#QuPlan - A Quantum of Planning - Episode 2015/0 - Business Case and Product Comparison
-
Upload
roberto-lofaro -
Category
Documents
-
view
215 -
download
1
description
Transcript of #QuPlan - A Quantum of Planning - Episode 2015/0 - Business Case and Product Comparison
UPDATE 2015-07-03
#QuPlan
#QuPlan discusses the current status of planning and project
management, and then builds up on “unconnected” dots to
derive a potential evolution of planning concepts
#QuPlan is part of the “Connecting the dots” series, short
pragmatic books (generally, up to 60 pages), based on
experience and aiming to inspire re-thinking your business ways
#QuPlan Episodes
Expanding on the #QuPlan book, this (free. online) series of
booklets (“episodes”) is a walkthrough within the lifecycle of a
fictional business case concerning a regulatory programme
This first “episode” shows the initial decision points, i.e. an
outline of the overall programme, key fact-finding, and the
choice of methodology, tools, key staff selection guidelines
See the back cover for the full list of the planned 2015 episodes
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
INTRODUCTION
I designed a realistic but not real case, focused on compliance to fictional new
legal requirements- and the table above lists some key elements of the corporate
culture.
The business case covered by the #QuPlan episodes was created to exemplify
typical issues that are part and parcel of any initiative involving change- with and
without technology.
This business case will be used in 2015 to support other books, and in this first
episode both the methodology and business case will contain introductory
material..
•any issue that is known can be managed as a risk
•any risk has to be managed to lower its impact
•no “pushing downstream”
Transparency
•awareness independent from a hierarchical mandate
•those who know by being on the frontline, notify issues
•aggregate their notifications and potential solutions
Emergence
•No tolerance for "corporate whodunnit"
•teamwork has to be routinely multidisciplinary No Whodunnit
•Consistent and continuous thesaurisation of lessons learned, and availability of tools to support that
Thesaurisation
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
Any regulation requiring to alter processes and organizational structures usually
implies also impacts on existing IT systems, but almost never legislators and
regulators have “in house” the knowledge required to assess business impacts, and
therefore generally there is a chance (few months, few years) to submit comments,
suggestions, etc.- before the final version is promulgated.
Stated aim of the fictional law: ensure that those interacting with consumers have
the knowledge and skills required to comply with current regulations, by extending
the approach already used e.g. to recover discarded electronics- it is suppliers’
duty..
The selection of a case about compliance allows to skip over some of the most
critical/”political” activities: if it is required by law, often a “quick and dirty”
approach is followed to minimize costs while ensuring compliance- what matters, is
identifying an appropriate balance between risks and costs.
In various cases, I saw that emerging programmes based on compliance were
used as an excuse to overcome resistance to change, expanding the scope of the
activities to cover what had been needed for a while, but kept on the back burner
while waiting for the appropriate combination of tools, motivation, and
opportunity.
Yes, if you do not attach to your “charter” a clear definition of the aims, purposes,
and rules to be followed, lessons learning turns into a CSI investigation.
Obviously, it is a risky choice, as once you start expanding the scope, often it keeps
expanding- with a “bandwagon effect”: with each expansion, it becomes more
difficult to deny further expansions.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
A SAMPLE/SIMPLE METHOD
This first episode is called episode zero, and outlines the rationale of the business
case, adopting a “storytelling approach” that I used decades ago in business to
have employees of a banking customer learn a new methodology and approach
to project management.
The programme roadmap is based on the concepts and lingo of MSP (basically,
the programme management side of PRINCE2), by OGC.
As any “designed” case, this too needs to be adapted to your own specific
business constraints.
The purpose of this business case is to share information about how activities could
evolve, as an excuse to discuss various elements and potential evolutions of
programme and project management discipline outlined within the book #QuPlan.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
As you can see from the map within the previous page, the contents of this
booklet cover the first phase, the definition of the mandate for the activities, i.e.
this first episode focuses on just part of the “Define” step.
Obviously, there are countless ways to deliver a project, and therefore I identified
one that covers the general steps shared by most methodologies (in some cases,
re-iterating more than one step).
Whatever the methodology that your organization selected, it is anyway advisable,
before starting any project or initiative, a review with the “guardians of orthodoxy”
(methodology, quality, etc.) to cross-check what is applicable, in terms of rules,
standards, and tools- both to avoid re-inventing the wheel, recycle what might
now be obsolete or non-compliant with current rules, or risk getting on board rules
“suggested” by suppliers (e.g. software packages and service vendors usually
implicitly follow their own rules, to optimize the use of their own resources).
This “episode” includes a quick review of the options available in terms of toolsets
to be used to support programme/project management, to enable tracking the
allocation and use of resources while delivering what has been agreed as the
stated aim(s) of your initiative, but without excessive overhead.
obviously, in a real environment usually the tools have already been chosen, but in
this case the tools that have been identified are those represented within the map
shown in the next page.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
TOOLS SCENARIOS
•Using just Office productivity tools
•Files stored on a network or directory structure
Office productivity
•Microsoft Project and Microsoft Sharepoint
•Integration with Office productivity tools Standard
•Potentially multiple vendors involved
•Need to work through a stricter «stage-based» approach
Workflow
•Either off-the-shelf or custom, but access and integration via Internet (including WAN Intranet or Extranet)
•Chosen an open source solution that I used to support start-ups
Online platform
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
Each tool has different strengths and weaknesses, but all share a common
element, the ubiquitous Gantt chart, representing the mutual dependencies and
sequence of activities; you can use the tools both at the project, subproject, or
programme level.
There are further shared elements, e.g. features to list people (“resources”) and
financial resources or costs, but for the purposes of this product comparison, as
those features are shared; whatever combination of tools you will choose, you will
need to be able to do at least the following:
Whatever tool you use, you need to consider that no organized activity can
survive without a communication plan that is prepared before the activity starts-
and this requires thinking about the audience(s) that you want to reach (a.k.a.
"stakeholder(s)").
pro
ject
man
agem
ent
kno
wle
dge
bas
e
to collect preliminary data, refine guesstimates, produce a “baseline”
to associate costs + people to activities, and track their allocation
to have instantaneous access to the current status of ongoing activities
to have a copy of each relevant document (minutes, timesheets, etc.)
to associate each document with the source/destination activities
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
AUDIENCE OVERLOAD
Information level Complexity level
I have been using Microsoft Project and general-purpose project management
tools for decades, and I still consider that most of the “standard” reports that they
produce are simply useless for both project managers and stakeholders.
This diagram presents the “complexity level” in information sharing, stating how
“knowledge-intensive” is the understanding of a chart, ranging from “intuitive” (if
you see a sequence of bars across a timeline, you know what they mean), to
“logic” (you need to at least grasp the concept behind the formalism), to
“quantitative” (you need to understand how the representation is created tomake
sense out of it).
Gantt
CPM
PERT
Intuitive
Logic
Quantitative
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
Both the project manager and stakeholders focused on few bits of information,
information that was actually partially misleading, , converting tools such as
Microsoft Project into a kind of “Excel less the formulas plus the Gantt”.
If Gantt, CPM, PERT are meaningless “alphabet soup samples” to you, have a
quick look on Wikipedia (or wait for the “Thinking” section)- basically, they are
three ways to represent how activities are delivered across time.
The first is a century old tool, derived from the manufacturing planning needs of
the early XX century, while the other two are roughly side-effects of the more
complex manufacturing needs of the early Cold War (e.g. building nuclear
submarines and power stations).
Tool designers, assuming that there were other “standard reports” on risks and
impacts, simply removed from the basic reports information on the confidence
level of the information provided.
It makes more sense to identify, within your guidelines for project managers, which
reports are required, and few lines about each one of the “standard reports”
available, to explain the who/what/when of their production.
A further element to consider is how and when to spread information: while for a
simple project or programme it might make sense to release information once in a
while, in some cases a continuous information stream is required.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
COMMUNICATING
Whenever stakeholders are both spectators and actors, i.e. when they are not just
a passive audience, communication implies something more than just sending out
files..
In the past (e.g. 1980s and 1990s), this required investing in tools or custom
applications, but in 2015 any company uses a form of spreadsheet that is able to
present data using what, until few years ago, would have required an investment
in business intelligence or dashboard presentation tools.
Since the late 1980s, I saw complex systems delivering DSS, EIS, management
reporting, dashboards, business intelligence, data warehousing, and an assorted
software paraphernalia that seems to be constantly mutating every couple of
years.
The risk with IT is always that the tool takes control- notably when, due to the
number of options available, instead of delegating just the execution, also design
is delegated to somebody who has no understanding of the business processes
and business people involved (typically, an intern or temp worker, no matter how
experienced).
In most cases, the anxiety from those that were assigned to the use of the tool took
over the purpose (quick but consistent and continuous information dissemination
to decision-makers or stakeholders), creating either system too simple and static
(for fear of misuse by the end users) or too complex (to “empower” them) for any
real use.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
Within this business case, there will be no sharing of minutes, reports, presentations,
project planning files, templates, etc. relating to this phase, as the release of files
(e.g. Gantt, presentations) is scheduled to be part of the last “episode”, on
thesaurisation, where the theory and practice of “knowledge retention” will be
explained.
I assume that you can find templates online, if needed (links provided under the
last part of this chapter, if you need immediately templates etc.).
It is worth anyway repeating: if you belong to a large organization, probably there
is a 'modus operandi' in communication that you have to follow.
It is something that often consultants forget- customers should remind them that
they are paid to fulfil a corporate need, not to promote their own methods or
standards.
There is another not so small issue: most project and programme teams often
forget that those that their stakeholders probably are on the receiving end of
plenty of communications.
What matters is consistency in communicating relevant information and timely
collection and management of feed-back.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
ENGAGEMENT TOOL
Does this sound familiar? To me, it does- since the late 1980s! Also when everybody
is using a smartphone, there are still endless technologies that are dumped on
users’ computers, as if information dissemination ended once the information is out
of your door.
Manager A needed to communicate continuously progress on activities (business, service, project) to Manager B
The staff member for Manager A eventually “evolved” the tool, and it became “too informative” (a.k.a. hair-splitting)
So, Manager B delegated to one of her/his staff members the task to routinely verify completeness of the information provided, and summarize what (s)he saw
Result: those who less understood what was involved became the communication channel, and the tool eventually expanded to add more information that to them seemed useful, further distancing their own managers from even daring to approach and use the tool- so that Manager B, in effect, turned to a “seat of the pants” decision-making approach
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
In most cases, this can be easily solved: streamline- both the information collecting
and processing tasks, and the presentation tool; if a tool delivers 100 features, and
you need just 3, once you have the tool in house, why should you feel compelled
to use the other 97?
In other cases, a “re-education plan” is needed, as deciding which information is
relevant to decision-making should be up to the decision-makers, not their number
crunchers (and I designed once a system that, while using just a handful of data
already available, was able to show progression and send shockwaves on specific
issues, without any need to create a “number crunching bureaucracy”).
Many larger organizations have in house a business intelligence tool, or just the
humble-yet-powerful “Excel Power Pivot”: an appropriate mix of data collection
and streamlined “dashboard” design can turn both into tools able to provide
much need information about a portfolio of projects or services.
The key issue is to have data reach (and be “consumed”) by those who really
know them: a PMO that provides just reporting and no organizational
development support is not always needed, if you have already a management
reporting function available.
In future “episodes” (2015/1 and 2015/2) a different approach to reporting on
project/programme management will be discussed.
The last section of this chapter contains some guidelines on documentation
lifecycle management.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
DOCUMENTATION
If your organization lacks formal standards, you may have a look at samples
published online, e.g. those provided, free-of-charge, by PRINCE2 1 ; it is also
advisable, before using those documents, to read some guidelines (both
documents require a free registration on Axelos, the company now managing
OGC’s methodology frameworks).
Phase 0: Definition It is advisable to attach to the “charter” the guidelines for
documentation production and delivery, including who/what/when/how, and any
“license to deviate from recognized corporate standards” (e.g. for shorter projects).
Phase 1: Ongoing Generally, documents are to be produced as soon as the
information is available, e.g. minutes of a meeting should be composed/drafted at
the end of the meeting, and shared as soon as possible- and anyway before the
next meeting involving the same people (as meetings should show progression, not
just that you had a schedule with X meetings each week!).
Phase 2: Thesaurisation Every project eventually ends- and this includes also
projects that are cancelled mid-way, or just scrapped before they even start (yes,
it happens, sometimes- and some lucky ones get even paid for work not done).
Unfortunately, once the adrenaline rush usually associated with the delivery of the
last leg of a project is gone, the first thing to disappear is the motivation to review
what was done.
1 https://www.axelos.com/best-practice-solutions/prince2
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
Your documentation should include both positives and negatives choices- as this
could be useful to avoid in the future to get through the same decision-making
routine, just with different people (with the potential that they will not understand
the logic of your choices).
Sharing both sides of each decision, along with the rationale, is useful also to help
keep whatever your activities deliver to adapt to changed business needs.
What was relevant when you made those choices might not be relevant anymore.
Thesaurisation is an activity whose usefulness rests on few basic elements:
1. Knowledge-based: it has to involve those who know (and not just the cheapest
ones available or those who cannot refuse to do it)
2. Timely: it has to be done immediately after the end of the project (actually, it
starts while the project is still ongoing)
3. Talking straight: it has to be done while avoiding any “politically correct”
scribbling (you have to say how it is/was)
4. Accessible: last but not least, it must deliver something that is then accessible
to others that might use it (e.g. by adding an “executive summary” or
“documentation roadmap” for future uses).
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
EXECUTIVE SUMMARY/1
A recent change in a national law [reference] extending on a European Directive
for consumer protection [reference] introduced, with just one line within the law,
the need for the creation of a new information service.
The stated aim is to ensure that agents and distributors of our products and
services are always compliant with regulations that could potentially affect their
business operations, and how they interact with customers obtaining our products
and services through them.
The costs for both the activation and delivery of the service have to be absorbed
by our company (the law currently doesn’t allow billing for the service).
It has been a trend since the 1990s: convert suppliers upstream into de facto
watchdogs on compliance (e.g. on recycling equipment sold to consumers),
extending responsibility across the product or service lifecycle.
The new law includes an automatic draconian measure for non-compliant
suppliers that repeatedly fail to deliver: any existing warranty on any product or
service delivered to consumers is extended automatically by a further 24 months.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
A new form of customer service is to become compulsory
Our legal department is exploring the possibility of challenging all the new
requirements at the EU level, as they seem to be disproportionate to the end,
notably when our agents and distributors are non-exclusive.
Considering all these constraints, it has been decided to adopt an approach that
will allow formal compliance at a minimum cost, but, should the new law be
confirmed, enable to expand the service, e.g. to convert the new requirements
into a business opportunity, by increasing the loyalty of both customers and agents
or distributors, as well as providing information useful to reduce the time-to-market
and risks associated with new products and services.
The first assessment on the impacts of the initiatives and how to cope with the
above mentioned constraints and decisions resulted in a list of 18 projects
[reference], involving all the business and support units, not just ICT and HR.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
EXECUTIVE SUMMARY/2
Organizational structure and staffing of the initiative
Due to the limited time available, it has been identified as critical the creation of
multiple small teams, each one led by a “subject matter expert” from our existing
operational staff (generally available only part-time, to steer more than manage
each project).
In order to ensure knowledge transfer and smooth delivery of each project, only
internal or external resources that are currently working or worked with our
organization within the last 24 months will be considered.
Furthermore, for some of the projects, it has been identified the potential full-time
use as consultants of recently retired line managers who are still occasionally used
as subject matter experts on organizational, process, and technological changes.
Mr. John Smith has been appointed as the Programme Manager, while Mr. Harold
Wilson from HR and Mr. Andrew Jackson from Finance will be members of the
steering team, under the coordination of Mr. George Patton, the COO, who will be
the programme budget owner.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
The timeframe allowed is limited, as the new information service must be fully
operational by January 1st 2016; the deadline for delivery is set at November 1st
2015, to allow monitoring for a couple of months before the deadline.
[In this section a description of the timeline and potential risks/stakeholders would
be discussed, along with budgeting guidelines; in this specific case, usually the
allocation will be focused only on the feasibility study, that will have the mandate
to identify the scenarios and cost options, to enable a further decision]
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
REQUIREMENTS
The only choice that has already been made (by law) is that we have to deliver
the following access channels, each one associated with a different timeframe:
The new regulation requires that, by year end, we deliver a single access point to
all our distributors, agents, dealers, providing information on changes within
regulations that could affect any part of their operations concerning customers,
including but not limited to sales, service, and withdrawal from market of our
products.
The next page contains a small table listing the projects identified, along with a
short rationale for each one; due to their size, they are named “subprojects”,
allowing the use of the streamlined version of our internal methodology.
Pull on-demand information
Push flash alerts
Updates periodic releases
Training periodic updates
Feed-back collection &
dissemination
Statistical return feed-back to
authorities
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
1 identify feasibility fact-finding and constraints identification
2a define service
requirements
identify stakeholder needs and SLA/OLA guidelines
2b define service location assess options for location and delivery mode
3a design service design service as per ITIL approach
3b design communication
and pre-emptive marketing
define, design, roadmap communication strategy and
actions/events/media
4a1 prepare service create service components according to prioritization
4a2 prepare service
environment
service delivery logistics and environment definition and
monitoring environment
4b test service with pilot
customer
rolling out the service in customer environment
4c train staff for initial svc train staff for initial service based upon the pilot
4d pre-emptive marketing activate communication elements associated with the pilot
progress
5a coach on-the-job initial
staff
use the pilot results to tune training and coach staff while
carrying out initial delivery
5b monitor at customer site monitoring to both tune and collect progress information
5c marketing campaign
and lead generation
activate communication elements associated with the end
of the pilot phase and lead generation
6 tune service continue tuning the service through the coach on-the-job
phase
7a retrain staff retrain staff based on the results of the tuning phase, and
feed-back from the marketing/lead generation activities
7b acquire further staff acquire new staff while retraining existing one, for scheduled
service roll-out capability readiness
8 transition to Business As
Usual
release project staff (service definition), and structured
knowledge transfer to ensure continuity
9 closing down programme
and thesaurisation
complete knowledge transfer, and assess lessons learned
and potential issues to monitor- plan KPI phase-in/phase-out
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
CONSTRAINTS
In the previous page, projects surrounded by the blue rectangle are actually
those that could be re-iterated (e.g. if, after the feasibility study, it is identified that
is possible to activate the service gradually and still be compliant).
The target identified during the preliminary assessment is compliance while
minimizing costs, and obviously the projects aren’t necessarily to be carried out as
a sequence, albeit there are some constraints.
Generally, considering the short timescale, this has an impact on the kind of
people that can be assigned to each project.
This obviously dictates for the selection of small teams, each led by a project
manager who de facto acts as “subject matter expert”, and, as such, not
necessarily allocated full-time; team members will be more experienced than in
most of our projects, and external resources will be allowed only if they have
current expertise on our environment.
This programme is to be delivered within a short timeframe, starting by early March
2015 and ending by late October 2015, with a two months “post-release”
monitoring period, in order to ensure that full formal compliance is in place by
January 1st 2016.
The direct impact of this choice is that roughly 1/2 of the time allocated to the
feasibility will be spent on brainstorming sessions
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
Considering the number of concurrent projects and activities that have been
initially identified, a first feasibility subproject lasting one month is to:
1. Define the overall architecture of the solution, and confirm concurrency
constraints between projects
2. Outline the SLAs/OLAs to be expected, as well as the specific roles and any
further information supplier that should be contacted
3. Activate the initial staffing for the activities
4. Activate the monitoring and reporting system to be used during the
programme
5. Validate the availability and structure of the environment, and/or procure
new equipment and offices if needed
6. Initiate the contract negotiations, be active by the start of the trial phase (i.e.
completed by the end of subproject 3a)
7. Procure the commitment of the appropriate staff and subject matter experts
that are to take on the roles of project manager for each project.
The results of this first feasibility activity have then to be structured within the
subproject 2a, while subproject 2b has to focus on the logistics of service delivery.
The subprojects from 3a on can potentially be repeated in the future to scale up
(expand) or scale down (reduce) the service.
A detailed schedule for the first subproject is provided in the next four pages.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
PRJ1: IDENTIFY FEASIBILITY/1
IDENTIFY key requirements to be fulfilled
ASSOCIATE stakeholders, and roles to be assigned
OUTLINE scenarios
COMPARE analysis of scenarios
DECISION on the scenario to be adopted
ANALYSE of the scenario selected, and schedule
BUDGET proposal to be submitted
DECISION on budget and resources
PREPARE resource guidelines and allocation
COMMUNICATE the roadmap to all the stakeholders
During the initial workshop has been identified as critical to devise an approach
that would keep involved, motivated, and informed all the stakeholders (internal
and external) that will be affected by the new compliance requirements, while, at
the same time, keeping at least informed those not directly affected.
Our distribution network will need to be actively involved up to January 1st 2016,
and therefore the assessment phase will have to discuss potential business benefits
not only for our organization, but also our distribution network.
The preliminary assessment that produced this document was carried out through
meetings held in one week-end-long workshop off the premises, involving the
managers in charge of the business units whose operations have been assumed to
be affected.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
A detailed list of the material presented by each participant, minutes of the
workshop, and decisions made (positive and negative) is provided within [add
reference].
The identification was based upon an analysis of our value chain, selecting a
“champion” for each phase, as per [insert here reference to organizational design
presentation provided by the Organizational Development office], with a direct
coordination by the COO, as per mandate from the CEO.
[add other relevant summary of key issues identified as constraints by the above
mentioned workshop].
18 projects (i.e. activities that could actually be delivered by separate teams)
have been identified, working across multiple business domains and business units,
therefore during the workshop was agreed that the above mentioned constraints
should be further analysed by a feasibility study. that should provide the results
outlined in the previous page.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
PRJ1: IDENTIFY FEASIBILITY/2
Start Activity/Activities Results
20
15
-03
-03
Ass
ess
me
nt
Confirmation of legal requirements
Confirmation of business requirements
Validation of internal constraints
Validation of constraints within our
distribution network (e.g. lack of
Internet or other relevant facilities)
Brainstorming sessions by type of
network membership, with
identification of a “network
representative” to be involved later
on as “programme evangelist”
Brainstorming session with all the
“programme evangelists” and the
assessment team
Summary of the activity
Standards adopted
and communication
plan drafted
Kickstarting and limited
communication done
Scope defined
Target defined
Approach defined
Roles/Activities defined
Milestones defined
20
15
-03-1
6
Sc
en
ario
s
Brainstorming with the Management
Team and approval or changes, with
scenario identification and preliminary
risk/budget assessment (SWOT)
Scenarios analysis
Scenarios comparison
Mapped current vs
target operating model
Assessed delta by BU
SWOT by scenario
Budget by scenario
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
20
15
-03
-23
Ro
ad
ma
p
Brainstorming with the Management
Team to select the scenario to further
investigate and turn into a roadmap
Roadmap definition
Brainstorming on the roadmap and
approval of the plan
Scenario selected
Roadmap defined
Communication plan
defined
Key roles assigned
Resources by phase
and activity mapped
Constraints and
delivery scheduled
Stakeholders and
communication
mapped
The feasibility study will be carried out in three phases (highlighted the key decision
points), and the next pages
[would contain the following information:
1. the rationale and content of each result
2. the key roles already identified
3. preliminary list of the stakeholders to be involved, by level of involvement
4. preliminary estimate of the activities to be carried out, with details for the
feasibility study, and milestones for the ensuing projects
In this business case, the next few pages contain examples on the adoption of
each one of the tools scenarios discussed within the “Method” chapter]
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
APPENDIX: TOOLS/1
Option 1: Office Automation
I assume that the audience of this book is from a business environment, and
therefore Microsoft Office is available (at least Word, Excel, Powerpoint).
If that is not the case, OpenOffice can be used, as it is a free OpenSource
alternative that includes also components covering the role of Access, with
Powerpoint replaced by two applications: a drawing application that includes a
limited version of the “smart drawings”, and a pure presentation application.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
The Gantt chart that you can see on the left is simply done by inserting as many
columns as you have weeks, and then applying a background; if your spreadsheet
software allows it (e.g. Excel), you can also use “conditional formatting”, so that
whenever a “1” is present, it turns into blue, allowing then to add a column with the
total by row that automatically tells you how many weeks (or days, or months) a
task is long, alter the plan, or add a further row to show what really happened.
Obviously, it is quite primitive, but it can be updated quickly, and, being based on
numeric values, you can add charts (e.g. to compare a “baseline” with actual
results), and use it to monitor the evolution of your resource allocation.
Anyway, if you need a proper Gantt, but do not want to use a specialized tool for
Gantt charts, probably you can find online an “add-on” for your spreadsheet
software that allows to create both a calendar and a Gantt.
From Microsoft Office 2010 on, you can also use “smart drawings” to create the
typical value chain chart, or even a network chart, built just by entering something
as simple as a bullet list with subdivisions.
The concept? The tool allows you to choose a “visual formatting” with a broad list
of options (in most cases, removing the need to acquire a license of Microsoft Visio,
as in my experience 90% of its uses are covered by “smart drawings” in both Office
2010 and 2013).
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
APPENDIX: TOOLS/2
Option 2: Corporate Standard
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
Each tool has different strengths and weaknesses, but all share a common
element, the ubiquitous Gantt chart.
Over the years, Microsoft Project added more features- so, you can actually use
Microsoft Project (and its server counterpart) to manage also the “bean counting”
side of project/programme/portfolio management, including by sharing at the
company level a pool of resources, and managing a “skills booking system”.
Frankly, most companies use Microsoft Project just for Gantt charts and little more-
including those that have the server part and Sharepoint (and sometimes add
Clarity too).
The main weaknesses of Microsoft Project (it isn’t workflow-based, and therefore
supporting “stage-based” project management approaches can be a nightmare,
and doesn’t manage a document repository) are overcome if you, with or without
the server part of Project, use also Sharepoint and its “workflow management”
abilities.
The main drawback of a “full Monty” solution involving Project, Project Server,
Sharepoint? You need deep pockets to buy the licenses, and deeper pockets to
create an integrated solution that runs smoothly and is able to withstand the
attempts of users to bypass controls or be “creative number crunchers”.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
APPENDIX: TOOLS/3
Option 3: Workflow-based
Actually, ProjectInABox is a tool composed of two tools, a planner (and risk
tracking) tool, and a workflow-based document management tool (available also
as an integrated, corporate-wide messaging and document repository).
If your company has a methodology, you might appreciate few characteristics: it
comes with a set of pre-defined methodologies; if you buy the lowest priced
version upgrade you can modify existing ones or create new ones; and it is a
scalable solution (both in terms of features, integration on a team or corporate
scale, and methodology add-ons).
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
I used it only for one reason: I was looking for a project management tool that
supported the programme management counterpart of PRINCE2, MSP, and this
was the only tool available.
Then, while I dislike some issues within the “planner” component, I like the ability to
see planning not just in term of human resources, costs, or time, but also of risks
(including by quantifying impacts).
Actually, in some cases I would skip using the planner to produce the Gantt, and
focus instead of mapping out and costing risks and their impacts (a boring task, if
you do it in Excel).
At the same time, if you do not have an internal methodology, the “support of
methodologies” I referred to is something more than just providing stages:
ProjectInABox contains, for each methodology, a graphical workflow, support
documentation (e.g. for Agile on DSDM, for MSP, and for PRINCE2 or ITIL), and
templates for each phase, so that it can be used also as a learning platform to
ensure consistency and self-learning across any organization whose
project/activity managers have a high turnover rate.
The Community Edition of ProjectInABox is free (you just need to register), and
works under Windows.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
APPENDIX: TOOLS/4
Option 4: Web-based
Over the last decade, another category of project management tools gained
traction: software tools based exclusively on the Web (or SaaS/PaaS, in “business IT
lingo”).
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
I used a few in the past, and even recently I resumed trying one, but for this
comparative test I selected an OpenSource option that I used a decade ago to
manage a concurrent pipeline of start-up projects (basically, from lead
qualification to business&marketing planning and management coaching).
dotProject is still available online (it requires a server with a database such as
MySQL, plus PHP), and can be easily modified and extended.
Nonetheless, it showcases features that should be available in any Web-based
project management tool, ranging from the possibility of integration with business
processes (e.g. invoicing, HR, email), to an internal messaging system, to
document warehousing by task/project/etc., to a feature that I used extensively in
the past: the possibility to attach a forum globally, by customer, or by project
(more about this in a future episode).
As you can see, a Gantt chart is a Gantt chart, and dotProject on that side
contains standard features (e.g. adding information about people, costs), plus a
quite flexible (albeit sometimes faulty- hence, my half-hearted support of it as a
corporate choice) access control system: you can allow users to do anything or
nothing, and on any information- down to no information at all (try managing that
with more than few dozen users- you would need an administrator).
Web based solutions usually have a freemium business model, i.e. basic services for
free, everything else for a monthly or yearly fee, with “packages” by project,
customer, or role/feature combinations.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
CHANGE AND COMPLIANCE
As outlined within the introduction, the case study is a compliance mini-
programme to be delivered within a really short timeframe: 18 projects in less than
8 months.
It is not just consistency that matters, but also how you cope with and recover with
unavoidable mistakes or “failures to comply”- “giving a second chance” is part of
this specific corporate culture.
Even for an initiative as short as the one outlined within this business case it is
advisable to have a preliminary “fact finding” before planning starts, a preliminary
“data collection”- about both what is required by the new law, and what is
already available within the organization, so that then a proper feasibility study
can be carried out.
In many organizations, “hitting the ground running” is considered the way to go:
and I will let you have a look at books on WWII events on what happens when you
drop paratroopers without first doing a proper fact-finding.
Business in most cases is more forgiving, but the less time you have, the higher the
potential impacts of any misstep, and the less you have excuses to skip a feasibility
study before committing resources based just on a “guesstimate”.
Therefore, I have always been puzzled by how organizations with less resources to
waste “save” by doing without feasibility and/or analysis, as if both were something
worth doing only if you are a mega-corporation.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
SCOPE & PLANNING
A first obvious step should be to identify the requirements embedded within the
new compliance requirements, and then assessing potential impacts by involving
relevant business units and operational staff (more than managers).
The fastest approach that I saw working in practical cases was to prepare a
“position paper” to be shared before a brainstorming involving those that could
contribute to definition of the roadmap.
Scope definition is still a business choice, but it should be based on a clear
assessment of potential impacts and risks/opportunities- it isn’t a matter of taste.
In a compliance case, there is an added “bonus”: as you know the “due by” date,
the activities identified can be distributed by starting from the end, with a “safety
margin” left between the due date and the end of the activities, and whatever is
identified as belonging to the scope is to be distributed across time accordingly.
Therefore, it often starts with a rough Gantt chart built around milestones- (see next
page) and the only resources identified from the beginning are those that will lead
the effort.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
MAPPING THE TERRITORY
In this business case, it might seem disproportionate to spend 1/8th of the time
available on planning and outlining, but in reality this is often the case, as that
month delivers what is actually, for similar activities, closer to a “business blueprint
and resources+deliverables shopping list”, so that a business choice can be made.
Typically, this isn’t delivered as a single sequence of activities, but with three main
phases:
1. Data collection (internal and external), and confirmation of guideline
2. Scenarios identification based upon the guidelines
3. Analysis and “roadmap for delivery” of the selected scenario.
Furthermore, you can then potentially identify areas where the timeline can be
“compressed”, e.g. by having teams working in parallel, and maybe then adding
steps to integrate and collate the results produced by each team (consider the
case of a complex business proposal: would you have just one team working for six
months sequentially?).
Obviously, you have first to identify what can be split between teams.
1 2a
2b
3a 4a1
4a2 4b
4c 5a
5b 6 7a 8 9
7b 3b 4d 5c
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
Decades ago it started on a
corkboard with pins and bits of
paper shuffled around.
Then evolved into a whiteboard
with PostIt™ notes), albeit if you
think visually, any tool allowing to
freely shuttle shapes around is
useful- including Powerpoint.
For the Powerpoint enthusiasts out
there: it is less than perfect, but
easier to maintain if you use
extensively “SmartArt” drawings for
your charts.
I use a "Mindmap" tool called
Xmind (again, a freemium, working
on various platforms)1.
THE PROJECTS
1 identify feasibility
2a define service requirements
2b define service location
3a design service
3b design communication/pre-emptive mktg
4a1 prepare service
4a2 prepare service environment
4b test service with pilot customer
4c train staff for initial service
4d pre-emptive marketing
5a coach on-the-job initial staff
5b monitor from customer side
5c marketing campaign&lead generation
6 tune service
7a retrain staff
7b acquire further staff
8 transition to Business As Usual
9 closing down programme&thesaurisation
1 A huge online library of maps from other users might actually save you some analysis time; see
http://www.xmind.net/share/aleph123/ for maps that I posted since 2009
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
GANTT, CPM, AND PERT
Our society is quite complex- but, eventually, tools developed by a “niche” of
specialists surface within mass media, and become common parlance.
Any activity involving more people and organizations requires a form of planning
and resource allocation, ranging from a mere agreement on who/what/when, to
more complex arrangements (e.g. conditions associated to what can be done
when and by whom).
Gantt charts were originally created to support production planning (we are used
to look at the width of a bar, but it used to be relevant also its height, and could
carry around other information on the resources used by the activities).
If you were born in the 1970s, since you started reading newspapers and
magazines you got used to see how activities evolve, presented with a form of
Gantt chart; so, you don’t need to be a project manager to be able to read one.
It might be because your local community has to deliver new roads, or just for the
plan leading to next Olympic Games, or (I hold an Italian passport, hence…) the
schedule for the next European Football cup (soccer, for my American readers):
they are all variants of a Gantt.
A Gantt (see examples within the “Appendix: Tools” of the “Business Case”
chapter) is nothing more than a (usually) vertical list of activities, whose delivery
across time is marked by a sign in columns representing time.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
For the more technically oriented (in planning, not ICT, terms), the link between
two bars can be somewhat more complex than a mere “first A, then B”, but overall
what a Gantt shows nowadays is a sequence of activities- within a project, or
across multiple projects, with some constraints (e.g. when, in relation to A, B can or
has to start/finish).
In the late 1980s, before Microsoft Project, I used other tools that were specialized,
e.g. producing just the Gantt chart, or producing a variant that allowed to identify
the “critical path”, or a more modern chart, PERT, created in the 1950s for complex
activities involving a myriad of projects and, as in the business case outlined here,
projects of a different sort.
When you have a relatively complex Gantt, eventually there might be activities
that overlap, and therefore require more resources to be available at the same
time, and activities that, if delayed, could wreak havoc on your wonderful plan.
A typical example is contained within the business case: you can train people to
deliver a service, but if the building (with the appropriate equipment) required to
deliver that service isn’t ready by when they will have been trained, they will just sit
idle.
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
PERT: INTRODUCTION
Early
start
Duration Early
finish
4 6.33 10.33
Task name Task name
Late
start
Slack Late
finish
8.68 4.68 15.01
In a complex project, sometimes there is a “backbone” of activities that have zero
or limited flexibility- keep track of the cascading impacts of any change.
No matter how good are the teams focused on other activities, the most critical
activities are those that could make all those efforts useless.
In a nutshell, this is what the “critical path method” is about- and I used software
being able to do just a Gantt and a CPM analysis decades ago (less visually
appealing than what you have now, but still useful).
A PERT diagram (shown above) can be useful in even more complex cases, and it
is filled in two steps (from beginning to end, and from end to the beginning), and
involves some statistical number crunching (the example is from Wikipedia).
It isn’t just a chart, it more a “technique” (it stands for Program Evaluation Review
Technique), and it is more or less a contemporary of the CPM.
The computations? 10.33 = 6.33 (duration) + 4 (early start); 15.01 = 6.33 (duration) +
4 (early start)+ 4.68 (slack)
Access to the online version of “#QuPlan – A Quantum of Planning
© 2015 Roberto Lofaro http:/www.linkedin.com/in/robertolofaro
Personally, after drafting a Gantt (more easily understood by non-
project/programme managers), and maybe using the CPM-equivalent within
Microsoft Project or other tools to “highlight” visually which activities, subprojects, or
projects are “critical”, whenever feasible I prefer to keep track by using a “macro-
level” PERT or at least a network chart, to allow the coordination of multiple
activities by immediately showing, quantitatively, how things are evolving.
If you read any book on project management that presents Gantt, CPM, PERT, you
will find reference to “tasks”, but actually if you work at a macro-level you can still
find them useful, as a “roadmap management tool”.
In this business case, it is even more probable, as some of the (sub)projects might
not have their own Gantt.
If you have an activity lasting two weeks and having a “standard” sequence of
tasks, using a Gantt instead of a plain sequence in Excel is often a sign that
whoever was assigned to it is “green” enough to put the tool before the aim.
A Gantt can be useful while planning, but a “tracking Gantt” (i.e. showing where
you are) and a CPM allow you to monitor and identify areas worth of intervention,
while a PERT allows you to continuously assess “how much” flexibility is left within
your schedule, so that maybe you can find expedient to postpone some non-
critical tasks and re-allocate temporarily people to tasks that require more
resources (if it makes sense to add resources- sometimes, it is just a waste, as it adds
then the need for further oversight or integration).
EPISODES SCHEDULE