Putting Up Sips Walls
Transcript of Putting Up Sips Walls
Enercept panels ready to ship
Shown here are all the panels to build our home.Enercept S.I.P. panels are manufactured indoors in a controlled environment.
Panels being unloaded
Enercept panels are delivered directly to the job site.Panels are easily unloaded one by one with the help of a couple friends.
Sill plate attached to sub floor
The floor system must be LEVEL and SQUARE.Outside dimension of sill plate must be 1” less than overall exterior dimension of structure.
The walls go up
All Enercept panels are numbered in the order of their installation.A ¼” bead of approved sealant must be applied before setting panels.
Enercept Window panels
Window rough openings will consist of a lower panel and upper lintel.Caulk upper portions of two adjoining panels.
Slide upper panel into place
Slide panel down into position.Push outside panel tightly against lower and upper panels.Nail into position.
Enercept gabled wall panels
Mark centerline of beams and windows prior to installation as per panel layout.Start with center panels, setting panels from the center to outside.