LARSEN & TOUBRO LIMITED - ECC DIVISION, NCD-5 , MEHSANA
Job Procedure For Pump House Piping
Job Procedure No WI/EXE/8.2.3/ST/JP-17, Rev 0
Index
Sl. No. Page No.
Index
Description Formats
1 Scope 2
2 Reference 2
3 Method 2-4
o erance
5 Documentation 4
5.1 ITP 5 WI/EXE/8.2.3/ST/ITP-16, Rev 0
5.2 Formats 6 WI/EXE/8.2.3/ST/F-16A, Rev 0
7 WI/EXE/8.2.3/ST/F-16B, Rev 0
-
8/9/2019 Pump House Piping-17
2/6
LARSEN & TOUBRO LIMITED - ECC DIVISION, NCD-5 , MEHSANA
Job Procedure For Pump House Piping
Job Procedure No WI/EXE/8.2.3/ST/JP-17, Rev 0
4.5.5
On co
pletion of each run craters,
elding irregularities, slag etc. shall be re
o
ed b
grinding or chiseling
etc.For pipes of all thickness of
& abo e, the ends to be elded shall secured in position ith the aid ofcla
ps or direct tack
elding to
aintain perfect align
ent. Te
porar
eld attach
ents of co
patible
aterial
a be used to align & reduce the
is
atch etc. at joints.
fter elding the attach
ents shall be cut off b
grinding
ith out causing an
da
age to pipe surface. Te
porar
attach
ents
ight be
elded b
tack
elder
qualified b site
person. irect tack elds shall be
ade onl b qualified elders using appro ed PS.
Tack
elds
hich are to incor orated in the final
eld shall carefull
be ins ected for cracks etc. and the
3 tacks For pipe size of 2 1/2" dia & belo
4 tacks For pipe size of 3" to 12" dia
tacks For pipe size of 14" & abo e
In general gal anised piping shall ha e threads for required to drain cooling ater fro
pu
ps or in sanitar
ork threads on fittings,
al
es etc.Threads shall be clean cut,
ithout an
burrs or stripping and the ends shall
be rea
ed. Threading of pipes shall be done preferabl after bending, forgoing or heat treating operations.pipes
shall be done preferabl after bending, forgoing or heat treating operations. uring asse
bl of threaded joints,
all threads of pipes and fittings shall be thoroughl
cleaned of cuttings, dirt, oil or an
other foreign
atter. The
ale threads shall be coated
ith thread sealant and the joint tightened sufficientl for the threads to size and
gi
e a leak proof joint.
.
defecti e tacks
ust be re
o ed. The
ini
u
No. Of tacks shall be as follo s.
4.6 Scre
ed Piping
In general gal anised piping shall ha e threads for required to drain cooling ater fro
pu
ps or in sanitar
ork threads on fittings,
al
es etc.Threads shall be clean cut,
ithout an
burrs or stripping and the ends shall
be rea
ed. Threading of pipes shall be done preferabl after bending, forgoing or heat treating operations.pipes
sh
all be done preferabl after bending, forgoing or heat treating operations. uring asse
bl of threaded joints,
all threads of pipes and fittings shall be thoroughl
cleaned of cuttings, dirt, oil or an
other foreign
atter. The
ale threads shall be coated ith thread sealant and the joint tightened sufficientl for the threads to size and
gi
e a leak proof joint.
ll flange facings shall be true and perpendicular to the a
is of pipe to
hich the
are attached. Flanged bolt
holes shall straddle the nor
al center lines unless different orientation is sho n in the dra ing.
.
4.8 Branch Connections
ll flange facings shall be true and perpendicular to the a
is of pipe to
hich the
are attached. Flanged bolt
holes shall straddle the nor
al center lines unless different orientation is sho
n in the dra ing.
The specific application of elded
iter bends and fabricated reducers shall be go erned b the Piping
aterial
Specifications. Prefabricated
iters shall be t
pe as per Standard practise. Reducers, if required, shall be
fabricated as per directions of
I
.
ranch connections shall be as indicated in the piping
aterial specifications. For end preparation,align
ent,
spacing, fit-up and
elding of branch connections refer
elding specifications. Te
plates or la
out shall be used
here er required to ensure accurate cutting and proper fit-up.Re-inforce
ent pads shall be pro ided 1.
here
er indicated in dra
ings/specifications etc.
.
4.10 Cutting and Trimming of Standard Fittings & Pipes
The specific application of
elded
iter bends and fabricated reducers shall be go erned b the Piping
aterial
Specifications. Prefabricated
iters shall be t
pe as per Standard practise. Reducers, if required, shall be
fabricated as per directions of
I .
4.10 Cutting and Trimming of Standard Fittings & Pipes
4 11 Shop Fabrication / Prefabrication
o
ponents like pipes, elbo
s, couplings, half-couplings etc. shall be cut/tri
ed/edge prepared
here
er
required to
eet fabrication and erection require
ents, as per dra ings.
-
8/9/2019 Pump House Piping-17
3/6
LARSEN & TOUBRO LIMITED - ECC DIVISION, NCD-5 , MEHSANA
Job Procedure For Pump House Piping
Job Procedure No WI/EXE/8.2.3/ST/JP-17, Rev 0
5.3 Flange Connections
hile fitting up ating flanges, care shall be e
ercised to properl
align the pipes and to check the flanges for
trueness, so that faces of the flanges can be pulled together,!
ithout inducing an
stresses in the pipes and the
"
equip
ent nozzles."
tra care shall be taken for flange connections to pu
ps,co
pressors, air coolers etc. The
flange connections to these equip ents shall be checked for isaligne tn, e
cessi # e gap etc. after the final
align
ent of the equip
ent is o#
er. The joint shall be
ade up after obtaining appro#
al of$ "
I % /G
SS&
.Te porar
protecti # e co# ers shall be retained on all flange connections of pu ps,
turbines,co
pressors and other si
ilar equip
ents, until the piping is finall
connected, so as to a#
oid an
!
!
#
foreign aterial fro entering these equip ents.The asse bl
of a flange, joint shall be done in such a !
a
that
the gasket bet!
een these flange faces is unifor
l
co
pressed. To achie#
e this the bolts shall be tightened in a
proper sequence.'
ll bolts shall e
tend co pletel
through their nuts but not ore than 1/4".Steel to$
.I. flange
joints shall be
ade up!
ith e
tre
e care, tightening the bolts unifor
l
after bringing
an atera a gn
ent ange us!
t gas ets!
t accurate pattern.
5.(
Vents an)
Drains
High pint#
ents and lo!
point drains shall be pro#
ided as per the instructions of"
I%
, e#
en if these are not sho!
n
in the dra ! in s. The details of # ents and drains shall be as er i in aterial s ecifications / ob standards.
5.5 Valves
!
.#
.
Val # es shall be installed ! ith spindle/actuator orientation/position as sho ! n in the la
out dra ! ings. In case of
an
difficult
in doing this or if the spindle orientation/position is not sho!
n in the dra!
ings, the G
SS&
/$ "
I%
,
shall be consulted and ! ork done as per his instructions.$
are shall be e
ercised to ensure that globe # al# es,
5.6 Instruments
#
al#
es,rota
eters, orifice f lange asse
bl
,#
enturi
eters, flo!
eters etc. shall f ro
part of piping erection
check#
al#
es and other uni-directional#
al#
es are installed!
ith the "Flo!
direction arro!
" on the#
al#
e bod
pointing in the correct direction.
! ork.Fabrication and erection of piping upto f irst block # al# e/nozzle/flange for installation of offline Instru ents
for
easure
ent of le#
el, pressure, te
perature, f lo!
etc. shall also fro
part of piping construction!
ork. The
li its of piping and instru entation ! ork ! ill be sho ! n in dra ! ings / standards / specifications. Orientations /
locations of take-offs for te
perature, pressure flo!
, le#
el connections etc. sho!
n in dra!
ings shall be
6.0 Pipe Supports
.
Pipe supports are designed and located to effecti # el
sustain the !
eight and ther al effects of the piping s
ste
and to pre#
ent its#
ibrations.%
ocation and design of pipe supports!
ill be sho!
n in dra!
ings , Ho!
e#
er, an
e
tra supports desired b
TPI shall also be installed.
'
long!
ith piping spool erection0
align
ent, pipe
#'
ll restraints ha # e been installed correctl
.
supporting shall also be done. The follo !
ing points shall be checked after installation, ! ith"
I% and necessar
confir
ation in!
riting obtained certif
ing that :
-
8/9/2019 Pump House Piping-17
4/6
LARSEN & TOUBRO LIMITED - ECC DIVISION, NCD-5, MEHSANA
Inspection & Test Plan For: PUMP HOUSE PIPING
Inspection & Test Plan No : WI/EXE/8.2.3/ST/ITP-17, Rev 0
INSPECTION & TEST PLAN
L&T CEIL GWSS
1 WPS / PQR Review Approved WPS Regular WPS/PQRWI/EXE/8.2.3/PL-
04A,04C Rev 0 R R R
2Welder's performance qualification
Review Approval WQR Regular WQRWI/EXE/8.2.3/PL-
15A,15B Rev 0 R R R
Reference
DocumentFormat of Record
AgencySl.
No.
Component /
ProcessNature of Check / Test
Method of
Check
Acceptable
Tolerance
Quantum
of Check
3
Material Test Certificate for pump
house of main components ReviewAs per specification
RegularMRIR
WI/EXE/8.2.3/PL-17,Rev
0 R R R
4
Weld consumable Manufacturer
Batch Test certificates ReviewAs per specification
RegularBTC Manufactrurer test
certificate R R R
5Weld joint Fit - up & dimension
check
Visual/Measur
ment Approved drawing 100%
Approved
drawingWI/EXE/8.2.3/ST/F-17A,
Rev 0 C RM RM
WI/EXE/8.2.3/ST/F-17A,
Fabrication
and Erection
of piping work
6 Visual As per WPS 100% Rev 0 C RM RM
7Fabrication of fittings Measurment + and - 5 mm 100%
DrawingWI/EXE/8.2.3/ST/F-17A,
Rev 0 W RM RM
8 Erection of Piping as per drawing Visual in level +/- 10mm 100% DrawingWI/EXE/8.2.3/ST/F-17B,
Rev 0 C RM RM
9Installation checklist of Pipe supports Visual
As per approved
drawing 100%Drawing
WI/EXE/8.2.3/ST/F-17B,
Rev 0 C C C
at station.
10Hydro Test/ commissioning Visual As per Procedure 100%
Tender Final Report W W W
Legend
W - Witness (100% Inspection) RM- Random (10% Inspection) R - Review Documents C-Check (Visualy 100% )
0 22/11/05 For review & approval
Rev Date Revisions Prepared By L&T Checked by CEIL Reviewed and Approved b
-
8/9/2019 Pump House Piping-17
5/6
OWNER GWSSB-Mehsana LOCATION:- REPORT NO:-
LARSEN & TOUBRO LIMITED - ECC DIVISION, NCD-5 JOB
FIT - UP & WELD VISUAL REPORT FOR STATION PIPING
CONSULTANT Certification Engineers International Ltd. PROJECT:- DATE:-
CONTRACTOR Larsen & Toubro Ltd - ECC Division
DIA
THICK
Sl. NO. DRAWING NO REMARKWELD
VISUALJOINT NOLOCATION /AREA
WELDER
ID
MATERIAL
CHECK
TYPE OF
JOINT
FIT UP
CHECK
DIMENSIO
N CHECK
WPS
NO
gend:- BW - Butt weld; SW- Socket weld; FW - Fillet weld; BR - Branch weld
FOR CEIL/GWSSBFOR L&T
Format No.:WI/EXE/8.2.3/ST/F-17A, Rev 0
FOR CEIL/GWSSBFOR L&T
-
8/9/2019 Pump House Piping-17
6/6
OWNER GWSSB-Mehsana REPORT NO:
CONSULTANT Certification Engineers International Ltd. DATE:
CONTRACTOR Larsen & Toubro Ltd - ECC Construction Group LOCATION:
LARSEN & TOUBRO LIMITED - ECC DIVISION, NCD-5 JOBField Installation check list of Station Piping prior to pressure testing / commissioning
Rev. Rev.
L&T CEIL/GWSSB L&T CEIL/GWSSB
1 Installation checked as per P&ID 7 Seal welding screwed connections ( if required )
P & ID Nos.
Items to Check Items to Check
GAD No. / Isometric No.
Sl.No
Checked Sl.No.
Checked
2 Installation checked as per Isometric 8 Vents, drains, reinforcing pads
9 Removal of temporary erection cleats, cleaning etc
3 Installation checked as per Piping Plan 10 Test limits verified at site
4 Isometric / Sketch marked with: 11 Supports
a) Weld Nos. ( as made ) a) Correct types / Dimensions
b) As built Dimensions b) Guides
c es m c ng5 Valve ( Incl. Control and Safety valves ) d) Fixed point ( Anchor )
a) Type e) Shoes, Special supports ( if any )
b) Rating f) Support welding
c) Bolting / length / type 12 NDT Completed ( Radiography / UT / PT )
d) Gaskets 13 Check removal & blinding-off of:
e) Facing a) Control, Safety and Check valves
f) Flow Direction b) In line instruments
6 Flanges c) Others:
a) Bolting length / type 14 Check installation of :
b) Gaskets a) Temporary blinds
c) Facing / Rating b) Temporary strainers
d) Orifice type, taps in right position c) others
Remarks ( if any )
The installation is checked as per above and found satisfactory. System released for hydrotesting / commissioning.
______________ _______________
Format No :WI/EXE/8 2 3/ST/F-17B Rev 0
For L&T For CEIL/GWSSB
Format No :WI/EXE/8 2 3/ST/F-17B Rev 0