QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL ... · quantity surveying division...
Transcript of QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL ... · quantity surveying division...
Page 1 of 26
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
PART I ASSESSMENT – AUGUST 2014
WRITTEN TEST
TIME ALLOWED: 3 hours 30 minutes
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 2 of 26
NOTES TO CANDIDATES A. Headings to questions are for ease of identification only and do not form part of
the questions. B. Sections of questions are as follows: (1) Section A – TEN (10) multiple choice questions of 2 marks for each
question. The recommended time for attempting the multiple choice questions is approximately 20 minutes.
(2) Section B – FIVE (5) short questions total 30 marks of 6 marks for each
question. The recommended time for attempting the short questions is approximately 40 minutes.
(3) Section C – TWO (2) questions on Measurement of 50 marks. The
recommended time for attempting this part is approximately 150 minutes. C. All Multiple Choice Questions, Short Questions and the tasks on
Measurement are compulsory. D. The total mark is 100. The overall passing mark is 55. E. Refer also to INSTRUCTIONS TO CANDIDATES which were issued to you in
advance. NOTE: (a) Whenever the term HKSMM is used, it shall mean the Hong Kong Standard
Method of Measurement of Building Works, Fourth Edition 2005. (b) Whenever the term SFC is used, it shall mean the Agreement & Schedule of
Conditions of Building Contract for use in the Hong Kong Special Administrative Region, Private Edition - With Quantities 2005 Edition or Without Quantities 2006 Edition, as appropriate.
ASSESSMENT CRITERIA Candidate is expected to demonstrate his/her acquisition of practical skills and theoretical knowledge in quantity surveying at the technical level and the ability to correctly and precisely express his/her understanding on some specific areas of quantity surveying practice at the technical level.
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 3 of 26
SECTION A – MULTIPLE CHOICE QUESTIONS [TOTAL 20 MARKS]
Candidate is required to choose his / her answers to the questions by writing “A”, “B”,
“C” or “D” in the answer sheet for the Multiple Choice questions.
[2 Marks each]
__________________________________________________________________
A1 When taking off concrete of suspended slab, and provided that the concrete
grades of slab, column and beam are the same, the measurement of slab
should be taken as:
A a x b x thickness of slab
B (a x b – column on plan area) x thickness of slab
C (a x b – column on plan area – beam on plan area) x thickness of slab
D None of the above
A2 Before a quantity surveyor prepares measurement for a BQ, he/she should
read:
i) drawings
ii) preambles
iii) specifications
A i & ii only
B ii & iii only
C i & iii only
D All of the above
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 4 of 26
SECTION A – MULTIPLE CHOICE QUESTIONS
Extracted Preambles for the PC rates as below:
“ Where prime cost rates (PC rates) are included in the description of items in these Bills
of Quantities, these prime cost rates are for the material cost of that item delivered to
site ( street level ) only and the Main Contractor shall allow in addition for all waste,
fixing, all ancillary materials ………… The contract rate will be adjusted by the net
difference between the prime cost rate and the actual price (cost) and will be applied
to the net quantity of the items measured as fixed in position.”
Ref. Item Quantity Unit Rate Total
C Supply and install water
closet (WC1) completed
with cistern, tank fitting,
plastic seat and cover
and angle valve (prime
cost $1,500/No. supply
only).
300 No. 1,750.00 525,000.00
Page 3/88
Based on the rules of adjustment of PC rates and the extracted BQ item as
above, find the correct answer to Question A3.
A3 For the selected water closet (WC1), “Hugo” of $1,200/No. is confirmed.
What is the amount of saving or extra expense resulting from the initial
adjustment of this BQ item 3/88/C of water closet (WC1)?
A Saving of $90,000
B Saving of $75,000
C Extra expense of $75,000
D Extra expense of $90,000
A4 No formwork deductions shall be made when openings are: A Not exceeding or equal to 0.50m2 B Not exceeding or equal to 0.75m2 C Not exceeding or equal to 1.00m2 D Not exceeding or equal to 1.50m2
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 5 of 26
SECTION A – MULTIPLE CHOICE QUESTIONS
A5 Based on the SFC, the Architect shall not instruct a Variation after the
issuance of: A Interim Certificate B Architect’s Instruction C Substantial Completion Certificate D Defects Rectification Certificate
A6 Upon receiving the tenders (lump sum tender with Bills of Quantities), your
senior quantity surveyor asked you to carry out checking of the returned
tenders. Which of the following item(s) of the tender submissions is (are)
required to be checked?
(1) Arithmetical check, including individual extension and page totals
(2) Incorporation of tender addenda
(3) Submission of any tender qualifications
(4) Whether the Surety Bond has been submitted
A (1) only
B (1) & (2)
C (1) & (2) & (3)
D (2) & (3) & (4)
A7 The tender sum breakdown is as follows:-
BQ works : $48,700,000
Provisional Sums : $220,000
Contingencies : $950,000
Total : $49,870,000
Arithmetical error: (–) $510,000
Submitted tender sum : $49,360,000
Calculate the discount factor that will be applied in valuation of future
variations and payment valuation.
A (–) 1.023%
B (–) 1.027%
C (–) 1.043%
D (–) 1.047%
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 6 of 26
SECTION A – MULTIPLE CHOICE QUESTIONS
A8 Under the SFC (without quantities), which of the following shall not form part
of the contract.
A Bills of Quantities
B Drawings
C Specification
D Form of Tender
A9 Based on the following Interim Certificate No. 18 issued by the Architect
(Interim Certificate), the Employer has to pay the Contractor on or before :
Date of Interim Certificate No. 18 : 1-March-2014
Date of Contractor’s invoice enclosing Interim Certificate
No. 18
: 3-March-2014
Date on which the Employer receives the Contractor’s
invoice
: 5-March-2014
Period for payment of certificates in Appendix of the SFC : 14 days
A 14-March-2014
B 16-March-2014
C 18-March-2014
D None of the above
A10 The Employer is not a signatory to the contract(s) of
i. Main Contract
ii. Direct Contract for Lift Installation
iii. Nominated Sub-Contract for Electrical Installation
iv. Nominated Supply Contract for Light Fittings
A (i) & (ii)
B (ii) & (iii)
C (iii) & (iv)
D None of the above
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 7 of 26
SECTION B – SHORT QUESTIONS [TOTAL 30 MARKS]
Candidate is required to state his / her answer to the question in the answer book
separately provided.
___________________________________________________________________________________________________
Question B1 Upon the award of a Foundation Contract (using SFC with quantities), you, as the assistant project quantity surveyor, are required to prepare the Contract Documents for execution. List out six documents which, according to the SFC, shall form part of and be
included in the Contract Documents.
[6 Marks]
Question B2
You are the assistant project quantity surveyor of a composite office and commercial
complex development at Kwun Tong.
Contract Particulars Commencement Date for both Phases 1 and 2 17 January 2013
Contract Periods:
Phase 1 Commercial block 330 days from and including the Commencement Date
Phase 2 Office block 510 days from and including the Commencement Date
Defects Liability Periods:
Phase 1 Commercial block 12 months from the next day of Substantial Completion Date of the last phase of the Works
Phase 2 Office block 12 months from the next day of Substantial Completion Date of the last phase of the Works
Liquidated and Ascertained Damages
Phase 1 $180,000/day
Phase 2 $200,000/day
Dates of Substantial Completion:
Phase 1 12 December 2013
Phase 2 22 July 2014
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 8 of 26
SECTION B – SHORT QUESTIONS
Question B2
There was an extension of time of 25 days granted by the Architect for the
completion of Phase 2 Works and the new Completion Date for Phase 2 was fixed
on 5 July 2014.
Calculate and advise:
(a) the original Completion Date for Phase 1 [1 Mark]
(b) the dates for the expiry of the Defects Liability Periods for Phases 1 and 2
respectively [2 Marks]
(c) the number of days of delay for Phases 1 and 2 respectively [1.5 Marks]
(d) the amount of the liquidated and ascertained damages for Phases 1 and 2
respectively [1.5 Marks]
Question B3
The following information is shown in a lump sum fixed price contract based on
Drawings and Specification. SFC (without quantities) is adopted in this project.
(i) Eight (8) T3 fluorescent lamps are shown in the Contract Drawing for a
meeting room
(ii) Six (6) T3 fluorescent lamps are stated by the Contractor in the Schedule
of Quantities and Rates for this room with price of $300.00/No. each.
(a) If no variation has been issued during construction stage, how many T3
fluorescent lamps should be installed in this meeting room? State the reason for
the answer. [3 Marks]
(b) If the architect issues an instruction to replace all the T3 fluorescent lamps in this
meeting room to T5 fluorescent lamps ($400.00/No. each), calculate the cost
effect of this variation.
(Note: No need to consider any abortive or disruption costs in your calculation).
[3 Marks]
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 9 of 26
SECTION B – SHORT QUESTIONS
Question B4
Your senior quantity surveyor gave you the attached two pages of the pricing
documents (Annex 1) and the following information for a piling contract:
(i) The agreed variation works : HK$800,000.00
(ii) The agreed sub-contract sum for street lighting : HK$1,900,000.00
Calculate the final contract sum for this piling contract with details for omission and
addition items.
[6 Marks]
Page 11 of 26
SOR/3/1
Project ABC SCHEDULE NO. 3
PRIME COST and PROVISIONAL SUMS
Description $ ¢
SCHEDULE NO. 3
PRIME COST AND PROVISIONAL SUMS
Prime Cost Sum
A Provide the Prime Cost Sum of HK$1,000,000.00 for Street Lighting 1,000,000 00
Add for profit 5 % 50,000 00 Allow for general attendance as described in the Specification. 200,000 00
Provisional Sums to be expended in part or in whole as directed by the Architect or wholly deducted from the Contract Sum if not required
B Provide a Provisional Sum of HK$2,500,000.00 for Contingency. 2,500,000 00
CARRIED TO GENERAL SUMMARY $ 3,750,000 00
Annex 1 to Question B4
Page 12 of 26
General Summary
Description $ ¢
DESIGN AND CONSTRUCTION OF PILING WORKS
GENERAL SUMMARY
Page No. Schedule No. 1 - Preliminaries SOR/1/46 3,000,000 00 Schedule No. 2 - Piling Works SOR/2/12 27,000,000 00 Schedule No. 3 - Prime Cost and Provisional Sums SOR/3/1 3,750,000 00
CARRIED TO FORM OF TENDER $ 33,750,000 00
Annex 1 to Question B4
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 13 of 26
SECTION B – SHORT QUESTIONS Question B5 You are the assistant quantity surveyor for ABC QS Consultant Limited for the
Residential Development, Lot 9999 in Tai Po, Hong Kong. Your senior quantity surveyor, Mr. James Chan, requested the contractor to provide
a quotation for supply and installation of sanitary fittings for maid toilets based on the
following project particulars. The quotation is to be in Hong Kong Dollars.
i. 2 Blocks of Residential Towers;
ii. Residential Floor: Tower 1 and Tower 2 – 15 and 16 storey respectively;
iii. 2 Flats per each of residential floor and 1 Maid Toilet per each flat.
Subsequently, you have received the following quotation from the contractor:
To: ABC QS Consultant Limited – Mr. James Chan
Project name: Residential Development, No. 1 Moon Street, Tai Po, Hong Kong
Re: Quotation of Sanitary Fittings for Maid’s Toilet
Unit Qty Unit Rate Amount (RMB)
Supply and delivery to Site ONLY the
following sanitary fittings including all
accessories
Maid’s Toilet
Close coupled P/S tray W.C. with plastic toilet
seat and cover, cistern and associated fittings
in white colour.
Brand name: Lu Lu
Model No.: MB4983
Supply and delivery to Site No. 62 535.00 33,710.00
Installation No. 62 150.00 9,300.00
Wall mounted wash basin with overflow, white
colour completed with white PVC bottle trap.
Supply and delivery to Site No. 60 328.00 20,336.00
Installation m 62 100.00 6,200.00
Total Amount 69,006.00 As requested by your senior quantity surveyor, list out FOUR irregularities which are
required to clarify with the contractor. You are required to mark up these irregularities
on the attached quotation (Annex 1 to Question B5) and write down the correct
details next to such irregularities with explanation. You shall affix your marked
quotation in the answer book provided.
[6 Marks]
Page 15 of 26
To: ABC QS Consultant Limited – Mr. James Chan
Project name: Residential Development, No. 1 Moon Street, Tai Po, Hong Kong
Re: Quotation of Sanitary Fittings for Maid’s Toilet
Unit Qty Unit Rate Amount
(RMB)
Supply and delivery to Site ONLY the
following sanitary fittings including all
accessories
Maid’s Toilet
Close coupled P/S tray W.C. with plastic toilet
seat, cover, cistern and associated fittings in
white colour.
Brand name: Lu Lu
Model No.: MB4983
Supply and delivery to Site No. 62 535.00 33,710.00
Installation No. 62 150.00 9,300.00
Wall mounted wash basin with overflow, white
colour completed with white PVC bottle trap.
Supply and delivery to Site No. 60 328.00 20,336.00
Installation m 62 100.00 6,200.00
Total Amount 69,006.00
Annex 1 to Question B5
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 16 of 26
SECTION C – QUESTION ON MEASUREMENT [TOTAL 50 MARKS]
Question C1 [TOTAL 10 MARKS]
The project architect requested a cost advice of a proposed variation - adding a 1.5 m wide pedestrian ramp to a level difference location by mass concrete filling as sketch A (attached in Appendix 1). The designated gradient of the pedestrian ramp is 1: 12. Your senior has highlighted three pages of Bills of Quantities (BQ) of the Main Contract (attached in Appendix 2) and instructs you to do a valuation for such proposed variation. Your senior has also reminded you to note the decimal place of the quantities to be used for pricing variation according to SMM. (a) Only based on the information in sketch A with reference to the BQ, calculate
the cost of concrete and formwork for this additional ramp. [4 Marks]
(b) Apart from the cost items identified in (a) above, based on the attached BQ
pages 2 and 3, Name other two probable cost addition items related to this pedestrian ramp (with some brief reasons or explanations). Please also indicate the BQ reference to your suggested items, where appropriate.
[2 Marks]
(c) Based on your answer to (a) and (b) above, work out the total cost implication of
this proposed variation of pedestrian ramp. [4 Marks]
Page 19 of 26
Appendix 2 to Question C1 Page 1 of 3
BILL NO. 5
Ref. Quantity Unit Rate Total編號編號編號編號 數量數量數量數量 單位單位單位單位 單價單價單價單價 總額總額總額總額SUNDRY CONCRETE
125 Concrete Grade 20D in plinth. 50 Cube 1,000.00 50,000.00
(PROVISIONAL)
126 Concrete Grade 20D in mass concrete 25 Cube 1,000.00 25,000.00
fill to form ramp.
127 Reinforced concrete Grade 20D in curb. 18 Cube 1,000.00 18,000.00
128 Lightweight concrete (maximum density 124 Cube 1,025.00 127,100.00
of 13.5 kN/m3) in general filling to trench.
(PROVISIONAL)
Formwork to
129 Side of plinth. (PROVISIONAL) 100 Sup. 258.00 25,800.00
130 Sides of mass concrete fill. 5 Sup. 300.00 1,500.00
Carried to Collection $ 247,400.00
項目項目項目項目
BQ 5/14
Item
Page 20 of 26
Appendix 2 to Question C1 Page 2 of 3
BILL NO. 5
Ref. Quantity Unit Rate Total編號編號編號編號 數量數量數量數量 單位單位單位單位 單價單價單價單價 總額總額總額總額SURFACE FINISHES (ALL PROVISIONAL)
Tamped finishes to provide non-slip surface
139 To ramp. 627 Sup. 20.00 12,540.00
Trowelled finish
140 To slab. 8,778 Sup. 16.00 140,448.00
(END OF ALL PROVISIONAL)
Carried to Collection $ 152,988.00
項目項目項目項目
BQ 5/16
Item
Page 21 of 26
Appendix 2 to Question C1 Page 3 of 3
BILL NO. 7
Ref. Quantity Unit Rate Total編號編號編號編號 數量數量數量數量 單位單位單位單位 單價單價單價單價 總額總額總額總額RAILINGS TO RAMP AS DRAWING NO. CYS5/TD/D/SR02
Grade 316 stainless steel framed and welded
55 Railing 900 mm high above finished floor 47 Run 580.00 27,260.00
level, comprising 50 mm diameter tubular
top rail, 30 mm diameter rail post
with 3 no. of 50 x 20 mm collars
and 1 no. 50 x 50 mm thick square base collar and base plate to each post
at 1500 mm centres and including
all necessary component parts and fixing accessories as described and as
drawing.
CAT LADDERS TO FILTRATION PLANT ROOM AS DRAWING NO. AD-4-254
Galvanized mild steel framed and welded
56 Cat Ladder 1370 mm girth comprising 1 No. 2,100.00 2,100.00 38 mm stringer with ends bend to shape 450 mm apart with 20 mm diameter rungs
welded to stringers at 300 mm centers generally, 4 No. of 125 x 125 x 10 mm thick
fixing plates with 4 no. of expansion bolts
to each plate including all necessary
fixing accessories.
Carried to Collection $ 29,360.00
Item項目項目項目項目
BQ 7/13
THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 29th AUGUST 2014 WRITTEN TEST
________________________________________________________________________________
Page 22 of 26
Question C – QUESTION ON MEASUREMENT
Question C2 [TOTAL 40 MARKS]
The architect has revised the entrance of the development and type C fence walls will be extended by 32m (see SK-001). The architect requests the project quantity surveyor to advise the additional cost of this change. Your senior, the project quantity surveyor of the development, asks you to prepare the valuation of this variation based on the Bills of Quantities and the typical details of the fence wall type C (see Appendix-I) and to provide the build-up including the details of measurement to support your valuation. Your senior also reminds the following: (a) The quantities of reinforcement can be calculated by using the steel ratio that
can be derived from the Bills of Quantities.
(b) All excavation shall be commenced at the site formation level +1.0mPD.
(c) All side casting shall be rounded to 3 decimal places while the figures in
taking-off column shall be rounded to 2 decimal places only.
[40 Marks]
Page 26 of 26
BILL NO. 5.5 FENCE WALLS
Ref. Description Quantity Unit Rate $ 項目 數量 單位 單價 總計 BILL NO. 5.5 FENCE WALLS (TYPE C) A Excavate for fence wall footings not 747 Cube 180.00 134,460.00 exceeding 1.5m deep B Backfill selected excavated material around 256 Cube 150.00 38,400.00 footings in layers and consolidation to make up levels C Load and remove surplus excavated materials 491 Cube 250.00 122,750.00 from site D Concrete Grade 10/20D in 75mm blinding layer 41 Cube 1,350.00 55,350.00 under fence wall footing Reinforced concrete Grade 45/20D in E Fence wall footing 437 Cube 1,450.00 633,650.00 F Fence wall 88 Cube 1,450.00 127,600.00 Formwork to G Fence wall footing 448 Super 450.00 201,600.00 H Fence wall 1,176 Super 450.00 529,200.00 Deformed high yield steel bar reinforcement I 12mm Bars 38,430 kg 11.00 422,730.00 J 16mm Bars 57,015 kg 11.00 627,165.00 _________________ K Spatterdash 1,064 Super 1.50 1,596.00 L 20 mm Cement and sand (1:3) screed on 1,106 Super 210.00 232,260.00 walls to receive porcelain tiles 100 x 300 x 10mm Porcelain tiles (PT-1) bedded and jointed in cement mortar (1:3) on screeds (measured separately) including colour cement grouting M Top and sides of fence wall 1,106 Super 631.00 697,886.00
TPTL No. 505 Carried to Collection $ 3,824,647.00
Main Contract
BQ5.5/1
- END OF PAPER -