    RECEIVING INSPECTION

    METHOD STATEMENTFOR

    RECEIVING INSPECTION

    Rev. No. Details Of Revision Date Prepared by Checkedby

    Approvedby

  • 7/28/2019 QA&QC_MS.docx

    2/4

    RECEIVING INSPECTION

    1. OBJECTIVE

    To ensure that receiving inspection of material and equipment is carried out at

    Projects and receiving stores in conformity with the laid down specifications.

    2. SCOPE

    This method statement covers all incoming material & equipment received fromcustomer or purchased by Projects.

    3. REFERENCES

    The following documents are considered as reference document:

    4. ABBREVIATIONS/DEFINATIONS

    5. RESPONSIBILITIES

    I/C Stores, I/C QA&QC

    6. PROCEDURE

    6.1 The procured materials are classified as

    Standard Items

    Project Specific Items

    E&P Items

    Tools

    Fixed Assets

    Manufactured Items

    a) Standard Items

    Items, which have been approved & accepted by QA&QC/Proc/User, shall be inspected through indent form at receiving store.

    b) Project Specific Items

    Project specific items can be divided into two groups:

    Items supplied from factory by vendor in packed & sealedcarton/container shall be inspected, for integrity of packing,quantity and actual material inside the packing, at the receivingstores.

    Unpacked/loose material and fabricated material procured fromvendor, shall be inspected at receiving stores.

    c) E&P Items

    E&P items for Projects shall be inspected by respective I/C

  • 7/28/2019 QA&QC_MS.docx

    3/4

    RECEIVING INSPECTION

    d) Tools

    IMTE shall be inspected at the receiving stores.

    e) Fixed Assets

    The user and QA&QC shall inspect fixed asset items at receivingstores.

    f) Manufactured Items

    Pre-shipment final inspection will be performed for all localmanufactured items at vendor and subcontractors premises.QA&QC co-coordinator for procurement and testing will performthis activity and will issue inspection certificate

    6.2 Inspection Methodology

    6.2.1 I/C Stores shall initiate a material inspection report for all incomingmaterial arranged through fresh purchase. For material of inter-site transfer, a thorough inspection will be carried out both at theconsignors end & at the receiving end.

    6.2.2 QA&QC inspector shall inspect the material as per referencedocuments.

    6.2.3 Material and equipment procured shall be inspected inline withfollowing guidelines:

    Specifications

    Packing condition

    Inspection report of the manufacturer (If applicable)

    Physical condition

    MTC (if required)

    6.2.4 Sampling and inspection methodology shall be followed as below:

    6.2.4.1 Establish the size of the lot to be inspected.

    6.2.4.2 Establish acceptability quality level, which is defined asthe upper limit of the percentage of defects acceptable

    6.2.4.3 Extent of examination based on vendor qualification iscategorized as below:

    6.2.4.3.1 100% inspection of chosen lot for non-approved vendor.

    6.2.4.3.2 Random inspection of chosen lot forapproved vendor, exact status dependingon the decision of I/C QA&QC at the time ofinspection of the specific commodity

    6.2.4.3.3 Items supplied by customers should bechecked for conforming to projectspecifications on random basis. However

  • 7/28/2019 QA&QC_MS.docx

    4/4

    RECEIVING INSPECTION

    the ultimate responsibility for performancefailures will still be of the customer.

    6.2.5 QA&QC inspector shall place an identification mark on theinspected items for segregation and traceability.

    6.2.6 Materials, which do not conform to the given specification, shall berejected. Incase incoming material is released for urgentproduction purposes prior to verification; it shall be positivelyidentified and recorded on MIR and duly countersigned by SM.

    6.2.7 6.2.9 Inspection of the imported material shall be carried out bythe I/C QA&QC/User at the receiving stores.

    6.2.10 Procurement shall ensure that all the materials, if rejected, shall

    be returned to suppliers at the latters own risk and cost.

    6.2.11 Every store shall prepare a vendor-wise quarterly rejection reportof materials procured under fresh purchases and send it toprocurement for assessment of vendor reliability and quality.

    7. TOOLSANDEQUIPMENTS

    Vernier Caliper

    Meter Tape

    Micrometer

    Battery Torch

    Welding Gauge

    Elcometer

    8. HSEINSTRUCTIONS

    - Keep your environment clean.

    - No smoking is permitted in the restricted areas.

    9. RELATEDDOCUMENTS