Quarterly Progress Report - Jan-March 2013
Transcript of Quarterly Progress Report - Jan-March 2013
National Cyclone Risk Mitigation Project (NCRMP)
Revenue (DM) Department Government of Andhra Pradesh
THIRD PARTY QUALITY AUDIT (TPQA)
in Joint Venture with
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
INDEX
1.0 Project Background 02
1.1 Third Party Quality Audit Consultant 03
1.2 Mobilization of Team 04
1.3 Setting up offices and logistics for the consultant teams 07
2.0 Review Meetings and Other Activities 08
3.0 Status of TPQA Visits 08
4.0 Progress of NCRMP works 09
5.0 District wise status of tests conducted by TPQA 27
6.0 Details of Quality Control Audit Reports Submitted During this 3 Months 28
7.0 Details of Environmental and Social Reports Submitted During this 3 Months 35
8.0Details of Consolidated Environmental and Social Reports Submitted During
this 3 Months 43
9.0 Inspections and Site Visits of TPQA During this 3 months 95
Photographs of site visits of TPQA 122
Page 1 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1.0 Project BackgroundAndhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the
state, the nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and
September-December, cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions,
the catastrophic events are increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is
enormous. In the 97 years ranging from 1892 to 1989, there were as many as 67 cyclones within the State.
It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or
disaster due to natural calamities such as cyclones and associated tidal waves and storm surges. The project is
formulated based on experiences of Government of Andhra Pradesh in mitigating such disasters during the past and
also keeping in view the existing facilities available in the project area in Andhra Pradesh.
The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development
Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the
proceeds to payments for goods, works, related services and consulting services under this Project.
National Cyclone Risk Mitigation Project (NCRMP) – Project Implementation Unit (PIU), Andhra Pradesh,
headquartered at Hyderabad has invited the consultants to submit proposals for providing the consultancy services
for Third Party Quality Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari,
West Godavari, Krishna, Guntur, Prakasam and Nellore. The project “Construction of Multipurpose Cyclone
Shelters, Roads to Cyclone Shelters, and Roads to habitations and Roads & Bridges under NCRMP” is
funded by International Development Association and received through Government of India. This consultancy is
envisaged to audit the quality of works being implemented by various line departments working under PIU. The
number of works under progress / for which agreements are concluded in each district is shown in the table below.
District
No. of works(Under ConcludedAgreements) No. of works Completed No. of works under Progress
No.
of w
orks
not
star
ted
RH
B
RC
S
MPC
S
Brid
ges
Roa
ds (R
&B
)
Tota
l
RH
B
RC
S
MPC
S
Brid
ges
Roa
ds (R
&B
)
Tota
l
RH
B
RC
S
MPC
S
Brid
ges
Roa
ds (R
&B
)
Tota
l
Srikakulam 6 8 2 4 1 21 3 8 0 3 1 15 3 0 2 1 0 6 0
Vizianagaram - - - 2 1 3 0 0 0 1 1 2 0 0 0 1 0 1 0
Visakhapatnam 8 6 7 - - 21 8 6 0 0 0 14 0 0 6 0 0 6 1
East Godavari 2 8 3 - - 13 2 7 0 0 0 9 0 0 3 0 0 3 1
West Godavari 10 - - - - 10 10 0 0 0 0 10 0 0 0 0 0 0 0
Krishna 5 3 - - - 8 5 3 0 0 0 8 0 0 0 0 0 0 0
Guntur 3 12 - 2 - 17 3 11 0 1 0 15 0 1 0 1 0 2 0
Prakasham 14 7 2 1 - 24 14 7 2 1 0 24 0 0 0 0 0 0
Nellore 16 10 - - - 26 16 8 0 0 0 24 0 2 0 0 0 2 0
64 54 14 9 2 143 61 50 2 6 2 121 3 3 11 3 0 20 2
Page 2 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1.1 Third Party Quality Audit Consultant.
To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone
Shelters, Roads to Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9
coastal districts The Commissioner for Disaster Management & Project Director, Project Implementation
Unit (PIU) NCRMP has selected Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.
On 31st May’2011, the Contract for Consultancy Service was signed between The Commissioner for
Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and the Egis
International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.
Page 3 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1.2 Mobilization of Team
In accordance with the Contract for Consultant Services, executed on 31st May’2011, by The
Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP
and the Egis India, professional services were authorized to commence work. The detail of team
mobilization and organization chart is shown below.
Sr.No. Name Designation Date Of
JoiningLast Day
ofWorking
NCRMP Project Office, Hyderabad
1 Bhavanna Rao Project Manager 01.06.2011
2 Dr. Surjit Singh Deepak Environmental Management Expert 09.06.2011
3 Dr. Sudesh Kaul Social Management Expert 01.06.2011
4 Mrityunjay Kumar MIS Expert 01.06.2011
5 V.Ravi Kumar Electrical 06.06.2011
6Ch.Giridhar Electrical 02.06.2011 13.12.2012
Prakash Rao Electro Mechanical 17.12.2012
7 Hari Shankar Prasad Field Staff - Environmental Engineer 09.06.2011
8 M. Venkata Ramana Field Staff - Social Expert 04.07.2011
9Viraj Premi Office Manager HYD 01.06.2011 31.03.2012
Suchan Kumar K P Office Manager HYD 02.04.2012
VISHAKAPATANAM
10 Ch.V.S.Sivakumar DPM / Vishakapatnam 28.09.2011
11 K.Siva Ramprasad Site Engineer 02.06.2011
12 Mallela Shyam sunder Site Engineer 07.07.2011
13 B.Srinivasulu Reddy Site Engineer 06.06.2011 22.09.2012
14 H.Venugopal Site Engineer 06.06.2011
15Siva Kishore Vedula Site Engineer 09.06.2011 04.01.2012
Sivaji Raju Site Engineer 13.02.2012
16Srinivas.Y Site Engineer 27.06.2011 06.01.2012
Venkateshwara Prasad Site Engineer 13.02.2012
17 Babu.G Office Manager 01.06.2011 19.06.2012
Page 4 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
KNVS.Malleswara Swamy Office Manager 20.06.2011 14.11.2012
N.Ramakrishana Office Manager 17.11.2012
ELURU
18M. Manohar DPM / Eluru 27.06.2011
R. Sathi Babu Randhi Deputy Project Manager 02.06.2011
19 Gudla Rama Naresh Site Engineer 06.06.2011
20 Nakka Jayasimha Site Engineer 06.06.2011
21 K. Jyothi Prasad Site Engineer 06.06.2011
22P.Durga Rao Site Engineer 06.06.2011 02.01.2012
Sridhar G Site Engineer 27.02.2012
23 N.Srinivas Site Engineer 01.07.2011
24 Vijaya Bhaskar Nalli Site Engineer 01.03.2012
25 Avinash Babu Gunnam Office Manager 01.06.2011
ONGOLE
26 Arun Kumar DPM / Ongole 22.02.2012
27P.Ramesh Reddy Site Engineer 06.06.2011 13.03.2012
T.SreeVishnu Site Engineer 14.03.2012
28Shaik Zaheer Ahamad Gori Site Engineer 02.06.2011 31.08.2012
S.Narendar Site Engineer 10.09.2012
29 K. Rama Rao Site Engineer 22.06.2011
30 Suresh Babu.P Site Engineer 06.06.2011
31 R.Balakrishna Reddy Site Engineer 02.06.2011
32Mallikarjuna Rao Site Engineer 02.06.2011 01.03.2012
Ravinder Reddy Site Engineer 15.07.2011
33 Neelakantan Office Manager 01.06.2011
Page 5 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Organization Chart of TPQA, NCRMP
Page 6 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1.3 Setting up offices and logistics for the consultant teams
We have established a Main office at Hyderabad, where all the necessary expertise that is required for this project.
There is a core team of national experts to monitor the project activities and discipline specialist will appropriately
support this core team. These experts will again be supported from the respective home office. Other than the
experts, support staff is also be stationed in this office. This office will be the base office during the project period of
consultants.
The details of our site offices are given in table below. These offices are provided with required communication
equipment, transportation facilities and necessary infrastructure. The offices are also equipped with computers with
basic software programs, printers, and other electronic gadgets like telephone, fax machines, etc. as felt needed.
Apart from the above PM and DPM offices, we have established site offices in all other districts
PM Office – Hyderabad
9-1-77/3, No.31, Third Floor
S.D. Road, Secundrabad – 500 003
Fax:=91-04-40179496
E- mail: [email protected]
DPM Office – Vishakhapatnam
Pavan Residency, Dr. No. 31-7-2/73,
Flat NO 503Kurmannapalem,
Opp to Bus Depot,
Vishakhapatnam - 530046
DPM Office – Eluru
Flat No. 504, Fourth Floor,
Yemireddy Residency Apartment,
Shekar Street, Gandhinagar,
Eluru, West Godavari Dist. A.P.
DPM – Ongole Office
H. No. 6-277, 2nd lane
Beside computer Centre
Maruthi Nagar
Ongole - 523002
Site Office for Krishna Dist.
D. No. 20-516-3/4,NGO Colony,
Frenchpet, Machilipatnam,Krishna Dist.,
Site Office for Srikakulam Dist.
Flat No T-1,3rd Floor Indiranagar Colony,
Ganesh Apartments,Srikakulam - 532421
Site Office for Guntur Dist.
H.No. 10-32,
Opposite Bhaskar Theatre,
Tenali road,Cherukapalli, Guntur-522309.
Site Office for East Godavari Dist.
D. No. 70-6-19/1,Upstairs,
Nagendragudi Veedhi,Ramanayyapet, Kakinada, E G Dist
Site Office for Nellore Dist.
Door No.23/218,2nd Floor Ravichettu Centre,
Fathekhanpet, Nellore – 524 003
Site Office for Krishna Dist.
Door No.20/516-27/8, NGO Colony,Parasupeta,Machilipatnam, Krishna District.
Page 7 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
2.0 Review Meetings and Other Activities
S.No. Place Date Activity
1 Hyderabad 07.01.2013 Attended Review meeting of TPQA at H Block in AP Secretariat with Commissionerand PD
2 Hyderabad 08.01.2013 Attended Review meeting of EPTRI at H Block in AP Secretariat withCommissioner and PD
3 Hyderabad 31.01.2013 Attended Review meeting at H Block in AP Secretariat with Commissioner and PD
4 Hyderabad 13.02.2013 Attended NCRMP State Level Committee review meeting conveyed by AP ChiefSecretary in ‘C’ Block of AP Secretariat.
5 Hyderabad 26.02.2013 Attended NCRMP Review meeting by World Bank Social Experts ‘H’ Block of APSecretariat.
6 Machilipatnam 27.02.2013 Attended to the Inspection of Saline Embankment and Bridge site in Krishnadistrict by World Bank Social Experts.
7 Hyderabad 14.03.2013 Attended NCRMP Review meeting by Hon’ble Minister Revenue in J Block, 7th
Floor of AP Secretariat.
3.0 Status of TPQA Visits:
The following table shows the details of TPQA visits to sites in respective districts.
DistrictTotal Number of Visits
TotalJan.'2012 Feb.'2012 Mar.'2012
Srikakulam 31 28 21 80
Vizianagaram 1 05 5 11
Vishakhapatnam 53 11 48 112
East Godavari 16 32 15 63
West Godavari 26 13 16 55
Krishna 5 14 0 19
Guntur 19 21 18 58
Prakasam 31 17 16 64
Nellore 18 13 13 44
Page 8 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
4.0 Progress of NCRMP works:
Third Party Quality Audit by Egis – India consulting servicesSummary of Activities
S.No. District
Agreements forPackages Communicated Status of works
PR R&B completed Progress Not Started/Deleted
1 Srikakulam 16 5 15 6 0
2 Vizianagaram - 3 2 1 0
3 Visakhapatnam 21 0 14 6 1
4 East Godavari 13 0 9 3 1
5 West Godavari 10 0 10 0 0
6 Krishna 8 0 8 0 0
7 Guntur 15 2 15 2 0
8 Prakasam 23 1 24 0 0
9 Nellore 26 0 24 2 0
Total 132 11 121 20 2
Total Packages for which Agreements are received 79
Total Number of works in the above packages 143
No. of Visits by TPQA
Page 9 of 198
The district wise progress of works is shown below.
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
TPQA STATUS REPORT FOR NCRMP WORKS TO THE END OF MARCH 2013
S.No.
District
Packages /Works
entrustedStatus of Works
Fin
al Q
ual
ity
Au
dit
repo
rts
subm
itte
d Total Visits up toMarch'13
Tota
l No.
of
QC
test
s do
ne
NCRs
Au
dit
Rep
orts
Iss
ued
Envi
ron
men
tal &
Soc
ial
Rep
orts
Iss
ued
Elec
tric
al R
epor
tsIs
sued
PR
R&
B
Star
ted
Not
Sta
rted
Del
eted
Pro
gres
s
Com
plet
ed
Civ
il Si
teEn
gin
eers
Env
& S
ocia
lTe
am
Elec
tric
alEn
gin
eers
Issu
ed
clos
ed
Pen
din
g
1 Srikakulam 16 5 21 0 0 6 15 10 524 80 15 1614 54 54 0 86 76 4
2 Vizianagaram - 3 3 0 0 1 2 2 82 15 - 521 3 3 0 11 12 -
3 Visakhapatnam 21 - 20 1 0 6 14 14 505 69 37 2585 25 25 0 86 61 11
4 East Godavari 13 - 12 0 1 3 9 8 695 49 17 1257 28 28 0 65 39 5
5 West Godavari 10 - 10 0 0 0 10 10 494 50 - 349 20 20 0 62 47 -
6 Krishna 8 - 8 0 0 0 8 8 304 38 - 88 3 3 0 43 29 -
7 Guntur 15 2 17 0 0 2 15 1 426 69 - 6668 14 14 0 65 48 -
8 Prakasam 23 1 24 0 0 0 24 12 470 76 20 1961 36 36 0 132 74 10
9 Nellore 26 - 26 0 0 2 24 23 369 104 - 1238 32 32 0 136 72 -
Total 132 11 141 1 1 20 121 88 3869 550 89 10281 215 215 0 686 458 30
Page 10 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN SRIKAKULAM DISTRICT AT THE END OF MARCH-2013
Category
Packages allottedunder Phase - 1
Names of works under eachpackage
AgreementNo. / Date Work Status Remarks
RHB
NCRMP/B-W/AP/RHB/PRED/
01/Santhabommali/003
Road from DPN R&B road toUddandapalem
/2010-11, Dt.30.04.2011 Work completed working estimate approval not received
Road from K. Umilada Junction toKoduru (Link Road)
/2010-11, Dt.30.04.2011 Work completed working estimate approval not received
Road from Borubhadra, Malagam toKollipadu via Seepuram, Gantapeta
/2010-11, Dt.30.04.2011 Work completed EOAT and working estimate approval not
received
NCRMP/B-W/AP/RHB/PRED/
01/Polaki/006
Road from R&B road Mobagam toDuubakavanipeta viaGajapathinagaram
/2010-11, Dt.30.04.2011 Work in Progress
300 mts CC road completed, GSB layingcompleted, GII spreading progress,
formation width vary from 6.00mts to7.50mts
Road from Talasamudram to DolaRegulator
/2010-11, Dt.30.04.2011
Work stopped dueto insufficientroad width.
400mts length of road was not taken updue insufficient road width on canal bund.Approval of WE with alternative proposal is
awaited. 1.1 KM completed
NCRMP/B-W/AP/RHB/PRED/01/P
olaki/005
Road from R&B road Edulavalasa -Killam to Jonnam viaTalasamudram
/2011-12, Dt.30.04.2011 Work in Progress
BT layer completed from Km 5/670 to Km7/270, and WBM Gr- III metal collection isin progress from Km 5/000 to Km 5/670
Bridges
NCRMP/B-W/AP/Br/R&B/01/
Patnavanipeta/001
Construction of bridge at Km 11/6-8 of NH-5 to PatnavanipetaConnecting Sundarapalem
46/2011, Dt.17.12.2010 Work completed working estimate approval not received
NCRMP/B-W/AP/Br/R&B/01/Surampeta/003
Construction of Minor Bridge at Km12/2-4 of NH-5 to Surampeta Roadvia Naruva, Mentada
45/2010-2011,Dt17.12.2010 Work completed -
NCRMP/B-W/AP/Br/R&B/
01/Bendigedda/004
Construction of High level bridgeacross Bendigedda at KM 4/10 ofPundi-Parlakimidi road
1/2010,Dt.11.11.2010 Work completed working estimate approval not received
Page 11 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/Br/R&B/01/Uppu
gedda/002
Construction of High level bridgeacross Uppugedda at KM 7/6 ofSrikakulam muncipal limits toPukkalapeta via Killipalem inSrikakulam Dt, A.P.
47/2010-2011,Dt17.12.20
10Work in Progress Foundation completed, Shuttering for
Aboutment and Piers is in progress
RoadsNCRMP/B-
W/AP/RD/R&B/01/Nowpada/006)
Improvesments Naupada-Venkatapuram road from0/0to15/0km
43/2010-11,17.12.2010 Work completed Working Estimates approved but ATRs are
pending
RCS
NCRMP/B-W/AP/RCS/PRED/01/V.
KOTTURU/002
Road from NP road to URKpuram G.o rt No 451 dt06.04.2010 Work completed Working Estimates approved but ATRs are
pendingRoad from Deppuru, Bahadapalliroad to Onkuluru & to cycloneshelter
G.o rt No 451 dt06.04.2011 Work completed Working Estimates approved but ATRs are
pending
Road from R&B road toDevunthalada
G.o rt No 451 dt06.04.2012 Work completed Working Estimates approved but ATRs are
pending
Road from pollada to Komarthalada& to cyclone shelter
G.o rt No 451 dt06.04.2013 Work completed Working Estimates approved but ATRs are
pending
NCRMP/B-W/AP/RCS/PRED/01/E
TCHERLA/005
Road from Koyyam R&B Road toMoosavanipeta
G.o rt No 451 dt06.04.2010 Work completed
Road from Mentada to Dovupeta G.o rt No 451 dt06.04.2010 Work completed
Road from Kotcherela road toKollibhemavaram & cyclone shelter
G.o rt No 451 dt06.04.2010 Work completed
Road from Kotcherla road toPathasundarapalem
G.o rt No 451 dt06.04.2010 Work completed
MPCSNCRMP/B_W/AP/MPCS/PRED/01/Santhabom
malli/005
Construction of Cyclone shelter atKollipadu
G.o rt No 451 dt06.04.2010 Work in Progress Silt floor level slab completed. First floor
slab shuttering is in progress
Construction of Cyclone Shelter atRunku
G.o rt No 451 dt06.04.2010 Work in Progress 1st floor Slab Shuttering for concrete in
progress
Page 12 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN VIZIANAGARAM DISTRICT AT THE END OF MARCH-2013
Category Packages allottedunder Phase - 1 Names of works under each package Agreement
No. / DateWorkStatus Remarks
Bridges
NCRMP/B-W/ AP/ Br/R&B/ 02/Puligadda/
007
Construction of Minor Bridge at Km. 7/2 nearPuligedda of Konada – Ramatheertham R&B Road to
Konathalapalem via Yerukonda, Pasupam,Kollayavalsa (Z.P. Road)
31/2010-2011Dt.
01.12.2010
Workcompleted
NCRMP/B-W/ AP/ Br/R&B/ 02/
Chakaligadda /008
Construction of Minor Bridge at Km 15/2 nearChakaligadda of Konada Ramatheertham R&B road to
Konathalapalem (via) Yerukonda, Pasupam,Kollayavalsa (ZP Road)
34/2010-2011Dt.
08.12.2010
Workcompleted
working estimate approvalnot received
RoadNCRMP/B-
W/AP/RD/R&B/ 02/Konada/009
Improvements to Road from Konada Ramatheertham(R&B) Road to Konathalapalem (Via) Pasupam,
Yerukonda, Kollayavalsa from Km 12/0 to 16/5 (Km0/0 to 4/0 i.e. up to NH-5 crossing)
33/2010-2011Dt.
08.12.2010
Workcompleted
Page 13 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF TOTAL WORKS IN VISAKHAPATNAM DISTRICT AT THE END OF MARCH-2013
Category
Packages allottedunder Phase - 1 Names of works under each package Agreement No. /
Date Work Status Remarks
MPCS
NCRMP/B-W/AP/MPCS/PRED
/03/Payakaraopeta/003
Construction of cyclone shelter atGajapathinagaram
/2011-12, Dt.03.10.2011
Nearingcompletion
expected to be completedby 30.03.2013
Construction of cyclone shelter atRatnayampeta
/2011-12, Dt.03.10.2011
Nearingcompletion
expected to be completedby 30.03.2013
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cyclone shelter atPatimeeda
/2011-12, Dt.03.10.2011 work in progress finishing stage
Construction of cyclone shelter atMullaparra
/2011-12, Dt.03.10.2011 work in progress finishing stage
Construction of cyclone shelter atBangarampeta
/2011-12, Dt.03.10.2011 work in progress finishing stage
NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004
Construction of cyclone shelter atVenkayyapalem
/2011-12, Dt.03.10.2011 work in progress Slabs completed, brick
work to be taken up
NCRMP/B-W/AP/MPCS/PRED/03/Parawada/001
Construction of cyclone shelter atThikkavanipalem
/2011-12, Dt.07.10.2011
Work not starteddue to siteproblem
-
RCS
NCRMP/B-W/AP/RCS/PRED
/03/Anandapuram/001Road from NH-5 to Ramarayadupalem /2011-12, Dt.
15.09.2011 Work completed
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002
Road from R & B road to Rajakoduru /2011-12, Dt.15.09.2011 Work completed
Road from R & B road to Kattubolu toMarripalem
/2011-12, Dt.15.09.2011 Work completed
Page 14 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from R & B road to Krishnampalem /2011-12, Dt.15.09.2011 Work completed
NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003
Road from R&B road to Pedatheernala toChinatheernala
/2011-12, Dt.15.09.2011 Work completed
Road from Upmaka Rajayyapeta R&B roadto Janakayyapeta
/2011-12, Dt.15.09.2011 Work completed
RHB
NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001
Road from Vempudi to Patimeeda /2010-11, Dt.11.01.2011 Work completed
Road from R&B road to Mullaparra up toBeach end
/2010-11, Dt.27.01.2011 Work completed
NCRMP/B-W/AP/RHB/PRED/
03/Anandapuram/003
Road from R&B B.P Kallalu toMatchvanipalem
/2010-11, Dt.10.03.2011 Work completed
NCRMP/B-W/AP/RHB/PRED/03/Paravada/004
Road from R & B road toPothurajanapalem
/2010-11, Dt.28.03.2011 Work completed
Road from R & B road to Jalaripeta /2010-11, Dt.28.03.2011 Work completed
NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006
Road from R & B road to Venkayyapalem /2010-11, Dt.11.01.2011 Work completed
NCRMP/B-W/AP/RHB/PRED/
03/Atchutapuram/007
Road from R&B road to Ava- Somavaram /2011-12, Dt.27.04.2011 Work completed
Road from R&B Road to Avarajam /2011-12, Dt.27.04.2011 Work completed
Page 15 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF TOTAL WORKS IN EAST GODAVARI DISTRICT AT THE END OF MARCH-2013
Category
Packages allottedunder Phase - 1
Names of works under eachpackage
AgreementNo. / Date
WorkStatus Remarks
RCS
NCRMP/B-W /RCS/PRED/04/Karapa/001
Approach Road to cyclone Shelter atAdivipudi
32/2011-12Dt:20.05.2011
Workcompleted -
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Road toP.Chodipallipeta CS
73/2011-12Dt:07.09.2011
Workcompleted -
NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004
Road from R&B Road toK.Chodipallipeta CS
73/2011-12Dt:07.09.2011
Workcompleted -
NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004
Road from R&B Road to HukumpetaCS
73/2011-12Dt:07.09.2011
Workcompleted -
NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/0
03
Road from R&B Road toChinaraghavulapeta Cyclone Shelter
74/2011-12Dt: 23.09.2011
Workcompleted Working Estimates & ATRs are pending
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Road to GaddipetaCS
73 /2011-12Dt:07.09.2011
Workcompleted -
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Road to DanavaipetaCS
73 /2011-12Dt:07.09.2011
Workcompleted -
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Road toG.Musalayyapeta CS
73/2011-12Dt:07.09.2011
Workdeleted -
RHB NCRMP/B-W/AP/RHB/PRED/04/Karapa/001
Road from Gurjanapalli toBandulavaripalem
24/2011-12Dt:27.04.2011
Workcompleted -
Page 16 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/
Road from PR roads toDasarivanipeta and to Cyclone
Shelter
18/2011-12Dt:27.04.2011
Workcompleted -
MPCSNCRMP/B-
W/AP/MPCS/PRED/ 04/Uppalaguptam/002
Construction of Cyclone Shelter atPedaraghavulapeta of Uppalaguptam
Mandal
78/2011-12Dt:17.10.2011
Work inProgress
Terrace floor Beam and slabCompleted. Stilt floor & First floor
Plastering and Brick work is inprogress.
MPCS
NCRMP/B-W /AP/MPCS/PRED/04/ Thondangi/001
Construction of Cyclone Shelter atLakshmanudipeta in Thondangi
77/2011-12Dt:07.09.2011
Work inProgress
Finishing Stage, white wash inprogress
NCRMP/B-W /AP/MPCS/PRED/ 04/Thondangi/001
Construction of Cyclone Shelter atAvulamanda
77/2011-12Dt:07.09.2011
Work inProgress
Finishing Stage, white wash inprogress
Page 17 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN WEST GODAVARI DISTRICT AT THE END OF MARCH-2013
Category
Packages allotted underPhase - 1 Names of works under each package Agreement
No. / DateWorkStatus Remarks
RHB
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/
001
Road from NH 214 A at Ranga Statue center to Harijanawadaof Kalipatnam (E) (Mogalthuru Mandal)
16 /2011-12Dt.27.04.2011
Workcompleted -
R&B road at Panchayat Office to Pulaparthivarithota viaBadava (Mogalthuru Mandal W.G.Dist.)
Workcompleted -
Mogalthuru Vempa R&B Road at Uchintha Kalava Bridge toGogulamma Harijanapeta (Mogalthuru Mandal)
Workcompleted -
From Narsapur Mogalthuru R&B road to Dayadaldaspeta viaVenkateshwara Swamy temple (Mogalthuru Mandal)
Workcompleted -
Road from NH 214 A road to Harijanapeta of Kothota Workcompleted -
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/
002
R&B road to Indira Nagar (via) Pochamma temple (NarsapurMandal)
21 /2011-12Dt.09.05.2011
Workcompleted -
Road from R&B road to Pedalanka (Narsapur MandalW.G.Dist.)
Workcompleted -
Road from LB Cheria CC road to Chillapalem of LB Cheria. Workcompleted -
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003
From A-U R&B Road to Satyanarayanapuram (Kalla Mandal) 25/2011-12Dt.26.05.2011
Workcompleted -
From A-U R&B Road to Mekaladibba (Kalla Mandal W.G.Dist.) Workcompleted -
Page 18 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN KRISHNA DISTRICT AT THE END OF MARCH-2013
Category Packages allotted underPhase - 1 Names of works under each package Agreement No.
/ Date Work Status Remarks
RHB
NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/001
Road connecting R&B road throughGantlammapalem
8/2011-12/27.04.2011 Work completed -
NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002
Road from R & B Road to B.V Thota 7/2011-12/27.04.2011 Work completed -
Road from Potalapalem Z.P road toChikativanipalem
7/2011-12/27.04.2011 Work completed -
NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003
Road from Intheru R&B Road to Rangaraopet 9/2011-12/27.04.2011 Work completed -
Road from R&B road to Cyclone Shelter atChandala
9/2011-12/27.04.2011 Work completed -
RCS NCRMP/B-W /AP/RCS/PRED/06/Machilipatnam/001
Road from Bhogireddypalli R&B Road toRamakhandam
32/2011-12/Dt.02.09.2011 Work completed -
Road from R&B Road Chinnapuram toGundupalem
32/2011-12/27.04.2011 Work completed -
Road from Potlapalem Z.P road to Pothepalli. 32/2011-12/Dt.02.09.2011 Work completed -
Page 19 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN GUNTUR DISTRICT AT THE END OF MARCH-2013
Category
Packages allottedunder Phase - 1 Names of works under each package Agreement
No. / DateWorkStatus Remarks
RHB
NCRMP/B-W/AP/RHB/PRED/07/Karlapalem/001
Road to Kesavapuri ST Colony 7/2011-1227.04.2011
Workcompleted
working estimate approval notreceived
NCRMP/B-W/AP/PRED/07/Nagaram/002
R/f R&B Road to Mohammad Alipalem8/2011-1227.04.2011
Workcompleted
working estimate approval notreceived
R/f R&B Road to Katurivaripalem Workcompleted
working estimate approval notreceived
Bridges
NCRMP/B-W/AP/Br/R&B/07/Bapatla/010
Reconstruction of High-level Bridge @Km5/2 ofBapatla-Suryalanka Road across perali drain
79/2010-111.12.2010
Workcompleted -
NCRMP/B-W/AP/Br/R&B/07/Bapatla/011
Reconstruction of HLB @Km2/4 of Bapatla-Pandurangapuram Road across perali drain
78/2010-111.12.2010
work inprogress Approaches is in progress
RCS
NCRMP/B-W/AP/RCS/PRED/07/PV Palem/001
Road from R&B road to Mandevaripalem
2011-20121.11.2011
Workcompleted
working estimate approval notreceived
Road from R&B Road Alluru to Yadavapalem work inprogress
From Km 0.071 to km 0.125 andkm 0.373 to km 1.046 CC
completed. From km 0.125 km0.373 CC road to be done
NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002
Road from Ganapavaram R&B Road toPedamarpuvaripalem 2011-2012
1.11.2011
Workcompleted
working estimate approval & ATRnot received
Road from R&B Road to Chinapuluguvaripalem Workcompleted
working estimate approval & ATRnot received
Page 20 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
From R&B road to Yaramvaripalem Workcompleted
working estimate approval & ATRnot received
Road from R&B Road to Pedagollapalem CS Workcompleted
working estimate approval & ATRnot received
Pedagollapalem PR road to Bonthagoralapalem Workcompleted
working estimate approval & ATRnot received
RCS
NCRMP/B-W/AP/RCS/PRED/
07/Nizampatnam/003
Road from R&B Road to Gurunadhanagar
2011-201217.10.2011
Workcompleted
working estimate approval & ATRnot received
Road from R & B Road to Adavala H/OBavajipalem
Workcompleted
working estimate approval notreceived
Road from R & B Road to Atlavaripalem Workcompleted
working estimate approval & ATRnot received
NCRMP/B-W/AP/RCS/PRED/07/Bapatla/004
Road from R & B Road to Hanumathanagar2011-201227.10.2011
Workcompleted
working estimate approval notreceived
Road from R & B Road to Adarsh nagar Workcompleted
working estimate approval notreceived
Page 21 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN PRAKASAM DISTRICT AT THE END OF MARCH-2013
Category
Packages allottedunder Phase - 1
Names of works under eachpackage
Agreement No. /Date
WorkStatus Remarks
BRIDGES
NCRMP/B-W/AP/Br/R&B/08/ Kanaparthy/012
Construction of High level Bridge at Km16/10 of Naguluppapadu – Kanaparthyroad
76/2010-11Dated1/12/2010
Workcompleted
Work completed & Final bill paid. Quadrantialrevetment & slopes are damaged duringNeelam cyclone, Because of its height
retaining walls and revetment is necessary.Which are not provided in the original
agreement. The Field officers informed that aseparate estimate for the protection workswould be got sanctioned under state funds
for the slope protection works.
RHB
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001
Road from Pakala ZP Road toAulavaripalem Cyclone shelter
Dated25.04.2011
Workcompleted -
Road from R&B Road to Somarajupalli Dated25.04.2011
Workcompleted -
Road from R&B road to Narravaripalem Dated25.04.2011
Workcompleted -
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002
Road from NH5 to Mulaguntapadu dated10/02/2011
Workcompleted working estimate approval not received
Road from R&B road toChalivendradibba
dated -10/02/2011
Workcompleted working estimate approval not received
Road from Pakala R&B road toMosanaladinne
dated10/02/2011
Workcompleted working estimate approval not received
Road from R&B road to BinginapalliHarijanawada Cyclone Shelter
dated10/02/2011
Workcompleted working estimate approval not received
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003
Road from R&B Road Allur to M T Rajucolony
Dated27/04/2011
Workcompleted -
Page 22 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004
Road from KEM R&B Road toSankuvarigunta
Dated27/04/2011
Workcompleted -
Road from KEM R & B Road toPullareddypalem
Dated27/04/2011
Workcompleted -
NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07
Road from MC Road to SubbarayuduSatram
dated27/04/2011
Workcompleted -
RHB
NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08
Road from R&B road Tettu toRamayapatnam
dated27/04/2011
Workcompleted -
NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09
Road from R&B road Pellur toVasepallipadu
dated16/03/2011
Workcompleted -
NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10 Road from R&B road to Kesupalem dated
19/04/2011Work
completed -
RCS
NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001
Road from R&B road to Vijayanagarcolony cyclone shelter
dated30.09.2011
Workcompleted working estimate approval not received
Road from NH road to Challareddypalem Workcompleted working estimate approval not received
Road from R&B road to jeevarakshnagar colony cyclone shelter
Workcompleted working estimate approval not received
Road from R&B road to Ramnagarcolony cyclone shelter
Workcompleted working estimate approval not received
Road from R&B road to cyclone shelterat Mankenavaripalem
Workcompleted working estimate approval not received
NCRMP/B-W/AP/RCS/PRED/08/Chirala/002
Road from R&B Road toKeerthivaripalem cyclone shelter dated
27.08.2011
Workcompleted working estimate approval not received
Road from R&B Road to Devinuthulacyclone shelter of Chirala Mandal
Workcompleted working estimate approval not received
Page 23 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
MPCS
NCRMP/B-W/APMPCS/PRED/08/Ulavapadu/001
Chakicharla cyclone shelter in UlavapaduMandal
Workcompleted -
NCRMP/B-W/APMPCS/PRED/08/NG Padu/003
Kanaparthy cyclone shelter inNaguluppapadu Mandal prakasamdistrict
Workcompleted working estimate approval not received
Page 24 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN SPSR NELLORE DISTRICT AT THE END OF MARCH-2013
Category
Packages allotted underPhase - 1 Names of works under each package
Agreement No. /Date
Work Status Remarks
RHB
NCRMP/B-W/AP/RHB/PRED/09/
BOGOLO/RHB/001
1. Road from NH5 to Sambasiva Puram
1/19/2011
Work completed -
Road from 9/6 of Juvvaladinne R&B Road to 11/0 ofJuvvaladinne R&B Road Via Venkateshpalem Work completed -
NCRMP/B-W/AP/RHB/PRED/09/BOGOLU/002
Road from 1/6 of Zuvvaladinne R&B Road to TellaguntaKM to 2/720 07.02.2011 Work completed -
NCRMP/B-W/AP/RHB/PRED/09/
CHITTAMURU/003
Road from R&B Road to Muttambeka Via Pittuvanipalla18.01.2011
Work completed -
Road from R&B Chittamur to Soma Samudram Work completed -
NCRMP/B-W/AP/RHB/PRED/09/RHB/KAVALI
/004
Road from5/8 of Chennayapalem Road to Gummadibandla
17.01.2011
Work completed -
Road from pedattapupalem R&B road to ChennayapalemH.wada Work completed -
Road from K.T R&B Road to Alliguntapalem Work completed -
NCRMP/B-W/AP/RHB/PRED/09/
VIDAVALURU/005
Road from KT R&B road to Alaganipadu to Vavilla
27.04.2011
Work completed working estimateapproval not received
Road from R&B road Kancharapalem HW toAlaganipadu. Work completed working estimate
approval not received
NCRMP/B-W/AP/ PRED/09/MUTHUKUR/RHB/ 006 Road from R&B road to Patuvari Kandriga 25.4.11 Work completed -
NCRMP/B-W/AP/RHB/PRED/09/
V.CHALEM/RHB/ 007
Road from Survepalli-Pudiparthi road to Srikanth Colony
27.04.2011
Work completed -
providing BT Surface to the road from R&B road toEdagali Kandriga Work completed -
Page 25 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/09/Allur/009
Road from R&B road Alluru to Galidibbalu (via)Chukavani dibba 24.01.2011 Work completed -
RHBNCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012
Ring Road to TP Gudur- Salipeta R & B Road via CSPuram and Mandapam Vill. 19.05.2011
Work completed -
Road from R & B Road C S Puram to Sivaramapuram Work completed -
RCS
NCRMP/B-W/AP/PRED/09/kota/RCS /001
Road from R&B road to A.S PURAM10.05.2011
Work completed -
Road from GD Road to Vavilla Palem Work completed -
NCRMP/B-W/AP/ PRED/09/MUTHUKUR/RCS/ 002
Road from R&B Road kappaladoruvu to bandla PalemH.wada 21.04.2011 Work completed -
NCRMP/B-W/AP/PRED/09/Chillakur/RCS/004 Road from Kakuvaripalem R&B road to Vellapalem 23.05.2011 Work completed -
NCRMP/B-W/AP/RCS/PRED/09/
T.P.GUDUR/005
Road from7/2 M.C Road to VenkannapalemPattuapalem 17.05.2011 Work completed -
NCRMP/B-W/AP/RCS/PRED/09/ KAVALI/006
Road Connecting R&B Road through Voturu Village inSPSR Nellore District. 21.09.2011 Work completed working estimate
approval not received
NCRMP/B-W/AP/RCS/PRED/09/ KAVALI/007
Road from Kotha satram R&B to Indrsanagar (via)Thumalapenta palam, Patharavadu palam, Ramudupalam, Karaduvari palam & Sreeramapuram
29.08.2011 Work completed -
NCRMP/B-W/AP/ PRED/09/D.V.SATRAM/RCS/ 008
Road from R&B road to Sullurpeta Mallam toBerijengalapalli cyclone shelter 09.05.2011 Work completed -
NCRMP/B-W/AP/RCS/PRED/ 09/TADA/009
Providing BT road to Pedapannamgadu in Tada Mandal14.09.2012
work in progress Road furniture isbalance
Road from @ 56/8 to C.K road to Periyavettu kuppamcyclone shelter work in progress Sub grade work in
progress
Page 26 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
5.0 District wise status of tests conducted by TPQA:
Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various
stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are
carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of
tests conducted in the field till end of December 2012 are presented.
Summary of QC Tests - Up to 31.03.2013
S.No. District
No. TestsConductedduring the
Month
Total no. of Tests Cumulative TestsDone
Total no. of Tests up to31.03.2013
Passed Failed Passed Failed
1 Srikakulam 51 51 0 1614 1608 6
2 Vizianagaram 14 14 0 521 521 0
3 Visakhapatnam 132 132 0 2585 2539 46
4 East Godavari 48 48 0 1257 1257 0
5 West Godavari 0 0 0 349 349 0
6 Krishna 0 0 0 88 88 0
7 Guntur 9 9 0 668 657 11
8 Prakasam 6 6 0 1961 1957 4
9 Nellore 23 23 0 1238 1217 21
Total 283 283 0 10281 10193 88
Page 27 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
6.0 Details of Final QARs & Quality Control Audit Reports Submitted during this 3 months:
6.1 Details of Final QARs & QCA Reports Submitted during the month of January-2013:
a) QCRs Submitted
Package Number Name of Work District
NCRMP/BW/AP/RHB/PRED/09/vidavalur/005
Road from R&B road Kancharapalem HW toAlaganipadu of SPSR Nellore Dt. Nellore
NCRMP/B-W/AP/RCS/PRED/08/VETAPALEM/001
Road from NH to Challareddypalem InPrakasam District Prakasam
NCRMP/BW/AP/RCS/PRED/07/Karlapalem/002.
Road from Pedagollapalem PR Road toBonthagorlapalem Prakasam
NCRMP/B-W/AP/RCS/PRED/ 07/PVPalem/001
Road from R&B Road Alluru to Yadavapalemin Guntur DT. Guntur
NCRMP/B-W/AP/RCS/PRED/09/TADA/009
Providing BT Road to Peda Pannam Gadu inTada Mandal of Nellore Dt. Nellore
NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003
Providing Road from R&B B.P Kallalu toMatchvanipalem in Visakhapatnam Dt. Visakhapatnam
NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001
Providing B.T to the Road from NH-5 toRamaraidupalem in Visakhapatnam Dt. Visakhapatnam
NCRMP/BW/AP/RHB/PRED/09/vidavalur/005
Road from R&B road Kancharapalem HW toAlaganipadu of SPSR Nellore Dt. Nellore
NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of cyclone shelter at Kollipadu inSanthabommali Mandal in Srikakulam Dt. Srikakulam
b) Final QARs submitted
NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003
Road from Interu ZP road to Rangaraopeta inKrishna Dt. Krishna
NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001
Road from Bhogireddypalli R&B road toRamakhandam in Krishna Dt. Krishna
NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001
Road from Potlapalem ZP road to Potepalli inKrishna Dt. Krishna
NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002
Road from R&B road to B.V.Thota in KrishnaDt. Krishna
NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001
Road from Chinnapuram R&B road toGundupalem in Krishna Dt. Krishna
NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/001
Road connecting R&B road throughGantalammapalem in Krishna Dt. Krishna
Page 28 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003
Road from R&B road to Cyclone shelter atChandala in Krishna Dt. Krishna
NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002
Road from Potlapalem Z.P road toChikativanipalem in Krishna Dt. Krishna
NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001
R&B Road at Panchayat office toPulaparthivarithota via Badava of Mogalthuru
Mandal in West Godavari Dt.West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narasapur/002
Road from R&B road to Pedalanka of NarsapurMandal in West Godavari District. West Godavari
NCRMP/B-W/AP/RHB/ PRED/05/Narasapur/002
R&B road to Indira Nagar (via) Pochammatemple of Narsapur Mandal in West Godavari
Dt.West Godavari
NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001
Road from NH 214 A road to Harjanawada ofkothota of Mogalthuru Mandal in West
Godavari Dt.West Godavari
NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001
Road from NH 214 A at Ranga statue centerto Harijanawada of Kalipatnam (E) of
Mogalthuru MandalWest Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narasapur/002
Road from LB Cherla CC road to Chillapalemof LB Cherla of Narsapur Mandal in West
Godavari Dt.West Godavari
NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001
Mogaltur Vempa R&B Road at Uchintha kalavaBridge to Gogulamma Harijanapeta of
Mogalthuru Mandal in West Godavari Dt.West Godavari
NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001
From Narsapur Mogaltur R&B road toDayaldaspeta via Venkateshwara SwamyTemple of Mogalthuru Mandal in West
Godavari Dt.
West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003
From A-U R&B Road to Satyanarayanapuramof Kalla Mandal in West Godavari Dt. West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003
From A-U R&B Road to Mekaladibba of KallaMandal in West Godavari Dt. West Godavari
6.2 Details of Final QARs & QCA Reports Submitted During the Month of February-2013:
a) QCRs submitted
Package Number Name of Work District
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cyclone shelter atBangarrampeta in Nakkapalli Mandal in
Visakhapatnam Dt.Visakhapatnam
NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004
Construction of cyclone shelter atVenkayypalem in Rambilli in Visakhapatnam
Dt.Visakhapatnam
Page 29 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/BW/AP/BR/R&B/001/Uppugedda/002
Construction of High level bridge acrossUppugedda at KM 7/6 of Srikakulam Municipal
limits to Pukkalapeta via KillipalemSrikakulam
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cyclone shelter at Mullaparrain Nakkapalli Mandal. Visakhapatnam
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001
Construction of Cyclone Shelter atLakshamanudipeta in Thondangi Mandal, East
Godavari District.East Godavari
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001
Construction of Cyclone Shelter atAvulamanda in Thondangi Mandal, East
Godavari District.East Godavari
NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002
Construction of Cyclone Shelter atPedaraghavulapeta in Uppalaguptham Mandal,
East Godavari District.East Godavari
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cyclone shelter at Patimeedain Nakkapalli Mandal, Visakhapatnam District. Visakhapatnam
NCRMP/B-W/AP/RCS/PRED/09/Kavali/006
Road Connecting R&B Road through VotturuVillage in SPSR Nellore District SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/TADA/009
Providing BT Road to Peda Pannam Gadu inTada Mandal in SPSR Nellore District SPSR Nellore
NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005
Road from R&B road Kancharapalem HW toAlaganipadu in SPSR Nellore District SPSR Nellore
NCRMP/B-W/AP/Br/R&B/07/Bapatla/010/2010
Reconstruction of HLB@Km 5/2 of Bapatla-Suryalanka Road across Perali drain. Guntur
b) Final QARs submitted
NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006
Providing BT surface to the Road from R&Broad to Venkayyapalem in Rambilli Mandal Visakhapatnam
NCRMP/B-W/AP/RHB/PRED/08/Tangatur/10
R&B Road to Kesupalem in Tangatur MandalPrakasam District. Prakasam
NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09
Road from R&B Road Pellur to Vasepallipadu-Tangutur (M) Prakasam
NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/007
Road from M.C Road to Subbarayudu Satramin Ulavapadu Mandal Prakasam
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003
Road from 7/2 M.C Road to Venkannapalampattapupalem of T.P Gudur in Nellore Dt. SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/KAVALI/007
Road from Kotha satram R&B to Indrsanagar(via) Thumalapenta palam, Patharavadu
palam, Ramudu palam, Karaduvari palam &Sreeramapuram
SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/D.V.Satram/008
Road from R&B Road Sullurpeta-Mallam toBerijangalapalli Cyclone Shelter SPSR Nellore
Page 30 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/09/T.P.GUDUR/012
Ring Road to T.P.Gudur-Salipeta R&B Road viaC.S.Puram and Mandapam Village. SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001
Road from R&B road to Narravaripalem inPrakasam District Prakasam
NCR MP/B-W/AP/RHB/PRED/09/Bogolu/002
Road from 1/6 of Zuvvaladinne R&B Road toTellagunta SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/008
Road from R&B Road Tettu to Ramayapatnamin Ulavapadu Mandal in Prakasam District Prakasam
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001
Road from R&B Road to Somarajupalli inPrakasam District Prakasam
NCRMP/B -W/AP/RHB/PRED/09/Bogolu/001
Road from 9/6 of Juvvaladinne R&B Road to11/0 of Juvvaladinne R&B Road via
Venkateshpalem of SPSR Nellore DistrictSPSR Nellore
NCRMP/B-W/AP/RHB/PRED/08/Singarayakonda/001
Road from Pakala ZP Road to AulavaripalemCyclone Shelter Prakasam
NCRMP/B -W/AP/RHB/PRED/09/Bogolu/001
Road from NH5 to Sambasivapuram in SPSRNellore District SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/Kota/001
Road from R&B road to A.S.Puram in SPSRNellore District SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003
Road from R&B Road to Allur to M.T.Rajucolony in Kothapatnam Mandal Prakasam
NCRMP/B-W/AP/RCS/PRED/09/Kota/001
Road from GD road to Vavillapalem in VakaduMandal. SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/T.P.GUDUR/012
Road from R&B C.S.Puram to Siva RamaPuram of SPSR Nellore District SPSR Nellore
NCRMP/BW/AP/RH/PRED/03/Nakkapalli/001
Providing Bt Surface To The Road FromVempudi To Patimeeda in Nakkapalli Mandal. Visakhapatnam
NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003
Road from R&B road to Pedatheernala toChinatheernala in Visakhapatnam District Visakhapatnam
NCRMP/B-W/AP/RCS/PRED/09/Chillakur/004
Road from Kakuvaripalem R&B Road toVellapalem in Chillakur Mandal SPSR Nellore
NCRMP/BW/AP/RHB/PRED/09/V.Chalem/007
Providing BT Surface to the road from R&Broad to Edagalikandriga. SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004
KEM R&B Road to Pullareddypalem villageKothapatnam Mandal in Prakasam District Prakasam
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004
Road from KEM R&B Road to Sankuvariguntavillage Kothapatnam Mandal Prakasam
NCRMP/BW/AP/RHB/PRED/09/V.Chalem/007
Providing BT Surface to the Road fromSurvepalli-Pudiparthi road to Srikanth Colony. SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003
Road from Upmaka Rajayyapeta R &B Road toJanakayyapeta Visakhapatnam
Page 31 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/09/Chittamuru/003
Road from R&B to Muttembaka (via)Pittuvanipalli in SPSR Nellore District SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Chittamuru/003
Road from R&B Chittamuru to SomaSamudram in SPSR Nellore District SPSR Nellore
NCRMP/BW/AP/RHB/PRED/09/Muthukur/006
Road from R&B Road to Patuvari Kandriga inSPSR Nellore District SPSR Nellore
NCRMP/B-W/AP/MPCS/PRED/08/Ulavapadu/001
Construction of Cyclone shulter at Chakicherlain Ulavapadu mandal in Prakasam District Prakasam
NCRMP/B-W/AP/RHB/PRED/09/Allur/009
Road from R&B road Alluru to Galidibbalu(via) Chukkavani dibba of Nellore Dt. SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/03/Paravada/004
Road from R&B Road to Jalaripeta of ParvadaMandal in Visakhapatnam District Visakhapatnam
NCR MP/B -W/AP/RCS/PRED/09/Muthukur/002
Road from R&B Road Kappaladoruvu toBandlapalem H.wada SPSR Nellore
NCRMP/B-W/AP/MPCS/PRED/08/Ulavapadu/001
Construction of Minor bridge At KM 12/2-4 ofNh-5 to Surampeta road via Naruva, Mentada Srikakulam
NCRMP/B-W/AP/RHB/PRED/03/Paravada/004
Road from R&B Road to Pothurajanapalem ofParavada Mandal in Visakhapatnam District Visakhapatnam
NCRMP/B-W/AP/Br/R&B/07/Bapatla/010/2010
Reconstruction of Hlb@Km 5/2 of Bapatla-Suryalanka Road Across Perali Drain Guntur
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002
Providing BT surface to the Road from R&BRoad to Krishnampalem in Rambilli Mandal Visakhapatnam
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002
Providing BT surface to the Road from R&BRoad to Kattubolu to Marripalem in Rambilli
MandalVisakhapatnam
NCRMP/BW/AP/RHB/PRED/03/Nakkapalli/002
Providing BT Surface to the Road from R&BRoad to Mullaparra up to Beach End in
Nakkapalli MandalVisakhapatnam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005
Road from Kotcherla road to Kollibhemavaram& Cyclone Shelter of Ranasathalam Mandal Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005
Road from Kotcherla road toPatasundarapalem of Ranasathalam Mandal Srikakulam
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002
Providing BT surface to the Road from R&BRoad to Raja Koduru in Ramibilli Mandal Visakhapatnam
NCRMP/B-W/AP/RHB/PRED/03/Achutapuram/007
Road from R & B Road to Ava Rajam inAchutapuram Mandal Visakhapatnam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005
Road from Koyyam R&B Road toMoosavanipeta in Etcherla Mandal Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005
Road from Mentada to Dovupeta inRanasathalam Mandal of Srikakulam Dt. Srikakulam
Page 32 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
6.3 Details of Final QARs & QCA Reports Submitted During the Month of March-2013:
a) QCRs submitted
Package Number Name of Work District
NCRMP/BW/AP/RCS/PRED/07/Karlapalem/002
Road from Ganapavaram R&B Road toPedamarpuvaripalem Guntur
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002
Road from NH5 to Mulaguntapadu village inSingarayakonda Mandal Prakasam
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002
Road from Pakala R&B road to Mosanaladinne inSingarayakonda Mandal Prakasam
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002
Road from R&B Road to Chalivendradibba inSingarayakonda Mandal Prakasam
NCRMP/B-W/AP/RHB/PRED/09/KOTA/023
Road from at km 22/5 of Yamadinnepalem roadto Gunnampadia of Kota Mandal SPSR Nellore
NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of Cyclone Shelter at Runku inSanthabommali Mandal Srikakulam
NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of Cyclone Shelter at Kollipadu inSanthabommali Mandal Srikakulam
NCRMP/B-W/AP/RCS/PRED/ 07/PVPalem/001 Road from R&B Road Alluru to Yadavapalem Guntur
NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/021
Road from Thirumalammapalem R&B road toGajulapalli Koneru of Venkatachalam Mandal SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/TADA/009
Providing BT road to Peda Pannam Gadu in TadaMandal. SPSR Nellore
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001
Construction of Cyclone Shelter at Avulamanda inThondangi Mandal East Godavari
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001
Construction of Cyclone Shelter atLakshamanudipeta in Thondangi Mandal East Godavari
NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002
Construction of Cyclone Shelter atPedaraghavulapeta in Uppalaguptham Mandal East Godavari
NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004
Construction of cyclone shelter at Venkayypalemin Rambilli Mandal Visakhapatnam
NCRMP/B-W/AP/RHB/PRED/09/KOTA/023
Road from at km 22/5 of Yamadinnepalem Roadto Gunnampadia of Kota Mandal SPSR Nellore
b) Final QARs submitted
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004 Road from R&B Road to Danavaipeta East Godavari
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Road to Gaddipeta of ThondangiMandal in East Godavari Dt. East Godavari
Page 33 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Road to Hukumpeta CycloneShelter East Godavari
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Road to K. Chodipallipeta ofThondangi Mandal in East Godavari Dt. East Godavari
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004 Road from R&B Road to P.Chodipallipeta East Godavari
NCRMP/B W/AP/RHB/PRED/09/Kavali/004
Road from pedattapupalem R&B road toChennyapalam H.wada SPSR Nellore
NCRMP/BW/AP/RHB/PRED/09/Kavali/004 Road from KT R&B Road to Alliguntapalem SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/04/Karapa/001
Road from Approach Road to Cyclone Shelter atAdavipudi of Karapa Mandal East Godavari
NCRMP/B-W/AP/RHB/PRED/04/Karapa/001
Road from Gurajanapalli to Bandulavaripalem ofKarapa Mandal East Godavari
NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003
Road from PR Road to Dasarivanipeta and toCyclone Shelter of Katrenikona Mandal East Godavari
NCRMP/B-W/AP/RHB/PRED/09/Kavali/004
Road from 5/8 of Chennayapalem Road toGummadi bandla SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Kavali/004
Road from R&B Road to Ava Somavaram inAchutapuram Mandal Visakhapatnam
NCRMP/B-W/AP/RD/R&B/02/Konada/009
Improvements to Road from KonadaRamatheertham (R&B) Road to Konathalapalem(Via) Pasupam, Yerukonda, Kollayavalasa fromKm 12/0 to 16/5 (Km 0/0 to 4/0 i.e. upto NH-5
crossing).
Vizianagaram
NCRMP/B-W/AP/Br/R&B/02/Puligadda/007
Construction of Minor Bridge at Km. 7/2 nearPuligadda of Konada – Ramatheertham R&B Road
to Konathalapalem via Yerukonda, Pasupam,Kollayavalasa (Z.P. Road)
Vizianagaram
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP road to URK Puram. Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B Road to Devunthalada. Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002
Road from Deppuru, bhadapalli road to Onkuluru& cyclone shelter Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002
Road from Pollada to Komaralthada cyclonicshelter. Srikakulam
NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005
Road from R&B road Kancharapalem HW toAlaganipadu SPSR Nellore
NCRMP/BW/AP/BR/R&B/001/Patnavanipeta/001
Construction of HLB Act KM 11/6-8 of NH-5 topatnavanipeta Road Via Tamada connecting
Sundarapalem.Srikakulam
NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005
Road from R&B road Alaganipadu to Vavilla ofVidavalur SPSR Nellore
Page 34 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
7.0 Details of Environmental and Social Reports Submitted During this 3 Months:
7.1. Details of Environmental and Social Reports Submitted During the Month January 2013:
Package Number Name of Work District
Nil Nil Nil
7.2. Details of Environmental and Social Reports Submitted During the Month February 2013:
Package Number Name of the Work District
NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001 Road from NH-5 to Ramarayadupalem Vishakhapatnam
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R & B road to Rajakoduru. Vishakhapatnam
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B road Kattubolu to Marripalem Vishakhapatnam
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R & B road to Krishnampalem. Vishakhapatnam
NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003
Road from R&B road Pedateernala toChinateernala in Nakkapalli Mandal. Vishakhapatnam
NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003
Road from Upmaka Rajayyapeta R&B Road toJanakayyapeta in Nakkapalli Mandal Vishakhapatnam
NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001 Road from Vempudi to Patimeeda Vishakhapatnam
NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/002
Road from R&B Road to Mulapura up to Beachend. Vishakhapatnam
NCRMP/B-W/AP/RHB/PRED/03/Anandpuram/003 Road from R&B B.P Kallulu to Matchavaniplem. Vishakhapatnam
NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R&B road to Pothurajannapalem. Vishakhapatnam
NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R&B road to Jalaripeta. Vishakhapatnam
NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 Road from R&B road to Venkayyapalem. Vishakhapatnam
NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/007 Road from R&B road to A.Somavaram. Vishakhapatnam
NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/007 Road from R&B road to Avarajam. Vishakhapatnam
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Bangarampeta. Vishakhapatnam
Page 35 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Mulaparra. Vishakhapatnam
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda. Vishakhapatnam
NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cyclone shelter atGajapathinagaram. Vishakhapatnam
NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Ratnayampeta. Vishakhapatnam
NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004
Construction of Cyclone Shelter at Venkayyapalemin Rambilli Mandal. Vishakhapatnam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002
Deppuru Bahadpalli Road to Onkuluru & to CycloneShelter Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 R&B Road to Devunaltada Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Pollada to Komraltada & to Cyclone shelter Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002
Road from Koyyam R&B Road to Moosavanipeta ofSrikakulam Dt. Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Mentada Dovupeta Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005
Road from Kotcherla Road to Kollibheemavaram &Cyclone Shelter Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Kotcherala road to Pathasundarapalem Srikakulam
NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003
of Road from Borubhadra, Malagam to Kollipaduvia Seepuram, Gantapeta Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Santhabommali/003 Road from DPN R&B Road to Udandapalem Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Santhabommali/003
Road from K. Umilada Junction to Koduru(Link Road) Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Polaki/005
Road from R&B Road Edulavalsa Killam to Jonnamvia Talasamudram Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Polaki/006
Road from R&B Road Mobagam toDubbakavanipeta via Gajapatinagram Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Polaki/006 Road from Talasamudram to Dola Regulator Srikakulam
NCRMP/B-W/AP/Br/R&B/01/Patnavanipeta/001
Construction of bridge at Km 11/6-8 of NH-5 toPatnavanipeta Connecting Sundarapalem Srikakulam
NCRMP/B-W/AP/Br/R&B/01/Surampeta/003
Construction of Minor Bridge at Km 12/2-4 of NH-5to Surampeta Road via Naruva, Mentada Srikakulam
Page 36 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/Br/R&B/01/Bendigaada/004
Construction of High level bridge acrossBendigedda at KM 4/10 of Pundi-Parlakimidi Road Srikakulam
NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005 Construction of Cyclone Shelter at Runku Srikakulam
NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005 Construction of Cyclone Shelter at Kollipadu Srikakulam
NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/001
Road from NH 214 A at Ranga Statue Centre toHarijanawada of Kalipatnam (E) West Godavari
NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/001
R&B Road at Panchayat office toPulaparthivarithota via Badava West Godavari
NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/001
Mogaltur Vempa R&B Road at Uchinta KalavaBridge to Gogulamma Harijanapeta West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001
Narsapur mogaltur R&B Road to Dayadaldaspetavia Venkateshwara Swamy Temple West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001
Road from NH 214 A to Harijanapeta of Kothota inWest Godavari District West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002
Road from R&B Road to Indiranagar (Via)Pochamma Temple West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002 Road from R&B Road Pedalanka West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002
Road from LB Cheria CC Road to Chillapalem of LBCheria West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003 Road from A_U Road to Satyanarayanapuram West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003 Road from A_U Road to Mekaladibba West Godavari
NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001
Road from R&B road to cyclone shelter atMankenavaripalem Prakasham
NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001
Road from R&B road to jeevaraksha nagar colonycyclone shelter Prakasham
NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001
Road from R&B road to Vijaynagar colony cycloneshelter. Prakasham
NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001
Road from R&B road to Ramnagar colony cycloneshelter. Prakasham
NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001 Road from NH Road to Challreddypalem. Prakasham
NCRMP/B-W/AP/RCS/PRED/08/Cheerala/002
Road from R&B Road to Devinuthula cycloneshelter. Prakasham
NCRMP/B-W/AP/RCS/PRED/08/Cheerala/002
Road from R&B Road to Keerthivaripalem cycloneshelter. Prakasham
NCRMP/B-W/AP/RCS/PRED/08/S.Konda/001
Road from Pakala ZP Road to AulavaripalemCyclone shelter. Prakasham
Page 37 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RCS/PRED/08/S.Konda/001 Road from R&B Road to Somarajupalli . Prakasham
NCRMP/B-W/AP/RCS/PRED/08/S.Konda/001 Road from R&B Road to Narravaripalem. Prakasham
NCRMP/B-W/AP/RCS/PRED/08/S.Konda/002 Road from NH-5 to Mulgantapadu Prakasham
NCRMP/B-W/AP/RCS/PRED/08/S.Konda/002 Road from R&B Road to Chalivendradibba Prakasham
NCRMP/B-W/AP/RCS/PRED/08/S.Konda/002
Road from R&B Road to Mosanaladinne ofPrakasam Dt. Prakasham
NCRMP/B-W/AP/RCS/PRED/08/S.Konda/002
Road from R&B Road to Binginapalli HarijanwadaCyclone Shelter of Prakasam Dt. Prakasam
NCRMP/B-W/AP/RCS/PRED/08/Kothapatnam/003 Road from R&B Road Allur to MT Raju colony. Prakasam
NCRMP/B-W/AP/RCS/PRED/08/Kothapatnam/004 Road from KEM R&B road to Sankuruvarigunta Prakasam
NCRMP/B-W/AP/RCS/PRED/08/Kothapatnam/004 Road from KEM R&B road to Pullareddypalem Prakasham
NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/07 Road from MC Road to Subarayaudu satram. Prakasam
NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/08 Road from MC Road to Tettu to Ramyapatnam. Prakasam
NCRMP/B-W/AP/RCS/PRED/08/Tangutur/08 Road from R&B Road Pellur to Vasepallipadu Prakasam
NCRMP/B-W/AP/RCS/PRED/08/Tangutur/10 Road from R&B Road to Kesuplem Prakasam
NCRMP/B-W/AP/RCS/PRED/09/Kota/001 Road from R&B Road to A.S.Puram Nellore
NCRMP/B-W/AP/RCS/PRED/09/kota/001 Road from GD road to Vavillapalem Nellore
NCRMP/B-W/AP/RCS/PRED/09/Muthukur/002
Road from R&B Road to Kappaladoruvu toBandlapalem H.Wada Nellore
NCRMP/B-W/AP/RCS/PRED/Chillakur/004 Road from Kakuvaripalem R&B road to Vellapalm Nellore
NCRMP/B-W/AP/RCS/PRED/09/T.P.Gudur/005
Road from 7/2 M.C. Road to VenkannapalemPattapupalem Nellore
NCRMP/B-W/AP/RCS/PRED/09/Kavali/006 Road connecting R&B Road through Votturu Village Nellore
NCRMP/B-W/AP/RCS/PRED/09/Kavali/007
Road from Kotha satram R&B to Indrsanagar (via)Thumalapenta palam, Patharavadupalam,
Ramudupalam, Karaduvari palam &Sreeramapuram
Nellore
NCRMP/B-W/AP/RCS/PRED/09/D.V. Satram/008
Road from R& B road to Sullurpeta Mallam toBerijengalapalli Cyclone Shelter Nellore
Page 38 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/09/Bogole/001 Road from NH5 to Sambasiva Puram Nellore
NCRMP/B-W/AP/RHB/PRED/09/Bogole/001
Road from 9/6 to 11/0 of Juvvaladinne R&B Roadvia Venkatespalem Nellore
NCRMP/B-W/AP/RHB/PRED/09/Bogole/002
Road from 1/6 of Zuvvaladinne R & B Road toTellgunta Nellore
NCRMP/B-W/AP/RHB/PRED/09/Chittamur/003
Road from R&B Road to Muttambeka ViaPittuvanipalli Nellore
NCRMP/B-W/AP/RHB/PRED/09/Chittamuru/003 Road from R&B Chittamur to Somasamudram Nellore
NCRMP/B-W/AP/RHB/PRED/09/Kavali/004 Road from KT R&B Road to Alliguntapaem Nellore
NCRMP/B-W/AP/RHB/PRED/09/Kavali/004
Road from KM 5/8 of Chennayapalem Road toGummadibandala Nellore
NCRMP/B-W/AP/RHB/PRED/09/Kavali/004
Road from Pedapattupalem R&B Road toChennyapalam H.Wada Nellore
NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005
Road from KT R&B Road to Alaganipadu to VavillaGC Nellore
NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005
Road from R&B road Kancharlapalam HW toAlaganipadu. Nellore
NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006 Road from R&B road to Patuvari Kandriga. Nellore
NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006
Road from Survepalli – Pudiparthi Road to SrikanthColony Nellore
NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/007 Road from R&B Road to Edagil Kandriga Nellore
NCRMP/B-W/AP/RHB/PRED/09/Allur/009
Road from R&B Road Allur to Galidibbalu (Via)Chilkaruvanidibba. Nellore
NCRMP/B-W/AP/RHB/PRED/09/Allur/009
Road from R&B Road to CS Puram and MandapamVillage Nellore
NCRMP/B-W/AP/RHB/PRED/09/T.P.Gudur/012 Road from R&B road CS Puram to Sivarampuram. Nellore
7.3. Details of Environmental and Social Reports Submitted During the Month March 2013:
NCRMP/B-W/AP/RCS/PRED/09/Kota/001 Road from R&B Road to A.S.Puram SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/kota/001 Road from GD road to Vavillapalem SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/Muthukur/002
Road from R&B Road to Kappaladoruvu toBandlapalem H.Wada SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/Chillakur/004 Road from Kakuvaripalem R&B road to Vellapalm SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/T.P.GUDUR/005
Road from 7/2 M.C. Road to VenkannapalemPattapupalem SPSR Nellore
Page 39 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RCS/PRED/09/Kavali/006 Road connecting R&B Road through Votturu Village SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/Kavali/007
Road from Kotha satram R&B to Indrsanagar (via)Thumalapenta palam, Patharavadu palam, Ramudu
palam, Karaduvari palam & SreeramapuramSPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/D.V. Satram/008
Road from R& B road to Sullurpeta Mallam toBerijengalapalli Cyclone Shelter SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Bogole/001 Road from NH5 to Sambasiva Puram SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Bogole/001
Road from 9/6 of Juvvaladinne R&B Road to 11/0 ofJuvvaladinne R&B Road via Venkatespalem SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Bogole/002
Road from 1/6 of Zuvvaladinne R & B Road toTellgunta SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Chittamur/003
Road from R&B Road to Muttambeka ViaPittuvanipalli SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Chittamuru/003 Road from R&B Chittamur to Somasamudram SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Kavali/004 Road from KT R&B Road to Alliguntapaem SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Kavali/004
Road from KM 5/8 of Chennayapalem Road toGummadibandala SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Kavali/004
Road from Pedapattupalem R&B Road toChennyapalam H.Wada SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005 Road from KT R&B Road to Alaganipadu to Vavilla GC SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005
Road from R&B road Kancharlapalam HW toAlaganipadu. SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006 Road from R&B road to Patuvari Kandriga. SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006
Road from Survepalli – Pudiparthi Road to SrikanthColony SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/007 Road from R&B Road to Edagil Kandriga SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Allur/009
Road from R&B Road Allur to Galidibbalu (Via)Chilkaruvanidibba. SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/Allur/009
Road from R&B Road to CS Puram and MandapamVillage SPSR Nellore
NCRMP/B-W/AP/RHB/PRED/09/T.P.Gudur/012 Road from R&B road CS Puram to Sivarampuram. SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/ 07/PVPalem/001 Road from R&B Road to Mandevaripalem Guntur
NCRMP/B-W/AP/RCS/PRED/07/PV Palem/001 Road from R&B Road Alluru to Yadavapalem Guntur
NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002
Road from Ganapavaram R&B Road toPedamarpuvaripalem Guntur
NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002 Road from R&B Road to Chinapuluguvaripalem Guntur
NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002 Road from R&B Road to Yaramavaripalem Guntur
NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002
Road from R&B Road Peddagollapalem CycloneShelter Guntur
Page 40 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002
Road from Peddagollapalem P.R Road toBothagorlapalem Guntur
NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003 Road from R&B Road to Adavala H/O Bavajipalem Guntur
NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003 Road from R&B Road to Atalavaripalem Guntur
NCRMP/B-W/AP/RCS/PRED/07/Baptala/004 Road from R&B Road to Hanuamathnagar Guntur
NCRMP/B-W/AP/RCS/PRED/07/Baptala/004 Road from R&B Road to Adarshnagar Guntur
NCRMP/B-W/AP/RHB/PRED/07/Karlapalem/001
Road from Ganapavaram R&B Road to Kesavapuri STcolony Guntur
NCRMP/B-W/AP/RHB/PRED/07/Nagaram/002 Road from R&B Road to Mohammad Alipalem Guntur
NCRMP/B-W/AP/RHB/PRED/07/Nagaram/002 Road from R&B Road Katuvanipalem Guntur
NCRMP/B-W/AP/Br/R&B/07/Bapatla/010
Reconstruction of HLB at Km. 5/2 of Bapatla-Suryalanka Road. Guntur
NCRMP/B-W/AP/Br/R&B/07/Perali/011
Reconstruction of HLB at Km. 2/4 of Bapatla-Pandurangapuram across Perali Drain. Guntur
NCRMP/B-W/AP/Br/R&B/02/Puligadda/007
Minor Bridge at Km. 7/2 near Puligadda of Konada –Ramatheertham R&B Road to Konathalapalem viaYerukonda, Pasupam, Kollayavalasa (Z.P. Road)
Vizianagaram
NCRMP/B-W/AP/Br/R&B/02/Chakaligadda/008
Minor Bridge at KM15/2 near chakaligadda of Konda-Ramatheertham R&B Road to Konathalapalem (via)
Yerukonda, Pasupam, Kollayavalasa (Z.P.Road)Vizianagaram
NCRMP/B-W/AP/Br/R&B/02/Konda/009
Improvements to Road from Konda Ramatheertham(R&B) Road to Konathalapalem (Via) Pasupam,
Yerukonda, Kollayavalasa from Km. 12/0 to 16/5 (Km.0/0 to 4/0 i.e., upto NH-5 crossing)
Vizianagaram
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004 Road from R&B Road to G.Musalayyapeta East Godavari
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004 Road from R&B Road to Danavaipeta East Godavari
NCRMP/B-W/AP/RCS/PRED/4/Thondangi/004 Road from R&B Road to Gaddipeta Cyclone shelter East Godavari
NCRMP/B-W/AP/RCS/PRED/4/Thondangi/004 Road from R&B Road to Hukumpeta Cyclone shelter East Godavari
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Road to K. Chodipallipeta Cycloneshelter East Godavari
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Road to P.Chodipallipeta Cycloneshelter East Godavari
NCRMP/B-W/AP/RHB/PRED/04/Karapa/001 Road from Gurjanpalli to Bandualavaripalem East Godavari
NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003
Road from PR Road to Dasarivanipeta and to CycloneShelter East Godavari
NCRMP/B-W/AP/MPCS/PRED/08/Ulavapadu/001 Construction of Cyclone Shelter at Chakicherla. Prakasam
NCRMP/B-W/AP/MPCS/PRED/08/NG Padu/003 Construction of Cyclone Shelter at Kanaparthy. Prakasam
Page 41 of 198
QUARTERLY SUMMARY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/Br/R&B/08/Kanaparthy/012 Construction of HLB @ Km.16/10 of Nagulapapadu Prakasam
NCRMP/B-W /AP/RCS/PRED/06/Machipatnam/001 Road from Potlapalem Z.P road to Pothepalli. Krishna
NCRMP/B-W /AP/RCS/PRED/06/Machipatnam/001 Road from Chinnapuram R&B Road to Gundupalem. Krishna
NCRMP/B-W /AP/RCS/PRED/06/Machipatnam/001
Road from Bhogireddipalli R&B Road toRamakhandam. Krishna
NCRMP/B-W /AP/RHB/PRED/06/Machipatnam/001
Road Connecting R&B Road throughGantalammapalem. Krishna
NCRMP/B-W /AP/RHB/PRED/06/Machipatnam/002 Road from R&B Road to B.V.Thota. Krishna
NCRMP/B-W /AP/RHB/PRED/06/Machipatnam/002 Road from Potalapalem Z.P Road to Chikativanipalem. Krishna
NCRMP/B-W /AP/RHB/PRED/06/Kruthivenu/003 Road from Intheru Z P Road to Rangaraopeta. Krishna
NCRMP/B-W /AP/RHB/PRED/06/Kruthivenu/003
Road from Intheru Z P Road to Cyclone shelter atChandala Krishna
Page 42 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
8.0 Consolidated E&S Reports during this 3 Months:
8.1 Consolidated E&S Report for Srikakulam, Visakhapatnam, West Godavari, Prakasam & SPSR Nellore Districts in the Month ofFebruary 2013:
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details of SrikakulamDistrict during February, 2013)
Sl.No Activity Measures to be implemented by the contractor Complied Not
CompliedNot
Applicable Total
1Work Plan forEMPimplementation
The Contractor’s Project Manager shall be responsible for implementation of EMPprovisions and will coordinate the over-all implementation of the said plan. Alongwith the Work Programme, the Contractor shall submit a plan including methodstatement and timeline about specific actions that will be taken by him to implementthe provisions laid out in the EMP
16 16
2RegulatoryPermissionsand Consents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consent forplants, water and extraction and borrow areas operations. This includes:
Consent for establishment and operation of plant (for concrete work) from SPCB. 16 16
PUC certification for all vehicles/equipment used for/during construction. 16 16Permission/consent of the District Administration/Mining Department/otheragencies for quarrying and/or borrowing operations for materials like sand andearth.
16 16
Permission for water extraction, if applicable in the local area context. 16 16
The Contractor shall abide by all conditions laid out in the said clearances. 16 16
Page 43 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3
ConsultationandCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/Panchayat/govt. agency) for temporary use of land for allconstruction related activities including:a) Setting-up and operation of construction camp including labour camps, stockyards etc. 16 16
b) borrow areas and 16 16c) Disposal of debris and other waste material. 16 16
4 Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shall be done ina manner that does not interfere or disturb the activities of local inhabitants,particularly those of schools and health facilities. Written permission (no objectioncertificate) shall be taken from the Gramsabha and the land owner prior to locationselection and a copy shall be submitted to the Engineer approval.
16 16
b) Camp site shall not be located within 250mts. From a water body includingvillage ponds. 16 16
c) A distance of at least 500mts. Shall be maintained from designated/protectednatural habitats (such as National Parks, Sanctuaries, Biosphere Reserves,Reserve Forests and Ramsar Sites) and Coastal Regulation Zone.
16 16
b) Accommodation and Basic Amenities: All weather shelter with the requiredtenement size and toilets shall be provided, as per provisions of Labour Laws.Separate toilet facilities shall be provided for women workers. If a common mess isnot provided/operated additional space for cooking shall be provided. Thecontractor shall ensure that hygienic conditions are maintained during the operationof such camps/facilities.
16 16
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is not used as acooking medium in the construction /labour camp. 16 16
d) Potable water supply: Drinking water supply of at least 40Ipcd with the requiredsupply points shall be provided. 16 16
e) Fire Safety: Adequate fire safety precautions shall be taken and required firesafety equipment (such as fire extinguishers) shall be provided by the contractor. 16 16
5 Site Clearancea) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s (includingthose from Forest Dept., if required) are obtained prior to cutting of such trees.
16 16
Page 44 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) The non-timber grade trees are to be stacked and possession is to be given toEmployer/concerned Govt. Department. 16 16
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. The top soilshall be reinstated in the cyclone shelter compound after the construction is over.
16 16
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to the followingresources during preparatory and construction work:a) Water supply lines 16 16b) Irrigation canals 16 16c) Cart, cattle and/or foot trail/tracks 16 16d) Cultural properties and sites/structures of religious importance 16 16e) Houses, Farmlands, Orchids and/or Trees. 16 16f) School and other existing buildings adjacent to the site of construction. 16 16In case of damage due to construction activity, the restoration/repairs shall becarried out by the contractor at his own cost. 16 16
7 QuarryOperations
The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.
16 16
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractor following thestipulations given below: The finalisation of all such locations shall be dependenton the approval of the Engineer on technical and environmental grounds. Thisincludes on-site verification to cross-check the accuracy of details provided by thecontractor. Only after receipt of the written approval from the Engineer, theContractor shall enter into a formal agreement with landowner.
16 16
b) The Contractor shall not procure any kind of construction material (such asaggregates, sand and earth) from ecologically protected areas. 16 16
c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to be doneon an agricultural land, top-soil stripping, stacking and preservation is must.
16 16
2. Borrow pits shall not be located within a distance of 100mts. From any NH, SHor other roads. 16 16
Page 45 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 16 16
4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centers. 16 16
5. No borrow area shall be opened with in 500mts. from a reserved or protectedforest area, protected sites, wildlife movement zone and cultural heritage site. 16 16
6. No tree cutting shall be undertaken. 16 167. Borrow area near any surface water body will be at least 100mts. away. 16 16d) Operation 161. Area up to which material will be extracted shall be cleared demarcated onground. 16 16
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 16 163. Borrowing of earth should be preferably limited to a depth of 1.5mtr from theexisting ground level. 16 16
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 16 16
e) Rehabilitation of Borrow Areas: 16 161. Rehabilitation shall be satisfactory undertaken immediately after the use hasceased and at least three weeks prior to monsoon 16 16
2. Preserved top soil has be spread uniformly over land (except in cases whereborrow area is developed as a water body) used as a borrow area. 16 16
9 WaterExtraction /Use
Water for construction and for use at construction camps (including labour camps)is to be extracted with prior written permission of(a) the individual owner, in casethe source is private well/tube well; (b) Gram Panchayat in case the source belongsto community: and (c) Irrigation Department in case the source is an irrigation canalor river.
16 16
10
Safety of RoadUsers andLocalResidents
a) Traffic safety arrangements (including provision of warning signage, speedbreakers etc.) shall be made by the contractor to ensure safety of road users andlocal people, particularly in the internal village roads which will be used fortransporting materials.
16 16
b) Material shall be covered during transportation to prevent spillage, accidentsand pollution. 16 16
Page 46 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) All required measures to ensure safety of local residents including childrenand other near-by residents shall be taken up by the Contractor. This shall includeprovisions to prevent un authorised entry into the construction.
16 16
11 Worker’sSafety
a) All measures required for ensuring safety and health of the workers shall betaken up by the Contractor. This includes provision and enforcement of appropriatepersonal protective equipment; first aid facility; emergency response arrangement;proper storage of hazardous/toxic and polluting materials and; measures forensuring fire electrical and mechanical safety arrangements in camp and in worksite.
16 16
b) All methods steps and measures are required for ensuring safety of workers,particularly those needed while undertaking work in or around excavations;workings at height; and; while handling inflammable, toxic and/or hazardousmaterials shall be ensured by the contractor.
16 16
c) Material safety data sheet record of fuel and other inflammable chemicalsshall be maintained at the site. 16 16
12 Air pollution a) Wind barriers or screens shall be provided in the downwind direction at airpollution causing sources like plant sites and fine material storage stock yards
16 16
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover on materials,based on activity and site conditions.
16 16
c) All plants and equipment shall comply with pollution control norms. 16 16d) Water shall be sprinkled at least twice during dry day on haulage roadspassing through or near settlements(including at least 100m before the settlement)
16 16
13 Water Pollution
a) All measures (including provision of temporary silt fencing to control sedimentrun-off) required for avoiding adverse impacts to water bodies (such as ponds,streams, canals and rivers), water sources (such as hand pumps and wells) andadjacent farmland shall be undertaken by the Contractor.
16 16
b) Storage of materials like fuel, chemicals, and cement shall be done in amanner (with impervious layer on bottom and a covered shed on top) that does notcontaminate land and ground/surface water.
16 16
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00 PM to6.00 AM). The Contractor shall schedule construction works in consultation withlocal Panchayat Authority and School Principal to ensure least disturbance toschool children and other adjacent residents.
16 16
Page 47 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) Ear plugs shall be provided to the labour facing risk from high noise pollutionsuch as plant site and those working near generators, heavy equipment/machinery.
16 16
c) Appropriate noise controlling devices including acoustic generators shall beused to minimize noise during construction work and operation of camp. 16 16
15 DisposalDebris/ wastes
a) Debris and other construction waste, if any, shall be disposed in locationspre-approved by the Engineer in a manner that it does not contaminate theenvironment.
16 16
b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In no case,debris shall be disposed within 500mts. of ecologically sensitive areas, includingforests, wetlands and protected natural habitats.
16 16
16
RestorationandRehabilitationof Sites
All work sites and areas under temporary use (including construction and labourcamps, plant, sites, haul roads and borrow areas) shall be restored/rehabilitated toa better condition (if not at least to its original condition) and to the satisfaction ofthe Engineer and land owner upon completion of construction work by theContractor.
16 16
Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps, plants,in and around the construction site; disposal of debris/construction wastes at pre-approved locations and; restoration of borrow areas and other sites/ locations usedfor material sourcing.
16 16
17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram Panchayat ( including those related to temporary use of land, waterextraction and disposal of debris) shall be settled by the Contractor.
16 16
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details ofViskhapatnam District during February, 2013)
Sl.No Activity Measures to be implemented by the contractor Complied Not
CompliedNot
Applicable Total
Page 48 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1Work Plan forEMPimplementation
The Contractor’s Project Manager shall be responsible for implementation of EMPprovisions and will coordinate the over-all implementation of the said plan. Alongwith the Work Programme, the Contractor shall submit a plan including methodstatement and timeline about specific actions that will be taken by him to implementthe provisions laid out in the EMP
21 21
2RegulatoryPermissionsand Consents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consent forplants, water and extraction and borrow areas operations. This includes:
Consent for establishment and operation of plant (for concrete work) from SPCB. 21 21
PUC certification for all vehicles/equipment used for/during construction. 21 21Permission/consent of the District Administration/Mining Department/otheragencies for quarrying and/or borrowing operations for materials like sand andearth.
21 21
Permission for water extraction, if applicable in the local area context. 21 21
The Contractor shall abide by all conditions laid out in the said clearances. 21 21
3
ConsultationandCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/Panchayat/govt. agency) for temporary use of land for allconstruction related activities including:a) Setting-up and operation of construction camp including labour camps, stockyards etc. 21 21
b) borrow areas and 21 21c) Disposal of debris and other waste material. 21 21
4 Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shall be done ina manner that does not interfere or disturb the activities of local inhabitants,particularly those of schools and health facilities. Written permission (no objectioncertificate) shall be taken from the Gramsabha and the land owner prior to locationselection and a copy shall be submitted to the Engineer approval.
21 21
b) Camp site shall not be located within 250mts. From a water body includingvillage ponds. 21 21
Page 49 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) A distance of at least 500mts. Shall be maintained from designated/protectednatural habitats (such as National Parks, Sanctuaries, Biosphere Reserves,Reserve Forests and Ramsar Sites) and Coastal Regulation Zone.
21 21
b) Accommodation and Basic Amenities: All weather shelter with the requiredtenement size and toilets shall be provided, as per provisions of Labour Laws.Separate toilet facilities shall be provided for women workers. If a common mess isnot provided/operated additional space for cooking shall be provided. Thecontractor shall ensure that hygienic conditions are maintained during the operationof such camps/facilities.
21 21
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is not used as acooking medium in the construction /labour camp. 21 21
d) Potable water supply: Drinking water supply of at least 40Ipcd with the requiredsupply points shall be provided. 21 21
e) Fire Safety: Adequate fire safety precautions shall be taken and required firesafety equipment (such as fire extinguishers) shall be provided by the contractor. 21 21
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s (includingthose from Forest Dept., if required) are obtained prior to cutting of such trees.
21 21
b) The non-timber grade trees are to be stacked and possession is to be given toEmployer/concerned Govt. Department. 21 21
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. The top soilshall be reinstated in the cyclone shelter compound after the construction is over.
21 21
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to the followingresources during preparatory and construction work:a) Water supply lines 21 21b) Irrigation canals 21 21c) Cart, cattle and/or foot trail/tracks 21 21d) Cultural properties and sites/structures of religious importance 21 21e) Houses, Farmlands, Orchids and/or Trees. 21 21f) School and other existing buildings adjacent to the site of construction. 21 21In case of damage due to construction activity, the restoration/repairs shall becarried out by the contractor at his own cost. 21 21
Page 50 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
7 QuarryOperations
The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.
21 21
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractor following thestipulations given below: The finalisation of all such locations shall be dependenton the approval of the Engineer on technical and environmental grounds. Thisincludes on-site verification to cross-check the accuracy of details provided by thecontractor. Only after receipt of the written approval from the Engineer, theContractor shall enter into a formal agreement with landowner.
21 21
b) The Contractor shall not procure any kind of construction material (such asaggregates, sand and earth) from ecologically protected areas. 21 21
c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to be doneon an agricultural land, top-soil stripping, stacking and preservation is must.
21 21
2. Borrow pits shall not be located within a distance of 100mts. From any NH, SHor other roads. 21 21
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 21 21
4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 21 21
5. No borrow area shall be opened with in 500mts. from a reserved or protectedforest area, protected sites, wildlife movement zone and cultural heritage site. 21 21
6. No tree cutting shall be undertaken. 21 217. Borrow area near any surface water body will be at least 100mts. away. 21 21d) Operation 211. Area up to which material will be extracted shall be cleared demarcated onground. 21 21
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 21 213. Borrowing of earth should be preferably limited to a depth of 1.5mtr from theexisting ground level. 21 21
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 21 21
Page 51 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
e) Rehabilitation of Borrow Areas: 21 211. Rehabilitation shall be satisfactory undertaken immediately after the use hasceased and at least three weeks prior to monsoon 21 21
2. Preserved top soil has be spread uniformly over land (except in cases whereborrow area is developed as a water body) used as a borrow area. 21 21
9 WaterExtraction /Use
Water for construction and for use at construction camps (including labour camps)is to be extracted with prior written permission of(a) the individual owner, in casethe source is private well/tube well; (b) Gram Panchayat in case the source belongsto community: and (c) Irrigation Department in case the source is an irrigation canalor river.
21 21
10
Safety of RoadUsers andLocalResidents
a) Traffic safety arrangements (including provision of warning signage, speedbreakers etc.) shall be made by the contractor to ensure safety of road users andlocal people, particularly in the internal village roads which will be used fortransporting materials.
21 21
b) Material shall be covered during transportation to prevent spillage, accidentsand pollution. 21 21
c) All required measures to ensure safety of local residents including childrenand other near-by residents shall be taken up by the Contractor. This shall includeprovisions to prevent un authorised entry into the construction.
21 21
11 Worker’sSafety
a) All measures required for ensuring safety and health of the workers shall betaken up by the Contractor. This includes provision and enforcement of appropriatepersonal protective equipment; first aid facility; emergency response arrangement;proper storage of hazardous/toxic and polluting materials and; measures forensuring fire electrical and mechanical safety arrangements in camp and in worksite.
21 21
b) All methods steps and measures are required for ensuring safety of workers,particularly those needed while undertaking work in or around excavations;workings at height; and; while handling inflammable, toxic and/or hazardousmaterials shall be ensured by the contractor.
21 21
c) Material safety data sheet record of fuel and other inflammable chemicalsshall be maintained at the site. 21 21
12 Air pollution a) Wind barriers or screens shall be provided in the downwind direction at airpollution causing sources like plant sites and fine material storage stock yards
21 21
Page 52 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover on materials,based on activity and site conditions.
21 21
c) All plants and equipment shall comply with pollution control norms. 21 21d) Water shall be sprinkled at least twice during dry day on haulage roadspassing through or near settlements(including at least 100m before the settlement)
21 21
13 Water Pollution
a) All measures (including provision of temporary silt fencing to control sedimentrun-off) required for avoiding adverse impacts to water bodies (such as ponds,streams, canals and rivers), water sources (such as hand pumps and wells) andadjacent farmland shall be undertaken by the Contractor.
21 21
b) Storage of materials like fuel, chemicals, and cement shall be done in amanner (with impervious layer on bottom and a covered shed on top) that does notcontaminate land and ground/surface water.
21 21
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00 PM to6.00 AM). The Contractor shall schedule construction works in consultation withlocal Panchayat Authority and School Principal to ensure least disturbance toschool children and other adjacent residents.
21 21
b) Ear plugs shall be provided to the labour facing risk from high noise pollutionsuch as plant site and those working near generators, heavy equipment/machinery.
21 21
c) Appropriate noise controlling devices including acoustic generators shall beused to minimise noise during construction work and operation of camp. 21 21
15 DisposalDebris/ wastes
a) Debris and other construction waste, if any, shall be disposed in locationspre-approved by the Engineer in a manner that it does not contaminate theenvironment.
21 21
b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In no case,debris shall be disposed within 500mts. of ecologically sensitive areas, includingforests, wetlands and protected natural habitats.
21 21
16
RestorationandRehabilitationof Sites
All work sites and areas under temporary use (including construction and labourcamps, plant, sites, haul roads and borrow areas) shall be restored/rehabilitated toa better condition (if not at least to its original condition) and to the satisfaction ofthe Engineer and land owner upon completion of construction work by theContractor.
21 21
Page 53 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps, plants,in and around the construction site; disposal of debris/construction wastes at pre-approved locations and; restoration of borrow areas and other sites/ locations usedfor material sourcing.
21 21
17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat (including those related to temporary use of land, waterextraction and disposal of debris) shall be settled by the Contractor.
21 21
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details of WestGodavari District during February, 2013)
Sl.No Activity Measures to be implemented by the contractor Complied Not
CompliedNot
Applicable Total
1Work Plan forEMPimplementation
The Contractor’s Project Manager shall be responsible for implementation of EMPprovisions and will coordinate the over-all implementation of the said plan. Alongwith the Work Programme, the Contractor shall submit a plan including methodstatement and timeline about specific actions that will be taken by him to implementthe provisions laid out in the EMP
10 10
2RegulatoryPermissionsand Consents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consent forplants, water and extraction and borrow areas operations. This includes:
Consent for establishment and operation of plant (for concrete work) from SPCB. 10 10
PUC certification for all vehicles/equipment used for/during construction. 10 10Permission/consent of the District Administration/Mining Department/otheragencies for quarrying and/or borrowing operations for materials like sand andearth.
10 10
Page 54 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Permission for water extraction, if applicable in the local area context. 10 10
The Contractor shall abide by all conditions laid out in the said clearances. 10 10
3
ConsultationandCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of land for allconstruction related activities including:a) Setting-up and operation of construction camp including labour camps, stockyards etc. 10 10
b) borrow areas and 10 10c) Disposal of debris and other waste material. 10 10
4 Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shall be done ina manner that does not interfere or disturb the activities of local inhabitants,particularly those of schools and health facilities. Written permission (no objectioncertificate) shall be taken from the Gramsabha and the land owner prior to locationselection and a copy shall be submitted to the Engineer approval.
10 10
b) Camp site shall not be located within 250mts. From a water body includingvillage ponds. 10 10
c) A distance of at least 500mts. Shall be maintained from designated/protectednatural habitats (such as National Parks, Sanctuaries, Biosphere Reserves,Reserve Forests and Ramsar Sites) and Coastal Regulation Zone.
10 10
b) Accommodation and Basic Amenities: All weather shelter with the requiredtenement size and toilets shall be provided, as per provisions of Labour Laws.Separate toilet facilities shall be provided for women workers. If a common mess isnot provided/operated additional space for cooking shall be provided. Thecontractor shall ensure that hygienic conditions are maintained during the operationof such camps/facilities.
10 10
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is not used as acooking medium in the construction /labour camp. 10 10
d) Potable water supply: Drinking water supply of at least 40Ipcd with the requiredsupply points shall be provided. 10 10
e) Fire Safety: Adequate fire safety precautions shall be taken and required firesafety equipment (such as fire extinguishers) shall be provided by the contractor. 10 10
Page 55 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s (includingthose from Forest Dept., if required) are obtained prior to cutting of such trees.
10 10
b) The non-timber grade trees are to be stacked and possession is to be given toEmployer/concerned Govt. Department. 10 10
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. The top soilshall be reinstated in the cyclone shelter compound after the construction is over.
10 10
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to the followingresources during preparatory and construction work:a) Water supply lines 10 10b) Irrigation canals 10 10c) Cart, cattle and/or foot trail/tracks 10 10d) Cultural properties and sites/structures of religious importance 10 10e) Houses, Farmlands, Orchids and/or Trees. 10 10f) School and other existing buildings adjacent to the site of construction. 10 10In case of damage due to construction activity, the restoration/repairs shall becarried out by the contractor at his own cost. 10 10
7 QuarryOperations
The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.
10 10
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractor following thestipulations given below: The finalisation of all such locations shall be dependenton the approval of the Engineer on technical and environmental grounds. Thisincludes on-site verification to cross-check the accuracy of details provided by thecontractor. Only after receipt of the written approval from the Engineer, theContractor shall enter into a formal agreement with landowner.
10 10
b) The Contractor shall not procure any kind of construction material (such asaggregates, sand and earth) from ecologically protected areas. 10 10
c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to be doneon an agricultural land, top-soil stripping, stacking and preservation is must.
10 10
Page 56 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
2. Borrow pits shall not be located within a distance of 100mts. From any NH, SHor other roads. 10 10
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 10 10
4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 10 10
5. No borrow area shall be opened with in 500mts. from a reserved or protectedforest area, protected sites, wildlife movement zone and cultural heritage site. 10 10
6. No tree cutting shall be undertaken. 10 107. Borrow area near any surface water body will be at least 100mts. away. 10 10d) Operation 101. Area up to which material will be extracted shall be cleared demarcated onground. 10 10
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 10 103. Borrowing of earth should be preferably limited to a depth of 1.5mtr from theexisting ground level. 10 10
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 10 10
e) Rehabilitation of Borrow Areas: 10 101. Rehabilitation shall be satisfactory undertaken immediately after the use hasceased and at least three weeks prior to monsoon 10 10
2. Preserved top soil has be spread uniformly over land (except in cases whereborrow area is developed as a water body) used as a borrow area. 10 10
9 WaterExtraction /Use
Water for construction and for use at construction camps (including labour camps)is to be extracted with prior written permission of(a) the individual owner, in casethe source is private well/tube well; (b) Gram Panchayat in case the source belongsto community: and (c) Irrigation Department in case the source is an irrigation canalor river.
10 10
10
Safety of RoadUsers andLocalResidents
a) Traffic safety arrangements (including provision of warning signage, speedbreakers etc.) shall be made by the contractor to ensure safety of road users andlocal people, particularly in the internal village roads which will be used fortransporting materials.
10 10
Page 57 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) Material shall be covered during transportation to prevent spillage, accidentsand pollution. 10 10
c) All required measures to ensure safety of local residents including childrenand other near-by residents shall be taken up by the Contractor. This shall includeprovisions to prevent un authorised entry into the construction.
10 10
11 Worker’sSafety
a) All measures required for ensuring safety and health of the workers shall betaken up by the Contractor. This includes provision and enforcement of appropriatepersonal protective equipment; first aid facility; emergency response arrangement;proper storage of hazardous/toxic and polluting materials and; measures forensuring fire electrical and mechanical safety arrangements in camp and in worksite.
10 10
b) All methods steps and measures are required for ensuring safety of workers,particularly those needed while undertaking work in or around excavations;workings at height; and; while handling inflammable, toxic and/or hazardousmaterials shall be ensured by the contractor.
10 10
c) Material safety data sheet record of fuel and other inflammable chemicalsshall be maintained at the site. 10 10
12 Air pollution a) Wind barriers or screens shall be provided in the downwind direction at airpollution causing sources like plant sites and fine material storage stock yards
10 10
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover on materials,based on activity and site conditions.
10 10
c) All plants and equipment shall comply with pollution control norms. 10 10d) Water shall be sprinkled at least twice during dry day on haulage roadspassing through or near settlements(including at least 100m before the settlement)
10 10
13 Water Pollution
a) All measures (including provision of temporary silt fencing to control sedimentrun-off) required for avoiding adverse impacts to water bodies (such as ponds,streams, canals and rivers), water sources (such as hand pumps and wells) andadjacent farmland shall be undertaken by the Contractor.
10 10
b) Storage of materials like fuel, chemicals, and cement shall be done in amanner (with impervious layer on bottom and a covered shed on top) that does notcontaminate land and ground/surface water.
10 10
Page 58 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00 PM to6.00 AM). The Contractor shall schedule construction works in consultation withlocal Panchayat Authority and School Principal to ensure least disturbance toschool children and other adjacent residents.
10 10
b) Ear plugs shall be provided to the labour facing risk from high noise pollutionsuch as plant site and those working near generators, heavy equipment/machinery.
10 10
c) Appropriate noise controlling devices including acoustic generators shall beused to minimise noise during construction work and operation of camp. 10 10
15 DisposalDebris/ wastes
a) Debris and other construction waste, if any, shall be disposed in locationspre-approved by the Engineer in a manner that it does not contaminate theenvironment.
10 10
b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In no case,debris shall be disposed within 500mts. of ecologically sensitive areas, includingforests, wetlands and protected natural habitats.
10 10
16
RestorationandRehabilitationof Sites
All work sites and areas under temporary use (including construction and labourcamps, plant, sites, haul roads and borrow areas) shall be restored/rehabilitated toa better condition (if not at least to its original condition) and to the satisfaction ofthe Engineer and land owner upon completion of construction work by theContractor.
10 10
Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps, plants,in and around the construction site; disposal of debris/construction wastes at pre-approved locations and; restoration of borrow areas and other sites/ locations usedfor material sourcing.
10 10
17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat ( including those related to temporary use of land, waterextraction and disposal of debris) shall be settled by the Contractor.
10 10
Page 59 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
8.2 Consolidated E&S Report of Vizianagaram, East Godavari, Krishna, Guntur, Prakasam & SPSR Nellore Districts in the Month ofMarch 2013:
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to Cyclone Shelters &Habitations, Bridges and Culverts under NCRMP (Details of Vizianagaram in March, 2013)
Sl.No Activity Measures to be implemented by the contractor Compliced Not
complicedNot
applicable Total
1 Work Plan for EMPImplementation
The Contractor’s Project Manager shall be responsible for implementation ofEMP provisions and will coordinate the over-all implementation of the saidplan. Along with the Work Programme, the Contractor shall submit a planincluding method statement and timeline about specific actions that will betaken by him to implement the provisions laid out in the EMP
3 3
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:
3
· Consent for establishment and operation of plant (for concrete work)from SPCB. 3 3
· PUC certification for all vehicles/equipment used for/duringconstruction. 3 3
· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.
3 3
· Permission for water extraction, if applicable in the local areacontext. 3 3
The Contractor shall abide by all conditions laid out in the said clearances. 3 3
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 3 3
Page 60 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) borrow areas and 3 3c) Disposal of debris and other waste material. 3 3
4 Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabhaand the land owner prior to location selection and a copy shall be submittedto the Engineer approval.
3 3
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 3 3
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.
3 3
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.
3 3
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 3 3
d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 3 3
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.
3 3
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cuttingof such trees.
3 3
b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 3 3
Page 61 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
3 3
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 3 3b) Irrigation canals 3 3c) Cart, cattle and/or foot trail/tracks 3 3d) Cultural properties and sites/structures of religious importance 3 3
e) Houses, Farmlands, Orchids and/or Trees. 3 3f) School and other existing buildings adjacent to the site ofconstruction. 3 3
In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 3 3
7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.
3 3
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.
3 3
b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 3 3
c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.
3 3
2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 3 3
Page 62 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 3 3
4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 3 3
5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.
3 3
6. No tree cutting shall be undertaken. 3 37. Borrow area near any surface water body will be at least 100mts.away. 3 3
d) Operation 31. Area up to which material will be extracted shall be cleareddemarcated on ground. 3 3
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 3 33. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 3 3
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 3 3
e) Rehabilitation of Borrow Areas: 3 31. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 3 3
2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 3 3
9
WaterExtraction/Use
Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.
3 3
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.
3 3
b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 3 3
Page 63 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.
3 3
11 Worker’s Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.
3 3
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
3 3
c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 3 3
12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards
3 3
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
3 3
c) All plants and equipment shall comply with pollution control norms. 3 3
d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)
3 3
13 Water Pollution
a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.
3 3
b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top)that does not contaminate land and ground/surface water.
3 3
Page 64 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.
3 3
b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavyequipment /machinery.
3 3 3
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.
3 3
15 Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
3 3
b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In nocase, debris shall be disposed within 500mts. of ecologically sensitive areas,including forests, wetlands and protected natural habitats.
3 3
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
3 3
Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas andother sites/ locations used for material sourcing.
3 3
17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat (including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contractor.
3 3
Page 65 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to Cyclone Shelters &Habitations, Bridges and Culverts under NCRMP (Details of East Godavari in March,2013)
Sl.No Activity Measures to be implemented by the contractor Compliced Not
complicedNot
applicable Total
1 Work Plan for EMPimplementation
The Contractor’s Project Manager shall be responsible for implementation ofEMP provisions and will coordinate the over-all implementation of the saidplan. Along with the Work Programme, the Contractor shall submit a planincluding method statement and timeline about specific actions that will betaken by him to implement the provisions laid out in the EMP
8 8
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:
8
· Consent for establishment and operation of plant (for concrete work)from SPCB. 8 8
· PUC certification for all vehicles/equipment used for/duringconstruction. 8 8
· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.
8 8
· Permission for water extraction, if applicable in the local areacontext. 8 8
The Contractor shall abide by all conditions laid out in the said clearances. 8 8
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 8 8
b) borrow areas and 8 8c) Disposal of debris and other waste material. 8 8
Page 66 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
4 Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabhaand the land owner prior to location selection and a copy shall be submittedto the Engineer approval.
8 8
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 8 8
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.
8 8
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.
8 8
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 8 8
d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 8 8
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.
8 8
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cuttingof such trees.
8 8
b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 8 8
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
8 8
Page 67 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 8 8
b) Irrigation canals 8 8c) Cart, cattle and/or foot trail/tracks 8 8d) Cultural properties and sites/structures of religious importance 8 8e) Houses, Farmlands, Orchids and/or Trees. 8 8f) School and other existing buildings adjacent to the site ofconstruction. 8 8
In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 8 8
7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.
8 8
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.
8 8
b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 8 8
c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.
8 8
2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 8 8
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 8 8
4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 8 8
Page 68 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.
8 8
6. No tree cutting shall be undertaken. 8 87. Borrow area near any surface water body will be at least 100mts.away. 8 8
d) Operation 81. Area up to which material will be extracted shall be cleareddemarcated on ground. 8 8
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 8 83. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 8 8
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 8 8
e) Rehabilitation of Borrow Areas: 8 81. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 8 8
2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 8 8
9 Water Extraction/Use
Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.
8 8
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.
8 8
b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 8 8
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.
8 8
Page 69 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
11 Worker’s Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.
8 8
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
8 8
c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 8 8
12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards
8 8
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
8 8
c) All plants and equipment shall comply with pollution control norms. 8 8d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)
8 8
13 Water Pollution
a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.
8 8
b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top)that does not contaminate land and ground/surface water.
8 8
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.
8 8
b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavy 8 8 8
Page 70 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
equipment /machinery.
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.
8 8
15 Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
8 8
b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In nocase, debris shall be disposed within 500mts. of ecologically sensitive areas,including forests, wetlands and protected natural habitats.
8 8
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
8 8
Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas andother sites/ locations used for material sourcing.
8 8
17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contractor.
8 8
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details of Krishna inMarch,2013)Sl.No Activity Measures to be implemented by the contractor Compliced Not
complicedNot
applicable Total
Page 71 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1 Work Plan for EMPimplementation
The Contractor’s Project Manager shall be responsible for implementationof EMP provisions and will coordinate the over-all implementation of thesaid plan. Along with the Work Programme, the Contractor shall submit aplan including method statement and timeline about specific actions that willbe taken by him to implement the provisions laid out in the EMP
8 8
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:
8
· Consent for establishment and operation of plant (for concrete work)from SPCB. 8 8
· PUC certification for all vehicles/equipment used for/duringconstruction. 8 8
· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.
8 8
· Permission for water extraction, if applicable in the local area context. 8 8
The Contractor shall abide by all conditions laid out in the said clearances. 8 8
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of land forall construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 8 8
b) borrow areas and 8 8c) Disposal of debris and other waste material. 8 8
4 Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabha andthe land owner prior to location selection and a copy shall be submitted tothe Engineer approval.
8 8
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 8 8
Page 72 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.
8 8
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.
8 8
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is not usedas a cooking medium in the construction /labour camp. 8 8
d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 8 8
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.
8 8
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cuttingof such trees.
8 8
b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 8 8
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
8 8
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 8 8b) Irrigation canals 8 8c) Cart, cattle and/or foot trail/tracks 8 8d) Cultural properties and sites/structures of religious importance 8 8e) Houses, Farmlands, Orchids and/or Trees. 8 8f) School and other existing buildings adjacent to the site of construction. 8 8
Page 73 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 8 8
7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.
8 8
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.
8 8
b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 8 8
c) Identification and Selection: 81. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.
8 8
2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 8 8
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 8 8
4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 8 8
5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.
8 8
6. No tree cutting shall be undertaken. 8 87. Borrow area near any surface water body will be at least 100mts.away. 8 8
d) Operation 81. Area up to which material will be extracted shall be cleareddemarcated on ground. 8 8
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 8 8
Page 74 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 8 8
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 8 8
e) Rehabilitation of Borrow Areas: 8 81. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 8 8
2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 8 8
9 Water Extraction/Use
Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.
8 8
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.
8 8
b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 8 8
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.
8 8
11 Worker’s Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.
8 8
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
8 8
Page 75 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 8 8
12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards
8 8
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
8 8
c) All plants and equipment shall comply with pollution control norms. 8 8d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)
8 8
13 Water Pollution
a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.
8 8
b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top) thatdoes not contaminate land and ground/surface water.
8 8
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.
8 8
b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavyequipment /machinery.
8 8 8
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.
8 8
15 Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
8 8
b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and water bodies. Inno case, debris shall be disposed within 500mts. of ecologically sensitiveareas, including forests, wetlands and protected natural habitats.
8 8
Page 76 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
8 8
Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas and othersites/ locations used for material sourcing.
8 8
17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat (including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contractor.
8 8
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to Cyclone Shelters &Habitations, Bridges and Culverts under NCRMP (Details of Guntur in March,2013)
Sl.No Activity Measures to be implemented by the contractor Compliced Not
complicedNot
applicable Total
1 Work Plan for EMPimplementation
The Contractor’s Project Manager shall be responsible for implementation ofEMP provisions and will coordinate the over-all implementation of the saidplan. Along with the Work Programme, the Contractor shall submit a planincluding method statement and timeline about specific actions that will betaken by him to implement the provisions laid out in the EMP
16 16
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:
16
· Consent for establishment and operation of plant (for concrete work)from SPCB. 16 16
· PUC certification for all vehicles/equipment used for/duringconstruction. 16 16
· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations for 16 16
Page 77 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
materials like sand and earth.
· Permission for water extraction, if applicable in the local areacontext. 16 16
The Contractor shall abide by all conditions laid out in the said clearances. 16 16
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 16 16
b) borrow areas and 16 16c) Disposal of debris and other waste material. 16 16
4 Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabhaand the land owner prior to location selection and a copy shall be submittedto the Engineer approval.
16 16
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 16 16
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.
16 16
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.
16 16
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 16 16
d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 16 16
Page 78 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.
16 16
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cuttingof such trees.
16 16
b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 16 16
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
16 16
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 16 16b) Irrigation canals 16 16c) Cart, cattle and/or foot trail/tracks 16 16
d) Cultural properties and sites/structures of religious importance 16 16e) Houses, Farmlands, Orchids and/or Trees. 16 16f) School and other existing buildings adjacent to the site ofconstruction. 16 16
In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 16 16
7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.
16 16
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.
16 16
Page 79 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 16 16
c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.
16 16
2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 16 16
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 16 16
4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 16 16
5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.
16 16
6. No tree cutting shall be undertaken. 16 167. Borrow area near any surface water body will be at least 100mts.away. 16 16
d) Operation 161. Area up to which material will be extracted shall be cleareddemarcated on ground. 16 16
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 16 163. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 16 16
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 16 16
e) Rehabilitation of Borrow Areas: 16 161. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 16 16
2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 16 16
Page 80 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
9 Water Extraction/Use
Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.
16 16
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.
16 16
b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 16 16
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.
16 16
11 Worker’s Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.
16 16
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
16 16
c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 16 16
12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards
16 16
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
16 16
c) All plants and equipment shall comply with pollution control norms. 16 16
Page 81 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)
16 16
13 Water Pollution
a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.
16 16
b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top)that does not contaminate land and ground/surface water.
16 16
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.
16 16
b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavyequipment /machinery.
16 16
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.
16 16
15 Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
16 16
b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In nocase, debris shall be disposed within 500mts. of ecologically sensitive areas,including forests, wetlands and protected natural habitats.
16 16
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
16 16
Page 82 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas andother sites/ locations used for material sourcing.
16 16
17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contractor.
16 16
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to Cyclone Shelters &Habitations, Bridges and Culverts under NCRMP (Details of Prakasam in March,2013)
Sl.No Activity Measures to be implemented by the contractor Compliced Not
complicedNot
applicable Total
1 Work Plan for EMPimplementation
The Contractor’s Project Manager shall be responsible for implementation ofEMP provisions and will coordinate the over-all implementation of the saidplan. Along with the Work Programme, the Contractor shall submit a planincluding method statement and timeline about specific actions that will betaken by him to implement the provisions laid out in the EMP
3 3
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:
· Consent for establishment and operation of plant (for concrete work)from SPCB. 3 3
· PUC certification for all vehicles/equipment used for/duringconstruction. 3 3
· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.
3 3
· Permission for water extraction, if applicable in the local areacontext. 3 3
The Contractor shall abide by all conditions laid out in the said clearances. 3 3
Page 83 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 3 3
b) borrow areas and 3 3c) Disposal of debris and other waste material. 3 3
4 Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabhaand the land owner prior to location selection and a copy shall be submittedto the Engineer approval.
3 3
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 3 3
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.
3 3
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.
3 3
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 3 3
d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 3 3
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.
3 3
5 Site Clearancea) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cutting
3 3
Page 84 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
of such trees.
b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 3 3
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
3 3
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 3 3b) Irrigation canals 3 3c) Cart, cattle and/or foot trail/tracks 3 3d) Cultural properties and sites/structures of religious importance 3 3e) Houses, Farmlands, Orchids and/or Trees. 3 3f) School and other existing buildings adjacent to the site ofconstruction. 3 3
In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 3 3
7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.
3 3
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.
3 3
b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 3 3
c) Identification and Selection:
Page 85 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.
3 3
2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 3 3
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 3 3
4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 3 3
5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.
3 3
6. No tree cutting shall be undertaken. 3 37. Borrow area near any surface water body will be at least 100mts.away. 3 3
d) Operation 31. Area up to which material will be extracted shall be cleareddemarcated on ground. 3 3
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 3 33. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 3 3
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 3 3
e) Rehabilitation of Borrow Areas: 3 31. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 3 3
2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 3 3
9 Water Extraction/Use
Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.
3 3
Page 86 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.
3 3
b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 3 3
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.
3 3
11 Worker’s Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.
3 3
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
3 3
c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 3 3
12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards
3 3
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
3 3
c) All plants and equipment shall comply with pollution control norms. 3 3d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)
3 3
Page 87 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
13 Water Pollution
a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.
3 3
b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top)that does not contaminate land and ground/surface water.
3 3
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.
3 3
b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavyequipment /machinery.
3 3
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.
3 3
15 Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
3 3
b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In nocase, debris shall be disposed within 500mts. of ecologically sensitive areas,including forests, wetlands and protected natural habitats.
3 3
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
3 3
Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas andother sites/ locations used for material sourcing.
3 3
Page 88 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram anchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contarctor.
3 3
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to Cyclone Shelters &Habitations, Bridges and Culverts under NCRMP (Details of Nellore in March,2013)
Sl.No Activity Measures to be implemented by the contractor Compliced Not
complicedNot
applicable Total
1 Work Plan for EMPimplementation
The Contractor’s Project Manager shall be responsible for implementation ofEMP provisions and will coordinate the over-all implementation of the saidplan. Along with the Work Programme, the Contractor shall submit a planincluding method statement and timeline about specific actions that will betaken by him to implement the provisions laid out in the EMP
24 24
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:
24
· Consent for establishment and operation of plant (for concrete work)from SPCB. 24 24
· PUC certification for all vehicles/equipment used for/duringconstruction. 24 24
· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.
24 24
· Permission for water extraction, if applicable in the local areacontext. 24 24
The Contractor shall abide by all conditions laid out in the said clearances. 24 24
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 24 24
Page 89 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) borrow areas and 24 24c) Disposal of debris and other waste material. 24 24
4 Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabhaand the land owner prior to location selection and a copy shall be submittedto the Engineer approval.
24 24
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 24 24
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.
24 24
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.
24 24
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 24 24
d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 24 24
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.
24 24
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cuttingof such trees.
24 24
b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 24 24
Page 90 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
24 24
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 24 24b) Irrigation canals 24 24c) Cart, cattle and/or foot trail/tracks 24 24d) Cultural properties and sites/structures of religious importance 24 24
e) Houses, Farmlands, Orchids and/or Trees. 24 24f) School and other existing buildings adjacent to the site ofconstruction. 24 24
In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 24 24
7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.
24 24
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.
24 24
b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 24 24
c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.
24 24
2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 24 24
Page 91 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 24 24
4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 24 24
5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.
24 24
6. No tree cutting shall be undertaken. 24 247. Borrow area near any surface water body will be at least 100mts.away. 24 24
d) Operation1. Area up to which material will be extracted shall be cleareddemarcated on ground. 24 24
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 24 243. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 24 24
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 24 24
e) Rehabilitation of Borrow Areas: 24 241. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 24 24
2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 24 24
9 Water Extraction/Use
Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.
24 24
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.
24 24
b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 24 24
Page 92 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.
24 24
11 Worker’s Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.
24 24
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
24 24
c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 24 24
12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards
24 24
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
24 24
c) All plants and equipment shall comply with pollution control norms. 24 24
d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)
24 24
13 Water Pollution
a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.
24 24
b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top)that does not contaminate land and ground/surface water.
24 24
Page 93 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.
24 24
b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavyequipment /machinery.
24 24 24
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.
24 24
15 Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
24 24
b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In nocase, debris shall be disposed within 500mts. of ecologically sensitive areas,including forests, wetlands and protected natural habitats.
24 24
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
24 24
Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas andother sites/ locations used for material sourcing.
24 24
17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contractor.
24 24
Page 94 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
9.0 Statement Showing the Inspections and Site Visits of Districts during this 3 Months:
9.1 Statement Showing the Inspections and Site Visits of Districts during the Month of January -2013
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THE MONTH OF JANUARY 2013
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of Cyclone shelter at Runku inSanthabommali Mandal. 19.01.13,26.01.13 2
2 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002
Road from Deppuru, bhadapalli road to Onkuluru &cyclone shelter. 8.01.13 1
3 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram 8.01.13 1
4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komrlathada&Cyclonic shelter 8.01.13 1
5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B ROAD TO Devunalthada 8.01.13 1
6 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of Cyclone shelter at Kollipadu inSanthabommali Mandal. 3.01.13, 19.01.13, 24.01.13 3
7 NCRMP/B_W/AP/Br/R&B/ 01/Bendigedda/004 Construction of High level Bridge across Bendigedda atkm 4/10 of Pundi-Parlkimidi road in Srikakulam Dist. 12.01.13 1
8 NCRMP/B-W/AP/MPCS/PRED/ 01/Polaki/006 Road from Talasamudram to Dola regulator 24.01.13 1
9 NCRMP/B-W/AP/MPCS/PRED/ 01/Polaki/006 Road from Mabagam R&B road to Dubbakavanipeta viagajapathinagaram. 24.01.13 1
10 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/005 Road from R&B road Edullavalasa-Killam to jonnam viatalasamudram 24.01.13 1
11 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Kotcherla road to Pathasundarapalem 11.01.13 1
Page 95 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
12 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Kotcherla road to Kollibhemavaram & tocyclone shelter 11.01.13 1
13 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from mentada to Dovupeta 11.01.13 1
14 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Koyyam R&B road to Moosavanipeta 11.01.13 1
15 NCRMP/B_W/BR/R&B/01/uppigedda/002 Construction of HLB across uppugedda at Km 7/6 ofSrikakulam municipal limits to Pukkalapeta 3.01.13, 5.01.13, 10.01.13, 24.01.13 4
16 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001
Construction of Bridge at km 11/6-8 of NH-5 toPatnavanipeta connecting Sundarapalem.
4.01.13, 10.01.13, 18.01.13, 21.01.13,22.01.13, 26.01.13, 27.01.13 7
17 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from DPN road Uddandapalem 9.01.13 1
18 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from K.Umilada to Koduru (Link road) 9.01.13 1
19 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003
Road from Borubadra, Malagam road to Kollipadu viaSeepuram, Ghantapeta 9.01.13 1
TOTAL 31
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THE MONTH OF JANUARY 2013
SNO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONSDURING THIS MONTH
DATES OFVISIT
NO. OFVISITS
1 NCRMP/B-W/ AP/ Br/ R&B/ 02/Chakaligadda /008
Construction of Minor Bridge at Km 15/2 near Chakaligadda of Konada Ramatheertham R&Broad to Konatalapalem (via) Yerukonda, Pasupam, Kollayavalasa (ZP Road). 29.01.2013 1
Total 1
Page 96 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISAKHAPATNAM DURING THIS MONTH OF JANUARY - 2013
SNO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004 Construction of cyclone shelter at Venkayyapalem in RambilliMandal
03.01.13, 05.01.13,08.01.13, 19.01.1322.01.13, 30.01.13
6
2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda in NakkapalliMandal
03.01.13, 09.01.13,10.01.13, 17.01.1323.01.13, 30.01.13
6
3 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Mullaparra in NakkapalliMandal
03.01.13, 17.01.13,23.01.13, 30.01.13 4
4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Bangarrampeta in NakkapalliMandal 03.01.13, 30.01.13 2
5 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Ratnayampeta inPayakaraopeta Mandal 04.01.13, 12.01.13 2
6 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Gajapathinagaram inPayakaraopeta Mandal
04.01.13, 09.01.13,12.01.13 3
7 NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003 Road from R&B road to B.P Kallalu to Matchavanipalem 18.01.13 1
8 NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001 Road from NH-5 to Ramarayyadupalem 19.01.13 1
9 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Rajakoduru 19.01.13, 22.01.13 2
10 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Krishnampalem 19.01.13 1
11 NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 B.T to the road from R & B road to Venkayyapalem 19.01.13, 22.01.13 2
12 NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R & B road to Pothurajanapalem 11.01.13 1
13 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from R&B road to Pedateenarla to Chinateenarla 23.01.13 1
14 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from Upamaka Rajayyapeta R&B road to Janakayyapeta 23.01.13 1
Page 97 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
15 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001 Providing B.T to the road from Vempudi to Patimeeda 23.01.13 1
16 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/002 B.T to the road from R&B to Mullaparra up to beach end 23.01.13 1
17 NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006 Road from R&B Road to Revupolavaram Cyclone shelter . 31.01.13 1
18 NCRMP/B-W/AP/MPCS/PRED/03/S.Rayavaram/009 Construction of Cyclone shelter at Bangarampalem I&II H/OVakadu. 31.01.13 1
19 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from R&B road to Gajareddypalem 08.01.13, 19.01.13,22.01.13 3
20 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Rajayyapeta 09.01.13, 17.01.13 2
21 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008 Road from ZP Road Palamanpeta to Korlayyapeta 09.01.13, 17.01.13 2
22 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Palmanpeta 09.01.13, 17.01.13 2
23 NCRMP/B-W/AP/MPCS/PRED/03/Atchutapuram/006 Construction of cyclone shelter at Kadapalem 08.01.13 1
24 NCRMP/B-W/AP/MPCS/PRED/03/Atchutapuram/006 Construction of cyclone shelter at Vadapalem 08.01.13 1
25 NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/009 Road from R&B road to Vadapalem 08.01.13 1
26 NCRMP/B-W/AP/RCS/PRED/03/Atchutapuram/007 Road from R&B road to Kothapatnam 08.01.13 1
27 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from Rajala R&B road to Rajarayyudupalem 08.01.13 1
28 NCRMP/B-W/AP/MPCS/PRED/03/Paravada/005 Construction of cyclone shelter at Jalaripeta 11.01.13 1
29 NCRMP/B-W/AP/MPCS/PRED/03/Paravada/005 Construction of cyclone shelter at Mutyalammpalem 11.01.13 1
TOTAL 53
Page 98 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DURING THIS MONTH OF JANUARY 2013
SNO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/AP/RHB/ PRED/04/Katrenikona/003
Road from PR road to Dasarivanipeta and to CycloneShelter 16.012.2013 1
2NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001
Cyclone Shelter at Avulamanda and of Thondangi Mandal, E.G.Dt.
03.01.2013, 11.01.2013, 15.01.2013and 31.01.2013 4
3 Cyclone Shelter at Lakshmanudipeta of ThondangiMandal, E.G.Dt.
03.01.2013, 11.01.2013, 15.01.2013and 31.01.2013 4
4 NCRMP/B-W/ AP/MPCS/PRED/04/Uppalaguptam/002
Cyclone Shelter at Pedaraghavulapeta of UppalaguptamMandal, E.G.Dt.
04.01.2013, 10.01.2013, 12.01.2013,18.01.2013, 22.01.2013, 24.01.2013
and 30.01.2013.7
TOTAL 16
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS OF WEST GODAVARI DISTRICT (YEAR-II WORKS) DURING THIS MONTH JANUARY2013
SNO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISITS NO. OF VISITS
1. NCRMP/B-W/AP/RCS/PRED/05/Achanta/002 Road from R&B road to Ayodya lanka Marrimula cyclone shelter. 19.01.2013 1
2.NCRMP/B-W/AP/RCS/PRED/05/Kalla/003
Road from R&B road to Modi Cyclone Shelter 10.01.2013 1
3. Road from R&B road to S.C Bose Colony Cyclone Shleter 10.01.2013 1
4. NCRMP/B-W/AP/RCS/PRED/05/Bhimavaram/004
Construction of approach road to cyclone shelter in Losari of BhimavaramMandal. 02.01.2013 1
Page 99 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
12. NCRMP/B-W/AP/RHB/PRED/05/Kalla/004 K.G. R&B Road to Mamidipudi of Kalawapudi. 10.01.2013 1
13.NCRMP/B-
W/AP/RHB/PRED/05/Bhimavaram/005
Road from Dongapindi R & B Road to Revu (Pallipalem) in Dongapindi ofBhimavaram Mandal. 02.01.2013 1
14. Road from R & B Road to Sarvodhyanagar (Garivelladibba) H/o Losari ofBhimavaram Mandal. 02.01.2013 1
41. NCRMP/B-W/AP/MPCS/PRED/05/Narsapur/001
Sardupalli Palem of Vemuladeevi 23.01.2013 1
42. Pedamynavani lanka 23.01.2013 1
43. NCRMP/B-W/AP/MPCS/PRED/05/Narsapur/003
Chinamynavani lanka 23.01.2013 1
44. Vemuladeevi East 23.01.2013 1
45. NCRMP/B-W/AP/MPCS/PRED/05/Mogalturu/002
Yetimondi of Perupalem 24.01.2013 1
46. Bellamkondavarimeraka 24.01.2013 1
Total 13
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN KRISHNA DISTRICT DURING THE MONTH JANUARY 2013
SNO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISITS NO. OFVISITS
1 NCRMP/B-W/AP/RCS/PRED/06/Nagayalanka/006
Road from China Zinkapalem to Gollamanda via peda Zinkapalem 09.01.13 1
Road from R&B road to Cyclone Shelter at Gollamanda 09.01.13 1
Road from ZP Road to Cyclone shelter at Natchugunta 09.01.13 1
Road from Krishna river to Elechetla Dibba Cyclone shelter 09.01.13 1
2 NCRMP/B-W/AP/RHB/PRED/06/Nagayalanka/009 Road from R&B Road Dananjaya Colony to Krishnapuram 09.01.13 1
TOTAL 5
Page 100 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DISTRICT DURING THIS MONTH OF JANUARY- 2013
SNO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OFVISITS
1
NCRMP/B-W/AP/RCS/PRED/07/Karalapalem/002
Road from Ganapavaram R&B Road to Pedamarpuvaripalem.7.1.2013, 8.1.203, 17.1.2013,
26.1.2013, 27.1.2013, 30.1.2013,31.1.2013.
7
2 Road from R&B road to chinapuluguvaripalem 5.1.2013, 30.1.2013, 31.1.2013. 3
3 Road from Ganapavaram PR Road to Bonthagorlapalem. 5.1.2013 1
4 NCRMP/B-W/AP/Br/R&B/07/Bapatla/010
Reconstruction of HLB @ km 5/2 of Bapatla - Suryalanka roadacross perali drain in Guntur District. 8.1.2013, 10.1.2013. 2
5 NCRMP/B-W/AP/RCS/PRED/07/Pvpalem/001
Road from R & B Road to Hanumanth Nagar. 31.1.2013. 1
6 Road from R & B Road to Adarshnagar. 31.1.2013. 1
7 NCRMP/B-W/AP/RCS/PRED/07/Pvpalem/001 Road from R & B Road Allur to Yadavapalem 4.1.2013, 5.1.2013, 7.1.2013, 8.1.2013. 4
TOTAL 19
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THE MONTH OF JANUARY-13
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/APMPCS/PRED/08/NG Padu/003 Kanaparthy cyclone shelter in Nagulappapadu mandal. 04.01.2013 1
2 NCRMP/B-W/AP/Br/R&B/08/Kanaparthi/012
Construction of High level Bridge at Km 16/10 ofNaguluppalapadu – Kanaparthi road in Prakasam District 03.01.2013 1
Page 101 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from NH5 to Mulaguntapadu 05.01.2013, 10.01.2013, 15.01.2013
29.01.2013, 30.01.2013, 31.01.2013 6
4 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne
05.01.2013, 10.01.2013, 15.01.201326.01.2013, 28.01.2013, 29.01.2013
31.01.20137
5 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002
Road from R&B road to Binginapalli Harijanawada CycloneShelter 10.01.2013 1
6 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Chalivendradibba 10.01.2013, 15.01.2013, 23.01.2013
25.01.2013, 28.01.2013 5
7 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001
Road from Pakala ZP Road to Aulavaripalem Cycloneshelter 10.01.2013 1
8 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Road from R&B Road to Somarajupalli 10.01.2013 1
9 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Road from R&B road to Narravaripalem 10.01.2013 1
10 NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07 Road from MC Road to Subbarayudu Satram 11.01.2013 1
11 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09 Road from R&B road Pellur to Vasepallipadu 10.01.2013, 23.01.2013
24.01.2013, 28.01.2013 4
12 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10 Road from R&B road to Kesupalem 10.01.2013 1
13 NCRMP/B-W/APMPCS/PRED/08/Ulavapadu/001
Chakicherla cyclone shelter in Ulavapadu mandalprakasam district 11.01.2013 1
TOTAL 31
Page 102 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN NELLORE DISTRICT DURING THE MONTH OF JANUARY 2013
SLNO Package Number Name of work
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISITS NO. OFVISITS
1 NCRMP/B-W/AP/RHB/PRED/09/V.CHALEM/RHB/007
Providing BT Surface to the road from R&B road toEdagali kandriga 01.01.2013, 02.01.2013 2
2 NCRMP/B-W/AP/RHB/PRED/09/V.CHALEM/RHB/007
Road from Suvepalli-Pudiparthi road to SrikanthColony 01.01.2013, 02.01.2013 2
3 NCRMP/B-W/AP/PRED/09/MUTHUKUR/RHB/006 Road from R&B road to Patuvarikandriga 01.01.2013 1
4 NCRMP/B-W/AP/PRED/09/MUTHUKUR/RCS/002
Road from R&B Road kappaladoruvu to bandla palemH.wada 01.01.2013 1
5 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005 Road from KT R&B road to Allaganipadu to vavilla 11.01.2013 1
6 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005
Road from R&B road Kancharlapalam HW toAlaganipadu.
09.01.2013, 11.01.2013,21.01.2013, 24.01.2013 4
7 NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006
Road Connecting R&B Road through Voturu Villagein SPSR Nellore District 21.01.2013 1
8 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 Providing BT road to Peda Pannam Gadu in TadaMandal of Nellore Dt. 09.01.2013, 31.01.2013 2
9 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 Road from @ km 56/8 to CK Road to PeriyavettuKuppam Cyclone Shelter 09.01.2013, 31.01.2013 2
10 NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012
Ring Road to TP Gudur- Salipeta R & B Road via CSPuram and Mandapam Village 16.01.2013 1
11 NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012 Road from R & B Road C S Puram to Sivaramapuram 16.01.2013 1
Total 18
Page 103 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
9.2 Statement Showing the Inspections and Site Visits of Districts during the Month of February -2013
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THE MONTH OF FEBRUARY 2013
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OF VISITS
1 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of Cyclone shelter at Runku inSanthabommali Mandal.
09.02.2013, 11.02.2013,12.02.2013, 13.02.2013,18.02.2013, 25.02.2013
6
2 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of Cyclone shelter at Kollipadu inSanthabommali Mandal.
11.02.2013, 12.02.2013,25.02.2013 3
3 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Kotcherla road to Pathasundarapalem 7.02.13 1
4 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005
Road from Kotcherla road to Kollibhemavaram & tocyclone shelter 7.02.13 1
5 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Mentada to Dovupeta 7.02.2013, 11.02.2013 2
6 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Koyyam R&B road to Moosavanipeta 7.02.13 1
7 NCRMP/B_W/BR/R&B/01/uppigedda/002
Construction of HLB across Uppugedda at Km 7/6 ofSrikakulam municipal limits to Pukkalapeta 8.02.2013, 11.02.2013 2
8 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001
Construction of Bridge at km 11/6-8 of NH-5 toPatnavanipeta connecting Sundarapalem.
7.02.2013, 8.02.2013,11.02.2013, 16.02.2013 4
TOTAL 20
Page 104 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THE MONTH OF FEBRUARY- 2013
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OF VISITS
1 NCRMP/B-W/AP/Br/R&B/02/Chakaligadda/008
Construction of Minor Bridge at Km 15/2 near Chakaligadda ofKonada Ramatheertham R&B road to Konatalapalem (via)Yerukonda, Pasupam, Kollayavalasa (ZP Road) inVizianagaram District.
05.02.201315.02.201319.02.201328.02.2013
4
Total 4
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISAKHAPATNAM DISTRICT DURING THE MONTH OF FEBRUARY - 2013
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTHDATES OF VISIT NO. OF VISITS
1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004
Construction of cyclone shelter at Venkayyapalem in RambilliMandal 04.02.2013 14.02.2013 2
2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda in Nakkapalli Mandal 06.02.2013 12.02.2013
21.02.2013 26.02.2013 4
3 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Mullaparra in Nakkapalli Mandal 06.02.2013 12.02.2013
21.02.2013 26.02.2013 4
4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cyclone shelter at Bangarrampeta in NakkapalliMandal 21.02.2013 26.02.2013 2
5 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cyclone shelter at Ratnayampeta in PayakaraopetaMandal
09.02.2013 12.02.201325.02.2013 26.02.2013 4
Page 105 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
6 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cyclone shelter at Gajapathinagaram inPayakaraopeta Mandal
09.02.2013 12.02.201325.02.2013 26.02.2013 4
7 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Kattubolu to Marriaplem 16.02.2013 1
8 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Krishnampalem 16.02.2013 1
9 NCRMP/B-W/AP/RHB/PRED/03/Achutapuram/007 Road from R & B road to Avarajam 16.02.2013 1
10 NCRMP/B-W/AP/RHB/PRED/03/Achutapuram/007 Road from R & B road to Avasomavaram 16.02.2013 1
11 NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R & B road to Jalaripeta 16.02.2013 1
12 NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R & B road to Pothurajanapalem 16.02.2013 20.02.2013 2
13 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from R&B road to Pedateenarla to Chinateenarla 09.02.2013 1
14 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from Upamaka Rajayyapeta R&B road to Janakayyapeta 09.02.2013 1
15 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001 Providing B.T to the road from Vempudi to Patimeeda 09.02.2013 1
16 NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006 Road from R&B Road to Revupolavaram Cyclone shelter 12.02.2013 1
17 NCRMP/B-W/AP/MPCS/PRED/03/S.Rayavaram/009
Construction of Cyclone shelter at Bangarampalem I&II H/OVakadu. 12.02.2013 1
18 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from R&B road to Rajvaram 12.02.2013 1
19 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Rajayyapeta 12.02.2013 1
Page 106 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
20 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008 Road from ZP Road Palamanpeta to Korlayyapeta 12.02.2013 1
21 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Kumarapuram 12.02.2013 1
22 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Palmanpeta 12.02.2013 1
23 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from Rajala R&B road to Rajarayyudupalem 16.02.2013 1
24 NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005 Road from R&B road to Annavaram cyclone shelter 08.02.2013 1
25 NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005 Road from R&B road to Chinanagamayyapalem cyclone shelter 08.02.2013 1
26 NCRMP/B-W/AP/MPCS/PRED/03/Bheemili/008 Construction of cyclone shelter at Chepala Dibbadapalem. 08.02.2013 1
27 NCRMP/B-W/AP/MPCS/PRED/03/Bheemili/008
Construction of cyclone shelter at Boyaveedhi (Bheemili Municipalityarea ) 08.02.2013 1
28 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B Road to Rajakoduru in Rambilli Mandal 23.02.2013 1
TOTAL 43
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DISTRICT DURING THIS MONTH OF FEBRUARY 2013
Sl.No PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OF VISITS
1 NCRMP/B-W/ AP/RHB/ PRED/04/ KARAPA/001 Road from Gurajanapalli to Bandulavaripalem 18.02.2013 1
2 NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001 Cyclone Shelter at Avulamanda and of Thondangi Mandal, E.G.Dt. 13.02.2013 17.02.2013 2
Page 107 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3 Cyclone Shelter at Lakshmanudipeta of Thondangi Mandal, E.G.Dt. 13.02.2013 17.02.2013 2
4 NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002
Cyclone Shelter at Pedaraghavulapeta of Uppalaguptam Mandal,E.G.Dt.
07.02.2013, 14.02.2013,18.02.2013, 20.02.2013,23.02.2013, 25.02.2013
26.02.2013
7
MPCS
5 NCRMP/B-W/AP/MPCS/PRED/04/I.Polavaram/003 Construction of Cyclone Shelter at Byravapalem (Type-D) 08.02.2013 18.02.2013 2
6 NCRMP/B-W/MPCS/PRED/04/Katrenikona/005 Construction of Cyclone Shelter at Mogasanitippa (Type-B) 12.02.2013 1
7 NCRMP/B-W/ AP/MPCS/PRED/04/Katrenikona/006
Construction of Cyclone Shelter at Balusutippa of KatrenikonaMandal in E.G.Dt. Type-D 18.02.2013 1
8
NCRMP/B-W/AP/MPCS/PRED/04/Katrenikona/007
Construction of Cyclone Shelter at Kothapalem 07.02.2013 18.02.2013 2
9 Construction of Cyclone Shelter at Molletimogga 07.02.2013 18.02.2013 2
10 Construction of Cyclone Shelter at Neelarevu-1 07.02.2013 1
11 Construction of Cyclone Shelter at Chirrayanam 07.02.2013 1
12 NCRMP/B-W/AP/MPCS/PRED/04/Katrenikona/008
Construction of Cyclone Shelter at Pallamkurru. 07.02.2013 18.02.2013 2
13 Construction of Cyclone Shelter at Pandi. 07.02.2013 1
14NCRMP/B-W/MPCS/PRED/04/Allavaram/009
Construction of Cyclone Shelter at Rameswaram (Type-A) 12.02.2013 1
15 Construction of Cyclone Shelter at samanthakuru (Type-B) 12.02.2013 1
16NCRMP/B-W/MPCS/PRED/04/Sakhinetipalli/010
Construction of Cyclone Shelter at Pallipalem (Type-D) 09.02.2013 1
17 Construction of Cyclone Shelter at Kesavadasupalem (Type-D) 09.02.2013 1
18 NCRMP/B-W/MPCS/PRED/04/Malikipuram/011 Construction of Cyclone Shelter at Kesanapalli (Type-D) 09.02.2013 1
Page 108 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
19 Construction of Cyclone Shelter at Padamatipalem (Type-D) 09.02.2013 1
20 NCRMP/B-W/MPCS/PRED/04/Mamidikudurua/012 Construction of Cyclone Shelter at Karavaka (Type-B) 09.02.2013 1
RHB
21 NCRMP/B-W/AP/RHB/PRED/04/Sakhinetipalli/008
Road from R&B road to Korukondavari group 09.02.2013 1
22 Road from R&B road to Gondi Kodapa 09.02.2013 1
23NCRMP/B-W/AP/RHB/PRED/04/Allavaram/012
BT Road from Komaragiripatnam to Kadadari and to Cyclone shelter 12.02.2013 1
24 Road from R&B road to Samanthakuru to ChakkavaripetaRamaswaram 12.02.2013 1
25NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/014
Road from R&B road to Guthanadeevi Gogulanka 08.02.201318.02.2013 2
26 Road from R&B Road to Ramalayampeta Pallamkurru (V) 18.02.2013 1
27 NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/016 Road from N.Kothapalli to G.Pora in Katrenikona 07.02.2013
18.02.2013 2
28NCRMP/B-W/AP/RHB/PRED/04/I.Polavaram&Tallarevu/009
Road from Gogullanka to Byravalanka. 08.02.2013 1
29 Road from G.Vemavaram to Gandivaripalem of G.Vemavaram. 09.02.2013 1
30 NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/016 Road from R&B road to Aravapalem 09.02.2013 1
RCS
31
NCRMP/B-W/AP/RCS/PRED/04/Malikipuram/009
Approach road from R&B road to Turupupalem Cyclone Shelter 09.02.2013 1
32 Road from R&B road to Kesanapalli (New) Cyclone Shelter 09.02.2013 1
33 Road from R&B road to Padamatipalem Cyclone Shelter 09.02.2013 1
34NCRMP/B-W/AP/RCS/PRED/04/Razole&Sakhinetipalli/010
Road from R&B road to Katrenipadu Lanka Cyclone Shelter 09.02.2013 1
35 Road from R&B road to Kesavadasupalem (New) Cyclone Shelter 09.02.2013 1
Page 109 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
36 NCRMP/B-W/AP/RCS/PRED/04/Mamidikuduru/013 Road from R&B road to Karavaka Cyclone Shelter 09.02.2013 1
37 NCRMP/B-W/AP/RCS/PRED/04/Katrenikona/015
CC Road from main proposed road to Neelarevu II Cyclone shelterin Neellarevu 07.02.2013 1
38 NCRMP/B-W/AP/RCS/PRED/04/Allavaram/016 Road from R&B road to Samanthakurru Cyclone Shelter 12.02.2013 1
Total 52
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN WEST GODAVARI DISTRICT DURING THE MONTH FEBRUARY 2013
S NO. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISITS NO. OF VISITS
9.
NCRMP/B-W/AP/RCS/PRED/05/Narsapur/006
R&B road to Chinamynavanilanka 19.02.2013 1
10. P.R road to Ramanujapuram 19.02.2013 1
11. Road from P.R road to Prakasapuram 19.02.2013 1
15. NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/006 Khalipatnam R&B Road to Khalipatnam ferry 19.02.2013 1
26.
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/010
Road from SP R&B road to Pasaladeevi 14.02.2013 1
27. LT R&B road to Modi 14.02.2013 1
28. SP R&B road to Gannabathulavari palem of Chamakuripalem 14.02.2013 1
29.
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/012
Road from R&B road to SC Colony of Pedalanka 19.02.2013 1
30. R&B road to Rajeev Nagar of Darbharevu 19.02.2013 1
31. SP R&B road to Pedathota of Turputallu 19.02.2013 1
Page 110 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
32. R&B road to Peta of Turputallu 19.02.2013 1
33. R&B road to Pedathota of Turputallu 19.02.2013 1
34.
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/013
R&B road to Guttulavarimeraka 12.02.2013 1
35. Road from R & B Road to Pulaparthivaripalem 12.02.2013 1
36. R&B road to Pedaedigapalem 12.02.2013 1
37. R&B road to Evanivarimeraka 12.02.2013 1
Total 16
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DURING THE MONTH OF FEBRUARY 2013
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THEMONTH
DATES OF VISIT NO. OF VISITS
1 NCRMP/B-W/AP/BR/R&B/07/Bapatla/010
Re construction Of HLB@ km 5/2 of Bapatla - Suryalanka Road acrossperali drain in Guntur DT. 4.2.2013 1
2
NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002
Road from Ganapavaram R&B raod to Pedamarpuvaripalem. 27.02.2013 1
3 Road from R&B raod to Chinapuluguvaripalem. 27.02.2013 1
4 Road from Ganapavaram PR Road to Bonthagorlapalem. 4.02.2013 1
5NCRMP/B-W/AP/RCS/PRED/
07/karlapalem/002
Road from R&B Road to HanumanthNagar. 4.02.2013 1
6 Road from R&B Road to AdarshNagar. 4.02.2013 1
7 NCRMP/B-W/AP/RCS/PRED/07/karlapalem/002 Road from R&B Road to Pedagollapalem Cyclone sheltor. 4.02.2013 1
Page 111 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
8 Road from R&B Road to Yaramvaripalem. 4.02.201227.02.2013 2
9 NCRMP/B-W/AP/RCS/PRED/07/PV palem/001 Road from R&B Road to Mandevaripalem. 4.02.2013 1
10 Year II Chandolu bridge to Nizampatnam road in km 14/6 in Guntur dt 18.02.2013 1
11 Year II Molugunta to Kothapalem road in Km ¼ in Nizampatnam mandal of GunturDistrict. 18.02.2013 1
12 NCRMP/B-W/AP/RCS/PRED/07/PV palem/001 Road from R&B Road Alluru to Yadavapalem. 18.02.2013,
27.02.2013 2
13 NCRMP/B-W/AP/Br/R&B/07/bapatla/011
Re construction of HLB @ km 2/4 Of Bapatla- pandurangapuram roadacross Perali drain 27.02.2013 1
14 Phase -1Alternate works
Road from NH 214 to Dandubata (via) M.V.Rajupalem in KarlapalemMandal 4.02.2013 1
TOTAL 16
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THE MONTH OF FEBRUARY-2013
S NO. PACKAGE NO NAME OF WORKTPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OF VISITS
1 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from NH5 to Mulaguntapadu
01.02.2013, 02.02.201315.02.2013, 18.02.2013
26.02.20135
2 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne
01.02.2013, 02.02.201315.02.2013, 21.02.2013
26.02.20135
3 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Binginapalli Harijanawada Cyclone Shelter 12.02.2013 1
4 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Chalivendradibba
01.02.2013, 02.02.201315.02.2013, 21.02.2013
26.02.20135
TOTAL 16
Page 112 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SPSR NELLORE DISTRICT DURING THE MONTH OF FEBRUARY 2013
SLNO Package Number Name of work
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISITS NO. OFVISITS
1 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005 Road from KT R&B road to Allaganipadu to vavilla 06.02.13 1
2 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005 Road from R&B road Kancharlapalam HW to Alaganipadu. 06.02.13, 25.02.13 2
3 NCRMP/B-W/AP/RCS/PRED/09/TADA/009
Providing BT road to Peda Pannam Gadu in Tada Mandal of NelloreDt.
01.02.13, 06.02.13, 12.02.13,20.02.13 4
4 NCRMP/B-W/AP/RCS/PRED/09/TADA/009
Road from @ km 56/8 to CK Road to Periyavettu KuppamCyclone Shelter 12.02.13, 20.02.13 2
5 NCRMP/B-W/AP/RHB/PRED/09/CHITTAMURU/003 Road from R&B Chittamur to Soma Samudram 01.02.13 1
6 NCRMP/B-W/AP/RHB/PRED/09/RHB/KAVALI/004 Road from pedattapupalem R&B road to chennyapalam H.wada 11.02.13 1
Year-II
7 NCRMP/B-W/AP/RHB/PRED/09/Kota/023 Road from At km 22/5 of Yamadinne palem road to Gunnampadia 22.02.13, 28.02.13 2
8 NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/021
Road from Thirumalammapalem R&B Road to Gajulapalli Koneru inV.Chalam mandal 15.02.13, 28.02.13 2
Total 15
Page 113 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
9.3 Statement Showing the Inspections and Site Visits of Districts during the Month of March -2013
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THIS MONTH OF MARCH 2013
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005 Construction of Cyclone shelter at Runku in Santhabommali Mandal. 4.03.13,8.03.13,11.3.13,1
9.3.13,25.3.13 5
2 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Deppuru, bhadapalli road to Onkuluru & cyclone shelter. 15.03.13 1
3 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram 15.03.13 1
4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komrlathada&Cyclonic shelter 15.03.13 1
5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B ROAD TO Devunalthada 15.03.13 1
6 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005
Construction of Cyclone shelter at Kollipadu in SanthabommaliMandal.
4.3.13,7.3.13,8.3.13,11.3.13,19.3.13,26.3.13 6
8 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Talasamudram to Dola regulator 31.03.13 1
9 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006
Road from Mabagam R&B road to Dubbakavanipeta viagajapathinagaram. 31.03.13 1
10 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/005
Road from R&B road Edullavalasa-Killam to jonnam viatalasamudram 31.03.13 1
11 NCRMP/B_W/BR/R&B/01/uppigedda/002
Construction of HLB across uppugedda at Km 7/6 of Srikakulammunicipal limits to Pukkalapeta 14.03.13,22.03.13 2
12 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001
Construction of Bridge at km 11/6-8 of NH-5 to Patnavanipetaconnecting Sundarapalem. 13.03.13 1
TOTAL 21
Page 114 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THIS MONTH OF March - 2013
SlNo. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/AP/RD/R&B/ 02/Konada/009
Improvements to Road from Konada Ramatheertham (R&B) Roadto Konathalapalem (Via) Pasupam, Yerukonda, Kollayavalasa fromKm 12/0 to 16/5 (Km 0/0 to 4/0 i.e. upto NH-5 crossing) inVizianagaram District, Andhra Pradesh
07.03.13 1
2 NCRMP/B-W/ AP/ Br/ R&B/ 02/Pulligadda/ 007
Construction of Minor Bridge at Km. 7/2 near Puligadda of Konada –Ramatheertham R&B Road to Konathalapalem via Yerukonda,Pasupam, Kollayavalasa (Z.P. Road)
07.03.13 1
3 NCRMP/B-W/ AP/ Br/ R&B/ 02/Chakaligadda /008
Construction of Minor Bridge at Km 15/2 near Chakaligadda ofKonada Ramatheertham R&B road to Konatalapalem (via)Yerukonda, Pasupam, Kollayavalasa (ZP Road) in VizianagaramDistrict.
07.03.1312.03.1326.03.13
3
Total 5
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISAKHAPATNAM DISTRICT DURING THIS MONTH OF MARCH - 2013
SlNo. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004
Construction of cyclone shelter at Venkayyapalem inRambilli Mandal
05.03.13, 08.03.13, 09.03.13,20.03.13, 22.03.13, 25.03.13,
28.03.137
2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cyclone shelter at Patimeeda in NakkapalliMandal
04.03.13, 08.03.13, 14.03.13,18.03.13, 19.03.13, 25.03.13,
28.03.137
Page 115 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cyclone shelter at Mullaparra in NakkapalliMandal
04.03.13, 08.03.13, 14.03.13,18.03.13, 19.03.13, 25.03.13,
28.03.137
4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cyclone shelter at Bangarrampeta inNakkapalli Mandal
04.03.13, 08.03.13, 14.03.13,18.03.13, 19.03.13, 25.03.13,
28.03.137
5 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cyclone shelter at Ratnayampeta inPayakaraopeta Mandal 08.03.13, 18.03.13, 28.03.13 3
6 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cyclone shelter at Gajapathinagaram inPayakaraopeta Mandal 08.03.13, 18.03.13, 28.03.13 3
7 NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006 Road from R&B Road to Revupolavaram Cyclone shelter . 21.03.13, 25.03.13, 27.03.13,
28.03.13 4
8 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from R&B road to Rajvaram 15.03.13, 18.03.13, 21.03.13,
25.03.13, 28.03.13 5
9 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from R&B road to Gajareddypalem 13.03.13, 20.03.13, 21.03.13,
25.03.13 3
10 NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/009 Road from R&B road to Vadapalem 13.03.13, 20.03.13 2
TOTAL 48
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DISTRICT DURING THIS MONTH OF MARCH 2013
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/ AP/RCS/ PRED/04/KARAPA/001
ROAD FROM APPROACH ROAD TO CYCLONESHELTER AT ADAVIPUDI IN E.G.Dt. 20.03.2013 1
2 NCRMP/B-W/ AP/RHB/ PRED/04/KARAPA/001
ROAD FROM GURAJANAPALLI TOBANDULAVARIPALEM 20.03.2013 1
Page 116 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001
Cyclone Shelter at Avulamanda and of Thondangi Mandal ,E.G.Dt.
05.03.2013, 14.03.2013, 18.03.2013,25.03.2013 & 29.03.2013 5
4 Cyclone Shelter at Lakshmanudipeta of Thondangi Mandal,E.G.Dt.
05.03.2013, 14.03.2013, 18.03.2013,25.03.2013 & 29.03.2013 5
5 NCRMP/B-W/ AP/MPCS/PRED/04/Uppalaguptam/002
Cyclone Shelter at Pedaraghavulapeta of UppalaguptamMandal, E.G.Dt.
07.03.2013, 11.03.2013 &22.03.2013. 3
Total 15
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DISTRICT DURING THIS MONTH OF MARCH 2013
SlNo. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003 Road from R&B Road to Alavaripalem. 1.03.2013 1
2 NCRMP/B-W/AP/RCS/PRED/07/karlapalem/002
Road from R&B Road to Chinapuluguvaripalem. 5.03.13,23.03.2013 2
3 Road from Ganapavaram R&B Road to Pedamarpuvaripalem. 23.03.2013 1
4NCRMP/B-W/AP/RCS/PRED/07/Pvpalem/002
Road from R&B Road Alluru to Yadavapalem. 7.03.2013, 23.03.2013. 2
5 Road from R&B Road mandevaripalem. 1.03.2013 1
6 NCRMP/B-W/AP/Br/R&B/07/Bapatla/011
Re construction of HLB @km 2/4 of Bapatla -Pandurangapuramroad across peralidrain in Guntur Dt. 7.03.2013 1
Year-2
7 NCRMP/B-W/AP/MPCS/PRED/07/NZM/004
Construction of Multi Purpose Cyclone Shelter at Fisherman Colonyof Nizampatnam Village of Nizampatnam Mandal 15.03.2013 1
Page 117 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
8 NCRMP/B-W/AP/MPCS/PRED/07/NZM/004
Construction of Multi-Purpose Cyclone Shelter at Padamata veedhiof Nizampatnam Village of Nizampatnam Mandal. 15.03.2013 1
9 NCRMP/B-W/AP/MPCS/PRED/07/NZM/004
Construction of Multi-Purpose Cyclone Shelter Near MRO Office inNizampatnam, Nizampatnam Mandal. 15.03.2013 2
10 NCRMP/B-W/AP/MPCS/PRED/07/Repalle/005 Lankevanidibba 15.03.2013, 20.03.2013 2
11 NCRMP/B-W/AP/MPCS/PRED/07/Nizampatham/003 Sanjeevanagar of Kothaptnam 15.03.2013 1
12 MPCSRCS/PRED/07/Repalle/001 Mollagunta of Kattava 15.03.2013 1
13MPCSRCS/PRED/07/Nizampatnam/001
At Harbour of Nizampatnam village 15.03.2013 1
14 At Nakshatranagar of Kothapalem 15.03.2013 1
TOTAL 18
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THIS MONTH OF MARCH-2013
Sl.No. PACKAGE NO NAME OF WORK
TPQA INSPECTIONS DURING THISMONTH
DATES OF VISIT NO. OFVISITS
1 NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001 Road from R&B road to vijayanagar colony cyclone shelter 02.03.2013 1
2 NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001 Road from R&B road to cyclone shelter at Mankenavaripalem 02.03.2013 1
3 NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001 Road from R&B road to Ramnagar colony cyclone shelter 02.03.2013 1
4 NCRMP/B-W/APMPCS/PRED/08/NGPadu/003 Kanaparthy cyclone shelter in Nagulappapadu mandal. 12.03.2013
14.03.2013 2
Page 118 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
5 NCRMP/B-W/AP/Br/R&B/08/Kanaparthi/012
Construction of High level Bridge at Km 16/10 of Naguluppalapadu– Kanaparthi road in Prakasam District 12.03.2013 1
6 Year-2 Road from ZP road to Sriramapattapupalem in Ulavapadu Mandal 14.03.201321.03.2013 2
7 Year-2 Road from MC Road to Veerapalli in Ulavapadu mandal. 14.03.201321.03.2013 2
8 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from NH5 to Mulaguntapadu 23.03.2013
28.03.2013 2
9 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne 23.03.2013
28.03.2013 2
10 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Chalivendradibba 23.03.2013
28.03.2013 2
total 16
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN NELLORE DISTRICT DURING THIS MONTH OF MARCH2013
Sl.No. Package Number Name of work
TPQA INSPECTIONS DURING THIS MONTH
DATES OF VISITS NO. OFVISITS
1 NCRMP/B-W/AP/RCS/PRED/09/TADA/009
Providing BT road to Peda Pannam Gadu in TadaMandal of Nellore Dt.
02.03.2013, 13.03.2013,20.03.2013, 25.03.2013 4
2 NCRMP/B-W/AP/RCS/PRED/09/TADA/009
Road from @ km 56/8 to CK Road to PeriyavettuKuppam Cyclone Shelter
02.03.2013, 20.03.2013,25.03.2013 3
Year-II
3 NCRMP/B-W/AP/RHB/PRED/09/Kota/023
Road from At km 22/5 of Yamadinne palem road toGunnampadia
06.03.2013, 23.03.2013,28.03.2013 3
4 NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/021
Road from Thirumalammapalem R&B Road toGajulapalli Koneru in V.Chalam mandal
14.03.2013, 22.03.2013,30.03.2013 3
Total 13
Page 119 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
10. Grama Sabhas for Community based Cyclone Shelter Management Maintenance WelfareCommittees (CSMMWC):
As per the instruction from the Client, The field staff (Social) of TPQA Consultant are involved in organizing the Grama
Sabhas to form committees for the cyclone shelters from 12-03-2013 to 25-03-2013 in Guntur, Machalipatnam, West
Godavari and East Godavari districts. The Grama Sabhas were conducted smoothly and in some of the villages, the
Secretary was unanimously elected by the local people. However, some suggestions were made by the people during the
Grama Sabhas which are as follows.
Suggestions made by the people in Grama Sabhas
It will be better if some honorarium or incentive is provided to the Secretary.
The Secretary alone cannot manage the shelter. He shall be associated with the VRO or the local Panchayat
Secretary. Then only the management will be strong.
As the government is planning to keep equipment for cyclone warning and some utensils in kitchen to cook during
cyclone period, there is a need for a watchman who shall reside in the Cyclone shelter so that there will be safety
for the material and building.
During the cyclone, no electricity or solar system will work in the shelter. Some alternative arrangement shall be
made for lighting in the shelter. There shall be provision for Generator.
Precautions for health and nutrition shall be made much before the rainy season.
In this regard, the field staff (Social) would like to make the following suggestions:
Suggestions by the Field Staff (Social)
The utilization of local knowledge and resources will be more useful and the people shall be educated through
Participatory Rural Appraisal (PRA) exercises.
Already in the Grama Sabhas, the field staff (Social) suggested the health officials to chalk out a program in their
time sheet for health education
The education on health and nutrition shall be regular as the ANM visits the villages regularly
There is need to think about the cooking arrangements and food during the cyclone period
The field staff (Social) also requested the Mandal level officials to organize some of their training programs through
cyclone shelters. In this regard, request was made to MPDO, Fisheries Development Officer, PHC Doctor etc. and
they agreed for the proposal. But formal suggestion shall be made from the government for more effective
implementation of the program.
The Grama Sabhas for Community based Cyclone Shelter Management Maintenance Welfare Committees (CSMMWC) in
March month are started from 12-3-2013 in Guntur district. The MROs and the MPDOs of the respective mandals along with
other mandal level officials who are members in the committee also attended the Grama Sabhas. The field staff (Social) of
TPQA Consultant, Mr. V. Srinivars, Communication Expert, NCRMP, A.P. Secretariat and N. Shyam Sagar. Field
Coordinator, PME, organized the Grama Sabhas. The public and local leaders of the respective villages also attended the
Page 120 of 198
QUARTERLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Grama Sabhas. The details of the district wise Grama Sabhas coordinated by the field staff (Social) were as follows:
GRAMA SABHAS FOR CSMMWC IN GUNTUR Dist.,Date Mandal Gramasabhas Remarks
14-03-2013 Nizampatnam
1) Harbour of Nizampatnam2) Nakshatra Nagar3) Sanjeevanagar4) Fishermen colony5) Near MRO office6) Padamativeedhi
14-03-2013 Repelle 7) Mollagunta of Katta8) Lankavanidibba
GRAMA SABHAS FOR CSMMWC IN WEST GODAVARI Dist.,Date Mandal Gramasabhas Remarks
20-03-2013 Narsapur
1) Sardupallipalem
Secretary elected unanimously
2) Chinmyavani Lanka3) Pedamaghavani Lanka4) Veemuladeevi (East)
20-03-2013 Mogalturu 5) Intheru6) Pedathadika
GRAMA SABHAS FOR CSMMWC IN KRISHNA Dist.,Date Mandal Gramasabhas Remarks
16-03-2013&
21-03-2013Bandar
1) Poletitippa
Secretary elected unanimously
2) Gilakaladindi3) Pedapatnam-I4) Tallapalem5) V. Kanuru6) Kammavari Cheruvu7) Pallitammalapalem
18-03-2013 Kruthivennu 8) Intheru Secretary elected unanimously9) Pedathadika
GRAMA SABHAS FOR CSMMWC IN EAST GODAVARI Dist.,Date Mandal Gramasabhas Remarks
25-03-2013 Thondangi 1) Avulamanda Secretary elected unanimously2) Laxmanudipeta
Page 121 of 198
Page 122 of 198
Page 123 of 198
Page 124 of 198
Page 125 of 198
Page 126 of 198
Page 127 of 198
Page 128 of 198
Page 129 of 198
Page 130 of 198
Page 131 of 198
Page 132 of 198
Page 133 of 198
Page 134 of 198
Page 135 of 198
Page 136 of 198
Page 137 of 198
Page 138 of 198
Page 139 of 198
Page 140 of 198
Page 141 of 198
Page 142 of 198
Page 143 of 198
Page 144 of 198
PM-TPQA-NCRMP Inspection of Runku Cyclone shelterin Srikakulam District. Stilt floor Slab Centering andreinforcement work is in progress.
PM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Slab centering verification.
PM-TPQA-NCRMP Inspection of Runku shelter inSrikakulam District. Verification slab Reinforcement .
PM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Slab centering verification.
Page 145 of 198
DPM-TPQA-NCRMP Inspection of Runku cyclone shelterin Srikakulam District. Verification of Steps.
PM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Slab centering verification at Beamand column junction.
PM-TPQA-NCRMP Inspection of Runku shelter inSrikakulam District. Verification slab Reinforcement .
PM-TPQA-NCRMP Inspection of Runku shelter inSrikakulam District. Verification slab Reinforcement .
Page 146 of 198
Patimeeda Cyclone shelter in VisakhapatnamDistrict. TPQA inspection on 09-01-2013.
Reinforcement spacing checking.
Reinforcement spacing checking.
Reinforcement spacing checking.
Reinforcement spacing checking.
Page 147 of 198
Patimeeda Cyclone shelter in VisakhapatnamDistrict. TPQA inspection on 09-01-2013.
Concrete temperature checking
Slump checking
Slump checking
Cube casting
Page 148 of 198
Patimeeda Cyclone shelter in VisakhapatnamDistrict. TPQA inspection on 30-01-2013.
Site view
First floor de shuttering work is in progress
Site view
Page 149 of 198
NCRMP,TPQA inspection of Road Connecting R&BRoad through Voturu Village in SPSR Nellore District
on 20.12.2012-View of BT layer
View of BT layer
View of BT layerView of BT layer at curve location
Page 150 of 198
NCRM-TPQA inspection of Providing BT road to Peda PannamGadu in Tada Mandal of Nellore width checking
View of WBM Gr-III layer
Volumetric analysis for WBM Gr-III layer Thickness checking for WBM Gr-III layer
Page 151 of 198
Gradation for WBM Gr-III layerGradation for WBM Gr-III layer
Gradation for WBM Gr-III layer Thickness checking for WBM Gr-III layer
Page 152 of 198
Page 153 of 198
Page 154 of 198
Page 155 of 198
Page 156 of 198
Page 157 of 198
Page 158 of 198
Page 159 of 198
Page 160 of 198
Page 161 of 198
Page 162 of 198
Page 163 of 198
Page 164 of 198
Page 165 of 198
Page 166 of 198
Page 167 of 198
DPM-TPQA-NCRMP Inspection of Runku Cyclone shelterin Srikakulam District on 11-03-2013. Stilt floor Slab
Completed.
DPM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Columns reinforcement verification.
PM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Verifying the alignment of First floor
columns.
PM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Verifying the alignment of First floor
columns.
DPM-TPQA-NCRMP Inspection of Kollipadu Cycloneshelter in Srikakulam District. First floor Slab Completed.
DPM-TPQA-NCRMP Inspection of Kollipadu Shelter inSrikakulam District. First floor curing work is in progress.
DPM-TPQA-NCRMP Inspection of Kollipadu Shelter inSrikakulam District. Verifying the dimensions of First floor
steps.
DPM-TPQA-NCRMP Inspection of Kollipadu Shelter inSrikakulam District on 11-03-2013. Curing for first floor
slab is in progress.
DPM, TPQA inspection on 14-03-2013
FDD testing of GSB
DPM, TPQA inspection on 14-03-2013
FDD testing of GSB
Text Box
Electrical PVC Pipe laying in slab at Cyclone ShelterPadaraghavulapeta in Uppalagutham Mandal, EG Dt
Electrical PVC Pipe laying in slab at Cyclone ShelterPadaraghavulapeta in Uppalagutham Mandal, EG Dt
Electrical PVC Pipe laying in slab at Cyclone Shelter Kollipaduin Santhabommali Mandal in Srikakulam District
Electrical PVC Pipe laying in slab at Cyclone Shelter Kollipaduin Santhabommali Mandal in Srikakulam District.
Wall chipping for Electrical Pipe laying at Cyclone ShelterPatimeeda in Nakkapalli Mandal of Visakhapatnam District
3 phase Distribution board at Cyclone Shelter Avulamanda inThondangi Mandal, EG Dist.
6 Amps Lighting Switch board at Cyclone ShelterGajapathinagaram in Payakaraopeta Mandal of VSKP District
Distribution Board at Cyclone Shelter Ratnayampeta inPayakaraopeta Mandal of Visakhapatnam District.
Electrical wiring in progress at Cyclone Shelter Ratnayampetain Payakaraopeta Mandal of Visakhapatnam District
Colour code for 3 phase wiring at Cyclone ShelterRatnayampeta in Payakaraopeta Mandal of Visakhapatnam Dt
Earth Continuity Testing at Cyclone Shelter ThopupalemKanuparthy in N G Padu Mandal, Ongole District
Earth Electrode Resistance Testing at Cyclone ShelterThopupalem Kanuparthy in N G Padu Mandal, Ongole District