Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC...

18
Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 1 / 13 ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report December 2018 Processing Plant Processing plant load commissioning and ramp up continuing, with strong progress made in overall plant availability and stability during Q4 2018 Consistent progressive increase in zinc and silver recoveries through the quarter Operations now regularly achieving 40-45% total zinc recovery (~70% of overall target nameplate recovery), with up to 49% total zinc recovery recently achieved Quarterly production of 25,500t of zinc concentrate from tailings operations at a grade averaging 47.0% Zn, 7.5% Pb, 6.5% SiO2 & 150g/t Ag Continued improvement in overall grade, with operations now consistently above the average Q4 2018 grade, producing a 47% - 51% zinc concentrate The progressive improvements in both recovery & grade during the quarter has resulted in a 55% increase in the average monthly production rate of zinc metal New Century is now targeting continued progression toward full nameplate plant recoveries in Q2 2019 Shipping & Sales Total 25,000t of zinc concentrate shipments to date (China & Europe) China shipping & sales: First shipment into China (11,000t) completed Further spot sales into China under contract, with next shipment (22,000t) scheduled for March 2019 and monthly shipments anticipated to follow Total 40,000t to date in sales to China completed or under contract Europe shipping & sales: First spot sale & ship loading of zinc concentrate for Europe (14,000t) complete Further European spot sale under contract (11,000t - shipment February 2019) Total 25,000t to date in sales to Europe completed or under contract

Transcript of Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC...

Page 1: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 1 / 13

ASX / MEDIA ANNOUNCEMENT ASX: NCZ

Quarterly Activities Report December 2018

Processing Plant

• Processing plant load commissioning and ramp up continuing, with strong progress

made in overall plant availability and stability during Q4 2018

• Consistent progressive increase in zinc and silver recoveries through the quarter

• Operations now regularly achieving 40-45% total zinc recovery (~70% of overall

target nameplate recovery), with up to 49% total zinc recovery recently achieved

• Quarterly production of 25,500t of zinc concentrate from tailings operations at a

grade averaging 47.0% Zn, 7.5% Pb, 6.5% SiO2 & 150g/t Ag

• Continued improvement in overall grade, with operations now consistently above

the average Q4 2018 grade, producing a 47% - 51% zinc concentrate

• The progressive improvements in both recovery & grade during the quarter has

resulted in a 55% increase in the average monthly production rate of zinc metal

• New Century is now targeting continued progression toward full nameplate plant

recoveries in Q2 2019

Shipping & Sales

• Total 25,000t of zinc concentrate shipments to date (China & Europe)

• China shipping & sales:

� First shipment into China (11,000t) completed

� Further spot sales into China under contract, with next shipment (22,000t)

scheduled for March 2019 and monthly shipments anticipated to follow

� Total 40,000t to date in sales to China completed or under contract

• Europe shipping & sales:

� First spot sale & ship loading of zinc concentrate for Europe (14,000t) complete

� Further European spot sale under contract (11,000t - shipment February 2019)

� Total 25,000t to date in sales to Europe completed or under contract

Page 2: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 2 / 13

� Initial European shipment represents the first zinc concentrate delivered to

New Century’s current long term offtake partners

Hydraulic Mining

• Mining ramp up continuing, with improved operational stability during Q4 2018

• Implementation of a third mining cannon and an additional pump train underway,

targeting production increase to a minimum 8Mtpa and up to 10Mtpa

• Continued strong reconciliation of mining grade to the ore reserve model, with the

ore grade mined during Q4 2018 averaging 2.95% Zn

• New Century is targeting an overall hydraulic mining development timeline of Phase

1 mining rate (8Mtpa) by the end of Q1 2019 and full ramp up to Phase 2 mining rate

(15Mtpa) by end of 2019

Other

• The Expansion PFS, which is assessing potential for development of insitu zinc &

lead resources, now due for completion at the end of Q1 2019, in line with

completion of Phase 1 ramp up of tailings mining rate

• Completion of A$40M senior secured debt facility with NAB

New Century Resources Limited (Company or New Century) (ASX:NCZ) is pleased to provide an

update on load commissioning and operational ramp up at Century during Q4 2018.

Page 3: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 3 / 13

Operational Developments

Processing Plant

• Plant load commissioning and operational ramp up continued throughout Q4 2018, with a

progressive increase in all aspects of production, including metal recovery, concentrate

tonnage and overall product quality

• Consistent increase in zinc and silver recoveries throughout Q4 2018, with the operations now

regularly achieving 40-45% total zinc recoveries (i.e. ~70% of overall target nameplate

recovery) and up to 49% total zinc recovery recently achieved

• Continued improvement in rougher/scavenger recovery, which is now achieving up to full

target nameplate recovery

• Continued program of bottleneck removal in the cleaner circuit, with the first implemented

initiatives already providing a step change in recovery performance

• Q4 2018 concentrate production of 25,500t at 47.0% Zn, 7.5% Pb, 6.5% SiO2 and 150g/t Ag

• Progressive load commissioning process and plant improvements initiatives have resulted in the

average monthly production rate of zinc metal increasing by over 55% during the quarter

During the quarter the Company continued the process of plant load commissioning and operational

ramp up. Strong progress to overall plant availability and stability has been made to date, which is

reflected in continued improvements to all production metrics including the operations now

regularly achieving 40-45% total zinc recovery (~70% of overall target nameplate recovery).

Figure 1: Century’s processing plant ramp up performance against other ASX listed start-up operations through

to the end of Q4 2018 (Source: public company data & Credit Suisse estimates)

Page 4: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 4 / 13

As shown in Figure 2 below, within the overall recovery increase achieved to date, the individual

circuits all continue to improve, via:

• the rougher/scavenger circuit now achieving up to 100% of target nameplate recovery (i.e.

up to 70% of total zinc in the feed recovered into the rougher/scavenger concentrate); and

• the first initiatives associated with the progressive removal of bottlenecks in the cleaner

circuit providing a step change in recovery performance.

The performance of the rougher/scavenger circuit achieving up to 70% total recovery of zinc from

the plant feed is significant, in that only zinc recovered by this circuit can ultimately report to final

product after the cleaning stage.

Figure 2: Flowsheet of operations at the Century Zinc Mine annotated for the current performance of each unit process during the course of the load commissioning process

The plant operations team is also targeting progressive improvement in concentrate quality toward

New Century’s target long term steady state concentrate specification (see Figure 5). During the

quarter, the Company continued to improve the stability of concentrate quality, producing saleable

commissioning grade concentrate averaging 47.0% Zn, 7.5% Pb and 6.5% SiO2 and 150g/t Ag.

The overall grade has continued to improve throughout the quarter, with the operations now above

the average Q4 2018 grade, consistently producing a 47% - 51% zinc concentrate.

As discussed in the ‘Shipping & Sales’ section of this report, the Company has experienced strong

demand for its current commissioning grade concentrate to date, which is anticipated to continue

as concentrate quality improves through the load commissioning process.

Focus for the plant during Q1 2019 remains on maintaining plant uptime and steady state

operations, while continuing the implementation of process improvements, in particular those

associated with the cleaner circuit.

Page 5: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 5 / 13

Figures 3 & 4: Cleaner 1A operational and 1B now online (left) & installation of pipe racks as part of the

refurbishment and upgrade of launder spray and reagent dosing systems (right)

New Century Steady State Specification

New Century Commissioning Specification

McArthur River

(Glencore)

Dugald River (MMG)

Gamsberg (Vedanta)

Red Dog (Teck)

Zn 51 - 54.5 % 46 - 50 % 47% 52% 50% 55.6%

Fe 0.8 - 2.0 % 1.5 - 4.5 % 5.9% 11.0% 8.9% 5.0%

Mn <0.15 % <0.15 % <0.01 % 2.0% 2.6% <0.01 %

SiO2 5.0 - 7.5 % 3.0 - 7.0 % 4.6% 3.5% 2.0% 4.5%

C 3.0 - 5.0 % 3.0 - 5.0 % <0.1% <0.1% 0.2% <0.1%

Cd 0.08 - 0.15 % 0.08 - 0.15 % 0.12% <0.1 % <0.1 % 0.4%

As <0.01 % <0.01 % 0.20% 0.02% <0.01 % 0.02%

Hg <50 ppm <50 ppm 40 ppm 15 ppm 22 ppm 80 ppm

Cu <0.6 % <0.6 % 1.1% 0.2% 0.1% 0.2%

Pb 1.2 - 3.0 % 6.0 - 10.0% 4.6% 0.2% 0.1% 3.8%

S 27 - 30 % 27 - 30 % 30.0% 31.0% 29.4% 31.7%

Ag 50 - 250 ppm 100 - 200 ppm 130 ppm 80 ppm 2 ppm 150 ppm

Figure 5: Peer concentrate comparison of New Century’s current commissioning concentrate and targeted steady

state specification (Source: Wood Mackenzie, August 2018, note peer concentrate specifications are indicative

only and may not represent current concentrate qualities)

Page 6: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 6 / 13

Shipping & Sales

• First shipment of 11,000t of New Century concentrate into China complete

• Further subsequent spot sale contracts into China in place & first spot sales into Europe

• Total 25,000t of shipments completed to date

• Shipments into Europe include the first purchase and delivery of zinc concentrate to New

Century’s existing long term offtake partners

During the quarter, the Company continued to ramp up activities associated with its concentrate

slurry pipeline, port facility and transhipment vessel, culminating in the successful restart of

regular concentrate shipments from the mining operations.

To date 25,000t of zinc concentrate produced from the operations has been shipped, with exports

destined for smelters in both China and Europe. The first shipment to China has been completed

and the second shipment has been loaded and is en-route to Europe.

Completed shipments to date have received no penalties for lead or carbon and only an immaterial

penalty for silica. Table 1: New Century current and projected shipping metrics

Date Contracted Shipments (delivered or scheduled)

China Europe

Q3 2018 - -

Q4 2018 11,000t 14,000t*

Q1 2019 22,000t 11,000t

Total 33,000t 25,000t

* Shipment loading and payment completed early January 2019

The Company has received continued strong demand for its current commissioning grade

concentrate, with 33,000t of Q1 2019 production already under sales contract.

Regular spot sales into China have been achieved via pre-payment contracts, with 11,000t of

40,000t delivered into those contracts to date. The next shipment into China (22,000t) is scheduled

for March 2019, after which regular monthly shipments are anticipated to follow.

Spot sales into Europe have been via CIF contracts, with 14,000t of 25,000t delivered into those

contracts to date. The next shipment into Europe is scheduled for February 2019, with production

of concentrate for this shipment nearing completion.

The first European shipment also represents the first sale to New Century’s long term offtake

partners. New Century continues to progress the overall concentrate quality towards its steady

state specification (see Figure 5), following which it anticipates regular supply to all existing long

term offtake partners.

Page 7: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 7 / 13

Figure 6: First grab of New Century concentrate associated with the initial shipment into China

Figure 7: Discharge of New Century concentrate onto a port stockpile in China

Page 8: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 8 / 13

Hydraulic Mining

• Hydraulic mining progressive ramp up continued throughout Q4 2018

• Mining grades reconciling strongly with the ore reserve model, averaging 2.95% Zn as expected

• Process underway for installation of a third cannon and an additional pump train, to boost the

overall mining rate consistently above 8Mtpa and up to 10Mtpa

During the quarter the Company continued the hydraulic mining ramp up toward the Phase 1

nameplate mining rate (8Mtpa), with the operations currently achieving a rate of up to 7.3Mtpa.

The mining grades during operations to date have reconciled strongly with the mine plan, averaging

2.95% Zn over the quarter.

Figure 8: Century’s hydraulic mining ramp up performance against other ASX listed start-up mining operations to

the end of Q4 2018 (Source: public company data & Credit Suisse estimates)

New Century’s mining contractors NPE are currently rolling out the installation of a third cannon

(currently two in operation) and an additional high pressure water pumping train in order to bring

the operation to a consistent rate above a minimum 8Mtpa and up to 10Mtpa.

The installation of the third cannon at the hydraulic mining operations forms part of the Company’s

existing planned overall expansion up to a 15Mtpa mining rate as part of the Phase 2 process (at

which time a total of five cannons are scheduled to be in operation).

Page 9: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 9 / 13

The third cannon and pump train are targeted to be online by the end of Q1 2019. Other areas of

focus for the hydraulic mining operations for Q1 2019 are on maintaining consistent uptime, steady

state feed density and continuing the ramp up process.

Figures 9 & 10: Overview of hydraulic mining progress at the Century Mine

Page 10: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 10 / 13

Expansion Prefeasibility Study Continuing

During the quarter the Company continued the Expansion PFS to investigate the incorporation of

Century’s existing in-situ Mineral Resources into the current tailings only mine plan.

As outlined in the Restart Feasibility Study (see ASX announcement 28 November 2017), once steady

operations at 8Mtpa have been achieved (Phase 1), the operations are scheduled to ramp-up in

Phase 2 to 15Mtpa on tailings via refurbishment of the remainder of the plant.

While the Company remains fully committed to the Phase 1 operational ramp up, it is assessing the

potential for an improved project value proposition via replacing the Phase 2 expansion on tailings

only to instead compliment the tailings operations with the introduction of in-situ Mineral Resources

on the mining lease (9.3Mt at 10.8% Zn + Pb & 66g/t Ag – see statement of JORC 2012 Resources &

Reserves in this report).

New Century considers that the PFS has the potential to increase the previously announced (tailings

only) 6.3-year mine life and 264,000tpa full scale zinc metal production. Different blending

strategies, as well as plant configurations, are being investigated to determine the optimum

pathway for zinc and lead production from the expanded operations.

Should New Century elect to expand operations via the insitu Mineral Resources, the Company will

refurbish the existing carbon and lead floatation circuits within the plant, enabling production of

separate zinc and lead concentrates as per historical operations.

Completion and release of the PFS has been delayed until the end of Q1 2019, with all resources of

the Company fully focused on the ramp up process for Phase 1 of the current tailings operations.

Once the completion of Phase 1 ramp up is at or nearing completion, the Company will finalise the

Expansion PFS, allowing the selected mine plan and plant configuration from the PFS to form the

basis of detailed design work. Pending the successful outcome of this work, the selected flow sheet

will then be progressively incorporated into site operations.

2018 Exploration IP Program

During the quarter, the Company completed its 2018 Exploration Program, with the focus being an

Induced Polarisation (IP) survey over a section of the Mining Lease considered prospective for

further Century style mineralisation.

Work completed to date has now formed the basis of drill planning of identified targets, which is

scheduled to occur in Q2 2019 on completion of the wet season.

Page 11: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 11 / 13

Corporate Developments

Completion A$40M Debt Facility with NAB

During the quarter the Company completed a A$40M senior secured debt and bank guarantee facility

with National Australia Bank (ASX:NAB).

Provision of this facility followed an extensive process of technical, commercial and legal due

diligence by NAB and the facility is believed to represent the first project debt financing package

provided for a mine rehabilitation and tailings reprocessing operation by a ‘Big 4’ Australian bank.

Other Projects: Kodiak Coal Project (NCZ 70%)

The Kodiak Coal Project is currently on care and maintenance.

The Company continues to consider options with regard to the future of the Kodiak Coking Coal

Project in Alabama, USA, including assessing options in relation to financing, joint venture

opportunities or a disposal of the asset.

To learn more, please visit: www.newcenturyresources.com

For further information, please contact:

New Century Resources Media enquiries

Patrick Walta Shane Goodwin

Managing Director Head of Corporate Affairs

P: +61 3 9070 3300 P: +61 434 039 106

E: [email protected] E: [email protected]

Page 12: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 12 / 13

Statement of JORC 2012 Compliant Resources & Reserves

Mineral Resources

Tonnes (Mt)

Zn (%)

Pb (%)

Ag (g/t)

Zn (t) Pb (t) Ag (Oz)

South Block (Indicated)

6.1 5.3 1.5 43 322,000 90,000 8,550,000

Silver King (Inferred)

2.7 6.9 12.5 120 186,000 337,500 10,500,000

East Fault Block (Inferred) 0.5 11.6 1.1 48 60,000 5,500 800,000

TOTAL 9.3 6.1 4.7 66 568,000 433,000 19,850,000

Ore Reserves Tonnes (Mt)

ZnEq (%)

Zn (%)

Ag (g/t) Zn (t) Pb (t) Ag (Oz)

Century Tails (Proved) 77.3 3.1 3.0 12 2,287,662 - 29,734,819

Zinc Equivalent Calculation

ZnEq was calculated for each block of the Century Tailings Deposit from the estimated block grades.

The ZnEq calculation takes into account, recoveries, payability (including transport and refining

charges) and metal prices in generating a zinc equivalent value for each block grade for Ag and Zn.

ZnEq = Zn%+ + Ag troy oz/t*0.002573. Metal prices used in the calculation are: Zn US$3,000/t, and

Ag US$17.50/troy oz.

Competent Persons Statement

Mineral Resources

The information in this announcement that relates to Inferred Mineral Resources on the Silver King

Deposit and the East Fault Block Deposit was first reported by the Company in its prospectus

released to ASX on 20 June 2017, and the South Block Deposit was first reported by the Company

to the ASX on 15 January 2018. The Company confirms that it is not aware of any new information

or data that materially affects the information included in the original market announcements, and

in the case of estimates of Mineral Resources or Ore Reserves, that all material assumptions and

technical parameters underpinning the estimates in the relevant market announcement continue

to apply and have not materially changed. The Company confirms that the form and context in

which the Competent Person's findings are presented have not been materially modified from the

original market announcement.

Page 13: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 13 / 13

Ore Reserves

The information in this announcement that relates to the Ore Reserve at the Century Tailings

Deposit was first reported by the Company in its ASX announcement titled "New Century Reports

Outstanding Feasibility Results that Confirm a Highly Profitable, Large Scale Production and Low

Cost Operation for the Century Mine Restart" dated 28 November 2017. The Company confirms that

it is not aware of any new information or data that materially affects the information included in

the original market announcement, and in the case of estimates of Mineral Resources or Ore

Reserves, that all material assumptions and technical parameters underpinning the estimates in

the relevant market announcement continue to apply and have not materially changed. The

Company confirms that the form and context in which the Competent Person's findings are

presented have not been materially modified from the original market announcement.

Appendix 1:

The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended

31 December 2018:

Project Location Status Interest

Century Zinc Mine Queensland, Australia

ML 90058 Mt Isa Granted 100%

ML 90045 Mt Isa Granted 100%

EPM 10544 Mt Isa Granted 100%

EPM 26722 Mt Isa Granted 100%

EPM 26772 Mt Isa Granted 100%

EPM 26812 Mt Isa Granted 100%

EPM 26873 Mt Isa Granted 100%

EPM 26868 Mt Isa Application 100%

EPM 26874 Mt Isa Application 100%

EPM 26778 Mt Isa Application 100%

EPM 26976 Mt Isa Application 100%

Kodiak Coking Coal Project Alabama, USA

Coke Seam, Gurnee Property Shelby & Bibb Counties Lease 70%

Atkins Seam, Gurnee Property Shelby & Bibb Counties Lease 70%

Gholson Seam, Gurnee Property Shelby & Bibb Counties Lease 70%

Clark Seam, Gurnee Property Shelby & Bibb Counties Lease 70%

Page 14: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 1

+Rule 5.5

Appendix 5B

Mining exploration entity and oil and gas exploration entity quarterly report

Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/13, 01/09/16

Name of entity

NEW CENTURY RESOURCES LIMITED

ABN Quarter ended (“current quarter”)

53 142 165 080 31 DECEMBER 2018

Consolidated statement of cash flows Current quarter $A’000

Year to date (6 months) $A’000

1. Cash flows from operating activities

31,208 58,646 1.1 Receipts from customers

1.2 Payments for

(678) (3,356) (a) exploration & evaluation

(b) development (46,732) (85,242)

(c) production - -

(d) staff costs (4,041) (7,054)

(e) administration and corporate costs (2,188) (4,622)

1.3 Dividends received (see note 3) - -

1.4 Interest received 110 225

1.5 Interest and other costs of finance paid (1) (2)

1.6 Income taxes paid - -

1.7 Research and development refunds - -

1.8 Other (MMG support fees) (645) (1,297)

1.9 Net cash from / (used in) operating activities

(22,967) (42,702)

2. Cash flows from investing activities

- (407)

2.1 Payments to acquire:

(a) property, plant and equipment

(b) tenements (see item 10) - -

(c) investments - -

(d) other non-current assets - -

Page 15: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 2

Consolidated statement of cash flows Current quarter $A’000

Year to date (6 months) $A’000

2.2 Proceeds from the disposal of:

549 549 (a) property, plant and equipment

(b) tenements (see item 10) - -

(c) investments - -

(d) other non-current assets 1,680 2,200

2.3 Cash flows from loans to other entities - -

2.4 Dividends received (see note 3) - -

2.5 Other - -

2.6 Net cash from / (used in) investing activities

2,229 2,342

3. Cash flows from financing activities

- - 3.1 Proceeds from issues of shares

3.2 Proceeds from issue of convertible notes - -

3.3 Proceeds from exercise of share options - -

3.4 Transaction costs related to issues of shares, convertible notes or options

- (15)

3.5 Proceeds from borrowings 11,438 11,438

3.6 Repayment of borrowings - -

3.7 Transaction costs related to loans and borrowings

(833) (833)

3.8 Dividends paid - -

3.9 Other – MMG Support fee received - 5,750

3.10 Net cash from / (used in) financing activities

10,605 16,340

4. Net increase / (decrease) in cash and cash equivalents for the period

32,195 46,249 4.1 Cash and cash equivalents at beginning of

period

4.2 Net cash from / (used in) operating activities (item 1.9 above)

(22,967)

(42,702)

4.3 Net cash from / (used in) investing activities (item 2.6 above)

2,229

2,342

4.4 Net cash from / (used in) financing activities (item 3.10 above)

10,605

16,340

4.5 Effect of movement in exchange rates on cash held

356

189

4.6 Cash and cash equivalents at end of period

22,418

22,418

Page 16: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 3

5. Reconciliation of cash and cash equivalents at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts

Current quarter $A’000

Previous quarter $A’000

5.1 Bank balances 22,304 25,197

5.2 Call deposits 114 6,998

5.3 Bank overdrafts - -

5.4 Other (provide details) - -

5.5 Cash and cash equivalents at end of quarter (should equal item 4.6 above)

22,418

32,195

6. Payments to directors of the entity and their associates Current quarter $A'000

6.1 Aggregate amount of payments to these parties included in item 1.2 358

6.2 Aggregate amount of cash flow from loans to these parties included in item 2.3

-

6.3 Include below any explanation necessary to understand the transactions included in items 6.1 and 6.2

Payments to directors/director associates for director fees, legal fees and other fees

7. Payments to related entities of the entity and their associates

Current quarter $A'000

7.1 Aggregate amount of payments to these parties included in item 1.2 38

7.2 Aggregate amount of cash flow from loans to these parties included in item 2.3

-

7.3 Include below any explanation necessary to understand the transactions included in items 7.1 and 7.2

Payments to key management personnel

Page 17: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 4

8. Financing facilities available Add notes as necessary for an understanding of the position

Total facility amount at quarter end

$A’000

Amount drawn at quarter end

$A’000

8.1 Loan facilities - -

8.2 Credit standby arrangements - -

8.3 Other (please specify) US$15,000*2

AUD$40,000*1

US$0

AUD$20,000

8.4 Include below a description of each facility above, including the lender, interest rate and whether it is secured or unsecured. If any additional facilities have been entered into or are proposed to be entered into after quarter end, include details of those facilities as well.

*1 A secured A$40M Debt facility with National Australia Bank with options on Debt and Bank Guarantees with a term of 2 years. For further details see the Company's announcement dated 31 October 2018.

*2 Per the Company’s ASX announcement dated 23 April 2018, the Company has a $US15m unsecured debt facility for use as general working capital for operations at the Century Mine from offtake party MRI Trading. The debt facility is structured as a prepayment for zinc concentrates to be delivered under the offtake agreement, with the period for delivery or repayment being 120 days from drawdown. Drawdown on the debt facility is conditional upon, among other things, the commencement of commercial production of zinc concentrate at the Century Zinc Mine.

9. Estimated cash outflows for next quarter $A’000

9.1 Exploration and evaluation 100

9.2 Development 6,279

9.3 Production 40,179

9.4 Staff costs 3,945

9.5 Administration and corporate costs 2,039

9.6 Other (provide details if material) * (57,853)*

9.7 Total estimated cash outflows (5,311)

* Company is targeting its first cash flow positive quarter. Expected other cash flows (total aggregate $57,853,000) are receivables of $55,853,000 from the net revenue of zinc concentrate sales ($14,750,000 already received in January 2019 from a recently completed shipment of December 2018 quarter production) and $5,750,000 from MMG support payments (already received in January 2019), less an additional cash back bond requirement of $3,750,000 associated with a long-term power generation contract.

10. Changes in tenements (items 2.1(b) and 2.2(b) above)

Tenement reference and location

Nature of interest Interest at beginning of quarter

Interest at end of quarter

10.1 Interests in mining tenements and petroleum tenements lapsed, relinquished or reduced

NA

-

-

-

10.2 Interests in mining tenements and petroleum tenements acquired or increased

NA

-

-

-

Page 18: Quarterly Activities Report December 2018€¦ · Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email info@newcenturyresources.com Website 1 / 13

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 5

Compliance statement

1 This statement has been prepared in accordance with accounting standards and policies which comply with Listing Rule 19.11A.

2 This statement gives a true and fair view of the matters disclosed.

Sign here: Date: 21 January 2019(Managing Director)

Print name: Patrick Walta

Notes

1. The quarterly report provides a basis for informing the market how the entity’s activities have beenfinanced for the past quarter and the effect on its cash position. An entity that wishes to discloseadditional information is encouraged to do so, in a note or notes included in or attached to thisreport.

2. If this quarterly report has been prepared in accordance with Australian Accounting Standards,the definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resourcesand AASB 107: Statement of Cash Flows apply to this report. If this quarterly report has beenprepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule19.11A, the corresponding equivalent standards apply to this report.

3. Dividends received may be classified either as cash flows from operating activities or cash flowsfrom investing activities, depending on the accounting policy of the entity.