Public Meeting November 9, 2016 SRQ Media Room

21
Public Meeting November 9, 2016 SRQ Media Room

Transcript of Public Meeting November 9, 2016 SRQ Media Room

Page 1: Public Meeting November 9, 2016 SRQ Media Room

Public Meeting November 9, 2016 SRQ Media Room

Page 2: Public Meeting November 9, 2016 SRQ Media Room

Agenda

• Call Meeting to Order • Approval of Minutes • Program Schedule Review • Phase 1 MOT Plan Update • LS 87 Landscape Plan • Phase 1 Schedule Review • Outstanding Business • New Business • Public Input • Adjournment

Page 3: Public Meeting November 9, 2016 SRQ Media Room

Program Overview

PHASE 3 LS 87 Gravity

Mains

PHASE 1 LS 87 Microtunneling

PHASE 2 LS 87 Structure

PHASE 3 LS 7 Demo and

Restoration

ALTA VISTA STREET

US 41

POMELO AVE O

SPR

EY

AVE

POM

ELO

PL

ACE

Construction Sequencing – 3 Phases

Page 4: Public Meeting November 9, 2016 SRQ Media Room

Program Overview

Phase Start Finish

2015 2016 2017 2018 2019 2020

Q 1/2

Q 3/4

Q 1/2

Q 3/4

Q 1/2

Q 3/4

Q 1/2

Q 3/4

Q 1/2

Q 3/4

Q 1/2

Q 3/4

Con

stru

ctio

n

Phase 1 May 2016

July 2017

Phase 2 May 2017

Oct. 2019

Phase 3 Aug. 2019

Dec. 2020

Projected Construction Timelines

Page 5: Public Meeting November 9, 2016 SRQ Media Room

Phase 1 – Lift Station 87 Microtunneling Maintenance of Traffic Plan Update

To maintain safe traffic flow during construction by:

• Directing traffic to Mound Street/US 41 to avoid neighborhoods

• Addressing pedestrian detours and sidewalk closures

• Identifying access to businesses on Osprey Avenue

Page 6: Public Meeting November 9, 2016 SRQ Media Room

Lift Station 87 Landscape Plan

Public Participation Overview

• Series of Public Meetings Hover Arcade

Brick Façade

• Public Meeting – July 26, 2016

Page 7: Public Meeting November 9, 2016 SRQ Media Room

Red Brick Option

Page 8: Public Meeting November 9, 2016 SRQ Media Room

Sarasota High School

Page 9: Public Meeting November 9, 2016 SRQ Media Room

Landscape Architectural Renderings

• Site Plan Application

December 2014

Input from Urban Design Studio

• Landscape Architect – David W. Johnston Associates, Inc.

Phillip J. Smith, ASLA

Page 10: Public Meeting November 9, 2016 SRQ Media Room
Page 11: Public Meeting November 9, 2016 SRQ Media Room
Page 12: Public Meeting November 9, 2016 SRQ Media Room
Page 13: Public Meeting November 9, 2016 SRQ Media Room
Page 14: Public Meeting November 9, 2016 SRQ Media Room
Page 15: Public Meeting November 9, 2016 SRQ Media Room
Page 16: Public Meeting November 9, 2016 SRQ Media Room
Page 17: Public Meeting November 9, 2016 SRQ Media Room
Page 18: Public Meeting November 9, 2016 SRQ Media Room

Phase 1 Schedule Review

• Jacking Shaft MH17 (Between Lincoln and Bridge)

October/November 2016

• Receiving Shaft MH21 (Osprey/US 41 Intersection) December 2016/January 2017

• Jacking Shaft MH24 (Luke Wood Park) December 2016/January 2017

Page 19: Public Meeting November 9, 2016 SRQ Media Room

Phase 1 Schedule Review

• MT Drive 1 (Osprey Avenue)

December/January 2017

• MT Drive 2 (Luke Wood Park) February 2017

• Demobilization July 2017

Page 20: Public Meeting November 9, 2016 SRQ Media Room

• Outstanding Business

• New Business

Page 21: Public Meeting November 9, 2016 SRQ Media Room

Public Input