
Figure 4.2: Tectonic map of SONATA VALLEY shows epicentral distribution of earthqu akes (after Girish Ch. Kothyari and B. K. Rastogi, 2013)
Historical and instrumental records indicate that compressive stresses still continue to accumulate
along the fault zone due to continued northward movement of the Indian plate.
![Page 19: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/19.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 19 of 64
Figure 4.3: Tectonic map of Madhya Pradesh (Narmada river valley, showing major faults, after GSI, 1995)
This is evidenced by the fault solution studies of the earthquakes at Broach, Gujrat (23 March
1970) and Jabalpur, M.P. (22 May 1997), which suggest a thrusting movement (Girish Ch.
Kothyari and B. K. Rastogi, 2013). The observations by J.R. Kayal, suggest that the Sonata faults
were developed in tensional regime in the geological past and are now under compressive stress
due to the NNE movement of the Indian plate. GPS observations of E.V. Apel et al. suggest that
“strain is accumulating beneath the Son-Narmada south fault. The accumulation of strain beneath
this zone probably may cause strong earthquakes in future”.
Another smaller possible/interpreted fault is showing in the relevant GSI’s Geological Map (55F/9)
of Madhya Pradesh, which crosses almost perpendicularly the existing two lines at approximately
the midpoint of the Midghat Station and the Gadariya Bridge.
All this information must be taken into consideration during the design phase of the major
structures i.e. bridges and embankments, tunnels and slopes.
4.5 ENVIRONMENTAL INTERFERENCES
4.5.1 Forest areas
The alignment, in all of its length, will pass through either core area or buffer area of wildlife
sanctuary which is part of the forest area (as Barkhera station is situated inside the revenue area
of Ratapani Wildlife Reserve Forest and Budni station is situated within 10 kms of the Wildlife
Reserve boundary). Since the layout of the forest map (Figure 4.5) is such that there is no
![Page 20: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/20.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
alternative but to intrude into the Ratapani Wildlife Scantuary and the forest area. However,
attempts have been made to keep the alignment within the existing Railway Land.
The diversion of forest land for non-forest purposes will have to be applied for under the Forest
(Conservation) Act, 1980.
Figure 4.4 : Forest map of the project area.
4.5.2 Wild life Sanctuary
The alignment will pass through the Ratapani Wildlife Reserve as Barkhera station lies inside the
Wildlife reserveThe Wild Life (protection) Act, 1972 provides for seeking the recommendation of
the State Board for Wildlife (a Board chaired by the State Chief Minister) for any diversion of land
or produce including water, etc. from a Sanctuary.
Further, in view of the directions dated 9th May 2002 of Hon'ble Supreme Court in Writ Petition
(Civil) No. 337/1995, all such proposals in respect of a Sanctuary or a National Park also require
Supreme Court's approval based on the recommendation of the Standing Committee of National
Board for Wildlife (a Committee chaired by the Minister in Charge of the Ministry of Environment
and Forests).
Also in case any project requiring Environmental Clearance, is located within the eco-sensitive
zone around a Wildlife Sanctuary or National Park or in absence of delineation of such a zone,
within a distance of 10 kms from its boundaries, the User agency/Project Proponent is required to
obtain recommendations of the Standing Committee of NBWL. However, Railways is exempt from
the requirements of obtaining Environmental clearances.
Project Area
![Page 21: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/21.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 21 of 64
4.5.3 Effects on Choice of Alignment
Since the design of alignment through Wildlife Reserve Forest is unavoidable, attempts have been
made to minimize the disturbance in the reserve. This attempt consists of minimizing the length of
alignment inside the reserve and in unavoidable cases, designing the alignment closely with other
existing infrastructure – thus minimizing disturbance in undisturbed areas of the reserve. Concious
attempts have also been made to contain the alignment inside the existing Railway land, as far as
possible.
There are a number of existing infrastructures present inside the Wildlife reserve as enumerated
below and are shown in the schematic diagram (Figure 3.4):
• Up-Line Railway track • Down-Line Railway track • NH 69 • Water Pipeline • Power Transmission Line
These infrastructures lie in a narrow band and divide the Reserve into two parts. The alignment
options hugging the existing tracks cause the minimum disturbance inside the Wildlife Reserve
Forest and are most likely to win approval from the concerned authorities. As such Alignment
options Alt-3 is most preferred options as far as environmental, ecological and wildlife aspects are
concerned. At the same time, alignment option Alt-1 is the most disruptive in terms of
environmental, ecological and wildlife aspects and would need substantial forest land
acquisition/diversion adding heavily to the project cost. This option would also introduce difficulties
in getting approvals from NBWL and the Honorable Supreme Court.
Further to the choice of alignment, the construction activities (and the project scheduling) inside the
Wildlife Reserve Forest would have to be managed as per the Wild Life (protection) Act, 1972. For
example, special permission will be needed for carrying out blasting in case of tunnelling (due to
complete restriction on the use of explosives inside Wildlife Reserve Forest) and construction will
have to be scheduled as per availibilty of access to the construction site (as permissions will be
required for use of existing forest roads & also for construction of new access roads inside the
forest area).
![Page 22: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/22.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
Figure 4.5: Ratapani Wildlife Reserve map showing a ll alignment alternatives.
Barkhera
Budni
Mid Ghat
Choka
![Page 23: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/23.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 23 of 64
5 COMMENTS ON PRELIMINARY ALIGNMENT SUGGESTED BY RAILWAYS
5.1 GENERAL DESCRIPTION
As per “Reconnaissance Engineering-cum-Traffic Survey for 3rd line between Bhopal and Itarsi
Section" conducted by WCR in October 2005, the work of construction of third line between
Barkhera & Budni stations was sanctioned by Railway board vide Pink book item no-4 of 2011-12
at a total cost od Rs 287.35 Cr. The sealient features of the alignment as per Reconnaissance
Engineering-cum-Traffic Survey in Barkera-Budni ghat section included a gradient of 1 in 170 and
curvature of 3.85 deg.
The work of final location survey was awarded by WCR to M/s Sipra Systems Banglore in
17.08.2011. The Plan & L-sections prepared by the firm have been critically examined in the
following sections.(Fig-5.1)
5.2 SEALIENT FEATURES OF FINAL LOCATION SURVEY AL IGNMENT PREPARED BY WCR
The Final location survey for 3rd line between Budni and Barkhera Section conducted by WCR
prior to transfer of the work to RVNL is the starting point of the present.
The data received from WCR, at the time of transfer of work to RVNL, consisted of L-sections and
plans (6 sheets in A0 size) as submitted by the contractor for approval and repesentation of the
alignment in KMZ format based only on topographical data. Following facts are noted from scrutny
of the Plan & L-section.
1. There are very long streaches of gradient of 1 in 125, the longest being 5 Km. Out of the
total length of 31.5 kms of the alignment, 25 km is at rulling gradient of 1 in 125. The
proposed alignment disregards the rulling gradient of 1 in 170 recommended at the time of
Reconnaissance Engineering-cum-Traffic Survey.
2. The total length of alignment in curvature is 6.93 km with 3 no of curves sharper than 4 deg
(1.648 km)
3. The alignment passes through two tunnels of length 1.15 & 0.75 km resp.
4. 17 major bridges have been proposed in the alignment with total lineal waterway of 0.54
km.
5. Two new stations have been proposed at a gradient of 1 in 1200.
6. The proposed alignment penetrates deep into the wild life sanctuary disturbing the flora and
fauna in virgin area.
7. The alignment has been designed on the basis of free versions of DEM available on the
internet.
![Page 24: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/24.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 24 of 64
5.3 REVIEW OF FINAL LOCATION SURVEY AL IGNMENT PREPARED BY WCR
As coordinate information of the alignment was not available, for accurate evaluation of the paper
alignment, paper alignment was located on the new DEM; by superimposing the alignment on the
raster image.
Figure 5.1 presents the Alignment alternatives proposed by WCR and the Paper Alignment on the
DEM prepared for the present study.
Figure 5.1: Plan showing Alignment alternative prop osed by WCR
5.3.1 Geometry of Paper Alignment (Budni - Barkhera Section)
The total length of Ghat route in the Paper Alignment is 31.40 km. It deviates the existing Down
line at Ch. 770 km (Chainage as per existing Railway system) after Budni and joins again at km
![Page 25: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/25.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 25 of 64
789.725 km before Barkhera station. In the initial stretches, up to about 6.5 kilometres after leaving
Budni, the alignment is almost flat with rulling gradient 1 in 200. With a short stretch of gradient of 1
in 125, New station -1 has been planned at a gradient 1 in 1200. Then the alignment starts to climb
from 9.5 km maintaining a continuous grade of 1 in 125 for 13.5 km. Such long steep grades are
unfavourable for hauling of loaded goods trains up hill even with two locomotives.
The proposed paper alignment takes of from Budni on down side and follows unavoidable sharp
curvatures of 3.9 & 5.83 deg between existing down line & Vardhman siding between Budni and
New station-1. Further, the paper alignment is designed with curvature of 5 Deg max between New
station & Barkhera. As the alignment drifts away from existing tracks, without giving due weigtage
to disturbance to wild life sanctuary, long straights have been designed with mild curves are up to 2
deg.
5.3.2 Station location in Paper Alignment (Budni - Barkhera Section)
The existing lines between the mandatory points at Budni & Barkhera have two stations namely
Choka & Midghat. The details are provided in Table 5.1.
Table 5.1: List of the stations on Existing Alignme nt
No Block Station KM
Inter-distance along UP track
(KM)
Inter-distance along DN track
(KM)
Inter-distance
along paper
alignment (KM)
1 Barkhera 789.430 6.2 6.2 6.2
2 Choka 783.000 6.4 6.4 6.4
3 Midghat 776.820 6.1 8.2 8.2
4 Budni 770.040
The Paper Alignment provided for two new stations with flatter gradients of 1 in 1200. The
locations of stations have not been chosen judiciously so as to keep the length of block section
same.
5.3.3 General comments
While the proposed alignment is suitable from operational point of view, the design method
adopted is not of the state-of-the-art level from construction as well as geological and Wildlife
points of view and therefore it should be further improved. The paper alignment has been
developed based only on topographical studies resulting in some disadvantages:
1. The route is longer than the existing up and down lines (31.4 kms length of paper alignment
against 26 kms of existing main Down line) while acchieving a ruling gradient of 1 in 125
which is similar to the existing Down main line.
![Page 26: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/26.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 26 of 64
2. Two new station locations are proposed but this is unavoidable as the alignment takes a
detour away from the existing lines. The increased length and requirement for new stations
increase the cost.
3. No geological mapping has been prepared for the study of paper alignment, which
increases the risk during construction.
4. Wildlife aspects have been completly ignored in developing the paper alignment. The
alignment passes straight through the undisturbed areas of Ratapani Wildlife Reserve
Forest and would severly damage the ecology & wildlife habitat during construction and
operation.
Thus we can say that the design approach followed for the paper alignment design does not
provide the optimal solution with respect to the overall project conditions.
5.4 CONCLUSION
The paper alignment has been designed as the new Down line with operational efficiency in mind.
Since this line will follow an uphill route, it has been developed with a ruling gradient of 1 in 125
(compensated) and up to 5.0 degree curves, excluding the curve just after Budni station (which is
5.83 deg and unavoidable for all options leaving Budni station and following a gradient more than 1
in 80). This alignment is relatively more acceptable (even with the requirement of double
locomotives for hauling the freight trains uphill to reach Barkhera from Budni) as it supports a
maximum speed of 120 kmph with speed restriction of 65 kmph on sharp curves for the passanger
trains travelling on this line.
In order to achieve the relatively gentle gradient, the paper alignment navigates a length of about
31.4 kms, away from the existing tracks, on the existing Down line side and is provided with low
degrees of curvature. The existing Down main line, in comparision, has a total length of 26 kms in
this section. The paper alignment remains almost flat (more than 1 in 500 & upto 1 in 2000) in the
initial 5 kms after Budni and then starts to climb. This not only results in the paper alignment having
a relatively high cost but also encroaching into the forest area and thus causing disturbances to the
flora and fauna in the ecologically sensitive region – specially in the Ratapani Wildlife Reserve.
Adding to the construction cost are a requirment access roads through core area of the sanctuary
for construction of the line. The proposal would also require setting up of two new stations for
operation which would further increase the operating costs for the railways.
The study carried out for the paper alignment does not include any geological, ecological, and
environmental inputs for the design, as such, not quantifying the possible risks during the
construction phase (and also possibly during getting approval for the project from various
agencies).
![Page 27: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/27.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 27 of 64
6 TERMS OF REFERENCE FOR PRESENT STUDY
The design has been carried out with the following technical parameters based on the TOR:
Table 6.1: Technical parameters adopted for alignme nt development
CIVIL WORKS
S. No. ITEM PARAMETERS
1.
Standard of Construction Group` A’ suitable for operation of 25t axle load-2008 trains.
2.
Gauge 1676 mm BG
3.
Track structure 60 Kg/90 UTS rails in mainline and 52 Kg rails in loop lines and sidings.
4.
Sleeper 60 kg PSC sleepers of existing design.
5. Sleeper density 1660 sleepers per km in main line and 1540 sleepers per km in
loop line.
6.
Ballast cushion Mainline -350mm Minimum.
Loop lines-250 mm.
7.
Welding of rails CWR/LWR will be provided.
8.
Points & Crossings 60 KG on MBC sleepers with 1 in 12 curved switch negotiated by passenger trains and 1 in 8.5 curved switch negotiated by goods
trains.
9.
Formation
1. Blanket of adequate depth will be provided depending on the sub-grade proposed.
2. Protective measures, as required ensuring safety in cutting must be incorporated.
10.
Maximum degree of curvature 1.2 Degrees
11.
Ruling gradient 1 in 170 (compensated).
12.
Gradient in yard Preferably 1 in 1200 but not steeper than 1 in 400. Gradient in
existing yards need not be changed.
13. Length of loop Minimum 735 meter CSR.
![Page 28: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/28.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 28 of 64
S. No. ITEM PARAMETERS
14.
Track centres 5.3 m minimum
15.
Maximum grade on approach to main river
bridges
As flat as possible, consistent with site conditions and not steeper than 1 in 200 compensated.
16.
Level crossing
At locations where track is parallel, the existing level crossing should be retained. However, in case alignment is not parallel,
preferably ROB/RUB should be provided on important roads/highways.
17.
Width of formation:
Bank: 6.85 on straight.
Cutting: 6.25m on straight.
Width of bank and cutting may be increased suitably on curves based on extra clearance requirement.
18.
Speed
160 Kmph for Mail / Express Trains
100 Kmph for Goods Trains
19.
Type of Loading 25t-2008.
ELECTRICAL AND OHE
SN ITEM PARAMETERS
1 System of electrification
Simple Polygonal type with 100 mm pre sag feed with single phase ,50 Hz,25 KV
2. Gauge 1676 mm BG
3. Pantograph 1800mmm wide
4. Wind zone 112.5 kg/m2
5. Maximum half tension length 750mtr.
6. Tension in CW 1000kgf
7. Tension on catenaries 1000kgf
8. Size of CW / catenaries 107 sqmm/65sqmm
9. Type of CW HDGCW
![Page 29: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/29.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 29 of 64
SN ITEM PARAMETERS
10. Type of catenary Cd-Cu stranded
11. Type of masts Galvanized Rolled /Fabricated
12. Type of portal Galvanized Fabricated
13. Type of DA Galvanized Rolled
14. Normal setting distance 2.9 mtr on tangent track for individual mast and 3.0 mtr for portals
15. Normal setting distance
of multiple cantilever supports:
3.0 mtrs
16.
Normal setting distance in front of signals
Electrical clearance
Vertical long time
Vertical short time
Horizontal on long time
Horizontal short time
Offset
250 mm
200-mm
250-mm
200mm
17. Type of OHE over ML turn outs Overlap type
18. Type of OHE over yard
turn outs
Overlap /cross type
19. Maximum fault current
on 25 KV side
8000A
20. 3 phase fault level
10000 MVA
21. BIL 95 KV p/250 KVp
22. Normal voltage 25 KV
23. Permissible variation 19KV -27.5 KV
24. Type of Locomotive Conventional/ regenerative
![Page 30: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/30.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 30 of 64
SIGNAL AND TELECOMMUNICATION
SN ITEM PARAMETERS
1 System of Train Working Absolute Block working
2. Standard of Interlocking Standard IIR
3. Type of signalling Multi Aspect Colour Light Signalling ( MACLS )
4. Distant Single Distant
5. Type of Interlocking Electronic Interlocking / Panel Interlocking / RRI
6. Type of Operation Route setting type
7. Signal Lighting LED Lamps with LED ECRs
8. Point Operation High Thrust Point machine suitable for TWS
9. Power Supply Integrated Power Supply with LMLA batteries
10. Last Vehicle Verification By Digital Axle Counter
11. Track Circuiting DC Track Circuits /analog / digital axle counters
12. Logging of events Networked data-logger
13. Calling On signals Below Home Signals
14. Shunting With shunt signals only provided below starters
15. Type of DA Galvanized Rolled
16. Earthing Maintenance free earths
17. Communication system
OFC, quad cable and radio frequancy communication in both station
18. Emergency communication EC sockets at not less than one Km and at LC gates
6.1 OTHER CRITERIA
The other technical criteria adopted for the alignment design are as follows:
• The range of gradient for study has been increased from 1 in 80 (Reference Railway board
letter No- 2004/W1/RVNL/15 Pt-I Dated 22.08.2013) to 1 in 170 (Reference WCR-JBP/T-
![Page 31: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/31.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 31 of 64
1249 Dated 08-11-2013).
• Attempts have been made to strike a balance between curvature and disturbance to wildlife
sanctuary. The speed potential of the alignment shall be dependent on the curvatures.
• Stipulation of a gradient of 1 in 400 in station yard has been kept in mind except where
existing station have been used as block stations.
• Formation width has been taken as 7.85m in embankments and cuttings in terms of
correction slip no 135 dated 7.05.2014 to IRPWM.
• Attempt has been made to keep the maximum length of the line between two stations
(block length) between 8 to 10 kms;
• Minimization of the height of the bridges;
• Wherever possible, tunnel longer than 3km should be avoided, In case, tunnel longer than
3km is unavoidable, the possibility of having construction adits to shorten construction time
and for safety reasons should be evaluated;
• Minimization of the stretches of line running on the contour slope of the mountains, due to
slope instability risk.
6.2 CRITERIA OF SELECTION
The different single stretches will be compared in terms of:
• Stability and geological aspects (as per available information to date);
• Accessibility;
• Constructability;
• Maintainability;
• Safety;
• Environmental considerations;
• Costs (based on tunnel length, bridges etc).
The favourable solution will be the sum of the single stretches.
6.3 DESIGN CODES AND STANDARDS
The codes and publications referred to for the design of the alignment have been enlisted in Section 10
![Page 32: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/32.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 32 of 64
7 DEVELOPMENT OF DIFFERENT VIABLE ALIGNMENT OPTIONS
7.1 DESCRIPTION OF ALIGNMENTS
7.1.1 ALT-1: West side and Detour with ruling gradient of 1 in 170:
The Alignment option Alt-1 lies to the west of the existing DOWN line and envisages the use of the
third line as the new 3rd line and the existing Down line as a bi-directional line. This option is the
lengthiest option amongst all the three alternatives and provides a ruling gradient of 1 in 170, thus
avoiding the use of double locomotive for hauling the Goods train uphill towards Barkhera. It
departs from the existing alignment after the Budni station, traversing through the forest and having
a substantial portion passing through Ratapani Wildlife Reserve away from the existing
infrastructure. The avoidance of encroachment into vergin forest area of Ratapani Reserve is
highly desirable as this would not only benefit the ecology but also reduce the additional efforts,
costs and time needed for the approval process and during construction. The encroachment into
the undisturbed area also necessitates the construction of intensive network of approach roads for
construction, further increasing the disturbance to the ecology and costs.
The alignment takes off from Budni station and turns left navigating a sharp 4 degree (approx)
curve which is unavoidable due to the sudden rise in topography after the Budni station. The
design speed in this curve is restricted to 90 and remaining alignment has potatial of 110kmph.
The alignment reaches the proposed NS1, passing besides the Talpura Lake. The Talpura Lake is
also another ecologically sensitive zone and efforts will be needed during construction to reduce
the impact of activities on the ecology. The alignment passes through a tunnel before reaching the
proposed New Station 1. The gradient in the station yard for NS-1 is 1 in 400.
After the Proposed NS-1 the alignment passes near the Yaar nagar village to reach proposed NS-
2. In this section between NS-1 & NS-2 the alignment passes over 3 major bridges and three
tunnels (one long tunnel of length 3 km). The gradient in the station yard for NS-2 is proposed as 1
in 400.
The block section between NS-2 and Barkhera station includes one bridge and three tunnels. The
alignment maintains a ruling gradient of 1 in 175 (compensated) and maximum Degree of curve of
2.18 degrees for this block section.
7.1.2 ALT-2: West side and Detour with ruling gradient of 1 in 125:
Alignment option Alt-2 is take off from Budni station and turn left, passing between the Talpura
Lake & Vardhaman factory and reach proposed NS1. The ruling gradient for this section is 1 in
213 and maximum Degree of curvature is 1.2 degrees. This alignment have 1 new station, and
after that it is passing near the Yaar nagar village reaches existing Choka station. The ruling
gradient is 1 in 130 and and the maximum Degree of curvature is 1.2 degrees. The next block
Connects the Choka and Barkhera stations. This section is designed for a ruling gradient of 1 in
125 (Compensated) and a maximum Degree of curvature of 4 deg. This section can be refined
![Page 33: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/33.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 33 of 64
further with a reduced degree of curvature (approx. 1.2 degrees) but in such a case will involve
some additional tunnels (approx additional tunnel length of less than 1 km). This alignment would
also need to traverse through virgin forests inside the Ratapani Wildlife Reserve Forest between
the New Station-1 and Choka station and after choka station it is running parallal to the existing
track. Howerver it is less (but not least) distrub the wildlife as compare to Alt-1.
The alignment take off from Budni station and turn left, passing between the Talpura Lake &
Vardhaman factory and reach proposed NS1. The ruling gradient for this section is 1 in 213 and
maximum Degree of curvature is 1.2 degrees (except the Budni curve which is 4 deg and is
mandatory for all alignment options that do not follow the existing UP line).
The next block section starts from the Proposed New station 1 and passing near the Yaar nagar
village reaches existing Choka station. The ruling gradient is 1 in 130 and and the maximum
Degree of curvature is 1.2 degrees (except just before the Choka station which is 3.5 deg – the
speed at this location is reduced to 98.28 KMPH )
This block Connects the Choka and Barkhera stations. This section is designed for a ruling
gradient of 1 in 125 (Compensated) and a maximum Degree of curvature of 4 deg. This section
can be refined further with a reduced degree of curvature (approx. 1.2 degrees) but in such a case
will involve some additional tunnels (approx additional tunnel length of less than 1 km).
7.1.3 ALT-3: DN track side with ruling gradient of 1 in 125:
This Alignment Alt-3 follows the existing Down track and travels just west of the existing track. This
option envisages the use of the new 3rd line as the new Down track and the existing Down track as
a bi-directional track. The traffic going uphill from Budni to Barkhera will have to negotiate a
gradient of 1 in 125 and Goods traffic will need a double locomotive for hauling. The alignment is
divided into three blocks and utilises the existing stations of Midghat and Choka as block stations,
avoiding the need of establishing new stations. This option traverses through the Ratapani Wildlife
Reserve almost hugging the existing infrastructure, mostly in the existing Railway land and
encroaching slightly into the undisturbed zone. The alignment consists of six tunnels with a total
length of 1705m and Eight major bridges with total length of around 820m
The alignment leaves Budni besides the Down track and navigates a sharp 4 degree (approx)
curve which is unavoidable due to the sudden rise in topography after the Budni station. Following
this, the alignment stays along the existing Down track at a slightly higher elevation and forms a
bulb over the existing bulb with a 3.5 degree curve. This bulb section includes one tunnel of length
1080m (approx) and high embankment. The design speed in this curve is limited to 95 kmph for a
length of 1751 m (approx). The alignment manages to achieve a gradient of 1 in 125
(compensated) up to Midghat station due to the increase in length in the bulb section. The bulb
section is a critical area for the design as construction of the line at this location would necessitate
construction of a tunnel. Provision of IBH is also possible in this section between KM 6.000 and KM
![Page 34: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/34.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of
Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015 Page 34 of 64
8.113 (2113 m) with a gradient of 1 in 200. The station yard at Midghat is proposed at a gradient of
1 in 125. The gradient in Midghat station is 1 in 125.
After Midghat, the alignment follows the existing Down track as much as possible within the
restrictions of design criterion. The alignment has a gradient of 1 in 380 (compensated) between
the two stations and has 4 degree curves which limit the design speed to 90 kmph in a length of
1287 m (approx). The station yard at Choka is at a gradient of 1 in 125 due to topography. The
existing station yard at Choka also has a steep gradient of about 1 in 125.
After Choka, the alignment keeps along the existing DOWN line up to Barkhera with a ruling
gradient of 1 in 125 (compensated. One tunnel is proposed in this section with a total length of 540
m and four bridges with a total length of 135 m (max 80m length). The Steepest gradient in this
block section is 1 in 125.
![Page 35: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/35.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central Railway in the State of Madhya Pradesh, India.
Alignment Design Report Stage I – Rev-4
- Project Nr. 01025 - March, 2015 Page 35 of 64
Figure 7.1: General scheme of the studied connectio ns among different station locations check location .
![Page 36: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/36.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
7.1.4 Discussion on Critical Aspects
Some of the most critical areas related to the design of the alignment options have been
presented below. Please note that all these comments are basically related to the evidences
obtained during the various field visits performed by the experts.
7.1.4.1 Tunnel section near Midghat station (Alt-3)
Near to Midghat station, on the existing Down line, the overburden over the tunnel is low and
the slope above the existing tunnel seems to be unstable. The alignment Alt-3 must pass
through a tunnel running almost parallel to the hill slope and adjacent to an existing tunnel
which is not favourable, especially if the tunnel is driven through the colluvium material as
seen above and around the existing portal. Special measures will be required for the slope
protection/stability and tunnelling. Controlled blasting will most likely be required to minimize
overbreaks and to control disturbance in the existing tunnel.
Photo-7.1: MIG Station, Close view of the overburde n material above the existing tunnel
7.1.4.2 Choka Station (Alt-3 &2 )
At the Choka station, existing up and down lines are at different elevations (about 7m difference in height with the down line being lower). Alt-3 proposes running the new line next to the down line along the existing river. There are two options for the construction of 3rd line track at Choka station on ALT-3 (Photo 7.6 & 7.7):
• One is to make a viaduct and run along the river bank .This situation is not very desirable since the entire via duct will be running parallel to the river. We would need to design the skew piers for the continuation of the river flow.
• Other option is to propose construction of a retaining wall (below the existing retaining wall) and retain the hill slope. This would facilitate the construction of another line just parallel to the existing DN track.
Construction of the abutment next to the vertical slope will present some problems since
Proposed
Alt3
![Page 37: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/37.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
measures will have to be taken to prevent rock falls from above. River rehabilitation works will also be required that will have to be evaluated from environmental and hydrological point of view. This area will have to be studied in detail in the next phase.
Photo-7.6: Choka Station Existing 2 lines, BKA to B NI on the left and BNI to BKA on the right about 7 to 10 m below (looking towards Budni) .
Photo 7.7: Choka station Existing 2 lines, BNI to B KA on the left and BKA to BNI on the
right (looking towards Barkhera)
BKA to BNI
Up Line
BNI to BKA
Down Line
River bed below
BKA to BNI
UP Line
BKA to BNI
UP Line
BNI to BKA
Down Line
Proposed
Alt3
![Page 38: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/38.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
Photo 7.8: Choka station Existing DN lines, BNI to BKA new line ALT-3 next to the DN line
near Choka station
Also Alt-1 proposes running the new lines next to the up line. This would need the extension of the present embankment to increase its width at the top for accommodating the new line.
Photo 7.9: Photo showing proposed new line Alt-1 next to the up line near Choka station
7.1.4.3 Bulb section near Budni station
After take off from Budni station the existing Dn track negotiates a bulb section where the alignment is rotated at 360 Degrees with a 4 Degree curve. There is one tunnel along the existing track at this location. ALT-3 alignment, proposes a new line just besides the existing line. This option increases the risk of disturbance in the service on the existing down line due to construction work being carried out for the 3rd line track but the risk can be managed.
BNI to BKA
Down Line
Proposed
Alt3
BKA to BNI
UP Line
![Page 39: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/39.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
Also, filling of up to 15-25m or a viaduct might be required in this location followed by tunnels or deep cutting/false tunnel near the existing tunnel in the bulb.
Photo 7.5: Photo showing the Bulb section just afte r Budni station.
7.1.5 Discussion on the alternatives and preliminary assessment
The key aspects of the three alignment alternatives studied in this report are presented in Table 7.2 below. These figures present a parametric comparison of the alignment solutions.
Table 7.1: Key aspects and comparison of alignments
Sl.
No Description
ALT-1
Detour away
from DN track
ALT-2
Detour + Dn
SIDE
ALT-3
Close to DN
track
1 TOTAL LENGTH 37500 32900 26200
2 Station
Budni Yes Yes Yes
Midghat No No Yes
Choka No No Yes
Barkhera Yes Yes Yes
3 Grade
Steepest Grade 1 in 175 1 in 125 1 in 125
Number of sections with Steepest
Grade 6 2 11
Total length of steepest grade(M) 5706.84 2997.71 7777
Max length of steepest grade(M) 1804.92 1919.21 1977
4 Degree of curve
Sharper Than 4 (Deg) 0 0 0
![Page 40: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/40.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
Sl.
No Description
ALT-1
Detour away
from DN track
ALT-2
Detour + Dn
SIDE
ALT-3
Close to DN
track
Sharpest curve(Deg) 2.2 3.5 4
Total No of curve 16 20 27
Total length in curve(M) 22662 15650 14631
Length in curve(M) at sharpest
Degree 877 2034.27 2509
5 Tunnels
No of tunnel 8 5 5
Total length in Tunnel(M) 6715 4215 2150
Length of longest Tunnel(M) 2845 3245 1080
Sharpest Curve in tunnel(Deg) 1.2 3.5 3.5
Steepest grade in tunnel 1 in 175 1 in 125 1 in 125
6 Cuttings
Cutting Length(M) 4680 5300 7764
Sharpest Curve in cutting (deg) 2.2 3.5 4
Steepest grade in cutting 1 in 175 1 in 125 1 in 125
7 Embankment
Filling Length (M) 11545 2500 7479
Sharpest Curve in Filling 2.2 3.5 4
Steepest grade in Filling 1 in 175 1 in 25 1 in 125
8 Major Bridges
Bridge total length (M) 2025 1020 275
No of Major Bridge 9 8 6
Longest bridge (M) 670 150 80
9 Ratapani Wildlife Reserve
Length in Core area (M) 12900 9280 9155
Length in Buffer area (M) 24600 23620 17045
In general, the following statements are possible:
1. To minimise the disturbance in the Ratapani Wildlife Reserve, efforts should be made to minimise the length of alignment inside the Reserve. Where necessary, the alignments should be designed near to the existing Railway tracks so that disturbance to the undisturbed area of the Reserve is avoided (Ref. Figure 4.5).
2. In general, the geology of the area is not varying and is thus favourable for tunnelling operations. Some difficulties are anticipated during the construction of tunnels however this can be effectively tackled by proper design and planning. Locations of portals, however, are critical and at some locations might present problems. These can be dealt with specialised solutions for the portal area.
![Page 41: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/41.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
3. WCR has specified a gradient of at least 1 in 125 or milder for movement of trains in uphill direction (Down line). The provision of 3rd track besides the existing Down line enables the existing Down track to function as bi-directional line thus ensuring a gradient of 1 in 125 for all trains climbing uphill.
In the following table a qualitative comparison of the pro&con of various alignment options is performed:
Table 7.2: Qualitative Assessment of the various al ignment solutions
TECHNICAL
ITEM Alternate 1 Alternate 2 Alternate 3
Construction
aspect
A Large part of the
alignment between
Barkhera and Budni is not
easily accessible.
Extensive network of
access roads will be
required during the
construction for access to
the site.
Existing forest road can
be used on tamporary
basis during construction
phases.
A Large part of the
alignment between
Choka and Budni is not
easily accesible.
Existing forest road can
be used on tamporary
basis during construction
phases.
All the locations are
relatively accessible
however since the
existing track is between
this alignment and NH 69,
there will be limited
crossing points.
The aspect of
construction work for the
3rd line disturbing the
service on existing track
needs to be studied due
to proximity to existing
track but is manageable.
Existing forest road can
be used on tamporary
basis during construction
phases.
Operation The option provides for a
gradient of 1 in 175 for
the uphill travel and
would dispense with the
need of double
locomotive.
There will be an
additional requirement of
two new block stations
The gradient of 1 in 125
and max.
One new station will be
needed increasing the
operating cost.
The gradient of 1 in 125
for uphill travel from
Budni to Barkhera will
require double locomotive
in case of Goods trains.
There is no need for new
stations which would
reduce operating costs.
![Page 42: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/42.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
TECHNICAL
ITEM Alternate 1 Alternate 2 Alternate 3
adding to the operating
costs.
Environment and
social impact
The alignment passes
through Wildlife Reserve
and Forest in most of its
length away from the
existing infrastructure
thus causing the most
disturbances to Ratapani
Wildlife sanctuary.
The alignment passes
through forest buts hugs
the existing alignment
after entering Ratapani
sanctuary thus causing
less disturbance.
Alignment hugs the
existing railway track but
lies just beside the
existing infrastructure and
mostly within the existing
Railway Land. Thus
causing least disturbance
to Ratapani Wildlife
Sanctuary.
Costs Highest cost option Intermediate cost option Lowest cost option
Existing railway
land.
This option requires
extensive land
acquisition/diversion
inside the Ratapani
Wildlife Reserve Forest
and would involve
additional costs on
account of this.
This option requires
extensive land
acquisition/diversion
inside the Ratapani
Wildlife Reserve Forest
and would involve
additional costs on
account of this.
The option remains
mostly within the existing
Railway land boundary
minimizing the need for
land acquisition/diversion.
![Page 43: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/43.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
8 PRELIMINARY COST ESTIMATE
As a factor considered very important in the evaluation of the best alignment, the cost plays
a crucial role.
A parametric cost study has been performed starting from the database available by GD in
its experiences in the Himalayan projects. These costs are only related to civil works and
have to be considered as indicative.
8.1 TUNNELS
For tunnels, the following support and functional sections have been referred:
• Main tunnel – Price reference is made to the Tender documents of T74R tunnel in
J&K USBRL Project;
• Escape tunnel – Price reference is made to the Tender documents of T74R tunnel in
J&K USBRL Project;
• Construction and safety and only safety tunnels – Price reference is made to the
Tender documents of T74R tunnel in J&K USBRL Project;
• Cross passages – Price reference is made to the Tender documents of T74R tunnel
in J&K USBRL Project;
As described in the Approach & Methodology report, the selection of the possible layout is
based on the requirements for operational safety. The safety standard commonly adopted in
all the big Indian Railway projects (for example USBRL and Sivok-Rangpo) is the UIC779-
9R “Safety in Railway Tunnels”. According to this standard, for a single track railway line, the
flowing possible layouts are available:
• Solution “A” - Single tube - single track tunnel including pedestrian escape way;
• Solution “B” - Single tube - single track tunnel including motorable escape way;
• Solution “C” - Single tube - single track tunnel including pedestrian escape way with
safety parallel escape tunnel;
• Solution “D” - Double tube-single track tunnels including pedestrian escape way;
The typical plan schematic view and the typical cross sections are reported below.
![Page 44: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/44.jpg)
Table
SCHEME OF TUNNEL LAYOUT
Sol
utio
n A
S
olut
ion
B
Sol
utio
n C
Figure 8.1: – Solution A –
Figure 8.2: Solution B – Single track
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl)Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment
Table 8.1: Possible Tunnel layouts
OF TUNNEL LAYOUT Description
Single-tube
Single-track
Single-tube
Single track along with a
rescue/maintenance motorable way
this cross
Single-tube
Single-track and separate motorable pathway (escape
tunnel)
Single track – single tube with pedestrian escape way.
Single track – single tube with motorable escape way.
iled Design Engineering in connection with Electrified 3rd Line of (excl) KM 770.040 (33KMs)
Itarsi route of Bhopal Division of West Central Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
Note
Solution adopted for T80 along the same railway line (no examples of
this cross-section are available in
Europe)
Solution adopted for T74R along
the same railway line Minimum
requirements as per safety standards
single tube with pedestrian escape way.
single tube with motorable escape way.
![Page 45: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/45.jpg)
Figure 8.3 : Solution C
For the preliminary comparison
tunnels has been detailed below
cost in all types of geological conditions. Since this is a preliminary cost computation
exercise, for the determination of
for the exact cost computation has not been employed.
Table 8.2: proposed tunnel layout
Tunnel length
L < 3km Solution A with one adit (or solution B with no
3km < L < 10km
8.2 CUTTINGS & EMBANKMENTS
For embankment, reference has been made to a typological height of 15m as per sketched
attached hereby.
Figure
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl)Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment
: Solution C – Single track – with parallel escape way.
comparison of proposed alignments based on cost, the unit cost for
tunnels has been detailed below in Table 8.2. The cost has been considered as an average
all types of geological conditions. Since this is a preliminary cost computation
of relative suitability of various alignments, a detailed analysis
for the exact cost computation has not been employed.
: proposed tunnel layout
Proposed solution Cost
Solution A with one adit (or solution B with no
adit)
100 Crores per km
Solution C 115 Crores per km
BANKMENTS
bankment, reference has been made to a typological height of 15m as per sketched
Figure 8.4: Embankment typical layout
iled Design Engineering in connection with Electrified 3rd Line of (excl) KM 770.040 (33KMs)
Itarsi route of Bhopal Division of West Central Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
on cost, the unit cost for
in Table 8.2. The cost has been considered as an average
all types of geological conditions. Since this is a preliminary cost computation
various alignments, a detailed analysis
Cost
Crores per km
Crores per km
bankment, reference has been made to a typological height of 15m as per sketched
![Page 46: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/46.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
The estimate is reported hereby:
Table 8.3: Embankments - cost estimate per meter
APPLICATION FIELD / (HEIGHT) 0-15m
SINGLE RAIL Rs 2,90,000
In case the stations located on embankment, a factor 5 is applied to the cost per meter.
For the cuttings, considering the problems related to instability of the slopes exposed after
cutting, the cost is related to the maximum cutting height. A considerable increase is taken in
case of stations (due to the width of the stations and to the problems that may arise in the
transversal-directions).
Figure 8.5: Cutting typical layout
Table 8.4: Cuttings - cost estimate per meter
APPLICATION FIELD / (HEIGHT) 0-5m 5-15m
SINGLE RAIL Rs 85,000 Rs 2,20,000
STATION Rs 13,00,000 Rs 29,25,000
8.3 BRIDGES
For the cost estimation of the bridges 3 different bridge typologies have been identified partly
in accordance with Indian Railway Bridge manual:
• Major bridge length< 300m;
• Important bridge length>300m;
In the following table, the used unit costs are reported.
![Page 47: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/47.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
Table 8.5: unit costs of each bridge typology
BRIDGE
Type Class of Bridge
Length / Height [m] Cost per meter
[Rs]
Reference
1 Major Bridge L < 300m 1,000,000
NFR Rangpo-Gangtok
2 Important
Bridge L >300m 1,200,000.
J&K alignment studies
8.4 APPROACH ROADS CHECK
Accessibility and also maintenance of the approach roads is a factor in this project. At this
stage for each alignment solution the rough length of approach roads are estimated
considering the location of portals and the distance from portals to approach roads multiplied
by a factor 2. The calculated length for each alignment solution is than multiplied by Rs
50,000 per meter to get the overall cost of the approach roads of the area.
8.5 SETTLEMENT
Settlement costs have been neglected as the existing infrastructure at stations are being
used for two of the three alignments and disturbance to the existing infrastructure will be
avoided as far as possible. In Alt-1, where two new stations are proposed, the block stations
will have minimum facilities and will not be used as passenger stations.
8.6 COST OF ALIGNMENT OPTIONS
The cost calculation for the alignments considered in the comparative study is presented in
Table 8.7 .
Table 8.6: Breakup of alignment options
S/No. Alignment
Typical Track
Section Length
Length on Embankment
Length in
Cutting
Length in
tunnel
Length on
Bridge Total
m m m m m m
1 Alt-1 12535 11545 4680 6715 2025 37500
2 Alt-2 19865 2500 5300 4215 1020 32900
3 Alt-3 8532 7479 7764 2150 275 26200
![Page 48: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/48.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
Table 8.7: Cost of alignment options
S/No. Alignment
Cost of Typical Track
Section
Cost for Section on
Embankment
Cost for
Section in
Cutting
Cost for Section
in Tunnel
Cost for
Section on
Bridge Total Cost
Rs (Crores)
Rs (Crores) Rs (Crores)
Rs (Crores)
Rs (Crores)
Rs (Crores)
Price per meter length (Rs) 90000 285000 220000 1100000 100000
Per Block
1 Alt-1 112.815 329.0325 102.96 738.65 20.25 1303.708
2 Alt-2 178.79 71.25 116.60 463.65 10.20 840.49
3 Alt-3 76.79 213.15 170.81 236.50 2.75 700.00
![Page 49: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/49.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
9 CONCLUSIONS
The Alignment study has been performed in order to select the most preferable alignment for
further detailed study.
This study has led to the creation of several alternative alignments and based on the site
visits, a number of viable options have been studied in close relationship with the client -
RVNL.
The study has been performed in accordance with the methodology proposed in the
Approach & Methodology report and after the finalization of the possible station locations,
series of possible connections among the stations have been evaluated (for a total length of
studied alignment that is approx.146km).
The feasibility of the proposed alignments has been evaluated during visits of the GD
technical experts and finally after detailed comparison, the preferred alignment from the
viewpoint of constructability, functionality, operational efficiency, geology, environment and
cost has been identified.
9.1 SUMMARY
WCR has expressed a desire for a minimum gradient of 1 in 125 based on the criteria of
operational efficiency and maintenance issues. This necessitates the alignment to be on the
west of the currently operating Down line and since minimum disturbance to the wildlife is a
very important criterion, the new alignment has to be as close as possible to the existing
lines.
Alignment option ALT-3 is hugging the existing operational Down line (to minimise the
encroachment into the Wildlife Reserve) with a ruling gradient of around 1 in 125
compancated and has been found to be the most beneficial in economic & operational
terms. The Alignment option Alt-3 takes off from Budni station and turns left with a 4 Degree
curve which is unavoidable. This restricts the speed of the train to 90 kmph at the takeoff
location. The alignment has several sharp curves which are unavoidable due to constraints
of topography and presence of Wildlife reserve thus limiting the speed to around 90 kmph at
various locations at the curves. The whole alignment is, however, designed for a ruling
gradient of 1 in 125.
In view of the above discussion, Alt-3 has been recommended for further studies.
9.2 TECHNICAL DATA ABOUT THE SELECTED ALIGNMENT
The list of stations for the alignment Alt-3 is presented below:
1. Budni
![Page 50: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/50.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
2. Midghat
3. Choka
4. Barkhera
The key features of the examined possible connections are shown below:
Table 9.1: Key aspects of the selected alignment be tween Budni and Barkhera
Sl.
No Description
ALT-3
Close to DN track
1 TOTAL LENGTH 26200
2 Station
Budni Yes
Midghat Yes
Choka Yes
Barkhera Yes
3 Grade
Steepest Grade 1 in 125
Number of sections with Steepest Grade 11
Total length of steepest grade(M) 7777
Max length of steepest grade(M) 1977
4 Degree of curve
Sharper Than 4 (Deg) 0
Sharpest curve(Deg) 4
Total No of curve 27
Total length in curve(M) 14631
Length in curve(M) at sharpest Degree 2509
5 Tunnels
No of tunnel 5
Total length in Tunnel(M) 2150
Length of longest Tunnel(M) 1080
Sharpest Curve in tunnel(Deg) 3.5
Steepest grade in tunnel 1 in 125
6 Cuttings
Cutting Length(M) 7764
Sharpest Curve in cutting (deg) 4
Steepest grade in cutting 1 in 125
7 Embankment
Filling Length (M) 7479
Sharpest Curve in Filling 4
Steepest grade in Filling 1 in 125
![Page 51: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/51.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
Sl.
No Description
ALT-3
Close to DN track
8 Major Bridges
Bridge total length (M) 275
No of Major Bridge 6
Longest bridge (M) 80
9 Ratapani Wildlife Reserve
Length in Core area (M) 9155
Length in Buffer area (M) 17045
![Page 52: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/52.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
10 REFERENCE
10.1 DESIGN CODES AND STANDARDS
1. GSI map (1:50000) – 55F/9
2. IS: 14680 - 1999, Landslide Control Guidelines
3. IS: 3764 -1966 - Safety Code for Excavation work.
4. IS: 4081-1967- Safety Code for Blasting and Related drilling operations.
5. IS: 4138 -1977- Safety Code for Working on Compressed Air
6. IS: 4756 - 1978, Safety Code for Tunnelling Work, 2nd Reprint May 1992, Reaffirmed 1996
7. IS: 5878 (Part I) – 1971 (Reaffirmed 1995), Code of practice for Construction of Tunnels , Part I - Precision Survey and setting out
8. IS: 5878 (Parts II-VII) - 1971 (Reaffirmed 1995), Code of practice for Construction of Tunnels , Underground Excavation, Supports and Lining
9. IS: 7293-1974- Safety Code for Working with construction Machinery.
10. Indian Explosive Act-1988
11. Indian Explosive Rules –1983
12. IS: 1200 (Part-XXV) 1971- Methods of Measurement of Building and Civil Engineering works.
13. IS: 1256-1967- Codes of Practice for Building Bylaws (First Revision)
14. IS: 1905-1980-Code of Practice for Structural safety of Buildings, Masonry walls.
15. Manual of Standards & Spec’s for Railway Stations, June 2009 – Gov’t of India, Ministry of Railway (Railway Board)
16. IS: 14458 (parts I-III) – 1998, Retaining Walls for Hill Area – Guidelines
17. Indian Railway Bridge Manual, 1998 – Gov’t of India, Ministry of Railway (Railway Board)
18. Indian Railway Works Manual, 2000 – Gov’t of India, Ministry of Railway (Railway Board)
![Page 53: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/53.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
19. Code of Practice for the Design of Sub-Structures and Foundations for Bridges (Bridge Sub-Structures & Foundation Code) – Gov’t of India, Ministry of Railway (Railway Board) Incorporating A & C Slip No 22, year 2003
20. Standard Railway Bridges, RDSO – Research Designs & Standards Organization (Ministry of Railways), Lucknow
21. IITK-RDSO Guidelines on Seismic Design of Railway Bridges, Indian Institute of Technology, Kanpur
22. RDSO - Code of Practice for Metal Arc Welding in Structural Steel Bridges Carrying Rail-Cum-Road or Pedestrian Traffic (Welded Bridge Code), Adopted 1972, Incorporating A & C Slip No 2, year 1989
23. Specifications for Road and Bridge Works (Parts 1 & 2), Nov. 2000 – MORTH – Ministry of Road Transport and Highways
24. Standard Spec’s and Code of Standard Practice for Road Bridges, IRC 1998 (Indian Roads Congress)
25. IS: 1893 (Part 1) – 2002, Criteria for Earthquake resistant design of structures, 5th Revision.
26. IS: 4386 - 1993 (Reaffirmed 2003), Earthquake Resistant Design and Construction of Buildings – Code of Practice, 2nd Revision
27. IS: 456-2000 – Plain and Reinforced Concrete. - Code of Practice (Fourth Revision)
28. IS: 875 (Parts 1-5) – 1987 (Reaffirmed 1997-2003), Code of Practice for Design Loads (Other than Earthquake loads) for Buildings and Structures
29. IS: 1443 – 1980 (Reaffirmed 1990), Code of Practice for Prestressed Concrete (First Revision)
30. IS: 9012 recommended practice for shotcreting.
31. IS: 9103-1979- Admixtures for Concrete.
32. IS: 458-1971-Concete pipes (with and without reinforcement).
33. IS: 800 - 2007, General Construction in Steel – Code of Practice (Third Revision)
34. IS: 816 – 1969, Code of practice for use of Metal Arc welding for General Construction in Mild steel.
35. IS: 823-1964- Code of procedure for manual metal Arc welding of mild steel.
![Page 54: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/54.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
36. IS: 961-1975 Indian Standard Specifications for Structural Steel (High tensile) revised SR-58-HTC grade with copper content of 0.2 to 0.35 per cent will be used for the High Tensile steel items.
37. IS: 1367-1967 for Mild Steel bolts and nuts;
38. IS: 1566-1967-Hard Drawn steel wise fabric for Concrete reinforcement.
39. IS: 2062-1992, Steel for General Structural Purpose, (6th Revision)
40. Code of Practice for Laying of Cables etc. for Electrical & S&T works
10.2 OTHER INTERNATIONAL TECHNICAL DOCUMENTS
In order to take into account the experiences related to different case histories or recent research results, especially, in the tunnelling sector, the technical documents mentioned below may be also considered for the design.
1. AFTES: "Temporary supports and permanent lining - Considerations on the usual methods of tunnel lining design" - Working Group n. 7 – 1993.
2. ASTM (1987). Commission on Testing Methods - Suggested methods for deformability determination using a flexible dilatometer. Int. J. Rock Mech. Min. Sci. and Geomech. Abstract, vol. XXIV, n. 2.
3. Bathe, K. J & Wilson E. L.1976. Roclin Programmi di calcolo per la generazione e l’analisi dei rivestimenti di gallerie tenendo conto del fenomeno di interazione.
4. Bieniawski, Z.T. 1989. Engineering Rock Mass Classification. John Wiley & Sons. New York. 251 pp.
5. Boresi A.P., R.J. Schmidt, O.M. Sidebottom. Advanced Mechanics of Materials - 5th Edition. John Wiley&Sons, New York, USA, 1993.
6. Bowles. J. E. 1982. Foundation analysis and design. McGraw-Hill.
7. Brown E.T., Bray J.W., Ladanyi B. and Hoek E., 1983. Ground Response Curves for Rock Tunnels. J. Geotech. Engng. Div., ASCE, Vol. 109, pp. 15-39.
8. Carranza-Torres, C. & Fairhurst, C. 2000. Application of convergence-confinement method of tunnel design to rock masses that satisfy the Hoek-Brown failure criterion. Tunnelling and Underground Space Technology; 15: 187-213.
9. Carranza-Torres, C.2004. Elasto-plastic solution of tunnel problems using the generalized form of the Hoek-Brown failure criterion. Int J Rock Mech Min Sci. 4: supplement 1, 629-639.
10. Duddeck, H., Erdmann, J. 1982. Structural design models for tunnels. Tunnelling ‘82, Proc. 3rd Int. Symp. Institution of Mining and Metallurgy, pp.83-91.
11. Harr M.E. 1987. Reliability-based design in civil engineering. McGraw-Hill. New York.
12. Hoek E. 2000. Practical Rock Engineering. HoekCorner.www.rocscience.com.
13. Hoek E. and Brown E.T., 1980. Underground Excavations in Rock. The Institution of Mining and Metallurgy, London, 527 p.
14. Hoek E., and E.T. Brown. Underground Excavations in Rock. Institution of Mining
![Page 55: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/55.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
and Metallurgy, London, UK, 1980.
15. Hoek E., Kaiser P.K. and Bawden W.F., 1995. Support of Underground Excavations in Hard Rock. Balkema, Rotterdam, 215pp.
16. Hoek E., and Brown E.T., 1997. Practical estimates of rock mass strength. Submitted for publication to the Int. J. Rock Mech. Min. Sc.& Geomech. Abstr.
17. Jaky, J. 1944. The coefficient of earth pressure at rest. J. Soc. Hung. Arch. Eng., Budapest, pp.355-358.
18. Jaw-Nan Wang, Ph.D., Seismic design of tunnel – A simple state of the art design approach; P.E. Professional Associate Parson Brinckerhoff Quade & Douglas, Inc. June 1993.
19. Kalamaras, G.S., Xu, S. Russo, G. and Grasso, P. 1999, “Estimating the reliability of the primary support for a given tunnel section,” Proc. 37th US Rock Mechanics Symposium, Vail Rocks, Vail, Colorado, USA.
20. Kavvadas, M. 2004.Computational methods in the design of tunnels. Department of civil engineering. National Technical University of Athens. 255 pp. (In Greek).
21. Lembo Fazio A., R. Ribacchi. Il calcestruzzo proiettato come elemento strutturale nell’esecuzione degli scavi in sotterraneo. In Proc. Giornata di Studio “Il Calcestruzzo Proiettato (SpritzBeton-Gunite): Impiego e Tecnologie”, Società Italiana Gallerie, Milan, Italy, 1994, pp.4-33.
22. Oreste. P. P.2003. Analysis of structural interaction in tunnels using the convergence–confinement approach. Tunnelling and Underground Space Technology; 18: 347-36.
23. Panet, M. 2001. Recommendations on the convergence-confinement method, Association Francese des Travaux en Souterrain (AFTES).
24. Petrangeli Mario P., Progettazione e costruzione di ponti, 1993, ESA.
25. Pottler R.. Time-dependent rock-shotcrete interaction. A numerical shortcut. Computer and Geotechnics, 1990, Vol. 9, pp. 29-49.
26. Potts, D.M., and Addenbrooke T.I., (1997). “ A structure’s influence on tunnelling induced ground movements”. Proceedings of the Institution of Civil Engineers, Geotechnical Engineering, 125:109–125.
27. Rabcewicz, L.V. The New Austrian Tunnelling Method. Water Power, Part 1, November 1964, pp. 511-515, Part 2. 1195-1197. 1964 & 1965.
28. Ribacchi R., R. Riccioni, R. Stato di sforzo e di deformazione intorno ad una galleria circolare. Gallerie e Grandi Opere Sotterranee, Vol. 5, 1977, pp. 7-20.
29. Rowe, R.K., and Kack G.J., (1983). “A theoretical examination of the settlements induced by tunnelling: four case histories”. Canadian Geotechnical Journal, 20: 299–314.
30. Russo G., Kalamaras G.S. and Grasso P., 1998. A discussion on the concepts of geomechanical classes, behavior categories and technical classes for an underground project. Gallerie e grandi opere sotterranee, N.54, pp.40-51.
31. Russo, G., Kalamaras, G.S., Xu, S., and Grasso, P. 1999. Reliability analysis of tunnel support systems. Proc. 9th International Congress on Rock Mechanics, Paris.
32. Russo G. & Grasso P. 2006. Un aggiornamento sul tema della classificazione
![Page 56: Railway in the State of Madhya Pradesh, India.€¦ · Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.04](https://reader033.fdocuments.us/reader033/viewer/2022050506/5f97cff78e1118426f3e7f20/html5/thumbnails/56.jpg)
Detailed Design Engineering in connection with Electrified 3rd Line of Barkhera (excl) KM 789.430 – Budni (excl) KM 770.040 (33KMs) Project on Bhopal-Itarsi route of Bhopal Division of West Central
Railway in the State of Madhya Pradesh, India.
Alignment Report Wlc – Rev-4
- Project Nr. 01025 - March 2015
geomeccanica e della previsione del comportamento allo scavo. Gallerie e grandi opere sotterranee, N.80, pp.56-65.
33. Russo, G. & Grasso, P. 2007. On the classification of rock mass excavation behaviour in tunneling ". 11th Congress of International Society of Rock Mechanics ISRM, Lisbon.
34. Swoboda G. and Dioda G., (1999). “Developments and applications of the numerical analysis of tunnels in continuous media”, Internation Journal fro Numerical and Analytical Methods in Geomechanics, Vol 23, 1393-1405.
35. Sakurai Shunsuke (1978). “Approximate time-dependent analysis of tunnel support structure considering progress of tunnel face”, Internation Journal fro Numerical and Analytical Methods in Geomechanics, Vol 2, 159-175.
36. Ünal, E.1983. Development of design guidelines and roof control standards for coal mine roofs, Ph.D. Thesis. The Pennsylvania State University.355 pp.
37. Ünal, E. 1992. Rock reinforcement design and its application in mining. Proc. Int. Symp. Rock Support, (eds. P.K. Kaiser & D.R. McCreath). 541-546. Sudbury, Canada.
38. Youssef M.A. Hashas, Jeffrey J. Hook, Birger Schmidt, John I-Chiang Yau, Seismic design and analysis of underground structures.
39. Wanniner Rainer (1979). “New Austrian tunnelling method and finite elements”, Third International Conference on Numerical Methods in Geomechanics, Aachen.
40. (Dhingra & Chakrapani, 2004).