    Creating a Master Inspection Characteristic (Quantitative)

    Prerequisites

    If you want to change a master inspection characteristic with history, you must have set

    the relevant indicator in Customizing.

    SAP MenuLogisticsQuality ManagementQuality PlanningBasic Data

    Inspection CharacteristicsCreate.

    Transaction code: QS21

  • 8/14/2019 QM User manual.doc

    2/61

    Creating MIC Normal

    Enter the fields marked in red box and press enter or click on icon to reach the following screen.

  • 8/14/2019 QM User manual.doc

    3/61

    Enter the required fields marked in red box and click on Control indicatorsto reach the

    following screen

    Click here to

    reach the

    following

  • 8/14/2019 QM User manual.doc

    4/61

    Tick on the fields marked in red box and click on icon to reach the following screen.

  • 8/14/2019 QM User manual.doc

    5/61

    Click on icon to reach the following screen.

  • 8/14/2019 QM User manual.doc

    6/61

    Enter in the Status fields marked in red box as

    Enter the values.

    Click here the

    reach the

    following screen

  • 8/14/2019 QM User manual.doc

    7/61

    Using Transaction code QS23, we can go to the change mode and make necessary

    changes.

    In the screen above we can make our necessary changes.

  • 8/14/2019 QM User manual.doc

    8/61

    Creating MIC for Statistical Process Control.

    Enter the required fields marked in red box and press enter to reach the following

    screen.

  • 8/14/2019 QM User manual.doc

    9/61

    Click here

    to reach the

    following

  • 8/14/2019 QM User manual.doc

    10/61

    Tick the following marked in red box and press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    11/61

    Press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    12/61

    Enter the following values in red box and press enter.

    Save it by clicking on icon, following message will be displayed click icon and

    save it.

  • 8/14/2019 QM User manual.doc

    13/61

    Creating MIC for incomplete and Formulae.

    Enter the required fields and press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    14/61

    Enter the fields marked in red box and click on Control Indicator to reach the following

    screen.

    Click here to

    reach the

    following screen

  • 8/14/2019 QM User manual.doc

    15/61

    Tick the required fields marked in red box and press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    16/61

    Press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    17/61

    Change the marked fields in to Released and Incomplete copy model and save it by

    clicking on icon , following message will be displayed .

    Click on icon to save MIC.

  • 8/14/2019 QM User manual.doc

    18/61

    Creating MIC Incomplete

    Enter the required fields in red box and press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    19/61

    Enter the required fields marked in red box and click on Control Indicator to reach the

    following screen.

    Click here to reach

    the following screen

  • 8/14/2019 QM User manual.doc

    20/61

    Tick on the fields marked in red box and press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    21/61

    Tick on No formula and then enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    22/61

    Change the fields marked in red box to Released and Incomplete Copy model and then

    save by click on icon following message will be displayed.

    Click on icon MIC will be saved.

  • 8/14/2019 QM User manual.doc

    23/61

    Creating MIC long term.

    Enter the fields marked in red box and press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    24/61

    Enter the fields marked in red box and click on Control indicator to reach the following

    screen.

    Click here to reach the

  • 8/14/2019 QM User manual.doc

    25/61

    Tick the fields marked in red box and press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    26/61

    Tick the red box no formulae and press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    27/61

    Change the status in red box to Released and Complete Copy model and click save

    icon to save, following message will be displayed.

  • 8/14/2019 QM User manual.doc

    28/61

    Enter value in the red box marked and press enter.

    Save it by clicking on save icon, following message will be displayed.

    Click on icon to save MIC.

  • 8/14/2019 QM User manual.doc

    29/61

    INSPECTION PLANS:

    Using Transaction code QP01creating Inspection plan (Raw material, Freely definedinspection point)-01

    Enter the fields marked in red box and press enter.

  • 8/14/2019 QM User manual.doc

    30/61

    Enter the fields marked in red box and click on tab and select a

    vendor in the following way.

  • 8/14/2019 QM User manual.doc

    31/61

    Selection criteria marked in red box.

  • 8/14/2019 QM User manual.doc

    32/61

  • 8/14/2019 QM User manual.doc

    33/61

    Enter the required fields marked in red box and go to operations tab page.

    Enter the fields marked in red box in operations tab page and Click on

    tab to reach the characteristics overview tab page.

  • 8/14/2019 QM User manual.doc

    34/61

    Select the Sampling procedure from the list and press enter.

  • 8/14/2019 QM User manual.doc

    35/61

    Enter all the other fields and check for any error message by clicking on the icon

    following screen appears .

    Shows no error message.

    Save the plan by clicking on the icon, following message will be displayed.

  • 8/14/2019 QM User manual.doc

    36/61

    Using Transaction code QP01creating Inspection plan (MINES+FREELY DEFINEDINSPECTION POINT)-89

    Enter the fields marked in red box and press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    37/61

    Enter the fields marked in red box and click on tab to reach the

    following screen.

  • 8/14/2019 QM User manual.doc

    38/61

    Enter the fields marked in red box in operations tab page, select the line and Click on

    tab to reach the characteristics overview tab page.

    Enter the fields marked in red box and click on icon to check for error message.

  • 8/14/2019 QM User manual.doc

    39/61

    Shows no error.

    Save the Plan , following message will be displayed.

  • 8/14/2019 QM User manual.doc

    40/61

  • 8/14/2019 QM User manual.doc

    41/61

    Double click on the option marked in red box, following screen appears.

  • 8/14/2019 QM User manual.doc

    42/61

    Click on tab to reach the following screen.

  • 8/14/2019 QM User manual.doc

    43/61

    Enter Z02 in the field marked in red box and click on back button , following screen

    appears.

  • 8/14/2019 QM User manual.doc

    44/61

    Select the operation and click on icon to reach the following screen.

  • 8/14/2019 QM User manual.doc

    45/61

    Tick on the No relationradio button and click on back button.

    Select the second operation from the operations list and click on icon to reach the

    following screen.

  • 8/14/2019 QM User manual.doc

    46/61

  • 8/14/2019 QM User manual.doc

    47/61

    Enter the fields marked in red box and click on the back button.

  • 8/14/2019 QM User manual.doc

    48/61

    Check for any errors by clicking on icon following messages will be displayed.

    Click on icon to get the details.

  • 8/14/2019 QM User manual.doc

    49/61

    Save the master recipe by clicking on icon , following message will be displayed.

    Click icon the master recipe will be saved with the following message.

  • 8/14/2019 QM User manual.doc

    50/61

    Using transaction code MM02

  • 8/14/2019 QM User manual.doc

    51/61

  • 8/14/2019 QM User manual.doc

    52/61

    Creating a equipment task list for Calibration Plan using Transaction code IA01

    Enter the fields marked in red box and press enter to reach the following screen.

  • 8/14/2019 QM User manual.doc

    53/61

    Enter the fields marked in red box and click on Operation tab page.

    Enter the required operations and click on icon to reach the following

    screen

  • 8/14/2019 QM User manual.doc

    54/61

    Enter the intervals at which the operations are to be performed and click on back button

    to reach the operation overview tab page.

    Select the first operation and click on tab to reach the following screen.

    Double clic

    here to

    reach the

    following

    screen

  • 8/14/2019 QM User manual.doc

    55/61

    Enter the master inspection characteristics column and enter the required entry and

    then click on Sampling Procedure column to reach the following screen.

    Enter the Sampling procedure and press back button to reach the following screen.

    Press back button to reach the operation overview tab page and select the next

    operations

  • 8/14/2019 QM User manual.doc

    56/61

    After defining Inspection characteristics for all the operations, save the Task List,

    following message will be displayed.

  • 8/14/2019 QM User manual.doc

    57/61

    Enter the field marked in red box and enter all the other datas will get populated from

    the master data of the equipment.

    Enter the task list we have already created or we can select it by clicking on icon

  • 8/14/2019 QM User manual.doc

    58/61

    Enter the fields marked in red in Maintenance plan scheduling parameter tab page and

    click on icon, system will prompt following message.

    Select the date from which you want to start the plan and press enter.

  • 8/14/2019 QM User manual.doc

    59/61

    Using transaction code IP10 schedule the Plan we have created.

    Click on start button to start the plan

    ck here to

    rt the

    n

  • 8/14/2019 QM User manual.doc

    60/61

    Now save the plan by clicking on icon, following message will be displayed.

  • 8/14/2019 QM User manual.doc

    61/61

    Go into the schedule maintenance tab page again and release the plan by clicking on

    the icon.

    Click on icon to display if any call object generated as a result of the Plan.