PTT303 /2 PROCESS MODELLING AND SIMULATION SEM 1 (2013/2014) Batch Processing Modelling (Unit...
-
Upload
dwight-gray -
Category
Documents
-
view
222 -
download
0
Transcript of PTT303 /2 PROCESS MODELLING AND SIMULATION SEM 1 (2013/2014) Batch Processing Modelling (Unit...
PTT303 /2 PROCESS MODELLING AND
SIMULATIONSEM 1 (2013/2014)
Batch Processing Modelling (Unit Procedures
Initialising)
STUDENT SHOULD BE ABLE TO;
DEMONSTRATE the methods of initialising of operation of unit procedures
SIMULATE the flowsheet of bioprocess production plant
WHAT IS A UNIT PROCEDURE?
In the batch modeling mode, a Unit Procedure may consists of various Operations:
Reactor procedure: feed charge, reaction, product withdraw, etc
Filtration procedure: filtration, cake wash, CIP, etc
In continuous modeling mode, a Unit Procedure= Unit Operation
HIERARCHY IN BATCH MODELING
Operation(s) level
Procedure(s) level
Entire plant
The same for continuous process modeling
FUNCTION OF EACH UNIT PROCEDURE
Vessel Procedure (P-1):Acts as a batch reactor to carry out reaction: A + B CHeptane is used to dissolve components A & B, to aid separation in P-2
Plate and Frame Filtration (P-2):Component C is not dissolved in heptane, hence is filtered out by the filter clothHeptane is used to wash out the trapped heptane ( and also the dissolved A & B) from the filter cake
STREAM SPECIFICATION
Click to insert Heptane here
Heptane flow =800 kg/batch
Ingredient flow
T, P = default
SET SPEC FOR STREAM A & B
Stream ID ComponentAmount
(kg/batch)Temperature
Pressure
HeptaneAB
HeptaneAB
8005040
Default
Sequential modular approach
Individual equipment blocks may require iterative solution algorithms
Overall process solution is sequential & not iterative
(Turton et al., 1998)
ADDING OPERATIONS TO P-1
3 Charge operation (to charge A, B and heptane respectively)1 React (Stoichiometric) operation (for reaction to be carried out)1 Transfer Out operation (to deliver product to next unit)
ADDING OPERATIONS TO P-1
Add new operation before the currently selected operation
Add new operation at the end of the list
INITIALISING CHARGE-1
Vol. flowrate=100 L/min
Setup time = 5 min
800 kg heptane
Emission calculation(next slide…)
EMISSION CALCULATION
Click to perform emission calculation
OK, next operation (CHARGE-2)
OK, previous Operation (none)
Previous operation (same tab –none)
Next operation (same tab)
Go to selected operation
INITIALISING CHARGE OPERATIONOperation Operating condition Emission
CHARGE-1 Charge 800kg/batch of heptane using stream “Heptane”Setup time= 5 minProcess time : 100L/min
Perform heptane emission on this stream
CHARGE-2 Charge 50 kg/batch of A (limiting component) using Stream “A”Setup time = 5minProcess time: calculated based on 20 kg/min
Nil
CHARGE-3 Charge 40/kg batch of B using Stream “B” (B is in excess)Setup time = 5 minProcess time : calculated based on 20 kg/min
Please complete the initialisation of CHARGE-2 & CHARGE-3
INITIALISING REACT-1 & TRANSFER-OUT-1
Operation Operating condition Volumes Reaction
REACT-1 Final temp = 50 °CHeat transfer agent:
steamProcess time = 6 hourLeave other values as
defaults
Max Allowable working/ vessel
volume: 80 %
Extent of reaction = 95 %
Reaction stoichiometryA + B C
TRANSFER-OUT-1
Using stream “Rxt out”Duration: same as Cloth Filtration in P-2 (using
Master-Slave Relationship)
Nil
INITIALISING REACT-1 IN P-1
Reaction extent = 95 %
Edit reaction stoichiometry
Rename reaction
Add reaction(s)
Delete stoichiometry (when needed)
Molar stoichiometry
OK, next operation (Transfer-out)
INITIALISING TRANSFER OUT
Transfer out stream
Click here to selectMaster-and-Slave to calculate duration
To quit Vessel Procedure
Select the MasterProcedure
Select the Master Operation in
Master Procedure
MASTER-SLAVE RELATIONSHIP
Slave
Master
Master operation – processing step that control the duration of another operation (slave)When simulation is executed, duration calculation for the slave operation will be bypassed (note: M&E balances affected), until the master operation is metBoth master and slave operation may exist in the same procedure or in another procedure
INITIALISING OPERATION FOR P-2
Cloth Filtration operation (by default, to filter product C)
Cake Wash operation (to wash out left over trapped A & B in filter cake)
Transfer Out operation (to deliver product)
INITIALISING FILTER-1Operation Operating condition Scheduling
FILTER-1 Particulate component removal: 95% C (assuming that A & B are completely soluble in Heptane & C is virtually insoluble).LOD (loss on drying) = 35% (this value cause a portion of heptane & any soluble component to be held in the wet cake 65% is insoluble C).Filtrate stream: “B + Heptane”
By default, first operation of any batch unit procedure is scheduled to start at the beginning of the batchStart time: relative to the START of TRANSFER-OUT-1 operation in P-1 procedure
INITIALISING FILTER-1
Scheduling
C = 95% removal
LOD = 35%
Filtrate
By default
Filtration will only start when product is
transferred out from P1
INITIALISING CAKE-WASH-1 & TRANSFER-OUT-1
Operation Operation condition
CAKE-WASH-1
Wash In stream: “Wash in”Wash Out stream: “Wash out”Wash solvent: heptane (click on “Composition”, select “Auto-adjust”, the program will estimate a value automatically)Wash time: 30 minutesWash type: slurry (Note: A “slurry” wash will essentially dilute the soluble components trapped in the cake and remove most of them in the wash stream, whereas a “displacement” wash will remove the soluble components form the cake in a plug-flow fashion.)
TRANSFER-OUT-1
Transfer out using stream “C”Duration: calculated based on 10kg/min
Simulating a process:1. Menu bar: Task/ Solve M&E balances2. Press “Ctrl 3”3. Solve icon in menu bar4. Press “F9”
RESULT VIEWING
1. Calculated output variables for each oeration can be viewed by revisiting the corresponding Operation Data dialog windows
2. To see the calculated equipment sizes, right click on the unit procedure icon & choose the Equipment Data… option
3. The contents of a piece of equipment as a function of time can be viewed by right clicking on a unit procedure and selecting Equipment Contents or Operation Sequence
4. The calculated flowrates and compositions of intermediate & output streams can be viewed by in the Simulation Data dialog windows of each stream
RESULT VIEWING
5. A list of reports can be viewed in Reports: Stream Reports (SR) Economic Evaluation Report (EER) Itemized Cost Report (ICR) Cash Flow Report (CFR) Throughput Analysis Report (THR) Environmental Impact Assessment Report (EIR) Emission Reports (EMS) Input Data Report (EDR) Equipment Report (EQR)
Let’s visit the one by one…
CHECK YOUR SCHEDULING RESULTS
Reaction A B C
MWInitial content, miO (kg)
Initial mol, niO (kg-mol)
X= 95% (based on A)Current mol, n (kg-mol)Current content, m (kg)
nAO-nAOX nBO-nBOX
--
nAOX
+
CHECK YOUR SCHEDULING RESULT Heptane charge =____kg/batch (stream
specification) Volumetric flowrate=___L/min (in Operation
Data/CHARGE-1) Task: Find out the density of the heptane stream
from your simulation sheet Verify the heptane charging duration
calculated by SPD heptane