Put Title Here Put date or other info here September 14, 2018

Transcript of Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project...

Page 1: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Put Title Here

Put date or other info here

September 14, 2018

Page 2: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Owner and Design Team

Grinnell College HSSC Project

Leadership Team:

Mike Latham

Jim Swartz

Erik Simpson

Keith Brouhle

Rick Whitney

Dave Robinson

Larry Gleason

Keith Archer

Nancy Combs

Christi Baker

Jane Taylor

EYP Architects

Jennifer Amster

Eric Kern

Eric Petersen

Angela Wilson

OPN Architects

Bill Catrenich

Pylar Eaton

Page 3: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

McGough Project Team

Dustin Schwake – Project Executive

Matt Schroeder – Senior Project Manager

Josh Miltenberger – Senior Project Manager

Ryan Drew – Senior Project Manager

Alex Maass – Assistant Project Manager

Amy Robinson – Project Coordinator

Chuck Carpenter – Senior Superintendent

Patrick Woodson – Assistant Superintendent

Page 4: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Subcontractors

1st Interiors

Advance Equipment Co.

All-American Scaffold

American Fence Co.

American Structural Metals

Architectural Wall Systems

Baker Electric

Bartley Sales

Bolander

CGA

DA Bunch

Danny’s Construction

Des Moines Marble

Floors by Beckers

Forman Ford

Heartland Finishes

J&M Roofing

Johnson Specialty Sales

KONE Elevator

Navetta

PAC-VAN

Pella Tree Service

Peterson Contractors, Inc.

Premier Edge

Pro-Bel

S&F Underground

Seedorff Masonry

Skold Companies

Soil-Tek

Summit Fire Protection

Superior Painting

Swanson & Youngdale

Waldinger Mechanical

Walsh Door & Security

Wilkie Sanderson

Wynn O. Jones

Page 5: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Current Highlights

High ceiling work progresses in the atrium

Finishes continue in south pavilion

Carpet, Tile, Millwork, Lab casework, Doors & hardware, Interior glass

Drywall and finishing nearly complete in north pavilion

Interior granite continues

South pavilion window wells are finished at skylights

Mechanical, electrical, fire protection trim continues

Chilled beams, light fixtures, fire alarm devices, electrical trim, fire sprinkler

heads

Page 6: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

View from commencement

Page 7: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

South elevation

Page 8: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

View of main courtyard / atrium

Page 9: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

View at northwest elevation

Page 10: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Window well – south end of south pavilion

Page 11: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Window well – 2nd floor – final details complete

Page 12: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Rough-in for A/V at S1310 – 1st floor south pavilion

Page 13: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Interior granite at main entrance to atrium

Page 14: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Louver install – 1st floor at north end of atrium hallway

Page 15: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Ceiling framing & trim for bridges in atrium

Page 16: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

South atrium wall – louvers being set

Page 17: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

2nd floor main street corridor looking north

Page 18: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Millwork set and protected – 2nd floor south

Page 19: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Raised flooring installation – 3rd floor south

Page 20: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Chilled beam install – 2nd floor north pavilion

Page 21: Put Title Here - Pushing beyond what's been done · 9/14/2018  · Ryan Drew –Senior Project Manager Alex Maass –Assistant Project Manager ... Window well –2nd floor –final

Upcoming Highlights

Tile flooring to start in south pavilion – main corridors

Exterior finish complete on overhangs – direct applied finish system

High ceiling work to continue in atrium – wood look ceiling/lights/fire sprinkler

Flooring to start in north pavilion

Equipment start-up and testing for AFA project

Interior finishes continue in south and north pavilions