RAEC_Capability_Final.pdf
Transcript of RAEC_Capability_Final.pdf
-
7/27/2019 RAEC_Capability_Final.pdf
1/89
September 2009
Rural Areas Electricity Company3 YEARCAPABILITY STATEMENT 2009-2011
-
7/27/2019 RAEC_Capability_Final.pdf
2/89
RAEC CAPABILITY STATEMENT 2009 Page 2
Table of Contents
Topic Page
1.0 Introduction 3
1.1Preamble.1.2Company Background.1.3Geographic Coverage Areas.
2.0 Information on current status of RAEC power Systems 6
2.1 System Overview 6
2.2 RAEC System users 122.3 Sources of electricity to RAEC Customers 172.4 Efficiency of RAEC Power systems 19
3.0 Demand On RAEC Power systems 41
3.1 Profile of Current Demand. 413.2 Forecasted Demand. 49
4.0 Constrains foreseen on RAEC systems 64
4.1 Status of power stations 644.2 Power capacities planned to be added. 664.3 Predicated power capacities at different areas of RAEC 69
5.0 Progress of current investments 72
5.1 Executed projects by the end of Dec. 2009. 725.2 Progress of on going projects. 73
6.0 Future developing Plans 78
6.1 Developing of the metering system. 786.2 Resizing of Power Plants. 786.3 Interlinking of small plants to local total systems. 796.4 Construction of Gas Power Station at Musandam area. 796.5 Implementation of Renewable energy.
7.0 List of Figures 85
8.0 List of Tables 87
9.0 List of appliances 89
-
7/27/2019 RAEC_Capability_Final.pdf
3/89
RAEC CAPABILITY STATEMENT 2009 Page 3
1.0 Introduction
1.1 Preamble
This document has been produced in accordance with Condition 35 of the RAEC license. The RAEC
systems are small and change relative rapidly and therefore whilst every care and diligence has been
exercised in the preparation of this document, reader are cautioned not to rely on the information
contained in this document for planning any major investment. Readers are strongly encouraged to
contact RAEC to confirm the status of any network or generation station before committing to any load or
generation project.No part of this Statement may be reproduced, stored in a retrieval system, transmitted or further
distributed in any form or means electronic, mechanical, photocopying, recording or otherwise for any
purpose other than with the written permission of RAEC.
The RAEC is requested under the terms of its License, to prepare annually, a RAEC Capability Statement
that provides, in respect of each of the three succeeding financial years:
information on the status of existing RAEC Capacity and the anticipated requirement for new
Capacity, including new Generation Capacity;
commentary indicating the views of the RAEC as to those of its RAEC Systems most suited to new
Connections and the Transmission and Distribution of further quantities of electricity;
commentary indicating the views of the RAEC as to those of its RAEC Systems most suited to
connecting to the Total System;
information on any constraints foreseen on RAEC Systems;
information relating to progress made with current investments;
such further information as shall be reasonably necessary to enable any Person to identify andevaluate opportunities available for Connecting to a RAEC System; and
such other matters as shall be specified in directions issued by The Authority from time to time for
these purposes.
-
7/27/2019 RAEC_Capability_Final.pdf
4/89
RAEC CAPABILITY STATEMENT 2009 Page 4
1.2 Company Background
The Rural Areas Electricity Company SAOC (RAECor the Company) was created in 2005 as part of
the Transfer Scheme implementation process of the new electricity market structure. Article (84) of the
Law for the Regulation and Privatization of the Electricity and Related Water Sector (Royal Decree No.
78/2004) specifies the functions and powers of RAEC, whilst Article (86) specifies its duties. The
Company License was granted by the Authority for Electricity Regulation, Oman (AER) on May 1, 2005
and it contains 57 Conditions and subsequent modifications that together enable the Company to
undertake its Licensed Activities. The Company is owned 99.99% by the Electricity Holding Company
(EHC) and 0.01% by the Ministry of Finance (MOF). EHC in turn is owned 100% by MOF.
RAEC is fully integrated utility with power generation, distribution and supply systems in the Sultanate of
Oman. At present, power is transmitted and distributed through low voltage, 11 kV and 33 kV lines.
RAECO has agreement with the Petroleum Developing Oman (PDO) to supply customers at areas of
license where it is difficult to connect them systems with its own generation.
1.3 Geographic Coverage Areas.
The Company is licensed to carry out generation and desalination activities within its geographic area of
responsibility. The key systems within Oman under the ownership of RAEC are scattered in 62 locationsat regions Musandam, Masirah, Al Wusta, Dhofar, Al Sharqiah (Fig 1.1) with other 21 interconnections
with PDO. Most of power generation sites are owned and operated by RAEC. The generation assets are
comprised of 62 locations, 6 of them includes desalination plants. As per the plans to decrease the cost of
generation where it is applicable RAEC has been closing many generation sites and shifting customers
supplying to the Main Interconnection System (MIS), PDO, Dhofar Power Company (DPC) to make
Transmission system operation (TSO) or interlinking the sites near each other to a total system to make
Distribution system operation (DSO) . In the end of 2009 the total number of producing power sites is 47
with a total available electricity generation capacity stood at about 200.252 MW. This includes the 71.2
MW capacity at Raysut A & B. Many of RAEC`s sites are cogeneration that are producing water in
addition to electricity, these are located in Musandam, Masirah, Al Wusta, Dhofar and Sharqiya with a
total installed capacity just under 2,500 m3 per day. Individual units vary in size from 50 m3 per day in Al
Wusta to 600 m3 per day in Sharquiah. The individual diesel units vary in capacity from less than 100 kW
at Hajar Bani Hameed to 7.5 MW at Raysut B in Salalah. There are two diesel power plants (Raysut A &
B) located in Salalah City owned and operated by RAEC. These are used each summer period to cover
-
7/27/2019 RAEC_Capability_Final.pdf
5/89
RAEC CAPABILITY STATEMENT 2009 Page 5
current shortages of the Dhofar Power Company (DPC) grid in meeting customer peak demands. The
operating parameters for these power plants are stipulated in the Power Purchase Agreement (PPA)
that RAEC has with Oman PWP.
Fig1.1: Geographic Coverage Area of RAEC Power &desalination Systems.
-
7/27/2019 RAEC_Capability_Final.pdf
6/89
RAEC CAPABILITY STATEMENT 2009 Page 6
2.0 Information on Current Status Of RAEC Power Systems
2.1 System Overview
RAEC`s power system consists of three phase 0.433, 11 and 33 kV systems. Electricity catered to
customers is either generated in power stations owned and operated by RAEC or purchased from PDO in
agreement to supply customers at areas of license where it is difficult to connect them to one of RAEC`s
systems RAEC manages 33 kV lines, 11kV lines and 0.415 kV lines including poles, pylons, conductors
and related equipment. This is in addition to assets such as substations, including buildings,
transformers, bus bars, circuit breakers, control systems, protection systems and metering systems.In addition to the above, the Company has 21 interconnections with PDO, DPC and other electricity
distribution companies within the EHC. There are also plans to have an interconnection with United Arab
Emirates at Musandam. At present, RAEC does not have lines greater than 33 kV under its management.
2.1.1 Technical, design and operational criteria
RAEC system and any RAEC system users connections to the distribution system shall be designed to be
consistent with the security requirements of the distribution and supply license. Licensed distributors shall
ensure that the distribution system complies with the following technical, design and operational criteriain relation to the part of the distribution system at the connection site with a distribution system user.
2.1.2 Voltage regulation
The voltage on the 33kV and 11kV sides of distribution transformers at Connection points with the
distribution system users shall normally be controlled within the limits +/-6.0% of the nominal value.
During some system disturbances such as where short circuits occur, the voltage may collapse transiently
to zero at the point of fault until the fault is cleared. Under fault and circuit
Switching conditions, the 50 Hz Frequency component of voltage may fall or rise transiently. Thefall or rise in voltage will be affected by the method of Earthing of the neutral point of the
distribution System and this variation in voltage shall be taken into account in selecting apparatus and
Plant from an appropriate specification for installation on or Connection to the System. The voltage at the
Consumers terminals shall not vary from the System nominal voltage
by more than HV 33/11 kV +6.0% to6.0%,
-
7/27/2019 RAEC_Capability_Final.pdf
7/89
RAEC CAPABILITY STATEMENT 2009 Page 7
LV415/240 V +6.0% to6.0%
2.1.3 Frequency deviations
The Frequency of the RAEC Systems shall be nominally 50.00 Hz with System Frequency set points
between 49.95Hz and 50.05Hz. Normal control deviations will not exceed 49.90Hz to 50.10Hz. Under
transient disturbed conditions, System Frequency could rise to 51.50Hz or fall to 48.00Hz.
2.1.4 Voltage waveform quality
All apparatus and Plant Connected to the Distribution System, and that part of the
Distribution System at each Connection Point, should be capable of withstanding the following
distortions of the voltage waveform in respect of harmonic content and phase unbalance.
The maximum total levels of harmonic distortion on the Distribution System at 33 and 11kV, from all
sources under both normal, planned outage and fault outage conditions, shall not
exceed a total harmonic distortion of 2.0% with no individual harmonic greater than 1.5% unless
abnormal conditions prevail. At LV, the maximum total levels of harmonic distortion from all
sources shall not exceed a total harmonic distortion of 2.5%.The maximum negative phase sequence
component of the phase voltage on the Distribution
System should remain below 1.0% unless abnormal conditions prevail. A maximum value of 2.0%ispermitted for phase unbalance.
2.1.5 Voltage fluctuations
Voltage fluctuations, arising from fluctuating Demands Connected at a Connection Point to
the Distribution System, shall not exceed 1.0% of the voltage level for step changes that may occur
repetitively. Any large voltage excursions, other than step changes, may be allowed up to a level of 3.0%
provided that this does not constitute a risk to the Distribution System or to any Distribution System User.
2.1.6 Distribution Networks
The network topologies associated with RAEC power systems range from compact 11, 33 kV ring
systems supplying small towns like Khasab, Dibba, Masirah, new town at Al Duqm through to wide area
radial systems interconnecting diesel generator power stations like, Al Jazir area , Saih Al Khairat, Shaab
Esaab, Mudhi, Ras Madrakah, Abu Mudhabi, etc. These areas involve nodes connected as a string with
-
7/27/2019 RAEC_Capability_Final.pdf
8/89
RAEC CAPABILITY STATEMENT 2009 Page 8
many kilometers 11 or 33 kV circuits. With compact systems (in towns) resupply arrangements (creating
a ring) is provided for securing power , whereas with most RAEC systems radial system is used because
the cost of resupply arrangements will be prohibitive due to the long distances involved. Table 2.1 bellow
shows the main equipment and materials used in design and construction of RAEC power distribution
networks. All equipment and materials should be specified according to OES as minimum.
Table 2.1: Standard Equipment and materials used in RAEC Power Distribution Systems
Equipment Size/Rating
11 /33 kV Step Down Transformer rating G/M 1,3, 6,10 &20 MVA
11 kV switchgear rating 1250A (Incomer & Bus section) 400 / 630A (Feeder)
11 kV RMU. 400/200 A.
33 kV switchgear rating 1250 A & 630A
33/0.433 kV Transformers P/M 200, 315 kVA
11/0.433 kV Transformers P/M 100, 200, 315 kVA
11/0.433 kV Transformers G/M 500, 1000 kVA
11kV Overhead lines Wolf (150mm2 ACSR)
AAAC 95
AAAC 195
Dog (100mm2 ACSR)
LV Overhead lines 200 mm2 AL conductor XLPE Insulated
120 mm2 AL conductor XLPE Insulated
33kV Overhead lines Panther (200mm2 ACSR)
Wolf (150mm2 ACSR)
AAAC 24033 kV Under Ground Cables 3C 300 mm2 CU XLPE
11 kV Under Ground Cables 3C 240, 185, 120, 70, 50 mm2 & 1C x 500 mm2 CU
XLPE
LV Under Ground Cables 4CX 240,185,120,70,50,35 &1CX630 CU XLPE
-
7/27/2019 RAEC_Capability_Final.pdf
9/89
RAEC CAPABILITY STATEMENT 2009 Page 9
2.1.7 Power generation systems:
At present RAEC owned 62 power sites of different capacities scattered in Musandam, Wusta, Dhofar
and Al Sharqiyah regions (table 2.3). The majority of the sites contain power generation sets (DG sets)
with distribution networks and are operated by the RAEC through operation and maintenance (O&M)
contractors. Other sites are being closed and the equipment of useful remaining operating life from the
closed stations are being relocated to power systems which are being implemented or resized by RAEC at
different locations in its area of license.
The number of power stations currently being operated by RAEC is 47 at different areas in Oman. Thepower stations are equipped by standard equipment and machines as per table 2.2.
The power stations sizes and efficiencies are being analyzed to establish a plan for improving power
system performance at different areas in RAEC licensed area.
Table 2.2: Standard Equipment used in RAEC Power Generation Stations.
Equipment Size/Rating
Diesel Generator Sets Different Ratings from 32 KW up to 7800 KW at different out put
voltages. 0.433, 3.3 &11 KV. Operating speed ranging from 600 RPM
up to 1500 RPM. Output power Frequency is 50 Hz.
0.433 KV switchgear Rating Up to 3500 A
0.433 /11 KV Step Up Transformer
rating
600-1600 KVA
3.3 /11 KV Step Up Transformer rating Up to 4400 KVA
11 /33 KV Step Down Transformer
rating G/M
1,3, 6,10 &20 MVA
11 kV switchgear rating 1250A (Incomer & Bus section)
400 / 630A (Feeder)
11 KV RMU. 400/200 A.
33 kV switchgear rating 1250 A & 630A
-
7/27/2019 RAEC_Capability_Final.pdf
10/89
RAEC CAPABILITY STATEMENT 2009 Page 10
Table 2.3 bellow shows the power generation sites that being owned and operated by RAEC, many of
these sites are closed at present and assets being shifted to other sites or sold. Customers are being
shifted to TSO or DSO.
No. R.S.No. R.S.Name Region TypeYear ofstarting
operation
No. ofDG units
installedcapacity(MW)
Availablecapacity (MW)
1 03/006 Kumzar Musandam Cogen. 1984 2 0.936 0.8
2 03/001 Al Rawda Musandam Electricity 1996 3 0.275 0.22
3 03/002 Dibba Musandam Electricity 1978 8 17.43 13.944
4 03/004 HB Hameed Musandam Electricity 1994 2 0.1 0.124
5 03/005 Khasab Musandam Electricity 1982 10 41 32.908
6 03/007 Madha Musandam Electricity 1982 8 7.516 6.01
7 02/001 AbuMudhabi Wusta Cogen. 1985 6 0.608 0.535
8 02/027 Sawgrah Wusta Cogen. 1998 4 0.874 0.467
9 02/004 Al Kahal Wusta Electricity 1999 4 2.378 4.288
10 02/005 Al Khaluf Wusta Electricity 2007 2 2 1.6
11 02/006 Al Khuiaima Wusta Electricity 2004 4 1.168 0.96
12 02/007 Al Lakbi Wusta Electricity 1998 5 1.772 1.419
13 02/008 Alajaiz Wusta Electricity 2006 4 1.13 0.904
14 02/010 AlNajdah Wusta Electricity 2007 3 2.2 1.76
15 02/012 AlZhaiah Wusta Electricity 2003 2 0.4 0.32
16 02/016 Hij Wusta Electricity 1999 7 10.5 8.48
-
7/27/2019 RAEC_Capability_Final.pdf
11/89
RAEC CAPABILITY STATEMENT 2009 Page 11
17 02/017 Hitam Wusta Electricity 2007 5 1.33 1.064
18 02/025 Ras Madraka Wusta Electricity 1999 5 1.071 0.863
19 02/030 Surab Wusta Electricity 2006 3 2.2 1.8
20 02/031 Al Duqm Wusta Electricity 1999 5 1.331 1.06+mobile dg
21 02/032 Al Dhafrat Wusta Electricity 2008 4 1.86 1.48
22 02/020 Masrooq Wusta Electricity 1994 6 0.712 0.523
23 02/019 Masirah Sharqiyah Cogen. 1976 10 10.597 8.478
24 BB Hassan Sharqiyah Electricity 1980 Closed Closed
25 Al Kamil Sharqiyah Electricity 1980 Closed Closed
26 Mudhairib Sharqiyah Electricity 1980 Closed Closed
27 Al Mudaibi Sharqiyah Electricity 1980 Closed Closed
28 Sur Sharqiyah Cogen. 1978 Closed Closed
9 01/001 Al Halaniyat Dhofar Cogen. 1985 4 0.544 1.28
30 01/002 Al Mathfa Dhofar Electricity 2002 3 0.46 0.338
31 01/005 Ayboot (1) Dhofar Electricity 2002 3 0.46 0.396
32 01/006 Ayboot (2) Dhofar Electricity 2006 3 0.7 0.46
33 01/007 Ayun Dhofar Electricity 2000 3 0.69 0.596
34 01/008 Barbazum Dhofar Electricity 2000 3 0.88 0.79
3501/009
Bithina Dhofar Electricity ---Under
Construction
36 01/010 Dalkut A Dhofar Electricity 1992 4 1.48 1.184
37 01/011 Dalkut B Dhofar Electricity 1997 5 3.128 2.502
38 01/012 Dhahabun Dhofar Electricity 2000 3 0.879 0.783
39 01/014 Fatkhat Dhofar Electricity 2002 3 0.416 0.368
-
7/27/2019 RAEC_Capability_Final.pdf
12/89
RAEC CAPABILITY STATEMENT 2009 Page 12
40 01/015 Hasik Dhofar Electricity 1992 3 1.196 0.957
41 01/016 Hirweeb Dhofar Electricity 2001 3 0.775 0.70
42 01/017 Horaat Dhofar Electricity 2002 3 0.49 0.39
43 01/019 Mahwice Dhofar Electricity 2002 3 0.362 0.318
44 01/020 Maqshan Dhofar Electricity 2001 4 1.29 1.112
45 01/021 Mazyunah Dhofar Electricity 1995 5 2.408 1.926
46 01/023 Mitan Dhofar Electricity 2001 3 0.885 0.79
47 01/024 Mothorah Dhofar Electricity 2006 2 0.44 0.38
48 01/025 Mudhai Dhofar Electricity 1992 4 1.084 1.00
49 01/026 Rabkut Dhofar Electricity 2000 3 0.75 0.64
50 01/030 Sadah Dhofar Electricity 1978 Closed Closed
51 01/031 Sadhoon Dhofar Electricity Closed Closed
52 01/032 Saih Alkirat Dhofar Electricity 2006 8 8 16.435
53 01/033 Salalah 1 Dhofar Electricity 1974 Closed Closed
54 01/034 Salalah 2 Dhofar Electricity Closed Closed
55 Raysut A Dhofar Electricity 1983 36 28.8
56 Raysut B Dhofar Electricity 1973 53 42.4
5701/035 Shahb
AsaybDhofar Electricity 1999 4 3.5 2.8
58 01/037 Sharbatat Dhofar Electricity 1999 5 2.722 2.18
59 01/038 Shasir Dhofar Electricity Closed Closed
60 01/039 Thumryt Dhofar Electricity 1993 Closed Closed
61 01/040 Tushnat Dhofar Electricity 2001 3 0.85 0.72
6201/004
Andat Dhofar Electricity --------UnderConstruction
Total RAEC 232.777 200.252
-
7/27/2019 RAEC_Capability_Final.pdf
13/89
RAEC CAPABILITY STATEMENT 2009 Page 13
Table 2.3: Power generation sites owned and operated by RAEC and their availablecapacities in 2009.
2.2 RAEC System UsersThe total Number of customers connected to RAEC systems in the end of 2008 was 18, 851, and 86.4%
of them are powered from power generation stations owned and operated by RAEC. The remaining
13.6% are at areas difficult to be connected to RAEC systems and they are near PDO power plants,
therefore RAEC has PPA with PDO to feed customers at the area of its license. Table 2.4 and Figures 2.1,
2.2&2.3 detail the percentage of number of customers, Load and Energy Demand of customers fed from
RAEC power generation stations and PDO.
In case of power interruption RAEC temporally caters power to customers from mobile DG sets.
Table 1.1 Details the total number of RAEC customers with the maximum Load and the total energy
consumed in 2008 and the total energy consumed.
86.4%
13.6%
No. of Customers Catered from RAEC system
No. of Customers catered from PDO power generation system
Source ofpower
No. ofCustomers
Max. Load(MW) 2008
EnergyDemand(MWH) 2008
RAEC 16,280 81272,936
PDO 2,571 14 38,606
Table 2.4 RAEC customers
Fig 2.1 Percentage ofCustomers Powered frRAEC and PDO powerstations in the end of
2008 .
-
7/27/2019 RAEC_Capability_Final.pdf
14/89
RAEC CAPABILITY STATEMENT 2009 Page 14
15%
11%
89%
MWH Demand from PDO
power generation
system
MWH Demand catered
from RAEC power
system
Total 18,851 95 311,542
Fig 2.3 Percentagtotal 2008 Energysupplied from RA
and PDO power
-
7/27/2019 RAEC_Capability_Final.pdf
15/89
RAEC CAPABILITY STATEMENT 2009 Page 15
2.2.1 Type of RAEC systems Users.
The RAEC is supplying power to customers at rural areas; therefore the main loads are domestic,
governmental commercial and farms. Industrial loads are very small. Figures2.4, 2.5, 2.6&2.7 and
Tables2.5, &2.6 show the classification of customers with their maximum load and total demand in 2008
at RAEC regions.
Type of CustomerNo.
2008
Percentage %Demand MWH
2008
Percentage
%Domestic 13,603 72.2 165,400 53.1
Governmental 2,021 10.7 76,066 24.4
Commercial 2,989 15.8 37,072 11.9
MOD 39 0.2 9,002 2.9
Agr. &Fisheries 168 0.9 10,053 3.2
Hotels &Tourism 20 0.1 10,643 3.4
-
7/27/2019 RAEC_Capability_Final.pdf
16/89
RAEC CAPABILITY STATEMENT 2009 Page 16
2.2.2 Regional number and maximum Load of RAEC systems Users:
25%
12%
De
A
Industrial 11 0.1 3,306 1.1
RAEC Total 18,851 100 311,542 100
Table 2.5:Numberand type ofcustomersconnectedto RAECsystems in2008
-
7/27/2019 RAEC_Capability_Final.pdf
17/89
RAEC CAPABILITY STATEMENT 2009 Page 17
17%
50%
33%No. of Customers at
Dhofar
No. of Customers at
Musandam
No .of Customers at
Wusta& Sharqiyah
RAEC AreasNo. ofCust.
Maximum Load(MW) IncludingPDO Supply
Maximum Load (MW)excluding PDO supply
Wusta 6262 30 18.45
Musandam 9369 45.6 45.6
Dhofar 3221 19.4 16.88
Fig 2.5 Percentageof Customers atRAEC areas
Table 2.6 :Numbers ofCustomers andMax. Load in 2008at RAEC areas
-
7/27/2019 RAEC_Capability_Final.pdf
18/89
RAEC CAPABILITY STATEMENT 2009 Page 18
48%
32%
20%
Musandam Max. Demand (MW)
Wusta Max. Demand(MW)
Dhofar Max. Demand (MW)
56%
23%
21%
Musandam Max Load MWWusta &Sharqiyah Max Load MW
Dhofar Max Load MW
Fig 2.7 Percentage ofLoad excludingsupplied from PDO
Fig 2.6 Percentage ofLoad includingsupplied from PDO
-
7/27/2019 RAEC_Capability_Final.pdf
19/89
RAEC CAPABILITY STATEMENT 2009 Page 19
2.3 Sources of Electricity Supply to RAEC customers
2.3.1 Regional Available Power Generation Capacity of RAEC power Systems:
Figure2.8 and Table2.7 show the total existing power generation capacity of RAEC system, and figure2.9
& table 2.8 Detail the regional power generation capacities of RAEC systems.
63%
37%
RAECPower
Capacity
for RAEC
CustomersRAEC
Power
Capacity
for PPA
with PWP
48%
29%
23%
Musandam
Available
capacity MW
Wusta &Al
Sharqiyah
available
capacity MWDhofar
available
capacity MW
RAEC Power Generation
CapacityMW
Connected to
Customers under RAEC
License
119.34
PPA with PWP 71.2
Total 190.5
RAEC AreasMaximumLoad from
RAEC system
(MW) 2008
AvailableCapacity
(MW)
Musandam 45.6 58
Wusta 18.45 35
Dhofar 16.88 27.5
Fig 2.8 Percentage of RAEC available capacity
Table 2.7 Available power
generation capacity of RAEC
power stations including Raysut
A&B power houses
Fig 2.9 Regional Percentage of RAEC available power generationcapacity excluding Raysut A&B.
Table 2.8 Regional available power
generation capacity of RAEC powerstations excluding Raysut A&B power
Stations
-
7/27/2019 RAEC_Capability_Final.pdf
20/89
RAEC CAPABILITY STATEMENT 2009 Page 20
2.3.2 RAEC Power Systems Interconnected to PDO.
RAECO has agreement with the Petroleum Developing Oman (PDO) to supply customers at areas of
license where it is difficult to connect them systems with its own generation as per table 2.9.
Table 2.9 RAEC interconnections with PDO
ID Region RSName RSNumber TypeMax.
Load
(MW)
1 9221 Al Wusta Ghobra 02/034 Interconnection 0.419
2 9234 Al Wusta Nahadah/Jabel ras 02/035 Interconnection 1.066
3 9245 Al Wusta Wadi Buthaila 02/036 Interconnection 0.123
4 9044 Al Wusta Natih 02/022 Interconnection N/A
5 9001 Al Wusta Alnuhaidah 02/011 Interconnection N/A
6 9012 Al Wusta Bahja 02/013 Interconnection N/A
7 9026 Al Wusta Namur 02/021 Interconnection N/A
8 9055 Al Wusta Qarn Alalam 02/024 Interconnection N/A
9 9063 Al Wusta Rima 02/026 Interconnection N/A
10 9080 Dhofar Al Shuwaimia 01/003 Interconnection N/A
11 9087Dhofar Amal (Shuwaimia &
Shaleem)01/045 Interconnection 2.133
12 9102 Dhofar Dimeet 01/013 Interconnection 0.252
13 9113 Dhofar Kabut 01/018 Interconnection 0.169
14 9131 Dhofar Shaleem 01/036 Interconnection N/A
15 9137 Dhofar Wadi Arah 01/041 Interconnection 0.190
16 9155 Dhofar Wadi Haka 01/042 Interconnection N/A
17 9166 Dhofar Wadi Rahab 01/043 Interconnection N/A
18 9176 Dhofar Zakhar 01/044 Interconnection N/A
19 9185 Musandam Sheesa 03/009 Interconnection N/A
20 9198 Al Wusta Haima 02/032 Interconnection 7.362
21 9209 Al Wusta Wadi Aswad 02/033 Interconnection 1.979
Total Maximum Interconnected Load (MW) 13.693
-
7/27/2019 RAEC_Capability_Final.pdf
21/89
RAEC CAPABILITY STATEMENT 2009 Page 21
2.4 Efficiency of RAEC Power Systems
2.4.1 Power Loss.
The Total Energy metered at customer metering equipment is different from the total energy sent from
the power generation stations; this is due to power losses (technical and un technical). Figure 2.10 and
Table 2.10 show the calculated loss at RAEC individual areas and the loss calculated for combined RAEC
systems.
0
5
10
15
20
25
RAEC
Wustaa
Dhofar
Musanda
m
Power Loss at RAEC Power Systems
AreaPower Units Sent
(kWh)Power Units
Metered (kWh)Losses %
Musandam
191,536,982 162,313,183 15.26
Dhofar 77,683,928 61,923,802 20.29
Wusta & shar 101,053,959 87,304,885 13.61
RAEC 370,274,869 311,541,870 15.86
Figure2.10:Regional& RAECpowerLoss
Table 2.10Summeryof RAEC
regionalPowerLoss
-
7/27/2019 RAEC_Capability_Final.pdf
22/89
RAEC CAPABILITY STATEMENT 2009 Page 22
Table 2.11 below details the losses of RAEC power systems calculated by the comparison of energy sent
from power stations and that metered by customers energy meters through billing system. From the
analysis it is shown that losses are very high in many systems while are very low in others, many power
systems show that power metered for billing is more than that Sent from the power house, this is
because of many factors such as, inaccurate metered data, power supplied without metering, rented
power which is not added to power sent, etc. Power losses in the remaining power systems can`t be
calculated since the billing system covers metering in area bases not on system where many areas are
being powered from more than power station.
S.No.
AREACODE &NAME
Consumed(Units)Gover.
Consumed(Units)
(Private)
Total(Units)
Total UnitsSent kWh
TotalLoss %
1 8 KHASAB - E 20,689,175 59,289,219 79,978,394 128,116,585 17.7
2 9 DIBBA - E 9,267,347 35,813,202 45,080,549 49,311,010 8.6
3 83 BUKHA - E/W 6,774,028 10,857,897 17,631,925 Khasab
4 84 ROWDHA 841,376 170,773 1,012,149 345,229 Khasab
5 85 MADHA - E/W 2,309,941 9,525,939 11,835,880 14,552,305 18.7
6 86 QUIDA - E/W 1,219,971 2,634,277 3,854,248 Khasab
7 87 KHUMZAR - 716,672 2,189,021 2,905,693 Khasab
8 88 SHISHA - E/W 112,480 238,596 351,076 Khasab
9 89 AL NUZAIF - E 50,347 621,186 671,533
10 92 MAHOOT 4,009,745 9,467,080 13,476,825 14,955,468 9.9
11 93 DAKHOOM 3,301,265 4,096,273 7,397,538 5,897,942 -25.4
12 94 JAZIR - E / W 2,186,029 5,295,321 7,481,350 9,289,556 19.5
13 96 MASIRAH - E 2,899,250 21,334,404 24,233,654 25,749,655 5.9
14 98 KHOAIMA -E 608,203 1,343,820 1,952,023 3,634,419 46.3
15 100 MASROOQ 7,741 237,109 244,850 479,224 48.9
16 102 ZAHIYAH 183,471 350,949 534,420 756,096 29.3
-
7/27/2019 RAEC_Capability_Final.pdf
23/89
RAEC CAPABILITY STATEMENT 2009 Page 23
Table 2.11 Calculated losses at many of RAEC`s power systems.
17 40 AIBOOT-2 125,618 264,677 390,295 734,056 46.8
18 42 FATKHEET 95,744 194,492 290,236 339,068 14.4
19 43 MAHVEES 63,441 196,897 260,338 304,663 14.5
20 44 HEBROT-ABT1 118,990 206,992 325,982 783,132 58.4
21 45 MUTHAFAH 45,108 69,069 114,177 124,807 8.5
22 46 HAROOT 84,759 295,743 380,502 422,105 9.9
23 47 MAQSHAN 760,327 436,412 1,196,739 1,369,810 12.6
24 48 HERWAIB 453,066 660,001 1,113,067 1,057,760 -5.2
25 49 METAN 403,163 954,576 1,357,739 1,915,654 29.1
26 51 TOSENAT 393,776 51,222 444,998 802,758 44.6
27 54 BARBAZOOM 136,804 588,419 725,223 1,055,300 31.3
28 55 AAYOON 46,393 252,879 299,272 285,763 -4.7
29 56 DHABOON 193,499 1,075,080 1,268,579 1,354,411 6.3
30 57 RABKOOT 155,016 482,921 637,937 726,764 12.2
31 58 SHAHBASAHEB 2,106,423 2,343,680 4,450,103 8,581,440 48.1
32 59 AL HALANIAT 159,895 127,384 287,279 929,090 69.1
33 61 AL SHASAR 3,696,369 12,984,070 16,680,439 23,354,025 28.6
34 62 AL MAZEUNA 1,996,738 3,497,710 5,494,448 7,302,521 24.8
35 70 SHARBATAT 792,504 2,003,987 2,796,491 2,867,290 2.5
36 72 MUDHAI 537,677 1,255,593 1,793,270 1,689,125 -6.2
37 80 HASIK 793,913 2,483,576 3,277,489 3,418,198 4.1
38 97 DHALKOOT 3,395,389 3,239,351 6,634,740 7,783,510 14.8
39 98 RAYKHUIT 1,699,732 1,424,243 3,123,975 726,764
-
7/27/2019 RAEC_Capability_Final.pdf
24/89
RAEC CAPABILITY STATEMENT 2009 Page 24
2.4.2 Efficiency of Power Stations
Combinations of DG with different generation capacities are used in RAEC Power stations. The DG sets
are connected in parallel to get the required power capacity of the power station. Synchronizing of the
DG sets is being done automatically and/or manually. Power evacuated is connected to common
switchgears and supplied to customers by .0.433, 11 or 33 kV lines. The main factors considered in
selecting the type and size of the DG sets are the base load, the maximum and minimum demand and
power security standard of the demand predicated in the considered area.
The output energy per litre is used to calculate the outage of each power station. The efficiency of each
power station is calculated with reference to (10.8 kWh/litre) which is an international reference value.
Fig 2.11 and table 2.12 detail the generated energy per litter and efficiency of existing RAEC power
stations.
0
5
10
15
20
25
30
35
40
0 10 20 30 40 50 60
Ece%
Power Station Number
RAEC Power Stations Efficiency
RAEC
Power
Stations
Efficiency
RAEC
average
efficiency,
31%
Fig 2.11 Efficiency of Power Stations
-
7/27/2019 RAEC_Capability_Final.pdf
25/89
RAEC CAPABILITY STATEMENT 2009 Page 25
No.
Powe
r
Station
Fuel
Consump
(2008)
Litter
Gene
rate
dEne
rgy
(2008)
kWh
kWh/L.
PSE
ff.%
No.
Powe
r
Station
Fuel
Consump
(2008)
Litter
Gene
rate
dEne
rgy
(2008)
kWh
kWh/L
PSEff.%
1 Khasab 36,425,952 135,574,000 3.72 34.5 26 Ayoon 120,000 296,352 2.47 22.9
2 Dibbah 14,822,185 53,052,960 3.58 33.1 27 Rabkut 250,000 738,215 2.95 27.3
3 Madah 4,220,652 15,150,830 3.59 33.2 28Sha.Assaib
2,684,900 8,659,307 3.23 29.9
4 HBH 111,000 207,544 1.87 17.3 29Mazyonah
2,300,800 7,329,410 3.19 29.5
5 Rawda 207,000 383,232 1.85 17.1 30 Makshan 448,000 1,410,950 3.15 29.2
6 Masrooq 227,500 515,749 2.27 21 31 Mittan 720,000 1,922,010 2.67 24.7
7 Al Lakbi 2,057,070 5,808,441 2.82 26.1 32 Tushnat 340,000 815,885 2.40 22.2
8 RasMadraka
1,312,130 3,431,960 2.62 24.2 33 Harweeb 460,000 1,068,545 2.32 21.5
9 Al Duqm 2,102,390 5,901,953 2.81 26 34 Mahwise 140,000 315,938 2.26 20.9
10 Al Kahal 1,255,690 3,517,127 2.80 25.9 35 Howrat 220,000 437,936 1.99 18.4
11 Hij 5,197,970 15,007,120 2.89 26.7 36 Matafa 70,000 128,855 1.84 17
12 Al Zahia 289,990 791,185 2.73 25.3 37 Fatkeet 140,000 349,825 2.50 23.1
13 Khuiaima 1,237,650 3,728,791 3.01 27.9 38 Ayboot1 190,000 371,933 1.96 18.1
14 Hitam 542,160 873,801 1.61 14.9 39 Ayboot2 200,000 393,580 1.97 18.2
15 Khaloof 509,640 1,020,827 2.00 18.5 40 Saih kirat 6,006,000 23,457,500 3.91 36.2
16 Sarab 400,420 1,072,270 2.68 24.8 41 Mothorah 200,000 447,011 2.24 20.7
17 AlNajda 254,780 460,735 1.81 16.7 42 Masirah 9,145,500 32,572,840 3.56 33
18 Alajaiz 646,090 1,258,283 1.95 18 43 Kumzar 313,084 850,590 2.72 25.2
19 Dhalqut A 720,000 2,322,657 3.23 29.9 44AbuMudabi
191,150 490,817 2.5723.8*
*
20 DhalqutB 1,795,000 5,466,718 3.05 28.2 45 Sograh 14,000 8,860 0.63 5.9**
21 Hassik 1,065,000 3,372,307 3.17 29.3 46Hallaniyat
400,000 1,303,290 3.26 30.2
22 Sharbatat 978,000 2,856,598 2.92 27 47 Raysut A 1,190,800 0
23 Mudhai 820,000 1,694,665 2.07 19.1 48 Raysut B 300,000 0
24 Barbazom 388,000 1,073,135 2.77 25.6
25 Dhaboon 460,000 1,352,260 2.94 27.2 RAEC104,090,503
349,264,797 3.36 31.1
** Power Stations are closed
Table 2.12: Summary of RAEC Power Stations Efficiencies
-
7/27/2019 RAEC_Capability_Final.pdf
26/89
RAEC CAPABILITY STATEMENT 2009 Page 26
2.4.3 Cost of Generating Power Unit
0
50
100
150
200
250
300
350
400
0 10 20 30 40 50
PerCostBz/Kwh
Power Station Number
R.S.No. No. P Station Name
per unit Gen.
cost BZ/kWh
03/001 1 Al Rawda 107
03/002 2 Dibba 43
03/004 3 HB Hameed 191
03/005 4 Khasab 41
03/007 5 Madha 47
02/019 6 Masirah 57
02/001 7 AbuMudhabi 101
02/004 8 Al Kahal 67
02/005 9 Al Khaluf 103
02/006 10 Al Khuiaima 62
02/007 11 Al Lakbi 63
02/008 12 Alajaiz 107
02/010 13 AlNajdah 120
02/012 14 AlZhaiah 126
02/016 15 Hiij 55
02/017 16 Hitam 131
02/025 17 Ras Madraka 70
02/030 18 Surab 82
02/031 19 Al Duqm 59
02/020 20 Masrooq 152
01/001 21 Al Halaniyat 88
01/002 22 Al Mathfa 377
01/005 23 Ayboot (1) 185
01/006 24 Ayboot (2) 177
01/007 25 Ayun 196
01/008 26 Barbazum 93
01/010 27 Dalkut A 64
01/011 28 Dalkut B 60
01/012 29 Dhahabun 81
01/014 30 Fatkhat 171
01/015 31 Hasik 65
01/016 32 Hirweeb 138
01/017 33 Horaat 164
01/019 34 Mahwice 196
01/020 35 Maqshan 131
01/021 36 Mazyunah 61
01/023 37 Mitan 90
01/024 38 Mothorah 242
01/025 39 Mudhai 10701/026 40 Rabkut 107
01/032 41 Saih Alkirat 44
01/035 42 Shahb Asayb 57
01/037 43 Sharbatat 75
01/040 44 Tushnat 132
Total RAEC 52
Cost of power generation units consists from the cost of
fuel, oils, spare parts and operation and maintenance costs.
As mentioned Previously RAEC power stations are of
different types and capacities and located in isolated areas
in Oman, therefore cost of generating power units is
different from site to site.
Figure 2.12 and table 2.13 show the generated per unit
costs of RAEC power stations in all areas of license. Cost of
power distribution and billing is excluded.
From the table it is shown that per unit cost of generation
of most Power Stations is more than RAEC average value.
Fig 2.12: Per unit cost of generation of RAEC Powerstations
Table 2.13: Per unit cost of generation of RAECPower stations
-
7/27/2019 RAEC_Capability_Final.pdf
27/89
RAEC CAPABILITY STATEMENT 2009 Page 27
2.4.4 Case Studies of Power Flow.
By the use of ReticMaster Software Case Studies of power flow, loss, and voltage drop in 11 and
33 KV systems from different RAEC systems of demand more than 1 MW in 2008 has been done
with the following assumptions:
Single Line Diagrams of Power circuits in 2008 are used.
Maximum Loads in summer 2008 were used in the analysis. If detail loads on each 11/
0.433 KV transformer not available, the maximum loads in summer 2008 have been
distributed among loading areas with reference to a load factor depends on the existing
capacity of equipment to the maximum load at the feeder. The load values are used for thecalculation of load flow, power loss and voltage drop calculations.
The available specifications of equipment are used in calculations, in case specifications not
enough for calculations, specifications of standard equipment were determined from the
software library.
Power Factor was assumed to be 0.85 or 0.8.
Calculations were done for the existing status of systems.
Power Flow analysis, losses and voltage drop calculations have been done using the ReticMaster.
The ReticMaster 2008 used for power flow analysis has the technical specifications detailed below:
Technologies
Combined High, Medium and Low voltage technologies, simulations with unbalance and
diversityinclude:
Delta or Star, 2 to 4 wire systems (120 Phase displacement) modeling,
1 phase systems (Phase to Neutral) modeling,
Single Wire Earth Return systems (SWER) modeling,
Dual phase systems (180 Phase Displacement, two phases & neutral).
Radial / Limited Mesh System Analysis
Any user defined voltage level (e.g. 275kV, 132kV, 400V, 120V, etc.)
Full Technology Mix
-
7/27/2019 RAEC_Capability_Final.pdf
28/89
RAEC CAPABILITY STATEMENT 2009 Page 28
Calculations are automatic
An unlimited number of nodes are supported
Results are immediately available and may be displayed as required Voltage analysis (caters for unbalance)
Current Flow analysis
Fault current analysis:
Three phase faults
Phase to Ground faults
Phase to Neutral faults
Phase to Phase to Ground faults
Phase to Phase faults
Full load energy and losses energy calculations are performed
Demand Side / Energy Management
Load types include Constant Power, Constant Impedance & Constant Current
Full domestic algorithms are available using appropriate diversity calculations for
residential load modeling.
Statistical load analysis is available for residential load modeling
Output
Graphic reporting such as under/over-voltage and over loaded equipment
Voltage profiles are directly available & are dynamically updated during network
modifications.
Fault current profiles are available & dynamically updated
User definable GUI outputs are directly available
User definable text reports are directly available
Text Report of problems such as:
Open points,
Islands,
Voltage problems,
Rating problems and
Unbalance problems.
Detailed results for RAEC systems as Case studies are shown in the CD-ROM.
The followings are current and voltage profiles and alerts of main systems from RAEC areas:
-
7/27/2019 RAEC_Capability_Final.pdf
29/89
RAEC CAPABILITY STATEMENT 2009 Page 29
1. Power Flow analysis at Khasab 11 & 33kV Power system (Musandam Area):
Output of the software indicates the following: Software output is shown in appendix 1 ).
Maximum demand at many locations exceeds the carrying capacity of feeders and transformers
Figs 2.13&2.14 .
From
the
From
load
Feeders Current
Carrying Capacity
Maximum Current 2008
Fig 2.14: Voltage Profile capacity.Output fromReticMaster SoftwKhasab Power Sys2008
Fig 2.13: MaximumDemand and feedercurrent carryingcapacity. Output fromReticMaster SoftwarKhasab Power Syste2008
-
7/27/2019 RAEC_Capability_Final.pdf
30/89
RAEC CAPABILITY STATEMENT 2009 Page 30
flow analysis it is concluded that reinforcement work is required to many parts of the distribution network
feeders and transformers at Khasab area to overcome overloading and under voltage problems at some
areas as shown in table 2.14 bellow.
N
o.Equipment Branch Description
LM
(kM)I max A I of A
Reinforcement Work
Required
1TX No. 2 Al QADI 500kVA 11kV/430V Star
Dyn1[30]
- 743.77 103.1 Changing transformer to
1000 kVA.
2TX_40 500kVA 11kV/430V Star
Dyn1[30]
- 615.47 85.3 Changing transformer to
1000 kVA.
3O/H line from BB
to TX 56 Feeder 6
dog (70m) 0.07 251.54 100.6 Changing O/H line to
3X185 U/G Cable
4O/H line from TX
56 to TX No. 13
dog (230m) 0.23 246.45 98.6 Changing O/H line to
3X185 U/G Cable
5TX No. 27 315kVA 11kV/430V Star
Dyn1[30]
- 449.01 98.8 Changing transformer to
500 KVA.
6O/H line from BB
to TX 48 feeder 3
dog (160m) 0.16 349.53 139.8 Changing O/H line to
3X185 U/G Cable
7O/H line at TX 48
feeder 3
dog (220m) 0.22 343.51 137.4 Changing O/H line to
3X185 U/G Cable
8
O/H line from TX
48 to TX no 70
dog (130m) 0.13 343.55 137.4 Changing O/H line to
3X185 U/G Cable
9O/H line from TX
72 a
dog (70m) 0.07 325.8 130.3 Changing O/H line to
3X185 U/G Cable
10O/H line from TX
73
dog (200m) 0.2 308.06 123.2 Changing O/H line to
3X185 U/G Cable
11O/H line from TX
1
dog (300m) 0.3 285.7 114.3 Changing O/H line to
3X185 U/G Cable
12O/H line from TX
61
dog (600m) 0.6 281.24 112.5 Changing O/H line to
3X185 U/G Cable
13O/H line from TX
75
dog (200m) 0.2 262.81 105.1 Changing O/H line to
3X185 U/G Cable
14TX 10 500kVA 11kV/430V Star
Dyn1[30]
- 706.82 97.9 Changing transformer to
1000 KVA.
15TX 410 500kVA 11kV/430V Star
Dyn1[30]
- 690.31 95.7 Changing transformer to
500 kVA.
-
7/27/2019 RAEC_Capability_Final.pdf
31/89
-
7/27/2019 RAEC_Capability_Final.pdf
32/89
RAEC CAPABILITY STATEMENT 2009 Page 32
2. Power Flow analysis of Saih Al Khairat 11 kV Power system (Dhofar Area) .
The followings have been deduced from the power flow analysis: Software output is shown in
appendix 2 ).
Maximum current is within the feeders current capacity Fig 2.15 . The conductor is too long therefore
high load loss was indicated from the analysis table 2.16.
Fig 2.15: Maximum Demand and feeder current carrying capacity.Output from ReticMaster Software Shasir Power System.
-
7/27/2019 RAEC_Capability_Final.pdf
33/89
RAEC CAPABILITY STATEMENT 2009 Page 33
Voltage Profile Curve fig 2.16 indicates that voltage drop along through the power system is morethan the accepted value. Therefore work is required for relocating the current voltage regulator to a
location marked on fig 2.17.
Starting Location
of under voltage Area of under
voltage
Existing Location
voltage regulator Fig 2.17 VoltProfile of F2(Shasir AreaWith proposlocation ofvoltage regu
Fig 2.16 VoltProfile of F2(Shasir AreaWith out volregulator
-
7/27/2019 RAEC_Capability_Final.pdf
34/89
RAEC CAPABILITY STATEMENT 2009 Page 34
3. Power Flow analysis at Mazyounah 11 kV Power system (Dhofar Area) .
The followings have been deduced from the power flow analysis (Software output is shown
in appendix 3). Under ground cables are used as feeders current capacity, therefore load losses
and voltage drop is limited Figs2. 18 and Fig 2.19.
Fig 2.19 VoltProfile of feeat Al MazyunPower Syste
Fig 2.18: MaxDemand and fcurrent carryicapacity. Outpfrom ReticMasSoftware (AlMazyuna PowSystem).
-
7/27/2019 RAEC_Capability_Final.pdf
35/89
RAEC CAPABILITY STATEMENT 2009 Page 35
4. Power Flow analysis at Masirah 11 kV Power system (Al Sharqiyah Area) .
The followings have been deduced from the power flow analysis ( Software output is shown
in appendix 4). Under ground cables are used as feeders current capacity, therefore load losses
and voltage drop is limited Figs2. 20 and Fig 2.21.
Fig 2.20: MaxiDemand and fecurrent carryincapacity. Outpfrom ReticMasSoftware MasiPower System2008
Fig 2.21: VolProfile, Outpfrom ReticMaSoftware MaPower Syste2008
-
7/27/2019 RAEC_Capability_Final.pdf
36/89
RAEC CAPABILITY STATEMENT 2009 Page 36
Power Flow analysis at Hiij 11 kV Power system (Al Sharqiyah Area) .The followings have been deduced from the power flow analysis: Software output is shown in
appendix 5).
Maximum Current is about 10% of current carrying capacity of the conductor and,therefore load loss is too small as shown in figures 2.22&2.23. Oversized conductors areused to overcome voltage drop.
Fig 2.22 CurrentProfile at Hiijpower system
Fig 2.23 VoltageProfile at Hiijpower system
-
7/27/2019 RAEC_Capability_Final.pdf
37/89
RAEC CAPABILITY STATEMENT 2009 Page 37
5. Power Flow analysis at Aduqum 11 kV Power system (Wusta Area) .
The followings have been deduced from the power flow analysis:Software output is shown in in
appendix 6).
Maximum Current is about 10% of current carrying capacity of the conductor and,
therefore load loss is too small as shown in figures 2.24&2.25.
Fig 2.24 CurreProfile at AlDuqum powersystem
Fig 2.25Voltage Profat Al Duqumpower system
-
7/27/2019 RAEC_Capability_Final.pdf
38/89
RAEC CAPABILITY STATEMENT 2009 Page 38
6. Power Flow analysis at Al Jazir 11 kV Power system (Wusta Area) .
The followings have been deduced from the power flow analysis: Software output is shown in in
appendix 7).
Maximum Current is less than of current carrying capacity of the conductor and, therefore
load loss is too small as shown in figures 2.26&2.27.
Fig 2.26 CurrentProfile at Al Jazirpower system
Fig 2.27 VoltageProfile at Al Jazirpower system
-
7/27/2019 RAEC_Capability_Final.pdf
39/89
RAEC CAPABILITY STATEMENT 2009 Page 39
7. Power Flow analysis at Ras Al Madrakah 11 kV Power system (Wusta Area) .
The followings have been deduced from the power flow analysis: Software output is shown in in
appendix 8).
Maximum Current is less than current carrying capacity of the conductor and, therefore
load loss is too small as shown in figures 2.28&2.29.
Fig 2.28Current Profileat Ras AlMadrakah
power system
Fig 2.29Voltage Profileat Ras AlMadrakahpower system
-
7/27/2019 RAEC_Capability_Final.pdf
40/89
RAEC CAPABILITY STATEMENT 2009 Page 40
8. Power Flow analysis at Khawaimiah 11 Kv Power system (Wusta Area) .
The followings have been deduced from the power flow analysis: Software output is shown in in
appendix 9).
Maximum Current is less than current carrying capacity of the conductor and, therefore load
loss is too small as shown in figures 2.30&2.31.
Fig 2.30Current Profileat Khawaimahpower system
Fig 2.31 VoltageProfile atKhawaimahpower system
-
7/27/2019 RAEC_Capability_Final.pdf
41/89
RAEC CAPABILITY STATEMENT 2009 Page 41
9. Power Flow analysis at Wadi Aswad 33&11 kv Power system (Wusta Area) .
The followings have been deduced from the power flow analysis:Software output is shown in in
appendix 10).Maximum Current is about 10% of current carrying capacity of the conductor and,
therefore load loss is too small as shown in figures 2.32&2.33.
Fig 2.32CurrentProfile at
WadiAswadpowersystem
Fig 2.33 VoltagProfile at Wad
Aswad powersystem
-
7/27/2019 RAEC_Capability_Final.pdf
42/89
RAEC CAPABILITY STATEMENT 2009 Page 42
2.4.5 Losses in Distribution Systems.
Total losses in power systems are mainly technical and nontechnical losses. The technical losses result
from power flow in distribution networks and equipment at 33 kV, 11 kV and LV systems and are divide
into Load and no load losses. The non technical losses result from inaccurate data delivered, power
metering and other factors related to system users; therefore it is difficult to be determined. Calculating
of Power loss requires detailed information of the distribution networks including type, size and length of
conductors, specifications of distribution equipment, details of maximum loads on transformers and
feeders, etc. Table 2.16 shows a comparison between total, no load and load losses at different areas of
RAEC power systems.
Table 2.16 Losses at 11 &33 KV systems of RAEC main systems.
PowerSystem
MaximumDemand(kW)
Power Loss of 11kV System atMaximumDemand (kW)
Loss Percentageof 11 kV systemfrom ReticMaster%
Total LossPercentage%
Percentageof no loadLoss from11 kV TotalLoss
Dibba (F1&2) 3,040 153 5.03 8.6 43.14
Saih Al Khairat 5,624 384 6.6 28.6 17.0
Hiij 3,400 113 3.32 9.9 23.89
Khasab 21,726 1460 6.72 17.7 47.05
Al Jazir 3,455 255 7.38 19.5 10.2
Wadi Aswad 2,749 184 6.69 N/A 22.83
Masirah 8,495 210 2.47 5.9 24.76
Ras Madrakah 1,710 49 2.87 N/A 36.79
Khawaimah 2,379 76 3.20 46% 15
Al Mazyunah 2,632 71 2.70 24.8% 26.62
Al Duqum 1,395 26 1.86 N/A 48.85
-
7/27/2019 RAEC_Capability_Final.pdf
43/89
RAEC CAPABILITY STATEMENT 2009 Page 43
3.0 Demand on RAEC Power systems:
3.1 Profiles of Current Demands.
The main type of customers at RAEC areas of license is residential; therefore it becomes the main factor
influencing the demand profiles. From the demand profiles in 2008 it is shown that the demand
decreases sharply in Jun and February, then it starts increasing and decreasing in such a way reflecting
the climate temperature. In Dhofar region demand reduces during June, July and August (Khareef
season) and then increases as temperature increases again till October when it starts decreasing. Wusta
Region has the same climate phenomena as that in Dhofar and reflects the same demand profile as that
of Dhofar area. Khasab Region hasnt the climate phenomena as in Dhofar and Wusta regions therefore
the demand profile shows increase from February and continues at maximum from May up to October
when it starts seasonal reduction.
Many power stations in Dhofar area are not affected by the climate phenomena; therefore the type of
demand profile is different from the others. The un effectiveness is either that the locations of these
power stations are far away from climate phenomena such as Al Mazyuna power station or the main type
of demand is not residential as in Saih Al Khairat Power Station.
Figures 3.1-3.12 and table 3.1 show the anuual maximum demand profile of RAEC differnet areas in
2008
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
0 2 4 6 8 10 12 14
Fig 3.1 Profileof MaximumDemand atdifferentregions ofRAEC areas in2008 License(2008)
Maximum
-
7/27/2019 RAEC_Capability_Final.pdf
44/89
RAEC CAPABILITY STATEMENT 2009 Page 44
0
5000
10000
15000
20000
25000
30000
35000
40000
0 2 4 6 8 10 12 14
Demandin 2008
kW Jan. Feb. March April May June July Aug. Sept. Oct. Nov. Dec.
Masandam
Max . 16715 15990 24317 31732 42820 43625 44785 44575 42808 42675 31524 18200
Masandam
Min 6970 6435 9215 13971 16781 23281 25673 24654 25380 17499 10815 8949
Wusta
Max. 7,924 8,705 13,397 17,467 17,667 17,489 10,955 12,501 16180 16097 13098 10036
Wusta
Min. 3114 2817 2702 6123 7663 5587 4602 4748 6408 5795 2990 3849
Dhofar
Max. 9,311 9,192 11,931 14,442 15,105 16,077 14,119 13,934 16,070 14,343 11,778 10,440Dhofar
Min. 2712 3217 3473 3673 4629 4761 5111 4608 4785 4380 4293 3420
RAEC
Max. 33,950 33,887 49,645 63,641 75,592 77,191 69,859 71,010 75,058 73,115 56,400 38,676
RAEC Min. 12796 12469 15390 23767 29073 33629 35386 34010 36573 27674 18098
16218
Fig 3.2 Profile oMinimum
Demand atdifferent regionof RAEC areas oLicense (2008).
Minimum
Months
Table 3.1 Min. & Max.Demands at different regions of RAEC areas of License (2008).
-
7/27/2019 RAEC_Capability_Final.pdf
45/89
RAEC CAPABILITY STATEMENT 2009 Page 45
-
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
- 2 4 6 8 10 12 14
Khasab Power Station Diba Power Station
Madha Power Station Masandam Profile Demand
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
0 2 4 6 8 10 12
Group 1 of Power Stations Hijj Power Station
Group 2 of Power Stations Masirah Power Station
Fig 3.3 demandProfile at
Masandampower systems(2008)M
aximum
Months
Months
Maximum
demand(kW)
Fig 3.4 demand
Profile at Wustapower systems(2008)
-
7/27/2019 RAEC_Capability_Final.pdf
46/89
RAEC CAPABILITY STATEMENT 2009 Page 46
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
0 2 4 6 8 10 12 14
Shaab Esaib Power Station Group 1 of Power Stations
Saih Al Khairat Power Station Group 2 of Power Stations
0
500
1000
1500
2000
2500
3000
3500
4000
0 2 4 6 8 10 12 14
Months
Hijj Area Load Profile Fig 3.6 LoadProfile at HiijPower SysteMax. &MinWusta Regio(2008).
Fig 3.5 demanProfile at Dhopower system(2008)
Months
demandkW
Maximum
demandkW
-
7/27/2019 RAEC_Capability_Final.pdf
47/89
RAEC CAPABILITY STATEMENT 2009 Page 47
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
0 2 4 6 8 10 12 14
Max Demand Profile at Masirah PS Min. Demand Profile at Masirah PS
-
500
1,000
1,500
2,000
2,500
0 2 4 6 8 10 12 14
Max Demand Profile at Shaab Esaib PS
Min Demand Profile at Shaab Esaib PS
Fig 3.7 Load
Profile at MasirahIsland PowerSystem Max. &Min
, Wusta Region(2008)
Fig 3.8 LoadProfile at ShahabEsaib PowerSystem Max. &Min,Wusta Region(2008)
Months
Months
demandkW
demandkW
-
7/27/2019 RAEC_Capability_Final.pdf
48/89
RAEC CAPABILITY STATEMENT 2009 Page 48
-
200
400
600
800
1,000
1,200
1,400
1,600
1,800
2,000
0 2 4 6 8 10 12 14
Max Demand at Mazyouna PS Min Demand at Mazyouna PS
-
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
0 2 4 6 8 10 12 14
Max Demand at Saih Al Khairat PS Min Demand at Saih Al Khairat PS
Fig 3.9 Load Profat Al MazyunahPower System Ma&Min, DhofarRegion (2008)
Fig 3.10 Load Proat Saih Al Khairat
Power System M&Min, DhofarRegion, the area irrigation type ofdemand (2008).
Months
Months
demandkW
demandkW
-
7/27/2019 RAEC_Capability_Final.pdf
49/89
RAEC CAPABILITY STATEMENT 2009 Page 49
-
50
100
150
200
250
300
350
0 2 4 6 8 10 12 14
MaxDemand at Al Halaniat PS Min Demand at Al Hilaniat PS
0
5
10
15
20
25
30
35
1 2 3 4 5 6 7 8 9 10 11 12
Khasab Max. Demand 2008
Khasab Min. Demand 2008
Fig 3.11 LoadProfile at Al Hilaniat
Power System Max.&Min, DhofarRegion
Fig ( 3.12) LoadProfile at Khasa
Power System M&Min, MasandamRegion
Months
Months
demandkW
demandkW
-
7/27/2019 RAEC_Capability_Final.pdf
50/89
RAEC CAPABILITY STATEMENT 2009 Page 50
3.2 Forecasted Demand.
3.2.1 Demand from regions normal growth
Demand in RAEC systems has shown continuing growth due to the development at the areas of license.
Figure 3.13 and table 3.2 show the peak demand in 2006, 2007 &2008 from the trend, annual growth
has been calculated as follows: the Average demand of 2006, 2007&2008 is calculated, then annual
growth as percentage value is estimated from the difference of demand in 2008 from the average divided
by the average. Average Demand =( 2006,2007&2008)/3 , then annual growth= (Demand
2008-Average)/Average*100.
.
0
20
40
60
80
100
120
140
160
0 1 2 3 4 5 6 7 8 9
MAX.DEMA
ND(MW)
Fig 3.13 Load Projection at RAEC Power 2009-2013 (Normal growth)
Year
-
7/27/2019 RAEC_Capability_Final.pdf
51/89
RAEC CAPABILITY STATEMENT 2009 Page 51
R.S.No. R.S.Name
AvailableCapacity2009
(MW)
2006PeakDemand
(MW)
2007PeakDemand
(MW)
2008PeakDemand
(MW)
AveragePeakDemand
(MW)
AnnualGrowth
%
2009PeakDemand
(MW)
2010PeakDemand
(MW)
2011PeakDeman
(MW)
03/006 Kumzar0.80 0.70 0.240 0.840 0.770 0 0.840 0.840
0.840
03/001 Al Rawda0.22 0.160 0.130 0.135 0.142 0 0.135 0.135 0.135
03/002 Dibba13.944 8.350 9.200 11.200 9.583 17 13.089 15.298 17.87
03/004 HB Hameed0.124 0.049 0.059 0.055 0.054 1 0.056 0.056 0.057
03/005 Khasab32.908 26.900 27.700 30.000 28.200 6 31.915 33.952 36.11
03/007 Madha6.010 2.580 2.950 3.420 2.983 15 3.921 4.494 5.152
02/019 Masirah 8.478 6.470 7.290 7.500 7.087 6 7.937 8.400 8.890
02/001 AbuMudhabi0.535 0.395 0.400 0.265
02/027 Sawgrah 0.467 0.275 0.240 0.160 0.225 0 0.160 0.160 0.160
02/004 Al Kahal4.288 0.700 0.830 0.950 0.827 15 1.092 1.255 1.442
02/005 Al Khaluf1.600 0.134 0.322 0.228 41 0.455 0.642 0.907
02/006 Al Khuiaima0.96 0.590 0.680 0.750 0.673 11 0.835 0.931 1.036
02/007 Al Lakbi1.419 0.705 1.105 1.245 1.018 22 1.522 1.861 2.275
02/008 Alajaiz0.904 0.160 0.330 0.410 0.300 37 0.560 0.766 1.047
02/010 AlNajdah1.76 0.024 0.255 0.140 83 0.466 0.852 1.558
02/012 AlZhaiah0.320 0.221 0.240 0.242 0.234 3 0.250 0.258 0.267
02/016 Hij 8.48 2.830 3.350 3.425 3.202 7 3.664 3.919 4.193
02/017 Hitam1.064 0.021 0.240 0.131 84 0.441 0.812 1.493
02/025
Ras
Madraka0.863 0.400 0.590 0.845 0.612 20 1.014 1.217 1.460
02/030 Surab1.800 0.160 0.385 0.273 20 0.462 0.554 0.665
-
7/27/2019 RAEC_Capability_Final.pdf
52/89
RAEC CAPABILITY STATEMENT 2009 Page 52
02/031 Al Duqm1.060 1.330 1.270 1.420 1.340 6 1.505 1.595 1.690
02/032 Al Dhafrat1.48 -------- ------- ------- ------- 10 0.450 0.495 0.545
02/020 Masrooq0.523 0.179 0.210 0.299 0.229 30 0.390 0.508
0.663
01/001 Al Halaniyat1.280 0.255 0.260 0.320 0.278 15 0.368 0.423 0.486
01/002 Al Mathfa0.388 0.06 .06 .078 .070 10 0.078 0.086 0.095
01/005 Ayboot (1)0.396 0.085 0.095 0.109 0.096 13 0.123 0.140 0.158
01/006 Ayboot (2)0.460 0.060 0.130 0.190 0.127 50 0.285 0.428 0.641
01/007 Ayun0.596 0.142 0.170 0.180 0.164 10 0.198 0.217 0.238
01/008 Barbazum0.790 0.200 0.270 0.270 0.247 9 0.296 0.323 0.354
01/009 Bithina
01/010 Dalkut A1.184 0.700 0.880 0.790 11 0.980 1.092 1.216
01/011 Dalkut B2.502 1.531 1.630 1.581 3 1.681 1.734 1.788
01/012 Dhahabun0.783 0.410 0.430 0.460 0.433 6 0.488 0.518 0.550
01/014 Fatkhat0.368 0.072 0.105 0.115 0.097 18 0.136 0.161 0.190
01/015 Hasik 0.957 0.740 0.820 0.790 0.783 1 0.797 0.804 0.810
01/016 Hirweeb0.700 0.230 0.301 0.335 0.289 16 0.389 0.451 0.524
01/017 Horaat0.390 0.140 0.145 0.173 0.153 13 0.196 0.222 0.252
01/019 Mahwice0.318 0.115 0.120 0.119 0.118 1 0.120 0.121 0.122
01/020 Maqshan1.112 0.460 0.460 0.400 0.440 0 0.400 0.400 0.400
01/021 Mazyunah1.926 1.635 1.530 1.720 1.628 6 1.817 1.919 2.027
01/022 MirbatClosed
01/023 Mitan0.790 0.450 0.510 0.530 0.497 7 0.566 0.604 0.644
01/024 Mothorah 0.380 0.130 0.161 0.146 11 0.178 0.197 0.218
-
7/27/2019 RAEC_Capability_Final.pdf
53/89
RAEC CAPABILITY STATEMENT 2009 Page 53
Table 3.2 Estimated normal growth 2009-2011
01/025 Mudhai1.000 0.480 0.511 0.557 0.516 8 0.601 0.649 0.701
01/026 Rabkut0.640 0.160 0.230 0.250 0.213 17 0.293 0.343 0.402
01/030 SadahClosed
01/031 SadhoonClosed
01/032 Saih Alkirat16.435 2.340 3.700 4.580 3.540 29 5.926 7.666 9.919
01/033 Salalah 1Closed
01/034 Salalah 2Closed
01/035Shahb
Asayb2.800 1.645 2.016 2.260 1.974 15 2.588 2.963 3.393
01/037 Sharbatat2.182 0.640 0.680 0.620 0.647 0 0.620 0.620 0.620
01/038 Shasir2.280 2.280 0 0.000 0.000 Closed
01/039 Thumryt0.000 0.000 0.000 Closed
01/040 Tushnat0.720 0.160 0.165 0.175 0.167 5 0.184 0.193 0.203
01/004 Andat
RAEC 118.972 65.693 72.162 80.922 90.389 100.1 114.32
-
7/27/2019 RAEC_Capability_Final.pdf
54/89
RAEC CAPABILITY STATEMENT 2009 Page 54
3.2.2 Proposed new Connections to RAEC systems:
Power Demand at RAEC areas of license showing continues growth. New connections are being studied
and electrification plans are scheduled to meet requirements as per the conditions of sector law.
Applications suited to new connections in 2009 are shown in table 3.3. Tables 3.4 and 3.5 show the
planned connections in 2010 and 2011 respectively. Other bulk demands are predicated to be catered
through 2010-2011 this is concentrated in Wusta (Aduqum) and Musandam. Table 3.6 shows a list of this
bulk demands. The power demand of the new connections is planned to be met by the construction of
new 11 and 33 substation and extension works at different distribution systems at RAEC. Satisfying the
demand of the new connections with the normal growth of the connected customers in efficient and
secured criteria, requires the upgrading of many power generation capacities, constructing new power
generation stations, interlinking of existing power systems to form TSO nad DSO systems .Tables 3.3-3.7
and figures 3.14-3.18 detail the new connections to RAEC power systems (2009-2011) normal growth
and bulk demands areas and regional , the areas and regions predicated demand with number and
category of customers predicated to be connected to RAEC systems up to the end of 2011.
3.2.2.1 Planned connections in 2009
Table 3.3 bellow shows the New Connections planned to be connected to RAEC power system in 2009.
Sl.No Willayat
No. of
Cust
Demand
(kW) Project Name
1Wusta/
Aduqum947 10,000
EPC for 33/11kV Substations and 33kV Distribution Network at
Al Duqm Area in Al Wusta Region.
2 Dhofar/ Hasik 212 1,700Power Supply to New Houses in Hasik Area in Dhofar
Governorate.
3Dhofar/
Hairoon22 210
Extension of HV& LV Distribution Networks (O/H Lines & U/G
Cables ) to Give a Power Supply at Hairoon Village .
4 Wusta/ Adam 16 1,000Extension of 33kV and Lv OH lines for power supply to Ghabain Wilayat Adam.
5 Wusta/ Hijj 440 3,500
Erection of Step-Up Transformer(11/33kV) at Hijj Power
Station and Construction of 33kV Overhead Line to Masila Area
in Wilayat Mahoot Al-Wusta Region.
-
7/27/2019 RAEC_Capability_Final.pdf
55/89
RAEC CAPABILITY STATEMENT 2009 Page 55
6 Wusta/ Hijj As in 5
Construction of 33kV Overhead line and Erection of
(33/11kV)Primary Substation at Muderah North in wilayat
Mahoot in Al-Wusta Region.
7Wusta/
Mahoot52 370
Extension of 11kV and LV to feed power supply to Nafi Area at
Wilayat Mahoot in Al Wusta.
8Musandam/
Khasab361 3300
Electrical Dstribution works ( 433V & 11kV Network Extensions
) To feed power Supply To Al- Sanayia Planned Area in Wilayat
Khasab at Musandam Governorate.
9 Wusta/ Hijj As in 5Construction of 33kV Overhead line to Al-Joubah west area
wilayat Mahoot in Al-Wusta Region.
10Dhofar/ Al
Mazyunah25 240
Extension Of 433V & 11 kV Networks To Feed Power Supply To
Un- Electrified Houses At Mazyuna.
11 Wusta/ Hijj As in 5
Electrical Distribution works ( 433V & 11kV Network Extensions
) to feed power Supply to Wadi Al-Sail South at Wilayat
Mahoot Al-Wusta Region.
12Wusta/ Al
Jazir5 50
Extension of 433V and 11kV network extension to feed power
supply to Gubrah south Al Wilayat Al Jazer.
13 Wusta/ Hijj As in 5
Electrical Distribution works ( 433V & 11kV Network Extensions
) to feed power Supply to Wadi Al-Sail North Area in Wilayat
Mahoot Al-Wusta Region.
14 Wusta/ Hijj As in 5Construction of 33kV Overhead line to Muderah South area in
wilayat Mahoot Al-Wusta Region.
15 Wusta/ Hijj As in 5
Electrical Distribution works ( 433V & 11kV Network Extensions
) to feed power Supply to Muderah Area(Part-1) in Wilayat
Mahoot Al-Wusta Region.
16 Wusta/ Hijj As in 5
Electrical Distribution works ( 433V & 11kV Network Extensions
) to feed power Supply to Abu Hasab Area near Wadi Al-SailSouth at Wilayat Mahoot Al-Wusta Region.
17 Wusta/ Hijj As in 5
Electrical Distribution works ( 433V & 11kV Network Extensions
) to feed power Supply to Muderah Area(Part-2) in Wilayat
Mahoot Al-Wusta Region.
-
7/27/2019 RAEC_Capability_Final.pdf
56/89
RAEC CAPABILITY STATEMENT 2009 Page 56
18 Wusta/ Hijj 15 160Extension of 11kV and LV to feed power supply to Al Jamaza
Village area at Wilayat Al Mudhaibi in Al Shargiyah(Part 1).
19 Wusta/ Bahla 15 150
Electrical Distribution works ( 433V & 11kV Network Extensions
) To feed power Supply To Aseel Area in Wilayat Bahla in
Dakhliya Region.
20Wusta/ Al
Jazir
Extension of 11kV and Lv OHL power supply to feed Abu Tahal
area.
21Wusta/ Al
Jazir
Extension of 11kV and Lv OHL power supply to Al Ajaiz north.
22 Wusta/ Hijj As in 18
Extension of 11kV and LV to feed power supply to Al Jamaza
Village area at Wilayat Al Mudhaibi in Al Shargiyah(Part II).
22
Dhofar/
Shahab
Essaib
Extension of 33Kv O/H Lines & U/G Cables to Interlink Shahab
Asaib P/S to Dhalquot area & construction 33/11Kv Outdoor
substation at hafoof.
23Dhofar/ Horat
Extension of 33Kv overhead line for Interlinking Horat with
Mudhai(Ayboot -1) in Dhofar Governorate.
24Wusta/ Al
Jazir20 210
Electrical Distribution works ( 433V & 11KV Network Extensions
) To feed power Supply to un electrified houses at Wilayat Al-
Jazer Al Wusta Region.
25Wusta/
Mudhai
Extension of 33Kv overhead line to Interlinking Ayboot-2 with
Mudhai (Ayboot -1) in Dhofar Governorate.
26Musandam/
Dibba5 60
Extension of 433V&11KV Networks to Feed Power Supply to
Un- electrified locations at Wilayat Dibba in Musandam
Governorate.
27Wusta/ Ras Al
Jabal20 200
Electrical Distribution works ( 433V & 11KV Network Extensions
) To feed power Supply to un electrified houses and farms at
Ras Al - Jabal in Wilayat Adam.
-
7/27/2019 RAEC_Capability_Final.pdf
57/89
RAEC CAPABILITY STATEMENT 2009 Page 57
28Wusta/
Mahoot
1 2000
Electrical Distribution works ( 433V & 11KV Network Extensions
) To feed power Supply To the Sultan's Special Force Camp at
Wilayat Mahout Al Wusta Region.
29Musandam
/Khasab10 120
Extension of 433V&11KV Networks to Feed Power Supply to
Un- electrified locations at Wilayat Khasab in Musandam
Governorate.
30Musandam/
Bukha7 70
Extension of 433V&11KV Networks to Feed Power Supply to
Un- electrified locations at Wilayat Bukha in Musandam
Governorate.
31 Musandam/Khasab
10 100
Electrical Dstribution works ( 433V & 11KV Network Extensions
) To feed power Supply To Aqbath Rubia Area in Wilayat
Khasab at Musandam Governorate.
Table 3.3 New Connections to RAEC power system in 2009.
3.2.2.2 Planned connections in 2010
Table 3.4 bellow shows the New Connections planned to be connected to RAEC power system in 2010.
Sl.
NoWillayat
No. of
Cust
Demand
(kW)Project Name
1Wusta/
Aduqum20 200
Power Supply to Shuwaier Village by the extension of 28 km, 11
kV line to for Exdental Company network at the area with
distribution network and transformers.
2 Wusta/ Al Jazir 40 400Power Supply to Nafoon Village by the extension of 41km, 11 kVline from the new duqum network with distribution network and
transformers.
3 Wusta/ Mahoot 26 250
Power Supply to Habdah Village the Village can be powered by
the extension of 7 km, 11 kV line from Khaloof network with
distribution network and transformers.
-
7/27/2019 RAEC_Capability_Final.pdf
58/89
RAEC CAPABILITY STATEMENT 2009 Page 58
4Wusta/ Jalan
Bani Bu Hassan30 300
Electricity Supply to Al Juwairiah Village the Village can be
powered by the extension of 35km, 11 /33KV line from the
network with distribution network and transformers.
5 Wusta/ Mahoot 180 1500
Power Supply to Sadrah &Madrasah Village by the extension of
15km, 11 KV line from the Nafoon network with distribution
network and transformers.
6 Wusta/ Mahoot 300 2000
Power Supply to 10 villages at Wadi Sail (Daasil, Ghafat
Rashid,.) by the networkexecuted in stage 1 from Hij power
station with distribution network and transformers.
7 Wusta/ Mahoot 25 250
Power Supply to Film Village by the extension of 26 km, 11 KV
line from Hij power station with distribution network and
transformers.
8Sharqiyah/
Masirah300 3500
Power Supply to new planned area at Nahdah City by the
extension 33 KV U/G Feeders from Masirah Power Station with
distribution network and transformers.
11 Dhakiliyah/Masrooq
N/A N/A
Interlinking Masrooq area to Majan PS by the extension of 45
Km , 33 KV OHL with step/ down S/s. To implement TSO systemby the connection of Masrooq area to Majan MIS and shut down
Masrooq
12 Wusta/ Haima. N/A N/A
Construction of new primary 33/11 KV Substation at Haima and
increase its capacity to 2x20 MVA primary S/s to satisfy MoD and
the other area growth of demand requirements.
13Musandam/
Khasab15 200
Electricity Supply to Ramt Village by the extension of 3km,
11KV line from the network with distribution network and
transformers.
14Musandam/
Khasab6 80
Electricity Supply to Umais Village by the extension of 2.0km,
33KV line from the network with distribution network and
transformers.
17Dhofar/
Thamreet40 500
Electricity Supply to Bithenah Village .
-
7/27/2019 RAEC_Capability_Final.pdf
59/89
RAEC CAPABILITY STATEMENT 2009 Page 59
18Dhofar/
ThamreetN/A N/A
Install new voltage regulator at Saih al kairat to overcome the
voltage drop at the area.
19Musandam/
KhasabN/A N/A
Import and install two voltage regulators to Jabal Aqabat at
Khasab to overcome the voltage drop at the area.
21 Dhofar/ Tusnat N/A N/A
Interlinking of Tusnat network with Anadat by the extension of
15 Km , OHL ,11 kV ,33 KV configuration to shut down Tusanat
and implementing DSO system at the area.
22 Dhofar/ Hiroot N/A N/A
Interlinking of Hiroot network with Anadat by the extension of
15 Km , OHL ,11 kV ,33 KV configuration to shut down Hiroot PS
and implementing DSO system at the area.
23Dhofar/
MatorahN/A N/A
Interlinking of Matorah network with Hiroon by the extension of17 Km ,33 KV OHL to shut down Matorah and implementing DSO
system.
24Dhofar/
HirweebN/A N/A
Interlinking of Hirweeb network with Motorah by the extension
of 17 Km , OHL ,11 kV ,33 KV configuration to shut down
Hirweeb and implementing DSO system at the area.
25 Wusta/ Hitam 7 85
Power Supply to Deethab Gharb Village by the extension of 1.8
km, 11 KV line for Exdental Company network at the area with
distribution network and transformers.
26 Sharqyiah/
Masirah
10 100
Power Supply to Difiat Village by the extension of 2.5km, 11 KV
line from the network near the hotel with distribution network
and transformers.
27Sharqyiah/
Masirah7 65
Power Supply to Ghadeer Village by the extension of 1.5km, 11
KV line from the network with distribution network and
transformers.
28Sharqyiah/
MasirahN/A N/A
interlinking Hajjer B. Hameed to Madha to shut down HBH PS
and implementing DSO system at the area.
29Sharqyiah/
MasirahN/A N/A
Interlinking MoD network at Masirah to RAEC PS to form a DSO
system and Connecting MoD base at Masirah to RAEC power
station. The work should be done by the Construction of new
11/33 substations and laying of 33 KV U/G cable .
-
7/27/2019 RAEC_Capability_Final.pdf
60/89
RAEC CAPABILITY STATEMENT 2009 Page 60
Table 3.4 New Connections to RAEC power system in 2010.
3.2.2.3 Planned connections in 2011
30 All RAEC areas N/A N/A
Power Extension to customers at different areas
Extension of power to customers at different areas of North,
Wusta and south regions of RAEC
31 All RAEC areas N/A N/AReinforcement works at different areas of North, Wusta and
south regions of RAEC.
32Wusta/
Aduqum
Distribution network for Duqum residential areas Phase 1, 11kV
network, distribution transformers, LV network and connections
to 938 customers in new Aduqum residential area.
Sl.No
WillayatNo. of
Cust.
Dem.
(kW)Project Name
1
Wusta/ Adam
8 100
Power Supply to Ghabat Al Haqaf Village by the extension of 18 km,
33 KV line from PDO network at the area with distribution network
and transformers.
2
Wusta/ Adam
11 120
Power Supply to Al Mukhaiznah Village by the extension of 8 km, 33
KV line for Exdental Company network at the area with distribution
network and transformers.
3
Wusta/
Al Jazir 7 90
Power Supply to un electrified houses at South Ghubrah-Ghfoodh
Village by the extension of 30 km, 11 KV line from the existing at the
area with distribution network and transformers.
4
Wusta/ Mahoot
11 120
Power Supply to Al Baseer Village by the extension of 21 km, 11 KV
line from Madeerah 33/11 kV Ss with distribution network and
transformers.
5Sharqiyah/
Masirah44 400
Power Supply to Dowa Village by the extension of 11km, 11 KV line
from the network with distribution network and transformers.
6Sharqiyah/
Masirah26 200
Power Supply to Sur Masirah Village by the extension of 9.0km, 11
KV line from the network with distribution network and transformers.
-
7/27/2019 RAEC_Capability_Final.pdf
61/89
RAEC CAPABILITY STATEMENT 2009 Page 61
7Musandam/Dib
ba8 110
Electricity Supply to Aqabah Village by the extension of (33kV &
0.433KV Networks) to feed power supply to Aqabah Vilage
8 Musandam/Khasab
4 55 Electricity Supply to Himssi Village by the extension of 3.5km, 11KVline from the network with distribution network and transformers.
9Musandam/
Khasab6 80
Electricity Supply to Nebbah Village by the extension of 4.0km, 11KV
line from the network with distribution network and transformers.
10Musandam/Dib
ba23 250
Electricity Supply to Adas Village the extension of 28.5, 33KV line
from the network with distribution network and transformers.
11
Musandam/
Dibba 12 130Electricity Supply to Al Shaira Village by the extension 14, 33KV line
from the network with distribution network and transformers.
13Dhofar/
Rakhyut6 75
Electricity Supply to Al Hottah Village by the extension of 12 km,
11 KV line with distribution network and transformers.
14
Dhofar/
Mazyunah 30 250
Electricity Supply to Tadhoo Village by the extension of 45 , 33KV
OHL from Mudhai new power station with step up/down S/s and
D.network .
15Dhofar/
Mazyunah15 100
Electricity Supply to Qafaa Village by the extension of 30 , 11KV
OHL from Tadhoo S/s with distribution network
16Dhofar/
Mazyunah
50 750Electricity Supply to Al Hishman Village by the extension of 40,
33KV L
17
Dhofar/
Maqshin6 4000
Electricity Supply to Doka Farms By the Extension of 60 , 33KV OHL
from Saih Al Khairat power station with upgrading the power station
by adding 8.0 Mw power capacity . Works include step up/down S/S
nd all the distribution network.
18Musandam/
Dibba4 55
Electricity Supply to Maawi Village by the extension of 1.0km, 33KV
line from the network with distribution network and transformers.
19
Wusta/ Al
Jazir10 115
Power Supply to un electrified houses at North Ghubrah Village
The Houses can be powered by the extension of 7 km, 11 KV line
from the existing at the area with distribution network and
transformers.
20Sharqiyah/
Masirah28 72
Power Supply to Al Samir Village by the extension of 4.0km, 11 KV
line from the network with distribution network
-
7/27/2019 RAEC_Capability_Final.pdf
62/89
RAEC CAPABILITY STATEMENT 2009 Page 62
Table 3.5 bellow shows the New Connections planned to be connected to RAEC power system in 2011
3.2.3 Special Bulk Demands at RAEC Areas (2009-2011).
In addition to the capacity demand above, Table 3.6 details Special Bulk Demands at RAEC power systems.
21
Wusta/ Mahoot
N/A N/A
Interlinking of Al Khloof power system to Hiij by the eExtension of
53 Km , 33 KV OHL with step/up& down S/s to implementing of DSO
system and shut down Al Khloof PS.
22
Wusta/ Al
Duqum 21 150
Power Supply to Wadi Zakhir Village by the extension of 7.0km, 11
KV line from Feeder No.2 Dhahar PS with distribution network and
transformers.
23
Wusta/ Al
Duqum 7 60
Power Supply to Dithab Gharb by the extension of 1.8 km, 11 KV
line from Feeder No.2 Hitam PS with distribution network and
transformers.
24Wusta/ Aseel
4 40Power Supply to Al Shuwaaid by the extension of 5.0 km, 11 KV line
from Aseel with distribution network and transformers.
25
Wusta/
Al Duqum 2109 12,600
Distribution network for Duqum residential areas Phase 2 by the
execution of 11kV network, distribution transformers , LV network
and connections to 2109 customers in new Aduqum residential area.
No. Scope of Demand Area Demand
(MW)
Proposed Action
1 Supply of New Duqum Town with
the required demand covering the
upcoming five years .
Wusta/
Duqum
81 Construction of New power plant of total
capacity 81 MW with complete
Distribution network at 33,11 and LV
networks.
2 Power Supply to Tourism resorts at
Khasb area
Musandam/
Khasab
18 New gas power plant of capacity 120 MW
with interconnection Khasab and Dibba
power system is under study.
3 Power Supply to Oman Oil
production and treatment plants at
Khasb area
Musandam/
Khasab
33 New gas power plant of capacity 120 MW
with interconnection Khasab and Dibba
power system is under study.
-
7/27/2019 RAEC_Capability_Final.pdf
63/89
RAEC CAPABILITY STATEMENT 2009 Page 63
Table 3.6 Bulk Demands Required at RAEC Power systems.
3.2.4 Regional Forecasted Demand of RAEC systems:
Table 3.7 shows the forecasted maximum demand of RAEC systems 2009-2011
No. Region Max. Demand in
2008 (MW)
Areas forecasted
Normal Growth
Demand in
2011(MW)
Areas forecasted
Bulk Demand in
2011(MW)
Total Demand
in 2011 (MW)
1 Musandam 46 16 51 113
2 Al Sharqiyah &Wusta. 20 13 97 130
3 Dhofar 19 11 12 42
RAEC95 33 160 285
Table 3.7 Forecasted Demand at RAEC power areas.
4 Power Supply to Masirah Military
Base at Masirah area.
Sharqiyah/
Masirah
6 Construction New power station at
Masirah area is required to meet the areademand.
5 Power Supply to Doka, Khawater,
Maqshin Sofa Farms and other un
electrified villages at Dhofar area
Dhofar/ Saih
Al Khairat
12 Catering the mentioned areas with power
under study to decide the suitable option.
6 Power Supply to Omani Army at
Wusta region
Wusta/
Haima area
10 Extension of 33 kV line from PDO power
system .
-
7/27/2019 RAEC_Capability_Final.pdf
64/89
RAEC CAPABILITY STATEMENT 2009 Page 64
Musandam
46 MW
54%
Wusta
20 MW
24%
Dhofar
19 MW
22%
Masandam
113 MW
40%
Wusta
130 MW
45%
Dhofar
42 MW
15%Fig 3.15RAECareas ForecastedMax demand in2011
Fig 3.14RAECareas Max.Demand in 2008
-
7/27/2019 RAEC_Capability_Final.pdf
65/89
RAEC CAPABILITY STATEMENT 2009 Page 65
1 2 3
46
20 19
113
130
42
2008 ACTUAL MAX DEMAND (Mw) 2011 FORECASTED DEMAND
Masandam
Wusta&AlSharqyiah
Dho
far
Domestic
45%
Govermental
7%
Commercial
14%
MoD
4%
Agr.&Fisheries
5%
Hotels &Tourism13%
Industrial12%
Fig 3.16Growth
AreasDemand(2008-2011)
Fig 3.17PredicatedCategory ofRAECCustomersin 2011
-
7/27/2019 RAEC_Capability_Final.pdf
66/89
RAEC CAPABILITY STATEMENT 2009 Page 66
53.1
24.4
11.9
2.9 3.2 3.41.1
45.4
7
14
4.2 4.7
13.311.5
1 2 3 4 5 6 7
2008 Actual Maximum Demand
2011 Predicated Demand
D
omestic
Comm
ercial
Govermental
MoD
Agri&Fisheries
H
otels
&
Tourisim
Industrial
Fig 3.18 Predicated Growth in Category of RAEC Customers (2008-2011)
-
7/27/2019 RAEC_Capability_Final.pdf
67/89
RAEC CAPABILITY STATEMENT 2009 Page 67
4.0 Constraints foreseen on RAEC systems
4.1 Status of power stations with the addition of the new connections.
Due to the Projection Demand at RAEC areas power systems and the inefficient operation of many power
systems, RAEC existing power systems and stations shall be in the conditions detailed in table 4.1 bellow.
No
S.No.
P.S.Name
2009A.
CapMW
2008Peak
Dem.MW
2011Exp
peakLoad
(MW)
Sh.incap.
(MW)
Power Station Status
1 03/006 Kumzar 0.8 0.840 0.840 -0.04Predicated Demand is more than station
capacity.
2 03/001 Al Rawda 0.22 0.135 0.135 0.09Predicated Demand is more than station
capacity.
3 03/002 Dibba13.94
411.20 17.878
-
3.934
Predicated Demand is more than station
capacity.
4 03/004HB
Hameed0.124 0.055 0.057 0.067
Small un efficient DG sets
5 03/005 Khasab
32.90
8 30.00 49.000
-
16.10
Predicated Demand is more than station
capacity..
6 03/007 Madha 6.01 3.420 5.152 0.858Predicated Demand is more than station
capacity.
7 02/019 Masirah 8.478 7.500 8.890-
0.412
Predicated Demand is more than station
capacity.
8 02/001Abu
Mudhabi0.535
9 02/027 Sawgrah 0.467Predicated Demand is more than station
capacity.
10 02/004 Al Kahal 4.288Predicated Demand is more than station
capacity..
11 02/007Al Lakbi
1.419Predicated Demand is more than station
capacity..
12 02/005 Al Khaluf 1.6 0.322 0.556 1.04Large DG sets (2x1000 kW) Supplying Low
Demand
-
7/27/2019 RAEC_Capability_Final.pdf
68/89
RAEC CAPABILITY STATEMENT 2009 Page 68
13 02 /006Al
Khuiaima0.96 0.750 1.036 -0.08
Predicated Demand is more than station
capacity.
14 02/008 Alajaiz 0.904 0.410 0.708 0.196OLD DG sets (1980)
15 02/010 AlNajdah 1.76 0.255 0.441 1.32Large DG sets (2x1000kW) Supplying Low
Demand
16 02/012 AlZhaiah 0.32 0.242 0.267 0.05 Small DG sets
17 02/016 Hiij 8.48 3.425 4.193 4.287
1802/017 Hitam 1.064 0.240 0.415 0.649 Large DG sets (2x1000kW) Supplying Low
Demand
1902/025 Ras
Madraka
0.863 0.845 1.460 -0.60 Predicated Demand is more than station
capacity.
20 02/030 Surab 1.8 0.385 0.665 1.13 Large D