Queen Street Sanitary Pumping Station Class Environmental ... · Design and Construction December...
Transcript of Queen Street Sanitary Pumping Station Class Environmental ... · Design and Construction December...
-
December 14, 2016
Queen Street Sanitary Pumping StationClass Environmental AssessmentPublic Information Centre
Page 1
-
Welcome
Please complete the sign-in sheet andreview display materials.
As you move through the informationpresented today, we encourage you toask questions and provide feedback.
Your input is valued! Please fill out asurvey/comment form.
Page 2
-
Phase 1
Problem or Opportunity- Identify problem/deficiency and
opportunity- Notification of Project Commencement
to public and agencies
Spring 2016
Phase 2
Alternative Solutions- Identify and evaluate alternative
solutions- Agency consultation
- Public Information Centre- Establish preferred solution and
confirm project schedule selection(i.e. A, A+, B or C)
30 day PublicReview Period
Fall 2016
Schedule BProject File Report
ImplementationDesign and Construction
December 2016
2017 - 2018
Class EA Process
July 2016
Page 3
Schedule A+Public Notification
-
Queen Street Sanitary Pumping Station and Catchment Area
• SPS is located near the intersectionof Queen St. and Harvey St.(accessible from Guelph Ave.)
• Sanitary sewer collectionmodifications in 2015:• revised catchment area from 435
to 227 hectares• reduced peak flows from 380 to
223 L/s• Sanitary Sewer Master Plan
identified required improvementsincluding:• pump & piping• stand-by generator• electrical• building
Page 4
-
Problem/Opportunity Statement
Recent changes to the City’s sanitary collection system have significantly
reduced the drainage area and flows to the Queen Street Sanitary Pumping
Station (SPS). The 2014 Cambridge Sanitary Sewer Master Plan identified the
need for a number of improvements and equipment replacements at the Queen
Street SPS that are required to address age and expected life span as well as to
meet current standards. The required improvements, planned over a 20 year
period, represent a large capital investment.
Proposed development plans in the area surrounding the SPS provide an
opportunity to review the location of the SPS to better integrate with adjacent
land uses.
Page 5
-
Identification of Potential SPS Sites
Criteria for selecting potentialsites:• Close proximity of the existing
wastewater pumping station• City owned, or available
privately-owned lands• Separation from residential
areas and/or other non-compatible land uses
• Proximity of trunk sewers andarea to be serviced
• Sufficient area for the SPSincluding emergency storage
• Avoid areas of archaeologicalpotential, natural heritageareas, future residentialdevelopment, etc.
• Separation from the SpeedRiver regulatory flood line
Page 6
-
Overview of Alternative SPS Siting Options
Page 7
-
Evaluation CriteriaComponent Description IncludesNaturalEnvironment
Component having regard forprotecting significant natural andphysical elements of theenvironment (i.e. air, land, waterand biota) including naturalheritage-environmentally sensitivepolicy areas.
Potential Impact of GRCA Regulated FloodplainSensitive species habitatSiting considerations or constraints, including displacements ordisruption to natural features (woodlands, trees and other terrestrialvegetation)Effects on ground/surface water quality
Social &Cultural
Component that evaluatespotential effects on residents,neighbourhoods, businesses,community character, socialcohesion, community features andhistorical/archaeological andheritage components in addition tomunicipal and provincialdevelopment objectives.
Potential effects on short-term and long-term community growthPotential impacts to businesses and residences andrecreational/institutional land uses (parking, odours, etc)Cultural heritage resourcesArchaeological resourcesPotential temporary disruption during construction (i.e. dust, noise,vibrations, traffic management, and pedestrian movement, detours,access to property and maintain existing services.)Complexity of ApprovalsLand Requirements (City or privately owned)Potential disruption during daily operation
Economic &Financial
Component that addresses thepotential effect on infrastructurecapital and O&M costs.
Capital cost, O&M costs.
TechnicalConsiderations
Component that considerstechnical suitability.
System stability and sustainabilityConstructability - ease of construction, construction scheduling(pumping station)Constructability - new forcemain and trunk sewersAdditional mitigation for floodplain issuesPotential for managing contaminated soilsOperational and maintenance issues
Page 8
-
Preliminary Evaluation
Page 9
-
Preferred Alternative – Option 1. Upgrade Existing SPSAdvantages:• Proposed construction withinexisting site
• Minimal impacts on localresidents
• Lower cost than reconstructionon new site
• Class EA Schedule A+Disadvantages:• In GRCA floodway – requiresfloodproofing measures
• Need to improve aesthetics• Constructability – need to keepexisting SPS operational duringconstruction
Conceptual Cost Estimate($2016): $4.63M
Description:• Upgrades to existing SPS including:• Pumps & piping; standby power replacement• Electrical, instrumentation and SCADA upgrades• Structural and building repairs; aesthetic improvements• Addition of underground emergency storage
Page 10
-
Proposed Mitigation MeasuresWork Near Water• In water works (if required) to take place
outside of fish spawning timing window• Develop comprehensive
erosion/sedimentation control strategyincluding regular inspections
• Prepare and follow contingency plans forcontrol and cleanup should a spill occur
Noise/Vibration/Dust:• Construction operations to occur during day
shift• Use of low noise equipment during
construction, where possibleTrees and Vegetation• Minimize tree and vegetation removal• Prepare Tree Protection Plan, if required• Breeding Birds - in accordance with the
Migratory Birds Convention Act, any treetrimming or site clearing should take placebetween August 1 and April 30
Archaeological• If any archaeological and/or historical resources
are discovered during the performance ofconstruction work, the performance of the work inthe area of the discovery is to halt. The Ministryof Culture (Archaeological Unit) will be notified foran assessment of the discovery. Work in the areaof the discovery would not resume until cleared todo so by the Ministry
Groundwater Management• Implement dewatering plan based on
hydrogeological assessment
Page 11
-
Next Steps
2016
• See project website for a copy of thedisplay materials
• Receive public comments byJanuary 6, 2017
2017• Design, Permitting - Approvals
2018*
• Tender and Construction• Post construction monitoring
The following steps will be completed next:
Page 12
-
Thank You for Attending
We appreciate the time you have taken to learnmore about the project and value your input.Stay involved and up-to-date as the projectprogresses:• Join our mailing list: leave us an email or
mailing address• Visit the project website:
http://www.cambridge.ca/QueenStSanitaryPS• Contact us with additional comments or
questions at any time:
Scott MacDonald, P. Eng.Project EngineerCity of Cambridge50 Dickson Street, PO Box 669Cambridge, ON, N1R 5W8Tel: 519-621-0740 ext [email protected]
Ms. Patricia Quackenbush, P.Eng.Senior Project ManagerAECOM50 Sportsworld Crossing Rd, Suite 290Kitchener, ON N2P 0A4Tel: [email protected]
Page 13