PU-PPPL Earned Value Management System Overview Thomas Egebo October 4-6, 2011 Princeton University...
-
Upload
darleen-howard -
Category
Documents
-
view
217 -
download
0
Transcript of PU-PPPL Earned Value Management System Overview Thomas Egebo October 4-6, 2011 Princeton University...
PU-PPPL Earned Value Management System Overview
Thomas EgeboOctober 4-6, 2011
Princeton UniversityPlasma Physics LaboratoryEVMS Certification Review
Outline:
• Background
• PU-PPPL EVMS Stewardship/Organization
• EVMS Description
• Summary
EVMS Certification October 4-6, 2011 2
Background:
Purpose:
EVMS measures actual performance of work scope and the associated cost and
schedule versus an agreed to baseline plan, while using disciplined means of
baseline change control for documenting any changes to the agreed to
baseline plan.
Although we’ve been using EV at PPPL for quite awhile; since NSTX-U TPC >
$50M the PU-PPPL contract with DOE requires compliance with DOE
413.3B which dictates EVMS Certification by DOE for Projects > $50M
EVMS Certification October 4-6, 2011 3
PPPL EVMS Stewardship:
The Deputy Director for Operations has the ultimate responsibility for overall oversight and implementation of project management.
Direct responsibility for the development and management of the PPPL Project Management System is delegated by the Deputy Director of Operations to the Project Management Officer who is supervised by the Associate Laboratory Director for Engineering and Infrastructure.
The PPPL Planning and Control Division is the steward of the earned value management system policy and has authority delegated to ensure that projects follow established Laboratory policy, and by extension, applicable industry standard.
EVMS Certification October 4-6, 2011 4
PPPL Organization:
EVMS Certification October 4-6, 2011 5
EVMS Certification October 4-6, 2011 6
PU-PPPL EVMS
Complies with ANSI/EIA 748-B Standard for EVMS & is suited to the needs of PU-PPPL
• Provides thorough planning of all work scope into finite elements
• Integration of scope, schedule and cost objectives
• Timely baseline establishment and control
• Objective measurement of accomplishment against plan
• Disciplined, summarized reporting
• Analysis of significant variances, forecasted impacts and management actions to mitigate risk
EVMS Certification October 4-6, 2011 7
PU-PPPL EVMS Documents
Project Management System Description (PMSD) addresses EVMS and contains the following supporting procedures:
• Procedure 1 Project Execution Plan• Procedure 2 Work Breakdown Structure (WBS)• Procedure 3 Project OBS and RAM• Procedure 4 Control Accounts, Work Packages & Planning Packages• Procedure 5 Control Account Plan/Work Authorization• Procedure 6 Project Schedule• Procedure 7 Cost Estimating• Procedure 8 Monthly Status Reporting• Procedure 9 Change Control• Procedure 10 EVMS Surveillance & Maintenance
EVMS Certification October 4-6, 2011 8
PU-PPPL EVMS deployed at the Project Level
Goal is deployment of a cost-effective system that provides PU-PPPL management with an effective tool for decision-making
Each project determines their own• variance thresholds• control account levels• work authorization• change control thresholds• software tools/scheduling styles• risk management methodology• reporting suite and style
Surveillance program will validate their implementation decisions
EVMS Certification October 4-6, 2011 9
PU-PPPL Projects Required to use Certified SystemCurrent:
NSTX-Upgrade; CD-2 Dec 2010 {TPC=$94.3M}CD-3 Jan 2012
Future:PPPL Science & Technology Support Infrastructure Project; CD-0 Aug 2010 {TEC $53M-$59M}CD-1 2012CD-2 2014
EVMS Certification October 4-6, 2011 10
5 Other PU-PPPL Projects using EVMS as a tool (following the overall principles of 413.3B and EVMS but to a lesser degree of rigor)
$0.3M to $2.6M
PU-PPPL Projects Undergo Continuous Surveillance•NSTX-U Regular updates to internal Directorate (weekly and monthly)
•NSTX-U Weekly Technical Meetings
•NSTX-U Monthly Status Meetings
•PPPL Project Status Review Board Meetings (PSRB)
•NSTX-U Integrated Project Team Meetings (monthly)
•NSTX-U Project Critical Decision Reviews
•FES Program Office Reviews (quarterly)
•Biannual Advisory Committee Reviews (e.g., PU PPPL Advisory Committee)
•Annual internal EVMS surveillance reviews
•Ad-Hoc Weekly/Daily meetings with PSO NSTX-U FPD
EVMS Certification October 4-6, 2011 11
Summary – PU-PPPL EVMS1. Compliant with ANSI/EIA-748-B Standard for EVMS (i.e., meets the
requirements of the 32 EVMS Guidelines embodied in the ANSI/EIA748; Standard for Earned Value Management Systems.)
2. Provides PPPL projects with timely and meaningful information to support program and project management as a decision enhancing tool and a critical component of risk management.
PPPL’s EVMS:• Effectively integrates a project’s work scope, cost, and schedule into a
single performance measurement baseline (PMB).• Reliably tracks planned value (PV) ,earned value (EV) actual cost (AC) of
work performed• Provides performance measures against the PMB.• Provides means of identifying, reviewing, approving, and incorporating
changes to the PMB.• Provides trend analysis and evaluation of estimated cost at completion.• Provides a sound basis for problem identification, corrective actions, and
management re-planning.
EVMS Certification October 4-6, 2011 12