Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Transcript of Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open...

Public Service Company of New Mexico

Open Transmission Planning Meeting November 2, 2017

Albuquerque, NM

2

INTRODUCTION • Public Stakeholder Meeting

– Order 890 Objective to improve transparency and stakeholder involvement.

– Planning Process Defined in Attachment K of OATT • March Meeting Reviewed

– Planning Process – Coordination with WECC (PCC & TEPPC), WestConnect – PNM 10-Year Plan Study Scope

• November Meeting – Review 10-Year Plan Results – Input to Next Planning Cycle – Certain Other Business

PNM Open Transmission Planning Meeting

November 2, 2017 Albuquerque, NM

3

10-YEAR TRANSMISSION PLAN

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

4

10-YEAR TRANSMISSION PLAN

• OBJECTIVES OF STUDY EFFORT: • Support Data Base Development for PNM and

Regional Studies – 2019 (1-yr), 2022 (5-yr), 2027 (10-yr)

• Maintain Reliability • Define Transmission for Native, Network and

Point-Point Customers • Incorporate Plans Developed Through FERC

Processes, NM IRP and Regional Planning Analysis

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

5

STUDY SCOPE

• Review transmission adequacy with retail and network customer updates to designated network resources and load.

• Determine if system mitigations are needed to serve expected obligations (load forecasts and expected firm transfers) during the 10 year planning horizon without violating WECC/NERC reliability standards.

• Develop operational mitigations or system improvements to maintain system reliability and associated cost estimates and schedule.

• Incorporate assessments of economic congestion to the extent a need is identified by PNM’s or other’s involvement in the WECC process for providing this type of assessment.

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

6

PROJECT DRIVERS

• Compliance with Reliability Standards • Provide Service to New Load Locations • Interconnection Projects • Recommendations for projects requiring

joint study or solutions

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

7

Project Overview

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

8

Northern New Mexico

Northern New Mexico Projects

Yah-Ta-Hey Transformer (ISD 2017)

Completed Project

Planned Project

Richmond Station (ISD 2017)

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

9

Southern New Mexico Projects

Southern New Mexico

Completed Project

Planned Project

Alamogordo Voltage support Phase 2 (ISD 2022+)

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

10

COMPLETED RELIABILITY PROJECTS

• Richmond Switching Station • 2nd Yah-Ta-Hey Transformer

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

11

RELIABILITY PROJECTS UNDER CONSTRUCTION

• None

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

12

PLANNED RELIABILITY PROJECTS

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

13

ALAMOGORDO VOLTAGE SUPPORT PHASE 2

• In-Service Date: 2012+ • Purpose – Provide adequate

voltage support and operational flexibility by increasing the transmission load serving capability.

• Project includes – Installation of an additional

switchable shunt capacitor

Holloman

Dona Ana Tularosa

Amrad

Load

Carrizo

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

14

OTHER PROJECTS

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

15

OPERATOR OR RAS SOLUTIONS

• Only Local Area Impacts • Certain N-2 overloads addressed by RAS or

Operator action. – Generation Re-dispatch – Load Shedding – Capacitor switching – Transformer Tap Adjustments

PNM Open Transmission Planning Meeting

November 2, 2017 Albuquerque, NM

16

Interconnection and Transmission Service Projects

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

17

Interconnection and Transmission Service Related Projects

• Generator Interconnection – El Cabo Wind Farm interconnection at Clines Corners completed

Spring 2017. • Wire-Wire Interconnections

– Blackwater Expansion for Western Interconnect Tie – completed – Cabezon Switching Station - 2018

• Transmission Service Projects – Guadalupe SVC – 2018 – Blackwater Synchronous Condenser – 2019 – Albuquerque-Clines Corners 345 kV Line – late 2020

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

18

El Cabo Wind Farm

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

19

Blackwater 345 kV Switchyard Expansion

• Expand to a 3 breaker ring bus configuration to accommodate an interconnection to Western Interconnect line.

• Western Interconnect transmission line will interconnect Broadview and planned Grady wind generation facilities.

• In-service date December 2016 (Broadview)

PNM Open Transmission Planning Meeting

November 2, 2017 Albuquerque, NM

20

Blackwater Station Expansion

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

21

Cabezon Switching Station • 33 miles north of Rio Puerco on the San Juan – Rio

Puerco 345 kV transmission line. • A 3 breaker ring that provides a new delivery point

Tristate G &T under the Network Transmission Service Agreement.

• Tristate will provide a 345 to 115 kV transformer which ties into the Algodones – La Jara 115 kV line segment.

• In-service spring of 2018

PNM Open Transmission Planning Meeting

November 2, 2017 Albuquerque, NM

22

Wires to Wires Interconnections

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

23

Guadalupe SVC

• Size: -100 to +250 MVAR • Voltage support for transmission service

provided to Pattern and Avangrid. • Guadalupe Switching Station expanded to four

terminations to accommodate SVC. • 2018 in-service date.

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

24

Guadalupe SVC

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

25

Blackwater Synchronous Condenser

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

26

Proposed Clines Corners-Albuquerque 345 kV Line

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

27

10-YEAR PLAN QUESTIONS?

Ten-Year Plan Report Available for Stakeholders completing CEII Request

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

28

2017 STUDY PLAN INPUT

• March Meeting to Review 10-Year Plan Scope

• Discussion

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

29

Large Generator Interconnection Cluster Activity

• Six Definitive Cluster closed August 10th, 2015 – Two requests of 120 MW are in LGIA negotiations. – One requests of 38 MW is in FACS study mode

• Seventh Definitive Cluster closed May 6th, 2016 – 400 MW is in LGIA negotiation.

• Eighth Definitive Cluster closed January 31, 2017 – Twelve requests of 1250 MW in SIS study mode

• Seventh Preliminary Cluster closed June 2, 2017 – One request of 50 MW in SIS study mode

• Ninth Definitive Cluster Closed October 30th – Reviewing requests, will be posted on oasis.

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

30

Next Cluster Window

• Definitive Interconnection Cluster Window opens April 29th, 2018 and closes July 27, 2018

• Preliminary Interconnection Cluster Window opens November 30thth, 2017 and closes February 27, 2018

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

31

REGIONAL ACTIVITIES • SunZia

– Permitting activities Ongoing – Commercial operation date in late 2020 – www.sunzia.net

• Lucky Corridor – Project modified to single 345 kV line from Gladstone area to Ojo switching

station – Completed WECC Project Coordination Review Group report

• Mora Line Project – Lucky Corridor's Mora Line project is designed to carry 180 MW at 115 kV. – 102 miles – Working on Facilities study with PNM

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

32

REGIONAL ACTIVITIES

• Southline Project – WECC Rating Process Completed March 23, 2015 – Construction expected to begin in 2018 – In Service Date: In phase between 2018 and 2020 – August 2017 Fact Sheet Available on website:

www.southlinetransmissionproject.com

• Centennial West Clean Line Project – See project website for latest developments.

• Western Spirit Clean Line Project – Approximately 1000 MW 345 kV Project to increase access from Central New

Mexico to the Four Corners hub. – Facilities Study for interconnection to PNM completed in September 2017.

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

33

REGIONAL ACTIVITIES

• Verde Project – Interconnects to PNM’s Ojo and Norton 345 kV stations – System Impact Study completed in March 2017 – Expecting completion of Facilities Study November 2017 – 2016-2017 Permitting, Public Engagement, ROW, Engineering – 2018-2019 Construction, In Service Date 2020

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

34

Map of Regional

Transmission Projects

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

35

ORDER 1000 UPDATE • Adds planning process for identifying regional projects that are more

cost effective and efficient than projects in local plans. • Establishes cost allocation methodology for regional projects. • Full Biennial Cycle 2016-2017 mostly complete

• No regional projects identified.

• Current Activities: – Annual Stakeholder meeting – November 16th – Tempe, AZ – Start discussions for scoping 2018-2019 Biennial Planning Cycle

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

36

NEXT MEETING

March 1, 2018

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

QUESTIONS OR COMMENTS?

Tom Duane [email protected]