Purbrook Way Hulbert Road Junction –Phasing Drawings · 2016. 8. 3. · • SE Rbt Part 2 of 2...

10
Purbrook Way Hulbert Road Junction – Phasing Drawings Revision 2 Current at 31-03-2016

Transcript of Purbrook Way Hulbert Road Junction –Phasing Drawings · 2016. 8. 3. · • SE Rbt Part 2 of 2...

  • Purbrook Way Hulbert Road Junction – Phasing Drawings

    Revision 2

    Current at 31-03-2016

  • From: Tuesday 29th March

    To: Friday 1st April

    Full Depth Road Construction –

    • SE Roundabout Part 2 of 2

    Surface Water Drainage

    • SE Rbt Part 2 of 2

    • HRS

    Splitter island and footway build

    • PWW, PWE, HRN

  • From: Monday 4th April

    To: Wednesday 6th April (end of day)

    3 days

    • Traffic directed around B&Q roundabout

    • Surfacing works to west side of main

    roundabout completed in one phase – same

    duration as half.

    Asda exit lane reduced in width

    � Two lines of traffic cannot safely join a roundabout with only 1 lane.

    Full Depth Road Construction –

    • SE Rbt Part 2 of 2

    Plane out and Lay Tarmac

    • SW Rbt Part 1 of 2

    Surface Water Drainage

    • SE Rbt Part 2 of 2, PWW

    Splitter island and footway build

    • PWW, PWE, HRS, HRN

    Extent of TM

    Extent of Surfacing

    LEGEND

  • From: Thursday 7th April

    To: Friday 15th April

    Kerbing

    • Asda entrance

    Splitter island works and footway build

    • PWW, PWE, HRS, HRN, Roundabout

    Signage, Guardrail, Traffic Signals, Street

    Lighting, CCTV works

    • Multiple areas

  • From: Monday 18th April

    To: Thursday 21st April

    4 Nights

    Surface Course

    • HRN and Roundabout

    Asda exit lane reduced in width

    � Single file, one direction traffic control in place

    Over night closures with 4-Way Traffic Light System in place

    Roundabout returned to normal operation during the day

    Extent of TM

    Extent of Surfacing

    LEGEND

  • Plane Out, Install Reinforcement Grid,

    lay Binder & Surface Course

    • Purbrook Way (East)

    Asda exit lane reduced in width

    � Two lines of traffic cannot safely join a roundabout with only 1 lane.

    From: Friday 22nd April

    To: Wednesday 27th April

    4 Nights

    Extent of TM

    Extent of Surfacing

    LEGEND

  • From: Thursday 28th April

    To: Friday 6th May

    6 Nights

    Note: Bank Holiday Monday 2nd May

    Plane Out, Install Reinforcement Grid,

    lay Binder & Surface Course

    • Purbrook Way (West)

    Over night closures with 4-Way Traffic Light System in place

    Roundabout returned to normal operation during the day

    Asda exit lane reduced in width

    � Single file, one direction traffic control in place

    � During this phase there will be the need to stop all traffic for 15-20mins

    to allow surfacing vehicles to lay entrance area. This will be controlled

    and co-ordinated with Asda and the public.

    Extent of TM

    Extent of Surfacing

    LEGEND

  • From: Monday 9th May

    To: Friday 13th May

    5 Nights

    Surface Course

    • Hulbert Road (South)

    Over night closures with 4-Way Traffic Light System in place

    Roundabout returned to normal operation during the day

    Asda exit lane reduced in width

    � Single file, one direction traffic control in place

    � During this phase there will be the need to stop all traffic for 15-20mins

    to allow surfacing vehicles to lay entrance area. This will be controlled

    and co-ordinated with Asda and the public.

    Extent of TM

    Extent of Surfacing

    LEGEND

  • Asda exit lane reduced in width

    � Works adjacent to Asda entrance/exit required, resulting in reduced width.

    From: Monday 16th May

    To: Wednesday 18th May• 2 days Break out and kerbing

    • Clear for the weekend

    • 1 day (Wednesday 18th May) surfacing

    Break out and build Asda Splitter island

    (including footway crossing and original

    kerbing)

    • Asda entrance/exit

    Surface Course

    • Around Asda splitter island

    Signage, Guardrail, Traffic Signals, Street

    Lighting, CCTV, Landscaping works

    • Multiple areas

  • Notes

    • The dates and durations detailed are the current best forecast based on

    current design and programme. They are subject to change should

    unforeseen circumstances arise, design changes, weather etc.

    • This phasing is different to that originally planned and has been produced

    to minimise the disruption to local stakeholders and travelling public.

    • Traffic Management layouts will be assessed when installed and may

    require alteration on site to reflect Health, Safety and operational

    requirements.