R5ufI TE-T

68
HREA-.uL.E-368 /81-7-2021-49(1u)/2017 gfde e, T Aoo-110002 afavr, yd seary ufRada 30-7 fa-TO yaostocto, T fa à faaa stogo w-673/2018 ufkT TRs: fATS :237T 2021 feit faaRTT 3Hogo io-673/2018 qifa 3ITdT 3Tfa Tfoa -u R5ufI U HRTd TE-T 2021 ECaR, 2021 (oyTO f ) TI-AIaI-368(1)/81-7-2021-49(at) /2017, TT H0-ut1-36640/-4/TRITKRT / 2020-21, f5 22.10.2021

Transcript of R5ufI TE-T

HREA-.uL.E-368 /81-7-2021-49(1u)/2017

gfde e, T Aoo-110002

afavr, yd seary ufRada 30-7fa-TO yaostocto, T fa à faaa stogo w-673/2018 ufkT

TRs: fATS :237T 2021

feit faaRTT 3Hogo io-673/2018 qifa 3ITdT 3Tfa Tfoa -u

R5ufI U HRTd TE-T 2021 ECaR, 2021

(oyTO f )

TI-AIaI-368(1)/81-7-2021-49(at) /2017, TT

H0-ut1-36640/-4/TRITKRT / 2020-21, f5 22.10.2021

1

National Mission for Clean Ganga

Monthly Progress Report in the NGT Matter OA No. 673 of 2018 (in compliance

to NGT order dated 24.09.2020)

For the State of Uttar Pradesh

Jun, 2021 - Sep, 2021

I. Status of implementation of Action Plan by States: Action Plan for Priority I to Priority

IV Rivers (Hindon, Yamuna, Varuna, Kali East, Gomti, Ganga and Ramganga) were

approved by State River Rejuvenation Committee and CPCB. Action Plan for Priority V

Rivers (Betwa, Ghaghra, Saryu, Rapti and Sai) were approved by State River

Rejuvenation Committee. Action Plan for two additional Rivers Ami and Tamsa were also

prepared and approved by State RRC.

II. STP/CETP wise status of projects grounded to-date, status of projects awaiting sanction

or in DPR stage (incremental progress in respect of projects):

A. Details of Under Construction STPs in the State-

S.No Name of

town/district

Nos. Capacity

(MLD) Expected date of

Commissioning

Present Progress

(Upto Sep-2021)

1 *Mathura 1 30 Oct-21 97.00%

2 Unnao 1 15 Dec-21 56.32%

3 Kanpur 1 30 Dec-21 64.00%

4 Naini, Fafamau,

Jhunsi

3 72 Dec-21 57.45%

5 Etawah 1 21 Dec-21 90.00%

6 Kasganj 1 15 Nov-21 94.00%

7 Sultanpur 3 17 Dec-21 45.00%

8 Jaunpur 1 30 Dec-21 71.50%

9 Shuklaganj 1 5 Nov-22 13.00%

10 Muzaffarnagar 2 54.5 Dec-22 21.00%

11 Budhana 1 10 Dec-22 21.50%

12 Baghpat 1 14 Dec-21 62.00%

13 Moradabad 1 25 24 months

after the

decision

Land Issue. Matter Sub-judice in Honorable High Court

(Allahabad Bench). AG UP and AAG are engaged for the case.

Next date of hearing was scheduled on 06.10.2021 but hearing

could not take place. Next date of hearing is scheduled on

27.10.2021.

2

S.No Name of

town/district

Nos. Capacity

(MLD) Expected date of

Commissioning

Present Progress

(Upto Sep-2021)

14 Lucknow 2 40 24 months

after the

decision

LOA was issued to M/s. RK Engineers Sales Ltd. Lucknow - M/s

Khilari Infrastructure Pvt. Ltd. (JV) on 17.09.2020. M/s. Geo

Miller, one of the bidders approached Hon’ble High Court,

Lucknow and subsequently matter was Sub-judice. Hon’ble

High Court, vide order dated 17.08.2021 dismissed the appeal

of M/s. Geo Miller and ruled the decision in favor of U. P. Jal

Nigam. M/s. Geo Miller has approached Hon’ble Supreme

Court in the matter. Counter Affidavit has been filed by U. P.

Jal Nigam on 21.09.2021. Hearing is scheduled on 26.10.2021.

15 Bulandshahar 1 40 Dec-21 95.00%, pertaining to U. P. Jal Nigam (Urban)

16 Hapur 1 30 Dec-21 80.00%, pertaining to U. P. Jal Nigam (Urban)

17 Mirzapur 1 7 Dec-21 98.00%, pertaining to U. P. Jal Nigam (Urban)

18 Bareilly 1 35 Mar-22 75.00%, pertaining to U. P. Jal Nigam (Urban)

19 Aligarh 1 45 Dec-21 80.00%, pertaining to U. P. Jal Nigam (Urban)

20 Rae Bareilly 1 18 Dec-21 99.00%, pertaining to U. P. Jal Nigam (Urban)

21 Etah 1 24 Oct-21 98.00%, pertaining to U. P. Jal Nigam (Urban)

22 Modinagar 1 20 Dec-21 95.00%, pertaining to U. P. Jal Nigam (Urban)

23 Shahjahanpur 1 40 Dec-22 12.00%, pertaining to U. P. Jal Nigam (Urban)

24 Lucknow 1 120 Dec-22 35.00%, pertaining to U. P. Jal Nigam (Urban)

25 Ballia 1 19.6 - DPR for balance works submitted to SMCG on 30.09.2020.

Observations on the DPR were communicated by SMCG vide

their office letter no.675/0632/SMCG/02 dated 16.07.2021.

Revised DPR, after incorporating observations submitted to

PPRBD cell, UPJN, Lucknow vide letter dated 02.09.2021 for

evaluation.

26 Pratapgarh 1 8.95 - Revised DPR, amounting Rs. 39.99 cr. for completing the

balance works has been approved by NMCG on 01.10.2021.

However, bids for the same project under State Sector (By U.

P. Jal Nigam-Urban) have been invited upto 29.10.2021.

27 Kanpur 1 15 - 98.00%

28 Mirzapur 2 17 Jun-23 Contract Agreement has been signed on 24.06.2021. BEP has

been submitted by the contractor. 29 Ghazipur 1 21 Jun-23

Total 36 839.05

*Operational in September

B. The status of sanctioned Projects which are under tendering stage is as

follows:-

S.No Name of

district/town

Nos. Capacity

(MLD)

Expected date of

Commissioning

Remarks

1 Fatehgarh 2 43 To be completed

within 24 months

NMCG has directed to award this work to

L1 bidder. Award process in underway.

3

S.No Name of

district/town

Nos. Capacity

(MLD)

Expected date of

Commissioning

Remarks

2 Bareilly 4 63 after signing of the

Contract

Agreement.

LOA issued to M/s. Enviro Infra Engineers

Pvt. Ltd. On 28.07.2021.

3 Agra 13 177.60 Bids have been received on 22.09.2021.

Evaluation under progress.

4 Meerut 1 220 Bids are to be received on 29.10.2021.

5 Kairana 1 15 Date of Start given as 28.08.2021 to M/s

SIPL-RKC (JV).

6 Ayodhya 1 33 AA&ES for the project issued by NMCG on

06.05.2021. NIT floated on 01.09.2021

and bids shall be received on 01.11.2021.

7 Azamgarh 1 8 Pertaining to U. P. Jal Nigam (Urban)

Total 23 559.60

Total 5500 MLD Sewage is being generated in 652 ULBs present in Uttar Pradesh.

Presently, 108 STPs are installed in Uttar Pradesh, which have 3471.84 MLD sewage treatment

capacity. In addition to above, 36 STPs having total capacity of 839.05 MLD are under

construction and 23 STPs having total capacity of 559.60 MLD are under tendering process. Upon

completion of these STPs, the total sewage treatment capacity shall become 4870.49 MLD. Gap of

629.51 MLD is still present.

For long term measures for reducing the gap of 629.51 MLD, 60 Projects for I&D of

drains and construction of STPs have been prepared by U.P. Jal Nigam and submitted to SMCG

for approval and allocation of funds. Of these 60 projects, 26 are Detailed Project Reports and 34

are Pre-Feasibility Reports. The total estimated cost of 26 DPRs is Rs. 5117 Crore. wherein

I&D of 200 drains and construction of 18 STPs, having total capacity of 664.45 MLD (excluding

capacities of 8.95 MLD at Pratapgarh and 19.6 MD STP at Ballia, as they are included in under

construction projects), are proposed.

The total estimated cost of 34 PFRs is Rs. 7667 cr. wherein I&D of 125 drains and

construction of 35 STPs, having total capacity of 737.70 MLD, are proposed.

The summary of above details is mentioned as follows:-

S. No. Description Capacity (MLD)

1 Estimated Sewage Generation 5500.00

2 Total installed capacity of 108 STPs 3471.84

3 Total capacity of 36 nos. STPs under

construction

839.05

4

S. No. Description Capacity (MLD)

4 Total capacity of 23 nos. sanctioned STPs

under tendering stage

559.60

5 Proposed capacity of 18 STPs in 26 DPRs

submitted for approval

664.45

6 Proposed capacity of 35 STPs in 34 PFRs

submitted for approval

737.70

Sub-Total (S. No. 2 - 6) 6272.64

C. Details of Under Construction CETPs in the State-

S.No. District Working Agency CETP Proposed Timeline

1. Unnao To be decided

DPR Sanctioned by NMCG for construction

of new CETP of capacity 4.5 MLD

Bidding under process. 02

years after allotment of

work

2. Unnao To be decided

DPR Sanctioned by NMCG for construction

of new CETP of capacity 2.15 MLD

Bidding under process. 02

years after allotment of

work

3. Mathura M/s. Fateh Enviro

Engineers Pvt. Ltd. Upgradation proposed under Namami Gange

Project for ZLD. Dec-2021

4. Kanpur JATETA New 20 MLD CETP is under construction &

to be completed by Dec, 2021- Dec-2021

D. Status of existing STPs in the State

Existing No. of STPs and Treatment Capacity (in MLD):

Total No. – 108

STPs in Varanasi- 10 MLD (Ramnagar) and 50 MLD (Ramana) have been commissioned.

Treatment Capacity - 3471.84 MLD

Capacity Utilization of existing STPs: 2616.74 MLD (75.37%)

MLD of sewage being treated through Alternate technology: -

Gap in Treatment Capacity in MLD: 629.51

No. of Operational STPs: 105

No. of Complying STPs: 91

No. of Non-complying STPs: 14

No. of Non-operational STPs - 03

5

Details of each existing, under construction and Sanctioned STPs in the State:

Details of each existing STP in the State (September, 2021)

1. Details of 14 Non- Compliant STPs

Sl.

No.

Name and

Address of

STP

City/

Town /

District

Install

ed

Capaci

ty

(MLD)

Utilized

Capacity

(MLD)

Technology

/process

STP based

Institutions

responsible for

O&M of STP

Date BOD

(mg/l)

COD

(mg/l)

TSS

(mg/l)

TC

(MPN/1

00ml)

FC

(MPN/100

ml)

whether

Achieving or

Not

Achieving

1

13.5

MLD

STP at

Mauja

Umrain

Etawah 13.5 3.0 WSP

Nagar Palika

Parishad,

Etawah 03.09.21 33.0 264.0 104.0 280000 140000

Not

Achieving

2

03 MLD

STP

Firozabad

Firozabad 3 3 UASB Jal Kal 14.09.21 33.0 256.0 103.0 220000 160000 Not

Achieving

3

36 MLD

(9 MLD

CETP +

27 MLD

STP)

Kanpur

36 (9

MLD

CETP

+ 27

MLD

STP)

36 (9

MLD

CETP +

27 MLD

STP)

ASP U.P. Jal

Nigam 24.09.21 * 260.0 196.0 240000 130000

Not

Achieving

4

130 MLD

Jajmau,

Kanpur

Kanpur 130 120 ASP U.P. Jal

Nigam 24.09.21 * 260.0 196.0 240000 130000

Not

Achieving

5

12 MLD

DLW

STP

Varanasi 12 12 ASP DLW 29.09.21 48.0 320.0 185.0 540000 350000 Not

Achieving

6

Sl.

No.

Name and

Address of

STP

City/

Town /

District

Install

ed

Capaci

ty

(MLD)

Utilized

Capacity

(MLD)

Technology

/process

STP based

Institutions

responsible for

O&M of STP

Date BOD

(mg/l)

COD

(mg/l)

TSS

(mg/l)

TC

(MPN/1

00ml)

FC

(MPN/100

ml)

whether

Achieving or

Not

Achieving

6

13.59

MLD,

Masani,

Mathura

Mathura 13.59 8 Oxidation

Pond

U.P. Jal

Nigam 21.09.21 38.0 176.0 60.0 540000 170000

Not

Achieving

7

14.5

MLD

Trans-

yamuna,

Jamunapa

r,

Mathura

Mathura 14.50 7 Oxidation

Pond

U.P. Jal

Nigam 06.10.21 54 251 72 - -

STP is

functional,

but non-

compliant

8

16 MLD

Trans

Yamuna,

Laxmi

Nagar,

Mathura

Mathura 16 6 UASB

Reacter

U.P. Jal

Nigam 21.09.21 52.0 224.0 76.0 430000 170000

Not

Achieving

9

2.76

MLD

Goverdha

n STP

Mathura 2.76 2.76 Oxidation

Pond

Nagar Palika

Parishad 21.09.21 40.0 216.0 64.0 350000 110000

Not

Achieving

10

2.0 MLD

Greater

Noida

Authority

STP, Vill-

Badalpur

Greater

Noida 2 2 MBBR

Greater Noida

Authority 28.09.21 49.0 99.0 106.0 1700 610

Not

Achieving

11

15 MLD

ECO tech

-2

Greater

Noida 15 8 SBR

Greater Noida

Authority 28.09.21 58.0 102.0 98.0 48000 3400

Not

Achieving

7

Sl.

No.

Name and

Address of

STP

City/

Town /

District

Install

ed

Capaci

ty

(MLD)

Utilized

Capacity

(MLD)

Technology

/process

STP based

Institutions

responsible for

O&M of STP

Date BOD

(mg/l)

COD

(mg/l)

TSS

(mg/l)

TC

(MPN/1

00ml)

FC

(MPN/100

ml)

whether

Achieving or

Not

Achieving

12

20 MLD

ECO tech

-3

Greater

Noida 20 10 SBR

Greater Noida

Authority 28.09.21 51.0 112.0 191.0 2200 1400

Not

Achieving

13

137 MLD

Kasana,

GreaterN

oida

Greater

Noida 137 50 SBR

Greater Noida

Authority 28.09.21 57.00 108.0 169.0 38000 32000

Not

Achieving

14 26 MLD

Jhansi Jhansi 26 -- --

U.P. Jal

Nigam -- -- -- -- -- --

STP is

functional,

but non-

compliant

2. List of 03 Non-Operational STPs –

Sl.

No.

Name and

Address of

STP

District /

City/ Town

Installed

Capacity

(MLD)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Operation Status

(functioning/non-

operational (reason for

non-operational)/under

construction/constructed

& commissioned

Name of

river

catchment

Remark

1 Moradabad Moradabad 20 NA SBR MDA Not Operational Ramganga

River

Due to lack of sewage

generation from the New

MDA Colony near STP.

8

Sl.

No.

Name and

Address of

STP

District /

City/ Town

Installed

Capacity

(MLD)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Operation Status

(functioning/non-

operational (reason for

non-operational)/under

construction/constructed

& commissioned

Name of

river

catchment

Remark

2

4 MLD

Kanwara

Road

Banda /

Kanwara 4 --

Oxidation

process

U.P. Jal

Nigam Not Operational

ken river

sub

tributary

Yamuna

/Tributary

Ganga

River

LOA for rehab works at

Banda STP was issued to

M/s Verdhmanh

Engineering Works Pvt.,

Delhi Ltd. on 25.11.2020,

but work could not be

started before as

permission from Railway

Deptt. was required for

laying the rising main

pipeline beneath the

railway line. The

permission has been

given on 24.06.2021 and

presently, the rehab work

is in progress. The STP

will be made

operational by October,

2021.

3

5 MLD

Hathia

Nala

Sultanpur 5 5

Oxidation

Pond( Ist

Pond of II

Phase)

U.P. Jal

Nigam

Not Operational since

01.05.2021 -

(Inspected on-23.09.21

)

River

Gomti

Capacity upgradation is

being done under the

Namami Gange

Programme which is

proposed to be

completed by Dec-21

9

3. List of 91 Achieving STPs –

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

1 1.65 MLD Saifai Etawah 1.65 1.65 SBR U.P. Jal

Nigam 07.09.21 27.0 200.0 180000 110000 Achieving

Treated

sewage is

used for

plantation

2

23 MLD STP at

Mauja Odenya,

Padaria

Mainpuri 23.0 10.4 UASB

Nagar

Palika

Parishad

07.09.21 30.0 216.0 220000 170000 Achieving Ishan River /

River Ganga

3 3.42 MLD Near

Divyang kendra Chitrakoot 3.42 3.42

Oxidation

Pond

U.P. Jal

Nigam 10.09.20 22.0 115.2 92000 43000 Achieving

Lowland area

to River

Mandakini

4 42 MLD, Sajari

Kanpur Kanpur 42 22 ASP

U.P. Jal

Nigam 22.09.21 - 100.0 94000 58000 Achieving

Tributary of

River Ganga

5 210 MLD,

Bingawan Kanpur Kanpur 210 140 UASB

U.P. Jal

Nigam 21.09.21 - 180.0 920000 170000 Achieving

Tributary of

River Ganga

6

2.7 MLD

Fatehgarh

STP

Farrukhabad 2.7 2.0 WSP U.P. Jal

Nigam 21.09.21 - 140.0 110000 49000 Achieving River Ganga

10

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

7 13 MLD Jalalpur,

Amrapur Kanpur Dehat 13 10 SBR

U.P. Jal

Nigam 21.09.21 27.0 80.0 68000 35000 Achieving

Tributary of

River Ganga

8 50 MLD STP

Numayadahi Prayagraj 50 50 Bio-tower

Ganga

Pollution

control

unit, U.P.

Jal Nigam

22.09.21 20.0 40.0 14000 450 Achieving River

Yamuna

9 10 MLD STP

Ponghat Prayagraj 10 10 Bio-tower

Ganga

Pollution

control

unit, U.P.

Jal Nigam

22.09.21 18.0 32.0 7000 400 Achieving River Ganga

10 25 MLD STP

Kodra Prayagraj 25 25 Bio-tower

Ganga

Pollution

control

unit, U.P.

Jal Nigam

22.09.21 22.0 38.0 12000 450 Achieving River Ganga

11 60 MLD STP

Rajapur Prayagraj 60 60 UASB

Ganga

Pollution

control

unit, U.P.

Jal Nigam

22.09.21 22.0 46.0 24000 680 Achieving River Ganga

12 29 MLD STP

Salori-1 Prayagraj 29 29 FAB

Ganga

Pollution

control

unit, U.P.

Jal Nigam

22.09.21 24.0 52.0 35000 920 Achieving River Ganga

13

14 MLD STP

Salori-2

Expansion

Prayagraj 14 14 SBR

Ganga

Pollution

control

unit, U.P.

22.09.21 12.0 28.0 7900 400 Achieving River Ganga

11

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

Jal Nigam

14

80 MLD STP

Naini Prayagraj

20 20

ASP

Ganga

Pollution

control

unit, U.P.

Jal Nigam

22.09.21 26.0 50.0 17000 680 Achieving

River

Yamuna

15 60 60 River

Yamuna

16 120 MLD

Goithaha STP Varanasi 120 120 SBR

U.P. Jal

Nigam 21.09.21 14.0 76.0 1300 500 Achieving Varuna

17 140 MLD

Dinapur STP Varanasi 140 140 ASP

U.P. Jal

Nigam 21.09.21 17.0 96.0 1400 800 Achieving

River Ganga/

Varuna

18 38 MLD STP,

Mahilpur Road Saharanpur 38 38 UASB Jal Kal 28.09.21 21.0 188.0 940 790 Achieving

Hindon river

to Yamuna

river

19

6.5 MLD Awas

vikas Parishad

STP

Lucknow 6.5 6.5 SBR

U.P.

Awas

vikas

Parishad

21.09.21 20.0 125.0 40000 26000 Achieving River Gomti

20

37.5 MLD Awas

vikas Parishad

STP

Lucknow 37.5 37.5 SBR

U.P.

Awas

vikas

Parishad

21.09.21 22.0 136.0 49000 33000 Achieving River Gomti

21 345 MLD STP,

Bharwara Lucknow 345 345

UASB

Reacter

U.P. Jal

Nigam 21.09.21 26.0 148.0 70000 49000 Achieving River Gomti

12

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

22 56 MLD STP,

Daulatganj Lucknow

42+1

4 42+14 FAB

U.P. Jal

Nigam 21.09.21 27.8 160.0 46000 17000 Achieving River Gomti

23 U.P. Jal

Nigam

24

56 MLD Trans

Hindon

(Indirapuram),

Ghaziabad

Ghaziabad 56 56 UASBR Nagar

Nigam 22.09.21 21.0 57.0 320000 26000 Achieving River Hindon

25

56 MLD S.B.R.,

Bapudham,

Ghaziabad

Ghaziabad 56 56 SBR

Ghaziaba

d

Developm

ent

Authority

13.09.21 15.0 157.0 3300 1100 Achieving Hindon

26

30 MLD,

Sadullabad

(Loni), Ghaziabad

Ghaziabad 30 30 MBR U.P. Jal

Nigam 22.09.21 9.0 71.0 1700 920 Achieving Hindon

27

74 MLD S.B.R.,

Indirapuram,

Ghaziabad

Ghaziabad 74 74 SBR U.P. Jal

Nigam 22.09.21 8.0 49.0 1400 610 Achieving River Hindon

28

56 MLD,

Indirapuram,

(GDA),

Ghaziabad

Ghaziabad 56 56 SBR GDA 22.09.21 17.0 178.0 70000 26000 Achieving River Hindon

13

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

29

56 MLD S.B.R.,

Dudahaida Vijay

Nagar, Ghaziabad

Ghaziabad 56 56 SBR GDA 22.09.21 8.0 66.0 1400 930 Achieving River Hindon

30 56 MLD S.B.R.,

Morty, Ghaziabad Ghaziabad 56 56 SBR GDA 22.09.21 17.0 69.0 1100 400 Achieving River Hindon

31

70 MLD

U.A.S.B.R.

Dudahaida Vijay

Nagar, Ghaziabad

Ghaziabad 70 70 UASBR Nagar

Nigam 22.09.21 23.0 87.0 280000 170000 Achieving River Hindon

32

3 MLD STP

Brijghat Zone,

Garhmukeshwar

Hapur

Hapur /

Garhmuktesw

ar

3 1.8

UASB

followed

by

extended

aeration

U.P. Jal

Nigam

(NGRBA)

21.09.21 12.0 61.0 13000 910 Achieving

River Ganga

(Brijghat

Area)

33

6 MLD STP Garh

Zone,

Garhmukeshwar

Hapur

Hapur /

Garhmuktesw

ar

6 3.5

UASB

followed

by

extended

aeration

U.P. Jal

Nigam

(NGRBA)

21.09.21 18.0 74.0 1400 610 Achieving

Garh

Catchment

Area

34 3 MLD Pilkhaun Ghaziabad 3 3 MBBR U.P. Jal

Nigam 21.09.21 13.0 58.0 2700 1200 Achieving

River kali/

River Ganga

14

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

35 5 MLD Tronica

City, Loni Ghaziabad 5 3 MBR UPSIDC 22.09.21 20.0 199.0 2200 610 Achieving

Green belts

development

36

56 MLD S.B.R.

Govindpuram,

Ghaziabad

Ghaziabad 56 56 SBR GDA 22.09.21 20.0 106.0 7900 4900 Achieving River Hindon

37

78 MLD

Dhadhupura,

Agra

Agra 78 68.41 UASB U.P. Jal

Nigam 25.09.21 29.0 160.0 250000 190000 Achieving Onland

38 2.25 MLD Budi

ka Nagla, Agra Agra 2.25 2.97

Oxidation

Pond

U.P. Jal

Nigam 25.09.21 30.0 168.0 700000 310000 Achieving

Irrigation/Riv

er Yamuna

39

12 MLD Devri

Road,

(Bhimnagri),

Agra

Agra 12 6.35 UASB U.P. Jal

Nigam 25.09.21 28.0 128.0 310000 130000 Achieving

River

Yamuna

40

14 MLD

Jaganpur,

Sikandarpur, Agra

Agra 14 13.39 UASB U.P. Jal

Nigam 25.09.21 27.0 144.0 280000 120000 Achieving Onland

41

40 MLD

Sadarban,

Bichhpuri, Agra

Agra 40 18.73 UASB U.P. Jal

Nigam 25.09.21 27.0 128.0 190000 110000 Achieving

River

Yamuna

42

24 MLD

Dhadhupura

(New), Agra

Agra 24 18.91 UASB U.P. Jal

Nigam 25.09.21 25.0 144.0 240000 120000 Achieving Onland

15

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

43

36 MLD

Sadarwan

(Bichpuri) New

Agra 36 36 SBR ADA 25.09.21 25.0 144.0 160000 110000 Achieving Land/ Agra

canal

44

4.50 MLD

Kalindi Vihar,

Agra

Agra 4.5 4.5 UASB ADA 25.09.21 28.0 168.0 240000 130000 Achieving River

Yamuna

45 03 MLD Pandav

Nagar, Meerut Meerut 3 2.7 ASP MDA 27.09.21 16.0 154.0 3200 2500 Achieving

River Kali

(East)

46

07 MLD

Pallavpuram-1,

Meerut

Meerut 7 6.5 ASP MDA 27.09.21 14.0 148.0 3100 2400 Achieving River Kali

(East)

47 10 MLD Lohiya

Nagar, Meerut Meerut 10 2 ASP MDA 27.09.21 17.0 156.0 3300 2700 Achieving

River Kali

(East)

48

15 MLD

Shatabdinagar,

Meerut

Meerut 15 4.8 ASP MDA 27.09.21 17.0 156.0 3200 2500 Achieving River Kali

(East)

49

7 MLD

Pallavpuram-2,

Meerut

Meerut 7 7 MBBR MDA 27.09.21 15.0 156.0 3300 2500 Achieving River Kali

(East)

50

15 MLD

Vedvyaspuri

Meerut

Meerut 15 4.5 ASP MDA 27.09.21 15.0 148.0 3100 2600 Achieving River Kali

(East)

51

06 MLD

Rakshapuram,

Meerut

Meerut 6 4.4 ASP MDA 27.09.21 15.0 144.0 3200 2600 Achieving River Kali

(East)

16

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

52

06 MLD

Shradhapuri-1,

Meerut

Meerut 6 5.5 ASP MDA 27.09.21 17.0 156.0 3400 2500 Achieving River Kali

(East)

53 06 MLD Sainik

Vihar Meerut 6 5.95 UASB MDA 27.09.21 15.0 144.0 3100 2500 Achieving

River Kali

(East)

54

5 MLD

Modipuram

Tiraha

Meerut 5 4.9 ASP MDA 27.09.21 17.0 152.0 3300 2700 Achieving River Kali

(East)

55

07 MLD Sports

Goods Complex,

Meerut

Meerut 7 4 ASP MDA 27.09.21 16.0 144.0 3300 2600 Achieving River Kali

(East)

56

72 MLD Garh

road (Jagriti

vihar)

Meerut 72 65 SBR U.P. Jal

Nigam 27.09.21 7.0 86.0 830 680 Achieving River Ganga

57 10 MLD Ganga

Nagar, Meerut Meerut 10 3.8 SBR MDA 27.09.21 16.0 152.0 3200 2600 Achieving

River Kali

(East)

58

06 MLD

Shradhapuri-

Phase-2, Meerut

Meerut 6 5.6 ASP MDA 27.09.21 15.0 146.0 3200 2500 Achieving River Kali

(East)

59

32.5 MLD Nagar

Palika Parishad,

Muzaffarnagar

Muzaffar

Nagar 32.5 32.5

Oxidation

Pond

Nagar

Palika

Parishad,

Muzaffar

nagar

07.09.21 28.0 120.0 230000 140000 Achieving River Hindon

17

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

60 12 MLD Ayodhya Ayodhya 12 6 UASB U.P. Jal

Nigam 21.09.21 20.0 88.0 540000 350000 Achieving River Saryu

61

08 MLD STP

Near 100 Bed

Hospital

Vrindavan,

Mathura

Mathura 8 7 UASB

Reacter

U.P. Jal

Nigam 21.09.21 28.0 160.0 140000 790000 Achieving

River

Yamuna

62 30 MLD Masani

Mathura Mathura 30 20 SBR

U.P. Jal

Nigam 15.09.21 29.0 152.0 ---- ---- Achieving

Final

Discharge on

Forest Land

63 33 MLD Sector-

54, Noida Noida 33 33 SBR

Noida

Authority 13.09.21 15.0 112.0 2200 680 Achieving

River

Yamuna

64 25 MLD Sector-

50, Noida Noida 25 25 SBR

Noida

Authority 13.09.21 21.0 114.0 1100 400 Achieving

River

Yamuna

65 35 MLD Sector-

123, Noida Noida 35 35 SBR

Noida

Authority 13.09.21 21.0 152.0 2200 1700 Achieving River Hindon

66 50 MLD Sector-

168, Noida Noida 50 50 SBR

Noida

Authority 13.09.21 22.5 160.0 2700 930 Achieving

River

Yamuna

67 34 MLD Sector -

50 Noida Noida 34 34 SBR

Noida

Authority 13.09.21 22.5 152.0 2700 1400 Achieving

River

Yamuna

68 54 MLD Sector-

54, Noida Noida 54 54 SBR

Noida

Authority 13.09.21 16.5 136.0 1400 610 Achieving

River

Yamuna

69

0.805 MLD Ahara

Road, Zone-A,

Anoopshahar

Bulandhsahar 0.80

5 0.805

Oxidation

Pond

U.P. Jal

Nigam 29.09.21 26.0 212.0 3400000 2100000 Achieving River Ganga

18

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

70

1.75 MLD Ahara

Road, Zone-B,

Anoopshahar

Bulandhsahar 1.75 1.75 Oxidation

Pond

U.P. Jal

Nigam 29.09.21 28.0 228.0 2800000 1600000 Achieving River Ganga

71 04 MLD Narora

(NGRBA) Bulandhsahar 4 4 SBR

U.P. Jal

Nigam 22.09.21 18.0 136.0 2400 920 Achieving For Irrigation

72

2.25 MLD Narora

Atomic power

Station Narora

Township

Bulandhsahar 2.25 2.25 ASP

Narora

Atomic

power

Station

22.09.21 20.0 144.0 1600 540 Achieving For Irrigation

73

1.5 MLD

Anoopshahar

Zone A

(NGRBA)

Bulandhsahar 1.5 1.5 MBBR U.P. Jal

Nigam 22.09.21 28.0 216.0 2100000 1100000 Achieving River Ganga

74

01 MLD STP

Zone-B

Anoopshahar

Bulandhsahar 1 1 MBBR U.P. Jal

Nigam 22.09.21 24.0 216.0 250000 130000 Achieving River Ganga

75 24 MLD Bijnor Bijnor 24 10 UASB U.P. Jal

Nigam 20.09.21 12.0 40.0 2800 130 Achieving River Ganga

76 58 MLD

Moradabad Moradabad 58 18 SBR

U.P. Jal

Nigam 21.09.21 22.0 92.0 110 50 Achieving

Ramganga

River

77 15 MLD

Pehrigaon Rampur 15 0.07 UASB

U.P. Jal

Nigam 21.09.21 22.0 88.0 1100 500 Achieving

Ramganga

River

78 14 MLD

Benzirpur Rampur 14 0.11 UASB

U.P. Jal

Nigam 21.09.21 26.0 96.0 120 50 Achieving

Ramganga

River

19

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

79 5 MLD Rampur Rampur 5 0.003 SBR U.P. Jal

Nigam 21.09.21 9.6 48.0 130 60 Achieving

Ramganga

River

80

15 MLD S.T.P.

Jharkhandi,

Maherwa ki Bari

Gorakhpur 15 15 ASP U.P. Jal

Nigam 25.09.21 9.0 40.0 2800 1600 Achieving Ramgarhtal

81

30 MLD S.T.P.

Opp. Deoria

bypass Road

Gorakhpur 30 30 ASP U.P. Jal

Nigam 08.10.21 9.0 24.0 2600 1400 Achieving Ramgarhtal

82

04 MLD

Vrindavan Near

Pagal Baba

Mandir, Mathura

Mathura 4 3.8 Oxidation

Pond

Nagar

Palika

Parishad

06.10.21 25.0 128.0 350000 140000 Achieving Yamuna

83 10 MLD

Peelakhar, Agra Agra 10 9.74

Oxidation

Pond

U.P. Jal

Nigam 18.10.21 260 90.0 900000 540000 Achieving Yamuna

84 9.8 MLD

Bhagwanpur STP Varanasi

8.0+

1.8 8.0+1.8 ASP

U.P. Jal

Nigam 16.10.21 32.0 162.0 31000 17000 Achieving Ganga

85 14 MLD Pakka

Pokhra Mirzapur 14 14 UASB

U.P. Jal

Nigam 05.10.21 28.0 49.0 49000 22000 Achieving Ganga

86 4 MLD

Vindhyachal

Vindhyachal /

Mirzapur 4 2.5 WSP

U.P. Jal

Nigam 25.09.21 30.0 48.0 34000 17000 Achieving Ganga

87 5 MLD, Jajmau

Kanpur Kanpur 5 5 UASB

U.P. Jal

Nigam 27.09.21 28.0 48.0 240000 130000 Achieving Ganga

88 43 MLD Jajmau,

Kanpur Kanpur 43 37 ASP

U.P. Jal

Nigam 12.10.21 30.0 92.0 240000 130000 Achieving Ganga

89

67 MLD

Mohammadpur,

Biharipur

Firozabad 67 67

ASP+

extended

aeration

U.P. Jal

Nigam 20.10.21 8.0 40.0 280000 180000 Achieving Yamuna

90 80 MLD Dinapur

STP Varanasi 80 80 ASP

U.P. Jal

Nigam 30.09.21 24.0 44.0 -- 402 Achieving Ganga

20

Sl.

No.

Name and Address of

STP

City/ Town /

District

Install

ed

Capac

ity

(MLD

)

Utilized

Capacity

(MLD)

Technology/

process STP

based

Institutions

responsible

for O&M of

STP

Date

BOD

(mg/

l)

COD

(mg/l)

TC

(MPN/100

ml)

FC

(MPN/100

ml)

whether

Achieving or

Not Achieving

Name of river

catchment

91 10.445 MLD STP

near Tixi Temple Etawah

10.4

45 10.44 WSP

U. P. Jal

Nigam 21.10.21 29 148 -- -- Achieving Yamuna

21

21

E. Details of Industrial Pollution:

No. of industries in the State: 11,332

Red- 2058, Orange- 5068, Green - 4206

No. of water polluting industries in the State: 1648 (Grossly Polluting Industries)

Quantity of effluent generated from the industries in MLD: 850.5 MLD

Quantity of Hazardous Sludge generated from the Industries: 524343.50 MTA

Number of industrial units having ETPs: 1404

Number of industrial units connected to CETP: 514 (Most of Tannery Unit at Kanpur are

presently closed)

Number and total capacity of ETPs (details of existing/ under construction / proposed)

Compliance status of the ETPs: 1464 GPI Industries were inspected by Board along with

third party. Actions taken are annexed as Annexure - I

Number and total capacity of CETPs (details of existing/ under construction / proposed)

Number of existing CETP- 07

Capacity of CETP – 58.55 MLD

No. of under construction CETP - 03

Capacity of under construction CETP – 26.65 MLD

Status of compliance and operation of the CETPs

S.No. Name Existing Capacity District Compliance Status

1. Apparel Park Tronica City CETP,

Phase-I (for textile units),

Ghaziabad

6 MLD Ghaziabad Yes

2. CETP, HPDA, Pilkhaun, Hapur 2.1 MLD Hapur, Ghaziabad Yes

3. Banther Industrial Pollution

Control Co. CETP, Banther, Unnao 4.5 MLD Unnao Yes

4. Unnao Tanneries Pollution Control

Company (CETP) Site-II, Unnao 2.15 MLD Unnao Yes

5. CETP, Industrial Area, Site-A,

Mathura 6.25 MLD Mathura Yes

6. CETP, UPSIDC Textile Complex,

Rooma, Kanpur (for textile units) 1.5 MLD Kanpur No

7. CETP Jajmau, Kanpur 36 MLD Kanpur No

22

22

F. Solid Waste Management:

Total number of Urban Local Bodies and their Population

Urban Local Bodies- 651

Urban Population – 4.5 Crore

Current Municipal Solid Waste Generation- 14468 TPD approx.

Number, installed capacity and utilization of existing MSW processing facilities in TPD

(bifurcated by type of processing eg- Waste to Energy (Tonnage and Power Output),

Compost Plants (Windrow, Vermi, decentralized pit composting), biomethanation, MRF

etc

No. of MSW processing facilities- 17 Plants (all are compost plant)

Installed Capacity- 5,520 TPD

Utilization of existing MSW processing facilities- 5,520 TPD (100%)

Action plan to bridge gap between Installed Capacity and Current Utilization of

processing facilities (if Gap > 20%) - NA

No. and capacity of C&D waste processing plants in TPD (existing, proposed and under

construction)

1. C& D Waste Processing Facilities

Noida

(Sector-81)

Facility of 300 MTD has come into operation since 05-10-

2020.

Ghaziabad (Hindon Vihar) Facility of 400 MTD is functional.

Lucknow, Agra, Varanasi,

Kanpur & Prayagraj

Funds @ Rs. 1.5 Crore/City released to concerned Municipal

Corporation. Expected to be commissioned by March, 2022.

Meerut C & D Waste Management Facility is to be developed in 2

years.

Town No. of

industries

Industrial

discharge

Status of ETPs Status of CETPs (existing,

under construction & proposed)

State of U.P. 1108

Operational

779.639 MLD Installed and Operational As Above

23

23

Total no. of wards, no. of wards having door to door collection service, no. of wards

practicing segregation at source

Total no. of wards - 12022

No. of wards having door to door collection service - 12022 (100%)

No. of wards practicing segregation at source – 8294

Details of MSW treatment facilities proposed and under construction (no., capacity, and

technology):

Proposed Completion

Date

Number, Place and Capacity

Plants to be made

operational by 31.03.2022

(Arbitration resolved)

08 Plants with 895 TPD (Fatehpur, Sambhal, Badaun, Mirzapur,

Balia, Rampur, Jhansi & Meerut)

Plants under land dispute to

be resolved and

commissioned

08 Plants with 930 TPD (Bareilly, Firozabad, Loni, Nazibabad,

Bhadohi, Basti, Gorakhpur, Akbarpur-Ambedkar Nagar)

The land has been Procured in Bareily, Firozabad and

Loni.

75% construction work is completed in Loni.

DPR has been approved from SHPSC in Bareily and

Bhadohi and in Firozabad, DPR is planned to be presented

before the committee in the next SHPSC.

Land identified in Basti was not suitable and work under

progress to make it suitable.

Land has been identified in the Gorakhpur. Soil testing and

survey is done. DPR is completed and shall be presented

before the next SHPSC.

Land has been identified in the Akbarpur (Ambedkar

Nagar).

New plants sanctioned to be

completed by December,

2022

20 plants with capacity of 1720 TPD are approved from the

SHPSC and are under tendering process. 14 Plants with capacity

of 2025 TPD, DPR is prepared and to be presented to the next

SHPSC. Other than these 34 plants the 11 more plants are planned

to be established by December 2022.

24

24

It is targeted that all smaller ULBs (approximately 450) that generate less

than 10 TPD of solid waste establish composting facility for processing by

December, 2022.

No. and area (in acres) of uncontrolled garbage dumpsites and Sanitary Landfills.-

No. and area (in acres) of legacy waste within 1km buffer of both side of the rivers-

There is no legacy waste site situated within 1 KM of the banks of rivers.

No. of drains falling into rivers and no. of drains having floating racks/screens installed to

prevent solid waste from falling into the rivers- Out of total 504 drains falling into the

rivers 96 drains having Bar mesh/ Floating Racks.

Status of ULB wise Management of Solid Waste

ULB Total MSW

generation in

TPD

Total MSW

being processed

in TPD

Existing

MSW

facilities

Utilization

Capacity of the

existing MSW

facilities

Proposed MSW

Facilities &

Completion

Timeline

651 14468 9,860 5,520

TPD

100% As Above

G. Bio-medical Waste Management:

Total Bio-medical generation: 52.5 MT/Day

No. of Hospitals and Health Care Facilities: 25,411

Status of Treatment Facility/ CBMWTF:

There are 20 Common Biomedical Waste Treatment Facilities (CBWTFs) installed in the

State, out of which18 are functional and 01 is under up gradation and 01 is closed by the

Board.

Total incineration capacity of 18 functional CBWTFs is 54.5 MT/Day which is adequate

to treat the Biomedical Waste generated in the State.

25

25

UPPCB regularly inspects the CBWTFs for ensuring treatment of BMW as per the

provisions of the BMW Rules, 2016.

08 CBWTFs were found defaulting in the past and action has been taken against them by

UPPCB by imposing Environmental Compensation of Rs. 1.43 Crore.

H. Hazardous Waste Management:

Total Hazardous Waste generation: 524343.50 MT/Annum

No. of Industries generating Hazardous waste: 2597

Treatment Capacity of all TSDFs: - 8.1 Lakh MT

Avg. Quantity of Hazardous waste reaching the TSDFs and Treated: 524343.50 MT /Annum

Details of on-going or proposed TSDF: One TSDF facility is proposed in Amroha

District, which got Environmental clearance from SEIAA and UPPCB issued Consent to

establish.

I. Plastic Waste Management:

Total Plastic Waste generation: 254401.8 Ton per Annum

Treatment/ Measures adopted for reduction or management of plastic waste:

100 Tons Plastic Waste used in Lucknow, Kanpur, Meerut and Jhansi

for Road Construction.

Total 635.22 MT Plastic Waste in Paper Mills has been disposed as co-processing with M/s Ultratech Cement during year 2020-21.

J. Details of Alternate Treatment Technology being adopted by the State/UT

Uttar Pradesh Septage Management Policy-2019 has been approved by the

Government on 30.10.2019. FSTP Projects costing Rs. 160 Crores have been

sanctioned for covering all the 58 AMRUT towns in State with population more

than 1 lakh. The Faecal and Septage Treatment Plant Projects have been

implemented in Jhansi and Unnao and are under construction in 54 cities namely,

Loni, Lakhimpur, Raebareli, Modinagar, Aligarh, Shahjahapur, Ayodhya,

Shamli, Baraut, Hapur,Khurja, Hathras, Amroha, Badaun, Farukhabad, Hardoi,

26

26

Sitapur, Bahraich, Gonda, Jhansi, Latitpur, Banda, Fatehpur, Basti, Deoria,

Saharanpur, Mathura, Rampur, Mujaffarnagar, Lucknow, Kanpur, Agra,

Meerut, Varanasi, Prayagraj, Ghaziabad, Gorakhpur, Etawah, Firozabad,

Mainpuri, Sultanpur, Bulandsahar, Faizabad, Moradabad, Pilibhit, Chandausi,

Orai, Akbarpur, Maunath Bhanjan, Mirzapur, Balia, Ghazipur, Chunar. The

projects of septage management have been approved in Pt. Deen Dayal

Upadhayay Nagar, Azamgarh, Sikohabad and Jaunpur and work will start after

availability of land.

K. Identification of polluting sources including drains contributing to river

pollution and action as per NGT order on in situ treatment: CPCB imposed

total Rs. 176.40 Crore EC on State Government vide Letter Dated 03.02.2021.

Rs. 102 Crore EC imposed on 170 untapped drains, Rs. 48 Crore on 120 untapped

drains in which Alternate Treatment Technology was not adopted (Annexure-II).

In order to ensure compliance of the orders of Hon’ble Tribunal, the Principal

Secretary Urban Development has issued instructions vide Letter No: 142/Nine-9-

2019- 89J/2001 Dated: 03.02.2020 to the concerned ULBs for taking up the

interim measures for treatment of drains till permanent infrastructure for treatment

of sewage is created.

L. Details of Nodal Officer appointed by Chief Secretary in the State/UT:

Three tier monitoring mechanism developed and functional as submitted in the

previous reports.

I. Details of meetings carried under the Chairmanship Chief of Secretary in the

State/UT: MoM Dated 16.08.2021 and 08.10.21 is Annexed as Annexure-II and

Annexure-II A

M. XIII. Latest water quality of polluted river, its tributaries, drains with flow

details and ground water quality in of polluted the catchment rivers:

Comparative Graphical presentation of water quality of Polluted Rivers (2019-

2021) in the State is enclosed herewith and marked as Annexure No.- III. Total

Coliform was found above the Acceptable limit (˂ 500 MPN/ 100 ml) for outdoor

bathing in all sampling locations of all the rivers. Maximum TC values was found

in Kali east River at sampling location of Babugarh (3300000 MPN/100 ml) and

27

27

minimum value of TC (600 MPN/100 ml) and BOD (1.6 mg/L) was reported in

Ramganga River at Agwanpur Village, Moradabad. Maximum BOD was found in

Hindon River. In river Ganga maximum TC value was reported at Downstream,

Kanpur.

XIV. Ground water regulation: Details submitted in Previous MPR (Dec. 2020 – Feb.

2021).

XV. Good irrigation practices being adopted by the State: Information not received

from Agriculture Department.

XVI. Rain Water Harvesting: Details submitted in Previous MPR (Dec. 2020 – Feb.

2021).

XVII. Demarcation of Floodplain and removal of illegal encroachments:

Details submitted in Previous MPR (Oct. – Nov. 2020).

XVIII. Maintaining minimum e-flow of river:

Details submitted in Previous MPR (Oct. – Nov. 2020).

XIX. Plantation activities along the rivers:

a). Across the State

22.59 Crore in 2019-20

25.87 Crore in 2020-21

XX. Development of Biodiversity Park: Status submitted in the MPR of Month June-

July 2020.

XXI. Reuse of Treated Water: At present nearly 410 MLD treated water is being used in

agriculture, rest is going for augmentation of river flow. Use of treated waste water

for any other purpose will require tertiary treatment and no STP in Uttar Pradesh as

on date has tertiary treatment facility. Central Public Health and Environmental

Engineering Organization (CPHEEO) manual permits the use of secondary treated

water only for non -edible crops. The use of treated water in agriculture is being

done at Jajmau, Prayagraj, Varanasi etc for non -edible crops.

28

28

XXII. Model River being adopted by the State & Action Proposed for achieving the

bathing quality standards:

XXIII. Status of Preparation of Action Plan by the 13 Coastal States: NA

XXIV. Regulation of Mining Activities in the State/UT: Details submitted in Previous

MPR (Dec. 2020 – Feb. 2021).

29

Status of Industries

Total Industries inspected (July 2020 to July 2021)

1464

Total Industries found Complying 856

Total Industries found Non-Complying (Show Cause issued) 296

Industries found Temporary closed 261

Industries found Permanently closed 51

Show cause for EC against 20 defaulter units Rs. 53.88 Lakhs

EC Imposed against 197 defaulter units Rs. 17.31 Cr

EC recovered from 94 Industries Rs. 3.60 Cr

Annexure - I

Scanned with CamScanner

Annexure- II

30

Scanned with CamScanner31

Scanned with CamScanner32

Scanned with CamScanner33

Scanned with CamScanner34

Annexure-II A

35

36

37

38

39

8.5

8.1

8.0

7.9

8.0

7.8

7.6

7.6

7.0

8.6

8.7

8.8

8.5

8.4

8.2

8.5

8.3

7.8

7.7

7.5 9.

2

9.39.7

9.3 9.9

9.7

9.6

9.3

8.4

8.2

8.1 8.

8

9.0

0.0

2.0

4.0

6.0

8.0

10.0

12.0

U/s

Kan

nau

j

D/s

Kan

nau

j

Bit

hoor,

Kan

pur

At

Bhai

rao G

hat

U/s

Kan

pur

At

D/s

Shukla

gan

j

At

Gola

Ghat

At

Jajm

au B

ridge

D/s

Kan

pur

Dal

mau

, R

aibar

eli

Kal

a K

ankar

, P

rata

pgar

h

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Ganga

Year 2019-2021 (Jan to July)2019

2020

2021

8.4 8.

8

8.4

8.4

8.2

7.5 7.9 8.2

7.1

7.2 7.

98.9

9.1

8.6 9.

1

8.3

7.4 7.8 8.

6

7.7

7.6 8.

18.4 8.

9

8.4

8.3 8.7

7.8 8.

3 8.9

8.0

7.7 8.

5

0.01.02.03.04.05.06.07.08.09.0

10.0

Kad

a G

hat

U/s

Pra

yag

raj

D/s

Pra

yag

raj

A/c

Tam

sa r

iver

, S

irsa

,S

on B

arsa

U/s

Vin

dhyac

hal

,M

irza

pur

D/s

Mir

zapur

At

Chunnar

Ponto

on

Bri

dge

U/s

Var

anas

i

D/s

Var

anas

i

Tar

ighat

D/s

Ghaz

ipur

A/c

Go

mti

riv

er,

Bh

usa

ula

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Ganga

Year 2019-2021 (Jan to July)

2019

2020

2021

Annexure-III

40

2.9 3.

3

3.1

3.1

3.1 3.

4 3.7 4.0 4.

4

3.7

3.6

2.4 2

.7 2.8 3.0

3.0 3.

2 3.7 3.9

3.9

3.8

3.8

2.7 3

.0 3.1

3.2

3.3 3.5 3.

7 4.0 4.

3

4.0

3.8

0.00.51.01.52.02.53.03.54.04.55.0

U/s

Kan

nau

j

D/s

Kan

nau

j

Bit

hoor,

Kan

pur

At

Bhai

rao G

hat

U/s

Kan

pur

At

D/s

Shukla

gan

j

At

Gola

Ghat

At

Jajm

au B

ridge

D/s

Kan

pur

Dal

mau

, R

aibar

eli

Kal

a K

ankar

,P

rata

pgar

h

BO

D (

mg

/L)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River Ganga

Year 2019-2021 (Jan to July)2019

2020

2021

3.1

2.8

2.8

2.6 2.

7

3.6

3.2

2.6

3.8

3.8

3.3

2.4

2.4

2.4

2.3 2

.6

3.7

3.3

2.6

3.8

3.8

3.2

2.6 2.

7

2.6

2.6

2.3

3.7

3.2

2.3

3.8 4.0

3.1

0.00.51.01.52.02.53.03.54.04.5

Kad

a G

hat

U/s

Pra

yag

raj

D/s

Pra

yag

raj

A/c

Tam

sa r

iver

, S

irsa

,S

on B

arsa

U/s

Vin

dhyac

hal

,M

irza

pur

D/s

Mir

zapur

At

Chunnar

Ponto

on

Bri

dge

U/s

Var

anas

i

D/s

Var

anas

i

Tar

ighat

D/s

Ghaz

ipur

A/c

Gom

ti r

iver

,B

husa

ula

BO

D (

mg/L

)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River Ganga

Year 2019-2021 (Jan to July)

2019

2020

2021

41

3817

4625

4100

4133

4442

5633

6266

2170

8

4225

0

3625

3575

3625

5325

4875 79

50

7900 12

875

1928

3

3591

7

4033

3

2773

2673

3180

3740

3480

4060

5200

6000 11

529

2000

0

2814

3

29

29

2857

05000

1000015000200002500030000350004000045000

U/s

Kan

nau

j

D/s

Kan

nau

j

Bit

hoor,

Kan

pur

At

Bhai

rao G

hat

U/s

Kan

pur

At

D/s

Shu

kla

gan

j

At

Gola

Ghat

At

Jajm

au B

ridge

D/s

Kan

pur

Dal

mau

, R

aibar

eli

Kal

a K

ankar

, P

rata

pgar

hTota

l C

oli

form

(M

PN

/100m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Ganga

Year 2019-2021 (Jan to July)2019

2020

202120

333

1778

3

1845

0

1483

3

1933

1616

7

1125

0

1992

3275

0

2858

3

1350

0

30

36

3058

32

83

33

00

2358

2000

0

1433

3

2075

2141

7

2241

7

1271

7

2129

2300

2286

1429

1886

2114

3

1371

4

1429

1842

9

2100

0

1200

0

05000

100001500020000250003000035000

Kad

a G

hat

U/s

Pra

yag

raj

D/s

Pra

yag

raj

A/c

Tam

sa r

iver

, S

irsa

, S

on

Bar

sa

U/s

Vin

dhyac

hal

, M

irza

pur

D/s

Mir

zapur

At

Chun

nar

Ponto

on B

ridge

U/s

Var

anas

i

D/s

Var

anas

i

Tar

ighat

D/s

Ghaz

ipur

A/c

Gom

ti r

iver

, B

husa

ula

Tota

l C

oli

form

(M

PN

/100m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Ganga

Year 2019-2021 (Jan to July)2019

2020

2021

42

2100

2717

2275

2367

2583

3533

3650

1107

5

2475

0

2933

2867

1633

2317

2142 39

33

3583 65

42 8317

1382

5

1850

8

1873

1818

1560

2140

1700

1920

2760

3060 60

57

1270

0

1340

0

1557

1500

0

5000

10000

15000

20000

25000

30000

U/s

Kan

nau

j

D/s

Kan

nau

j

Bit

hoor,

Kan

pur

At

Bhai

rao G

hat

U/s

Kan

pur

At

D/s

Shukla

gan

j

At

Gola

Ghat

At

Jajm

au B

ridge

D/s

Kan

pur

Dal

mau

, R

aibar

eli

Kal

a K

ankar

,P

rata

pgar

h

Faec

al C

oli

form

(M

PN

/100m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Ganga

Year 2019-2021 (Jan to July)2019

2020

202110

225

87

42

9158

7075

933

9250

6417

983

1900

0

1300

0

7333

1464

1293

1397

1347

1217

1195

0

7442

1025

1253

3

1277

5

7258

1020

1103

10

39

819

1000

1185

7

8143

829

1114

3

12

28

6

70

00

02000400060008000

100001200014000160001800020000

Kad

a G

hat

U/s

Pra

yag

raj

D/s

Pra

yag

raj

A/c

Tam

sa r

iver

, S

irsa

, S

on

Bar

sa

U/s

Vin

dhyac

hal

, M

irza

pur

D/s

Mir

zapur

At

Chunnar

Po

nto

on B

ridge

U/s

Var

anas

i

D/s

Var

anas

i

Tar

ighat

D/s

Ghaz

ipur

A/c

Gom

ti r

iver

, B

husa

ula

Faec

al C

oli

form

(M

PN

/100m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Ganga

Year 2019-2021 (Jan to July)

2019

2020

2021

43

Zero (0)/NIL indicates value of Dissolved Oxygen not reported from RO Noida in respective year i.e.2021.

2.6

0.3

4.5

5.4

5.3

5.3

4.8

4.8

4.6

5.8

5.3

4.8

7.4

7.8

5.8 5.9

8.4

8.1

8.1

8.0

3.1

0.8

6.4

6.2

6.1 6.2

5.9 6.0

5.9

6.3

5.8

5.3

5.7

5.5 5

.8

5.6

8.7

8.7

8.4

8.2

0.5

0.0

6.9

6.5

6.5

6.1

5.7

5.6

5.5

6.7

6.1

5.6

5.6

5.3

5.9

5.5

8.1

7.8

7.8

7.8

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

U/S

Okhla

Bar

rage,

Noid

a

D/S

Vil

lage

Ghar

bar

a/T

ilw

ara,

Noid

a

Shah

pur,

Mat

hura

U/s

Vri

ndav

an

Kes

i G

hat

Vri

ndav

an

D/s

Vri

ndav

an

U/s

Mat

hura

Vis

hra

m G

hat

, M

athura

D/s

Mat

hura

U/s

Kai

lash

ghat

, A

gra

U/s

Wat

erw

ork

s, A

gra

D/s

Taj

mah

al, A

gra

U/s

Fir

oza

bad

D/s

Fir

oza

bad

U/s

Eta

wah

D/s

Eta

wah

U/s

Wat

er I

nta

ke,

Pra

yag

raj

D/s

Bal

ua

Gh

at P

rayag

raj

D/s

Ch

hac

hh

ar n

ala,

Pra

yag

raj

D/s

Em

ergen

cy O

utf

all,

Pra

yag

raj

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Yamuna

Year 2019-2021 (Jan to July)

2019

2020

2021

44

26

.9

50

.8

12.5

8.8

9.4

9.2

9.7 11

.0

10.9

11.3

12.7

14.5 16

.7 20

.3

14.1 16

.0

2.0

2.4

2.4

2.4

18.8

34

.8

7.5

8.1

8.1

8.3

8.3

8.9 9.0 11

.2

13.0

14.2

14.5

16.3

14.8

16.4

1.9

2.1

2.2

2.1

23.4

29.4

7.9

8.3

8.3

8.7 9.2

10.1

10.1

11.6 13

.5 15.5 1

9.1 21

.1

17

.5 20

.0

2.4

2.5

2.5

2.6

0.0

10.0

20.0

30.0

40.0

50.0

60.0

U/S

Ok

hla

Bar

rage

, No

ida

D/S

Vil

lage

Gh

arb

ara/

Til

war

a, N

oid

a

Shah

pu

r, M

ath

ura

U/s

Vri

nd

avan

Kes

i Gh

at V

rin

dav

an

D/s

Vri

nd

avan

U/s

Mat

hu

ra

Vis

hra

m G

hat

, Mat

hu

ra

D/s

Mat

hu

ra

U/s

Kai

lash

ghat

, Agr

a

U/s

Wat

erw

ork

s, A

gra

D/s

Taj

mah

al, A

gra

U/s

Fir

oza

bad

D/s

Fir

oza

ba

d

U/s

Eta

wah

D/s

Eta

wah

U/s

Wat

er I

nta

ke, P

raya

graj

D/s

Bal

ua

Gh

at P

raya

graj

D/s

Ch

hac

hh

ar n

ala,

Pra

yagr

aj

D/s

Em

erg

ency

Ou

tfal

l, P

raya

graj

BO

D (

mg

/L)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River Yamuna

Year 2019-2021 (Jan to July)

2019

2020

2021

45

Zero (0) indicates Total & Feacal Coliform not reported from RO Noida & Firozabad in respective years.

0 0

1034

17

8300

0

8091

7

7955

6

8000

0

8883

3

9800

0

3633

3 5466

7

1092

50

0 0 0 0

4708 11

042

87

83

8458

0 0

6072

7

6908

3

6800

0

7883

3

8150

0

9250

0 1070

00

3441

7

4516

7

8375

0

0 0 0 0 1792

2425

2342

2117

0 0

6371

4

7014

3

7014

3 8571

4

6900

0 9071

4

9828

6

29

71

4

3657

1

8800

0

3385

7

1051

43

3500

0

9714

3

1214

1457

1400

1400

0

20000

40000

60000

80000

100000

120000

U/S

Ok

hla

Bar

rage,

Noid

a

D/S

Vil

lag

e G

har

bar

a/T

ilw

ara,

Noid

a

Shah

pur,

Math

ura

U/s

Vri

ndav

an

Kes

i G

hat

Vri

ndav

an

D/s

Vri

ndav

an

U/s

Mat

hura

Vis

hra

m G

hat,

Mat

hura

D/s

Mat

hu

ra

U/s

Kai

lash

ghat

, A

gra

U/s

Wate

rwork

s, A

gra

D/s

Taj

mah

al, A

gra

U/s

Fir

oza

bad

D/s

Fir

oza

bad

U/s

Eta

wah

D/s

Eta

wah

U/s

Wate

r In

tak

e, P

ray

agra

j

D/s

Bal

ua

Ghat

Pra

yag

raj

D/s

Ch

hac

hh

ar n

ala,

Pra

yagra

j

D/s

Em

erg

en

cy O

utf

all

, P

rayag

raj

Tota

l C

oli

form

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Yamuna

Year 2019-2021 (Jan to July)

2019

2020

2021

46

Zero (0) indicates Total & Feacal Coliform not reported from RO Noida & Firozabad in respective years.

0 0

4010

0

4190

9

4436

4 5727

3

54

16

7 6475

0 7345

5

1525

0

1925

0

3800

0

0 0 0 0 605

10

26

960

872

0 0

3500

0

3657

1

3657

1 4957

1

3642

9

5800

0

6314

3

1257

1

1671

4 2985

7

1942

9 3028

6

2114

3

2900

0

479

716

674

669

0

10000

20000

30000

40000

50000

60000

70000

80000

U/S

Okhla

Bar

rage,

Noid

a

D/S

Vil

lag

e G

har

bar

a/T

ilw

ara,

Noid

a

Shahpur,

Math

ura

U/s

Vri

ndav

an

Kes

i G

hat

Vri

ndav

an

D/s

Vri

ndav

an

U/s

Mat

hura

Vis

hra

m G

hat,

Mat

hura

D/s

Mat

hura

U/s

Kai

lash

ghat

, A

gra

U/s

Wate

rwo

rks,

Ag

ra

D/s

Taj

mah

al, A

gra

U/s

Fir

oza

bad

D/s

Fir

oza

bad

U/s

Eta

wah

D/s

Eta

wah

U/s

Wate

r In

take,

Pra

yag

raj

D/s

Bal

ua

Ghat

Pra

yag

raj

D/s

Chhac

hh

ar n

ala,

Pra

yag

raj

D/s

Em

erg

en

cy O

utf

all

, P

rayag

raj

Faecal

Coli

form

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Yamuna

Year 2019-2021 (Jan to July)

2019

2020

2021

47

7.88

2.97

7.69

3.19

8.21

4.51

0.00

2.00

4.00

6.00

8.00

10.00

Rameshwar, Varanasi Before Confluence with river Ganga

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Varuna Year 2019-2021 (Jan to July) 2019

2020

2021

3.23

22.22

3.25

12.26

3.20

10.9

0.00

5.00

10.00

15.00

20.00

25.00

Rameshwar, Varanasi Before Confluence with river Ganga

BO

D (

mg/L

)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River Varuna Year 2019-2021 (Jan to July) 2019

2020

2021

48

2683

167583

2717

79250

2729

50714

0

50000

100000

150000

200000

Rameshwar, Varanasi Before Confluence with river Ganga

Tota

l C

oli

form

(M

PN

/100 m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Varuna Year 2019-2021 (Jan to July) 2019

2020

2021

1433

99417

1300

50333

1386

31286

0

20000

40000

60000

80000

100000

120000

Rameshwar, Varanasi Before Confluence with river Ganga

Faecal C

oli

form

(M

PN

/100 m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Varuna Year 2019-2021 (Jan to July) 2019

2020

2021

49

7.2 7.2

7.4

7.5

7.20

7.50

7.0

7.1

7.2

7.3

7.4

7.5

7.6

U/s Badhalganj Turtipur, D/s Deoria

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River

Ghaghra Year 2019-2021 (Jan to July) 2019

2020

2021

5.0 5.04.5

3.8

5.1

4.2

0.0

1.0

2.0

3.0

4.0

5.0

6.0

U/s Badhalganj Turtipur, D/s Deoria

BO

D (

mg/L

)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in

River Ghaghra Year 2019-2021 (Jan to July)2019

2020

2021

50

20858 20333

41583

24667

48714

34000

0

10000

20000

30000

40000

50000

60000

U/s Badhalganj Turtipur, D/s DeoriaTota

l C

oli

form

(M

PN

/100 m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Ghaghra

Year 2019-2021 (Jan to July) 2019

2020

2021

10558 9775

22667

17833

33571

24429

0

5000

10000

15000

20000

25000

30000

35000

40000

U/s Badhalganj Turtipur, D/s Deoria

Faec

al C

oli

form

(M

PN

/100 m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Ghaghra

Year 2019-2021 (Jan to July) 2019

2020

2021

51

7.16.9

8.0

7.37.5

7.1

6.0

6.5

7.0

7.5

8.0

8.5

Domingarh, D/s Gorakhpur D/s, Rajghat, Gorakhpur

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Rapti Year

2019-2021 (Jan to July) 2019

2020

2021

5.05.7

4.0

5.5

4.1

5.6

0.0

1.0

2.0

3.0

4.0

5.0

6.0

Domingarh, D/s Gorakhpur D/s, Rajghat, Gorakhpur

BO

D (

mg/L

)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River

Rapti Year 2019-2021 (Jan to July) 2019

2020

2021

52

25167

35275

26750

45500

32857

53000

0

10000

20000

30000

40000

50000

60000

Domingarh, D/s Gorakhpur D/s, Rajghat, Gorakhpur

Tota

l C

oli

form

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Rapti Year 2019-

2021 (Jan to July) 2019

2020

2021

14225

2010017917

27583

19143

32571

0

5000

10000

15000

20000

25000

30000

35000

Domingarh, D/s Gorakhpur D/s, Rajghat, Gorakhpur

Faecal C

oli

form

(M

PN

/100m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Rapti Year 2019-

2021 (Jan to July) 2019

2020

2021

53

7.8

7.9

6.9

2.7

2.2

2.6 2.7

1.9

1.6

7.4

7.68.

8

8.0

7.3

4.6

3.7

3.3

3.0

2.5

2.0

7.2

7.48.

3

7.6

7

1.5

1.4

1.3 1.4

1 0.7

7.8

8

02468

10

Dad

hn

amau

Gh

at, S

itap

ur

Man

jhig

hat

,

Lu

ckno

w

Up

stre

am

Wat

er I

nta

ke,

Gau

gh

at,L

uck

n

ow

Ku

diy

ag

hat

,

Lu

ckno

w

D/s

Mo

han

Mea

kin

s,

Lu

ckno

w

Nis

hat

gan

j

Bri

dg

e,

Lu

ckno

w

U/s

Bair

aj,

Lu

ckno

w

D/s

Pip

rag

hat

,

Lu

ckno

w

D/s

Aft

er

mee

ting

of

ST

P, N

ala

Bharwara,…

D/s

Go

mti

,

Jau

np

ur

Go

mti

b

efore

mee

ting

to

Gan

ga,

Raj

war

i

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Gomti

Year 2019-2021 (Jan to July)2019

2020

20212.

6

2.7

3.2

9.9

10.7

9.8 10

.8

10.7

18

3.8

3.4

2.4

2.8 3.2 6.

2 7.3 8.7

9.4 10

.4 12.7

3.9

3.7

2.30

2.80

3.30

10.9

0

11.8

0

13.1

0

13.8

0

14.6

0

15.9

0

4.10

3.70

0

5

10

15

20

Dad

hnam

au

Ghat

, S

itap

ur

Man

jhig

hat

,

Luck

now

Upst

ream

Wat

er

Inta

ke,

Gau

ghat

,Luck

n

ow

Kudiy

aghat

,

Luck

now

D/s

Moh

an

Mea

kin

s,

Luck

now

Nis

hat

gan

j

Bri

dge,

Luck

now

U/s

Bai

raj,

Luck

now

D/s

Pip

ragh

at,

Lu

ckno

w

D/s

Aft

er

mee

ting o

f S

TP

,

Nal

a B

har

war

a,

Luck

now

D/s

Gom

ti,

Jaunpur

Gom

ti bef

ore

mee

ting t

o

Gan

ga,

Raj

war

i

BO

D (

mg

/L)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River Gomti

Year 2019-2021 (Jan to July)2019

2020

2021

54

Feacal Coliform not compiled in year 2019.

3572

7750

1952

5

4204

17

3905

83

42

29

17

4290

83

1957

50

1079

167

2091

7

1345

0

1812

4564

6945

5772

7

8281

8

1117

27

1456

36

19

72

73

3663

64

2081

8

1600

0

2343

4086

6986 11

3429

1384

29

1762

86

2157

14

2671

43

3557

14

2285

7

1571

4

0

200000

400000

600000

800000

1000000

1200000

Dad

hnam

au G

hat

,S

itap

ur

Man

jhig

hat

, L

uck

now

Upst

ream

Wat

er I

nta

ke,

Gau

ghat

,Luck

now

Kudiy

aghat

, L

uck

now

D/s

Mohan

Mea

kin

s,L

uck

now

Nis

hat

gan

j B

ridge,

Luck

now

U/s

Bai

raj, L

uck

now

D/s

Pip

raghat

, L

uck

now

D/s

Aft

er m

eeti

ng o

fS

TP

, N

ala

Bhar

war

a,L

uck

now

D/s

Gom

ti, Ja

unpur

Gom

ti bef

ore

mee

ting

to G

anga,

Raj

war

i

Tota

l C

oli

form

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Gomti

Year 2019-2021 (Jan to July)2019

2020

2021

875

2680

4564 35

364

4800

0

6845

5

8518

2

9863

6 1680

91

1127

3

8364

947

2643

4314

7057

1

80

00

0

1027

14

1185

71

1598

57

1957

14

1228

6

8286

0

50000

100000

150000

200000

250000

Dad

hn

amau

Ghat

, S

itap

ur

Man

jhig

hat

, L

uck

now

Up

stre

am W

ater

Inta

ke,

Gau

gh

at,L

uck

now

Ku

diy

aghat

, L

uck

now

D/s

Mo

han

Mea

kin

s,

Luck

now

Nis

hat

gan

j B

ridge,

Luck

now

U/s

Bai

raj,

Luck

now

D/s

Pip

rag

hat

, L

uck

no

w

D/s

Aft

er m

eeti

ng o

f S

TP

,

Nal

a B

har

war

a, L

uck

now

D/s

Gom

ti, Ja

unpur

Go

mti

b

efore

mee

ting t

o

Gan

ga,

Raj

war

i

Faecal

Co

lifo

rm

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Gomti

Year 2019-2021 (Jan to July)2019

2020

2021

55

0.0

0.0

1.6

1.25

1.0

0.0

0.0

0.0 0.0

1.1

1.6

1.1

0.1

0.0

0.0

0.0

0.0

1.7

1.4

0.0

0.0

0.00.20.40.60.81.01.21.41.61.8

Hin

do

n D

/S M

ahes

hpu

r

Sah

aran

pur

Hin

do

n, S

ard

han

a -

Bu

dh

ana

Ro

ad, V

ill

Bap

arsi

, M

eeru

t

Hin

do

n, M

eeru

t B

agh

pat

Ro

ad, M

eeru

t

Hin

do

n, k

arh

eda

vil

lag

e ,

Gh

azia

bad

Hin

do

n, ri

ver

Mo

han

nag

ar R

oad

Bri

dg

e,

Gh

azia

bad

Hin

do

n, ri

ver

Ch

ijar

si

Bri

dg

e, G

haz

iab

ad

Hin

do

n, D

/S K

uls

era

Bri

dg

e, N

oid

a

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Hindon

Year 2019-2021 (Jan to July) 2019

2020

2021

44.6

69

.9

42.3

21.3 29

.7

54.1

56.9

44.5 59

.5

42.0

17.

2

21.4 3

4.9

38.

3

43.0

0 63.1

45.7

19.

6

23.

4 41.2 52

.0

0.010.020.030.040.050.060.070.080.0

Hin

do

n D

/S M

ahes

hpur

Sah

aran

pur

Hin

do

n, S

ardhan

a -

Budh

ana

Ro

ad, V

ill

Bap

arsi

, M

eeru

t

Hin

do

n, M

eeru

t B

aghpat

Ro

ad, M

eeru

t

Hin

do

n, k

arhed

a vil

lage

,

Gh

azia

bad

Hin

do

n, ri

ver

Mohan

nag

ar R

oad

Bri

dge,

Ghaz

iabad

Hin

do

n, ri

ver

Chij

arsi

Bri

dg

e, G

haz

iabad

Hin

do

n,

D/S

Kuls

era

Bri

dg

e, N

oid

a

BO

D (

mg

/L)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River

Hindon Year 2019-2021 (Jan to July)2019

2020

2021

56

Zero (0) indicates Total & Feacal Coliform not reported from RO Saharanpur in respective years. *Feacal Coliform not compiled in year 2019.

0 1550

00

1288

33

18

41

83

4375

0

6108

33

2566

67

0.0 13

9167

1102

50

6209

09

5663

64 1283

636

9966

67

0.0 13

1429

1500

00

2285

71

2314

29

2211

429

1921

429

0500000

1000000150000020000002500000

Hin

do

n D

/S M

ahes

hpu

r

Sah

aran

pur

Hin

do

n, S

ard

han

a -

Bu

dh

ana

Ro

ad, V

ill

Bap

arsi

, M

eeru

t

Hin

do

n, M

eeru

t B

agh

pat

Road

, M

eeru

t

Hin

do

n, k

arh

eda

vil

lag

e ,

Gh

azia

bad

Hin

do

n, ri

ver

Mo

han

nag

ar

Road

Bri

dg

e, G

haz

iabad

Hin

do

n, ri

ver

Ch

ijar

si

Bri

dg

e, G

haz

iab

ad

Hin

do

n, D

/S K

uls

era

Bri

dg

e, N

oid

a

To

tal

Co

lifo

rm

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Hindon Year

2019-2021 (Jan to July)2019

2020

2021

0.0 96

20

0

8210

0 4809

09

2481

82 7527

27

6877

78

0 1007

14

1068

57

1628

57

1642

86

16

88

57

1

1345

714

0200000400000600000800000

10000001200000140000016000001800000

Hin

do

n D

/S

Mah

eshpur

Sah

aran

pur

Hin

don, S

ardhan

a -

Bu

dh

ana

Road

, V

ill

Bap

ars

i, M

eeru

t

Hin

don, M

eeru

t

Bag

hpat

Road

,

Mee

rut

Hin

don, kar

hed

a

vil

lag

e , G

haz

iabad

Hin

do

n, ri

ver

Mo

han

nag

ar R

oad

Bri

dge,

Ghaz

iabad

Hin

don, ri

ver

Ch

ijar

si B

ridge,

Ghaz

iabad

Hin

do

n, D

/S K

uls

era

Bri

dge,

Noid

a

Faecal

Co

lifo

rm

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Hindon Year

2019-2021 (Jan to July)2019

2020

2021

57

7.4

7.2

6.2

6.1 6.8

6.9

5.9 7.

7

7.1

7.3

6.7

6.5 7.1

7.2

6.5 7.

6

6.7

7.1

6.3

6.2 6.8

6.8

6.2 8

02468

10

Sai

riv

er,B

ani,

Un

nao

Sai

riv

er,S

irsa

gh

at,

Rai

bar

eli

Sai

riv

er,

Raj

gh

at,R

aib

ar

eli

Sai

riv

er,P

icn

ic

spo

t

Rai

bar

eli,

Sai

riv

er,G

aig

hat

Rai

bar

eli,

Pra

tapg

arh

Sai

riv

er,B

elam

ai

Gh

at,

Pra

tapg

arh

Sai

Nad

i,at

D/s

Str

eam

Pra

tapg

arh

,nea

r R

ail

way

Bri

dg

e

Sai

Nad

i,Ja

lalp

ur,

Jau

np

ur

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Sai Year 2019-

2021 (Jan to July) 2019

2020

20213.

2 4.2 4.

9

5.1

4.6

4.5 5.

1

3.5

3.4 4.

2 4.5

4.7

4.3

4.3 4.7

3.6

2.9

4.7 5.1

5.2

4.8

4.7 5.

2

3.6

0123456

Sai

riv

er,B

ani,

Unnao

Sai

riv

er,S

irsa

ghat

,

Rai

bar

eli

Sai

riv

er,

Raj

ghat

,Rai

bar

eli

Sai

riv

er,P

icnic

spot

Rai

bar

eli,

Sai

riv

er,G

aighat

Rai

bar

eli,

Pra

tap

gar

h

Sai

riv

er,B

elam

ai G

hat

,

Pra

tapgar

h

Sai

Nad

i,at

D/s

Str

eam

Pra

tapgar

h,n

ear

Rai

lway

Bri

dge

Sai

Nad

i,Ja

lalp

ur,

Jaunpur

BO

D (

mg

/L)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River Sai

Year 2019-2021 (Jan to July) 2019

2020

2021

58

Zero (0) indicates Feacal Coliform not reported from RO Raibareli in respective years. *Feacal Coliform not compiled in year 2019.

5190

6950

8075

8392

7767

7642

8675 12

700

78

64

5355

7118

7373

6455

6355

7500

1527

3

9286

6929 10

043

10

22

9

8143

7757 10

029

1285

7

0

5000

10000

15000

20000

Sai

riv

er,B

ani,

Un

nao

Sai

riv

er,S

irsa

gh

at,

Rai

bar

eli

Sai

riv

er,

Raj

gh

at,R

aib

ar

eli

Sai

riv

er,P

icn

ic

spo

t

Rai

bar

eli,

Sai

riv

er,G

aig

hat

Rai

bar

eli,

Pra

tapg

arh

Sai

riv

er,B

elam

ai

Gh

at,

Pra

tapg

arh

Sai

Nad

i,at

D/s

Str

eam

Pra

tapg

arh

,nea

r R

ail

way

Bri

dg

e

Sai

Nad

i,Ja

lalp

ur,

Jau

np

ur

Tota

l C

oli

form

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Sai

Year 2019-2021 (Jan to July) 2019

2020

2021

3655

0 0 0 0 0 0

7000

3743

0 0 0 0 0 0

6714

010002000300040005000600070008000

Sai

riv

er,B

ani,

Unnao

Sai

riv

er,S

irsa

ghat

, R

aibar

eli

Sai

riv

er, R

ajg

hat

,Rai

bar

eli

Sai

riv

er,P

icnic

spot

Rai

bar

eli,

Sai

riv

er,G

aighat

R

aibar

eli,

Pra

tapg

arh

Sai

riv

er,B

elam

ai G

hat

,

Pra

tapgarh

Sai

Nad

i,at

D/s

Str

eam

Pra

tapg

arh,n

ear

Rai

lway

Bri

dg

e

Sai

Nad

i,Ja

lalp

ur,

Jau

npur

Faecal C

oli

form

(M

PN

/100m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Sai

Year 2019-2021 (Jan to July)2019

2020

2021

59

0.0

0.0

0.0

0.0 0.2

0.2

2.6

2.5

5.0

7.6

0.0

0.0

0.0

0.0

0.0

0.0

3.9 4.1 5

.5

7.0

0.0

0.0

0.0

0.0

0.0

0.0

1.7

1.7

5.9 6

.9

0.01.02.03.04.05.06.07.08.0

D/s

M/s

New

Ban

anza

, p

aper

mil

ls v

ill.

, S

ain

i-

Maw

ana

Ro

ad,

Mee

rut

Gar

h R

oad

,

Mee

rut

Kh

ark

ho

da-

Pri

ksh

it G

arh

Road

, M

eeru

t

Bab

ug

arh

,

Gaz

iab

ad

U/s

Dev

ipu

ra,

Bu

lan

dsh

ahar

D/s

Mo

han

Ku

teer

,

Bu

lan

dsh

ahar

U/s

Kal

i ri

ver

bef

ore

wav

e

dis

till

ery

Ram

ghat

ro

ad,

Atr

auli

, A

lig

arh

D/s

Kal

i ri

ver

afte

r w

ave

dis

till

ery

Ram

ghat

ro

ad,

Atr

auli

, A

lig

arh

Nad

rai

Gat

e,

Kas

gan

j

U/s

Kan

nau

j

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Kali (East)

( Year 2019-2021 (Jan to July)2019

2020

2021

55.5

56

.4

57.8

44.9

71.0

73.

3

30.3

32.7

17.1

4.7

58

.3

58.6

54.

4

40.

2 61.0

62.5

13.

3

13.

9

11.0

4.6

51.

1

55.1

53.4

42.8 60

.6

61

.1

41.1

41.7

27.1

5.5

0.010.020.030.040.050.060.070.080.0

D/s

M/s

New

Ban

anza

, pap

er

mil

ls v

ill.

, S

ain

i- M

awan

a

Ro

ad, M

eeru

t

Gar

h R

oad

, M

eeru

t

Kh

ark

ho

da-

Pri

ksh

it G

arh

Road

, M

eeru

t

Bab

ug

arh

, G

azia

bad

U/s

Dev

ipu

ra, B

ula

ndsh

ahar

D/s

Mo

han

Ku

teer

,

Bu

lan

dsh

ahar

U/s

Kal

i ri

ver

bef

ore

wav

e

dis

till

ery

Ram

gh

at r

oad

,

Atr

auli

, A

lig

arh

D/s

Kal

i ri

ver

aft

er w

ave

dis

till

ery

Ram

gh

at r

oad

,

Atr

auli

, A

lig

arh

Nad

rai

Gat

e, K

asg

anj

U/s

Kan

nau

j

BO

D (

mg

/L)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River Kali (East)

Year 2019-2021 (Jan to July)2019

2020

2021

60

1110

83

1245

00

1483

33

4116

667

1825

00

5431

67

0 0 0 8792

8841

7

1250

83

1683

33

4690

909

1700

00

6700

0

0 0 0 1670

0

1128

57

1371

43

1557

14

3742

857

0 0.0

0.0 0.0

0.0 28

286

010000002000000300000040000005000000

D/s

M/s

New

Ban

anza

,

pap

er m

ills

vil

l. , S

ain

i-

Maw

ana

Ro

ad, M

eeru

t

Gar

h R

oad

, M

eeru

t

Kh

ark

ho

da-

Pri

ksh

it

Gar

h R

oad

, M

eeru

t

Bab

ug

arh

, G

azia

bad

U/s

Dev

ipu

ra,

Bu

lan

dsh

ahar

D/s

Mo

han

Ku

teer

,

Bu

lan

dsh

ahar

U/s

Kal

i ri

ver

bef

ore

wav

e d

isti

ller

y R

amgh

at

road

, A

trau

li,

Ali

gar

h

D/s

Kal

i ri

ver

aft

er w

ave

dis

till

ery

Ram

gh

at r

oad

,

Atr

auli

, A

lig

arh

Nad

rai

Gat

e, K

asg

anj

U/s

Kan

nau

j

To

tal

Co

lifo

rm

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Kali (East)

Year 2019-2021 (Jan to July)

2019

2020

202169

222

8811

1

1242

22

3536

364

1350

00

6050

0

0 0 0 6120

9371

4

1105

71

1228

57

2585

714

0 0.0

0.0

0.0

0.0

16

57

1

0500000

1000000150000020000002500000300000035000004000000

D/s

M/s

New

Ban

anza

,

pap

er m

ills

vil

l. , S

aini-

Maw

ana

Ro

ad, M

eeru

t

Gar

h R

oad

, M

eeru

t

Kh

ark

ho

da-

Pri

ksh

it G

arh

Road

, M

eeru

t

Bab

ug

arh

, G

azia

bad

U/s

Dev

ipu

ra, B

ula

ndsh

ahar

D/s

Mo

han

Kute

er,

Bu

lan

dsh

ahar

U/s

Kal

i ri

ver

bef

ore

wav

e

dis

till

ery

Ram

gh

at r

oad

,

Atr

auli

, A

lig

arh

D/s

Kal

i ri

ver

aft

er w

ave

dis

till

ery

Ram

gh

at r

oad

,

Atr

auli

, A

ligar

h

Nad

rai

Gat

e, K

asgan

j

U/s

Kan

nau

j

Faecal

Co

lifo

rm

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Kali (East)

Year 2019-2021 (Jan to July)2019

2020

2021

61

7.3

4.7 5.1

7.9

10

.1

9.0

8.3

5.1 6.

6 8.1 9

.5

8.6

8.5

4.2 5.0

7.8 9

.4

9.1

0.02.04.06.08.0

10.012.0

U/s

Ram

gan

ga

nea

r A

gw

anpur,

Dis

tt.

Mora

dab

ad

Mora

dab

adR

ampur

road

bri

dge,

Mora

dab

ad

D/s

Ram

gan

ga,

Shah

abad

Ram

pur

U/s

Ram

gan

ga

Kap

urp

ur

vil

lage,

Mee

rgan

j, b

arei

lly

D/s

Ram

gan

ga

FB

D r

oad

bri

dge

Shah

jahap

ur

Ram

gan

ga

atK

annau

j

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Ramganga

( Year 2019-2021 (Jan to July) 2019

2020

20211.

8

11.

1

7.6

3.2

3.0

4.6

2.5

8.6

6.2

3.4

2.8 4.

0

1.9

8.4

7.2

3.0 3.0 4.

1

0.0

2.0

4.0

6.0

8.0

10.0

12.0

U/s

Ram

gan

ga

nea

rA

gw

anpur,

Dis

tt.

Mora

dab

ad

Mora

dab

ad R

ampur

road

bri

dge,

Mora

dab

ad

D/s

Ram

gan

ga,

Shah

abad

Ram

pur

U/s

Ram

gan

ga

Kap

urp

ur

vil

lage,

Mee

rgan

j, b

arei

lly

D/s

Ram

gan

ga

FB

Dro

ad b

ridg

eS

hah

jahap

ur

Ram

gan

ga

at K

annau

j

BO

D (

mg/L

)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River

Ramganga Year 2019-2021 (Jan to July)2019

2020

2021

62

Zero (0) indicates Feacal Coliform not reported from RO Moradabad & Bareilly in respective years. *Feacal Coliform not compiled in year 2019.

1616

7

5583

33

4308

33

1908

3

1450

0

1477

5

1842

3583

3

4241

7

1358

3

1316

7

1432

5

1014

2742

9

3157

1

1314

3

1228

6

17

62

9

0100000200000300000400000500000600000

U/s

Ram

gan

ga

nea

rA

gw

anpur,

Dis

tt. M

ora

dab

ad

Mora

dab

ad R

ampur

road

bri

dge,

Mora

dab

ad

D/s

Ram

gan

ga,

Shah

abad

Ram

pur

U/s

Ram

gan

ga

Kap

urp

ur

vil

lage,

Mee

rgan

j, b

arei

lly

D/s

Ram

gan

ga

FB

D r

oad

bri

dge

Shah

jahap

ur

Ram

gan

ga

at K

annau

j

Tota

l C

oli

form

(M

PN

/10

0m

L

Sampling Stations

Graphical Representation of Total Coliform in River RamgangaYear

2019-2021 (Jan to July)2019

2020

2021

0 0 0 0 0

8367

0 0 0 0 0

9829

02000400060008000

1000012000

U/s

Ram

gan

ga

nea

rA

gw

anpur,

Dis

tt.

Mora

dab

ad

Mo

radab

adR

ampur

road

bri

dge,

Mora

dab

ad

D/s

Ram

gan

ga,

Shah

abad

Ram

pur

U/s

Ram

gan

ga

Kap

urp

ur

vil

lage,

Mee

rgan

j, b

arei

lly

D/s

Ram

gan

ga

FB

D r

oad

bri

dge

Shah

jahap

ur

Ram

gan

ga

atK

annau

j

Fa

ecal C

oli

form

(M

PN

/100m

L

Sampling Stations

Graphical Representation of Faecal Coliform in River Ramganga

Year 2019-2021 (Jan to July)2019

2020

2021

63

9.7

6

9.90

9.7

1

9.60

9.65

9.70

9.75

9.80

9.85

9.90

9.95

Saryu at Ayodhya

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Saryu

Year 2019-2021 (Jan to July)2019

2020

2021

3.0

2

2.9

3

3.27

2.70

2.80

2.90

3.00

3.10

3.20

3.30

Saryu at Ayodhya

BO

D (

mg/L

)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River Saryu

Year 2019-2021 (Jan to July)2019

2020

2021

64

Feacal Coliform not compiled in year 2019.

6050

2790

2943

0

1000

2000

3000

4000

5000

6000

7000

Saryu at Ayodhya

To

tal

Co

lifo

rm

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Saryu

Year 2019-2021 (Jan to July)2019

2020

2021

1810

1471

0

500

1000

1500

2000

Saryu at Ayodhya

Faecal

Co

lifo

rm

(M

PN

/10

0m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Saryu Year

2019-2021 (Jan to July) 2019

2020

2021

65

Data for the year 2021 not available for compilation.

6.5

7

6.9

3

0.001.002.003.004.005.006.007.008.00

Betwa at Hamirpur, Banda

DO

(m

g/L

)

Sampling Stations

Graphical Representation of Dissolved Oxygen in River Betwa

Year 2019-2021 (Jan to July) 2019

2020

2021

5.5

8

5.1

8

0.00

1.00

2.003.00

4.00

5.006.00

Betwa at Hamirpur, Banda

BO

D (

mg/L

)

Sampling Stations

Graphical Representation of Biochemical Oxygen Demand in River

Betwa Year 2019-2021 (Jan to July) 2019

2020

2021

66

Data for the year 2021 not available for compilation. * Feacal Coliform not compiled in year 2019.

1466

7

1600

0

02000400060008000

1000012000140001600018000

Betwa at Hamirpur, Banda

Tota

l C

oli

form

(M

PN

/100m

L)

Sampling Stations

Graphical Representation of Total Coliform in River Betwa

Year 2019-2021 (Jan to July) 2019

2020

2021

1644

0

500

1000

1500

2000

Betwa at Hamirpur, Banda

Faec

al C

oli

form

(M

PN

/100m

L)

Sampling Stations

Graphical Representation of Faecal Coliform in River Betwa

Year 2019-2021 (Jan to July) 2019

2020

2021

67