Pure Water San Diego Program
Transcript of Pure Water San Diego Program
![Page 1: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/1.jpg)
Pure Water San Diego ProgramPure Water Facility Tour
![Page 2: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/2.jpg)
of our water is imported…
85% San Diego is downstream
![Page 3: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/3.jpg)
We Face Numerous Water Challenges
Imported Water Cost per Acre-Foot▪ Limited local & imported
supplies
▪ Population growth
▪ Bay Delta constraints
Imported water cost per acre-foot
▪ Natural disaster risk
▪ Rising imported water costs
▪ Recurring drought
![Page 4: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/4.jpg)
▪ Pure Water Program
▪ Recycled Water
▪ GroundwaterDevelopment
▪ Desalination▪ Conservation
Multi-faceted Approach
![Page 5: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/5.jpg)
What is Pure Water San Diego?
Safe
Reliable
Cost-effective
![Page 6: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/6.jpg)
Existing System… Primarily a Single-Use System
Point Loma WWTP / Ocean Discharge
San Diego’s Water Supply System
![Page 7: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/7.jpg)
Pure Water… Completes Our Water Cycle
Point Loma WWTP / Ocean Discharge
San Diego’s Water Supply System
![Page 8: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/8.jpg)
Pure Water Runs a Successful Demonstration Facility
▪ 50,000+ lab tests: Met all standards
▪ Water quality: Exceptional
They want to replace this photo with ‘cool photos’ of MF, RO, UV
![Page 9: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/9.jpg)
Phase 1▪ 30 mgd▪ North City PWF to Miramar
1/3Pure Water will produce
of your water locally
![Page 10: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/10.jpg)
Phase 1▪ 30 mgd▪ North City PWF to Miramar
Phase 2▪ 2035 Completion▪ 53 mgd▪ Central Area PWF to
San Vicente or Lake Murray
1/3Pure Water will produce
of your water locally
![Page 11: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/11.jpg)
North City Pure Water Pump Station & Pipeline
NCPWF
Morena Pump Station & Pipelines
Phase 1 – North City will produce 30 mgd of purified water
100% Design Completed on all Phase 1 projectsMBC = Metro Biosolids Center
NCWRP = North City Water Reclamation Plant
NCPWF = North City Pure Water Facility
Phase 1 Projects
Miramar Water
Treatment Plant
NCWRPExpansion
Miramar
Reservoir
MBC Improvements
![Page 12: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/12.jpg)
Two 10.5 milePipelines
Pump Station
▪ Conveys wastewater to North City Water Reclamation Plant (WRP)
▪ Supports Phase 1 purified water and recycled water production
▪ Trenchless construction will be used to avoid:
▪ environmentally sensitive areas
▪ freeway crossings
Morena Pump Station and Pipelines
North City WRP
▪ Construction begins in early 2021
![Page 13: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/13.jpg)
▪ Treats wastewater to recycled water standards
▪ Expansion nearly doubles the amount of recycled water produced to meet needs of:
▪ Pure Water Facility▪ Recycled Water System
Morena Pipeline
Pure Water Facility
NCWRP
North City Water Reclamation Plant Expansion
▪ Early site work is being completed
▪ Expansion begins in fall 2021
![Page 14: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/14.jpg)
▪ Treats recycled water to produce 30 mgd of purified water
▪ Includes a proven 5-step advanced water purification treatment process
▪ Early site work is being completed
▪ Construction begins in early 2021
Pure Water Facility
North City Pure Water Facility & Pump Station
NCWRP
Pump Station
![Page 15: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/15.jpg)
North City Pure Water Pipeline
Pure Water Facility
Miramar Reservoir
~8-miles of Pipeline
Pump Station
▪ Pure Water to Miramar Reservoir via:
▪ Pump Station
▪ Pipeline
▪ Water will be dechlorinated before release to reservoir
▪ Construction begins in summer 2021
![Page 16: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/16.jpg)
Miramar Water Treatment Plant
De-chlorination Facility
▪ The purified water:
▪ Is released via underwater pipeline in the reservoir
▪ Will blend with imported and local water supplies
▪ The Miramar Reservoir Pump Station is being upgraded
Pump Station
Miramar Reservoir
![Page 17: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/17.jpg)
Who Supports Pure Water?
![Page 18: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/18.jpg)
What Can I Do?
Join our mailing list and sign a support card
Pure Water San Diego @PureWaterSDPureWaterSD PureWaterSD
www.purewatersd.org
![Page 19: Pure Water San Diego Program](https://reader034.fdocuments.us/reader034/viewer/2022050516/62724b4f190cf4505a6b3bbc/html5/thumbnails/19.jpg)
Virtual Tour Video
Want to take a guided tour of the Pure Water Demonstration Facility? Learn all about the five-step process from members of the Pure Water team by viewing the Pure Water Virtual Tour at one of the links below.
Pure Water San Diego Website Video Link: virtualtour.purewatersd.orgPure Water San Diego YouTube Video Link: YouTube.com/PureWaterSD