RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

40
RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Transcript of RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Page 1: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

RAILROAD BRIDGE AND TRACK DESIGN AND

COORDINATION ISSUESLloyd M. Wolf, P.E.

Page 2: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.
Page 3: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Coordination with Railroad

• Meet with Railroad Early in Project Development to Discuss

• Railroad Track Operations are Very Important

• Minimize Impact on RR Operations• LOA and RR Agreement

Page 4: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Structure Type Selection

andBridge Design

Page 5: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Superstructure Considerations

• Safety

–Highway Users

–Railroad

• Required Span for Horizontal Clearance

–Column Protection

• Adequate Vertical Clearance

Page 6: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Preferred Railroad Grade Separations

1. Overpass2. UPRR Steel Deck Girder Standards3. Deck Plate Girder w/ Steel Deck4. Steel Girder w/ Conc Deck5. Prestressed Beam w/ Conc Deck6. Thru-Girder w/ Steel Deck

Page 7: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

UPRR Deck Girder Standard• Depth-Top / Rail to Low Chord = 5’-5”

• Steel Deck

• 69 ft Max

Span Length

Page 8: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Thru Girder• Depth-Top / Rail to Low Chord = 4’-6”

• Steel Deck

• 155 ft Max

Span Length

Page 9: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Superstructure Considerations

• TxDOT Design Requirements

• UPRR-BNSF Design Guidelines

• KCS Design Guidelines

• Composite and Non-Composite Design

• No Sacrificial Beams

• Design for 30” Ballast

• Ballast Depth for Concrete Tie

Page 10: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Vertical Clearance

• Steel Deck Girder 16.5 ft

• Steel Thru Girder-Bolt Bot Fl 17.5 ft

• Prestressed Conc 17.5 ft

• Hwy Over RR 23.33 ft

Page 11: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Design Development and Review

Processwith Railroads

Page 12: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Railroad Underpass

• 30% Submittal - Exhibit “A”

• 60% Submittal

• 90% Submittal

• 100% PS&E Plans

RR Agreement with Exhibit “B”

Page 13: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

30% Submittal - Exhibit “A”• Preliminary:

– Bridge Layout

– Track Plan and Profile

– Track Typical Sections

• Structure Type Selection Report

– Thru Girder

• LOA Facilitate RR Review

Page 14: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Structure Type Selection Report

• Required for Thru-Girder• Design Factors Considered

–Underpassing Roadway Width–Clear Zone–Vertical Clearance

• Consider All Options for Railroad

Page 15: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

RR Requirements Sheets

Page 16: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

60% Submittal

• Complete Bridge Plans

• Complete Mainline and ShooFly Track Plans and Profiles

• Railroad Track Standards

• Mainline and ShooFly Typical Sections

Page 17: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

60% Submittal, ctd• Track Sections every 50 ft

• Division of Labor

• Sequence

of Work

Page 18: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

90% Submittal

• Revised Complete Bridge Plans

• Revised Complete Mainline and ShooFly

• Track Plans and Profiles

• Mainline & ShooFly Typ Sections

Page 19: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

90% Submittal, ctd

• Track Sections every 50 ft

• All Parts of PS&E that Affect the Railroad

• All Specifications

Page 20: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

100% Submittal• Complete PS&E That Affects RR• Complete Bridge Plans• Complete Mainline and ShooFly• Track Plans and Profiles• Mainline & ShooFly Typ Sections• Sequence and Division of Work• RR Agreement w/ Exhibit “B”

Attachment

Page 21: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Mainline Bridge Replacement

Shoo-Fly Construction

Page 22: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Track Plans & Sequence of Work

• Bridge Replacement on Mainline• Longer Span and Increased

Clearance• Track Raise• Shoo-Fly Construction Best

Maintains RR Operations

Page 23: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Track Design Speed

• Railroad Operating Dept

Determines Speed

• Mainline & ShooFly Same Speed ?

–Existing Conditions

–Future Upgrades

–Design Speed Agreement

Page 24: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Railroad Track Grade Raise

• No Grade Raise is Desirable

• 6” Max Raise with Ballast Only

• Use Subballast for Greater Raises

• ShooFly Profile Grade

• Ballast Delivery May Be an Issue

Page 25: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.
Page 26: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Bridge Designand

Track DesignResources

Page 27: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Bridge and Track Design Resources

• TxDOT and Individual Railroad• Use TxDOT Annotated Guidelines

–TxDOT Website• BRG Project Development Web Page

–BRG FTP Site• AREMA and AASHTO

Page 28: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Bridge and Track Design Resources

• UPRR, BNSF, KCS Guidelines and Standards

• Updated Requirements and Standards

TxDOT Bridge FTP Site:

–ftp://bridge:[email protected]

–Railroad Bridge and Track Design

Page 29: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.
Page 30: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Ballasted Track Construction Specification

• Bridge Division has a Reference Spec Available for Project Use

• Bridge Division is Workingto Develop StatewideSpecial Spec

Page 31: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

ThankYou

Page 32: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Lloyd M. Wolf, P.E.512-416-2279

[email protected]

Page 33: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Estimated Costs 2008

Bridgeand

Track

Page 34: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Estimated Railroad Costs 2008

Steel Deck Girder = $350 / SFwith Steel Deck

Steel Thru Girder = $450 / SFwith Steel Deck

Prestressed Beam = $225 / SFwith Concrete Deck

Page 35: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Estimated Railroad Costs 2008

ShooFly Bridge

with Open Deck =

$350,000 / EA

Temp SpecialShoring = $60 / SF

Page 36: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Estimated Railroad Costs 2008

Ballasted Track = $240 / LFwith 1 ft Raise

Ballasted Track = $170 / LFNo Raise

Ballasted Track = $45 / LFRemoval

Page 37: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Estimated Railroad Costs 2008

Turnout / Switch = $85,000 / EA

Signal for Switch = $50,000 / EA

Including Circuit

Page 38: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Estimated Railroad Costs 2008

Engineering Design Review = $100-175,000

And Construction Inspection

Railroad Flagging = $900 / Day

Page 39: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Mainline Track Raise at Turnout

Page 40: RAILROAD BRIDGE AND TRACK DESIGN AND COORDINATION ISSUES Lloyd M. Wolf, P.E.

Mainline Track Raise with Ballast Retainer