RAEC_Capability_Final.pdf

download RAEC_Capability_Final.pdf

of 89

Transcript of RAEC_Capability_Final.pdf

  • 7/27/2019 RAEC_Capability_Final.pdf

    1/89

    September 2009

    Rural Areas Electricity Company3 YEARCAPABILITY STATEMENT 2009-2011

  • 7/27/2019 RAEC_Capability_Final.pdf

    2/89

    RAEC CAPABILITY STATEMENT 2009 Page 2

    Table of Contents

    Topic Page

    1.0 Introduction 3

    1.1Preamble.1.2Company Background.1.3Geographic Coverage Areas.

    2.0 Information on current status of RAEC power Systems 6

    2.1 System Overview 6

    2.2 RAEC System users 122.3 Sources of electricity to RAEC Customers 172.4 Efficiency of RAEC Power systems 19

    3.0 Demand On RAEC Power systems 41

    3.1 Profile of Current Demand. 413.2 Forecasted Demand. 49

    4.0 Constrains foreseen on RAEC systems 64

    4.1 Status of power stations 644.2 Power capacities planned to be added. 664.3 Predicated power capacities at different areas of RAEC 69

    5.0 Progress of current investments 72

    5.1 Executed projects by the end of Dec. 2009. 725.2 Progress of on going projects. 73

    6.0 Future developing Plans 78

    6.1 Developing of the metering system. 786.2 Resizing of Power Plants. 786.3 Interlinking of small plants to local total systems. 796.4 Construction of Gas Power Station at Musandam area. 796.5 Implementation of Renewable energy.

    7.0 List of Figures 85

    8.0 List of Tables 87

    9.0 List of appliances 89

  • 7/27/2019 RAEC_Capability_Final.pdf

    3/89

    RAEC CAPABILITY STATEMENT 2009 Page 3

    1.0 Introduction

    1.1 Preamble

    This document has been produced in accordance with Condition 35 of the RAEC license. The RAEC

    systems are small and change relative rapidly and therefore whilst every care and diligence has been

    exercised in the preparation of this document, reader are cautioned not to rely on the information

    contained in this document for planning any major investment. Readers are strongly encouraged to

    contact RAEC to confirm the status of any network or generation station before committing to any load or

    generation project.No part of this Statement may be reproduced, stored in a retrieval system, transmitted or further

    distributed in any form or means electronic, mechanical, photocopying, recording or otherwise for any

    purpose other than with the written permission of RAEC.

    The RAEC is requested under the terms of its License, to prepare annually, a RAEC Capability Statement

    that provides, in respect of each of the three succeeding financial years:

    information on the status of existing RAEC Capacity and the anticipated requirement for new

    Capacity, including new Generation Capacity;

    commentary indicating the views of the RAEC as to those of its RAEC Systems most suited to new

    Connections and the Transmission and Distribution of further quantities of electricity;

    commentary indicating the views of the RAEC as to those of its RAEC Systems most suited to

    connecting to the Total System;

    information on any constraints foreseen on RAEC Systems;

    information relating to progress made with current investments;

    such further information as shall be reasonably necessary to enable any Person to identify andevaluate opportunities available for Connecting to a RAEC System; and

    such other matters as shall be specified in directions issued by The Authority from time to time for

    these purposes.

  • 7/27/2019 RAEC_Capability_Final.pdf

    4/89

    RAEC CAPABILITY STATEMENT 2009 Page 4

    1.2 Company Background

    The Rural Areas Electricity Company SAOC (RAECor the Company) was created in 2005 as part of

    the Transfer Scheme implementation process of the new electricity market structure. Article (84) of the

    Law for the Regulation and Privatization of the Electricity and Related Water Sector (Royal Decree No.

    78/2004) specifies the functions and powers of RAEC, whilst Article (86) specifies its duties. The

    Company License was granted by the Authority for Electricity Regulation, Oman (AER) on May 1, 2005

    and it contains 57 Conditions and subsequent modifications that together enable the Company to

    undertake its Licensed Activities. The Company is owned 99.99% by the Electricity Holding Company

    (EHC) and 0.01% by the Ministry of Finance (MOF). EHC in turn is owned 100% by MOF.

    RAEC is fully integrated utility with power generation, distribution and supply systems in the Sultanate of

    Oman. At present, power is transmitted and distributed through low voltage, 11 kV and 33 kV lines.

    RAECO has agreement with the Petroleum Developing Oman (PDO) to supply customers at areas of

    license where it is difficult to connect them systems with its own generation.

    1.3 Geographic Coverage Areas.

    The Company is licensed to carry out generation and desalination activities within its geographic area of

    responsibility. The key systems within Oman under the ownership of RAEC are scattered in 62 locationsat regions Musandam, Masirah, Al Wusta, Dhofar, Al Sharqiah (Fig 1.1) with other 21 interconnections

    with PDO. Most of power generation sites are owned and operated by RAEC. The generation assets are

    comprised of 62 locations, 6 of them includes desalination plants. As per the plans to decrease the cost of

    generation where it is applicable RAEC has been closing many generation sites and shifting customers

    supplying to the Main Interconnection System (MIS), PDO, Dhofar Power Company (DPC) to make

    Transmission system operation (TSO) or interlinking the sites near each other to a total system to make

    Distribution system operation (DSO) . In the end of 2009 the total number of producing power sites is 47

    with a total available electricity generation capacity stood at about 200.252 MW. This includes the 71.2

    MW capacity at Raysut A & B. Many of RAEC`s sites are cogeneration that are producing water in

    addition to electricity, these are located in Musandam, Masirah, Al Wusta, Dhofar and Sharqiya with a

    total installed capacity just under 2,500 m3 per day. Individual units vary in size from 50 m3 per day in Al

    Wusta to 600 m3 per day in Sharquiah. The individual diesel units vary in capacity from less than 100 kW

    at Hajar Bani Hameed to 7.5 MW at Raysut B in Salalah. There are two diesel power plants (Raysut A &

    B) located in Salalah City owned and operated by RAEC. These are used each summer period to cover

  • 7/27/2019 RAEC_Capability_Final.pdf

    5/89

    RAEC CAPABILITY STATEMENT 2009 Page 5

    current shortages of the Dhofar Power Company (DPC) grid in meeting customer peak demands. The

    operating parameters for these power plants are stipulated in the Power Purchase Agreement (PPA)

    that RAEC has with Oman PWP.

    Fig1.1: Geographic Coverage Area of RAEC Power &desalination Systems.

  • 7/27/2019 RAEC_Capability_Final.pdf

    6/89

    RAEC CAPABILITY STATEMENT 2009 Page 6

    2.0 Information on Current Status Of RAEC Power Systems

    2.1 System Overview

    RAEC`s power system consists of three phase 0.433, 11 and 33 kV systems. Electricity catered to

    customers is either generated in power stations owned and operated by RAEC or purchased from PDO in

    agreement to supply customers at areas of license where it is difficult to connect them to one of RAEC`s

    systems RAEC manages 33 kV lines, 11kV lines and 0.415 kV lines including poles, pylons, conductors

    and related equipment. This is in addition to assets such as substations, including buildings,

    transformers, bus bars, circuit breakers, control systems, protection systems and metering systems.In addition to the above, the Company has 21 interconnections with PDO, DPC and other electricity

    distribution companies within the EHC. There are also plans to have an interconnection with United Arab

    Emirates at Musandam. At present, RAEC does not have lines greater than 33 kV under its management.

    2.1.1 Technical, design and operational criteria

    RAEC system and any RAEC system users connections to the distribution system shall be designed to be

    consistent with the security requirements of the distribution and supply license. Licensed distributors shall

    ensure that the distribution system complies with the following technical, design and operational criteriain relation to the part of the distribution system at the connection site with a distribution system user.

    2.1.2 Voltage regulation

    The voltage on the 33kV and 11kV sides of distribution transformers at Connection points with the

    distribution system users shall normally be controlled within the limits +/-6.0% of the nominal value.

    During some system disturbances such as where short circuits occur, the voltage may collapse transiently

    to zero at the point of fault until the fault is cleared. Under fault and circuit

    Switching conditions, the 50 Hz Frequency component of voltage may fall or rise transiently. Thefall or rise in voltage will be affected by the method of Earthing of the neutral point of the

    distribution System and this variation in voltage shall be taken into account in selecting apparatus and

    Plant from an appropriate specification for installation on or Connection to the System. The voltage at the

    Consumers terminals shall not vary from the System nominal voltage

    by more than HV 33/11 kV +6.0% to6.0%,

  • 7/27/2019 RAEC_Capability_Final.pdf

    7/89

    RAEC CAPABILITY STATEMENT 2009 Page 7

    LV415/240 V +6.0% to6.0%

    2.1.3 Frequency deviations

    The Frequency of the RAEC Systems shall be nominally 50.00 Hz with System Frequency set points

    between 49.95Hz and 50.05Hz. Normal control deviations will not exceed 49.90Hz to 50.10Hz. Under

    transient disturbed conditions, System Frequency could rise to 51.50Hz or fall to 48.00Hz.

    2.1.4 Voltage waveform quality

    All apparatus and Plant Connected to the Distribution System, and that part of the

    Distribution System at each Connection Point, should be capable of withstanding the following

    distortions of the voltage waveform in respect of harmonic content and phase unbalance.

    The maximum total levels of harmonic distortion on the Distribution System at 33 and 11kV, from all

    sources under both normal, planned outage and fault outage conditions, shall not

    exceed a total harmonic distortion of 2.0% with no individual harmonic greater than 1.5% unless

    abnormal conditions prevail. At LV, the maximum total levels of harmonic distortion from all

    sources shall not exceed a total harmonic distortion of 2.5%.The maximum negative phase sequence

    component of the phase voltage on the Distribution

    System should remain below 1.0% unless abnormal conditions prevail. A maximum value of 2.0%ispermitted for phase unbalance.

    2.1.5 Voltage fluctuations

    Voltage fluctuations, arising from fluctuating Demands Connected at a Connection Point to

    the Distribution System, shall not exceed 1.0% of the voltage level for step changes that may occur

    repetitively. Any large voltage excursions, other than step changes, may be allowed up to a level of 3.0%

    provided that this does not constitute a risk to the Distribution System or to any Distribution System User.

    2.1.6 Distribution Networks

    The network topologies associated with RAEC power systems range from compact 11, 33 kV ring

    systems supplying small towns like Khasab, Dibba, Masirah, new town at Al Duqm through to wide area

    radial systems interconnecting diesel generator power stations like, Al Jazir area , Saih Al Khairat, Shaab

    Esaab, Mudhi, Ras Madrakah, Abu Mudhabi, etc. These areas involve nodes connected as a string with

  • 7/27/2019 RAEC_Capability_Final.pdf

    8/89

    RAEC CAPABILITY STATEMENT 2009 Page 8

    many kilometers 11 or 33 kV circuits. With compact systems (in towns) resupply arrangements (creating

    a ring) is provided for securing power , whereas with most RAEC systems radial system is used because

    the cost of resupply arrangements will be prohibitive due to the long distances involved. Table 2.1 bellow

    shows the main equipment and materials used in design and construction of RAEC power distribution

    networks. All equipment and materials should be specified according to OES as minimum.

    Table 2.1: Standard Equipment and materials used in RAEC Power Distribution Systems

    Equipment Size/Rating

    11 /33 kV Step Down Transformer rating G/M 1,3, 6,10 &20 MVA

    11 kV switchgear rating 1250A (Incomer & Bus section) 400 / 630A (Feeder)

    11 kV RMU. 400/200 A.

    33 kV switchgear rating 1250 A & 630A

    33/0.433 kV Transformers P/M 200, 315 kVA

    11/0.433 kV Transformers P/M 100, 200, 315 kVA

    11/0.433 kV Transformers G/M 500, 1000 kVA

    11kV Overhead lines Wolf (150mm2 ACSR)

    AAAC 95

    AAAC 195

    Dog (100mm2 ACSR)

    LV Overhead lines 200 mm2 AL conductor XLPE Insulated

    120 mm2 AL conductor XLPE Insulated

    33kV Overhead lines Panther (200mm2 ACSR)

    Wolf (150mm2 ACSR)

    AAAC 24033 kV Under Ground Cables 3C 300 mm2 CU XLPE

    11 kV Under Ground Cables 3C 240, 185, 120, 70, 50 mm2 & 1C x 500 mm2 CU

    XLPE

    LV Under Ground Cables 4CX 240,185,120,70,50,35 &1CX630 CU XLPE

  • 7/27/2019 RAEC_Capability_Final.pdf

    9/89

    RAEC CAPABILITY STATEMENT 2009 Page 9

    2.1.7 Power generation systems:

    At present RAEC owned 62 power sites of different capacities scattered in Musandam, Wusta, Dhofar

    and Al Sharqiyah regions (table 2.3). The majority of the sites contain power generation sets (DG sets)

    with distribution networks and are operated by the RAEC through operation and maintenance (O&M)

    contractors. Other sites are being closed and the equipment of useful remaining operating life from the

    closed stations are being relocated to power systems which are being implemented or resized by RAEC at

    different locations in its area of license.

    The number of power stations currently being operated by RAEC is 47 at different areas in Oman. Thepower stations are equipped by standard equipment and machines as per table 2.2.

    The power stations sizes and efficiencies are being analyzed to establish a plan for improving power

    system performance at different areas in RAEC licensed area.

    Table 2.2: Standard Equipment used in RAEC Power Generation Stations.

    Equipment Size/Rating

    Diesel Generator Sets Different Ratings from 32 KW up to 7800 KW at different out put

    voltages. 0.433, 3.3 &11 KV. Operating speed ranging from 600 RPM

    up to 1500 RPM. Output power Frequency is 50 Hz.

    0.433 KV switchgear Rating Up to 3500 A

    0.433 /11 KV Step Up Transformer

    rating

    600-1600 KVA

    3.3 /11 KV Step Up Transformer rating Up to 4400 KVA

    11 /33 KV Step Down Transformer

    rating G/M

    1,3, 6,10 &20 MVA

    11 kV switchgear rating 1250A (Incomer & Bus section)

    400 / 630A (Feeder)

    11 KV RMU. 400/200 A.

    33 kV switchgear rating 1250 A & 630A

  • 7/27/2019 RAEC_Capability_Final.pdf

    10/89

    RAEC CAPABILITY STATEMENT 2009 Page 10

    Table 2.3 bellow shows the power generation sites that being owned and operated by RAEC, many of

    these sites are closed at present and assets being shifted to other sites or sold. Customers are being

    shifted to TSO or DSO.

    No. R.S.No. R.S.Name Region TypeYear ofstarting

    operation

    No. ofDG units

    installedcapacity(MW)

    Availablecapacity (MW)

    1 03/006 Kumzar Musandam Cogen. 1984 2 0.936 0.8

    2 03/001 Al Rawda Musandam Electricity 1996 3 0.275 0.22

    3 03/002 Dibba Musandam Electricity 1978 8 17.43 13.944

    4 03/004 HB Hameed Musandam Electricity 1994 2 0.1 0.124

    5 03/005 Khasab Musandam Electricity 1982 10 41 32.908

    6 03/007 Madha Musandam Electricity 1982 8 7.516 6.01

    7 02/001 AbuMudhabi Wusta Cogen. 1985 6 0.608 0.535

    8 02/027 Sawgrah Wusta Cogen. 1998 4 0.874 0.467

    9 02/004 Al Kahal Wusta Electricity 1999 4 2.378 4.288

    10 02/005 Al Khaluf Wusta Electricity 2007 2 2 1.6

    11 02/006 Al Khuiaima Wusta Electricity 2004 4 1.168 0.96

    12 02/007 Al Lakbi Wusta Electricity 1998 5 1.772 1.419

    13 02/008 Alajaiz Wusta Electricity 2006 4 1.13 0.904

    14 02/010 AlNajdah Wusta Electricity 2007 3 2.2 1.76

    15 02/012 AlZhaiah Wusta Electricity 2003 2 0.4 0.32

    16 02/016 Hij Wusta Electricity 1999 7 10.5 8.48

  • 7/27/2019 RAEC_Capability_Final.pdf

    11/89

    RAEC CAPABILITY STATEMENT 2009 Page 11

    17 02/017 Hitam Wusta Electricity 2007 5 1.33 1.064

    18 02/025 Ras Madraka Wusta Electricity 1999 5 1.071 0.863

    19 02/030 Surab Wusta Electricity 2006 3 2.2 1.8

    20 02/031 Al Duqm Wusta Electricity 1999 5 1.331 1.06+mobile dg

    21 02/032 Al Dhafrat Wusta Electricity 2008 4 1.86 1.48

    22 02/020 Masrooq Wusta Electricity 1994 6 0.712 0.523

    23 02/019 Masirah Sharqiyah Cogen. 1976 10 10.597 8.478

    24 BB Hassan Sharqiyah Electricity 1980 Closed Closed

    25 Al Kamil Sharqiyah Electricity 1980 Closed Closed

    26 Mudhairib Sharqiyah Electricity 1980 Closed Closed

    27 Al Mudaibi Sharqiyah Electricity 1980 Closed Closed

    28 Sur Sharqiyah Cogen. 1978 Closed Closed

    9 01/001 Al Halaniyat Dhofar Cogen. 1985 4 0.544 1.28

    30 01/002 Al Mathfa Dhofar Electricity 2002 3 0.46 0.338

    31 01/005 Ayboot (1) Dhofar Electricity 2002 3 0.46 0.396

    32 01/006 Ayboot (2) Dhofar Electricity 2006 3 0.7 0.46

    33 01/007 Ayun Dhofar Electricity 2000 3 0.69 0.596

    34 01/008 Barbazum Dhofar Electricity 2000 3 0.88 0.79

    3501/009

    Bithina Dhofar Electricity ---Under

    Construction

    36 01/010 Dalkut A Dhofar Electricity 1992 4 1.48 1.184

    37 01/011 Dalkut B Dhofar Electricity 1997 5 3.128 2.502

    38 01/012 Dhahabun Dhofar Electricity 2000 3 0.879 0.783

    39 01/014 Fatkhat Dhofar Electricity 2002 3 0.416 0.368

  • 7/27/2019 RAEC_Capability_Final.pdf

    12/89

    RAEC CAPABILITY STATEMENT 2009 Page 12

    40 01/015 Hasik Dhofar Electricity 1992 3 1.196 0.957

    41 01/016 Hirweeb Dhofar Electricity 2001 3 0.775 0.70

    42 01/017 Horaat Dhofar Electricity 2002 3 0.49 0.39

    43 01/019 Mahwice Dhofar Electricity 2002 3 0.362 0.318

    44 01/020 Maqshan Dhofar Electricity 2001 4 1.29 1.112

    45 01/021 Mazyunah Dhofar Electricity 1995 5 2.408 1.926

    46 01/023 Mitan Dhofar Electricity 2001 3 0.885 0.79

    47 01/024 Mothorah Dhofar Electricity 2006 2 0.44 0.38

    48 01/025 Mudhai Dhofar Electricity 1992 4 1.084 1.00

    49 01/026 Rabkut Dhofar Electricity 2000 3 0.75 0.64

    50 01/030 Sadah Dhofar Electricity 1978 Closed Closed

    51 01/031 Sadhoon Dhofar Electricity Closed Closed

    52 01/032 Saih Alkirat Dhofar Electricity 2006 8 8 16.435

    53 01/033 Salalah 1 Dhofar Electricity 1974 Closed Closed

    54 01/034 Salalah 2 Dhofar Electricity Closed Closed

    55 Raysut A Dhofar Electricity 1983 36 28.8

    56 Raysut B Dhofar Electricity 1973 53 42.4

    5701/035 Shahb

    AsaybDhofar Electricity 1999 4 3.5 2.8

    58 01/037 Sharbatat Dhofar Electricity 1999 5 2.722 2.18

    59 01/038 Shasir Dhofar Electricity Closed Closed

    60 01/039 Thumryt Dhofar Electricity 1993 Closed Closed

    61 01/040 Tushnat Dhofar Electricity 2001 3 0.85 0.72

    6201/004

    Andat Dhofar Electricity --------UnderConstruction

    Total RAEC 232.777 200.252

  • 7/27/2019 RAEC_Capability_Final.pdf

    13/89

    RAEC CAPABILITY STATEMENT 2009 Page 13

    Table 2.3: Power generation sites owned and operated by RAEC and their availablecapacities in 2009.

    2.2 RAEC System UsersThe total Number of customers connected to RAEC systems in the end of 2008 was 18, 851, and 86.4%

    of them are powered from power generation stations owned and operated by RAEC. The remaining

    13.6% are at areas difficult to be connected to RAEC systems and they are near PDO power plants,

    therefore RAEC has PPA with PDO to feed customers at the area of its license. Table 2.4 and Figures 2.1,

    2.2&2.3 detail the percentage of number of customers, Load and Energy Demand of customers fed from

    RAEC power generation stations and PDO.

    In case of power interruption RAEC temporally caters power to customers from mobile DG sets.

    Table 1.1 Details the total number of RAEC customers with the maximum Load and the total energy

    consumed in 2008 and the total energy consumed.

    86.4%

    13.6%

    No. of Customers Catered from RAEC system

    No. of Customers catered from PDO power generation system

    Source ofpower

    No. ofCustomers

    Max. Load(MW) 2008

    EnergyDemand(MWH) 2008

    RAEC 16,280 81272,936

    PDO 2,571 14 38,606

    Table 2.4 RAEC customers

    Fig 2.1 Percentage ofCustomers Powered frRAEC and PDO powerstations in the end of

    2008 .

  • 7/27/2019 RAEC_Capability_Final.pdf

    14/89

    RAEC CAPABILITY STATEMENT 2009 Page 14

    15%

    11%

    89%

    MWH Demand from PDO

    power generation

    system

    MWH Demand catered

    from RAEC power

    system

    Total 18,851 95 311,542

    Fig 2.3 Percentagtotal 2008 Energysupplied from RA

    and PDO power

  • 7/27/2019 RAEC_Capability_Final.pdf

    15/89

    RAEC CAPABILITY STATEMENT 2009 Page 15

    2.2.1 Type of RAEC systems Users.

    The RAEC is supplying power to customers at rural areas; therefore the main loads are domestic,

    governmental commercial and farms. Industrial loads are very small. Figures2.4, 2.5, 2.6&2.7 and

    Tables2.5, &2.6 show the classification of customers with their maximum load and total demand in 2008

    at RAEC regions.

    Type of CustomerNo.

    2008

    Percentage %Demand MWH

    2008

    Percentage

    %Domestic 13,603 72.2 165,400 53.1

    Governmental 2,021 10.7 76,066 24.4

    Commercial 2,989 15.8 37,072 11.9

    MOD 39 0.2 9,002 2.9

    Agr. &Fisheries 168 0.9 10,053 3.2

    Hotels &Tourism 20 0.1 10,643 3.4

  • 7/27/2019 RAEC_Capability_Final.pdf

    16/89

    RAEC CAPABILITY STATEMENT 2009 Page 16

    2.2.2 Regional number and maximum Load of RAEC systems Users:

    25%

    12%

    De

    A

    Industrial 11 0.1 3,306 1.1

    RAEC Total 18,851 100 311,542 100

    Table 2.5:Numberand type ofcustomersconnectedto RAECsystems in2008

  • 7/27/2019 RAEC_Capability_Final.pdf

    17/89

    RAEC CAPABILITY STATEMENT 2009 Page 17

    17%

    50%

    33%No. of Customers at

    Dhofar

    No. of Customers at

    Musandam

    No .of Customers at

    Wusta& Sharqiyah

    RAEC AreasNo. ofCust.

    Maximum Load(MW) IncludingPDO Supply

    Maximum Load (MW)excluding PDO supply

    Wusta 6262 30 18.45

    Musandam 9369 45.6 45.6

    Dhofar 3221 19.4 16.88

    Fig 2.5 Percentageof Customers atRAEC areas

    Table 2.6 :Numbers ofCustomers andMax. Load in 2008at RAEC areas

  • 7/27/2019 RAEC_Capability_Final.pdf

    18/89

    RAEC CAPABILITY STATEMENT 2009 Page 18

    48%

    32%

    20%

    Musandam Max. Demand (MW)

    Wusta Max. Demand(MW)

    Dhofar Max. Demand (MW)

    56%

    23%

    21%

    Musandam Max Load MWWusta &Sharqiyah Max Load MW

    Dhofar Max Load MW

    Fig 2.7 Percentage ofLoad excludingsupplied from PDO

    Fig 2.6 Percentage ofLoad includingsupplied from PDO

  • 7/27/2019 RAEC_Capability_Final.pdf

    19/89

    RAEC CAPABILITY STATEMENT 2009 Page 19

    2.3 Sources of Electricity Supply to RAEC customers

    2.3.1 Regional Available Power Generation Capacity of RAEC power Systems:

    Figure2.8 and Table2.7 show the total existing power generation capacity of RAEC system, and figure2.9

    & table 2.8 Detail the regional power generation capacities of RAEC systems.

    63%

    37%

    RAECPower

    Capacity

    for RAEC

    CustomersRAEC

    Power

    Capacity

    for PPA

    with PWP

    48%

    29%

    23%

    Musandam

    Available

    capacity MW

    Wusta &Al

    Sharqiyah

    available

    capacity MWDhofar

    available

    capacity MW

    RAEC Power Generation

    CapacityMW

    Connected to

    Customers under RAEC

    License

    119.34

    PPA with PWP 71.2

    Total 190.5

    RAEC AreasMaximumLoad from

    RAEC system

    (MW) 2008

    AvailableCapacity

    (MW)

    Musandam 45.6 58

    Wusta 18.45 35

    Dhofar 16.88 27.5

    Fig 2.8 Percentage of RAEC available capacity

    Table 2.7 Available power

    generation capacity of RAEC

    power stations including Raysut

    A&B power houses

    Fig 2.9 Regional Percentage of RAEC available power generationcapacity excluding Raysut A&B.

    Table 2.8 Regional available power

    generation capacity of RAEC powerstations excluding Raysut A&B power

    Stations

  • 7/27/2019 RAEC_Capability_Final.pdf

    20/89

    RAEC CAPABILITY STATEMENT 2009 Page 20

    2.3.2 RAEC Power Systems Interconnected to PDO.

    RAECO has agreement with the Petroleum Developing Oman (PDO) to supply customers at areas of

    license where it is difficult to connect them systems with its own generation as per table 2.9.

    Table 2.9 RAEC interconnections with PDO

    ID Region RSName RSNumber TypeMax.

    Load

    (MW)

    1 9221 Al Wusta Ghobra 02/034 Interconnection 0.419

    2 9234 Al Wusta Nahadah/Jabel ras 02/035 Interconnection 1.066

    3 9245 Al Wusta Wadi Buthaila 02/036 Interconnection 0.123

    4 9044 Al Wusta Natih 02/022 Interconnection N/A

    5 9001 Al Wusta Alnuhaidah 02/011 Interconnection N/A

    6 9012 Al Wusta Bahja 02/013 Interconnection N/A

    7 9026 Al Wusta Namur 02/021 Interconnection N/A

    8 9055 Al Wusta Qarn Alalam 02/024 Interconnection N/A

    9 9063 Al Wusta Rima 02/026 Interconnection N/A

    10 9080 Dhofar Al Shuwaimia 01/003 Interconnection N/A

    11 9087Dhofar Amal (Shuwaimia &

    Shaleem)01/045 Interconnection 2.133

    12 9102 Dhofar Dimeet 01/013 Interconnection 0.252

    13 9113 Dhofar Kabut 01/018 Interconnection 0.169

    14 9131 Dhofar Shaleem 01/036 Interconnection N/A

    15 9137 Dhofar Wadi Arah 01/041 Interconnection 0.190

    16 9155 Dhofar Wadi Haka 01/042 Interconnection N/A

    17 9166 Dhofar Wadi Rahab 01/043 Interconnection N/A

    18 9176 Dhofar Zakhar 01/044 Interconnection N/A

    19 9185 Musandam Sheesa 03/009 Interconnection N/A

    20 9198 Al Wusta Haima 02/032 Interconnection 7.362

    21 9209 Al Wusta Wadi Aswad 02/033 Interconnection 1.979

    Total Maximum Interconnected Load (MW) 13.693

  • 7/27/2019 RAEC_Capability_Final.pdf

    21/89

    RAEC CAPABILITY STATEMENT 2009 Page 21

    2.4 Efficiency of RAEC Power Systems

    2.4.1 Power Loss.

    The Total Energy metered at customer metering equipment is different from the total energy sent from

    the power generation stations; this is due to power losses (technical and un technical). Figure 2.10 and

    Table 2.10 show the calculated loss at RAEC individual areas and the loss calculated for combined RAEC

    systems.

    0

    5

    10

    15

    20

    25

    RAEC

    Wustaa

    Dhofar

    Musanda

    m

    Power Loss at RAEC Power Systems

    AreaPower Units Sent

    (kWh)Power Units

    Metered (kWh)Losses %

    Musandam

    191,536,982 162,313,183 15.26

    Dhofar 77,683,928 61,923,802 20.29

    Wusta & shar 101,053,959 87,304,885 13.61

    RAEC 370,274,869 311,541,870 15.86

    Figure2.10:Regional& RAECpowerLoss

    Table 2.10Summeryof RAEC

    regionalPowerLoss

  • 7/27/2019 RAEC_Capability_Final.pdf

    22/89

    RAEC CAPABILITY STATEMENT 2009 Page 22

    Table 2.11 below details the losses of RAEC power systems calculated by the comparison of energy sent

    from power stations and that metered by customers energy meters through billing system. From the

    analysis it is shown that losses are very high in many systems while are very low in others, many power

    systems show that power metered for billing is more than that Sent from the power house, this is

    because of many factors such as, inaccurate metered data, power supplied without metering, rented

    power which is not added to power sent, etc. Power losses in the remaining power systems can`t be

    calculated since the billing system covers metering in area bases not on system where many areas are

    being powered from more than power station.

    S.No.

    AREACODE &NAME

    Consumed(Units)Gover.

    Consumed(Units)

    (Private)

    Total(Units)

    Total UnitsSent kWh

    TotalLoss %

    1 8 KHASAB - E 20,689,175 59,289,219 79,978,394 128,116,585 17.7

    2 9 DIBBA - E 9,267,347 35,813,202 45,080,549 49,311,010 8.6

    3 83 BUKHA - E/W 6,774,028 10,857,897 17,631,925 Khasab

    4 84 ROWDHA 841,376 170,773 1,012,149 345,229 Khasab

    5 85 MADHA - E/W 2,309,941 9,525,939 11,835,880 14,552,305 18.7

    6 86 QUIDA - E/W 1,219,971 2,634,277 3,854,248 Khasab

    7 87 KHUMZAR - 716,672 2,189,021 2,905,693 Khasab

    8 88 SHISHA - E/W 112,480 238,596 351,076 Khasab

    9 89 AL NUZAIF - E 50,347 621,186 671,533

    10 92 MAHOOT 4,009,745 9,467,080 13,476,825 14,955,468 9.9

    11 93 DAKHOOM 3,301,265 4,096,273 7,397,538 5,897,942 -25.4

    12 94 JAZIR - E / W 2,186,029 5,295,321 7,481,350 9,289,556 19.5

    13 96 MASIRAH - E 2,899,250 21,334,404 24,233,654 25,749,655 5.9

    14 98 KHOAIMA -E 608,203 1,343,820 1,952,023 3,634,419 46.3

    15 100 MASROOQ 7,741 237,109 244,850 479,224 48.9

    16 102 ZAHIYAH 183,471 350,949 534,420 756,096 29.3

  • 7/27/2019 RAEC_Capability_Final.pdf

    23/89

    RAEC CAPABILITY STATEMENT 2009 Page 23

    Table 2.11 Calculated losses at many of RAEC`s power systems.

    17 40 AIBOOT-2 125,618 264,677 390,295 734,056 46.8

    18 42 FATKHEET 95,744 194,492 290,236 339,068 14.4

    19 43 MAHVEES 63,441 196,897 260,338 304,663 14.5

    20 44 HEBROT-ABT1 118,990 206,992 325,982 783,132 58.4

    21 45 MUTHAFAH 45,108 69,069 114,177 124,807 8.5

    22 46 HAROOT 84,759 295,743 380,502 422,105 9.9

    23 47 MAQSHAN 760,327 436,412 1,196,739 1,369,810 12.6

    24 48 HERWAIB 453,066 660,001 1,113,067 1,057,760 -5.2

    25 49 METAN 403,163 954,576 1,357,739 1,915,654 29.1

    26 51 TOSENAT 393,776 51,222 444,998 802,758 44.6

    27 54 BARBAZOOM 136,804 588,419 725,223 1,055,300 31.3

    28 55 AAYOON 46,393 252,879 299,272 285,763 -4.7

    29 56 DHABOON 193,499 1,075,080 1,268,579 1,354,411 6.3

    30 57 RABKOOT 155,016 482,921 637,937 726,764 12.2

    31 58 SHAHBASAHEB 2,106,423 2,343,680 4,450,103 8,581,440 48.1

    32 59 AL HALANIAT 159,895 127,384 287,279 929,090 69.1

    33 61 AL SHASAR 3,696,369 12,984,070 16,680,439 23,354,025 28.6

    34 62 AL MAZEUNA 1,996,738 3,497,710 5,494,448 7,302,521 24.8

    35 70 SHARBATAT 792,504 2,003,987 2,796,491 2,867,290 2.5

    36 72 MUDHAI 537,677 1,255,593 1,793,270 1,689,125 -6.2

    37 80 HASIK 793,913 2,483,576 3,277,489 3,418,198 4.1

    38 97 DHALKOOT 3,395,389 3,239,351 6,634,740 7,783,510 14.8

    39 98 RAYKHUIT 1,699,732 1,424,243 3,123,975 726,764

  • 7/27/2019 RAEC_Capability_Final.pdf

    24/89

    RAEC CAPABILITY STATEMENT 2009 Page 24

    2.4.2 Efficiency of Power Stations

    Combinations of DG with different generation capacities are used in RAEC Power stations. The DG sets

    are connected in parallel to get the required power capacity of the power station. Synchronizing of the

    DG sets is being done automatically and/or manually. Power evacuated is connected to common

    switchgears and supplied to customers by .0.433, 11 or 33 kV lines. The main factors considered in

    selecting the type and size of the DG sets are the base load, the maximum and minimum demand and

    power security standard of the demand predicated in the considered area.

    The output energy per litre is used to calculate the outage of each power station. The efficiency of each

    power station is calculated with reference to (10.8 kWh/litre) which is an international reference value.

    Fig 2.11 and table 2.12 detail the generated energy per litter and efficiency of existing RAEC power

    stations.

    0

    5

    10

    15

    20

    25

    30

    35

    40

    0 10 20 30 40 50 60

    Ece%

    Power Station Number

    RAEC Power Stations Efficiency

    RAEC

    Power

    Stations

    Efficiency

    RAEC

    average

    efficiency,

    31%

    Fig 2.11 Efficiency of Power Stations

  • 7/27/2019 RAEC_Capability_Final.pdf

    25/89

    RAEC CAPABILITY STATEMENT 2009 Page 25

    No.

    Powe

    r

    Station

    Fuel

    Consump

    (2008)

    Litter

    Gene

    rate

    dEne

    rgy

    (2008)

    kWh

    kWh/L.

    PSE

    ff.%

    No.

    Powe

    r

    Station

    Fuel

    Consump

    (2008)

    Litter

    Gene

    rate

    dEne

    rgy

    (2008)

    kWh

    kWh/L

    PSEff.%

    1 Khasab 36,425,952 135,574,000 3.72 34.5 26 Ayoon 120,000 296,352 2.47 22.9

    2 Dibbah 14,822,185 53,052,960 3.58 33.1 27 Rabkut 250,000 738,215 2.95 27.3

    3 Madah 4,220,652 15,150,830 3.59 33.2 28Sha.Assaib

    2,684,900 8,659,307 3.23 29.9

    4 HBH 111,000 207,544 1.87 17.3 29Mazyonah

    2,300,800 7,329,410 3.19 29.5

    5 Rawda 207,000 383,232 1.85 17.1 30 Makshan 448,000 1,410,950 3.15 29.2

    6 Masrooq 227,500 515,749 2.27 21 31 Mittan 720,000 1,922,010 2.67 24.7

    7 Al Lakbi 2,057,070 5,808,441 2.82 26.1 32 Tushnat 340,000 815,885 2.40 22.2

    8 RasMadraka

    1,312,130 3,431,960 2.62 24.2 33 Harweeb 460,000 1,068,545 2.32 21.5

    9 Al Duqm 2,102,390 5,901,953 2.81 26 34 Mahwise 140,000 315,938 2.26 20.9

    10 Al Kahal 1,255,690 3,517,127 2.80 25.9 35 Howrat 220,000 437,936 1.99 18.4

    11 Hij 5,197,970 15,007,120 2.89 26.7 36 Matafa 70,000 128,855 1.84 17

    12 Al Zahia 289,990 791,185 2.73 25.3 37 Fatkeet 140,000 349,825 2.50 23.1

    13 Khuiaima 1,237,650 3,728,791 3.01 27.9 38 Ayboot1 190,000 371,933 1.96 18.1

    14 Hitam 542,160 873,801 1.61 14.9 39 Ayboot2 200,000 393,580 1.97 18.2

    15 Khaloof 509,640 1,020,827 2.00 18.5 40 Saih kirat 6,006,000 23,457,500 3.91 36.2

    16 Sarab 400,420 1,072,270 2.68 24.8 41 Mothorah 200,000 447,011 2.24 20.7

    17 AlNajda 254,780 460,735 1.81 16.7 42 Masirah 9,145,500 32,572,840 3.56 33

    18 Alajaiz 646,090 1,258,283 1.95 18 43 Kumzar 313,084 850,590 2.72 25.2

    19 Dhalqut A 720,000 2,322,657 3.23 29.9 44AbuMudabi

    191,150 490,817 2.5723.8*

    *

    20 DhalqutB 1,795,000 5,466,718 3.05 28.2 45 Sograh 14,000 8,860 0.63 5.9**

    21 Hassik 1,065,000 3,372,307 3.17 29.3 46Hallaniyat

    400,000 1,303,290 3.26 30.2

    22 Sharbatat 978,000 2,856,598 2.92 27 47 Raysut A 1,190,800 0

    23 Mudhai 820,000 1,694,665 2.07 19.1 48 Raysut B 300,000 0

    24 Barbazom 388,000 1,073,135 2.77 25.6

    25 Dhaboon 460,000 1,352,260 2.94 27.2 RAEC104,090,503

    349,264,797 3.36 31.1

    ** Power Stations are closed

    Table 2.12: Summary of RAEC Power Stations Efficiencies

  • 7/27/2019 RAEC_Capability_Final.pdf

    26/89

    RAEC CAPABILITY STATEMENT 2009 Page 26

    2.4.3 Cost of Generating Power Unit

    0

    50

    100

    150

    200

    250

    300

    350

    400

    0 10 20 30 40 50

    PerCostBz/Kwh

    Power Station Number

    R.S.No. No. P Station Name

    per unit Gen.

    cost BZ/kWh

    03/001 1 Al Rawda 107

    03/002 2 Dibba 43

    03/004 3 HB Hameed 191

    03/005 4 Khasab 41

    03/007 5 Madha 47

    02/019 6 Masirah 57

    02/001 7 AbuMudhabi 101

    02/004 8 Al Kahal 67

    02/005 9 Al Khaluf 103

    02/006 10 Al Khuiaima 62

    02/007 11 Al Lakbi 63

    02/008 12 Alajaiz 107

    02/010 13 AlNajdah 120

    02/012 14 AlZhaiah 126

    02/016 15 Hiij 55

    02/017 16 Hitam 131

    02/025 17 Ras Madraka 70

    02/030 18 Surab 82

    02/031 19 Al Duqm 59

    02/020 20 Masrooq 152

    01/001 21 Al Halaniyat 88

    01/002 22 Al Mathfa 377

    01/005 23 Ayboot (1) 185

    01/006 24 Ayboot (2) 177

    01/007 25 Ayun 196

    01/008 26 Barbazum 93

    01/010 27 Dalkut A 64

    01/011 28 Dalkut B 60

    01/012 29 Dhahabun 81

    01/014 30 Fatkhat 171

    01/015 31 Hasik 65

    01/016 32 Hirweeb 138

    01/017 33 Horaat 164

    01/019 34 Mahwice 196

    01/020 35 Maqshan 131

    01/021 36 Mazyunah 61

    01/023 37 Mitan 90

    01/024 38 Mothorah 242

    01/025 39 Mudhai 10701/026 40 Rabkut 107

    01/032 41 Saih Alkirat 44

    01/035 42 Shahb Asayb 57

    01/037 43 Sharbatat 75

    01/040 44 Tushnat 132

    Total RAEC 52

    Cost of power generation units consists from the cost of

    fuel, oils, spare parts and operation and maintenance costs.

    As mentioned Previously RAEC power stations are of

    different types and capacities and located in isolated areas

    in Oman, therefore cost of generating power units is

    different from site to site.

    Figure 2.12 and table 2.13 show the generated per unit

    costs of RAEC power stations in all areas of license. Cost of

    power distribution and billing is excluded.

    From the table it is shown that per unit cost of generation

    of most Power Stations is more than RAEC average value.

    Fig 2.12: Per unit cost of generation of RAEC Powerstations

    Table 2.13: Per unit cost of generation of RAECPower stations

  • 7/27/2019 RAEC_Capability_Final.pdf

    27/89

    RAEC CAPABILITY STATEMENT 2009 Page 27

    2.4.4 Case Studies of Power Flow.

    By the use of ReticMaster Software Case Studies of power flow, loss, and voltage drop in 11 and

    33 KV systems from different RAEC systems of demand more than 1 MW in 2008 has been done

    with the following assumptions:

    Single Line Diagrams of Power circuits in 2008 are used.

    Maximum Loads in summer 2008 were used in the analysis. If detail loads on each 11/

    0.433 KV transformer not available, the maximum loads in summer 2008 have been

    distributed among loading areas with reference to a load factor depends on the existing

    capacity of equipment to the maximum load at the feeder. The load values are used for thecalculation of load flow, power loss and voltage drop calculations.

    The available specifications of equipment are used in calculations, in case specifications not

    enough for calculations, specifications of standard equipment were determined from the

    software library.

    Power Factor was assumed to be 0.85 or 0.8.

    Calculations were done for the existing status of systems.

    Power Flow analysis, losses and voltage drop calculations have been done using the ReticMaster.

    The ReticMaster 2008 used for power flow analysis has the technical specifications detailed below:

    Technologies

    Combined High, Medium and Low voltage technologies, simulations with unbalance and

    diversityinclude:

    Delta or Star, 2 to 4 wire systems (120 Phase displacement) modeling,

    1 phase systems (Phase to Neutral) modeling,

    Single Wire Earth Return systems (SWER) modeling,

    Dual phase systems (180 Phase Displacement, two phases & neutral).

    Radial / Limited Mesh System Analysis

    Any user defined voltage level (e.g. 275kV, 132kV, 400V, 120V, etc.)

    Full Technology Mix

  • 7/27/2019 RAEC_Capability_Final.pdf

    28/89

    RAEC CAPABILITY STATEMENT 2009 Page 28

    Calculations are automatic

    An unlimited number of nodes are supported

    Results are immediately available and may be displayed as required Voltage analysis (caters for unbalance)

    Current Flow analysis

    Fault current analysis:

    Three phase faults

    Phase to Ground faults

    Phase to Neutral faults

    Phase to Phase to Ground faults

    Phase to Phase faults

    Full load energy and losses energy calculations are performed

    Demand Side / Energy Management

    Load types include Constant Power, Constant Impedance & Constant Current

    Full domestic algorithms are available using appropriate diversity calculations for

    residential load modeling.

    Statistical load analysis is available for residential load modeling

    Output

    Graphic reporting such as under/over-voltage and over loaded equipment

    Voltage profiles are directly available & are dynamically updated during network

    modifications.

    Fault current profiles are available & dynamically updated

    User definable GUI outputs are directly available

    User definable text reports are directly available

    Text Report of problems such as:

    Open points,

    Islands,

    Voltage problems,

    Rating problems and

    Unbalance problems.

    Detailed results for RAEC systems as Case studies are shown in the CD-ROM.

    The followings are current and voltage profiles and alerts of main systems from RAEC areas:

  • 7/27/2019 RAEC_Capability_Final.pdf

    29/89

    RAEC CAPABILITY STATEMENT 2009 Page 29

    1. Power Flow analysis at Khasab 11 & 33kV Power system (Musandam Area):

    Output of the software indicates the following: Software output is shown in appendix 1 ).

    Maximum demand at many locations exceeds the carrying capacity of feeders and transformers

    Figs 2.13&2.14 .

    From

    the

    From

    load

    Feeders Current

    Carrying Capacity

    Maximum Current 2008

    Fig 2.14: Voltage Profile capacity.Output fromReticMaster SoftwKhasab Power Sys2008

    Fig 2.13: MaximumDemand and feedercurrent carryingcapacity. Output fromReticMaster SoftwarKhasab Power Syste2008

  • 7/27/2019 RAEC_Capability_Final.pdf

    30/89

    RAEC CAPABILITY STATEMENT 2009 Page 30

    flow analysis it is concluded that reinforcement work is required to many parts of the distribution network

    feeders and transformers at Khasab area to overcome overloading and under voltage problems at some

    areas as shown in table 2.14 bellow.

    N

    o.Equipment Branch Description

    LM

    (kM)I max A I of A

    Reinforcement Work

    Required

    1TX No. 2 Al QADI 500kVA 11kV/430V Star

    Dyn1[30]

    - 743.77 103.1 Changing transformer to

    1000 kVA.

    2TX_40 500kVA 11kV/430V Star

    Dyn1[30]

    - 615.47 85.3 Changing transformer to

    1000 kVA.

    3O/H line from BB

    to TX 56 Feeder 6

    dog (70m) 0.07 251.54 100.6 Changing O/H line to

    3X185 U/G Cable

    4O/H line from TX

    56 to TX No. 13

    dog (230m) 0.23 246.45 98.6 Changing O/H line to

    3X185 U/G Cable

    5TX No. 27 315kVA 11kV/430V Star

    Dyn1[30]

    - 449.01 98.8 Changing transformer to

    500 KVA.

    6O/H line from BB

    to TX 48 feeder 3

    dog (160m) 0.16 349.53 139.8 Changing O/H line to

    3X185 U/G Cable

    7O/H line at TX 48

    feeder 3

    dog (220m) 0.22 343.51 137.4 Changing O/H line to

    3X185 U/G Cable

    8

    O/H line from TX

    48 to TX no 70

    dog (130m) 0.13 343.55 137.4 Changing O/H line to

    3X185 U/G Cable

    9O/H line from TX

    72 a

    dog (70m) 0.07 325.8 130.3 Changing O/H line to

    3X185 U/G Cable

    10O/H line from TX

    73

    dog (200m) 0.2 308.06 123.2 Changing O/H line to

    3X185 U/G Cable

    11O/H line from TX

    1

    dog (300m) 0.3 285.7 114.3 Changing O/H line to

    3X185 U/G Cable

    12O/H line from TX

    61

    dog (600m) 0.6 281.24 112.5 Changing O/H line to

    3X185 U/G Cable

    13O/H line from TX

    75

    dog (200m) 0.2 262.81 105.1 Changing O/H line to

    3X185 U/G Cable

    14TX 10 500kVA 11kV/430V Star

    Dyn1[30]

    - 706.82 97.9 Changing transformer to

    1000 KVA.

    15TX 410 500kVA 11kV/430V Star

    Dyn1[30]

    - 690.31 95.7 Changing transformer to

    500 kVA.

  • 7/27/2019 RAEC_Capability_Final.pdf

    31/89

  • 7/27/2019 RAEC_Capability_Final.pdf

    32/89

    RAEC CAPABILITY STATEMENT 2009 Page 32

    2. Power Flow analysis of Saih Al Khairat 11 kV Power system (Dhofar Area) .

    The followings have been deduced from the power flow analysis: Software output is shown in

    appendix 2 ).

    Maximum current is within the feeders current capacity Fig 2.15 . The conductor is too long therefore

    high load loss was indicated from the analysis table 2.16.

    Fig 2.15: Maximum Demand and feeder current carrying capacity.Output from ReticMaster Software Shasir Power System.

  • 7/27/2019 RAEC_Capability_Final.pdf

    33/89

    RAEC CAPABILITY STATEMENT 2009 Page 33

    Voltage Profile Curve fig 2.16 indicates that voltage drop along through the power system is morethan the accepted value. Therefore work is required for relocating the current voltage regulator to a

    location marked on fig 2.17.

    Starting Location

    of under voltage Area of under

    voltage

    Existing Location

    voltage regulator Fig 2.17 VoltProfile of F2(Shasir AreaWith proposlocation ofvoltage regu

    Fig 2.16 VoltProfile of F2(Shasir AreaWith out volregulator

  • 7/27/2019 RAEC_Capability_Final.pdf

    34/89

    RAEC CAPABILITY STATEMENT 2009 Page 34

    3. Power Flow analysis at Mazyounah 11 kV Power system (Dhofar Area) .

    The followings have been deduced from the power flow analysis (Software output is shown

    in appendix 3). Under ground cables are used as feeders current capacity, therefore load losses

    and voltage drop is limited Figs2. 18 and Fig 2.19.

    Fig 2.19 VoltProfile of feeat Al MazyunPower Syste

    Fig 2.18: MaxDemand and fcurrent carryicapacity. Outpfrom ReticMasSoftware (AlMazyuna PowSystem).

  • 7/27/2019 RAEC_Capability_Final.pdf

    35/89

    RAEC CAPABILITY STATEMENT 2009 Page 35

    4. Power Flow analysis at Masirah 11 kV Power system (Al Sharqiyah Area) .

    The followings have been deduced from the power flow analysis ( Software output is shown

    in appendix 4). Under ground cables are used as feeders current capacity, therefore load losses

    and voltage drop is limited Figs2. 20 and Fig 2.21.

    Fig 2.20: MaxiDemand and fecurrent carryincapacity. Outpfrom ReticMasSoftware MasiPower System2008

    Fig 2.21: VolProfile, Outpfrom ReticMaSoftware MaPower Syste2008

  • 7/27/2019 RAEC_Capability_Final.pdf

    36/89

    RAEC CAPABILITY STATEMENT 2009 Page 36

    Power Flow analysis at Hiij 11 kV Power system (Al Sharqiyah Area) .The followings have been deduced from the power flow analysis: Software output is shown in

    appendix 5).

    Maximum Current is about 10% of current carrying capacity of the conductor and,therefore load loss is too small as shown in figures 2.22&2.23. Oversized conductors areused to overcome voltage drop.

    Fig 2.22 CurrentProfile at Hiijpower system

    Fig 2.23 VoltageProfile at Hiijpower system

  • 7/27/2019 RAEC_Capability_Final.pdf

    37/89

    RAEC CAPABILITY STATEMENT 2009 Page 37

    5. Power Flow analysis at Aduqum 11 kV Power system (Wusta Area) .

    The followings have been deduced from the power flow analysis:Software output is shown in in

    appendix 6).

    Maximum Current is about 10% of current carrying capacity of the conductor and,

    therefore load loss is too small as shown in figures 2.24&2.25.

    Fig 2.24 CurreProfile at AlDuqum powersystem

    Fig 2.25Voltage Profat Al Duqumpower system

  • 7/27/2019 RAEC_Capability_Final.pdf

    38/89

    RAEC CAPABILITY STATEMENT 2009 Page 38

    6. Power Flow analysis at Al Jazir 11 kV Power system (Wusta Area) .

    The followings have been deduced from the power flow analysis: Software output is shown in in

    appendix 7).

    Maximum Current is less than of current carrying capacity of the conductor and, therefore

    load loss is too small as shown in figures 2.26&2.27.

    Fig 2.26 CurrentProfile at Al Jazirpower system

    Fig 2.27 VoltageProfile at Al Jazirpower system

  • 7/27/2019 RAEC_Capability_Final.pdf

    39/89

    RAEC CAPABILITY STATEMENT 2009 Page 39

    7. Power Flow analysis at Ras Al Madrakah 11 kV Power system (Wusta Area) .

    The followings have been deduced from the power flow analysis: Software output is shown in in

    appendix 8).

    Maximum Current is less than current carrying capacity of the conductor and, therefore

    load loss is too small as shown in figures 2.28&2.29.

    Fig 2.28Current Profileat Ras AlMadrakah

    power system

    Fig 2.29Voltage Profileat Ras AlMadrakahpower system

  • 7/27/2019 RAEC_Capability_Final.pdf

    40/89

    RAEC CAPABILITY STATEMENT 2009 Page 40

    8. Power Flow analysis at Khawaimiah 11 Kv Power system (Wusta Area) .

    The followings have been deduced from the power flow analysis: Software output is shown in in

    appendix 9).

    Maximum Current is less than current carrying capacity of the conductor and, therefore load

    loss is too small as shown in figures 2.30&2.31.

    Fig 2.30Current Profileat Khawaimahpower system

    Fig 2.31 VoltageProfile atKhawaimahpower system

  • 7/27/2019 RAEC_Capability_Final.pdf

    41/89

    RAEC CAPABILITY STATEMENT 2009 Page 41

    9. Power Flow analysis at Wadi Aswad 33&11 kv Power system (Wusta Area) .

    The followings have been deduced from the power flow analysis:Software output is shown in in

    appendix 10).Maximum Current is about 10% of current carrying capacity of the conductor and,

    therefore load loss is too small as shown in figures 2.32&2.33.

    Fig 2.32CurrentProfile at

    WadiAswadpowersystem

    Fig 2.33 VoltagProfile at Wad

    Aswad powersystem

  • 7/27/2019 RAEC_Capability_Final.pdf

    42/89

    RAEC CAPABILITY STATEMENT 2009 Page 42

    2.4.5 Losses in Distribution Systems.

    Total losses in power systems are mainly technical and nontechnical losses. The technical losses result

    from power flow in distribution networks and equipment at 33 kV, 11 kV and LV systems and are divide

    into Load and no load losses. The non technical losses result from inaccurate data delivered, power

    metering and other factors related to system users; therefore it is difficult to be determined. Calculating

    of Power loss requires detailed information of the distribution networks including type, size and length of

    conductors, specifications of distribution equipment, details of maximum loads on transformers and

    feeders, etc. Table 2.16 shows a comparison between total, no load and load losses at different areas of

    RAEC power systems.

    Table 2.16 Losses at 11 &33 KV systems of RAEC main systems.

    PowerSystem

    MaximumDemand(kW)

    Power Loss of 11kV System atMaximumDemand (kW)

    Loss Percentageof 11 kV systemfrom ReticMaster%

    Total LossPercentage%

    Percentageof no loadLoss from11 kV TotalLoss

    Dibba (F1&2) 3,040 153 5.03 8.6 43.14

    Saih Al Khairat 5,624 384 6.6 28.6 17.0

    Hiij 3,400 113 3.32 9.9 23.89

    Khasab 21,726 1460 6.72 17.7 47.05

    Al Jazir 3,455 255 7.38 19.5 10.2

    Wadi Aswad 2,749 184 6.69 N/A 22.83

    Masirah 8,495 210 2.47 5.9 24.76

    Ras Madrakah 1,710 49 2.87 N/A 36.79

    Khawaimah 2,379 76 3.20 46% 15

    Al Mazyunah 2,632 71 2.70 24.8% 26.62

    Al Duqum 1,395 26 1.86 N/A 48.85

  • 7/27/2019 RAEC_Capability_Final.pdf

    43/89

    RAEC CAPABILITY STATEMENT 2009 Page 43

    3.0 Demand on RAEC Power systems:

    3.1 Profiles of Current Demands.

    The main type of customers at RAEC areas of license is residential; therefore it becomes the main factor

    influencing the demand profiles. From the demand profiles in 2008 it is shown that the demand

    decreases sharply in Jun and February, then it starts increasing and decreasing in such a way reflecting

    the climate temperature. In Dhofar region demand reduces during June, July and August (Khareef

    season) and then increases as temperature increases again till October when it starts decreasing. Wusta

    Region has the same climate phenomena as that in Dhofar and reflects the same demand profile as that

    of Dhofar area. Khasab Region hasnt the climate phenomena as in Dhofar and Wusta regions therefore

    the demand profile shows increase from February and continues at maximum from May up to October

    when it starts seasonal reduction.

    Many power stations in Dhofar area are not affected by the climate phenomena; therefore the type of

    demand profile is different from the others. The un effectiveness is either that the locations of these

    power stations are far away from climate phenomena such as Al Mazyuna power station or the main type

    of demand is not residential as in Saih Al Khairat Power Station.

    Figures 3.1-3.12 and table 3.1 show the anuual maximum demand profile of RAEC differnet areas in

    2008

    -

    10,000

    20,000

    30,000

    40,000

    50,000

    60,000

    70,000

    80,000

    90,000

    0 2 4 6 8 10 12 14

    Fig 3.1 Profileof MaximumDemand atdifferentregions ofRAEC areas in2008 License(2008)

    Maximum

  • 7/27/2019 RAEC_Capability_Final.pdf

    44/89

    RAEC CAPABILITY STATEMENT 2009 Page 44

    0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    40000

    0 2 4 6 8 10 12 14

    Demandin 2008

    kW Jan. Feb. March April May June July Aug. Sept. Oct. Nov. Dec.

    Masandam

    Max . 16715 15990 24317 31732 42820 43625 44785 44575 42808 42675 31524 18200

    Masandam

    Min 6970 6435 9215 13971 16781 23281 25673 24654 25380 17499 10815 8949

    Wusta

    Max. 7,924 8,705 13,397 17,467 17,667 17,489 10,955 12,501 16180 16097 13098 10036

    Wusta

    Min. 3114 2817 2702 6123 7663 5587 4602 4748 6408 5795 2990 3849

    Dhofar

    Max. 9,311 9,192 11,931 14,442 15,105 16,077 14,119 13,934 16,070 14,343 11,778 10,440Dhofar

    Min. 2712 3217 3473 3673 4629 4761 5111 4608 4785 4380 4293 3420

    RAEC

    Max. 33,950 33,887 49,645 63,641 75,592 77,191 69,859 71,010 75,058 73,115 56,400 38,676

    RAEC Min. 12796 12469 15390 23767 29073 33629 35386 34010 36573 27674 18098

    16218

    Fig 3.2 Profile oMinimum

    Demand atdifferent regionof RAEC areas oLicense (2008).

    Minimum

    Months

    Table 3.1 Min. & Max.Demands at different regions of RAEC areas of License (2008).

  • 7/27/2019 RAEC_Capability_Final.pdf

    45/89

    RAEC CAPABILITY STATEMENT 2009 Page 45

    -

    5,000

    10,000

    15,000

    20,000

    25,000

    30,000

    35,000

    40,000

    45,000

    50,000

    - 2 4 6 8 10 12 14

    Khasab Power Station Diba Power Station

    Madha Power Station Masandam Profile Demand

    0

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    18000

    20000

    0 2 4 6 8 10 12

    Group 1 of Power Stations Hijj Power Station

    Group 2 of Power Stations Masirah Power Station

    Fig 3.3 demandProfile at

    Masandampower systems(2008)M

    aximum

    Months

    Months

    Maximum

    demand(kW)

    Fig 3.4 demand

    Profile at Wustapower systems(2008)

  • 7/27/2019 RAEC_Capability_Final.pdf

    46/89

    RAEC CAPABILITY STATEMENT 2009 Page 46

    0

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    18000

    0 2 4 6 8 10 12 14

    Shaab Esaib Power Station Group 1 of Power Stations

    Saih Al Khairat Power Station Group 2 of Power Stations

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 2 4 6 8 10 12 14

    Months

    Hijj Area Load Profile Fig 3.6 LoadProfile at HiijPower SysteMax. &MinWusta Regio(2008).

    Fig 3.5 demanProfile at Dhopower system(2008)

    Months

    demandkW

    Maximum

    demandkW

  • 7/27/2019 RAEC_Capability_Final.pdf

    47/89

    RAEC CAPABILITY STATEMENT 2009 Page 47

    -

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    0 2 4 6 8 10 12 14

    Max Demand Profile at Masirah PS Min. Demand Profile at Masirah PS

    -

    500

    1,000

    1,500

    2,000

    2,500

    0 2 4 6 8 10 12 14

    Max Demand Profile at Shaab Esaib PS

    Min Demand Profile at Shaab Esaib PS

    Fig 3.7 Load

    Profile at MasirahIsland PowerSystem Max. &Min

    , Wusta Region(2008)

    Fig 3.8 LoadProfile at ShahabEsaib PowerSystem Max. &Min,Wusta Region(2008)

    Months

    Months

    demandkW

    demandkW

  • 7/27/2019 RAEC_Capability_Final.pdf

    48/89

    RAEC CAPABILITY STATEMENT 2009 Page 48

    -

    200

    400

    600

    800

    1,000

    1,200

    1,400

    1,600

    1,800

    2,000

    0 2 4 6 8 10 12 14

    Max Demand at Mazyouna PS Min Demand at Mazyouna PS

    -

    500

    1,000

    1,500

    2,000

    2,500

    3,000

    3,500

    4,000

    4,500

    5,000

    0 2 4 6 8 10 12 14

    Max Demand at Saih Al Khairat PS Min Demand at Saih Al Khairat PS

    Fig 3.9 Load Profat Al MazyunahPower System Ma&Min, DhofarRegion (2008)

    Fig 3.10 Load Proat Saih Al Khairat

    Power System M&Min, DhofarRegion, the area irrigation type ofdemand (2008).

    Months

    Months

    demandkW

    demandkW

  • 7/27/2019 RAEC_Capability_Final.pdf

    49/89

    RAEC CAPABILITY STATEMENT 2009 Page 49

    -

    50

    100

    150

    200

    250

    300

    350

    0 2 4 6 8 10 12 14

    MaxDemand at Al Halaniat PS Min Demand at Al Hilaniat PS

    0

    5

    10

    15

    20

    25

    30

    35

    1 2 3 4 5 6 7 8 9 10 11 12

    Khasab Max. Demand 2008

    Khasab Min. Demand 2008

    Fig 3.11 LoadProfile at Al Hilaniat

    Power System Max.&Min, DhofarRegion

    Fig ( 3.12) LoadProfile at Khasa

    Power System M&Min, MasandamRegion

    Months

    Months

    demandkW

    demandkW

  • 7/27/2019 RAEC_Capability_Final.pdf

    50/89

    RAEC CAPABILITY STATEMENT 2009 Page 50

    3.2 Forecasted Demand.

    3.2.1 Demand from regions normal growth

    Demand in RAEC systems has shown continuing growth due to the development at the areas of license.

    Figure 3.13 and table 3.2 show the peak demand in 2006, 2007 &2008 from the trend, annual growth

    has been calculated as follows: the Average demand of 2006, 2007&2008 is calculated, then annual

    growth as percentage value is estimated from the difference of demand in 2008 from the average divided

    by the average. Average Demand =( 2006,2007&2008)/3 , then annual growth= (Demand

    2008-Average)/Average*100.

    .

    0

    20

    40

    60

    80

    100

    120

    140

    160

    0 1 2 3 4 5 6 7 8 9

    MAX.DEMA

    ND(MW)

    Fig 3.13 Load Projection at RAEC Power 2009-2013 (Normal growth)

    Year

  • 7/27/2019 RAEC_Capability_Final.pdf

    51/89

    RAEC CAPABILITY STATEMENT 2009 Page 51

    R.S.No. R.S.Name

    AvailableCapacity2009

    (MW)

    2006PeakDemand

    (MW)

    2007PeakDemand

    (MW)

    2008PeakDemand

    (MW)

    AveragePeakDemand

    (MW)

    AnnualGrowth

    %

    2009PeakDemand

    (MW)

    2010PeakDemand

    (MW)

    2011PeakDeman

    (MW)

    03/006 Kumzar0.80 0.70 0.240 0.840 0.770 0 0.840 0.840

    0.840

    03/001 Al Rawda0.22 0.160 0.130 0.135 0.142 0 0.135 0.135 0.135

    03/002 Dibba13.944 8.350 9.200 11.200 9.583 17 13.089 15.298 17.87

    03/004 HB Hameed0.124 0.049 0.059 0.055 0.054 1 0.056 0.056 0.057

    03/005 Khasab32.908 26.900 27.700 30.000 28.200 6 31.915 33.952 36.11

    03/007 Madha6.010 2.580 2.950 3.420 2.983 15 3.921 4.494 5.152

    02/019 Masirah 8.478 6.470 7.290 7.500 7.087 6 7.937 8.400 8.890

    02/001 AbuMudhabi0.535 0.395 0.400 0.265

    02/027 Sawgrah 0.467 0.275 0.240 0.160 0.225 0 0.160 0.160 0.160

    02/004 Al Kahal4.288 0.700 0.830 0.950 0.827 15 1.092 1.255 1.442

    02/005 Al Khaluf1.600 0.134 0.322 0.228 41 0.455 0.642 0.907

    02/006 Al Khuiaima0.96 0.590 0.680 0.750 0.673 11 0.835 0.931 1.036

    02/007 Al Lakbi1.419 0.705 1.105 1.245 1.018 22 1.522 1.861 2.275

    02/008 Alajaiz0.904 0.160 0.330 0.410 0.300 37 0.560 0.766 1.047

    02/010 AlNajdah1.76 0.024 0.255 0.140 83 0.466 0.852 1.558

    02/012 AlZhaiah0.320 0.221 0.240 0.242 0.234 3 0.250 0.258 0.267

    02/016 Hij 8.48 2.830 3.350 3.425 3.202 7 3.664 3.919 4.193

    02/017 Hitam1.064 0.021 0.240 0.131 84 0.441 0.812 1.493

    02/025

    Ras

    Madraka0.863 0.400 0.590 0.845 0.612 20 1.014 1.217 1.460

    02/030 Surab1.800 0.160 0.385 0.273 20 0.462 0.554 0.665

  • 7/27/2019 RAEC_Capability_Final.pdf

    52/89

    RAEC CAPABILITY STATEMENT 2009 Page 52

    02/031 Al Duqm1.060 1.330 1.270 1.420 1.340 6 1.505 1.595 1.690

    02/032 Al Dhafrat1.48 -------- ------- ------- ------- 10 0.450 0.495 0.545

    02/020 Masrooq0.523 0.179 0.210 0.299 0.229 30 0.390 0.508

    0.663

    01/001 Al Halaniyat1.280 0.255 0.260 0.320 0.278 15 0.368 0.423 0.486

    01/002 Al Mathfa0.388 0.06 .06 .078 .070 10 0.078 0.086 0.095

    01/005 Ayboot (1)0.396 0.085 0.095 0.109 0.096 13 0.123 0.140 0.158

    01/006 Ayboot (2)0.460 0.060 0.130 0.190 0.127 50 0.285 0.428 0.641

    01/007 Ayun0.596 0.142 0.170 0.180 0.164 10 0.198 0.217 0.238

    01/008 Barbazum0.790 0.200 0.270 0.270 0.247 9 0.296 0.323 0.354

    01/009 Bithina

    01/010 Dalkut A1.184 0.700 0.880 0.790 11 0.980 1.092 1.216

    01/011 Dalkut B2.502 1.531 1.630 1.581 3 1.681 1.734 1.788

    01/012 Dhahabun0.783 0.410 0.430 0.460 0.433 6 0.488 0.518 0.550

    01/014 Fatkhat0.368 0.072 0.105 0.115 0.097 18 0.136 0.161 0.190

    01/015 Hasik 0.957 0.740 0.820 0.790 0.783 1 0.797 0.804 0.810

    01/016 Hirweeb0.700 0.230 0.301 0.335 0.289 16 0.389 0.451 0.524

    01/017 Horaat0.390 0.140 0.145 0.173 0.153 13 0.196 0.222 0.252

    01/019 Mahwice0.318 0.115 0.120 0.119 0.118 1 0.120 0.121 0.122

    01/020 Maqshan1.112 0.460 0.460 0.400 0.440 0 0.400 0.400 0.400

    01/021 Mazyunah1.926 1.635 1.530 1.720 1.628 6 1.817 1.919 2.027

    01/022 MirbatClosed

    01/023 Mitan0.790 0.450 0.510 0.530 0.497 7 0.566 0.604 0.644

    01/024 Mothorah 0.380 0.130 0.161 0.146 11 0.178 0.197 0.218

  • 7/27/2019 RAEC_Capability_Final.pdf

    53/89

    RAEC CAPABILITY STATEMENT 2009 Page 53

    Table 3.2 Estimated normal growth 2009-2011

    01/025 Mudhai1.000 0.480 0.511 0.557 0.516 8 0.601 0.649 0.701

    01/026 Rabkut0.640 0.160 0.230 0.250 0.213 17 0.293 0.343 0.402

    01/030 SadahClosed

    01/031 SadhoonClosed

    01/032 Saih Alkirat16.435 2.340 3.700 4.580 3.540 29 5.926 7.666 9.919

    01/033 Salalah 1Closed

    01/034 Salalah 2Closed

    01/035Shahb

    Asayb2.800 1.645 2.016 2.260 1.974 15 2.588 2.963 3.393

    01/037 Sharbatat2.182 0.640 0.680 0.620 0.647 0 0.620 0.620 0.620

    01/038 Shasir2.280 2.280 0 0.000 0.000 Closed

    01/039 Thumryt0.000 0.000 0.000 Closed

    01/040 Tushnat0.720 0.160 0.165 0.175 0.167 5 0.184 0.193 0.203

    01/004 Andat

    RAEC 118.972 65.693 72.162 80.922 90.389 100.1 114.32

  • 7/27/2019 RAEC_Capability_Final.pdf

    54/89

    RAEC CAPABILITY STATEMENT 2009 Page 54

    3.2.2 Proposed new Connections to RAEC systems:

    Power Demand at RAEC areas of license showing continues growth. New connections are being studied

    and electrification plans are scheduled to meet requirements as per the conditions of sector law.

    Applications suited to new connections in 2009 are shown in table 3.3. Tables 3.4 and 3.5 show the

    planned connections in 2010 and 2011 respectively. Other bulk demands are predicated to be catered

    through 2010-2011 this is concentrated in Wusta (Aduqum) and Musandam. Table 3.6 shows a list of this

    bulk demands. The power demand of the new connections is planned to be met by the construction of

    new 11 and 33 substation and extension works at different distribution systems at RAEC. Satisfying the

    demand of the new connections with the normal growth of the connected customers in efficient and

    secured criteria, requires the upgrading of many power generation capacities, constructing new power

    generation stations, interlinking of existing power systems to form TSO nad DSO systems .Tables 3.3-3.7

    and figures 3.14-3.18 detail the new connections to RAEC power systems (2009-2011) normal growth

    and bulk demands areas and regional , the areas and regions predicated demand with number and

    category of customers predicated to be connected to RAEC systems up to the end of 2011.

    3.2.2.1 Planned connections in 2009

    Table 3.3 bellow shows the New Connections planned to be connected to RAEC power system in 2009.

    Sl.No Willayat

    No. of

    Cust

    Demand

    (kW) Project Name

    1Wusta/

    Aduqum947 10,000

    EPC for 33/11kV Substations and 33kV Distribution Network at

    Al Duqm Area in Al Wusta Region.

    2 Dhofar/ Hasik 212 1,700Power Supply to New Houses in Hasik Area in Dhofar

    Governorate.

    3Dhofar/

    Hairoon22 210

    Extension of HV& LV Distribution Networks (O/H Lines & U/G

    Cables ) to Give a Power Supply at Hairoon Village .

    4 Wusta/ Adam 16 1,000Extension of 33kV and Lv OH lines for power supply to Ghabain Wilayat Adam.

    5 Wusta/ Hijj 440 3,500

    Erection of Step-Up Transformer(11/33kV) at Hijj Power

    Station and Construction of 33kV Overhead Line to Masila Area

    in Wilayat Mahoot Al-Wusta Region.

  • 7/27/2019 RAEC_Capability_Final.pdf

    55/89

    RAEC CAPABILITY STATEMENT 2009 Page 55

    6 Wusta/ Hijj As in 5

    Construction of 33kV Overhead line and Erection of

    (33/11kV)Primary Substation at Muderah North in wilayat

    Mahoot in Al-Wusta Region.

    7Wusta/

    Mahoot52 370

    Extension of 11kV and LV to feed power supply to Nafi Area at

    Wilayat Mahoot in Al Wusta.

    8Musandam/

    Khasab361 3300

    Electrical Dstribution works ( 433V & 11kV Network Extensions

    ) To feed power Supply To Al- Sanayia Planned Area in Wilayat

    Khasab at Musandam Governorate.

    9 Wusta/ Hijj As in 5Construction of 33kV Overhead line to Al-Joubah west area

    wilayat Mahoot in Al-Wusta Region.

    10Dhofar/ Al

    Mazyunah25 240

    Extension Of 433V & 11 kV Networks To Feed Power Supply To

    Un- Electrified Houses At Mazyuna.

    11 Wusta/ Hijj As in 5

    Electrical Distribution works ( 433V & 11kV Network Extensions

    ) to feed power Supply to Wadi Al-Sail South at Wilayat

    Mahoot Al-Wusta Region.

    12Wusta/ Al

    Jazir5 50

    Extension of 433V and 11kV network extension to feed power

    supply to Gubrah south Al Wilayat Al Jazer.

    13 Wusta/ Hijj As in 5

    Electrical Distribution works ( 433V & 11kV Network Extensions

    ) to feed power Supply to Wadi Al-Sail North Area in Wilayat

    Mahoot Al-Wusta Region.

    14 Wusta/ Hijj As in 5Construction of 33kV Overhead line to Muderah South area in

    wilayat Mahoot Al-Wusta Region.

    15 Wusta/ Hijj As in 5

    Electrical Distribution works ( 433V & 11kV Network Extensions

    ) to feed power Supply to Muderah Area(Part-1) in Wilayat

    Mahoot Al-Wusta Region.

    16 Wusta/ Hijj As in 5

    Electrical Distribution works ( 433V & 11kV Network Extensions

    ) to feed power Supply to Abu Hasab Area near Wadi Al-SailSouth at Wilayat Mahoot Al-Wusta Region.

    17 Wusta/ Hijj As in 5

    Electrical Distribution works ( 433V & 11kV Network Extensions

    ) to feed power Supply to Muderah Area(Part-2) in Wilayat

    Mahoot Al-Wusta Region.

  • 7/27/2019 RAEC_Capability_Final.pdf

    56/89

    RAEC CAPABILITY STATEMENT 2009 Page 56

    18 Wusta/ Hijj 15 160Extension of 11kV and LV to feed power supply to Al Jamaza

    Village area at Wilayat Al Mudhaibi in Al Shargiyah(Part 1).

    19 Wusta/ Bahla 15 150

    Electrical Distribution works ( 433V & 11kV Network Extensions

    ) To feed power Supply To Aseel Area in Wilayat Bahla in

    Dakhliya Region.

    20Wusta/ Al

    Jazir

    Extension of 11kV and Lv OHL power supply to feed Abu Tahal

    area.

    21Wusta/ Al

    Jazir

    Extension of 11kV and Lv OHL power supply to Al Ajaiz north.

    22 Wusta/ Hijj As in 18

    Extension of 11kV and LV to feed power supply to Al Jamaza

    Village area at Wilayat Al Mudhaibi in Al Shargiyah(Part II).

    22

    Dhofar/

    Shahab

    Essaib

    Extension of 33Kv O/H Lines & U/G Cables to Interlink Shahab

    Asaib P/S to Dhalquot area & construction 33/11Kv Outdoor

    substation at hafoof.

    23Dhofar/ Horat

    Extension of 33Kv overhead line for Interlinking Horat with

    Mudhai(Ayboot -1) in Dhofar Governorate.

    24Wusta/ Al

    Jazir20 210

    Electrical Distribution works ( 433V & 11KV Network Extensions

    ) To feed power Supply to un electrified houses at Wilayat Al-

    Jazer Al Wusta Region.

    25Wusta/

    Mudhai

    Extension of 33Kv overhead line to Interlinking Ayboot-2 with

    Mudhai (Ayboot -1) in Dhofar Governorate.

    26Musandam/

    Dibba5 60

    Extension of 433V&11KV Networks to Feed Power Supply to

    Un- electrified locations at Wilayat Dibba in Musandam

    Governorate.

    27Wusta/ Ras Al

    Jabal20 200

    Electrical Distribution works ( 433V & 11KV Network Extensions

    ) To feed power Supply to un electrified houses and farms at

    Ras Al - Jabal in Wilayat Adam.

  • 7/27/2019 RAEC_Capability_Final.pdf

    57/89

    RAEC CAPABILITY STATEMENT 2009 Page 57

    28Wusta/

    Mahoot

    1 2000

    Electrical Distribution works ( 433V & 11KV Network Extensions

    ) To feed power Supply To the Sultan's Special Force Camp at

    Wilayat Mahout Al Wusta Region.

    29Musandam

    /Khasab10 120

    Extension of 433V&11KV Networks to Feed Power Supply to

    Un- electrified locations at Wilayat Khasab in Musandam

    Governorate.

    30Musandam/

    Bukha7 70

    Extension of 433V&11KV Networks to Feed Power Supply to

    Un- electrified locations at Wilayat Bukha in Musandam

    Governorate.

    31 Musandam/Khasab

    10 100

    Electrical Dstribution works ( 433V & 11KV Network Extensions

    ) To feed power Supply To Aqbath Rubia Area in Wilayat

    Khasab at Musandam Governorate.

    Table 3.3 New Connections to RAEC power system in 2009.

    3.2.2.2 Planned connections in 2010

    Table 3.4 bellow shows the New Connections planned to be connected to RAEC power system in 2010.

    Sl.

    NoWillayat

    No. of

    Cust

    Demand

    (kW)Project Name

    1Wusta/

    Aduqum20 200

    Power Supply to Shuwaier Village by the extension of 28 km, 11

    kV line to for Exdental Company network at the area with

    distribution network and transformers.

    2 Wusta/ Al Jazir 40 400Power Supply to Nafoon Village by the extension of 41km, 11 kVline from the new duqum network with distribution network and

    transformers.

    3 Wusta/ Mahoot 26 250

    Power Supply to Habdah Village the Village can be powered by

    the extension of 7 km, 11 kV line from Khaloof network with

    distribution network and transformers.

  • 7/27/2019 RAEC_Capability_Final.pdf

    58/89

    RAEC CAPABILITY STATEMENT 2009 Page 58

    4Wusta/ Jalan

    Bani Bu Hassan30 300

    Electricity Supply to Al Juwairiah Village the Village can be

    powered by the extension of 35km, 11 /33KV line from the

    network with distribution network and transformers.

    5 Wusta/ Mahoot 180 1500

    Power Supply to Sadrah &Madrasah Village by the extension of

    15km, 11 KV line from the Nafoon network with distribution

    network and transformers.

    6 Wusta/ Mahoot 300 2000

    Power Supply to 10 villages at Wadi Sail (Daasil, Ghafat

    Rashid,.) by the networkexecuted in stage 1 from Hij power

    station with distribution network and transformers.

    7 Wusta/ Mahoot 25 250

    Power Supply to Film Village by the extension of 26 km, 11 KV

    line from Hij power station with distribution network and

    transformers.

    8Sharqiyah/

    Masirah300 3500

    Power Supply to new planned area at Nahdah City by the

    extension 33 KV U/G Feeders from Masirah Power Station with

    distribution network and transformers.

    11 Dhakiliyah/Masrooq

    N/A N/A

    Interlinking Masrooq area to Majan PS by the extension of 45

    Km , 33 KV OHL with step/ down S/s. To implement TSO systemby the connection of Masrooq area to Majan MIS and shut down

    Masrooq

    12 Wusta/ Haima. N/A N/A

    Construction of new primary 33/11 KV Substation at Haima and

    increase its capacity to 2x20 MVA primary S/s to satisfy MoD and

    the other area growth of demand requirements.

    13Musandam/

    Khasab15 200

    Electricity Supply to Ramt Village by the extension of 3km,

    11KV line from the network with distribution network and

    transformers.

    14Musandam/

    Khasab6 80

    Electricity Supply to Umais Village by the extension of 2.0km,

    33KV line from the network with distribution network and

    transformers.

    17Dhofar/

    Thamreet40 500

    Electricity Supply to Bithenah Village .

  • 7/27/2019 RAEC_Capability_Final.pdf

    59/89

    RAEC CAPABILITY STATEMENT 2009 Page 59

    18Dhofar/

    ThamreetN/A N/A

    Install new voltage regulator at Saih al kairat to overcome the

    voltage drop at the area.

    19Musandam/

    KhasabN/A N/A

    Import and install two voltage regulators to Jabal Aqabat at

    Khasab to overcome the voltage drop at the area.

    21 Dhofar/ Tusnat N/A N/A

    Interlinking of Tusnat network with Anadat by the extension of

    15 Km , OHL ,11 kV ,33 KV configuration to shut down Tusanat

    and implementing DSO system at the area.

    22 Dhofar/ Hiroot N/A N/A

    Interlinking of Hiroot network with Anadat by the extension of

    15 Km , OHL ,11 kV ,33 KV configuration to shut down Hiroot PS

    and implementing DSO system at the area.

    23Dhofar/

    MatorahN/A N/A

    Interlinking of Matorah network with Hiroon by the extension of17 Km ,33 KV OHL to shut down Matorah and implementing DSO

    system.

    24Dhofar/

    HirweebN/A N/A

    Interlinking of Hirweeb network with Motorah by the extension

    of 17 Km , OHL ,11 kV ,33 KV configuration to shut down

    Hirweeb and implementing DSO system at the area.

    25 Wusta/ Hitam 7 85

    Power Supply to Deethab Gharb Village by the extension of 1.8

    km, 11 KV line for Exdental Company network at the area with

    distribution network and transformers.

    26 Sharqyiah/

    Masirah

    10 100

    Power Supply to Difiat Village by the extension of 2.5km, 11 KV

    line from the network near the hotel with distribution network

    and transformers.

    27Sharqyiah/

    Masirah7 65

    Power Supply to Ghadeer Village by the extension of 1.5km, 11

    KV line from the network with distribution network and

    transformers.

    28Sharqyiah/

    MasirahN/A N/A

    interlinking Hajjer B. Hameed to Madha to shut down HBH PS

    and implementing DSO system at the area.

    29Sharqyiah/

    MasirahN/A N/A

    Interlinking MoD network at Masirah to RAEC PS to form a DSO

    system and Connecting MoD base at Masirah to RAEC power

    station. The work should be done by the Construction of new

    11/33 substations and laying of 33 KV U/G cable .

  • 7/27/2019 RAEC_Capability_Final.pdf

    60/89

    RAEC CAPABILITY STATEMENT 2009 Page 60

    Table 3.4 New Connections to RAEC power system in 2010.

    3.2.2.3 Planned connections in 2011

    30 All RAEC areas N/A N/A

    Power Extension to customers at different areas

    Extension of power to customers at different areas of North,

    Wusta and south regions of RAEC

    31 All RAEC areas N/A N/AReinforcement works at different areas of North, Wusta and

    south regions of RAEC.

    32Wusta/

    Aduqum

    Distribution network for Duqum residential areas Phase 1, 11kV

    network, distribution transformers, LV network and connections

    to 938 customers in new Aduqum residential area.

    Sl.No

    WillayatNo. of

    Cust.

    Dem.

    (kW)Project Name

    1

    Wusta/ Adam

    8 100

    Power Supply to Ghabat Al Haqaf Village by the extension of 18 km,

    33 KV line from PDO network at the area with distribution network

    and transformers.

    2

    Wusta/ Adam

    11 120

    Power Supply to Al Mukhaiznah Village by the extension of 8 km, 33

    KV line for Exdental Company network at the area with distribution

    network and transformers.

    3

    Wusta/

    Al Jazir 7 90

    Power Supply to un electrified houses at South Ghubrah-Ghfoodh

    Village by the extension of 30 km, 11 KV line from the existing at the

    area with distribution network and transformers.

    4

    Wusta/ Mahoot

    11 120

    Power Supply to Al Baseer Village by the extension of 21 km, 11 KV

    line from Madeerah 33/11 kV Ss with distribution network and

    transformers.

    5Sharqiyah/

    Masirah44 400

    Power Supply to Dowa Village by the extension of 11km, 11 KV line

    from the network with distribution network and transformers.

    6Sharqiyah/

    Masirah26 200

    Power Supply to Sur Masirah Village by the extension of 9.0km, 11

    KV line from the network with distribution network and transformers.

  • 7/27/2019 RAEC_Capability_Final.pdf

    61/89

    RAEC CAPABILITY STATEMENT 2009 Page 61

    7Musandam/Dib

    ba8 110

    Electricity Supply to Aqabah Village by the extension of (33kV &

    0.433KV Networks) to feed power supply to Aqabah Vilage

    8 Musandam/Khasab

    4 55 Electricity Supply to Himssi Village by the extension of 3.5km, 11KVline from the network with distribution network and transformers.

    9Musandam/

    Khasab6 80

    Electricity Supply to Nebbah Village by the extension of 4.0km, 11KV

    line from the network with distribution network and transformers.

    10Musandam/Dib

    ba23 250

    Electricity Supply to Adas Village the extension of 28.5, 33KV line

    from the network with distribution network and transformers.

    11

    Musandam/

    Dibba 12 130Electricity Supply to Al Shaira Village by the extension 14, 33KV line

    from the network with distribution network and transformers.

    13Dhofar/

    Rakhyut6 75

    Electricity Supply to Al Hottah Village by the extension of 12 km,

    11 KV line with distribution network and transformers.

    14

    Dhofar/

    Mazyunah 30 250

    Electricity Supply to Tadhoo Village by the extension of 45 , 33KV

    OHL from Mudhai new power station with step up/down S/s and

    D.network .

    15Dhofar/

    Mazyunah15 100

    Electricity Supply to Qafaa Village by the extension of 30 , 11KV

    OHL from Tadhoo S/s with distribution network

    16Dhofar/

    Mazyunah

    50 750Electricity Supply to Al Hishman Village by the extension of 40,

    33KV L

    17

    Dhofar/

    Maqshin6 4000

    Electricity Supply to Doka Farms By the Extension of 60 , 33KV OHL

    from Saih Al Khairat power station with upgrading the power station

    by adding 8.0 Mw power capacity . Works include step up/down S/S

    nd all the distribution network.

    18Musandam/

    Dibba4 55

    Electricity Supply to Maawi Village by the extension of 1.0km, 33KV

    line from the network with distribution network and transformers.

    19

    Wusta/ Al

    Jazir10 115

    Power Supply to un electrified houses at North Ghubrah Village

    The Houses can be powered by the extension of 7 km, 11 KV line

    from the existing at the area with distribution network and

    transformers.

    20Sharqiyah/

    Masirah28 72

    Power Supply to Al Samir Village by the extension of 4.0km, 11 KV

    line from the network with distribution network

  • 7/27/2019 RAEC_Capability_Final.pdf

    62/89

    RAEC CAPABILITY STATEMENT 2009 Page 62

    Table 3.5 bellow shows the New Connections planned to be connected to RAEC power system in 2011

    3.2.3 Special Bulk Demands at RAEC Areas (2009-2011).

    In addition to the capacity demand above, Table 3.6 details Special Bulk Demands at RAEC power systems.

    21

    Wusta/ Mahoot

    N/A N/A

    Interlinking of Al Khloof power system to Hiij by the eExtension of

    53 Km , 33 KV OHL with step/up& down S/s to implementing of DSO

    system and shut down Al Khloof PS.

    22

    Wusta/ Al

    Duqum 21 150

    Power Supply to Wadi Zakhir Village by the extension of 7.0km, 11

    KV line from Feeder No.2 Dhahar PS with distribution network and

    transformers.

    23

    Wusta/ Al

    Duqum 7 60

    Power Supply to Dithab Gharb by the extension of 1.8 km, 11 KV

    line from Feeder No.2 Hitam PS with distribution network and

    transformers.

    24Wusta/ Aseel

    4 40Power Supply to Al Shuwaaid by the extension of 5.0 km, 11 KV line

    from Aseel with distribution network and transformers.

    25

    Wusta/

    Al Duqum 2109 12,600

    Distribution network for Duqum residential areas Phase 2 by the

    execution of 11kV network, distribution transformers , LV network

    and connections to 2109 customers in new Aduqum residential area.

    No. Scope of Demand Area Demand

    (MW)

    Proposed Action

    1 Supply of New Duqum Town with

    the required demand covering the

    upcoming five years .

    Wusta/

    Duqum

    81 Construction of New power plant of total

    capacity 81 MW with complete

    Distribution network at 33,11 and LV

    networks.

    2 Power Supply to Tourism resorts at

    Khasb area

    Musandam/

    Khasab

    18 New gas power plant of capacity 120 MW

    with interconnection Khasab and Dibba

    power system is under study.

    3 Power Supply to Oman Oil

    production and treatment plants at

    Khasb area

    Musandam/

    Khasab

    33 New gas power plant of capacity 120 MW

    with interconnection Khasab and Dibba

    power system is under study.

  • 7/27/2019 RAEC_Capability_Final.pdf

    63/89

    RAEC CAPABILITY STATEMENT 2009 Page 63

    Table 3.6 Bulk Demands Required at RAEC Power systems.

    3.2.4 Regional Forecasted Demand of RAEC systems:

    Table 3.7 shows the forecasted maximum demand of RAEC systems 2009-2011

    No. Region Max. Demand in

    2008 (MW)

    Areas forecasted

    Normal Growth

    Demand in

    2011(MW)

    Areas forecasted

    Bulk Demand in

    2011(MW)

    Total Demand

    in 2011 (MW)

    1 Musandam 46 16 51 113

    2 Al Sharqiyah &Wusta. 20 13 97 130

    3 Dhofar 19 11 12 42

    RAEC95 33 160 285

    Table 3.7 Forecasted Demand at RAEC power areas.

    4 Power Supply to Masirah Military

    Base at Masirah area.

    Sharqiyah/

    Masirah

    6 Construction New power station at

    Masirah area is required to meet the areademand.

    5 Power Supply to Doka, Khawater,

    Maqshin Sofa Farms and other un

    electrified villages at Dhofar area

    Dhofar/ Saih

    Al Khairat

    12 Catering the mentioned areas with power

    under study to decide the suitable option.

    6 Power Supply to Omani Army at

    Wusta region

    Wusta/

    Haima area

    10 Extension of 33 kV line from PDO power

    system .

  • 7/27/2019 RAEC_Capability_Final.pdf

    64/89

    RAEC CAPABILITY STATEMENT 2009 Page 64

    Musandam

    46 MW

    54%

    Wusta

    20 MW

    24%

    Dhofar

    19 MW

    22%

    Masandam

    113 MW

    40%

    Wusta

    130 MW

    45%

    Dhofar

    42 MW

    15%Fig 3.15RAECareas ForecastedMax demand in2011

    Fig 3.14RAECareas Max.Demand in 2008

  • 7/27/2019 RAEC_Capability_Final.pdf

    65/89

    RAEC CAPABILITY STATEMENT 2009 Page 65

    1 2 3

    46

    20 19

    113

    130

    42

    2008 ACTUAL MAX DEMAND (Mw) 2011 FORECASTED DEMAND

    Masandam

    Wusta&AlSharqyiah

    Dho

    far

    Domestic

    45%

    Govermental

    7%

    Commercial

    14%

    MoD

    4%

    Agr.&Fisheries

    5%

    Hotels &Tourism13%

    Industrial12%

    Fig 3.16Growth

    AreasDemand(2008-2011)

    Fig 3.17PredicatedCategory ofRAECCustomersin 2011

  • 7/27/2019 RAEC_Capability_Final.pdf

    66/89

    RAEC CAPABILITY STATEMENT 2009 Page 66

    53.1

    24.4

    11.9

    2.9 3.2 3.41.1

    45.4

    7

    14

    4.2 4.7

    13.311.5

    1 2 3 4 5 6 7

    2008 Actual Maximum Demand

    2011 Predicated Demand

    D

    omestic

    Comm

    ercial

    Govermental

    MoD

    Agri&Fisheries

    H

    otels

    &

    Tourisim

    Industrial

    Fig 3.18 Predicated Growth in Category of RAEC Customers (2008-2011)

  • 7/27/2019 RAEC_Capability_Final.pdf

    67/89

    RAEC CAPABILITY STATEMENT 2009 Page 67

    4.0 Constraints foreseen on RAEC systems

    4.1 Status of power stations with the addition of the new connections.

    Due to the Projection Demand at RAEC areas power systems and the inefficient operation of many power

    systems, RAEC existing power systems and stations shall be in the conditions detailed in table 4.1 bellow.

    No

    S.No.

    P.S.Name

    2009A.

    CapMW

    2008Peak

    Dem.MW

    2011Exp

    peakLoad

    (MW)

    Sh.incap.

    (MW)

    Power Station Status

    1 03/006 Kumzar 0.8 0.840 0.840 -0.04Predicated Demand is more than station

    capacity.

    2 03/001 Al Rawda 0.22 0.135 0.135 0.09Predicated Demand is more than station

    capacity.

    3 03/002 Dibba13.94

    411.20 17.878

    -

    3.934

    Predicated Demand is more than station

    capacity.

    4 03/004HB

    Hameed0.124 0.055 0.057 0.067

    Small un efficient DG sets

    5 03/005 Khasab

    32.90

    8 30.00 49.000

    -

    16.10

    Predicated Demand is more than station

    capacity..

    6 03/007 Madha 6.01 3.420 5.152 0.858Predicated Demand is more than station

    capacity.

    7 02/019 Masirah 8.478 7.500 8.890-

    0.412

    Predicated Demand is more than station

    capacity.

    8 02/001Abu

    Mudhabi0.535

    9 02/027 Sawgrah 0.467Predicated Demand is more than station

    capacity.

    10 02/004 Al Kahal 4.288Predicated Demand is more than station

    capacity..

    11 02/007Al Lakbi

    1.419Predicated Demand is more than station

    capacity..

    12 02/005 Al Khaluf 1.6 0.322 0.556 1.04Large DG sets (2x1000 kW) Supplying Low

    Demand

  • 7/27/2019 RAEC_Capability_Final.pdf

    68/89

    RAEC CAPABILITY STATEMENT 2009 Page 68

    13 02 /006Al

    Khuiaima0.96 0.750 1.036 -0.08

    Predicated Demand is more than station

    capacity.

    14 02/008 Alajaiz 0.904 0.410 0.708 0.196OLD DG sets (1980)

    15 02/010 AlNajdah 1.76 0.255 0.441 1.32Large DG sets (2x1000kW) Supplying Low

    Demand

    16 02/012 AlZhaiah 0.32 0.242 0.267 0.05 Small DG sets

    17 02/016 Hiij 8.48 3.425 4.193 4.287

    1802/017 Hitam 1.064 0.240 0.415 0.649 Large DG sets (2x1000kW) Supplying Low

    Demand

    1902/025 Ras

    Madraka

    0.863 0.845 1.460 -0.60 Predicated Demand is more than station

    capacity.

    20 02/030 Surab 1.8 0.385 0.665 1.13 Large D