QBE Technical Claims Brief January 2012

download QBE Technical Claims Brief January 2012

of 12

Transcript of QBE Technical Claims Brief January 2012

  • 7/28/2019 QBE Technical Claims Brief January 2012

    1/12

    Technical claims briefMot pdt J 2012

  • 7/28/2019 QBE Technical Claims Brief January 2012

    2/12

    Contents

    Costs 1

    Costs award based on withdrawn

    art 36 offer: Epsom College v Pierse

    Contracting Southern Ltd - Court of

    Appeal (2011) 1

    Credit hire 2

    Court of Appeal rules on credit hirerates and interest: Vasant Pattni v

    First Leicester Buses and Darren Bent v

    Highways Utilities and Another

    - Court of Appeal (2011) 2

    Hire claim not wiped out by refusal of

    replacement vehicle from Defendant:

    Sayce v TNT Court of Appeal (2011) 3

    Liability 4

    Court of Appeal rules on Elf and Safety:

    Duffosse v Melberry Events Ltd

    - Court of Appeal (2011) 4

    Procedure 5

    District Judge criticises claimants

    expert for attempting to mislead

    the Court: Walker v Brown

    - Stockport County Court (2011) 5

    European Court of Justice (ECJ)

    rules that injured car owners

    permitting uninsured driving must be

    compensated: Wilkinson v

    Churchill and Evans v

    Equity Claims Ltd ECJ (2011) 6

    Court of Appeal rules on meaning of

    Package in Holiday Claim:

    Sean Titshall v Qwerty Travel Ltd

    Court of Appeal (2011) 7

    Quantum 8

    European Court of Justice (ECJ) limits

    application of Rome II:

    Homawoo v GMF Assurances

    ECJ (2011) 8

    Disclaimer 9

  • 7/28/2019 QBE Technical Claims Brief January 2012

    3/12

    T m , mot pdt J 2012

    1

    Costs

    Costs award based onwithdrawn Part 36 offer:Epsom College v PierseContracting Southern Ltd -Court of Appeal (2011)

    The defendant contractors appealed

    against an award of costs made in favourof the claimant, which was based on a

    Part 36 offer that had been withdrawn.

    The contractors were sued by the

    claimant college after flooding damaged

    their dining hall. The college alleged that

    the flooding had been caused by a nail,

    driven through a pipe by the contractors,

    but did not initially produce the damaged

    section of pipe in evidence because it had

    been mislaid after it was replaced. In the

    absence of evidence, liability was denied.

    The claimants made three settlement

    offers. The first was on a Part 36 basis

    before proceedings were issued. It made

    no real allowance for the uncertainty over

    liability and the risk that the college might

    not prove its case and was rejected by the

    defendant contractors. The second offer

    was made after proceedings were issued

    for about half of the pleaded claim. It was

    also on a Part 36 basis and was stated as

    not withdrawing the first Part 36 offer. The

    second offer was rejected. The claimant

    made one final offer not on a Part 36basis, which was also rejected.

    The pipe section was then found and

    disclosed in evidence. The college

    withdrew their second and third offers,

    leaving the first offer in place. At trial, the

    defendant contractors conceded that

    the leak had been caused by the nail and

    the college was awarded damages with

    interest exceeding the value of all their

    settlement offers. The judge awarded the

    claimant costs based on its second Part

    36 offer. This offer had however been

    withdrawn and the defendant contractors

    appealed arguing that costs could not be

    based on a withdrawn offer.

    At the appeal, the parties agreed that

    costs should not have been awarded

    based on a withdrawn Part 36 offer. The

    question for the court was whether the

    award could be allowed to stand based on

    the first Part 36 offer or under Part 44 of

    the Civil Procedure Rules (CPR).

    The Court of Appeal held that it should

    as far as possible, put itself in the shoes

    of the trial judge and be slow to impose

    its own views even where the judge was

    technically wrong in his approach. Part44 could not be adopted to support the

    costs award, as the trial judge had not

    considered this in making his award.

    The trial judge had been reluctant to

    base the costs award on the first Part 36

    offer because there was little discount

    for the uncertainty on liability and the

    defendants had not acted unreasonably in

    refusing it when the claimant had failed to

    produce the damaged pipe in evidence.

    The second Part 36 offer was far morereasonable given the absence of evidence.

    The Court of Appeal held that the first

    Part 36 offer was still in force and

    reference to that offer could be made to

    justify the costs award. The defendants

    should pay the claimants costs on

    an indemnity basis but only from a

    reasonable period after the pipe had

    been disclosed to them. The essence of

    the trial judges ruling on costs was thus

    preserved and the appeal dismissed.

    Comment: Another illustration that when

    considering costs and the application of

    the CPR, the courts will look closely at the

    conduct of the parties and how reasonable

    they have been in making or considering

    offers. In this case, the claimant collegewas penalised for failing to disclose

    essential evidence until late in the day

    whilst the defendant contractors were

    penalised for not accepting a reasonable

    offer once supporting liability evidence was

    to hand.

  • 7/28/2019 QBE Technical Claims Brief January 2012

    4/12

    T m , mot pdt J 2012

    2

    Credit hire

    Court of Appeal rules oncredit hire rates and interest:Vasant Pattni v First LeicesterBuses and Darren Bentv Highways Utilities andAnother - Court of Appeal(2011)

    In the above two linked appeals the Court

    of Appeal ruled on two longrunning

    areas of dispute between credit hirers and

    defendants.

    In the Pattnicase, the issue was the

    claimants entitlement to interest on

    credit hire charges for the period from the

    end of the hire to the date of judgment.

    The claimant advanced three alternative

    grounds on which he should be awarded

    interest:

    Hewascontractuallyliabletopay

    interest to the hire company and this

    was a reasonably foreseeable loss

    arising from the accident

    Anawardofinterestshouldbemade

    based on the non-credit hire charge

    rates to compensate him for the loss of

    use of the money that he would have

    paid but for the credit hire arrangement

    Hewasentitledtoastatutoryawardof

    interest pursuant to section 69 of theCounty Courts Act 1984.

    The Court of Appeal rejected all three

    arguments. The latter two did not apply

    because the claimant had not actually

    made any payment and had not been

    deprived of the use of his money. The

    contractual liability argument was rejected

    on the basis that the interest charge

    constituted the cost of an additional

    benefit to the claimant. It enabled him to

    delay payment beyond the date it would

    otherwise have been due and in the light of

    the analysis in Dimond v Lovell, that was

    not recoverable by a claimant who could

    have afforded not to use credit hire.

    In the Bentcase, the claimant had hired

    an Aston Martin DB9 on credit for a

    period of 94 days in 2007 at a cost of

    63,406.90.

    The issue was the hire rate that the

    claimant could recover. The hire company,

    Accident Exchange appealed an earlier

    decision, which based the recoverable

    rates on those the judge found that the

    claimant could have obtained if he had

    made reasonable efforts to hire a car on

    a non-credit hire basis (which he could

    certainly have afforded to do).

    The Court of Appeal found that the judge

    had erred in her approach to determining

    the rate. The defendants had not proved

    that the basic hire rate (i.e. the non-credit

    hire rate) was any cheaper than the credit

    hire rate and the judge had therefore been

    wrong to reject the rate evidence supplied

    by the hire company in favour of the

    defendants evidence on average rates for

    2009 (a different year). The claimant was

    entitled to the actual cost of a like for like

    replacement not an average rate and in thecircumstances, this was the credit hire rate.

    The Court of Appeal however, rejected the

    Claimants argument that it was wrong to

    apply a cheaper 28-day hire rate. It was

    clear in this case the repair time would

    exceed 28 days and the claimant could

    have mitigated his loss by obtaining a better

    rate if he had contracted for a longer initial

    period of hire. A reduction of 12% was

    applied to the rate to reflect the saving that

    a longer initial hire period would have made.

    Comment Defendants will welcome the

    decision in the Pattni case which effectively

    puts an end to claims for interest on credit

    hire for the period from the end of the hire

    to judgment. The Bent decision will be less

    welcome as spot (average) rates will no

    longer be sufficient evidence on which to

    challenge credit hire rates.

  • 7/28/2019 QBE Technical Claims Brief January 2012

    5/12

    T m , mot pdt J 2012

    3

    Hire claim not wiped outby refusal of replacementvehicle from Defendant:Sayce v TNT Court ofAppeal (2011)

    The claimant sought recovery of vehiclehire charges from the defendants. The

    defendants had offered the claimant a

    replacement vehicle at no cost to her. At

    first instance, the defendants successfully

    defeated the claim for hire on the

    basis that the claimant would not have

    incurred any loss had she accepted the

    replacement vehicle from them.

    The claimant appealed. When the appeal

    was heard the Court of Appeal had

    already ruled in the case ofCopley v

    Lawn that a claim for hire was not wiped

    out by the offer of a replacement vehicle.

    A claimant was still entitled to recover an

    amount equal to actual reasonable hire

    charges even if they had declined the

    offer of a replacement vehicle from the

    defendant.

    The judge hearing the appeal however,

    declined to follow the decision in Copley

    prompting a second appeal by the

    claimant, this time to the Court of Appeal.

    The parties prepared a joint statement

    saying that the appeal should be allowed

    as the judge had clearly erred in refusing

    to follow binding authority but that the

    defendant intended to make an appeal

    to the Supreme Court as Copleywas

    inconsistent with established authorities on

    mitigation and wrong in principle.

    Not surprisingly, the appeal was allowed

    and the judge, who heard the first

    appeal, was criticised for his failure to

    adopt precedent. He should have given

    judgment based on Copleywhilst raising

    his concerns about the case, to give the

    defendant grounds for appeal. As matters

    stood, the Court of Appeal could not grant

    leave to appeal to the Supreme Court in

    this case due to the serious procedural

    irregularities that had occurred.

    Comment: The decision in Copley remains

    good law until such time as defendants

    successfully bring a test case before the

    Supreme Court.

  • 7/28/2019 QBE Technical Claims Brief January 2012

    6/12

    T m , mot pdt J 2012

    4

    Liability

    Court of Appeal rules onElf and Safety: Duffosse vMelberry Events Ltd - Courtof Appeal (2011)

    The elderly claimant was visiting Santas

    grotto in Selfridges with her grandchildren

    when she tripped over a plastic Christmastree decoration lying on the floor. She fell

    and fractured her thighbone.

    The grotto was manned by Santa and an

    elf, whose duty it was to remove any trip

    hazards on the floor. At first instance, the

    judge found that there was no breach of

    duty by the defendants. There was a good

    safety system in place and since neither

    Santa nor his elf spotted the bauble, it was

    not in plain view but probably obscured by

    a toy train. The claimant appealed.

    The Court of Appeal found that whilst the

    inspection system used by Santa and his

    elf may have been excellent, the elf had

    many other duties and it was possible that

    she and Santa had not been as careful

    as they should have been. Since the

    bauble was there to be stepped on, on the

    balance of probabilities it was also there

    to be seen and should have been spotted

    and removed.

    There was no contributory negligenceon the part of the claimant as she had

    stepped on the bauble whilst moving back

    out of camera shot at the request of the

    elf. The grotto was dark and the claimants

    attention on entry would have been drawn

    to the toy display on the opposite side of

    the entrance.

    Judgment was given for the claimant with

    damages to be assessed.

    Comment: The District Judge who

    originally heard the case was criticised by

    the Court of Appeal for taking an overly

    benevolent view of the performance by

    Santa and his elf... perhaps proving that

    even District Judges are not immune to

    the Christmas spirit.

  • 7/28/2019 QBE Technical Claims Brief January 2012

    7/12

    T m , mot pdt J 2012

    5

    Procedure

    District Judge criticisesclaimants expert forattempting to mislead theCourt: Walker v Brown -Stockport County Court(2011)

    The claimant suffered a neck and back

    injury in an accident. His solicitors

    instructed a doctor to examine him who

    produced a report giving a prognosis for

    recovery in five months. When the claimantsaid he had not recovered, the doctor did

    not re-examine him but simply produced

    a revised report with the same date giving

    a new prognosis for recovery 12 months

    post accident.

    The original report was served rather than

    the revised one (presumably in error) and

    the defendants solicitors were unaware

    of the revised prognosis until a month

    before trial when they received a witness

    statement from the claimant referring to a12- month recovery period. They queried

    this with the claimants solicitors who

    did not reply until a little over two weeks

    before the trial. The trial judge held that the

    defendant was deprived of any opportunity

    to increase their settlement offer pre-issue

    and/or to make use of Part 36 offers to

    protect themselves on costs.

    The judge was highly critical of both the

    conduct of the medical expert and the

    claimants solicitors and ordered that the

    claimant pay the defendants costs of the

    action.

    District Judge Horans forthright

    comments about the revised medical

    report are set out below:

    If a doctor is changing his mind at the

    behest of a claimant, there should be

    a totally separate report with a totally

    separate date indicating that he haschanged his original view and explaining

    why he has and to do other than this is

    an attempt to mislead the other party and

    an attempt to mislead the court and I do

    not like it one iota and I request and I am

    going to order that you inform this doctor

    and these solicitors, Leech and Co, they

    must not do anything like that again and

    I shall remember this, I shall mention it to

    my colleagues to look out in particular for

    Leech and Co and for Dr Evans.

    An expert has a duty to the court, not to

    the claimant and not to the claimants

    solicitors. He has got a duty to the court

    and he should not have changed his

    opinion just like that without there being a

    further re-examination. Had there not been

    this mess up, this error by the claimants

    solicitors, we would not have known about

    this. You then wonder is this the tip of

    the iceberg? How often is it happening?

    It is unprofessional, very unprofessional.

    I have half mind to adjourn the case for

    a representative from Leech and Co and

    for Dr Evans to attend personally before

    me and explain what they are up to and,

    in fact, I am going to order that they both

    provide a written explanation as to how

    this has come about.

    Comment: Under Part 35 of the Civil

    Procedure Rules, an expert witness

    duty is to the court and they must report

    impartially. Sometimes experts are

    suspected of either lacking impartiality

    or at least of being unaware of their

    obligations under Part 35. It is encouraging

    to see a judge taking such a firm line on

    this issue.

    Our thanks go to DWF solicitors for

    sending us the Transcript of the Judgment

    in this case.

  • 7/28/2019 QBE Technical Claims Brief January 2012

    8/12

    T m , mot pdt J 2012

    6

    European Court of Justice(ECJ) rules that injuredcar owners permittinguninsured driving must becompensated: Wilkinson vChurchill and Evans v EquityClaims Ltd ECJ (2011)

    In June of 2010, we reported on two

    cases involving car owners who had

    permitted uninsured drivers to drive their

    vehicles and who were both seriously

    injured when their cars crashed. In both

    cases the insurers of the vehicles declined

    to pay the owners injury claims on the

    basis that any damages paid to them

    would be immediately recoverable under

    Section 151 (8) of the Road Traffic Act

    1988 (RTA) (because they had permitted

    uninsured drivers to use their vehicles).

    The claimants argued that thisinterpretation of the RTA conflicted with

    European Union policy that victims of

    road traffic accidents who were injured by

    negligent drivers should be compensated

    regardless of whether the drivers were

    insured or not.

    The cases were referred by the Court of

    Appeal to the European Court of Justice

    (ECJ). The ECJ has now ruled that under

    EU law, insurers cannot rely on Section

    151 (8) to reject claims from policyholders

    who have been injured whilst being

    driven by uninsured drivers, regardless

    of whether they knew the driver to be

    uninsured or not.

    The Court of Appeal will now decide

    whether or not to apply the ECJs ruling.

    If they decide that insurers may continue

    to rely on Section 151 (8) of the RTA even

    though it is in conflict of EU law, injured

    claimants denied compensation in this

    situation, would have a right of action

    against the UK Government.

    Comment: It is not certain how the Court

    of Appeal will rule or if the UK Government

    will now amend the RTA. Insurers will be

    watching the outcome with interest as this

    is not an unusual scenario.

  • 7/28/2019 QBE Technical Claims Brief January 2012

    9/12

    T m , mot pdt J 2012

    7

    Court of Appeal rules onmeaning of Package inHoliday Claim: Sean Titshall vQwerty Travel Ltd Court ofAppeal (2011)

    The claimant was seriously injured when

    a glass door shattered at a hotel whilst he

    was on holiday. He alleged that the glass

    was faulty and brought a claim under the

    Package Travel, Package Holidays

    and Package Tours Regulations 1992

    against the defendant travel agents.

    The defendants denied that they owed any

    obligation to the claimant. They maintained

    that the claimant had entered into two

    separate contracts with two companies for

    flights and accommodation. The claimant

    had booked his holiday by making a short

    telephone conversation to one of the

    defendants clerks. Neither the claimantnor the clerk could remember the detail of

    their conversation nor was there an invoice

    available. The claimant had however,

    been provided with a statement showing

    the individual costs of the flights and

    accommodation and three unspecified

    service fees.

    At first instance, the court dismissed the

    claim after ruling as a preliminary issue that

    the claimant had purchased two separate

    services rather than a package and

    the travel agents were not a party to the

    holiday contract. The claimant appealed

    arguing that the pre-arranged combination

    of services had been sold at an inclusive

    price.

    The Court of Appeal ruled that to assess

    whether the components of the holiday

    were sold or offered at an inclusive

    price, it needed to determine whether

    they were being sold as components of

    a combination or separately but at the

    same time. In this case, the travel agentshad advertised a last minute get-away

    at an inclusive price and at no time had

    they suggested that either the flights or

    the accommodation were available for

    purchase separately. The service fees

    were also presented at least partly, as

    the price of putting the package together.The service fees could not be attributed

    between flights and accommodation

    and there was no way of determining the

    separate costs of either of these inclusive

    of service fees.

    The travel agents were liable to the

    claimant for the proper performance of the

    obligations of the contract.

    Comment: In the lead judgment, Lord

    Justice Tomlinson commented that whilst

    consumer protection was not the primary

    object of the European Directive which

    underpinned the regulations, one aim

    was to make it more straight forward for a

    claimant to obtain recovery from a single

    domestic supplier in the event of some

    failure of the holiday providers.

  • 7/28/2019 QBE Technical Claims Brief January 2012

    10/12

    T m , mot pdt J 2012

    8

    Quantum

    European Court of Justice(ECJ) limits application ofRome II: Homawoo v GMFAssurances ECJ (2011)

    The claimant was seriously injured in a

    road traffic accident, in France by a French

    motorist in August of 2007. He broughtproceedings in England and argued that

    his compensation should be assessed

    by reference to English law, which would

    mean a far higher award than under

    French law.

    Under European Community regulation

    864/2007 known as Rome II the law

    used to determine damages is usually

    the law applicable in the country where

    the tort (in this case a motor accident)

    occurred. Prior to the implementation

    of Rome II, the law used in assessing

    damages for an English claimant injured

    abroad was the English law.

    The High Court was asked to determine

    whether Rome II was in force at the

    time of the accident (see September

    2010 Brief) but this was by no means

    straightforward.

    The claimant argued that Rome II did

    not apply to events before 11 January

    2009, as that was the application datespecifically referred to in the regulation.

    The defendant argued that it applied to

    any determination by the court conducted

    on or after 11 January 2009 provided the

    original tort occurred after 20 days from

    the date that Rome II was first published

    i.e. from 20 August 2007 (European

    regulation is normally deemed to be in

    force 20 days after publication unless

    otherwise specified).

    The High Court realising the need for

    consistency and the large number of

    cases that might be affected by their

    ruling, referred the case to the European

    Court of Justice (ECJ).

    The ECJ has now ruled that Rome II

    applied only to torts giving rise to damage

    occurring after 11 January 2009 meaning

    that the claim in this case was not subject

    to it and damages would be assessed

    under English law.

    Comment: The ECJ has now ended the

    uncertainty effecting cross-border claimsoccurring between 20 August 2007 and

    11 January 2009. Damages in England

    and Wales are amongst the highest in

    Europe however and the fact that these

    claims will now achieve damages based

    on this jurisdictions law will make most of

    them more expensive.

    Our thanks go to Berrymans Lace Mawer

    solicitors for drawing this case to our

    attention.

  • 7/28/2019 QBE Technical Claims Brief January 2012

    11/12

    T m , mot pdt J 2012

    9

    Completed 21 December 2011 written

    by and copy judgments and/or source

    material for the above available from

    John Tutton (contact no: 01245 272

    756, e-mail: [email protected]).

    Disclaimer

    This publication has been produced by

    QBE Insurance (Europe) Ltd (QIEL).

    QIEL is a company member of the QBE

    Insurance Group.

    Readership of this publication does not

    create an insurer-client, or other business

    or legal relationship.

    This publication provides information

    about the law to help you to understand

    and manage risk within your organisation.

    Legal information is not the same as legal

    advice. This publication does not purportto provide a definitive statement of the law

    and is not intended to replace, nor may it

    be relied upon as a substitute for, specific

    legal or other professional advice.

    QIEL has acted in good faith to provide

    an accurate publication. However, QIEL

    and the QBE Group do not make any

    warranties or representations of any kind

    about the contents of this publication, the

    accuracy or timeliness of its contents, or

    the information or explanations given.

    QIEL and the QBE Group do not have

    any duty to you, whether in contract, tort,

    under statute or otherwise with respect to

    or in connection with this publication or the

    information contained within it.

    QIEL and the QBE Group have no

    obligation to update this report or any

    information contained within it.

    To the fullest extent permitted by law,

    QIEL and the QBE Group disclaim any

    responsibility or liability for any loss or

    damage suffered or cost incurred by you

    or by any other person arising out of or in

    connection with you or any other persons

    reliance on this publication or on the

    information contained within it and for any

    omissions or inaccuracies.

    QBE Insurance (Europe) Limited and

    QBE Underwriting Limited are authorised

    and regulated by the Financial Services

    Authority. QBE Management Services

    (UK) Limited and QBE Underwriting

    Services (UK) Limited are both Appointed

    Representatives of QBE Insurance

    (Europe) Limited and QBE Underwriting

    Limited.

  • 7/28/2019 QBE Technical Claims Brief January 2012

    12/12