SITE COMMUNICATION REPORT
SHERATON HOTEL RENOVATION
PREPARED BY: Ammar Albizreh ARCHITECT
APPROVED BY: FOUAD ABI KHALIL-PROJECT MANAGER
HOTEL BUILDING- ZONE 1(FOH)3RD FLOOR-ROOM 343-344
REF-SC-0507-May-2014
SITE OFFICE
2
Room NO. 343-344 REF: RA-SC-050
N.B: The above comments are subject to change until handing over of the project to client
1. Cables and wires to be organized. 2. Old canceled wires to be removed for safety .3. MEP clearance to be given.4. Damaged steel structure to be replaced.5. Old Ceiling is not entirely removed .
3
Room NO. 343-344 REF: RA-SC-050
N.B: The above comments are subject to change until handing over of the project to client
6. All damaged gypsum boards to be replaced / repaired prior to cement boards installation.
7. Ensure all wall partition to be properly leveled and edges to be squared prior to cement board installation .
8. MEP clearance to be given.9. Floor screed to be properly leveled and prepared to ensure proper tiles installation.10. Floor slope toward FD to be taken into consideration .
4
Room NO. 343-344 REF: RA-SC-050
N.B: The above comments are subject to change until handing over of the project to client
11. Cables and wires to be organized. 12. Old canceled wires to be removed for safety .13. All damaged gypsum board to be replaced / repaired prior to cement board
installation.14. MEP clearance to be given.15. Ac and ventilation ducts opening to be covered during works . 16. Damaged steel structure to be replaced.
5
Room NO. 343-344 REF: RA-SC-050
N.B: The above comments are subject to change until handing over of the project to client
17. Vanity metal structure to be replaced.18. All damaged insulation to be properly repaired or replaced.19. Old canceled wires to be removed for safety .20. MEP clearance to be given.21. All damaged gypsum board to be replaced / repaired prior to cement board
installation .22. Ensure that gypsum board is properly leveled prior to cement board installation.23. Floor screed to be properly leveled and prepared to ensure proper tiles installation.24. Old ceiling is not entirely removed .
6
Room NO. 343-344 REF: RA-SC-050
N.B: The above comments are subject to change until handing over of the project to client
25. All damaged insulation to be properly repaired or replaced.24. Old canceled wires to be removed for safety .25. MEP clearance to be given.26. All damaged gypsum board and wooed structure to be replaced / repaired prior to
cement board installation .27. Ensure that gypsum board is properly leveled prior to cement board installation.28. Old Ceiling is not entirely removed .
7
Room NO. 343-344 REF: RA-SC-050
N.B: The above comments are subject to change until handing over of the project to client
29. All damaged insulation to be properly repaired or replaced.30. Old canceled wires to be removed for safety .31. MEP clearance to be given.32. All damaged gypsum board to be replaced / repaired prior to cement board
installation .33. Ensure that gypsum board is properly leveled prior to cement board installation.34. Floor screed to be properly leveled and prepared to ensure proper tiles installation
8
Room NO. 343-344 REF: RA-SC-050
N.B: The above comments are subject to change until handing over of the project to client
35. Old canceled wires to be removed for safety .36. MEP clearance to be given.37. All damaged gypsum board to be replaced / repaired prior to cement board
installation .38. Ensure that gypsum board is properly leveled prior to cement board installation.39. Damaged steel structure to be replaced.
9
Room NO. 343-344 REF: RA-SC-050
N.B: The above comments are subject to change until handing over of the project to client
40. Floor screed to be properly leveled and prepared to ensure proper floor finish installation .
41. Remove residue of old carpet tracks strips , holes to be properly filled .42. Wall surface preparation to start and to be inspected after primary coat application .43. Electrical box to be properly leveled and aligned .44. Old canceled wires to be removed for safety .
10
Room NO. 343-344 REF: RA-SC-050
N.B: The above comments are subject to change until handing over of the project to client
45. Floor screed to be properly leveled and prepared to ensure proper floor finish installation .
46. Remove residue of old carpet tracks strips , holes to be properly filled .47. Wall surface preparation to start and to be inspected after primary coat application .48. Electrical box to be properly leveled and aligned .49. Old canceled wires to be removed for safety .50. New sanitary tool to be properly covered and store it at the proper area .
11
Room NO. 343-344 REF: RA-SC-050
N.B: The above comments are subject to change until handing over of the project to client
51. Floor screed to be properly leveled and prepared to ensure proper floor finish installation .
52. Wall surface preparation to start and to be inspected after primary coat application.53. Balcony FD to be replaced with approved samples .54. Balcony floor to be waterproofed .55. Balconies floor slope toward FD to be taken into consideration .56. Balcony Floor screed to be properly leveled and prepared to ensure proper floor
finish installation .