Quick Quiz 1 SQA
description
Transcript of Quick Quiz 1 SQA
![Page 1: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/1.jpg)
SQA&T
Quick Quiz
![Page 2: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/2.jpg)
Q1_01
In general, people's quality expectations for software systems they use and rely upon are
Choose one answer. • a. All of the others • b. The software systems must do the things
right • c. The software systems must do the right things • d. None of the others
![Page 3: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/3.jpg)
Q1_01
In general, people's quality expectations for software systems they use and rely upon are
Choose one answer. • a. All of the others (x)• b. The software systems must do the things
right • c. The software systems must do the right things • d. None of the others
![Page 4: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/4.jpg)
Q1_02
Which of the following statements about Quality problems in large software systems are true?
Choose at least one answer. a. All software systems nowadays are highly complex and
contain millions of lines of source code b. Software testing plays a central role among the software
QA activitiesc. Dealing with the problems that may impact customers and
users negatively d. Various QA techniques can help produce high-quality
software systems
![Page 5: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/5.jpg)
Q1_02
Which of the following statements about Quality problems in large software systems are true?
Choose at least one answer. a. All software systems nowadays are highly complex and
contain millions of lines of source code b. Software testing plays a central role among the software
QA activities (x)c. Dealing with the problems that may impact customers and
users negatively (x)d. Various QA techniques can help produce high-quality
software systems (x)
![Page 6: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/6.jpg)
Q1_03
In quality assurance, we can divide the people into two broad groups:
Choose at least one answer. a. Consumers b. Producers c. Users d. Customers
![Page 7: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/7.jpg)
Q1_03
In quality assurance, we can divide the people into two broad groups:
Choose at least one answer. a. Consumers (x)b. Producers (x)c. Users d. Customers
![Page 8: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/8.jpg)
Q1_04
The terms error, fault, failure are related in the following causal chain:
Choose one answer. • a. errors-> failures-> faults. • b. faults -> errors -> failures. • c. faults -> failures -> errors. • d. errors -> faults -> failures.
![Page 9: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/9.jpg)
Q1_04
The terms error, fault, failure are related in the following causal chain:
Choose one answer. • a. errors-> failures-> faults. • b. faults -> errors -> failures. • c. faults -> failures -> errors. • d. errors -> faults -> failures. (x)
![Page 10: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/10.jpg)
10
The primary objective of user acceptance testingis to:
A. Identify requirements defectsB. Determine if software is fit for useC. Identify missing requirementsD. Verify that software is maintainable
![Page 11: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/11.jpg)
11
The primary objective of user acceptance testingis to:
A. Identify requirements defectsB. Determine if software is fit for use (x)C. Identify missing requirementsD. Verify that software is maintainable
![Page 12: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/12.jpg)
12
• A key concept of quality control is that all work products
A. are delivered on time and under budget C. have measurable specifications for process
outputs B. have complete documentation D.are thoroughly tested/reviewed before
delivered to the customer
![Page 13: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/13.jpg)
13
• A key concept of quality control is that all work products
A. are delivered on time and under budget C. have measurable specifications for process
outputs B. have complete documentation D.are thoroughly tested/reviewed before
delivered to the customer (x)
![Page 14: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/14.jpg)
14
Viewing QA as dealing with defects, we can classify QA alternatives into the following 3 generic categories
• A. Defect Prevention, Defect Removal, Defect Containment
• C. Testing, Education and Training, Safety Assurance• B. Error source removal, Inspection, Fault Tolerance • D. Inspection, Formal method, Failure Containment
![Page 15: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/15.jpg)
15
Viewing QA as dealing with defects, we can classify QA alternatives into the following 3 generic categories
• A. Defect Prevention, Defect Removal, Defect Containment (x)
• C. Testing, Education and Training, Safety Assurance• B. Error source removal, Inspection, Fault Tolerance • D. Inspection, Formal method, Failure Containment
![Page 16: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/16.jpg)
16
Beta testing is A. performed by customers at their own siteC. performed by an Independent Test TeamB. performed by customers at the software
developer's siteD. performed as early as possible in the lifecycle
![Page 17: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/17.jpg)
17
Beta testing is A. performed by customers at their own site (x)C. performed by an Independent Test TeamB. performed by customers at the software
developer's siteD. performed as early as possible in the lifecycle
![Page 18: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/18.jpg)
18
We split testing into distinct sub-phases because:a.Each test stage has a different purpose.c.We can run different tests in different
environments.b.It is easier to manage assign doersd.The more stages we have, the better the testing.
![Page 19: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/19.jpg)
19
We split testing into distinct sub-phases because:a.Each test stage has a different purpose. (x)c.We can run different tests in different
environments.b.It is easier to manage assign doersd.The more stages we have, the better the testing.
![Page 20: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/20.jpg)
20
The difference between re-testing and regression testing is:
A. re-testing ensures the original fault has been removed; regression testing looks for unexpected side-effects
C. re-testing is done after faults are fixed; regression testing is done earlier
b. re-testing looks for unexpected side-effects; regression testing ensures the original fault has been removed
D. re-testing is done by developers; regression testing is done by independent testers
![Page 21: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/21.jpg)
21
The difference between re-testing and regression testing is:
A. re-testing ensures the original fault has been removed; regression testing looks for unexpected side-effects (x)
C. re-testing is done after faults are fixed; regression testing is done earlier
b. re-testing looks for unexpected side-effects; regression testing ensures the original fault has been removed
D. re-testing is done by developers; regression testing is done by independent testers
![Page 22: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/22.jpg)
22
Which one is more meaningful to customers and users?
a. Defect countc. Reliabilityb. Defect densityd. Defect type
![Page 23: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/23.jpg)
23
Which one is more meaningful to customers and users?
a. Defect countc. Reliability (x)b. Defect densityd. Defect type
![Page 24: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/24.jpg)
24
What is the focus of CFT?A. Correct handling of data items C. Computational resultsB. Execution pathD. Data dependencies
![Page 25: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/25.jpg)
25
What is the focus of CFT?A. Correct handling of data items C. Computational resultsB. Execution path (x)D. Data dependencies
![Page 26: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/26.jpg)
26
The place to start if you want a test tool isA. Attend a tool exhibitionC. Analyse your needs and requirementsB. Invite a vendor to give a demoD. Find out what your budget would be for the
tool
![Page 27: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/27.jpg)
27
The place to start if you want a test tool isA. Attend a tool exhibitionC. Analyse your needs and requirements (x)B. Invite a vendor to give a demoD. Find out what your budget would be for the
tool
![Page 28: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/28.jpg)
28
An input field takes the year of birth between 1900 and 2004. The boundary values for testing this field are
A. 0, 1900, 2004, 2005C. 1899, 1900, 2004, 2005B. 1900, 2004D. 1899, 1900, 1901, 2003, 2004, 2005
![Page 29: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/29.jpg)
29
An input field takes the year of birth between 1900 and 2004. The boundary values for testing this field are
A. 0, 1900, 2004, 2005C. 1899, 1900, 2004, 2005 (x)B. 1900, 2004D. 1899, 1900, 1901, 2003, 2004, 2005
![Page 30: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/30.jpg)
30
In the problem analysis meeting, a leader is a person who
a.books meeting roomc. encourages all members to give their opinionsb. takes minutes of the meetingd. takes telephone calls
![Page 31: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/31.jpg)
31
In the problem analysis meeting, a leader is a person who
a.books meeting roomc. encourages all members to give their opinions
(x)b. takes minutes of the meetingd. takes telephone calls
![Page 32: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/32.jpg)
32
What is not defined in ISO 9000?a. Standard for quality assurancec. How to do to reach the quality targetb. What to do for quality management d. Process approach
![Page 33: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/33.jpg)
33
What is not defined in ISO 9000?a. Standard for quality assurancec. How to do to reach the quality target(x)b. What to do for quality management d. Process approach
![Page 34: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/34.jpg)
34
Mitigating the risk byA. Minimizing the probability of occurrenceC. Deflecting the risk elsewhereB. Minimizing the value of impactD. All of the above
![Page 35: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/35.jpg)
35
Mitigating the risk byA. Minimizing the probability of occurrenceC. Deflecting the risk elsewhereB. Minimizing the value of impactD. All of the above (x)
![Page 36: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/36.jpg)
36
What is NOT an activity of cause analysis?a. Identify the common defects c. Identify the way to fix the defectsb. Identify the causes of the defectsd. Identify actions to avoid the same defects
![Page 37: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/37.jpg)
37
What is NOT an activity of cause analysis?a. Identify the common defects c. Identify the way to fix the defects (x)b. Identify the causes of the defectsd. Identify actions to avoid the same defects
![Page 38: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/38.jpg)
38
What is NOT an activity of cause analysis?a. Identify the common defects c. Identify the way to fix the defects (x)b. Identify the causes of the defectsd. Identify actions to avoid the same defects
![Page 39: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/39.jpg)
39
A branching node isA. a entry nodeC. a node associated with multiple outlinksB. a node associated with multiple inlinksD. a exit node
![Page 40: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/40.jpg)
40
A branching node isA. a entry nodeC. a node associated with multiple outlinks (x)B. a node associated with multiple inlinksD. a exit node
![Page 41: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/41.jpg)
41
Defect prevention involves which of the following steps:
a. Identify critical tasksc. Minimize expected impactb. Estimate expected impactd. Evaluate the performance
![Page 42: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/42.jpg)
42
Defect prevention involves which of the following steps:
a. Identify critical tasksc. Minimize expected impact (x)b. Estimate expected impactd. Evaluate the performance
![Page 43: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/43.jpg)
43
Which of the following is NOT one of the five maturity levels in the SEI CMMI framework?
A. RepeatableC. ManagedB. TestableD. Optimized
![Page 44: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/44.jpg)
44
Which of the following is NOT one of the five maturity levels in the SEI CMMI framework?
A. RepeatableC. ManagedB. Testable (x)D. Optimized
![Page 45: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/45.jpg)
45
If you were given a bar chart which showed defects by the phase in which they were introduced, in chronological order, you would have been handed a(n):
A.Cause-effect diagramC.Pareto chartB. HistogramD.Control chart
![Page 46: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/46.jpg)
46
If you were given a bar chart which showed defects by the phase in which they were introduced, in chronological order, you would have been handed a(n):
A.Cause-effect diagram (x)C.Pareto chartB. HistogramD.Control chart
![Page 47: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/47.jpg)
47
The condition that represents a potential for loss to an organization is called:
A. RiskC. Threat B. ExposureD. Control
![Page 48: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/48.jpg)
48
The condition that represents a potential for loss to an organization is called:
A. Risk (x)C. Threat B. ExposureD. Control
![Page 49: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/49.jpg)
49
Which item is NOT included in Risk planning of the project?
A. List of possible risks which can impact to the project
C. Contingency actionsB. Mitigation actions d. Number of planned defects
![Page 50: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/50.jpg)
50
To prepare Quality plan for next year, QA leader needs to focus on the most major problems of last year.
Which quality tool is used firstly for the purpose?A. HistogramC. Control chart B. Pareto ChartD.Cause-effect diagram
![Page 51: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/51.jpg)
51
To prepare Quality plan for next year, QA leader needs to focus on the most major problems of last year.
Which quality tool is used firstly for the purpose?A. HistogramC. Control chart B. Pareto Chart (x)D.Cause-effect diagram
Pareto Diagram
0100200300400500
D©y hángM¸y kªnhChu«ngháng
Kh«ng tr¶lêi
YÕu tèkh¸c
Impact
Stat
istic
0%20%40%60%80%100%
¶nh h ëng
Céng dån
![Page 52: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/52.jpg)
52
What is the formula of the metric Defect density?
A. Total defects/ Product sizeC. Review defects/Total defectsB. Test defects/Total defectsD. Test defects/ Test effort
![Page 53: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/53.jpg)
53
What is the formula of the metric Defect density?
A. Total defects/ Product size (x)C. Review defects/Total defectsB. Test defects/Total defectsD. Test defects/ Test effort
![Page 54: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/54.jpg)
54
Which techniques are applied for Fault tolerance?
A. Duplication techniqueC. Both of the aboveB. Backup techniqueD. None of the above
![Page 55: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/55.jpg)
55
Which techniques are applied for Fault tolerance?
A. Duplication techniqueC. Both of the above (x)B. Backup techniqueD. None of the above
![Page 56: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/56.jpg)
56
The company has spent a lot of money to buy automation test tool QuickTestPro. Project team uses the tool for performance testing. It is counted to
A. Direct quality costsC.Prevention costsB.Indirect quality costsD.None of the above
![Page 57: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/57.jpg)
57
The company has spent a lot of money to buy automation test tool QuickTestPro. Project team uses the tool for performance testing. It is counted to
A. Direct quality costsC.Prevention costsB.Indirect quality costs (x)D.None of the above
![Page 58: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/58.jpg)
58
On-job training does NOT includeA. Formal training sponsored by IT companiesC. Background information in software
developmentB. Informal training within the company for
product historyD. Guidance of some experts
![Page 59: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/59.jpg)
59
On-job training does NOT includeA. Formal training sponsored by IT companiesC. Background information in software
development (x)B. Informal training within the company for
product historyD. Guidance of some experts
![Page 60: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/60.jpg)
60
• A deviation from the specified or expected behaviour that is visible to end-users is called
A. An errorB. A failureC. A faultD. A defect
![Page 61: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/61.jpg)
60
• A deviation from the specified or expected behaviour that is visible to end-users is called
A. An errorB. A failure (x)C. A faultD. A defect
![Page 62: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/62.jpg)
61
• A fault is • a. found in the software; the result of an
error.• b. departure from specified behaviour.• c. an incorrect step, process or data
definition in a computer program.• d. a human action that produces an
incorrect result.
![Page 63: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/63.jpg)
61
• A fault is • a. found in the software; the result of an
error.• b. departure from specified behaviour.• c. an incorrect step, process or data
definition in a computer program. (x)• d. a human action that produces an
incorrect result.
![Page 64: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/64.jpg)
62
What are Verifications?a. Review and acceptance testb. To check whether a function needed and
expected by customers is present in a software product
c. To answer the question, did we build the right system?
d. To confirm that work products properly reflect the requirements specified for them
![Page 65: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/65.jpg)
62
What are Verifications?a. Review and acceptance testb. To check whether a function needed and
expected by customers is present in a software product
c. To answer the question, did we build the right system?
d. To confirm that work products properly reflect the requirements specified for them (x)
![Page 66: Quick Quiz 1 SQA](https://reader036.fdocuments.us/reader036/viewer/2022081503/5695d1b71a28ab9b0297a6c1/html5/thumbnails/66.jpg)
I can pass
It is too easy!!!