Queen Street Sanitary Pumping Station Class Environmental ... · Design and Construction December...

13
December 14, 2016 Queen Street Sanitary Pumping Station Class Environmental Assessment Public Information Centre Page 1

Transcript of Queen Street Sanitary Pumping Station Class Environmental ... · Design and Construction December...

  • December 14, 2016

    Queen Street Sanitary Pumping StationClass Environmental AssessmentPublic Information Centre

    Page 1

  • Welcome

    Please complete the sign-in sheet andreview display materials.

    As you move through the informationpresented today, we encourage you toask questions and provide feedback.

    Your input is valued! Please fill out asurvey/comment form.

    Page 2

  • Phase 1

    Problem or Opportunity- Identify problem/deficiency and

    opportunity- Notification of Project Commencement

    to public and agencies

    Spring 2016

    Phase 2

    Alternative Solutions- Identify and evaluate alternative

    solutions- Agency consultation

    - Public Information Centre- Establish preferred solution and

    confirm project schedule selection(i.e. A, A+, B or C)

    30 day PublicReview Period

    Fall 2016

    Schedule BProject File Report

    ImplementationDesign and Construction

    December 2016

    2017 - 2018

    Class EA Process

    July 2016

    Page 3

    Schedule A+Public Notification

  • Queen Street Sanitary Pumping Station and Catchment Area

    • SPS is located near the intersectionof Queen St. and Harvey St.(accessible from Guelph Ave.)

    • Sanitary sewer collectionmodifications in 2015:• revised catchment area from 435

    to 227 hectares• reduced peak flows from 380 to

    223 L/s• Sanitary Sewer Master Plan

    identified required improvementsincluding:• pump & piping• stand-by generator• electrical• building

    Page 4

  • Problem/Opportunity Statement

    Recent changes to the City’s sanitary collection system have significantly

    reduced the drainage area and flows to the Queen Street Sanitary Pumping

    Station (SPS). The 2014 Cambridge Sanitary Sewer Master Plan identified the

    need for a number of improvements and equipment replacements at the Queen

    Street SPS that are required to address age and expected life span as well as to

    meet current standards. The required improvements, planned over a 20 year

    period, represent a large capital investment.

    Proposed development plans in the area surrounding the SPS provide an

    opportunity to review the location of the SPS to better integrate with adjacent

    land uses.

    Page 5

  • Identification of Potential SPS Sites

    Criteria for selecting potentialsites:• Close proximity of the existing

    wastewater pumping station• City owned, or available

    privately-owned lands• Separation from residential

    areas and/or other non-compatible land uses

    • Proximity of trunk sewers andarea to be serviced

    • Sufficient area for the SPSincluding emergency storage

    • Avoid areas of archaeologicalpotential, natural heritageareas, future residentialdevelopment, etc.

    • Separation from the SpeedRiver regulatory flood line

    Page 6

  • Overview of Alternative SPS Siting Options

    Page 7

  • Evaluation CriteriaComponent Description IncludesNaturalEnvironment

    Component having regard forprotecting significant natural andphysical elements of theenvironment (i.e. air, land, waterand biota) including naturalheritage-environmentally sensitivepolicy areas.

    Potential Impact of GRCA Regulated FloodplainSensitive species habitatSiting considerations or constraints, including displacements ordisruption to natural features (woodlands, trees and other terrestrialvegetation)Effects on ground/surface water quality

    Social &Cultural

    Component that evaluatespotential effects on residents,neighbourhoods, businesses,community character, socialcohesion, community features andhistorical/archaeological andheritage components in addition tomunicipal and provincialdevelopment objectives.

    Potential effects on short-term and long-term community growthPotential impacts to businesses and residences andrecreational/institutional land uses (parking, odours, etc)Cultural heritage resourcesArchaeological resourcesPotential temporary disruption during construction (i.e. dust, noise,vibrations, traffic management, and pedestrian movement, detours,access to property and maintain existing services.)Complexity of ApprovalsLand Requirements (City or privately owned)Potential disruption during daily operation

    Economic &Financial

    Component that addresses thepotential effect on infrastructurecapital and O&M costs.

    Capital cost, O&M costs.

    TechnicalConsiderations

    Component that considerstechnical suitability.

    System stability and sustainabilityConstructability - ease of construction, construction scheduling(pumping station)Constructability - new forcemain and trunk sewersAdditional mitigation for floodplain issuesPotential for managing contaminated soilsOperational and maintenance issues

    Page 8

  • Preliminary Evaluation

    Page 9

  • Preferred Alternative – Option 1. Upgrade Existing SPSAdvantages:• Proposed construction withinexisting site

    • Minimal impacts on localresidents

    • Lower cost than reconstructionon new site

    • Class EA Schedule A+Disadvantages:• In GRCA floodway – requiresfloodproofing measures

    • Need to improve aesthetics• Constructability – need to keepexisting SPS operational duringconstruction

    Conceptual Cost Estimate($2016): $4.63M

    Description:• Upgrades to existing SPS including:• Pumps & piping; standby power replacement• Electrical, instrumentation and SCADA upgrades• Structural and building repairs; aesthetic improvements• Addition of underground emergency storage

    Page 10

  • Proposed Mitigation MeasuresWork Near Water• In water works (if required) to take place

    outside of fish spawning timing window• Develop comprehensive

    erosion/sedimentation control strategyincluding regular inspections

    • Prepare and follow contingency plans forcontrol and cleanup should a spill occur

    Noise/Vibration/Dust:• Construction operations to occur during day

    shift• Use of low noise equipment during

    construction, where possibleTrees and Vegetation• Minimize tree and vegetation removal• Prepare Tree Protection Plan, if required• Breeding Birds - in accordance with the

    Migratory Birds Convention Act, any treetrimming or site clearing should take placebetween August 1 and April 30

    Archaeological• If any archaeological and/or historical resources

    are discovered during the performance ofconstruction work, the performance of the work inthe area of the discovery is to halt. The Ministryof Culture (Archaeological Unit) will be notified foran assessment of the discovery. Work in the areaof the discovery would not resume until cleared todo so by the Ministry

    Groundwater Management• Implement dewatering plan based on

    hydrogeological assessment

    Page 11

  • Next Steps

    2016

    • See project website for a copy of thedisplay materials

    • Receive public comments byJanuary 6, 2017

    2017• Design, Permitting - Approvals

    2018*

    • Tender and Construction• Post construction monitoring

    The following steps will be completed next:

    Page 12

  • Thank You for Attending

    We appreciate the time you have taken to learnmore about the project and value your input.Stay involved and up-to-date as the projectprogresses:• Join our mailing list: leave us an email or

    mailing address• Visit the project website:

    http://www.cambridge.ca/QueenStSanitaryPS• Contact us with additional comments or

    questions at any time:

    Scott MacDonald, P. Eng.Project EngineerCity of Cambridge50 Dickson Street, PO Box 669Cambridge, ON, N1R 5W8Tel: 519-621-0740 ext [email protected]

    Ms. Patricia Quackenbush, P.Eng.Senior Project ManagerAECOM50 Sportsworld Crossing Rd, Suite 290Kitchener, ON N2P 0A4Tel: [email protected]

    Page 13