PTS (Conductor Design and installation manual for offshore platform)

303
MANUAL CONDUCTOR DESIGN AND INSTALLATION MANUAL FOR OFFSHORE PLATFORM PTS 20.052 DECEMBER 1980

description

PTS 20.05.2

Transcript of PTS (Conductor Design and installation manual for offshore platform)

Page 1: PTS (Conductor Design and installation manual for offshore platform)

MANUAL

CONDUCTOR DESIGN AND INSTALLATIONMANUAL FOR OFFSHORE PLATFORM

PTS 20.052DECEMBER 1980

Page 2: PTS (Conductor Design and installation manual for offshore platform)

PREFACE

PETRONAS Technical Standards (PTS) publications reflect the views, at the time of publication,of PETRONAS OPUs/Divisions.

They are based on the experience acquired during the involvement with the design, construction,operation and maintenance of processing units and facilities. Where appropriate they are basedon, or reference is made to, national and international standards and codes of practice.

The objective is to set the recommended standard for good technical practice to be applied byPETRONAS' OPUs in oil and gas production facilities, refineries, gas processing plants, chemicalplants, marketing facilities or any other such facility, and thereby to achieve maximum technicaland economic benefit from standardisation.

The information set forth in these publications is provided to users for their consideration anddecision to implement. This is of particular importance where PTS may not cover everyrequirement or diversity of condition at each locality. The system of PTS is expected to besufficiently flexible to allow individual operating units to adapt the information set forth in PTS totheir own environment and requirements.

When Contractors or Manufacturers/Suppliers use PTS they shall be solely responsible for thequality of work and the attainment of the required design and engineering standards. Inparticular, for those requirements not specifically covered, the Principal will expect them to followthose design and engineering practices which will achieve the same level of integrity as reflectedin the PTS. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting from hisown responsibility, consult the Principal or its technical advisor.

The right to use PTS rests with three categories of users :

1) PETRONAS and its affiliates.2) Other parties who are authorised to use PTS subject to appropriate contractual

arrangements.3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with

users referred to under 1) and 2) which requires that tenders for projects,materials supplied or - generally - work performed on behalf of the said userscomply with the relevant standards.

Subject to any particular terms and conditions as may be set forth in specific agreements withusers, PETRONAS disclaims any liability of whatsoever nature for any damage (including injuryor death) suffered by any company or person whomsoever as a result of or in connection with theuse, application or implementation of any PTS, combination of PTS or any part thereof. Thebenefit of this disclaimer shall inure in all respects to PETRONAS and/or any company affiliatedto PETRONAS that may issue PTS or require the use of PTS.

Without prejudice to any specific terms in respect of confidentiality under relevant contractualarrangements, PTS shall not, without the prior written consent of PETRONAS, be disclosed byusers to any company or person whomsoever and the PTS shall be used exclusively for thepurpose they have been provided to the user. They shall be returned after use, including anycopies which shall only be made by users with the express prior written consent of PETRONAS.The copyright of PTS vests in PETRONAS. Users shall arrange for PTS to be held in safecustody and PETRONAS may at any time require information satisfactory to PETRONAS in orderto ascertain how users implement this requirement.

Page 3: PTS (Conductor Design and installation manual for offshore platform)

EP/23.4 TEL: (070)

Dear Sirs,

CONDUCTOR DESIGN AND INSTALLATION MANUAL (EP 52510 - DECEMBER 1980)

In response to requests from operating companies for advice on offshore conductor installation we aresending a copies of a Shell Group "Conductor Design and Installation Manual", which we believe willbe of assistance on this subject.

The manual is of loose-leaf construction to permit easy insertion of updates as they becomenecessary.

As with all operationally oriented subjects, feedback from your local experience offshore is essentialfor further development of techniques.

Yours faithfully,

Shell Internationale Petroleum Maatschappij B.V

Page 4: PTS (Conductor Design and installation manual for offshore platform)

CONTENTS

INTRODUCTION

DEFINITIONS

1. GENERAL DESIGN AND INSTALLATION CONSIDERATIONS

Functions of Conductors

Sequence of Design and Installation

Figure 1.1

2. DATA COLLECTION

Site Investigation

Bathymetric, Side Scan Sonar and TV Surveys

Shallow Seismic Survey

Soil Borings

Design Check List

(i) Penetration

(ii) Steel Section and Grade

(iii) Special Considerations

Installation Equipment

(i) Derrick Barge

(ii) Hammers

(iii) Drilling Rig

(iv) Contingencies

3. CALCULATING THE SETTING DEPTH

Factors which determine the Setting Depth

Formation Breakdown (Hydraulic Fracture)

Leak - Off Tests

Other Causes of Lost Circulation

Setting Depth and Spacing between Conductors and Piles

Conductor Installation by Drilling or Drill-Drive

Unstable Strata

Conductor Tip in Clay

Page 5: PTS (Conductor Design and installation manual for offshore platform)

References

Figure 3.1

Figure 3.2

4. SPUDDING-IN PROCEDURES

Cleaning-out of Conductor

Pilot Hole

Drilling Techniques

Setting the First Casing

5. INSTALLATION METHODS

Driving

Drill-Drive

Drill and Drive

Drill and Cement

6. AXIAL BEARING CAPACITY OF CONDUCTORS

General

Safety Factor

The Conductor as a Pile

Conductors Installed by Driving

Conductors Installed by the Drill-Drive Technique

Conductors Installed by the Drill and Drive Technique

Conductors Installed by the Drill and Cement Technique

Computing the Axial Load on the Conductor

References

Figure 6.1

7. SELECTION OF INSTALLATION METHOD

Assessing Driving for Safety

Assessing Driving for Feasibility

Assessing Drill-Drive for Safety

Page 6: PTS (Conductor Design and installation manual for offshore platform)

Assessing Drill-Drive for Feasibility

Assessing Drill-and-Drive

Assessing Drill-and-Cement

Current Practice

8. RECORDING THE INSTALLATION AND INSTRUMENTATION

Why Installation Records are Essential

Current Practice

Instrumentation

General Quality Control

Figures 8.1, 8.2 and 8.3

9. CONDUCTOR SHOES

Improving Drivability

Reducing the Possibility of Damage to the Conductor Tip

Directional Control

Clearances

Length off Shoe

References

Figure 9.1

10. CURVED CONDUCTORS

Reasons for using Curved Conductors

Disadvantages of Curved Conductors

Limitations on Curvature

Drivability

Alternatives

11. CONTINGENCY PROCEDURES FOR CONDUCTORS WHICH DO NOT REACH SETTINGDEPTH

Conductors not Satisfying Axial Capacity Requirements

Conductors not Satisfying Formation Fracture Requirements

Other Contingency Measures

Page 7: PTS (Conductor Design and installation manual for offshore platform)

12. DO's and DON'T's

Do's

Dont's

APPENDICES

APPENDIX I : Records of Meetings with Personnel of various Shell Group Companies.

APPENDIX II-1 : Soil Parameters Required for Conductor Design and Installation Planning.

APPENDIX II-2 : Calculation of the Coefficient of Earth Pressure at Rest (Ko ).

APPENDIX III-1 : Use of the Wave Equation in Drivability Analyses.

APPENDIX III-2 : Example of Wave Equation Analyses for Conductor Drill-Drive Sequence.

APPENDIX III-3 : Extract from "Construction Specification for Installation of Steel Platforms",Prepared by SSB (September 1978).

APPENDIX III-4 : Extract from "Outline Installation Procedure for SFDP A", Prepared by SSB.

APPENDIX III-5 : Cormorant Alpha Conductor Installation Procedure, Prepared by Shell Expro(October 1978).

APPENDIX III-6 : Extract from "Drill and Cement Conductor Installation Specification", Prepared byQPPA

APPENDIX IV-1 : American Petroleum Institute (API RP 2A 1979) Axial Capacity Calculations

APPENDIX IV-2 : Axial Capacity of a Drilled and Cemented Conductor

APPENDIX V-1 : Report prepared by BSP entitled "Conductors for Tender Assisted Drilling Platforms"dated October 1972

APPENDIX V-2 : Calculation of Allowable Stick-up Height.

APPENDIX V-3 : Typical Blowcount Record Sheet for offshore use together with a completedexample from SBPT

APPENDIX V-4 : Instrumentation for Conductors, Piles and Hammers

APPENDIX V-5 : "Curved Conductor and Guide Considerations - Gulf of Mexico", Prepared by ShellOil.

APPENDIX V-6 : Use of Wave Equation for curved Conductors. Fugro Report for Shell Expro,U0227dated 25th September, 1978.

Page 8: PTS (Conductor Design and installation manual for offshore platform)

INTRODUCTION

The purpose of this Manual is to serve as a guide for Company staff involved in the design andinstallation of conductors for fixed steel platforms. It is not a complete and infallible rule book for usein all circumstances. It cannot, therefore, replace common sense, sound judgement based on theknowledge of engineering principles, and field experience.

The design and installation of conductors involves engineers from a number of different disciplines.Some may have difficulty in fully appreciating the requirements of others. Problems with conductorsmost frequently occur because of lack of communication between the different disciplines during theinitial stages of the project. It is hoped that the contents of this Manual will enable the dialoguebetween departments to be improved. For this reason some subjects which are usually dealt with byDrilling Department are discussed, e.g. spudding-in procedures. Such discussions are for backgroundpurposes only, and Drilling Department should be consulted for advice on current good practice. Asimilar comment applies to design procedures which are always the responsibility of a platform designgroup, e.g. the computation of stress in a conductor due to environmental loading. If advice is requiredon such matters, Structural Engineering should be consulted.

Any document concerning conductors is complicated by the fact that each discipline uses its ownterminology and system of units. Therefore, a list of definitions has been provided together withcommonly used alternatives. With regard to units it has proved impractical to standardise in thisManual. Sizes are quoted in the vernacular of the relevant discipline, e.g. the majority of the drillersstill use inches and pounds, platform designers generally use SI units. The Group's efforts to achievefull metrication are, however, fully recognized.

During the preparation of the Manual, discussions were held with Engineers in a number of GroupOperating Companies. Brief records of these discussion are presented in Appendix I. From theserecords it is apparent that there, is considerable diversity of practice around the world. This is notsurprising because different environments will result in varying solutions to the same problems. Hencean approach to conductor design and installation which may have proved ideal in one operating areamay be less suitable in another. However, a lot can be learnt from the experiences of others and anexchange of knowledge can improve even the best practices.

This Manual has been written by Fugro Limited in the U.K., under the direction of SIPMDepartment EP/23.4.

NOTE :

There is quite some confusion in the definition of a conductor. The definitions given above are of theReport EP - 40806 "Well Control and Blowout Prevention Manual" and it is perhaps somewhatunfortunate that the names "marine conductor" and "conductor" so closely resemble each other. Toadd to the confusion, construction engineers tend to drop the prefix "marine" and just speak of "drivingthe 30" conductor". Since this manual was written by construction oriented engineers, the single wordconductor refers to the first pipe installed, typically 30" in diameter, typically driven, with apologies tothe authors of the Well Control and Blowout Prevention Manual.

SURFACE STRING :

A pipe which is installed inside the conductor, typically of 13 3/8" diameter. It is the second casingstring, normally cemented to the seabed and serves to provide blowout protection, to seal off shallowwater sands and prevent loss of circulation.

SPUDDING-IN : The procedure for drilling the hole for the first casing string.

Page 9: PTS (Conductor Design and installation manual for offshore platform)

DEFINITIONS

MARINE CONDUCTOR (see NOTE on next page)

The first pipe to be installed when drilling an offshore well typically 30" in diameter although othersizes are used. The marine conductor usually extends from the seabed up to the cellar deck of theplatform and may have a penetration of a few hundred feet. The purpose is to provide lateral supportto the well, to case off very soft formations below the seabottom, to facilitate circulation of drilling fluidand to guide the drill string until the next casing string has been set. The term "marine conductor"relates specifically to offshore drilling from a bottom- supported fixed or mobile platform (as opposedto a floating platform) with above water well control equipment.

CONDUCTORS (see NOTE on next page)

A pipe which is installed inside the marine conductor typically 20" in diameter although other sizes arealso used. The conductor is run into a predrilled hole and its function is to case off unconsolidatedformations and water sands and to provide protection against shallow gas. This string is normallycemented to seabed and is the first string on which blowout preventers are installed. The conductor isconsidered to be the first casing string of the well.

Page 10: PTS (Conductor Design and installation manual for offshore platform)

1. GENERAL DESIGN AND INSTALLATION CONSIDERATIONS

Functions of Conductors

1.1 The primary functions of a conductor are to facilitate the spudding-in of the well and to provideprotection and lateral support to the well casings. The conductor assists spudding-in byproviding guidance for the drilling tools, allowing the circulation of drilling fluid and supportingweak formations above the conductor tip level. Also, in conjunction with a diverter system, theconductor enables diverting a possible flow, originating from shallow formations. In the longterm the conductor protects the well from external corrosion and provides lateral supportagainst environmental loads by spanning between guides.

1.2 On some platforms the conductor bracing is designed so that the conductors act as laterallyloaded piles and assist the foundations in taking-out shear at mudline. This may have thebeneficial effect of reducing the number of foundation piles required. However, the conductormust be designed for this mudline shear and this can involve increasing the wall thickness ofthe conductor pipe. When there are no advantages in using the conductors as laterally loadedpiles, guides in the bottom horizontal bracing are either omitted or designed with sufficientclearance to prevent conductors acting as piles.

1.3 If curved, slanted or otherwise "deviated" conductors are used they may provide initialalignment in the preferred azimuth and increase the separation of conductors at tip level. Thelatter reduces the risk of the drill string colliding with a previously installed casing string.

SETTING DEPTH

The depth from some datum to the conductor shoe. This datum is the derrick floor during the drillingphase. In the production stage it may be the bottom flange of the wellhead or seabed.

ADD-ON

An extension pipe welded to the top of the conductor to permit further penetration to be achieved.Also it generally forms part of the final conductor configuration.

ABBREVIATIONS

OPCOS - Operating Companies

DB - Derrick Barge

GBS - Gravity Base Structure

NDT - Non-destructive testing

SRD - Soil Resistance at Time of Driving

dia. - diameter

O.D. - outside diameter

I.D. - internal diameter

w.t. - wall thickness

Page 11: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 1.1 DESIGN AND INSTALLATION SEQUENCE

Page 12: PTS (Conductor Design and installation manual for offshore platform)

1.4 Under some circumstances the conductor may be required to serve as a temporary supportfor casing strings during cementation.

Sequence of Design and Installation

1.5 The considerations of paragraphs 1.1 to 1.4 together with information concerning:

site and soil conditions

platform and foundation design

environmental conditions

installation equipment

determine the diameter, wall thickness and setting depth of the conductor and the method ofinstalling it. A schematic representation of the design and planning procedure is provided onFigure 1.1. The numbers in each box on Figure 1.1 refer to the relevant paragraphs of thisManual.

1.6 A decision on the number of conductors, their diameter, the setting depth and whether theyare to be vertical, slanted or curved has to be taken before the commencement of finalplatform design. This may be up to four or five years before the first well is installed. It is mostimportant that the detailed planning of the installation of the conductor and the well are startedat this early stage and are not left, as is the practice of some Oil Companies outside theShell Group, until after the platform has been launched. The reason why conductor designand installation planning must start so far in advance of well installation is that the conductorshave a large influence on the size of the platform, its structural configuration and the waveloads acting upon it.

2. DATA COLLECTION

2.1 The purpose of this Section is to ensure that the Project Engineer or the members of theProject Team collect or generate sufficient data with which to optimise the design and methodof installing the conductors. Some of the information concern physical parameters at theproposed platform location; other data result partly from decisions made by the Project Team,eg. spudding-in procedure, see Section 4.

Site Investigation

2.2 A site investigation has to be made as part of the design procedure for the platformfoundation. Its scope should be such that it also provides data for conductor design andinstallation planning. Site investigations for platforms may include:

(a) bathymetric survey

(b) side scan sonar survey

(c) shallow seismic survey

(d) soil borings and insitu tests

(e) TV inspection

Page 13: PTS (Conductor Design and installation manual for offshore platform)

It is common practice to carry out the first three items simultaneously from one vessel equipped forgeophysical work. The soil borings would be made from a different vessel, usually under a separatecontract and at a different time. The TV inspection of the seabed can be made in conjunction witheither the soil or geophysical survey. Alternatively it can be performed as part of a "submarine"survey.

Bathymetric, Side Scan Sonar, and TV Surveys

2.3 These surveys provide data on water depth, seabed topography and obstructions on theseabed such as wrecks, pipelines and boulders. The requirements for platform design will beadequate for the conductors.

2.4 If there are any obstructions on the seabed, such as boulders, it will be necessary to removethem prior to platform or conductor installation, whichever is first. This is usually done by a"trawling" technique.

2.5 Before installing the conductors of a platform, it may be necessary to carry out an additionalsurvey for "junk" (material dropped from the platform during installation). A number oftechniques are available for carrying out this survey, for example TV can be used if there isno guide at bottom bracing level. In other cases each guide might have to be "fished".

Shallow Seismic Survey

2.6 The shallow seismic survey is made for a number of reasons? for the conductors the mostimportant being:

(a) to indicate whether shallow gas is likely to be encountered within the foundation soils

(in conjunction with deep seismic records)

(b) to provide information on soil stratification in conjunction with the soil borings

(c) to detect "boulders" below seabed

2.7 The information obtained on the presence or absence of shallow gas is important for thewhole casing and drilling programme, including the setting depth of the conductor and the"spudding-in" procedure. A pocket of shallow gas shows up as a "bright spot" on the seismicrecord. However not all "bright spots" are caused by shallow gas and the survey may notdetect every pocket of gas. Therefore the results of the seismic survey provide a goodindication, but not absolute proof, as to whether or not gas is present.

2.8 Boulders below seabed may act as major obstructions to conductors (and to foundation piles).If their presence is suspected, this may influence the selection of the site and of the conductorinstallation technique, ie. drilling may be preferred to driving. A large boulder will produce areflection on the seismic record. The reflection from a boulder has similar characteristics tothat produced by folded bedding within clay strata. A geological assessment is required todetermine the most likely cause of such a reflection and the assistance of an expert ininterpreting the shallow seismic record is recommended, e.g. EP/12 can assist.

2.9 It is essential that the equipment which is to be used for the shallow seismic work will provideinformation to the depths required for conductor design.

Page 14: PTS (Conductor Design and installation manual for offshore platform)

Soil Borings

2.10 To provide data for conductor installation at least one of the soil borings should be taken 15m(50ft) or more below the expected setting depth of the conductors. This involves estimatingthe expected setting depth using a combination of

(a) past experience in the Operating Area

(b) data obtained during the drilling of the exploration wells

(c) calculations of setting depth as described in Section 3.

The drilling, sampling, insitu testing and laboratory testing requirements for conductors arevery similar to those for piled foundations. Because of this, there is no need to regard oneborehole as the "conductor borehole" and other boreholes as "foundation boreholes".However, the brief to the Geotechnical Consultant should include ensuring that the scope ofthe soil investigation is sufficient for the conductors.

2.11 The soil parameters to be determined from the survey and subsequent laboratory testing arelisted in Appendix II-1 and are used for:

(a) calculating the setting depth

(b) determining the "bearing capacity" of the conductor

(c) providing input for the decision on installation method (in conjunction with otherconsiderations)

(d) computing the response to lateral loading

Design Check List

2.12 Having ensured that the data concerning the site is available, the Project Team must checkthat the conductor has been designed to satisfy all requirements. These include:

(i) Penetration

Has the setting depth been calculated,? (see section 3)

Do the parameters used in the computation correspond to the proposed spudding-inprocedure? (see Section 4)

Have the correct values of discharge height and mud density been used?

Are there any other criteria governing conductor penetration, eg. proximity of piles, unstableshallow strata? (see Section 3)

At the design setting depth does the conductor have sufficient bearing capacity (in outsidefriction alone) to support its own weight and that of all equipment and casings hung off it? Inthis context are the weights used in the calculation realistic? Have curvature and buoyancyeffects been included? (see Section 6)

(ii) Steel Section and Grade

Would a stock size, e.g. 30in. O.D. x 1 in. w.t. or 26in. O.D. x ½ in. w.t., be suitable?

Is there sufficient clearance on the inside diameter (allowing for the shoe and stabbing points)for the maximum bit size to pass up and down the conductor when spudding-in?

Page 15: PTS (Conductor Design and installation manual for offshore platform)

Is there any possibility of the drillstring or next casing string standing-up on, or being caughtunderneath an internal shoulder?

Remember that the outside diameter of the conductor usually determines the guide size.Once the design is frozen and the guide size fixed it is difficult to alter the conductor O.D.

Have the structural designers satisfied themselves that the conductor section and grade ofsteel are sufficient to protect the well from environmental forces by acting as:

(a) a beam spanning between guides?

(b) a laterally loaded pile?

If the conductor is to carry axial load has it been checked for combined stresses?

If the conductor is to be driven, have drivability and driving stresses been checked?

(see Section 5)

Finally in case of high steel stresses, are there any possibilities of increasing the section orupgrading the steel to bring stresses within allowable limits?

(iii) Special Considerations

Will corrosion be a particular problem? Could this involve increasing the steel section in thesplash zone?

Should thermal effects be considered?. This might lead to increased stresses in the conductorif the inner casing strings are cemented up to the top of the well.

Will settlement of soil around the conductor impose additional loads upon it?

Is the platform in a mudslide area and have the conductors been designed to resist, or arethey protected against, mudslides?

Is the platform in an earthquake zone and have the conductors been designed accordingly?

Installation Equipment

2.13 A variety of methods are commonly used to install conductors. They are listed on Figure 1.1and are described in detail in Section 5. However the number of options which can beconsidered for a particular platform may be limited by the equipment available:

(i) Derrick Barge

Is it feasible to drive the conductors to the specified setting depth using the derrick bargewhich installed the piles? This would have to be done shortly after the completion of piledriving.

If the conductors cannot be driven would it be worthwhile stabbing the lead sections with thederrick barge and completing their installation later from the platform drilling rig?. It is notnormally advisable to plan to drive the conductors part way by the derrick barge andsubsequently drive to the setting depth from the drilling rig. This is because the "freeze-up"during the inevitable delay can cause serious restart problems.

Page 16: PTS (Conductor Design and installation manual for offshore platform)

(ii) Hammers

What hammers are available? The use of steam hammers is only really practical when aderrick barge is alongside the platform (to lift the hammers and to generate enough steam). Ifthe drilling mast or derrick is to be used to handle the hammer then, normally only diesel andcompressed air hammers can be considered (note - "steam" hammers can operate oncompressed air). The use of hydraulic hammers to install conductors is feasible but up to nowthis has not been tried by any Group Company. Will the hammer overstress the conductors ? Could this problem be solved by increasing the conductor section or by using ahigher grade of steel?

(iii) Drilling Rig

Has the rig been designed to handle hammers and what is the maximum weight of hammerthat may be used?

What is the maximum length of add-on that can be handled within V-door, derrick and piperack constraints? Add-ons should preferably be in one of the standard lengths that aredelivered by the mills, i.e. 6, 8, 12 and 16m.

(iv) Contingencies

What plant is available if contingency procedures have to be employed? (see Section 11)

Page 17: PTS (Conductor Design and installation manual for offshore platform)

3. CALCULATING THE SETTING DEPTH

Factors which determine the Setting Depth

3.1 The setting depths of marine conductors are generally determined on the basis of thefollowing considerations:

(i) the conductor shoe level should be such that drilling for the first casing does not havean adverse effect on the foundations of the platform, eg. reduce the bearing capacityof a pile.

(ii) when drilling below the conductor tip for the first casing string, formation breakdownshould not occur. Formation breakdown takes place when the drilling fluid pressure issufficient to crack the soil forming the borehole wall. This increases the permeabilityof the soil to such an extent that fluid flows freely into the formation. It is thenimpossible to obtain returns to drill floor. This phenomenon is termed "lostcirculation", cuttings cannot be lifted from the bottom of the borehole and the holecannot be advanced.

(iii) the penetration of the conductor below mudline should be sufficient to generate therequired "bearing capacity" in outside skin friction, see Section 6.

(iv) the tip of the conductor should be below any unstable formations.

(v) whenever feasible the conductor tip should be in an impermeable strata such as clayrather than in porous soil such as sand.

The relative importance of each of the criteria listed above will vary from site to site. In fact, in someoperating areas some of the above may not be considered at all. For example some Group Companiesignore item (ii) and are prepared to drill "blind", for the first casing. "Blind" drilling is drilling withoutreturns of the, drilling fluid, which is pumped into the formation. Under these circumstances the firstcasing string is normally set at shallower depths. (See minutes of meetings with QPPA, SSB, andSOC). However, unless there is considerable experience in the operating area at similar platformlocations, "blind" drilling cannot be recommended, (see minutes of meeting with SIPM ). Inblind drilling formation fracture occurs, circulation is lost, cuttings are not lifted and the drilling isproceeding without returns. The principal objection to blind drilling is that drilling fluid is being pumpedinto the soil. This may cause cratering and channelling, which may affect the bearing capacity ofadjacent piles and/or cause the conductor to settle unexpectedly, particularly a shallower drivenconductor.

Formation Breakdown (Hydraulic Fracture)

3.2 Formation Breakdown of the soil below the conductor tip will occur during drilling for the firstcasing if the hydrostatic pressure of the drilling fluid exceeds the strength of the soil formation.Instead of the drilling fluid being returned to the drill floor it is pumped into the soil formation.Remedial measures, other than "blind" drilling, for this situation are discussed in Section 11.Formation breakdown should be avoided because:

(a) remedial measures are costly in rig time and materials

(b) mud losses may have an adverse effect on the foundations of the platform and on theconductor.

(c) mud is expensive.

Page 18: PTS (Conductor Design and installation manual for offshore platform)

3.3 In most circumstances the soil formation strength at any depth can be obtained from thelesser of:

(i) the effective overburden pressure of the soil

(ii) the effective horizontal earth pressure

The effective overburden pressure is the difference between the density of the soil and the density ofseawater multiplied by the depth below mudline. The effective horizontal earth pressure is equal to theeffective overburden pressure multiplied by the "at rest earth pressure coefficient" for the soil,"Ko,".The value of Ko is a function of the soil properties and is generally 0.5 to 3.0. Thus to avoid hydraulicfracture

3.4 The inequalities of paragraphs 3.3 may be arranged as:

and

Thus the setting depth to avoid formation breakdown is sensitive to the discharge heightabove sea level, the drilling fluid density and the depth of water. Also soil type may have aconsiderable effect on the setting depth. For example a normally consolidated clay or sandcould have a Ko value of 0.5 and the vertical cracking criterion would govern. A heavilyoverconsolidated clay might have a Ko of 2 or more in which case formation breakdown wouldoccur due to horizontal cracking, the first criterion. All other things being equal, the settingdepth below mudline of the conductor in the normally consolidated soil could be up to twicethat required in the overconsolidated clay.

Page 19: PTS (Conductor Design and installation manual for offshore platform)

3.5 It is recommended that the results of the calculations are presented graphically as onFigure 3.1. A method for computing Ko is described in Appendix II-2. A more rigorousapproach to calculating the formation strength may be found in Ref. 3.1.

Leak-Off Tests

3.6 The formation strength may be measured in the field by performing a leak-off test. In outlinethe test is carried out a follows:-

(a) drill-out to a depth of 3m to 6m (10 ft to 20 ft) ahead of the conductor shoe: cap conductor andconnect to a pump.

(b) fill the entire conductor with fluid and commence pumping.

(c ) raise the fluid pressure in small increments of approximately 10% of the effective soil overburden pressure. At each increment plot the fluid pressure versus the measured flow rate.The points should fall on a straight line until the "formation intake pressure" is reached. Atpressures greater than this very much greater flow rates will occur for a given pressureincrement, see figure 3.2, and the points will deviate from the straight line to form a curve ofreducing gradient. Attempts to increase the pressure further will lead to formation breakdown.There are a number of different techniques for performing these tests. The method used willdepend on the circumstances and the equipment available. A description of the standardmethod used by the drillers may be found in Appendix 15 of EP- 40806, "Well Control andBlowout Prevention Manual".

3.7 An alternative form of this test is the "limit test". This is exactly the same as the leak-off testexcept that the fluid pressure is not increased beyond the "maximum required mudholdingcapacity". It will confirm that the formation strength is sufficient for the proposed drillingprogramme without indicating what the strength is, see Fig.3.2.

3.8 The drillers have strong reservations concerning the performance of leak-off tests atconductor shoe level. This is because of the risk of fracturing the formation which could giverise to problems during subsequent drilling. The preferred method would then be a "circulatingtest" using a mud with a density which is required for drilling the hole below the marineconductor. During development drilling carefully controlled and supervised tests have beenperformed from North Sea platforms for assisting in the determination of conductor settingdepths.

Other Causes of Lost Circulation

3.9 In highly permeable strata such as coarse sand, gravel, cobbles, shell beds etc., the naturalpermeability may be so great that circulation is lost without formation fracture, i.e. at depthsdeeper than those computed from paragraph 3.4. Rock strata which are heavily jointed andfissured will also have locally high permeability. If circulation is lost because of high naturalpermeability, it can usually be restored by forming a "mud cake" or by use of lost circulationmaterial, LCM. Setting the tip of a conductor in highly permeable strata should be avoided.

3.10 If a conductor is installed by drilling or by a drill drive technique, precautions must be taken toensure that there is an adequate seal between the outside of the conductor and the soil. Thisis to prevent drilling fluid returning up the outside of the conductor to mudline. For drill-drivetechniques this may involve driving the conductor into virgin soil for the last add-on length. Fordrill and cement techniques the utmost care should be exercised to ensure propercementation.

Page 20: PTS (Conductor Design and installation manual for offshore platform)

Setting Depth and Spacing between Conductors and Piles

3.11 Having calculated the setting depth to avoid formation breakdown it is necessary to checkwhether or not such a depth will be detrimental to the piles. if the conductors were driven to asignificant depth below the tip of the piles, there would be little likelihood of the piles beingaffected by the drilling procedure for the first casing. This is why some oil companiesoperating in the Gulf of Mexico, but not SOC, insist that all conductors be taken below the tipof the piles, (see minutes of meetings with SOC).This rule, although safe, may beunnecessarily conservative in some cases. However, if there is a chance of encounteringshallow gas during drilling, the conductor of the first well to be drilled should be set at least 15m below the tip of the piles.

3.12 If the conductors are sufficiently distant from the piles and provided formation breakdowndoes not occur and shallow gas is not encountered, drilling for the first casing, or theconductor itself, will have no effect on pile capacity. In these circumstances the conductorsetting depth need not be related to the pile tip level. At this "sufficient distance" there mustbe enough clear space such that there is no danger of the conductor being driven into theside of a pile and that washout does not affect the soil in which the pile develops its capacity.To allow for the use of contingency procedures, such as drilling ahead of conductors whichrefuse prematurely, it is recommended that all conductors have this safe clearance from thepiles. This distance will depend upon:

(a) the diameters of the pile and conductor

(b) the soil conditions

(c) whether the pile capacity is developed mainly by friction or mainly by end bearing

3.13 The experience of operating companies is useful in determining the required clearance

- for well head jackets installed after a mud line suspension well, it has been noted thatspacings of 6ft centre to centre between pile and conductor may affect pile driving,(see minutes of meeting with QPPA)

- when drilling for the first casing, returns are occasionally noted upadjacent,conductors, (see minutes of meeting with SSB). This presumablyindicates washout at conductor tip level

- a rule of thumb is that the minimum distance between a pile and conductor should begreater than 10ft, (see minutes of meetings with SOC)

- conductors may deviate from their proposed alignment, (see minutes of meeting withShell Expro, SSB, SOC). Directional surveys indicate this may be as much as2 degrees per 100ft locally

- supposedly straight conductors may have a small curvature, (see minutes ofmeetings with Shell Expro)

- for conductors set in a sand strata, drilling through one of them may cause anadjacent conductor to settle, (see minutes of meeting with SOC)

- collisions between conductors occurred on a 5ft x 5ft grid, (see minutes of meetingwith SOC).

Page 21: PTS (Conductor Design and installation manual for offshore platform)

3.14 From the observations in paragraph 3.13 the following conclusions may be drawn:

(a) in sand, drilling may result in a hole several times the diameter of the bit. There areindications that, in extreme cases, the washout zone may extend to a distance of fourtimes the nominal hole diameter.

(b) over relatively shallow depths driven conductors may deviate from proposedalignments by 3ft and deviations of one degree per 100ft are common.

3.15 To ensure that there is no reduction in the capacity of a pile, the zone of soil within 2 pilediameters of the centre of the pile should not be disturbed by drilling. Thus the minimumcentre to centre spacings between piles and conductors for the clearances to be safe are

- for piles embedded in CLAY:

S = (2 x D) + 3 + d 3.5

where: S = the minimum centre to centre spacing between a pile and conductor

D = pile diameter

d = conductor diameter

and all dimensions are in feet. The 3ft term is for deviation and the formula allows for drillingan oversize hole.

- for piles obtaining much of their capacity from end bearing in SAND:

S = (2 x D) + 3 + (4 x d) 3.6

where all dimensions are in feet. The "4 x d" term assumes that washout will occur in thefounding sand stratum.

3.16 If the pile penetration exceeds 300ft the allowance for deviation should be increased to 6ft(2m); for penetrations in excess of 400ft the allowance for deviation should be 10ft (3m).

3.17 As an example, for a 48in diameter pile and a 30in diameter conductor the required minimumcentre to centre spacings are:

for friction piles in CLAY, 8 + 3 + 2.5 = 13.5ft

for end bearing piles in SAND, 8 + 3 + 10 = 21ft

The value calculated above for a friction pile is in reasonable agreement with the rule ofthumb used by SOC. For the same pile and conductor SOC would calculate a centre to centrespacing of 2 + 10 + 1.25 = 13.25ft.

3.18 If for some special reason the conductor to pile spacings were less than the minimumspecified here, the conductors would have to be driven to a depth of at least 4 pile diametersbelow the tip of the piles. However, in these circumstances drilling below the tip of theconductor before it reached this depth could not be allowed until the effect this could have onthe piles had been carefully evaluated.

Page 22: PTS (Conductor Design and installation manual for offshore platform)

3.19 The centre to centre spacings between conductors is a separate matter and should bedecided by the drilling department.

Conductor Installation by Drilling or Drill-Drive Technique

3.20 Drilling ahead at relatively shallow depths will be required for conductors installed by the drill-drive technique. The same comment obviously applies to drilled and cemented conductors. Itis essential that the drilling for the conductors does not result in formation breakdown. Mostoperating companies overcome this problem by using seawater as the drilling fluid anddischarging the returns at some convenient level below the drill floor. For example,Shell Expro when using the drill-drive technique employ a circulating gravity connectorwhich allows discharge below sea level. QPPA, who use drilled and cemented conductors,use seawater for drilling and clean out the hole with slugs of viscous mud. Because of thesmall air gap and shallow water depth at most platform sites offshore Qatar, hydraulic fractureduring conductor drilling is not a problem for QPPA, see paragraph 3.4

3.21 Drilling close to mudline may result in surface washout or collapse of seabed formations. Thiswill cause a cone of depression around the conductors and if it extends towards a pile, mayreduce the lateral capacity of the pile. This phenomenon has been observed by QPPA, seeminutes of meetings. Washout can also have a serious effect on drilling templates, causingthem to tilt. To overcome these problems it is recommended that conductors penetrate atleast 20ft (6m) before drilling commences. With soft soils the self weight of the conductor willoften be sufficient to cause this penetration. With harder soils, driving, vibrating or some othermeans will have to be employed.

Unstable Strata

3.22 Unstable strata are defined here as those which under some design or installation conditionsmay suffer collapse or movement. They are usually encountered near seabed level andconductors should be driven through them if possible. In certain circumstances they mayoccur deeper down. For example, in a seismically active area, loose granular strata even atdepths of 100ft or more below seabed may liquefy during an earthquake. Specialist advicemust be sought with respect to liquefaction potential.

3.23 Sites with sloping seabeds may be susceptible to mudslides. Conductors must always betaken below the sliding zone to protect the casing strings. However in many cases theconductors have not the structural strength to resist the mudslide and must be protectedthemselves. For example in the Gulf of Mexico this is done either by driving a caisson, 10 to15ft (3m to 5m) in diameter to below the sliding zone and installing the conductors inside it; orby installing the conductors inside a foundation pile. In the latter case they must be driven atleast 4 pile diameters below the tip of the pile. The piles cannot be considered to have anyend bearing since the soil plug inside the pile is removed before conductor installation.

Conductor Tip in Clay

3.24 If it is possible, without significantly increasing the penetration, to set the conductors in a soilof very low permeability (such as clay) rather than a soil which is prone to washout (such assand) then this should be done. It will make spudding-in safer by reducing the possibility ofthe conductor (or an adjacent conductor) suddenly dropping, (see minutes of meeting withBSP and SOC) It will be easier to obtain returns and facilitate the cementing of the nextcasing string.

Page 23: PTS (Conductor Design and installation manual for offshore platform)

References

3.1 BJERRUM, L. et al. "Hydraulic Fracturing in Field Permeability Testing" Geotechnique Vol. 221972 pp319-3 32.

Page 24: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 3.1 PLOT OF HYDROSTATIC MUD AND SEAWATER PRESSURE AND LIMITINGSTRESS CONDITION AGAINST DEPTH

Page 25: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 3.2 TYPICAL LEAK-OFF AND LIMIT TEST RESULTS

Page 26: PTS (Conductor Design and installation manual for offshore platform)

4. SPUDDING-IN PROCEDURES

4.1 In this Manual the term "spudding-in" is used to describe the drilling procedures for the firstcasing. It is necessary that all those involved in conductor design and installation have anappreciation of spudding-in procedures since they are the next stage in drilling the well afterthe conductor has been set. Because of this, conductor design and installation and spudding-in procedures are interdependent. For example in Section 3 it is explained how the drillingprocedure for the first casing string determines the conductor setting depth if formationbreakdown is to be avoided. Therefore, this Section of the Manual is included to provideengineers who are unfamiliar with drilling techniques with some background data onspudding-in procedures. It is not intended to be a definitive guide to spudding-in practice.

Cleaning-out of Conductor

4.2 For driven conductors the soil plug in the conductor is removed by drilling. For conductorsinstalled by the drill and cement technique the residual cement plug above the float shoe mustbe drilled out. After the conductor has been cleaned out it is common practice to drill a pilothole which is subsequently opened to the size required for the first casing. However, prior todrilling the pilot hole it may be advisable to drill a full size hole approximately 3m ahead of theconductor shoe. The reasons for drilling this short hole are:-

(a) to check that the shoe is not damaged

(b) to centralise subsequent holes

(c) to confirm that the axial external skin friction capacity exceeds the weight of the conductor.

Pilot Hole

4.3 Having cleaned out the conductor it is the practice of a number of operating companies to drilla pilot hole to the setting depth of the first casing. A typical procedure for a 16in. casing wouldbe:

(i) place BOP stack (or diverter) on top of conductor

(ii) using a 13 3 /4" bit, drill the pilot hole with returns to deck level

(iii) remove BOP stack (or diverter)

(iv) if this is the first well on a platform run logging tools

(v) open hole with hole opener or bit.

(vi) set 16" casing.

Of course the sizes of bits used vary with conductor and casing dimension.

4.4 The pilot hole is used for two reasons. First, it is a precaution against shallow gas. If any gasis encountered the flow will be less than for the main hole. In the example quoted above, theflow from a 13 3/4" hole would be less than one half of that from a 20" hole and with a smallerbit, standard BOP stacks can be used. It should be noted that with this technique noprotection is available when opening the hole to final size. The second reason for the pilothole is to allow standard logging tools to be run.

Page 27: PTS (Conductor Design and installation manual for offshore platform)

Drilling Techniques

4.5 When drilling for the first casing it is recommended by all Shell Group companies that,if possible, returns should be obtained at deck level. One advantage is that the driller has anearlier warning of a shallow gas influx. To achieve returns, drilling with a controlledpenetration rate may be required to reduce annular pressures and the risk of formationbreakdown.

4.6 Some Shell Group companies use seawater as a drilling fluid; others use mud. If seawater is used slugs of viscous mud are periodically spotted to prevent sticking of the drillstring. After completing drilling, the hole must be filled with lightweight viscous mud to keep it open prior to setting the first casing. These considerations do not arise if mud is used as the drilling fluid.

Setting the First Casing

4.7 The casing string is lowered into the hole from the derrick floor. It is fitted with a float shoe tofacilitate cementation. Normal practice is to cement the annulus between the casing and thehole, and extend the cementation for some distance up the conductor, typically to 30ft or 40ftbelow mudline.

4.8 It is common practice to specify that the cement should not be taken above mudline. Thereasons for this are:

a) the abandonment is easier and the conductor can be recovered and re-used(particularly important for exploration wells)

b) the stress in the conductor at mudline can be determined using simple analyticaltechniques (i.e. there are no thermal or secondary axial effects)

c) also it is preferable that the conductor should not take any vertical load (except itsown weight) above seabed so that its full strength is available for resisting wave andcurrent action.

Typically it is recommended that the cementation of the conductor to casing annulus shouldnot be taken above a level of 40ft below mudline. However some group companies take thecementation to deck level. This has to be accounted for in the conductor design, seeSection 6.

Page 28: PTS (Conductor Design and installation manual for offshore platform)

5. INSTALLATION METHODS

5.1 Although in areas with a long operating experience established practice is usually followed,for new and larger platforms or in new areas the method of installing the conductors shouldbe determined on the basis of a time and cost analysis of various techniques. Importantparameters which influence the viability of different methods are:

the setting depth

the soil conditions

the conductor section

the equipment available

5.2 The most commonly used installation techniques are:

driving (continuous driving)

drill-drive (repeatedly alternating drilling and driving)

drill and drive (single drilling operation followed by continuous driving)

drill and cement (single drilling operation followed by cementation) jetting

Jetting is not recommended as an installation technique for conductors on platforms. This isbecause jetting may adversely affect the integrity of the platform foundations. The other fourmethods are described and discussed below. In addition specifications for driving prepared bySSB are presented in Appendices III-3 and III-4, for drill-drive prepared by Shell Exproin Appendix III-5 and for drill and cement prepared by QPPA in Appendix III-6.

Driving

5.3 The drivability of conductors can be determined using the same analytical Approach as forpiles. The soil properties are used to calculate the soil resistance at the time of driving (SRD).The hammer and conductor dimensions are used as input to a computer program (the waveequation) which can determine whether or not a particular hammer is capable of overcomingthis maximum anticipated SRD. The output of the program also provides the maximum wallstress during driving. Thus it is possible to assess whether or not a conductor can be drivenwith a given hammer to the specified setting depth without damage. On many platforms forwhich driven conductors are used, foundations piles are driven prior to conductor installation.The results of the pile driving can be used to check or amend the drivability analyses of theconductors. This was done by SBPT for the Maui A platform.

5.4 Drivability analyses are described in detail in Appendix III-1. However, a generalappreciation of the effect of various parameters on drivability is required. The SRD generallyincreases with soil strength and depth of penetration. The SRD which can be overcomeincreases with hammer energy and conductor wall thickness.

5.5 Driving is generally a fast installation technique. It results in the least disturbance of thefoundation soils and there is no danger of washout at any level due to conductor installation.

Page 29: PTS (Conductor Design and installation manual for offshore platform)

5.6 There are a number of different approaches to driving to be considered:

(i) drive the conductors as soon as pile driving is complete using the derrick barge andsteam hammers. This method of installing the conductors is extensively used byNAM, SSB, BSP and SOC. It was used initially by SBPT for Maui A. However, it isweather dependent and derrick barges are expensive. Therefore, even for conductorswhich can be driven easily, it may not be the best solution in all operating areas.

(ii) drive the conductors from the drilling floor using the drilling derrick or a "pile" handlingrig. This approach is much less weather dependent than item (i) above but mayrestrict the choice of hammer to diesel or steam hammers driven by air. Thesehammers are usually less powerful than those available from a derrick barge andtherefore drivability may not be so good and installation can take longer.

(iii) stab the lead sections with the derrick barge and drive the conductors from the drillfloor as in (ii) above. This enables the boom height of the derrick barge to beemployed together with the "weather independence" of the jacket. Under nocircumstances should the conductors be driven to refusal with the derrick barge in theexpectation that it will be possible to advance them further with the drilling derrick. Infact, apart from the stabbing operation, it is not recommended to install conductorspartly with the derrick barge and partly with the drilling derrick.

5.7 For conductors which are to be installed by driving it is necessary to connect add-ons bywelding. It may be possible to use a mechanical joint provided its fatigue life can be shown tobe satisfactory. However, there is little Shell Group experience on the use of mechanicalconnectors with conductors on permanent platforms.

Drill-Drive

5.8 At a number of Shell Expro's platforms the setting depths are so great and the soilconditions so hard that it is impossible to drive conductors to the required penetrations. It wasconsidered that "drill and drive" or "drill and cement" techniques might result in anunacceptable amount of washout at seabed level. ( Shell Expro have a number ofGBS's beneath which washout must be avoided.) To solve their conductor installationproblems Shell Expro developed a "drill-drive" technique.

5.9 The drilling derrick is used to handle add-ons, hammers and drilling equipment. A followerwith a modified driving head is used to hang the drillstring inside the conductor during driving.A circulating gravity connector is incorporated in the lead section of the conductor. It isopened during drilling and allows returns to be discharged below decklevel.

5.10 The main characteristic of this method is that the drillstring remains inside the conductorduring driving and does not have to be pulled and re-run at each change from drilling todriving and vice versa. This enables the drilling of short pilot holes ahead of the conductorwithout losing a lot of time. A typical procedure would be:

(a) drive the tip of the conductor from seabed level to the depth at which the first add-onis made.

(b) drill out and form pilot hole to the depth at which the next add-on will be made.(c) drive to the bottom of the pilot hole.(d) repeat until conductor tip approaches setting depth(e) for the last few add-ons drive a sufficient length of conductor without a pilot hole to

generate the required axial capacity of the conductor. This length must be calculated,see Section 6.

Page 30: PTS (Conductor Design and installation manual for offshore platform)

Shell Expro generally use 30in diameter conductors. For cleaning-out the conductorand drilling the pilot hole they use a 17 ½ in. bit with a 26 in. hole opener. The hammer isusually a heavy diesel hammer such as a Delmag D55 or D62A. Seawater is used as drillingfluid with pills of drilling mud being used to clean the hole. Welded connections are used foradd-ons to the conductor.

5.11 An assessment of whether or not the drill-drive technique will be successful at a particular sitecan be made using a modified version of the drivability analyses. The calculation of the SRDmust take into account the effect of cleaning-out the conductor (no inside friction) and pilothole (reduced outside friction and end bearing). The wave equation analysis is the same asfor a driven pile. An example is provided in Appendix III-2.

Drill and Drive

5.12 In the "drill and drive" method a pilot hole is drilled from mudline to the setting depth beforeany attempt is made to drive the conductors below seabed. Open-hole drilling using seawateris employed, i.e. cuttings discharged at seabed level. At Auk, Shell Expro used thefollowing technique for 30 in. conductors with welded add-on connections:

(i) run conductor to a few feet above seabed

(ii) drill a 26" hole and fill with mud to prevent borehole collapse.

(iii) drive the conductor to the bottom of the hole and beyond until sufficient capacity isobtained. This distance must be calculated, see Section 6.

5.13 This technique will result in mudline washout which may affect the lateral analyses. The waveequation can be used to determine driving stresses and it is possible to make approximateestimates of the SRD.However, if the hole exceeds its nominal diameter, such low drivingresistances may result that the conductor runs away under the hammer blows, i.e. suddenlydrops several (or many) feet.

Drill and Cement

5.14 The "drill and cement" technique can be used in most situations although it may prove timeconsuming and expensive. For example QPPA use this method because many of theirplatforms are underlain by soil strata containing bands of rock. Trying to drive through therock is difficult and could damage the tip of the conductor. Also for the calcareous soils foundin QPPA's operating area, the axial capacity of driven conductors may be very much lowerthan drilled and cemented conductors.

5.15 The installation procedure is to drill "open hole"using seawater as the drilling fluid. The holeopener must have a larger diameter than that of the conductor so that an oversize hole isformed. Slugs of viscous mud may be required in certain strata to stabilize and clean the hole.On reaching the required setting depth, the borehole is filled with lightweight mud. Theconductor (fitted with a float shoe) is then lowered into the borehole and the annulus betweenthe borehole wall and the outside surface of the conductor is cemented. A salt water cementmay be used. It is normal to allow for 100% more volume of cement slurry than the nominalvolume of the annulus. Since driving is not required "squnch" joints may be used betweenadd-ons.

Page 31: PTS (Conductor Design and installation manual for offshore platform)

6. AXIAL BEARING CAPACITY OF CONDUCTORS

General

6.1 As a general rule, well casings should not be hung from conductors. In principle, conductorsshould only be required to take lateral forces, not axial forces. The reasons for this are:

(i) depending on the span between supports, the magnitude of environmental forces andman other factors, the strength of the conductor section may be committed to takingbending.

(ii) the axial bearing capacity may be relatively small and difficult to calculate with anydegree of reliability.

(iii) the stress distribution in a series of cemented casing strings is difficult to analyse.There will always be uncertainties as to the magnitude of the load on the conductor,particularly when considering temperature effects.

However, every conductor must be able to support its own weight and that of any equipmentplaced on it, e.g. a diverter, and because of this an estimate must be made of its bearingcapacity.

6.2 If despite the reservations of paragraph 6.1, it is decided to support well casings and otherequipment on the conductor, then the system must be very carefully engineered. It can neverbe assumed that the conductor can take a load simply because it has a deep penetrationbelow seabed.

Safety factor

6.3 The ultimate axial capacity of a conductor must be at least twice the sum of its self weight andthat of any equipment or casings it supports. The methods of calculating the capacity varywith the installation technique and are described in paragraphs 6.10 to 6.17.

The Conductor as a Pile

6.4 Offshore steel platforms are generally supported on foundations made up of open ended pipepiles. This type of pile develops its capacity by mobilising end bearing at the tip and frictionbetween the shaft and the soil. In some cases, the end bearing is limited by the friction whichcan be developed between the soil plug and the inside of the pile.

6.5 Superficially a conductor is similar to a pipe pile. However, to install casings the soil pluginside the conductor must be drilled out and there can be no end bearing component. Thusthe bearing capacity of a conductor is developed only by friction between its outside surfaceand the soil.

6.6 In most situations the bearing capacity of a pile increases with time to some maximum value.The foundations of a jacket do not usually have to carry their design load until several months(or years) after they have been installed. These two factors are taken into account, to someextent, in the pile design methods used for offshore piles. On some platforms the sameconsiderations will apply to the conductors but on others the conductors may have to carrytheir maximum loads a few weeks (or days) after they have been installed. This must bereflected in a slightly more conservative approach to conductor design.

Page 32: PTS (Conductor Design and installation manual for offshore platform)

6.7 An indication of the capacity of a driven pile may be obtained from its driving records.Frequently, piles are driven to refusal in a sand layer to develop as much end bearing aspossible and "refusal" with a specified hammer is used as an acceptance criterion. However,the situation with driven conductors is completely different. Because the end bearing isremoved during spudding-in, see paragraph 6.5, refusal cannot be used as an indication ofthe capacity of a conductor.

6.8 The fact that "refusal" is not an acceptance criterion for conductors does not mean that drivingbehaviour may be ignored. In fact for conductors installed by the drill-drive or drill-and-drivetechniques the driving record may provide the only reliable data by which to estimatecapacity. This is because the pilot hole is of a similar diameter to that of the conductor,typically a 26in. nominal hole diameter for a 30in. O.D. conductor. Washout and other factorsmay result in a hole which is larger than its nominal value. Locally the size of the hole mayexceed that of the conductor. Under these circumstances, the normal techniques of predictingoutside skin friction from the results of soil testing are inapplicable. However, with there beinglittle or no end bearing and no inside frictional resistance to driving, the SRD is generated onlyby outside friction. Thus by backfiguring the SRD versus depth relationship from theblowcount records, an estimate may be made of the bearing capacity of the conductor. Thisinvolves equating that part of the SRD which is clearly attributable to the outside soilresistance to the bearing capacity.

6.9 The estimation of the bearing capacity of conductors may be further complicated by therelatively small centre to centre spacings between conductors, typically 7ft 6in. andsometimes 5 ft. The capacity of a conductor could be reduced by installation of subsequentadjacent conductors, see paragraphs 3.11 to 3.19, particularly if drilling is involved.

Conductors Installed by Driving

6.10 For conductors installed by driving only, the ultimate axial capacity may be computed by themethod recommended in API RP2A (Ref. 6.1) for piled foundations. These are summarised inAppendix IV-1 which also contains an example calculation. The ultimate capacity is calculatedon the basis that skin friction acts over the outside surface of the conductor except wherethere is scour at mudline or washout at the tip.

6.11 The allowance for scour will vary with the soil conditions at mudline, the waterdepth, current,environmental conditions etc. In most cases it will have little if any effect on capacity. In theabsence of reliable data it is recommended that at least 3ft (1m) of scour is assumed. If thereis sand at seabed level the scour depth should be at least 1.5 times the conductor diameter.

6.12 If the conductor is set in a sand or silt stratum the possibility of washout occurring duringdrilling for the first casing must be considered. This could result in the soil immediately abovethe tip being loosened or collapsing. To account for this it should be assumed in thecalculations that no friction is developed over the bottom 10 ft (3m) length of the conductor.This allowance for washout need not be made for conductors with their tips in clay.

Page 33: PTS (Conductor Design and installation manual for offshore platform)

Conductors Installed the "Drill-Drive" technique

6.13 The capacity of conductors installed by the "drill-drive" technique is difficult to predict becauseof the uncertainties regarding the skin friction which can be developed in soil through which apilot hole has been drilled. The friction will be a function of hole size, conductor size, drillingpractice and soil type but there is insufficient data to provide guide-lines. Shell Exprohave used their experience to draw-up a detailed installation specification which they strictlyenforce by providing tight supervision. The capacity can be assessed in two ways. First bybackfiguring an SRD from the blowcount record and equating this to the capacity. Secondlyby assuming that outside friction is developed only over a length near mudline and a lengthnear the tip where pilot holes were not used. An example calculation is provided inAppendix IV-1.

Conductors Installed by the "Drill and Drive" technique

6.14 The same considerations apply to the capacity of a conductor installed by the "drill and drive"technique as for the "drill-drive" conductor of paragraph 6.13.

Conductors Installed by the "Drill and Cement" technique

6.15 The "drill and cement" technique is described in paragraphs 5.14 to 5.16. There are twoconstraints on the capacity of such conductors; the limiting bond stress between grout andsteel and the skin friction at the grout/soil interface. The first is referred to the outside surfaceof the conductor, the second to the nominal diameter of the hole. To avoid confusion and thepossibility of error it is recommended that the limiting bond stress be converted to anequivalent limiting friction at the grout/soil interface, thus

gg Tdf σ•= 6.1

where

fg = equivalent limiting skin friction

d = outside diameter of conductor

T = nominal hole diameter

gσ = limiting bond stress

If no other data are available it is common practice to assume a limiting bond stress betweenthe grout and steel of 185 kN/m 2 (3.9 ksf, 27 psi). This assumes that the hole has beendrilled with mud or with water and subsequently filled with mud. Higher values might apply ifwater alone were to be used. The quality control on site must ensure that the cement grout isbatched, mixed and placed in accordance with the specification (Refs. 6.2 and 6.3).

6.16 The ultimate unit skin friction between the grout and the soil may be computed using amodification of the method described in API for driven piles (Ref. 6.1). For sands and normallyconsolidated clays the API recommendations are unchanged. However, for heavily overconsolidated clays the skin friction factor (α) should be taken as 0.4 rather than 0.5, i.e. theultimate unit skin friction (fs) in a hard clay stratum would be 0.4 multiplied by the undrainedshear strength.

Page 34: PTS (Conductor Design and installation manual for offshore platform)

6.17 To determine the ultimate axial capacity of a "drilled and cemented" conductor, the ultimateunit skin friction of the soil (fs ) in each layer is computed. In strata in which fs exceeds fg, thevalue of fg applies. The remainder of the computations follow the standard procedures and anexample calculation is provided in Appendix IV-2.

Computing the Axial Load on the Conductor

6.18 The axial load depends upon a number of factors some of which are difficult to determine andmust be simplified (or ignored) in order to make the analysis possible. They are:

(a) the weight of the casings

(b) the precise details of the installation sequence of well casings

(c) the densities of the drilling fluid and the cement for the first casing string

(d) the degree of deviation of the well

(e) temperature gradient

(f) the level of cementation in annulus between first casing and the conductor.

(g) rig tensioning and overpull

(h) the mechanical properties of the grout

The complexity of the situation is one reason why some Group companies avoidcarrying axial forces on the conductors and do not cement above seabed, eg. ShellExpro. Other Group Companies use arbitrary rules which, experience has shown,provide reasonable guidance in a particular operating area, eg. SSB require the ultimatecapacity of a conductor to be at least twice the sum of the weights of the BOP stack plus2000ft of 20in. casing plus the conductor self weight. QPPA specify that 200ft penetration isrequired for axial capacity. Such rules cannot be exported from one operating area to another,they are only valid locally.

6.19 Consider a conductor from which it is proposed to hang a well casing. The casing is placedinside a deviated hole full of drilling mud. The annulus between the hole and the casing iscemented through a float shoe, mud remaining inside the casing. The casing support is thentransferred to the conductor, see Fig.6.1 What is the axial force acting on the conductor dueto this casing? Should the curved length or the resolved vertical length be considered? Howcan buoyancy effects between mud and grout be included in the computation? Buoyancyshould be included and the curved length of the casing considered. Thus the axial force at thetop of the conductor is

Page 35: PTS (Conductor Design and installation manual for offshore platform)

References

6.1 AMERICAN PETROLEUM INSTITUTE, "Recommended practice for planning, designing andconstructing fixed offshore platforms", API RP2A 1979.

6.2 REESE, L.C. and COX, W.R., "Pullout tests of grouted piles in stiff clay", OffshoreTechnology Conference 1976, Paper OTC 2473.

6.3 EHLERS, C.J. and ULRICH, E.J., "Design criteria for grouted piles in sand", OffshoreTechnology Conference 1977, Paper OTC 2941.

Page 36: PTS (Conductor Design and installation manual for offshore platform)

Figure 6.1

Page 37: PTS (Conductor Design and installation manual for offshore platform)

7. SELECTION OF INSTALLATION METHOD

7.1 The selection of the most appropriate installation procedure for the conductors on a particularplatform is not always a simple matter. There is a temptation to adopt the method which wasused on previous platforms in the operating area concerned. On many occasions this is thecorrect choice. However, changes in platform type, setting depth, soil conditions, casingprogramme, conductor size, equipment availability and technology will affect the economicand technical viability of a given procedure vis-a-vis the others available. It is recommendedthat for each new project the conductor installation procedure is selected on the basis of anengineering judgement and not necessarily on precedent.

7.2 Descriptions of the various methods currently used within Shell Group companies toinstall conductors are provided in Section 5. The methods are:

driving drill-drive

drill-and-drive drill-and-cement

jetting (not recommended)

The purpose of this Section of the Manual is to provide guidance in assessing the suitability ofeach of the above against the others.

7.3 The overriding consideration must be the safety of the platform. The first step in the selectionprocedure is to rule out any conductor installation method which might lower the safety factorsof the foundations or reduce the integrity of the well to below acceptable levels. The next-stage is to assess which of the remaining installation methods are likely to be successful. If atheoretical analysis shows that a particular technique will not achieve the required settingdepth then it must be modified or rejected. Finally, a time and cost study should be made ofthose methods which are both safe and feasible. A rational selection based on therequirements of the field development programme may then be made. This was done by BSPin 1972 and their study forms Appendix V-1 of this Manual.

7.4 It is understood that Shell Expro developed the drill-drive technique as a result of aselection procedure similar to that described above. For some of their GBS platforms in theNorth Sea, Shell Expro required conductor setting depths of over 350ft below seabottom. The foundation soils are sands and hard clays. For a GBS an important safetyconsideration is that the base should not be undermined by washout of the seabed soils. Thisruled out "drill-and-drive" and "drill- and-cement" techniques. Wave equation analyses andfield experience showed that conductors could not be driven through these soils to the depthrequired. The driving method was therefore modified, by a number of standard proceduressuch as soil plug removal and pilot hole drilling, to produce the basic drill-drive technique. Therefinement, which reduces the time and cost considerably, is that the drillstring remains withinthe conductor during driving.

Page 38: PTS (Conductor Design and installation manual for offshore platform)

Assessing Driving for Safety

7.5 Provided that there is no danger of the conductors running into the piles, see paragraphs 3.12to 3.20, conductors installed by driving are unlikely to have an adverse effect on the safety ofthe platform foundations. With respect to damage to the conductor itself it must be checkedthat driving stresses do not exceed permissible values using wave equation techniques, seeAppendix III-1. If it is possible that a ledge of rock or coral will be encountered specialprecautions may have to be taken to prevent damage to the conductor tip, see paragraph 9.5.it is recommended that add-ons be connected using welded joints. There is little groupexperience of mechanical connections on driven conductors. The add-on length may belimited by the maximum permissible stick-up height, which is governed by allowable steelstress criteria. The method for calculating maximum stick-up height is identical to that for pilesand is described in Appendix V-2. Stick-up height is the distance from the last point ofrestraint to the top of the conductor.

Assessing Driving for Feasibility

7.6 Determine whether or not the conductors can be driven to the specified setting depth using:-

(i) the hammers available on the derrick barge, usually steam hammers.

(ii) the hammers which can be handled from the drilling derrick, usually diesel or smallsteam hammers operated by compressed air.

The method of computation used to assess drivability is described in Appendix III-1. Should itappear that the conductors would refuse before the setting depth is reached, assess whethersoil plug removal would enable them to be driven to grade.

7.7 If the specified conductor cannot be driven, investigate whether it is possible to, increase thewall thickness. This possibility will be constrained by internal clearance, structural,manufacturing and handling considerations. Wave equation analyses must be repeated forevery conductor make- up considered.

Assessing Drill-Drive for Safety

7.8 The spacing between each pile and the nearest conductor should be at least thatrecommended in paragraphs 3.8 to 3.16. This may be quite significant for piles which obtain alarge proportion of their capacity from end bearing in sand. All the comments of paragraph 7.5again apply.

Assessing Drill-Drive for Feasibility

7.9 Using the conductor make-up determine whether or not the conductors can be installed to therequired setting depth using the drill-drive technique. The methods of analyses are describedin Appendix III-2. Remember that the hammers will have to be handled by the drilling derrick.Check that the axial capacity requirements are satisfied. Also ensure that the technology isavailable in the particular operating area. If not consult SIPM to see if it can beintroduced in the time available. Should there be a problem of drivability investigate whetherthe wall thickness can be increased as in paragraph 7.7.

Page 39: PTS (Conductor Design and installation manual for offshore platform)

Assessing Drill-and-Drive

7.10 The safety aspects of the drill-and-drive method are the same as in paragraphs 7.5 and 7.8.However, there is an additional aspect in that erosion and washout of surface soils ispossible. This may have an adverse affect on some types of foundation. The analyticalprocedures for assessing feasibility are the same as in paragraph 7.9. In general the drill-drive technique is to be preferred if the technology is available.

Assessing Drill-and-Cement

7.11 With the drill-and-cement technique there is little danger of damaging the conductorsthemselves and mechanical connections may be used. The principle safety considerationsinvolve the effect the technique may have on the surrounding soil and the platformfoundations. The spacing between the piles and conductors must be checked against therecommendations of paragraphs 3.12 to 3.20. Surface washout may be a problem.Installation should be feasible provided hydraulic fracture of formations with either drilling fluidor cement can be avoided. The method of computation to check this is described in Section 3.

7.12 For a number of recent field development projects wells have been drilled through a seabedtemplate before a jacket was placed. For such cases a 30" conductor is also set, although itdoes not extend above the template. In these circumstances the conductors are usuallyinstalled by the drill-and-cement technique from a jack-up or semi submersible rig. Thecementation procedures must be designed so that grout losses into the soil strata areminimised. This means that formation fracture by the grout pressures must be avoided. Thisis because the presence of grout in the soil, particularly for sand layers, may makesubsequent pile driving much more difficult than anticipated. Also formation fracture mayaffect the bearing capacity of the piles supporting the template.

Current Practice

7.13 From time to time most Group Companies have carried out analyses such as thosedescribed above. These studies have resulted in a variety of techniques being adopted andthe current practice of some Companies together with relevant parameters are listed below.

Page 40: PTS (Conductor Design and installation manual for offshore platform)
Page 41: PTS (Conductor Design and installation manual for offshore platform)

8. RECORDING THE INSTALLATION AND INSTRUMENTATION

Why Installation Records are Essential

8.1 Over a period of many years, a large number of wells may be installed in any one part icularfield or concession. It is important that data obtained from previous conductors are consideredwhen selecting the techniques to be used in the future. Due to personnel movementsbetween OPCOS it is essential to initiate recording procedures to permit continuity. Withoutsuch records it is possible that the same difficulties with conductor installation will arise timeafter time.

8.2 There are a number of reasons, other than continuity, for making conductor installationrecords. They are:

(a) to ensure that the conductors fulfil all aspects of the specification.

(b) the taking and checking of records is a Quality Assurance procedure.

(c) if conductor installation does not proceed as planned, the records can be used todetermine what has gone wrong and to design appropriate remedial measures.

(d) records will provide a data base for improving methods of conductor installation.

Normal practice is to oblige the contractor to take the records. The Shellrepresentative is responsible for checking and approving them.

Current Practice

8.3 Most Group Companies prepare, as a matter of routine, installation records for drivenconductors. These are virtually identical to pile driving records and consist of a plot ofblowcount versus depth, annotated where necessary. An example of such a record preparedby SBPT is shown on Fig. 8.1. A similar record processed by computer for BSP is given onFig. 8.2. A form, suitable for compiling this data offshore, is included in Appendix V-3 togetherwith a completed example by SBPT.

8.4 Shell Expro have developed a standard presentation for conductors installed by thedrill-drive technique. This is shown on Fig. 8.3.

8.5 Records are not generally kept for conductors installed by the drill-and-cement technique.This is probably because the specification can be followed precisely on most occasions.However, the lack of records makes realistic economic comparisons with other methodsdifficult. It is recommended that a format for such records be developed.

Page 42: PTS (Conductor Design and installation manual for offshore platform)

Instrumentation

8.6 Hammer performance can be monitored by instrumentation, and instrumentation provides theonly method of assessing the efficiency of a diesel hammer. Both Shell Expro andSOC have suspected that conductors have refused prematurely because of poor dieselhammer performance, but without instrumentation have not had data to substantiate theirviews. For steam hammers, a qualitative assessment of efficiency may be obtained byobserving the free fall. However, if a reliable estimate of efficiency is required instrumentationmust be employed.

8.7 SBPT used strain gauges and accelerometers on a conductor on Maui A to monitor theperformance of a diesel hammer. The theory and practice of such measurements for bothpiles and conductors is described in Appendix V-4.

General Quality Control

8.8 Consideration should be given to setting up a Quality Assurance Procedure for both welding(NDT) and cementation. These are outside the scope of this Manual but the ConstructionDepartment or EP 23.4 can provide advice.

Page 43: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 8.1

Page 44: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 8.2

Page 45: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 8.3

Page 46: PTS (Conductor Design and installation manual for offshore platform)

9. CONDUCTOR SHOES

9.1 It is common practice for there to be an internal driving shoe at the toe of a conductor.Generally, such shoes increase the wall thickness at the toe to 1 .5 times the nominal wallthickness, eg. the shoe of a 26"dia. x 0.5" wt conductor would increase the wall thickness atthe toe to 0.75". It is essential that the dimensions of the shoe allow the drilling bits to passwith adequate clearance. Also the transition from the nominal conductor wall thickness to theshoe should be gradual both to allow easy passage of tools and casings, and to reduce stressconcentrations during driving. Although conductor shoes are widely used, they are notobligatory and in some circumstances serve no useful purpose. External conductor shoes, i.e.those which increase the outside diameter of the conductor, should be avoided. This isbecause they may reduce the bearing capacity of a conductor and, if a weak path is formedup the outside of the conductor, they may reduce well security.

9.2 The reasons for using conductor shoes are:

(a) to make driving easier by reducing the friction between the conductor and the soilplug inside it (see paragraph 9.3)

(b) to reduce the probability of damage at the end of the conductor when driving throughhard strata (see paragraph 9.5)

(c) to cause the conductor to deviate in a preferred direction during driving, a specialconfiguration being required to do this (see paragraph 9.6).

From the above it is apparent that the use of a shoe only benefits driven conductors. Becausethere are some disadvantages associated with driving shoes (such as an increased risk ofdrilling tools or casing strings standing up or snagging on the reduced pipe diameter) theyshould not be used unnecessarily. For example, it would be pointless to use a driving shoe ona conductor which is to be installed by the drill-and-cement technique (a float shoe is howeverrequired for annulus cementation).

Improving Drivability

9.3 An internal driving shoe is a relatively cheap and simple method of improving drivability. It ismost effective in hard clays where it may reduce the internal skin friction during driving bybetween 30% and 50%. In sands and normally consolidated clays, experience to dateindicates that a shoe has only a slight effect on drivability.

9.4 If a further improvement in drivability is required, it may be advisable to dispense with thedriving shoe altogether and increase the wall thickness of the whole conductor to themaximum possible compatible with bit clearance. This has been done by SSB and SOC whouse 26" dia. x 0.75" wt pipe without a shoe for curved conductors. The equivalent straightconductor with a shoe is described in paragraph 9.1.

Reducing the Possibility of Damage to the Conductor Tip

9.5 The increased wall thickness of the shoe should reduce driving stresses at the conductor tipand this may prevent distortion if a local hard spot is met, eg. a cobble. However, the changeof section at the top of the shoe may result in stress concentrations and stress wavereflections during driving. A shoe will not reduce overall driving stresses in the remainder ofthe conductor and may increase them in that portion of the conductor immediately above theshoe. The provision of a shoe should not be regarded by itself as sufficient protection against

Page 47: PTS (Conductor Design and installation manual for offshore platform)

damage. If it is expected that the conductors will have to be driven through a hard layer, suchas a ledge of rock or coral, a detailed study must be made of the implications using waveequation techniques. The results of the study should include; predictions of driving stresses;limits on the blowcount; recommendations regarding wall thickness and drilling out. Acommon practice is to drill ahead once the limiting blowcount has been reached.

Directional Control

9.6 Shell Expro have developed a conductor shoe which, in conjunction with their drill-drive technique, is expected to cause a conductor to deviate from the vertical during driving.The intention is to increase the spacing between conductors at tip level and to have theconductors aligned in preferred directions. A schematic drawing of the Shell Exproshoe is provided on Fig. 9.1 A proprietary systems is also available (Ref.9.1) but as far as isknown there is no group experience of its use.

9.7 The Shell Expro shoe has been used on a number of projects in the North Sea. Theresults of directional surveys (Sperry Sun) to confirm that the technique works were awaitedat the time of writing this manual.

9.8 Other methods of increasing the spacing of conductor tips are described in Section 10.

Clearances

9.9 To allow the bit and drillstring to pass through the conductor it is normal practice to have theminimum conductor internal diameter at least one inch greater than the maximum bit size.This involves interaction between the drilling and structural aspects of conductor design. Theminimum conductor i.d. usually occurs at the shoe. If stabbing points are used it should bechecked that this i.d. is not reduced. However even with these clearances, NAM have hadoccasional problems with the drill string snagging on the shoe when it is being withdrawn. Tofacilitate retrieval of drilling equipment NAM now use an internal bevel on their shoes.

Length of Shoe

9.10 For shoes which are fitted solely to improve drivability, lengths of approximately 1.5 times theconductor diameter have proved satisfactory. If the shoe is required to prevent damage to thetip, the wave equation analyses mentioned in paragraph 9.5 should allow the optimum lengthsto be determined. It will probably be in excess of 1.5 times the conductor diameter. As a firsttrial 3 times the diameter may be considered.

References

9.1 SIMPSON, J.K., "Drive shoe controls conductor pipe", Oil and Gas Journal, Sept 10, 1979.

Page 48: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 9.1

Page 49: PTS (Conductor Design and installation manual for offshore platform)

10. CURVED CONDUCTORS

10.1 If it is proposed to use curved conductors it is normal practice to install the lead sectionsthrough the guides prior to float-out. The uppermost guides are usually vertical, the remainderfollowing the specified conductor curvature. The lead section is fabricated to the samealignment as the guides. Straight add-ons may be used for the remainder of the conductorlength. This means that straight sections of conductor may eventually be driven throughcurved guides resulting in the guides being subjected to static and dynamic lateral forces. Ifcurved add-ons are used a straight follower should be used for driving. A brief note on the useof curved conductors in the Gulf of Mexico, prepared by Shell Oil, is presented inAppendix V-5.

Reasons for using Curved Conductors

10.2 The principal advantages of using curved rather than straight conductors are:

(a) they allow increased coverage of the reservoir from one platform.

(b) the centre to centre spacings at the conductor tips are greater than at deck level. Thisreduces the possibility of one casing running into another

Disadvantages of Curved Conductors

10.3 There are several disadvantages associated with the use of curved conductors. These are:

(a) the detailed design and fabrication of the jacket is more complicated and strongerconductor guides are required to resist the additional lateral forces

(b) the decision to use curved conductors must be taken at the start of jacket design. Ifreservoir maps are revised prior to installation, the conductors may be orientated inthe wrong direction

(c) it leads to greater casing wear.

Limitations on Curvature

10.4 Conductor curvature is usually expressed in degrees per 100ft, the angle being thatsubtended by a 100ft arc at the centre of its circle. The curvature is limited by:

casing and well head wear

casing joint design

fatigue of the drillstring

strain in outer fibres of the conductor

10.5 All Group Companies which have had experience of installing curved conductors agreethat curvature should not exceed 7º per 100ft. Most specify smaller values. SOC restrictcurvature to 6º per 100ft because at higher values there is a danger of overstressing thethreaded connections of the casing strings. Similarly SSB set a limit of 5 º per 100 ft. BSPhave found it difficult to run a 20in. dia. casing through a 26" dia. x 0.75in. wt conductor if thecurvature exceeds 5° per 100ft. However by substituting a 185/8in. casing for the 20in. theyhave been able to run casings through 7 º per 100ft.

Page 50: PTS (Conductor Design and installation manual for offshore platform)

10.6 Conductors may wander and the results of Sperry Sun surveys indicate that the curvature inthe soil may be 2 º less than expected, (see minutes of meetings with SOC, SSB and BSP).

Drivability

10.7 A wave equation program suitable for analysing the driving of curved conductors has beendeveloped by SOC and is available through SIPM . In addition to providing data ondrivability it predicts the forces induced in the conductor guides by driving. A description of theprogram and an input guide is provided in EP 42513 "Driving Analysis for Initially CurvedMarine Conductors". However, this may be difficult to follow for a new user and for this reasona Fugro Report to Shell Expro which comments on its use forms Appendix V-6 of thismanual.

10.8 It is the practice of SOC, SSB and BSP to use the maximum possible wall thickness forcurved conductors, ie. they use 26in. dia x 0.75in. wt for curved conductors and 26in. dia x0.5in. wt for straight conductors. This means there is no shoe on their curved conductors.With this increased wall thickness SOC report that they are just as easy to drive as straightconductors.

10.9 Shell Expro are proposing to use curved conductors on their North Cormorant jacket.The conductors will be installed using the drill-drive technique. A theoretical analysis indicatesthat pilot holes may have to be shorter than for straight conductors, but that overall drivingshould be no more difficult than for straight conductors.

Alternatives

10.10 The advantages of curved conductors may be obtained, but to a lesser degree, by usingslanted or mitred conductors. A mitred conductor is in essence a curved conductor fabricatedfrom a series of straight sections, the joint between each section being made at a small angle.Slanted conductors are straight conductors driven at a batter.

Page 51: PTS (Conductor Design and installation manual for offshore platform)

11. CONTINGENCY PROCEDURES FOR CONDUCTORS WHICH DO NOT REACH SETTINGDEPTH

11.1 If a conductor fails to reach its setting depth the methods proposed for spudding-in andinstalling the first casing string may have to be revised. Generally the drillers have a numberof contingency procedures available to them, some of which may affect the structural integrityof the conductor. It is therefore essential that the drillers and designers jointly agree anycontingency procedures.

Conductors not Satisfying Axial Capacity Requirements

11.2 On some projects SOC design conductors to carry the weight of the casing string. If thespecified setting depth is not reached and the conductor has inadequate "bearing capacity"SOC would either:

(a) vary the well design so that internal casings can be carried on the first casing string or

(b) cement the annulus between the conductor and first casing string up to the well headand use the conductor plus casing string as a composite pile.

As described in paragraph 6.1 (iii) the analyses required to justify the latter are complex andsecondary effects become important. For this and other reasons SIPM recommendthat conductors should not be required to carry axial loads.

Conductors not Satisfying Formation Fracture Requirements

11.3 If the setting-depth is insufficient to allow returns at the drill floor when drilling for the firstcasing the following contingency procedures may be considered:

a) reduce the drilling rate but maintain the circulation rate, this should reduce the densityof returns

(b) aerate the drilling mud or use oil in the drilling fluid again to reduce density. Theremay be environmental restrictions in some operating areas which prevent the use ofoil

(c) install a centrifugal pump near sea level to enable cuttings to be lifted to the shaleshaker

(d) use LCM (lost circulation material).

11.4 In many cases the contingency procedures described in paragraph 11.3 are either notsuitable for a particular project or do not restore circulation. Under these circumstances acommonly used procedure is to cut slots in the conductor at a few feet above sea level anddischarge the returns into the sea. When using this technique attention should be paid to theremaining structural strength of the conductor. Also environmental and/or economicconsiderations may require that seawater is used as the drilling fluid. Most GroupCompanies have experience of this technique, (see minutes of meetings).

11.5 If the procedures described above fail to restore circulation and/or remove the cuttings it isthe practice of some Companies to use "blind" drilling, (see minutes of meetings with SOC).However for the reasons given in paragraph 3.1 this is not generally recommended.

Page 52: PTS (Conductor Design and installation manual for offshore platform)

Other Contingency Measures

11.6 SSB have reported that if a conductor has refused prematurely during driving from a derrickbarge, they subsequently try to pull the conductor out with the drilling derrick and reinstall itusing a drill-drive or drill-and- drive technique. However, on no account should this procedurebe relied upon as a "cure-all" for conductor installation. On many occasions the drilling derrickmay have insufficient capacity to pull the conductor. For further comments on this matter seeminutes of meeting with NAM and paragraph 5.6.

12. DO'S AND DON'T'S

12.1 This Section is a summary of the discussions which were held with the Group Companies,and the contents of the Manual itself. Its purpose is to briefly highlight accepted good practiceand assist the reader in avoiding the mistakes of others.

Do's

12.2 The majority of the points listed below may appear obvious. However, pressures on time andcost have caused them to be omitted on some projects, occasionally with seriousconsequences. Do:

1. have a soil investigation made at the location of the platform.

2. ensure that there is sufficient clearance inside the conductor for the drilling bit to passfreely ,up and down. This is particularly important if there are any local reductions indiameter due to shoes, stabbing points etc.

3. calculate a setting depth of the conductor which is compatible with the drilling andcasing programme and the soil conditions.

4. have a drivability study performed if driving is part of the installation procedure.

5. specify a minimum acceptable blowcount at final setting depth if bearing capacity is tobe assessed on the basis of driving records.

6. check that there is adequate spacing between the foundation piles and theconductors.

7. specify the procedures to be followed if the blowcount suddenly rises and quantifythis blowcount. This is particularly important if the soil borings indicate that layers ofrock may be encountered during conductor driving and should avoid damage to theconductor tip.

8. design the shoe to suit the method of installation and soil conditions.

9. consider what contingency procedures should be taken if the conductors do not reachthe specified setting depth.

10. specify any spare or back-up equipment which should be available offshore.

11. make sure a responsible person who is conversant with the platform design and theconductor design is either offshore or available for consultation on a 7 day week, 24hour basis during installation.

12. ensure that the add-on lengths are within the capacity of the handling equipment andthat at maximum stick-up height the conductors are not overstressed. Also specify thelengths of any cut-off.

Page 53: PTS (Conductor Design and installation manual for offshore platform)

13. put all of the above in an installation specification, take records (at least sufficient tocheck the contractor's records) and incorporate them in an "as- built" report.

Don't's

12.3 A list of things not to do obviously includes the opposites of many of the items in paragraph.In addition to these,

1. do not economise on materials, e.g. wall thicknesses, to such an extent that theconductors are difficult to install.

2. unless there are overriding reasons to the contrary do not plan to

(a) support casing strings on the conductor

(b) use blind drilling techniques

c) cement the annulus between the conductor and first casing string abovemudline

3 . do not use square shoulders on the inside of the conductor. These may snag thedrillstring or casing string and may cause stress concentrations.

4. do not use mechanical connectors for driven conductors unless there is satisfactoryevidence of their field performance.

5. do not abdicate all control responsibility to the installation contractor.

6. do not assume that the installation will go exactly as planned.

Page 54: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX 1

RECORDS OF MEETINGS WITH PERSONNEL OF VARIOUS SHELL GROUP COMPANIES

Page 55: PTS (Conductor Design and installation manual for offshore platform)

Discussions on the content notes of this Manual were held with a number of Shell GroupCompanies. The range of topics covered at each meeting varied from company to company.Frequently the agenda was influenced by the outcome of previous meetings and the particularinstallation problems in the operating area concerned. In this Appendix the meeting records arepresented in chronological order;

Company Date

SIPM 12 October 1978

SBPT 15, 16 and 22 November 1978

Shell Expro 16 November 1978

NAM 29 November 1978

QPPA 5 and 6 December 1978

BSP 11 to 14 December 1978

SSB 14 and 15 December 1978

SOC (Houston) 22 and 24 January 1979

SOC (New Orleans) 23 January 1979

It should be noted that, except for the meetings with BSP, the records have been compiled by thewriter without reference of the other attendees at the meetings. They are not intended to be officialminutes of meetings and should be regarded as the informal notes of the writer alone. On somesubjects contradictory viewpoints were expressed by different companies. No attempt was made inthe meetings to reconcile such differences in the belief that this could best be done in the Manualitself.

The original Content Notes were based on a concept of a Manual of twelve Sections, the samenumber as in this final version. However the original Section 12 "Case Histories" has been absorbedinto Sections 5 and 7. The Section "Do's and Don't's" was not in the original concept. Otherwise thereis general agreement between the Sections in this Manual and the Content Notes.

Page 56: PTS (Conductor Design and installation manual for offshore platform)
Page 57: PTS (Conductor Design and installation manual for offshore platform)
Page 58: PTS (Conductor Design and installation manual for offshore platform)
Page 59: PTS (Conductor Design and installation manual for offshore platform)
Page 60: PTS (Conductor Design and installation manual for offshore platform)
Page 61: PTS (Conductor Design and installation manual for offshore platform)
Page 62: PTS (Conductor Design and installation manual for offshore platform)
Page 63: PTS (Conductor Design and installation manual for offshore platform)
Page 64: PTS (Conductor Design and installation manual for offshore platform)
Page 65: PTS (Conductor Design and installation manual for offshore platform)
Page 66: PTS (Conductor Design and installation manual for offshore platform)
Page 67: PTS (Conductor Design and installation manual for offshore platform)
Page 68: PTS (Conductor Design and installation manual for offshore platform)
Page 69: PTS (Conductor Design and installation manual for offshore platform)
Page 70: PTS (Conductor Design and installation manual for offshore platform)

SESSION 1

E. Toolan Fugro Ltd.

M. Brinded EPE/4

M. Langereis OPE/1

C. Shepherd OPE/15

G. Bayer ECC/22

J. Caminada EDA/23

J. Dawson EDA/22 (Reporter)

This was a generalised discussion to cover the purpose, style, scope and format of the Manuals.

A. GENERAL POINTS

1) The questionnaire, mentioned in the S.I.P.M. notes on the project, had not in fact beensent to operating companies, as S.I.P.M. and Fugro agreed that mare useful informationwould be obtained from visits to the operating companies.

2 B.S.P. would like to receive the manuals in their Final Draft form, to permit scrutiny andcomment prior to publication by S.I.P.M. and Fugro. A time limit would be imposed forsubmission of comments. (say 1 month)

Mr. Toolan would raise this point with S.I.P.M., and B.S.P. should do so independently.

(Action: EDA/22)

3) Updating of Manuals. B.S.P. would like to see the Manuals updated at specific intervals toincorporate new experience by operating companies, new developments in equipment andtechniques, and changes in design and installation criteria.

Mr. Toolan agreed that the layout of the Manuals would be designed for ease of revision.

B.S.P. would propose to S.I.P.M. that a provision for regular updating be incorporated into theFugro/ S.I.P.M. contract.

(Action: EDA/22)

B. PURPOSE

4) Mr. Toolan stated that in his brief these Manuals were intended primarily to cover installationcriteria for conductors and piles. They were for presentation of recommended procedures.

5) B.S.P. stressed that in their view an important function of the Conductor Manual would be toitemise and specify the design considerations for the structural, operational, and drillingdepartments.

6. An additional purpose was to identify areas, in which data gathering would be required.

Page 71: PTS (Conductor Design and installation manual for offshore platform)

C. STYLE

7. The style proposed for the Manuals was generally agreed, with the proviso that all formulasused should be derived or referenced, with constants and parameters specified.

In each section, basic principles would be highlighted, with references where subjects werenot covered in detail.

D. SCOPE

8. There was a request from B.S.P. for greater emphasis, in the pile Manual, on design methodsand parameters.

9. Mr. Toolan stated that to expand the manuals to include all aspects of design would makethem very large and somewhat clumsy.

NOTE: In subsequent discussions, certain topics were pinpointed for coverage of designfactors in greater depth in the manuals.

10. A section will be included on Freestanding and guyed conductors, mudline suspension wells,and tie-ins to jackets.

11. The main points of interest from Operational Viewpoints were emphasised to be formationstrength, conductor setting depths, and casing cementing setting levels.

Mr. Toolan was able immediately to provide information on calculation methods to determinethe correct conductor setting depth for avoidance of formation fracture.

More detailed discussions on Conductor criteria are covered in subsequent notes.

E. FORMAT

12. As stated in the notes on the manuals, the main part of the Manuals will be sections coveringbasic principles in general terms, with detailed specific information contained in appendices.

13. Where sections will cover installation procedures, examples will be quoted wherever possibleof operating Companies who use these procedures. Examples of Good Practice and BadPractice will be included, as well as alternative methods.

Page 72: PTS (Conductor Design and installation manual for offshore platform)

SESSION 3

M. Langereis OPE/1

A. Schouten OPE/13

C. Shepherd OPE/15

M. Brinded EPE/4

J. Caminada EDA/23

J. Dawson EDA/22 (Reporter)

This session concentrated on the Drilling/operational criteria for conductor Specifications.

Drilling Department have found from experiences over the past few years that the old conductorinstallation criteria dating from about 1972 have not been completely satisfactory and have suggestedthat those procedures should be revised.

The following points summarise the main areas of concern among Drilling, Operational andEngineering Departments of B.S.P., for inclusion into the Conductor Installation Manual beingcompiled by Fugro.

1. A general point was made that criteria governing free- standing conductors should beincluded - with references.

SECTION 3 - Conductor Setting Depths

2. The manual should describe how to calculate conductor setting depths using normal soil data,so as to satisfy the following requirements.

a) Enable Drilling Department to obtain mud returns to surface when drilling surfacecasing (normally diameter 20")

b) Have sufficient axial conductor capacity.

c) Ensure that pile capacities of structure are not adversely affected.

d) Locate the conductor shoes in clay rather than sand, as far as possible within theabove constraints.

SECTION 4 - Spudding-in Procedures

3. The manual should advise that prior to drilling a pilot hole in spudding procedure in theconductor shoe be drilled through to a depth approx. 10' below the conductor shoe, using thelargest bit to be used for drilling the next casing.

The reasons for this are:-

a) To check the shoe is not damaged.

b) To centralise the subsequent holes.

c) To confirm that the axial external skin friction capacity of the conductor exceeds it'sown weight.

4. There was a strong request that the criteria for cementing the first casing to surface or tomudline be closely examined. This should be covered in depth by the manual.

Page 73: PTS (Conductor Design and installation manual for offshore platform)
Page 74: PTS (Conductor Design and installation manual for offshore platform)
Page 75: PTS (Conductor Design and installation manual for offshore platform)
Page 76: PTS (Conductor Design and installation manual for offshore platform)
Page 77: PTS (Conductor Design and installation manual for offshore platform)
Page 78: PTS (Conductor Design and installation manual for offshore platform)
Page 79: PTS (Conductor Design and installation manual for offshore platform)
Page 80: PTS (Conductor Design and installation manual for offshore platform)

SECTION 7 - Selection of Installation Method

5. This section or an appendix should include the results of a wave equation analysis for theconductor sizes and hammers commonly used by B.S.P. For this Mr. Toolan has beenprovided with information on all hammers used in B.S.P. offshore areas, also information oncommon conductor sizes and material strengths.

SECTION 9 - Conductor Shoes

6. It was recommended that internal conductor shoes should be used generally 1.5 x conductorwall-thickness.

SECTION 10 - Curved Conductors

7. The section of the manual dealing with curved conductors should be expanded to discussmitred and slanted conductors and any other techniques used in the Group to maximiseseparation of conductor shoes.

8. A note should be included that it has been B.S.P.'s experience that diameter φ 20" casingcannot be run through a diameter φ 26"x 3/4 conductor at a dogleg severity or more than 5°per 100'.

Furthermore, diameter φ 18 5/8" casing has become an important size in B.S.P. and hasbeen run inside a diameter φ 26" curved conductor thro' a dogleg severity of 7º per 100'.

Data on the directional survey for Magpie D/P, and installation planning data was provided forMr. Toolan by OPE/15.

INTERNAL DISCUSSION

Arising out of this discussion, it was agreed that the following installation procedures should berecommended for trial by B.S.P. in the near future.

a) ECO will attempt to drive marine conductors on the drilling platform to or below the settingdepths calculated in point (2) above.

Notes have been left with EPE/4 on this procedure, and relevant parameters are beingreceived by Telex from Fugro, U.K.

b) If required by Drilling Department, one conductor will be stabbed by the installation barge, butnot driven. This will usually be a conductor furthest away from adjacent piles. Normally, thisdecision should of course be made before placing of the jacket.

c) Drilling Department can then install this conductor using the most appropriate techniques, andperform formation leak-off test at any depths desired.

The conductor will finally be set to a depth 50' - 150' below the pile tips.

It is intended that the first well from the platform be drilled through this conductor, setting thediameter φ 20" casing following current normal practice.

Page 81: PTS (Conductor Design and installation manual for offshore platform)

d) Should difficulties be encountered in this first well, either from loss of circulation or fromshallow gas pockets, it is agreed that for the remaining conductors on the jacket the φ 20" casing would be set at a shallow depth of typically 75' - 150' below pile tips.

For this situation, it is recommended that, as in the past, sea-water would be used for drilling,with the casing being set and cemented as in normal practice.

Page 82: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX II-1

SOIL PARAMETERS REQUIRED FOR CONDUCTORDESIGN AND INSTALLATION PLANNING

Page 83: PTS (Conductor Design and installation manual for offshore platform)

SOIL PARAMETERS REQUIRED FOR CONDUCTORDESIGN AND INSTALLATION PLANNING

The soil parameters required for the design and installation planning of conductors are given in theTable below. Also included in this Table are the types of laboratory tests which are used to obtainthese parameters.

In addition to the soil parameters, it is also necessary to know the specific gravity of any drilling fluidsto be used and the discharge height of drilling returns above sea level.

SOIL PARAMETER TEST

_ Visual description

Bulk density density test

Submerged density

Moisture content Moisture content test

Undraine Shear Strength Unconsolidated undrained triaxial test; pocket penetrometer;torvane; fall cone; consolidated undrained triaxial test (ifinsitu stresses can be estimated)

Remoulded Shear Strength plasticity index; moisture content; remoulded triaxial test

Strain required to mobilise 50% ofmaximum soil shear strength(cohesive soils only)

unconsolidated undrained triaxial test

unconsolidated undrained triaxial test

Overconsolidation

Ratio

Coefficient of Earth

Pressure at Rest

oedometer test; unconsolidated

undrained triaxial test

consolidated undrained traixial

test; plasticity index

Page 84: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX II-2

CALCULATION OF THE COEFFICIENT OFEARTH PRESSURE AT REST (Ko )

Page 85: PTS (Conductor Design and installation manual for offshore platform)

CALCULATION OF THE COEFFICIENT OFEARTH PRESSURE AT REST (Ko )

The method of calculation of Ko is dependent upon the soil type under consideration. Basically themethods differentiate between cohesionless and cohesive soils.

COHESIONLESS SOILS

For a cohesionless soil which has not experienced an overburden pressure greater than the existingvalue, i.e. the precompression ratio (PCR) is unity, the value of Ko is obtained from the expression:-

Ko = 1 - sin φ'

where φ is the angle of internal friction of the soil.

If the PCR of the soil is greater than unity, Schmertmann (Ref. 1) has developed the formula:-

Ko = (PCR) 0.42 x (1 - sin φ')

COHESIVE SOILS

For a normally consolidated cohesive soil the theoretical value of Ko is the same as for a cohesionlessmaterial:-

Ko = 1 - sin φ'

Due to the difficulty in assessing whether a clay is normally or lightly overconsolidated it is preferableto carry out laboratory tests to obtain a Ko value. These tests are relatively inexpensive and can beperformed on standard soils laboratory equipment. In addition to laboratory testing, variousrelationships have been developed linking Ko to the index properties of the material.

For a heavily overconsolidated clay, the following procedure is used to assess the Ko value of thesoil:-

1) Calculate the ratio of (c/p') on the basis of the results of the laboratory testing

where c = the undrained shear strength

p' = the effective overburden pressure

2) Calculate the ratio of (c/p') nc applicable for a normally consolidated clay, based on therelationship proposed by Skempton (Ref. 2)

(c/p') nc = 0.11 + 0.0037 (PI)

where PI is the plasticity index of the soil

3) Determine the ratio of (c/p')/ (c/p') nc and use this value to determine the overconsolidationratio (OCR) of the clay, based on the relationship proposed by Ladd and Foott (Ref. 3).

4) Estimate the value of Ko from published relationships between Ko, the OCR and the PI of thesoil, Brooker and Ireland (Ref. 4), Vijayvergiya (Ref. 5).

Page 86: PTS (Conductor Design and installation manual for offshore platform)

References

1) SCHMERTMANN, J., "The measurement of in-situ shear strength". Proceedings ASCEspecialty conference on in- situ measurements of soil properties Vol. 2 1975.

2) SKEMPTON, A.W., Discussion on "The planning and design of New Hong Kong Airport".Proc. Institution of Civil Engineers 7. 1957.

3) LADD C. and FOOTT, R. (1 974), "New design procedure for stability of soft clays", A.S.C.E.,J-GED, July, p 769.

4) BROOKER, E.W., and IRELAND, H.O., (1965) "Earth Pressures at rest related to stresshistory" Canadian Geotechnical Journal Vol. II No. 1 (Feb.).

5) VIJAYVERGIYA, V.N. "Procedure for computing axial pile capacity" Fugro Internal Paper.July 1977.

Page 87: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX III-1

THE USE OF THE WAVE EQUATION IN DRIVABILITY ANALYSIS

Page 88: PTS (Conductor Design and installation manual for offshore platform)

THE USE OF THE WAVE EQUATION IN DRIVABILITY ANALYSIS

General

For most conductor installations, use is made of driving methods for at least part of the installation.With computer programs based on the wave equation, the ability of a particular hammer to drive aconductor to its required penetration may be assessed. Such programs can also determine whether ornot the conductor is overstressed during driving.

To use the wave equation correctly it is necessary to have a basic understanding of the phenomenainvolved in pile driving. The impact of the hammer generates a compressive stress wave in theconductor. This stress wave travels down the conductor at the velocity of sound in steel, 5000 m/s. Ifthe wave meets a resistance or discontinuity a proportion is reflected back up the conductor, reducingthe magnitude of the downward travelling wave by an equal amount. Once the wave has reached theportion of the conductor shaft within the soil, the downward movement of the conductor behind thewave front generates a frictional resistance at the soil/conductor interface. This causes a reflectionwhich reduces the intensity of the wave. Eventually the wave reaches the conductor tip. If there issufficient power left in the wave to cause permanent deformation in the soil below the conductor tip, orif only elastic movements occur in the soil below the tip, the conductor will be in the same positionafter the blow as before it. In this situation the conductor is said to have refused.

Most conductor driving analyses use computer programs based on one dimensional wavetransmission. Those available within the Shell Group employ finite difference techniques for thenumerical analyses. The hammer is modelled as a falling weight striking a cushion and/or anvil, seeFig. 1. The conductor is modelled as a series of lumped masses of the conductor. The soil springs aredefined by; an ultimate static resistance (Ru); a displacement over which the soil behaves elastically,the quake (Q); and a damping factor which increases the static soil resistance as a function of theconductor velocity (J). The soil springs are shown on Fig.2.

The input data for hammer and conductor are simple to prepare and field measurements indicate thatthe mathematical model is sufficiently realistic. Standard values have been established for soil quakeand damping. These values have been backfigured from instrumented driving tests in conjunction withsoil resistances obtained from static load tests. The only input data which has to be specially preparedby the user is the Soil Resistance at time of Driving, SRD.

Experience gained from back analysing driving records indicates that the SRD is not equal to theultimate static capacity. For conductors in soft clays the capacity tends to increase with time and sothe SRD is generally much less than the static capacity. In hard clays the increase in capacity withtime is less, marked and the SRD may be of the same order of magnitude as, or greater than, thecalculated static capacity. Generally in all types of clay the majority of the SRD is developed in theskin friction whereas in sand a large proportion may be developed at the tip. In sands the calculatedSRD is greater than the calculated static capacity, see Refs. 1 and 2 for Shell Group experience.

There are a number of published methods for calculating the relationship between SRD and depth(Refs. 3 to 7). Since in each case SRD's, quakes and damping values have been developed intandem, it is not necessarily valid to use the SRD's calculated from one reference with quakes anddamping factors quoted in another.

The methods given in this Appendix will provide SRD values suitable for use with the wave equationprograms available within Shell . An example calculation is presented in Appendix III-2 and theresults in the form of a plot of SRD versus depth are given in that Appendix. These SRD valuesshould be used in conjunction with quake and damping factors quoted on Fig. 2. Comparisonsbetween predictions and field experience indicate that the method will predict harder than averagedriving, i.e. it provides reasonable correlations for the conductors which were hardest to drive (Ref. 5).This is deliberate. if it predicted average driving behaviour there would be a danger of a considerableproportion of conductors in the field refusing at shallower penetrations than anticipated. This couldhave costly consequences. The other methods listed in the references have been found to predictaverage driving. In addition to calculating the SRD during continuous driving, it may be necessary inclay soils to compute the SRD after set-up. This is simply done by substituting the static skin friction

Page 89: PTS (Conductor Design and installation manual for offshore platform)

by API method 1 or 2 (whichever is higher, see Appendix IV-1) for the calculated shaft friction duringdriving. The rest of the computation is as before. In some hard clay soils the SRD computed after set-up may be less than that calculated for continuous driving. This indicates that set-up effects may beignored.

Calculation of SRD versus depth relationship

The SRD at any depth is determined from the following considerations. If the soil inside the conductor(soil plug) remains stationary during driving the SRD must be made up of inside and outside frictionand wall end bearing. In this situation the magnitude of the inside friction which can be mobilised maybe limited by the end bearing capacity of the soil plug. Alternatively the soil plug may move downduring driving in which case the inside friction must be equal to or greater than the plug end bearing.Generally the conductor will behave in the manner which produces least resistance to penetration.

Thus at any depth the SRD will be the least of:-

where : fs' = unit shaft friction during driving (outside)

fi' = unit shaft friction during driving (inside)

qp' = unit point resistance during driving

These concepts for predicting SRD are shown on Figs.3 and 4.

Calculation of point resistance during driving

The Cone Penetration Test (CPT) is a model test for the penetration of a conductor. The pointresistance during driving (qp') may be calculated from the cone resistance (qc). When the conductor isplugged (i.e. the inner soil plug moves down with the conductor) the unit base resistance may becalculated by the method shown on Fig. 5. No limits are applied. Thus,

qp' = qu ……….. ........................... (3)

When the conductor is unplugged (i.e. the inner soil plug remains stationary as the conductor tippenetrates the ground) the unit resistance acting on the conductor wall annulus is taken to be equal tothe cone resistance at that depth,

qp' = qc ………… ........................... (4)

In clays in which CPT's have not been made a cone resistance for use in drivability studies can beestimated as 18 times the undrained shear strength. In sand strata it is difficult to assess drivabilitywithout the results of CPT's.

Page 90: PTS (Conductor Design and installation manual for offshore platform)

Calculation of shaft friction in cohesive soils

The contribution of skin friction to total SRD is calculated on the basis of laboratory test results. Alongthe length of the conductor, the soil at the interface with the conductor wall is strained to failure byevery hammer blow. In a cohesive material the soil is. compressed to accommodate the volume of theconductor as it penetrates. The displacement, shearing and compression remould the soil and causeexcess pore water pressures to be developed. Thus during continuous driving in a clay:

In many cases it may prove impossible to perform sufficient meaningful remoulded triaxial tests in thetime available. This is particularly the case with heavily overconsolidated clays which may have to beground down, reconstituted and reconsolidated prior to shearing.

In order to overcome this problem, considerable reliance is placed on empirical relationships betweenremoulded shear strength and other properties of a soil such as those developed by Skemption andNorthey (Ref. 8) and Houston and Mitchell (Ref. 9). The remoulded shear strength according toSkempton and Northey depends on a relationship between ιr and plasticity and liquidity indicesderived from laboratory measurements. This relationship is shown on Fig.6.

Calculation of shaft friction during driving in granular soils

In granular oil it is assumed that the unit shaft friction during driving is equal to the static unit shaftfriction :-

and may be calculated using the cone resistance as described previously. A limit of 0.12 MN/m²should be applied but no allowance should be made for lateral displacement effects. Equation (6)should be applied at all levels.

Results of Wave Equation Analysis

The input to the wave equation program may be divided into three parts,

hammer data

soil data

pile data

The output includes the permanent set per blow (the reciprocal of the blowcount) and the stresses inthe conductor during driving. Normal practice is to vary the SRD, while keeping all other input dataconstant. In this manner for a given hammer, conductor penetration and soil profile a relationshipbetween SRD and blowcount can be obtained. This is normally presented in the form of blowcount-resistance curves, see Fig. 7.

Page 91: PTS (Conductor Design and installation manual for offshore platform)

Two relationships have now been developed, SRD versus depth and SRD versus blowcount. Theseare used to determine the predicted blowcount versus depth relationship, see Appendix III-2.However, the situation is complicated by the fact that the SRD versus blowcount relationship varieswith

hammer efficiency (which may change during a drive)

conductor penetration (distribution of SRD between tip and shaft, soil damping increasing withdepth, different soils at tip of conductor)

Prior to describing drivability analyses in detail it is essential to return to first principles and considerthe effect of various parameters on drivability.

Parametric Considerations

The discussion of wave transmission earlier in this Appendix-enables some simple conclusions to bedrawn on the effect on drivability of various parameters. A given hammer will transmit approximatelythe same amount of energy, E, to any conductor irrespective of the conductor's dimensions. Theenergy in the conductor may be expressed as:

Since the mass is directly proportional to the cross sectional area of the wall, (A):-

The force F in the conductor which is available to overcome the soil resistance, is determined by theamplitude of the stress in the compression wave and the amplitude of the stress in the compressionwave and the cross sectional area of the conductor.

From wave theory, the stress amplitude is proportional to the ratio of the velocity of the lumped massto that of the wave front, i.e. the speed of sound, c.

Page 92: PTS (Conductor Design and installation manual for offshore platform)

And from equation (3)

Hammer Energy

It would appear from equation (13) that for a given conductor the maximum soil resistance which canbe overcome is proportional to the square root of the hammer's delivered energy.

The improvement in drivability due to increased energy is less favourable than the ratio of squareroots since higher energies involve higher velocities, stresses and elastic compression of theconductor, see equation (9). These lead to increased losses from side friction and damping. Thustrying to improve drivability by increasing hammer size is subject to the "law of diminishing returns".Eventually a stage is reached at which the hammer is so powerful (or heavy) that permissible driving(or static) stress levels in the conductor are exceeded. It is concluded that more powerful hammersare useful but they cannot solve every driving problem. This is confirmed by theoretical study and fieldexperience.

Wall Thickness

If a conductor is to be installed with a given hammer, its drivability will improve in proportion to thesquare root of its wall thickness. This results from equation (13). However, equation (9) indicates thatthe benefit of increased wall thickness will be greater than this since velocities, stresses and elasticpile compression are reduced. The consequence is that attenuation of the wave due to side frictionand side damping is lessened. The conclusion is that drivability improves with increasing wallthickness and this is confirmed by theoretical studies, see Fig. 7, and field experience, e.g. SOCfound that 26" x 3/4" curved conductors were easier to drive than straight 26" x ½" conductors.

It should be noted that there may be penalties involved in increasing the wall thickness of conductors.These are firstly the straightforward material costs and secondly increased fabrication costs.

Diameter

For a given wall thickness an increase in the diameter of a conductor will produce a linear increase inits cross sectional area. In accordance with equations (9) and (13) drivability will be improved by aproportion slightly greater than the square root of the diameter. However, at a given penetration thesoil resistance to be overcome will be increased by a similar amount. Thus with a given hammer, thelarger diameter conductor may not be able to be driven as deep as the smaller but the largerconductor will have a higher axial capacity.

Page 93: PTS (Conductor Design and installation manual for offshore platform)

Penetration in Uniform Soils

As a conductor is driven deeper, the length of shaft in contact with the soil increases. Hence a greaterproportion of energy is lost in soil damping. Thus for a given conductor hammer, the greater the pilepenetration the lower will be the soil resistance which causes refusal. However for penetrations whichare within approximately ±30% of that analysed significant errors do not occur, i.e. an analysis madefor 50m would be valid for penetrations within the range 35m to 65m.

The length of conductor above mudline has little if any effect on drivability.

Penetration in Stratified Soils

The drivability of a conductor is affected by the distribution of the soil resistance. Generally the greaterthe proportion of soil resistance at the tip the harder driving becomes. There are a number of reasonsfor this:

(a) high tip resistance is usually associated with sand and much higher point damping is appliedin sand than in clay', see Fig. 2.

(b) if the soil resistance on the shaft is low, velocities are high and energy losses due to soildamping are proportionately higher.

(c) the permanent movement of the conductor is governed by the situation for driving may arisewhen the conductors reach maximum penetration, or at some shallower depth when the tip isin sand.

Yield Strength

The higher the yield strength of the pile the higher is the allowable driving stress. There is littleguidance given in codes of practice as to a permissible driving stress. However experience in theNorth Sea and Gulf of Mexico (see record of meeting with SOC in New Orleans, Appendix 1) indicatethat a value of 80% of yield has often been used. This has not resulted in any unusual distress inconductors.

Referring to the paragraph on hammer energy, it appears that in some cases the use of high strengthsteels may allow the use of more powerful hammers. This may be an alternative to increasing the wallthickness.

References

1) "Pile driving in the North Sea", Paper 307, Shell 1978 Offshore EngineeringConference, Houston.

2) "Pile driving in the Gulf of Mexico", Paper 309, Shell 1978 Off shore EngineeringConference, Houston.

3) YOUNG, A.G., SULLIVAN, R.A. and RYBICKI, C.A., "Pile design and Installation Features ofthe Thistle Platform". EUR 12, European Offshore Petroleum Conference and Exhibition,London 1978.

4) HEEREMA E.P. "Predicting Pile Drivability: Heather as an Illustration of the 'Friction Fatigue'Theory". EUR 50, European Offshore Petroleum Conference and Exhibition, London, 1978.

5) TOOLAN, F.E. and FOX, D.A., "Geotechnical planning of piled foundations for offshoreplatforms". Proceedings of the Institution of Civil Engineers, Part 1, May 1977, pp 221-244.

Page 94: PTS (Conductor Design and installation manual for offshore platform)

6) DURNING, P.J., and RENNIE, I.A., "Determining Pile Capacity and Pile Drivability in Hard,Overconsolidated North Sea Clay". EUR 47, European Offshore Petroleum Conference andExhibition, London 1978.

7) NAUGHTON, H.R., and MILLER, T.W., "The Prediction and Subsequent Measurement of PileDriving Behaviour at the Hondo Platform in Santa Barbara". EUR 11, European OffshorePetroleum Conference and Exhibition, London, 1978.

8) SKEMPTON, A.W. and NORTHEY, R.D., "The sensitivity of clays". Geotechnique, III, 1,1952.

9) HOUSTON, W.N. and MITCHELL, J.K., "Property interrelationships in sensitive clays".Journal of the Soil Mechanics and Foundation Division, ASCE 95, SM4, July 1969.

Page 95: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 1 IDEALISATION OF HAMMER PILE AND GROUND FOR WAVE EQUATION ANALYSIS

Page 96: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 2 SUMMARY OF INPUT QUAKE AND DAMPING FACTORS FOR WAVE EQUATION

Page 97: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 3 BASIC CONCEPTS FOR PREDICTING SOIL RESISTANCE DURING DRIVING FOR ANUNPLUGGED CONDUCTOR

Page 98: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 4 BASIC CONCEPTS FOR PREDICTING SOIL RESISTANCE DURING DRIVING FOR APLUGGED CONDUCTOR

Page 99: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 5 COMPUTATION OF THE ULTIMATE UNIT END BEARING OF A PILE FROM A CONEPENETRATION TEST

Page 100: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 6 LIQUIDITY INDEX .V. REMOULDED SHEAR STRENGTH

Page 101: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 7 SOIL RESISTANCE AT TIME OF DRIVING VS BLOW COUNT

Page 102: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX III-2

EXAMPLE OF WAVE EQUATION ANALYSIS FOR CONDUCTOR DRILL-DRIVE SEQUENCE

Page 103: PTS (Conductor Design and installation manual for offshore platform)

EXAMPLE OF WAVE EQUATION ANALYSIS FOR CONDUCTOR DRILL-DRIVE SEQUENCE

1) The first stage of the analysis is to determine the soil resistance to driving (SRD) of theconductor, using the standard procedures described in Appendix III-1. An example of such anSRD calculation for a 28in. diameter conductor, at a North Sea site, is presented on Fig. 1.

2) For a drill-drive sequence, the computed SRD will need modification to allow for the effects ofdrilling-out. The amount of modification is difficult to predict on a purely theoretical basis.Wherever possible, use should be made of back-analyses of conductors installed by similarmethods at nearby sites. An example of this approach is shown on Figs. 2 to 4 of thisAppendix.

Figs. 2 and 3 show the observed soil resistance at the time of driving conductors atShell 's Dunlin Field in the North Sea. From the relationships shown on Figs. 2 and 3the generalised relationship shown on Fig. 4 has been obtained. It can be seen that the drill-drive procedure adopted at Dunlin generally inhibited the development of skin friction alongthe length of the conductors. Beyond the initial drive into virgin soil (necessary to form a sealto avoid washout at the mud-line) no significant build up in soil resistance occurs with depth.Where resistance has built up, it is due to tip resistance resulting from the conductor reachingthe bottom of the predrilled pilot hole. This resistance is destroyed on drilling out the nextlength of the pilot hole.

3) The next stage is to plot out the calculated SRD versus depth for a purely driven conductor,see Fig. 5. Combining this relationship with the results of a wave equation analysis performedfor the proposed installation plant, it is possible to calculate what percentage of total SRD canbe overcome by the conductor/hammer combination. An example of the wave equationanalysis is given on Fig. 6. In this example only approximately 25% of the calculated SRD atsetting depth could be overcome by a Delmag D-55 hammer.

4) The drill-drive sequence is then developed on the basis of the above information. After drivingthe conductor for an initial penetration, generally governed by the requirement to minimisewashout due to subsequent drilling operations, blowcount should be limited to a prescribedvalue. In the example shown, blowcount must not exceed a figure which would indicate that25% of the theoretical value SRD value at any particular depth has been accumulated. Thisblowcount is obtained from Figs. 5 and 6.

Page 104: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 1 : 28" CONDUCTOR - SRD 1 ½" W.T

Page 105: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 2 SOIL RESISTANCE DURING DRIVING AGAINST DEPTH DUNLIN A

Page 106: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 3 SOIL RESISTANCE DURING DRIVING AGAINST DEPTH DUNLIN A

Page 107: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 4 SOIL RESISTANCE DURING GENERALISED DRILL-DRIVE SEQUENCE DUNLIN A

Page 108: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 5 SOIL RESISTANCE AT THE TIME OF DRIVING DUE TO EXTERNAL SKIN FRICTIONONLY

Page 109: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 6 SOIL RESISTANCE AT THE TIME OF DRIVING VS BLOW COUNT

Page 110: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX III-3

EXTRACT FROM

"CONSTRUCTION SPECIFICATION FOR INSTALLATION OF STEEL PLATFORMS"

PREPARED BY SSB (SEPTEMBER 1978)

Page 111: PTS (Conductor Design and installation manual for offshore platform)

a) The CONTRACTOR shall continue to drive the pile with a higher number of blows per foot,

or

b) The CONTRACTOR shall jet out the soil plug inside the pile (in accordance with sub-section5.13) and then continue to drive the pile.

or

c) The CONTRACTOR shall drill out the soil plug inside the pile and drill a pilot hole (inaccordance with sub-section 5.14) and then continue to drive the pile.

The above procedures shall be approved by the COMPANY.

5.3.13 The CONTRACTOR shall carry out buckling analyses to ensure that add-on lengths/piledriving hammer to be utilized are compatible.

5.4 Shims

5.4.1 Every attempt shall be made to centralize all piles by using the largest shim plates possible.They should be driven in if necessary. Before commencement of welding shim plate fit-upshall be subject to inspection and approval by the COMPANY.

5.4.2 The number and size of shim plates issued for each installation is as shown on the ContractDrawings.

5.4.3 The shim plates shall be blast cleaned before fitting Once the shim plates are fitted thepile/leg area where the fillet, welds are to be made shall also be blast cleaned to a whitemetal finish.

5.4.4 Before all piles are driven to final penetration no welding between a shim and a pile ispermitted. If shim have been installed on certain piles while driving continues on another pile ,making of welds only between shim and jacket top is permitted. No welding during drivingoperations is permitted .If welding of shims to the jacket top can is temporarily suspended toallow further driving(of any pile , the weld made shall be inspected prior to recommencing theweld.

5.4.5 If need to be welded-off to the jacket so as to maintain the jacket level, use shall be made ofplates so as to 'dog-off' the piles, and not the shim plates

5.4.6 Fillet welds on the shim plates shall be in accordance with the Contract Drawings andstandard drawing S-0121,and shall be inspected on completion, in accordance with Section 4of this specification.

5. Conductors

5.5.1 The CONTRACTOR shall exercise controlled driving to minimise set-up and arrange thatconductors can be driven to the required target penetration by straight driving alone , withoutrecourse to jetting or drilling

5.5. It is recommended that the CONTRACTOR provides a hammer having a rated striking energyof about 50,000 ft. lbs. for driving the conductors

5.5.3 The conductors shall be as stated once pile driving is complete and the pile shims are at least50% welded out at each jacket leg. The maximum number of conductors which may besimultaneously hung off from the jacket top brace elevation is as shown on the ContractDrawing or specified in the outline Installation Procedures.

Page 112: PTS (Conductor Design and installation manual for offshore platform)

5.5.4 No driving of a conductor is permitted while other conductors are still hung off from the jackettop brace elevation i.e. all conductors must be self-supporting; or when welding out shims

5.5.5 Curved conductor sections shall be accurately lined up to ensure the correct curvature whenmaking field joints in curved sections

5.5.6 All field welds in conductors shall be made and inspected in accordance with Section 4 of thisSpecification. Cut offs shall be held to a minimum

5.5.7 The conductors shall be driven to the target penetration, at which penetration a ' good' drivingresistance should be achieved. 'Good driving' resistance is defined as approximately 40 blowsper foot with a hammer having a rated striking energy of about 50,000 ft. Ibs.

In the event that this 'good' driving resistance is not met at target penetration, driving mustbe continued until this requirement is achieved, or until all available conductor length isutilized.

5.5.8 In general the blowcount should always be limited to a maximum of 200 blows per foot for thetype of hammer recommended above. In the event that such blowcounts are encounteredbefore the target penetration is reached, driving must be discontinued when such hard drivingresistance is obviously caused by a hard layer at the tip of the conductor and not due set upin clay (e.g while making an add-on connection).

5.5.9 Conductors shall be cut off at the correct level, extended up to deck level and cover platesinstalled, as indicated on the Contract Drawings or in the Outline Installation Procedures.

Page 113: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX III-4

EXTRACT FROM

"OUTLINE INSTALLATION PROCEDURE FOR SFDP-A"

PREPARED BY SSB

Page 114: PTS (Conductor Design and installation manual for offshore platform)

Before stabbing the initials of skirt piles SA-2 and SB-2 the skirt pile sleeves must be flooded. Theprocedure for the installation/driving of the four skirt piles shall be similar to that for the centre piles.Skirt pile add-ons shall be reworked, and the skirt piles cut off underwater, in accordance with theContract Drawings.

The piles shall be driven with hammers having the rated striking energy recommended in ConstructionSpecification No.7, and in accordance with the following criteria:

(a) Design (Target) Penetration is 220 ft. for the main piles, 260 ft. for the skirt piles, wherebyover the last 10 consecutive feet, without driving stoppage, the blowcount should be at least:

HAMMER ENERGY BLOWCOUNT/FOOT

200,000 ft. lbs 100

300,000 ft. lbs 60

(b) Maximum penetration. If, at the target penetration, the blowcounts is less than the acceptableblowcount criteria under (a) driving must continue until the acceptable blowcount given under(a) is reached or until all available pile length is utilized.

It is emphasized that once pile driving has commenced, stoppage(e.g for welding of add-ons ) shouldbe kept to a minimum to avoid possible pile-freeze up.

The piles shall be shimmed-out in accordance with 6.4 below and cut-off in accordance with ContractDrawings.

Installation of Shims

The shim plates shall be installed and welded out in accordance with Construction Specification No.7and the Contract Drawings.

Conductor Installation

The conductors shall be installed in accordance with Construction Specification No. 7, and driven to apenetration of 100 ft. The following sequence shall be followed:

Curved Conductors

(a) Fill the four seal curved conductors with water, and then remove the covers at both ends ofthese conductors.

(b) install, weld-out and lower down the 1st. curved add-on for conductor nos. 4 and 5,

(c) install, weld-out and lower down the 2nd. add-on, until self-supporting, for conductor nos. 4and 5.

(d) repeat (b) and (c) for conductor nos. 10 and 15,

(e) install, weld-out and lower down the 1st. add-on, until self-supporting, for conductor nos. 3and 13,

Page 115: PTS (Conductor Design and installation manual for offshore platform)

(f) repeat (e) for conductor nos. 6 and 14,

(g) repeat (e) for conductor nos. 2 and 12,

(h) drive curved conductor nos 3,5,6,13 and 15 down to the cut-off level shown on the ContractDrawings,

(i) install and weld-out last add-on on all five conductors and drive to penetration,

(j) repeat (h) and (i) for conductors nos.2,4,10,12 and 14.

Straight Conductors

(a) hang-off conductor initial in conductor slots 1,11 and 9

(b) install, weld-out and lower down the 1st. add-on until self-supporting,

(c) repeat (a) and (b) for conductor slots 7 and 3,

(d) drive all five conductors,

(e) install and weld-out 2nd. add-on for all five conductors,

(f) drive all five conductors to final penetration.

The conductors shall be cut off, extended up to the cellar deck level and cover plates installed, all inaccordance with the Contract Drawing.

Jacket Top Walkways

After pile installations is complete the jacket top walkways shall be installed, all in accordance with theContract Drawings.

Deck Installations

The stub piles shall be installed in accordance with Construction Specifications No. 7 and cut offhorizontally at the correct level to accommodate the decks.

The decks shall be installed in three separate lifts, as shown on the Contract Drawings. The Drop-insection shall be accurately located and jacked into position as required . All field splices shall be made in accordance with the Contract Drawings, and all field installed timber, grating, handrails, pumpcaissons and drain lines accurately positioned and located.

Page 116: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX III-5

CORMORANT ALPHA CONDUCTOR INSTALLATION PROCEDURE

PREPARED BY SHELL EXPRO

Page 117: PTS (Conductor Design and installation manual for offshore platform)

CORMORANT ALPHA

CONDUCTOR INSTALLATION PROCEDURE

Page 118: PTS (Conductor Design and installation manual for offshore platform)

CORMORANT ALPHA

RELATIVE POSITIONS OF GUIDES/DECKS

Page 119: PTS (Conductor Design and installation manual for offshore platform)

Each Conductor Comprises:

Page 120: PTS (Conductor Design and installation manual for offshore platform)

CONDUCTOR DRILL/DRIVE PROCEDURE

In order to achieve a projected penetration of 360 ft. with ± 40º angle of deviation at the shoe, areference mark has to be made on the drill floor in the direction of the desired azimuth of each well.

1. Fit 35 ft. x 2½" dia. slings in the ears of the hook which is set to swivel. Attach a liftingelevator via 55 ton shackles to the slings.

2. Pick up the shoe joint on a lifting elevator, correctly positioned in the lifting strips. Align thehigh side of the deviated shoe to the reference mark and hang off on the rotary using the liftingelevator. Unshackle.

3. Pick up the second joint using a second lifting elevator as above. If connectors are fitted, staband connect; otherwise weld as per attached procedure (Appendix I) having first aligned thejoints by laser.

4. Lift the conductor a few inches and remove the lower lifting elevator. Lower the conductorthrough the rotary and in turn through the upper air-spider which is connected via 35 ft. long x2½" dia. slings to the B.O.P. jacks, and the lower air-spider (if connectors are used) which isresting on a spider support frame located en the production deck.

Land the conductor on the rotary as before, using the upper lifting elevator.

Note: Ensure the line denoting the high side of the deviation shoe has been followedthrough on this and every subsequent joint.

5. Continue with joints 3 through to 8, as above, if a "slack" sea is running (otherwise seeAppendix 2). Take care when locating and running through the guide frames.

6. With 8 joints, the total string length is ± 425 ft.

7. a) For welded conductor, land the conductor on the R.T. and shackle (35 ton) the slingsthrough two holes in the top. Release the elevator and lower the conductor through therotary.

b) If connectors are fitted, lower the string such that the elevator is a few inches above the R.T. Close the lower spider, remove the elevator and change over to 60 ft. long slings.Attach these slings to the upper spider and raise same as high as possible. Close upperspider, open the lower spider and lower the conductor.

c) Whether a) or b) applies, lower the conductor gently through the top of the caisson (459 ft,B.D.F.). Pull it back so that the shoe is 457 ft. B.D.F. and suspend it in the lower spider.

8. Make up and run 14" Magnet assy. to the bottom seal (649 ft. B.D.F.). until no recovery.Before reaching the bottom seal, circulate 5 minutes with 300 G.P.M. seawater.

9. Make up and run the following drilling assy.

Page 121: PTS (Conductor Design and installation manual for offshore platform)

17½" Bit26" H.O.26" Stabiliser30' x 9 ½" D.C.26" Stabiliser30' x 9 ½" D.C.26" Stabiliser60' x 9 ½" D.C.H.W.D.P. to surface

Tag bottom to see if any grout is on the seal, drill and ream to 658 ft. B.D.F. (5 ft. penetration)with 5/10,000 W.0.B., 50/60 R.P.M. and 350 G.P.M.

P.O.H. and remove collars run back with H.W.D.P. to 2 ft. from bottom (656 ft. B.D.F.). Spota H.V. slug of the corrosion inhibitor (see Appendix 3) at bottom and then pump 300 bbls ofthe same through the drill pipe as it is slowly pulled back to the caisson top (459 ft. B.D.F.).

P.O.H. the H.W.D.P.

10. Pull back the conductor through the R.T. by reversing either a) or b) in 7 above. Add joints 9and 10.

11. Add joint 11 (C.G.C.). Open the C.G.C. prior to lowering and test its operation.

Note. If transport strips are fitted to the C.G.C. these have to be ground flush beforelowering.

12. Add joints 12 and 13. Total conductor length is ± 670 ft. Lower the conductor to seabed (653 ft.B.D.F.) and work through the bottom of the caisson to ensure no drag or overpull.

ORIENTATE the shoe and run into seabed.

13. Pick up the hammer and chaser and drive to a maximum blow count of 50/60 B.P.F. Set backthe hammer and chaser, close upper spider and open the C.G.C. using the B.O.P. jacks.

14. R.I.H. as under 9 and drill a pocket (± 15 ft) with 10/15,000 W.O.B., 60 R.P.M. and 450 G.P.M.such that the top of the conductor will arrive at the connecting station (55 ft. B.D.F.)

Circulate 30 bbls H.V. mud, chase out with 450 bbls seawater and spot 30 bbls H.V. mud.

Note: H.V. mud is hydrated bentonite in fresh water or cellosize 2ppb in seawater withmarsh funnel viscosity ± 60.

15. Pull back 2 stands of D.P., close the C.G.C. and open the spiderPick up hammer and chaser. Latch the chaser hang-off assy. on to the drill string, set aside thebushings, stab the chaser and drive the conductor (max. 50/60 B.P.F.)

Set back hammer and chaser.

Page 122: PTS (Conductor Design and installation manual for offshore platform)

16. Pick up joint 14 (on shackles if welding, or on the single joint handling tool if connectors arefitted) having first inserted 100 ft. long slings and D.P. elevator through the joint. Latch theD.P. elevator on to the drill assy., set aside the bushings, lower the joint through the rotary andadd to the existing conductor.

17. Open the C.G.C. and R.I.H.

Drill 40 ft. below the shoe using 20/25,000 W.O.B., 50/60 R.P.M. and 450/500 G.P.M

Circulate 50 bbls and spot 50 bbls H.V. mud.

18. P.O.H. two stands, close C.G.C. and drive conductor to a max. 60 B.P.F., otherwise re-reamhole if connecting station is not reached.

Note: A close watch is to be kept on the hammer blow-count. If high blow-counts persistduring the first 3 to 5 ft. of hammering, or if a sudden rise occurs, the hole is to be re-reamed.

19 Continue adding joints of conductor, until a penetration of 350 ft. is achieved (i.e. ± 1,003 ft.B.D.F.).

After the last drill-out to 1,003 ft. B.D.F., pull out the whole drill assy. and drive the conductor torefusal (250/300 B.P.F.) with a final penetration of 355-360 ft. (1,008-1,013 ft. B.D.F.). Theseam of the C.G.C. is to be ± 5 ft. above the caisson at refusal.

20. Cut the conductor above the production deck - 59-04 ft. B.D.F. (see Appendix 4).

Install the neoprene packers (3 x 90º segments) between the conductor and guide sleeve -located just below the production deck.

Page 123: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX IWELDING PROCEDURE

1. Weld preparation will be a single V bevel with 35º on the leading end and 15º on the trailingedge.

2. The weld area is to be preheated to 200º F, 6" either side of the bevels.

3. Root run with E7010 Nos. 10 rods (e.g. Shield-Arc 85).

4. Fill and cap with E7016 or E7018 Nos. 6 or 8 rods (e.g. ESAB OK -Unitrode 48.00).

5. The interpass temperature is not to exceed 750º F.

6. The weld is to be allowed to cool slowly and to be protected from air streams.

7. Cleaning of slag is to be done using needle-guns.

8. No water/rain is to enter the weld area during welding and cooling.

9. The weld is to be allowed to cool slowly.

LASER ALIGNMENT

Prior to each weld made on the drill floor, the butt area is to be aligned by laser, as follows:

1. Attach the laser target to the incoming joint, approximately 2 ft. below the lifting elevator, whilstthis joint is horizontal in the V-door.

2. Stab the joints, clean the bevels and connect the laser running tool below the levels. Affix thetwo lasers to the running tool and, using the target , align the incoming joint to the outgoingjoint(s).

3. Preheat and root the weld. Recheck the alignment by laser. If O.K., disconnect the running tooland complete the weld.

Page 124: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX - 2

In order to locate the 1st guide (below sealevel) during "heavy seas", the following procedure may beadopted:

A Offshore Welded Conductor

1. Following the addition of joint 3, land the conductor on the R.T. Disconnect the slingsfrom the lifting elevator and shackle them through two holes in the top of the conductor.14ft the conductor, release the elevators and lower the conductor 5 ft. below the R.T.Suspend the conductor in the (upper) spider.

2. Make up and run the following assembly:

Note: Take care when stabbing the assembly through the first guide.

3. Pick up joint 4 via shackles through holes in the top of this joint, having first threaded 100ft. slings and a D.P. elevator through it.

4. Latch D.P. elevator to drill assy. and lift it together with the joint.

5. Set aside bushings, attach two 15 ft. long slings to D.P. elevator and shackle thesethrough the two holes in the conductor beneath it.

6. Open spider, pull back conductor and land on R.T. using a lifting elevator.

7. Rebevel the conductor and stab and weld incoming joint. In this position shoe is ± 145 ft.B.D.F. (string length being 205 ft.). Using the centraliser assembly to locate the first guide(176.97 ft. B.D.F.) run the conductor through it, such that the top is again 5 ft. B.D.F. andclose the spider.

8. Set back the centraliser assy. and then pull back the conductor using 35 ft. slings and landon the R.T. as before. The shoe will then be ± 200 ft. B.D.F . Continue adding joints.

B. Connected Conductor

1 Following the addition of joint 3, lower the conductor such that lifting elevator is a fewinches above the R.T. Close the upper spider ensuring the B.O.P. jacks are in their upperposition.

Page 125: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX 2

(contd)

Release the lifting elevator and lower the conductor on the B.O.P. jacks. Close the lowerspider, raise B.O.P. jacks, close upper spider, open the lower and lower conductor again on theB.O.P. jacks. Continue until top of conductor is 5. ft. B.D.F.

2. Make up and run assy. as in A.2. above.

3. Pick up joint 4 using a lifting elevator with 100 ft. slings and D.P. elevator through it.

4. As in A.4. above.

5. Pull the existing conductor back through the R.T. by reversing the lowering procedure of B.1.above and land on the R.T.

6. Make the connection, lower the conductor through the first guide as in A.7. and then furtherbelow the R.T. as in B.1.

7. Set back the centraliser assy., pull back conductor by reversing B.1. and land on the R.T. asbefore. Continue adding joints.

Page 126: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX 3

CORROSION INHIBITOR

From: UETA/123 of 3/8/78

1) Fill tank with required fresh water.

2) Add caustic soda + 0.5 lbs/bbl. to give pH of 11-11.5.

3) Add bentonite, 20 lbs/bbl through hopper, allow to hydrate for 15 minutes.

4) Add saltgel, 20 lbs/bbl.

The resulting mixture gives:

pH - 11-11.5PV - 17 cpYP - 66 lbs/l00 ft 2

Gels - 55 lbs/100 ft 2

140 lbs/l00 ft 2 (10 minutes)

API fluid loss - 20 ccs

After 24 hours:

pH - 11

Pv - 15 cp

Yp - 17 lbs/100 ft2

Gels - 29 lbs/100 ft2 (initial)

84 lbs/100 ft2 (10 minutes)

API fluid loss - 16 ccs

Page 127: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX 4

CONDUCTOR SLOT No. 3

In order to keep the circulating gravity connector open upon completion of the installation of theconductor in slot No. 3 (the -first in the conductor drilling sequence), the following procedure is to beadopted:

1) Upon driving the conductor to refusal, mark a circumferential line around the conductor 43"above the production deck (i.e. 62.62 ft. B.D.F.), before cutting!

2) Open the C.G.C. via 60 ft. slings (or the 30" Varco Spider suspended from the B.O.P. jacks).

3) Position the landing frame around the conductor.

4) Weld the pad-eyes (2 off) to the conductor such that they rest on the landing frame.(Remove frame during welding). -

5) Reposition the frame and bolt together. Take the weight off the slings supporting theconductor and cut the conductor at the aforementioned mark (item 1)

For the remaining seven conductors -of this sequence, cut the conductor with the C.G.C. closed, 55"above the 62.62 ft. B.D.F. level; then cut 2 x 3" dia. holes at 4" centres from the top.

P.A. KIDD,

UEOA/53.

3rd October, 1978.

Page 128: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX III-6

EXTRACT FROM

"DRILL AND CEMENT CONDUCTOR INSTALLATION SPECIFICATION"

PREPARED BY QPPA

Page 129: PTS (Conductor Design and installation manual for offshore platform)

OPE/5/78 APPENDIX 3

LOC MM NORTH FLANK

(WELL MM-26)

MUD PROGRAMME

Anticipated Problems

1. Possible losses in tertiary formations, resulting in H2S attack, washouts, poor logging, bad

cementation, etc

2. Laffan, Nahr Umr and Hawar shales : Washed out holes, cavings, sloughing.

3. Differential sticking and/or losses due to slightly depleted reservoirs (Yamama/Sulaiy/Arab-I/Arab-

II)

4. Unknown formation strength near fault (Mishrif/Kharaib).

5. Differential pressure between Arab-III/IV, depleted reservoirs and overlying Arab-I/-Il.

A. Programmes

I - 26-inch Hole (sea bed to 430 ft)

Objectives 1. To clean hole thoroughly while drilling.

2. To prevent hole collapse prior to running 20-inch casing.

1. Drill with sea water.

2. Slug hole at every connection and at bottom with 50 bbl high viscous SMR pill (ca. 3 ppbSM(R) in sea water, pH 9.5, vis. > 120 sec. M.F.).

3. Prior to pulling out to sea bed and pulling out of hole (refer item 1 (b), (c) of mainProgramme), spot Ca. 250 bbl high viscous SM(R) pill (composition as above) to fill up holecontents + 50% excess).

Page 130: PTS (Conductor Design and installation manual for offshore platform)

CASING AND CEMENTATION PROGRAMMES

Summary

A. Programme I to V Runnig and cementation of 20", 13 3/8" , 9 5/8" casings, and of 7" and4½" liner.

B. Minimum stock requirements

_____________________________________

A. Programmes

I : 20-inch Conductor

1. a) Run 20-inch (94-K55-BCSG) conductor to ca.410 ft (i.e. ca.200 ft penetration) as follows:

a) Float shoe.

b) 20-inch conductor to surface, with one centraliser per joint on bottom 3 joints.

b) Suspend casing on elevators.

2. - Run stab-in tool (with 2 centralisers) on 5-inch drill pipe and stab into shoe.

- Fill up 5-inch/20-inch annulus with sea water to check seals.

3 Circulate clean with sea water (twice hole contents).

4. Pump a 16.0 ppg slurry containing class G cement, seawater and 2% CaCl2 (byweight of cement).

Mixing water requirement 0.118 bbl/sx

Slurry Yield 0.201 bbl/sx

Pump either annulus contents, assuming 30" hole plus 100% excess (i.e. ca.1000sks) or until divers observe returns at seabed, whichever occurs first.-

5. Observe for backflow:

- If backflow ensure cement has been just displaced out of DP and close DP,after surface samples are hard, unlatch and pull out of hole.

- If no backflow unlatch at once and pull out of hole.

Note: If divers do not observe returns at sea bed, top fill cernentation(s) will becarried out as required, but at a later stage.

6. Revert to Main Programme.

Page 131: PTS (Conductor Design and installation manual for offshore platform)

LIST OF APPENDICES

I. Prognosis

2. Casing cement and other requirements.

3. Mud Programme.

4. Casing and cementation programme..

5. Evaluation programme (coring, logging, open hole testing)

6. Optimisation of drilling parameters in 12¼-inch hole (to be issued separately)

7. Time and Cost Estimates.

_____________________________________

PROGRAMME

Summary : - Phases I, II, III, IV and V (Drilling 26", l7½", 12¼", 8½" and 6" hole sections)

Phase I - Drilling 26-inch Hole Section

1. a) - Spud with 17½-inch bit (at slack tide).

- Drill 20 ft. Pull back above seabed.

- Run back to bottom (if unable to re-enter hole, spud again)

- Pull out of hole.

b) - Drill 26-inch hole to ca. 480 ft with sea water, slugging hole with 30 bbls high viscous pillat every connection.

- Circulate hole clean with high viscous pill.

- Spot high viscous pill to fill-up hole contents.

- Pull back 10 ft below seabed.

c) - Wait 6 hours.

- Run to bottom, checking for fill

- Circulate clean, spot high viscous pill to fill-up hole contents

- Pull out of hole.

Note: See Appendix 3-I for mud engineering.

2. Run and cement 20-inch conductor at ca. 460 ft (i.e. ca. 250 ft penetration) as perAppendix 4-1

3. - While waiting on cement, secure 20-inch conductor to barge using 3½-inch pipe, 20-inchclamp and turn buckles. Back off landing joint.

- Install - 20-inch casing head housing.

- 20-inch hydril (+ diverter).

- 20-inch flow riser.

Page 132: PTS (Conductor Design and installation manual for offshore platform)

PROGRAMME

Summary: - Phases I, II, III, IV and V (Drilling 26", 17½", 12¼", 8½" and 6 1/8" hole sections).

- Phase VI (Completion).

Phase - Drilling 26-inch Hole section

Note: Check that bit guide for 20-inch lower 61amp (below sea level) has been installed.

1. a) - Spud with 17½-inch bit (at slack tide).

- Drill 20 ft. Pull back above seabed.

- Run back to bottom (if unable to re-enter hole, spud again).

- Pull out of hole.

b) - Drill 26-inch hole to ca.430 ft with sea water, slugging hole with 30 bbl high viscous pill atevery connection.

- Circulate hole clean with high viscous pill.

- Spot high viscous pill to fill-up hole contents.

- Pull back 10 ft below seabed

c) - wait 6 hours

- Run to bottom, checking for fill.

- Circulate clean, spot high viscous pill to fill-up hole contents..

- Pull out of hole.

Note: See Appendix 3-I for mud engineering.

2. Run and cement 20-inch conductor at ca. 410 ft (i.e. ca. 200 ft penetration) as per Appendix 4-I.

Note: 1) Remove bit guide prior to running 20-inch conductor.

2) Space out to have 20-inch collar 1 ft above grating.

3. - While waiting on cement, secure 20-inch conductor to jacket. Back off landing joint.

- Install - 20-inch casing head housing.

- 20-inch hydril (+ diverter).

- 20-inch flow riser.

Page 133: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX 4

LOCATION BH NORTH NOSE

(WELL BH-23)

OPE/7/78

RIG-103

Summary

A. Programmes I to IV : Running and Cementation of 20" , 13 3/8" 9 5/8" Casing and 7" Liner.

Programmes

I : 20-inch Conductor

1. Run 20-inch (94-K55-BCSG) conductor to ca. 460 ft (i.e. ca. 250 ft penetration) as follows:

a) Halliburton float shoe.

b) 20-inch conductor to ca. 5 ft above sea bed, with one centralizer per joint on bottom3 joints.

c) 20-inch Cameron mudline suspension housing.

d) 20-inch Cameron MLS running tool.

e) 20-inch running string

2 - Run Halliburton stab-in tool (with 2 centralizers) on 5-inch drill pipe and stab intoshoe.

- Fill up 5-inch/20-inch annulus with sea water to check seals.

3. Circulate clean with 50 bbl viscous pill (SMR, viscosity ca.l20 sec. MF), followed by seawater(twice hole contents).

4. Pump a 16 ppg slurry containing class G cement, sea water and 2% CaCl2 (by weight ofcement):

Mixing water 0.118 bbl/sx

Slurry yield 0.201 bbl/sx

Pump either theoretical annulus contents (26" hole) plus 150% excess (i.e. ca. 1000 sks)or until divers observe returns at surface, whichever occurs first.

Note : Have 2000 sks on site.

Page 134: PTS (Conductor Design and installation manual for offshore platform)

5. Observe

- If backflow: ensure cement has been just displayed out of DP and close DP, after surfacesamples are hard, unstab and pull out of hole.

- If no backflow: unlatch at once and pull out of hole.

Note: If drivers do not observe returns at sea bed, top fill cementation(s) will be carried out asrequired later stage.

6. After cement is hard, divers to check top of cement.

7. Revert to main programme.

Page 135: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX IV-l

AMERICAN PETROLEUM INSTITUTE (API RP 2A 1979)

AXIAL CAPACITY CALCULATIONS

Page 136: PTS (Conductor Design and installation manual for offshore platform)

AMERICAN PETROLEUM INSTITUTE (API RP 2A 1979)

AXIAL CAPACITY CALCULATIONS

The axial capacity of a conductor is usually calculated using the API RP 2A. 1979 method. This

method gives the short term capacity of a conductor, which is the most applicable condition to be

considered. This is because a conductor usually has to support the maximum axial load shortly after

its installation. This axial load is due to the weight of the first inner conductor casing, which is

suspended from the outer conductor prior to being grouted.

Using the API method, unit values of shaft friction (f) and end bearing (q) are calculated using the

design criteria showing Figs. 1 and 2. However, due to their shape and method of installation,

conductors can normally only develop axial capacity due to external shaft friction.

An example of an axial capacity calculation for a conductor is presented on Figs. 3 and 4. Axial

capacity is developed due to external shaft friction only, and also no contribution to axial capacity is

assumed for that portion of the conductor shaft affected by the drill-drive sequence (14m to 50m

below ground level).

Page 137: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 1 DESIGN CRITERIA FOR ULTIMATE BEARING CAPACITY OF

PILES IN COHESIVE SOIL (METHOD 2)

Page 138: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 2 DESIGN CRITERIA FOR ULTIMATE BEARING CAPACITY OF

PILES IN COHESIONLESS SOIL (METHOD 1 & 2)

Page 139: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 3 PILE CAPACITY

Page 140: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 4 ULTIMATE STATIC BEARING CAPACITY

Page 141: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX IV-2

AXIAL CAPACITY OF A DRILLED AND CEMENTED CONDUCTOR

Page 142: PTS (Conductor Design and installation manual for offshore platform)

AXIAL CAPACITY OF A DRILLED AND CEMENTED CONDUCTOR

The axial capacity of a drilled and cemented conductor may be calculated using a modification to the

API RP 2A 1979 method. Values of unit shaft friction (f) and unit end bearing (q) are calculated using

the design criteria shown on Figs. 1 and 2.

The major alteration to the standard API method is the way in which unit shaft friction in cohesionless

soils is calculated. For a drilled and cemented conductor, the shaft friction developed is a function of

the effective lateral stress on the wall of the hole. If the grout in the annulus around the conductor is

in a fluid state, the grout pressure and therefore the lateral stress adjacent ot the hole, increases

linearly with depth. Theoretically the available unit shaft friction will also increase linearly with depth.

However, the allowable shaft friction will in practice be limited by the need to avoid failure of the band

between the grout and the conductor (Ref.1)

Another important consideration is to choose a grout density such that the resulting fluid pressure will

not cause hydrofracture of the soil formation. Such a failure may occur in either a vertical or

horizontal plane, see Section 3 of the Manual for details.

In cohesive soils the recommendations of API RP 2A 1979 are followed more closely, with the

exception that in overconsolidated clays a reduced α value of 0.4 is adopted.

References

1. EHLERS, C.J., and ULRICH, E.J., "Design criteria for grouted piles in sand". Paper OTC

2941, Offshore Technology Conference, Houston 1977.

An example of the bearing capacity calculation for a 1.07m pile to be installed by a drill and cement

sequence is given below.

Page 143: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 1 DESIGN CRITERIA FOR ULTIMATE BEARING CAPACITY OF PILES

IN COHESIVE' SOIL

Page 144: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 2 DESIGN CRITERIA FOR ULTIMATE BEARING CAPACITY OF PILES IN

COHENSIONLESS SOILS

Page 145: PTS (Conductor Design and installation manual for offshore platform)
Page 146: PTS (Conductor Design and installation manual for offshore platform)
Page 147: PTS (Conductor Design and installation manual for offshore platform)
Page 148: PTS (Conductor Design and installation manual for offshore platform)
Page 149: PTS (Conductor Design and installation manual for offshore platform)
Page 150: PTS (Conductor Design and installation manual for offshore platform)
Page 151: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 3 ULTIMATE STATIC BEARING CAPACITY

Page 152: PTS (Conductor Design and installation manual for offshore platform)

CONDUCTORS

FOR

TENDER ASSISTED DRILLING

PLATFORMS

BY

D. HENERY

BRUNEI SHELL PETROLEUM COMPANY LIMITED

OCTOBER 1972

CONFIDENTIAL

Page 153: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX V-1

REPORT PREPARED BY BSP ENTITLED

"CONDUCTORS FOR TENDER ASSISTED DRILLING PLATFORMS"

OCTOBER 1972

Page 154: PTS (Conductor Design and installation manual for offshore platform)

CONTENTS

1. Introduction

2. Conclusions

3. Conductors for drilling platforms

4. METHODS of installation of conductors available to BSP and SSB at present or in nearfuture.

5. Technical aspects of the six methods of installation of 26" x ½" conductors and 20" casing.

6. Technical aspects of the six methods of installation of 30" x 1" conductors and 20" casing.

7. Financial and probability study of the six methods of installation of 26" x ½" and 30" x 1"conductors and 20" casing.

8. Effect of tender platform and jacket design and construction of replacing 26" x ½" conductorby 30" x 1" conductors.

Page 155: PTS (Conductor Design and installation manual for offshore platform)

APPENDICES

APPENDIX I - Financial assumption and equipment performance for installation of 26" x ½"and 30" x 1" conductors and 20" casing.

APPENDIX II - Cost of the six methods of installation and materials costs of 26" x ½"conductors and 20" casing.

APPENDIX III - Cost of the six methods of installation and materials costs of 30" x 1"conductors and 20" casing.

FIGURES

FIG.1 - 6 pile jacket tender assisted drilling platform for 10 wells.

FIG.2 - pile, conductor and casing penetrations - case (A) 120 feet water depth

FIG.3 - pile, conductor and casing penetrations - case (B) 205 feet water depth

FIG.4 - decision tree for installation of 20" casing and/or 26 inch diameter, 0.5 inchwall conductor - case (A) 120 feet water depth

FIG.5 - decision tree for installation of 20" casing and/or 26 inch diameter, 0.5 inchwall conductor - case (A) 120 feet water depth

FIG.6 - decision tree for installation of 20" casing and/or 30 inch diameter, 1.0 inchwall conductor - case (B) 205 feet water depth

FIG.7 - decision tree for installation of 20" casing and/or 30 inch diameter, 1.0 inchwall conductor - case (B) 205 feet water depth

FIG.8 - average costs (from the decision tree) for materials and installation of 20"casing and/or 26" x ½" conductor in a 10 well platform case (A) 120 feetwater depth

FIG.9 - average costs (from the decision tree) for materials and installation of 20"casing and/or 30" x 1" conductor in a 10 well platform case (A) 120 feetwater depth

FIG.10 - average costs (from the decision tree) for materials and installation of 20"casing and/or 26" x ½" conductor in a 10 well platform case (B) 205 feetwater depth

FIG.11 - average costs (from the decision tree) for materials and installation of 20"casing and/or 30" x 1" conductor in a 10 well platform case (B) 205 feetwater depth

Page 156: PTS (Conductor Design and installation manual for offshore platform)

1. INTRODUCTION

Brunei Petroleum Company Limited and Sarawak Shell Berhad between there have to date installed 4self contained multiwell drilling platforms and 10 tender assisted drilling platforms in the South ChinaSea (neglecting the shallow water Marine platform offshore Seria). Twenty six inch outside diameter,half inch wall conductors or fixed marine risers have been installed in the platforms prior to spudding.the wells.

This report looks at the reasons why a conductor is required, and discusses the six methods ofinstallation for conductors available to the Companies at present or in the near future. The technicalaspects of the. six methods of installation of 26" x ½" conductors are listed together with thelimitations that are imposed on the methods duo to the limited inherent strength of the 26" x ½" pipe

The report then discusses the technical aspects of the six methods of installation when applied to alarger diameter heavier wall conductor -namely 30" x 1" , which Is the same diameter as the 6 jacketpiles of the tender assisted drilling platform.

A financial and probability study is described and decision trees are given for the six methods ofinstallation of 26" x ½" and 30" x 1" conductors in platforms in 120 feet and 205 feet water depth.

Thereafter, the costs of materials and installation and drilling tender hours required by the mainmethods for installing 26" x ½" conductors and 30" x 1" conductors are given in further detail.

Page 157: PTS (Conductor Design and installation manual for offshore platform)

2. CONCLUSIONS AND RECOMMENDATIONS

(a) It is concluded that the method of driving 26" x ½" conductor to refusal by the derrick bargeMantorek and subsequently setting 20" casing in every well by the drilling tender is the mostattractive method when financial, technical and operational details are considered.

(b) It is recommended that the method given in (a) above is adopted as soon as possible..

(c) It is also recommended that if and when a simulation model for scheduling derrick equipmentsets is designed that a study be made of the possibility of scheduling theengineering/production workover barge Mendu and the derrick equipment sets fordrilling/driving 26" x ½" conductors to target penetration. A study of equipment requirementsand a detailed design study will also be required.

(d) It should be noted that on the advice of Petroleum Engineering Department, it was decidedthat deffered production should not be taken into account.

Page 158: PTS (Conductor Design and installation manual for offshore platform)

3. CONDUCTORS FOR DRILLING PLATFORMS

There are several reasons by conductors are required, some of which are:-

(a) to prevent the washout around and below the jacket piles during spudding in and beforesetting the first casing in the well.

(b) to support the surface casing string before the current has set.

(c) to attempt to control shallow gas blowouts and avoid cratering below the platform.

(d) to provide a method of getting mud returns to the platform during the drilling operation andbefore setting the first casing in the well.

(e) to protect the well casing against wave attack.

(f) to prevent surface formation collapse before setting the first casing.

The conductor is a steel pipe driven into the seabed by a pilling hammer to a target penetration ofabout 20 feet below the toe of the deepest jacket pile. The conductor is supported laterally above theseabed by conductor guides into the jacket and platform celler deck. Jetting and/or drilling may berequired to assist with obtaining the required conductor target penetration.

If the conductor meets resistance beyond which it is impossible to safely proceed without the risk ofdamaging the conductor, it may be necessary to drill a hole and set a shallow casing string inside theconductor. This casing string (usually 20" casing) is set at about 50 to 100 feet below the toe of thedeepest pile.

Sketches (1), (2) and (3) indicate the spacing and setting depths of the jacket piles, conductors and20" surface casing for two typical tender assisted drilling platforms.

Page 159: PTS (Conductor Design and installation manual for offshore platform)

4 METHODS OF INSTALLATION OF CONDUCTORS AVAILABLE TO BSP AND SSB AT PRESENT OR IN NEAR FUTURE.

There are 6 method by which. BSP or SSB can, or will, be able to install conductors on tenderplatform. The 6 methods are given below, following each method are the sequence of methods whichare used to ensure that in the event of failure of one method another method is used to complete thesurface casing and/or conductor requirements on the platforms. The methods are also shown inFig. 4

1. Derrick barge Mantorek, drilling tender and derrick equipment set.

(a) Mantorek stab initial length of conductor, add on further lengths of conductor, weldand drive conductor into seabed. Continue operation until conductor reaches targetpenetration.

(b) Mantorek can jet out the plug of soil inside the conductor or below the toe of theconductor to reduce the driving resistance and enable the conductor to reach targetpenetration.

(c) Mantorek can attempt to drill in advance of the toe of the conductor. Thedrilling/driving may be carried out in several stages or alternatively a hole may bedrilled to conductor target penetration and the conductor driven into it.

(d) Failing the above methods, the conductor will be driven to an acceptable hammerblowcount/penetration by the Mantorek and the drilling tender and derrick equipmentset will then set 20" surface casing inside the conductors.

2. Derrick bare Mantorek, drilling tender and derrick equipment set..

(a) Mantorek stab initial lengths of conductor.

(b) Mantorek add on further lengths of conductor and drive conductor to an acceptablehammer blowcount/penetration..

(c) Drilling rig and derrick equipment set - set 20" surface casing inside every conductor.

3. Drilling tender (Nickle, Pieree, Sidewinder or Jumbo) and derrick equipment set

(a) Mantorek stab initial lengths of conductor

(b) Drilling rig and derick equipment set drill/drive conductors to target penetration.

(c) If the drilling/driving method fails to get the conductors to target penetration, the rigwill drive the conductors to an acceptable blowcount/penetration and then set 20"surface casing inside the conductors.

Page 160: PTS (Conductor Design and installation manual for offshore platform)

4. Engineering/Production workover barge Mendu and packaged workover rig.

(a) Mantorek stab initial lengths of conductor

(b) Mendu and workover rig drill/drives conductors to target penetration.

(c) If the drilling/driving method fails to get the conductors to target penetration, Menduand the workover rig will drive the conductors to an acceptable hammerblowcount/penetration and then the drilling rig and derrick equipment set - set 20"surface casing inside the conductors.

5. Engineering/Production workover barge Mendu and derrick equipment set

a) Mantorek stab initial lengths of conductor

(b) Mendu and DES drill/drives conductors to target penetration.

(c) If the drilling/driving method fails to get the conductors to target penetration, Menduand the DES rig will drive the conductors to an acceptable hammerblowcount/penetration and then the drilling rig and derrick equipment set - set 20"surface casing inside the conductors.

6. Derrick barge Atlas (or similar), drilling tender and derick equipment set

(a) Atlas stab initial length of conductor, add on further lengths of conductor, weld anddrive conductor into seabed. Continue operation until conductor reaches targetpenetration.

(b) Atlas can jet out the plug of soil inside the conductor or below the toe of the conductorto reduce the driving resistance and enable the conductor to reach target penetration.

(c) Atlas can attempt to drill in advance of the toe of the conductor. The drilling/drivingmay be carried out in several stages or alternatively a hole may be drilled toconductor target penetration and the conductor driven into it.

(d) Failing the above methods, the conductors can be driven to an acceptable hammerblowcount/penetration by the Atlas arid the drilling tender and derrick equipment setwill then set 20" surface casing inside the conductors.

Page 161: PTS (Conductor Design and installation manual for offshore platform)

5. TECHNICAL ASPECTS OF THE SIX METHODS OF INSTALLATION OF 26" x ½"CONDUCTORS AND 20" CASING

1. MANTOREK - DRILLING TENDER AND DERRICK EQUIPMENT SET

A. Mantorek drive 26" x ½" conductor to target penetration

(a) Limited to using Shell owned Delmag D22 diesel hammer. (39,700 ft/lbs strikingenergy, 42-60 blows per minute) or the Brown and Root Vulcan 200C steam hammer(50,200 ft/lbs striking energy, differential action, 98 blows per minute normal speed)with reduced steam pressure and hence reduced blows per minute and greatlyreduced efficiency.

(b) The blowcount of the D22 or 200C hammer on 26" x ½" conductor has to be carefullylimited to avoid damaging the toe of the conductor. The low maximum blowcounttogether with the frequency halts in driving required for greasing the diesel hammersresult in a high probability of freezing up of the conductor before reaching targetpenetration.

(c) It is essential that Mantorek successfully drives the first conductor to targetpenetration before attempting to drive further conductors.

B. Mantorek jet/drive 26" x ½" conductor to target penetration.

(a) An "airlift" will be necessary to assist with removal of the plug materials during jetting.

(b) The use of a "flexible" jetting string which can be lowered into and out of theconductor by the Mantorek crane should reduce jetting times.

C. Mantorek drill hole and drive 26" x ½" conductor to target penetration

(a) The Mantorek has the basic equipment for drilling in piles - a Bowen Power Sub (ahydraulic powered pipe rotating device capable of producing up to 26 000 ft/lbs oftorque, the power sub is attached to the top of the drill string) a swivel, a basic 5" drillstring, bumper sub and drill collars. More equipment and design effort will be neededto make the drilling- operation by the Mantorek successful and efficient.

D. Drilling tender and derrick equipment set - set 20" casing inside 26" x ½" conductor

a) Before the rig begins drilling out the conductors to set 20" casing, the conductorsshould be driven to an acceptable hammer blowcount/penetration (by Mantorek) suchthat the conductor can support the weight of the 20" surface casing during cementingwithout the possibility of the conductor settling, end also to minimise the possibility ofcratering around the conductor in the event of drilling through a shallow gas pocketbefore setting the first casing string.

Page 162: PTS (Conductor Design and installation manual for offshore platform)

(b) Extreme care should be taken when drilling from the toe of the conductor down pastthe jacket piles to avoid washout around the piles. A pilot hole is usually drilled tocasing target penetration at a drilling speed of about 1 foot per minute and a pumprate of about 300 gallons per minute. The hole is then "opened" with the pilot bit anda hole opener in the string. Under certain circumstances it may be possible to drill asingle stage hole or it may be necessary to drill the hole in 3 stages.

2. MANTOREK - DRILLING TENDER AND DERRICK EQUIPMENT SET

A. Mantorek drive 26" x ½" conductor to acceptable blowcount/penetration

(a) The Mantorek will be limited to using the Delmag D22 or Vulcan 2000 hammer withthe same limitations as given in 1A above.

(b) Neither jetting nor drilling will be necessary since it is accepted that when using thismethod the conductor will only be driven to resistance and then 20" surface casingset in all the conductors by the drilling tender and derrick equipment set.

B. Drilling tender and derrick equipment set - set 20" casing inside 26" x ½" conductor in everywell.

See lD above.

3. DRILLING TENDER AND DERRICK EQUIPMENT SET

A Drilling tender and derrick equipment set - drill/drive 26" x ½" conductors to target penetration

(a) The drilling rig is limited to using the Delmag D22 hammer on 26" x ½" conductors.

(b) The rig will be limited to using 40 feet addons due to the limited headroom below the"A" door of the derrick.

(c) The performances of a drilling tender and D.E.S drilling/driving conductors in two platforms are given below:

NOTE : Times include time required for skidding derrick equipment set between wells etc.

Page 163: PTS (Conductor Design and installation manual for offshore platform)

B. Drilling tender and derrick equipment set - set 20" casing inside 26" x ½" conductor

(a) The conductors will have been stabbed to a penetration of about 100 feet by theMantorek . In the event of the rig not being able to drill/drive the conductors to targetpenetration, the rig will have to drive each conductor to an acceptable blowcount/penetration before setting 20" surface casing.

C. The following table gives a list of tender platforms installed to-date with information aboutwhether conductors were successfully drilled/driven or whether 20" casing was set.

4 MENDU AND WORKOVER RIG - DRILLING TENDER AND DERRICK EQUIPMENT SET

A. Mendu and workover rig drill/drive 26" x ½" conductor to target penetration

(a) The packaged workover rig proposal includes a 27 ½ inch rotary drive, hence itshould be possible to drill and drive 26 inch diameter conductors.

(b) The workover rig will become available about mid 1973.

(c) The workover rig will be required for 4 months for offshore workovers and for 3months for onshore workovers during the next 2 years, thereafter it is anticipated thatthis rig will be used continuously throughout the year. Hence, scheduling of theMendu and the workover rig for conductor driving could be difficult if not impossible.

(d) It is anticipated that a special crow would be assigned to rig-up work anddrilling/driving of conductors. After initial training of crews with the packagedworkover rig it is anticipated that times for drilling and driving conductors will be aboutthe same as those for the rigs (or marginally better).

Page 164: PTS (Conductor Design and installation manual for offshore platform)

B. Drilling tender and derrick equipment set - set 20" casing inside 26" x ½" conductor

(a) 20" casing is set in the first well of each tender platform for protection against theposssibility of shallow gas. If Mendu and the workover rig were used to set the 20"casing it would be necessary for the Mendu to carry out a full scale drilling operationwith adequate equipment to deal with a potential gas problem when setting this initialcasing. Hence, the Mendu and workever rig will not be used for setting 20" casing.

(b) The Mendu and workover rig will have to drive the conductors to an acceptableblowcount/penetration before the drilling tender and derrick equipment set - set 20"casing.

5. MENDU AND DERRICK EQUIPMENT SET - DRILLING TENDER AND DERRICK

EQUIPMENT SET

A. Mendu and derrick equipment set drill/drive conductors to target penetration

(a) This will necessitate the derrick equipment set being fully rigged and operationalearlier than normal.

(b) It is anticipated that a special crew would be assigned for derrick equipment set rig-upwork and drilling/driving of conductors. After initial training of crews with the derrickequipment set it is anticipated that times for drilling and driving conductors will beabout the same as these for the rigs (or marginally better).

B. Drilling tender and derrick equipment set - set 20" casing inside 26" x ½" conductor

(a) The Mendu and the DES cannot set 20" casing inside the 26" conductors for thesame reasons as given in 4.B above.

(b) The Mendu and the DES will have to drive the conductors to an acceptableblowcount/penetration before the drilling tender and DES set 20" casing,

6. ATLAS - DRILLING TENDER AND DERRICK EQUIPMENT SET

A. Atlas drive 26" x ½" conductor to target penetration

(a) Similar to Montorek drive conductors to target penetration.

B. Atlas jet/drive 26" x ½" conductor to target penetration

(a) Similar to Montorek jet/drive conductors to target penetration.

C. Atlas drill hole and drive 26" x ½" conductor to target penetration

(a) Atlas is equipment with basic drilling equipment. The drilling power units is of therotary table type, hence weather downtime should be less than with the Bowen PowerSub. It is considered however, that for drilling in 26" x ½" conductor virtually all thepoints mentioned for the Mantorek drilling and driving will apply to the Atlas.

Page 165: PTS (Conductor Design and installation manual for offshore platform)

6 TECHNICAL ASPECTS OF THE SIX METHODS OF INSTALLATION OF 30" x 1"CONDUCTORS AND 20" CASING

1. MANTOREK - DRILLING TENDER AND DERRICK EQUIPMENT SET

(A) Mantorek drive 30" X 1" conductors to target penetration

(a) Tender platform jacket piles are composite 30" tubulars inside 33" tubular legs. If30" x 1" conductors with 1¼" driving shoes are used on the platform, it should bepossible to obtain at least the same penetration with the conductors as that of thejacket piles, then it is estimated that further jetting and./ or driving has a reasonableprobability (see decision trees) of achieving target penetration (assumed to be 20 feetbelow the toe of the deepest jacket pile).

(B) Mantorek jet/drive 30" x 1" conductor to target penetration

(a) An "airlift" will be necessary to assist with removal of the plug materials during jetting.

(b) The use of a "flexible" jetting string which can be lowered into and out of theconductor by the Mantorek crane should reduce jetting times.

(C) Mantorek drill/drive 30" x 1" conductor to target penetration

(a) Refer to Mantorek drill/drive 26" x ½" conductor

(D) Drilling tender and derrick equipment set - set 20" casing inside 30" x 1" conductor

(a) Before the rig begin drilling out the conductors to set 20" casing, the conductorsshould be driven to an acceptable hammer blowcount/penetration.

(b) The times to set 20 inch casing inside 30" conductors should not vary greatly fromthose to set 20" easing inside 26" conductor.

2. MANTOREK - DRILLING TENDER AND DERRICK EQUIPMENT SET

(A) Mantorek drive 30" x 1" conductor to acceptable blowcount/penetration

See 1(A)(a)

(B) Drilling tender and derrick equipment set - set 20" casing in every well

See 1 (D) (b)

3. DRILLING TENDER AND DERRICK EQUIPMENT SET

(A) Drilling tender and derrick equipment set drill/drive 30" x 1" Conductors to target penetration

(a) The drilling tenders JUMBO, NICKLE and PIERCE have derrick equipment sets with

37½" diameter rotary tables, hence they can pass 30" x 1" conductors through the

table without having to remove the rotary drive.

Page 166: PTS (Conductor Design and installation manual for offshore platform)

(b) The Shell derrick equipment set rotary tales, however, cannotaccommodate 30" x 1" conductors for drilling/driving operation it will necessitateremoval of the table when adding on and driving the conductor and replacement ofthe table for drilling or alternatively the purchase of new rotary tables (costs aboutB$110,000)

(c) The drilling rig will be limited to using the Shell D44 and/or the M40 dieselhammers. These hammers may present problems of conductor freeze-up duringfrequent hammer servicing.

(B) Drilling tender and derrick equipment set - set 20" casing inside 30" x 1" conductor.

(a) The times to set 20 inch casing inside 30" conductor should not vary greatly fromthose to set 20" casing inside 26" conductor.

4. MENDU AND WORKOVER RIG - DRILLING TENDER AND DERRICK EQUIPMENT SET

(A) Mendu and workover rig drill/drive 30" x 1" conductors to target penetration

(a) The packaged workover rig proposal for a 27½ inch rotary drive would have to bealtered to a 37½ inch rotary drive.

(b) The rig will be limited to using the Shell D44 and/or the M40 hammers. Thesehammers may present problems of conductor freeze-up during frequent hammerservicing.

(c) Scheduling of the Mendu and rig could be difficult due to the well repair programme.

(B) Drilling tender and derrick equipment set - set 20" casing inside 30" x 1" conductor

(a) Mendu and workover rig would firstly drive conductors to acceptableblowcount/penetration.

(b) Casing setting times would be as in 3 (B) (a) above.

5 MENDU AND DERRICK EQUIPMENT SET - DRILLING TENDER AND DERRICKEQUIPMENT SET

(A) Mendu and Derrick equipment set drill/drive 30" x 1" conductors to target penetration.

(a) Require derrick equipment set being fully rigged and operational earlier than normal.

(b) The Mendu and DES will be limited to using the Shell D44 and or the M40 hammers.

(c) The Shell derrick equipment set rotary tables would have to be changed from27 ½" to 37½" diameter.

(B) Drilling tender and derrick equipment set -set 20" casing inside 30" x 1" conductors.

Page 167: PTS (Conductor Design and installation manual for offshore platform)

6. ATLAS - DRILLING TENDER AND DERRICK EQUIPMENT SET

(A) Atlas drive 30" x 1" conductors to target penetration.

Similar to Mantorek drive 30" x 1" conductors to target penetration.

(B) Atlas drive/jet 30" x 1" conductors to target penetration.

Similar to Mantorek drive/jet 30" x 1" conductors to target penetration.

(C) Atlas drill/drive 30" x 1" conductors to target penetration.

Similar to Mantorek drill/drive 30" x 1" conductors to target penetration.

(D) Drilling tender and derrick equipment set - set 20" casing inside 30" x 1" conductor.

Similar to 1.D (b) above.

Page 168: PTS (Conductor Design and installation manual for offshore platform)

7. FINANCIAL AND PROBABILITY STUDY OF THE SIX METHODS OF INSTALLATION OF26" x ½" AND 30" x 1" CONDUCTORS AND 20" CASING

The fig (1) gives the layout of a 6 pile jacket - tender assisted drilling platform for 10 wells Afinancial and probability study was made into two typical platforms - case (A) - a tender platform in 120feet water depth (see fig 2 for assumed pile, conductor and casing penetrations) and case (B) - atender platform in 205 feet water depth (see fig. 3 for assumed pile, conductor and casingpenetrations).

The six methods of installation of 26" x ½" and 30" x 1" conductors in case (A) and case (B) aredisplayed in decision trees in fig. 4 through 7 respectively. Typical probabilities shown on the treetogether with the costs of the various methods of installation and materials costs.

The explanation of one method is as follows:-

Drilling tender and derrick equipment set-install 20" casing and/ or conductor - case (A) (fig 4)

(a) the equipment performances (rig, derrick barge etc.) based on past performance have beenevaluate for the different method of installation of conductors. The equipment day rates andmaterial costs are given in Appendix I. The time breakdowns for operations are given inAppendices II and III.

(b) the total costs of the methods of installation including weather downtime and material costsfor each method are given for 26" x ½" and 30" x 1" conductors in Appendices II and IIIrespectively.

(c) referring to fig 4, the main method of installation by the drilling tender and derrick equipmentset is given, followed by the sequence of method which are used to ensure that in the event offailure of one methods, another method is used to completed the surface casing and/orconductor requirements on the platform.

(d) the cost of each operation as evaluated in Appendices II or III is shown on each branch of thetree.

(e) a probability is assigned to each node of the tree of success (S) and failure (F) of the methodbased upon past performances and the technical aspects of the six methods of installationgiven.

(f) hence, commencing of the outermost limb of this branch of the tree, a failure by the RIG toDRILL/DRIVE CONDUCTORS TO TARGET PENETRATION will result in the RIG DRIVECONDUCTORS TO ACCEPTABLE BLOWCOUNT/PENETRATION and then RIG SET 20"CASING, the latter 2 operations costing B$721,000.

Page 169: PTS (Conductor Design and installation manual for offshore platform)

Therefore, assuming the rig drill/drive technique to be 40% successful, the average cost ofpreparing a platform for drilling using this method will be 40% of the cost of RIG DRILL/DRIVETO TARGET PENETRATION and 60% of the cost of RIG DRIVE CONDUCTORS TOACCEPTABLE BLOWCOUNT/RESISTANCE and RIG SET 20" CASING i.e.: 40% ofB$538,000 and 60% of B$721,000 respectively which amounts to B$648,000.

(g) it can be argued that this is unrealistic for one platform, since we would not contemplatedrilling/driving say 4 conductors to target penetration and driving 6 conductors to anacceptable/penetration and setting 20" casing. However, if 5 platforms are considered, it isfeasible to drill/drive all conductors on 2 platforms to target penetration and to drive allconductors to an acceptable blowcount/penetration on the other 3 platforms and set 20"casing in all the wells on the 3 platforms..

The fig 4 through 7 give the average equipment and material costs per 10 well tender assistedplatform for installing 20" casing and/or 26" x ½" (or 30" x 1") conductors in cases (A) and (B) for the 6different methods of installation. The average drilling tender vessel hours are also given for eachmethod together with the material costs.

For convenience, the total equipment material costs are given in figs. 6 to 11 together with thematerial costs and the drilling tender hours. The. methods are rated below according to costs, no lostproduction/ income has been assigned to the drilling tender hours involved in the methods. (On theadvice of Petroleum Engineering Department)

(A) Analysis of decision tree costs for 6 methods of installation of 26" x ½" conductors.

Considering figs 8 and 10 i.e.: for 26" x ½" conductor and 20" casing used on caes A and

case B jackets, and bearing in mind that the costs given are based on assumed probabilities

and hence are not precise but indicate the order of magnitude, it can be seen that:-

(a) the installation (method 6) by Atlas -- drilling tender and derrick equipment set is the mostexpensive.

(b) the installation (method 4) by Mendu and workover rig - drilling tender and derrick equipmentset is the second most expensive.

(c) the installations methods- 1, 2 and 3 are about equally priced.

However, the method 1 - Mantorek attempt to drive, jet/drive or drill/drive conductors totarget penetration - drilling tender and derrick equipment set - set 20" casing, requires a largeamount of Mantorek time which could results in the necessity to mobilise the Atlas and hencethe cost for method 1 could increase to about the cost of method 6. Moreover, this methodwould require additional drilling equipment and further design studies.

The method 3 - drilling tender and derrick equipment set drill/ drive conductor or set 20"casing is operationally unattractive to Drilling Departments.

Page 170: PTS (Conductor Design and installation manual for offshore platform)

(d) the installation (method 5) by Mendu and Derrick equipment set-drilling tender and derrickequipment set is financially attractive but would require additional equipment and furtherdesign study. This method could also present complex scheduling problems.

Therefore, the most attractive method is method 2 - MANTOREK drive 26" x ½" conductors toacceptable blowcount/penetration, DRILLING TENDER and DERRICK EQUIPMENT SET -set 20" casing in every well and it is recommended that this method is adopted as soon aspossible.

(B) Analysis of decision tree costs for 6 methods of installation of 30" x 1" conductor.

Considering fig. 9 and 11, i.e.: for 30" x 1" conductor and 20" casing used on case A and caseB jackets, it can be seen that:-

(a) methods 1 to 6 inclusive for 30" x 1" conductor are less expensive than method 6 for 26" x ½"conductor, but are more expensive than methods 1 to 5 for 26" x ½" conductor.

Hence, the recommendation given in (A) above about method 2 is still applicable.

Page 171: PTS (Conductor Design and installation manual for offshore platform)
Page 172: PTS (Conductor Design and installation manual for offshore platform)
Page 173: PTS (Conductor Design and installation manual for offshore platform)
Page 174: PTS (Conductor Design and installation manual for offshore platform)
Page 175: PTS (Conductor Design and installation manual for offshore platform)

8. EFFECT ON TENDER PLATFORM AND JACKET DESIGN AND CONSTRUCTION OFREPLACING 26" X ½" CONDUCTOR BY 30" x 1" CONDUCTOR

1. The wave forces (inertia and drag) are greater on a 30 inch conductor than on a 26 inchconductor. However it is considered, that the increased stiffness and strength of the largerconductor will result in little or no additional loading being transferred to the jacket and piles.

2. To date, decks have been ordered abroad and have arrived in a fully fabricated condition, inthe near future Brown and Root Contractor will fabricate decks from basic structural membersat the Labuan construction yard. Hence, slight modifications to conductor guides in the jacketand deck and deck beam layout will result only in drawing office modifications and minorchanges in fabrication costs.

3. Under certain circumstances e.g.; deep water and poor soil conditions, the initial lengths ofconductor have to be supported by the jacket top bracing until they are added onto and drivento a sufficient penetration to enable the soil to support them. When this circumstances areanticipated, it will be necessary to strengthen the jacket top bracing.

Page 176: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX I

FINANCIAL ASSUMPTIONS AND EQUIPMENT PERFORMANCES FOR INSTALLATION OF 26"½" AND 30" x 1" CONDUCTOR AND 20" CASING

(A) The following equipment rates and material costs have been used in the financial analysis

(a) Mantorek day rate (24 hours) - 23,800 B$

This is the full spread rate for the Brown and Root barge including derrick barge, anchor tug,contractor's transportation barge and tug, contract divers, Shell barges, supply andgeneral purpose boats, Shell helicopter and contract inspection.

(b) Atlas (or similar) day rate (24 hours) - 64,000 B$

This is the full spread rate similar to that for the Mantorek and also including part mobilisationand dermobilisation costs.

(c) Drilling tender and derrick equipment set day rate (24 hours) -29,000 B$

This rate is obtained by taking the average of the SSB tariff rates (commencing January1972) for the drilling tenders J.W. Nickle, I.J. Pierce, Jumbo and Sidewinder and theirrespective derrick equipment sets - amounting to 25,500 B$/day. The rates for Shellstandby boat, supply and general purpose boats, additional personnel and Shellhelicopter amount to about 3,500 B$/day.

The rate of 29,000 B$/day does not allow for the increase in Sidewinder tariff rate resultingfrom her extensive refit during 1972.

(Note: SSB rates are used instead of BSP rates, since the former include anelement of depreciation and the latter do not).

(d) Engineering /Production workover barge Mendu and packaged workover rig day rate (24hours) - 16,000 B$

This rate is compounded from a rate for Mendu and a rate for the workover rig.

The Mendu rate of 9,000 B$/day is a spread rate based on the SSB tariff rates,including the derrick barge, anchor tug, standby boat and supply boat and personnel.

The packaged workever rig rate of 7,000 B$ is an estimated rate based on a capital cost of4.8 m. B$ depreciated over 5 years, an average usage of 10 months per annum and includingpersonnel, fuel and marine insurance costs.

(c) Engineering/Production workover barge Mendu and derrick equipment set day rate (24 hours)- 15,000 B$

This rate is compounded from the rate for the Mendu of 9,000 B$ and an average rate for aD.E.S. of about 4,500 B$ and personnel costs etc.

Page 177: PTS (Conductor Design and installation manual for offshore platform)

(f) 26" x ½" conductor x 40' joint - 1,510 B$

(g) 30" x 1" conductor x 40' joint - 3,700 B$

(h) 20" casing x 40' joint - 2,046 B$

(i) cement (per bag of 42.5 kilos) - 6.7 B$

(B) The following assumptions have been used in the financial analysis:-

(a) The tender platform pile penetrations are given in fig. 2 and 3 for the tender platforms in 120feet and 205 feet water depth respectively. The pile penetrations are based upon soilconditions experienced at West Lutong and South-West Ampa for case (A) -the tender platformin 120 feet water depth and at Fairley and Baram for case (B) - the tender platform in 205 feetwater depth.

(b) Conductor penetrations and casing setting depths are also given in figs. 2 and 3. The 20"surface casing is usually set at a depth of 50 to 100 feet below the toe of the deepest pile of thetender platform. However, for this study the casing setting depth has been assumed to beidentical to the conductor target penetration, that is, 20 feet below the toe of the deepest tenderplatform pile.

(c) 20" surface casing is set to a depth of 1000-1500 feet in the first well drilled on each tenderplatform for protection against the possibility of a shallow gas blowout. Hence, when it isnecessary to set 20" casing in all wells on the platform owing to the conductors not reachingtarget penetration, the costs of setting 9 casing strings only (for a 10 well platform) areassessed.

(d) Cementing of surface casing - the cost has been evaluated on the assumption that 3 times theamount of cement would be required to cement the annulus between the outside of the 20"casing and the opened hole (24" diameter) for the length of casing from setting depth tomudline. The 200% excess cement would be accounted for by possible losses to the formationetc.

(e) Mooring-up times for floating equipment - these times have not been taken into account for theMantorek or Atlas since they would already be moored up for placing the tender platform jacketand for piling etc, for the tender and derrick equipment set when the former would be mooredup for normal drilling operations, or for the Mendu end derrick equipment set when the formerwould be moored up for rigging up the derrick equipment set.

The mooring up time for the Mendu when drilling/driving conductors with the packagedworkever rig has been included in the 72 hour rigging up and 72 hour rigging down of thepackaged workover rig.

(f) Conductor stabbing, add-ons end welding - the initial lengths of conductor stabbed by theMantorek or Atlas were assumed to be 165 feet for 26" or 30" conductor.

Generally, add-on lengths were assumed to be 80 feet of 30" conductors and 60 feet of 26"conductors when added-on by Mantorek or Atlas, and 40 feet of 30" or 26"' conductors whenadded-on by the tender and derrick equipment set or Mendu and derick equipment set orMendu and packaged workover rig - the 40 feet add-on is due to the limitations of headroombelow the "A" door of the derrick.

Page 178: PTS (Conductor Design and installation manual for offshore platform)

The lifting line up and welding times for 26" x ½" conductors were assumed to be 2½" hour:per weld and for 30" x 1" conductors 4 hours per weld. It was assumed that there was nooverlap in operations e.g. welding/driving etc.

(g) Equipment operating hours -. the Mantorek, Atlas and drilling tenders are assumed to be fullymanned for 24 hours operations. The Mendu, however, is assumed to be operational for 12hours per day.

(h) Transportatin of conductors/casing - the spread rate for Mantorek and Atlas includestransportation barges and tugs. As the rates for the drilling tender and Mendu do not includetransportation ,an additional transport charge has been added.

(i) Weather downtime has been assessed at the following rate:-

Mantorek (derrick barge) - 10.0% per annum

Atlas (derrick barge) - 10.0% " "

Drilling tender and derrick equipment set - 0.5% " "

Mendu and packaged workover rig - 5.0% " "

Mendu and derrick equipment set - 0.5% " "

(j) Equipment performances - in order to make a realistic comparison of equipmentperformances, the equipment times have been estimated based on past performances of theequipment.

Page 179: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX II

COSTS OF THE SIX METHODS OF INSTALLATION AND MATERIAL COSTS OF 26" x ½"CONDUCTORS AND 20" CASING

Two typical tender assisted drilling platforms are considered:-

CASE (A) Tender platform in 120 feet water depth, jacket pile penetration 200 feet, conductorrequired target penetration of 220 feet and casing setting depth of 220 feet.

CASE (B) Tender platform in 205 feet water depth, jacket pile penetration 300 feet, conductorrequired target penetration of 320 feet and casing setting depth of 320 feet.

(Note: See Appendix I regarding comments about pile penetrations and casing settingdepths).

Page 180: PTS (Conductor Design and installation manual for offshore platform)
Page 181: PTS (Conductor Design and installation manual for offshore platform)
Page 182: PTS (Conductor Design and installation manual for offshore platform)
Page 183: PTS (Conductor Design and installation manual for offshore platform)
Page 184: PTS (Conductor Design and installation manual for offshore platform)
Page 185: PTS (Conductor Design and installation manual for offshore platform)
Page 186: PTS (Conductor Design and installation manual for offshore platform)
Page 187: PTS (Conductor Design and installation manual for offshore platform)
Page 188: PTS (Conductor Design and installation manual for offshore platform)
Page 189: PTS (Conductor Design and installation manual for offshore platform)
Page 190: PTS (Conductor Design and installation manual for offshore platform)
Page 191: PTS (Conductor Design and installation manual for offshore platform)
Page 192: PTS (Conductor Design and installation manual for offshore platform)
Page 193: PTS (Conductor Design and installation manual for offshore platform)
Page 194: PTS (Conductor Design and installation manual for offshore platform)
Page 195: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX III

COSTS OF THE SIX METHODS OF INSTALLATION AND MATERIAL COSTS OF 30" X 1"CONDUCTORS AND 20" CASING

Two typical tender assisted drilling platforms are considered:-

CASE (A) Tender platform in 120 feet water depth, jacket pile penetration 200 feet, conductorrequired target penetration of 220 feet and casing setting depth of 220 feet.

CASE (B) Tender platform in 205 feet water depth, jacket pile penetration 300 feet, conductorrequired target penetration of 320 feet and casing setting depth of 320 feet.

(Note: See Appendix I regarding comments about pile penetrations and casing settingdepths).

Page 196: PTS (Conductor Design and installation manual for offshore platform)
Page 197: PTS (Conductor Design and installation manual for offshore platform)
Page 198: PTS (Conductor Design and installation manual for offshore platform)
Page 199: PTS (Conductor Design and installation manual for offshore platform)
Page 200: PTS (Conductor Design and installation manual for offshore platform)
Page 201: PTS (Conductor Design and installation manual for offshore platform)
Page 202: PTS (Conductor Design and installation manual for offshore platform)
Page 203: PTS (Conductor Design and installation manual for offshore platform)
Page 204: PTS (Conductor Design and installation manual for offshore platform)
Page 205: PTS (Conductor Design and installation manual for offshore platform)
Page 206: PTS (Conductor Design and installation manual for offshore platform)
Page 207: PTS (Conductor Design and installation manual for offshore platform)
Page 208: PTS (Conductor Design and installation manual for offshore platform)
Page 209: PTS (Conductor Design and installation manual for offshore platform)
Page 210: PTS (Conductor Design and installation manual for offshore platform)
Page 211: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX V-2

CALCULATION OF ALLOWABLE STICK-UP HEIGHT

Page 212: PTS (Conductor Design and installation manual for offshore platform)

1 INTRODUCTION

Calculation of the allowable stick-up length for a particular pile/hammer combination involves a static

stress analysis being performed at the critical pile section (the pile section at which the maximum

stresses occur).

The stress level so determined is then related to a permissible stress level for the particular load

conditions being experienced by the pile. This process is in accordance with API recommendations

(Section 2.31(d) API RP 2A). However, for the purposes of analysis the loading may be assumed to

consist of "combined bending and axial compression", resulting in a requirement of relating

permissible stress to actual stress as illustrated by the AISC combined stress equation below:-

Values of Fb and Fa are obtainable from current standards or codes of practice (e.g. AISC Manual ofSteel Construction).

It should be noted that when the pile add-on has a variable wall thickness, it may be necessary to

check combined stresses at a number of control points along the add-on length. It must be borne in

mind that all calculation methods are based on the assumption of full fixity at top of first pile guide and

this may not always be valid.

The results of any stick-up calculation should be tempered with common sense since the deflection

under driving is not considered. No rules are at present available but deflection will affect driving

efficiency. This is particularly critical with the use of high yield steels and large batters. This matter is

subject to further study by SIPM with a view to issuing a revision of this Section containing

more firm recommendations.

Page 213: PTS (Conductor Design and installation manual for offshore platform)

2 METHODS OF COMPUTATION

Several methods have been proposed for determining allowable stick-up length with the differences

between them depending upon the validity of the assumptions made in calculating the critical bending

moment sustained by the pile. Three methods are described in this Appendix.

2.1 Vissers Method (Described in EP ...)

This method is relatively simple, consisting of a static analysis of the problem based on the

assumption that the secondary moments resulting from pile deflexions are not significant (i.e.

the pile is considered as a rigid member during moment calculation). Therefore permissible

stresses are governed by buckling and Equation (2) is used as a condition for stability.

though correct, this condition is applicable only to members where .Ff

a

a > 0.15, a situation which

may not always apply when setting a hammer.

The principal advantages of the method are that it is simple to use and that experience

indicates that it produces safe and realistic results.

2.2 BSP Method (after M. Brinded)

This method involves an iteractive approach to the problem of calculating the critical bending

moment. An initial deflection of the pile head is assumed with the appropriate causal moment

then calculated, a corresponding pile deflection is then found using the previously established

moment; the iteration is continued until an acceptable closure is achieved.

Page 214: PTS (Conductor Design and installation manual for offshore platform)

The deflexion finally calculated is doubled to account for dynamic effects during setting of the

hammer, and it is this increased deflection which is used for computing the stresses at the

critical section The stresses are considered acceptable if they are less than the yield

strength divided by 1.2.

2.3 Fugro Method (after E.P. Popov)

To overcome the difficulties in establishing the critical bending moment and hence the

maximum stress level, a third method of analysis is proposed which involves the use of an

approximate solution in the evaluation of the pile deflexion. Equation (3) is used.

Using the deflexion so calculated the maximum moment may be found and so the maximum

stress level evaluated. The standard condition for stability in Equation (1) is then applied and

an allowable add-on length estimated, thus

Page 215: PTS (Conductor Design and installation manual for offshore platform)

This method shows the same form of relationship between combined stress and stick-up as

the BSP (Brinded) method. In the same way as in the BSP (Brinded) method it is possible to

take account of some of the dynamic effects of stabbing the hammer. This may be done by

multiplying the weight of the hammer by two in equation (4) only. (Use the true weight in

equations (5) and (6).) The advantages of the method are that it is simple to use and yet

accounts for secondary bending effects.

Page 216: PTS (Conductor Design and installation manual for offshore platform)

3 SUMMARY

Three methods for estimating add-on lengths have been described and examples of the results of

using them are shown on Plate. All computations have been made for a pile of 30 in od x 1 in wt at a

batter of 1:8. The hammer is a Vulcan 030. The maximum stick-ups from each method for various

types of steel are:

Yield Strength 36 ksi 42 ksi

Method: Stick-up (ft)

Visser 100 114

BSP (Brinded) 100 110

Fugro (1) 90 100

Fugro (2) 97 107

The number in brackets after Fugro indicates the factor by which the hammer weight is multiplied inequation (4). Vissers method and Fugro (1) are based on permissible combined stresses of 0.66

yF . BSP (Brinded) and Fugro (2) use 0.83 yF

The results on Plate 1 show that for ordinary steels the differences between the results of the

methods are small and Fugro (1) appears to be the most conservative. For high yield steels Vissers

method would produce the least conservative results.

It is recommended that BSP (Brinded) method is used if the engineer has access to suitable computer

facilities. In other circumstances it is recommended that the allowable stick-up be determined by

applying the Visser, Fugro (1) and Fugro (2) methods and adopting the most conservative results.

Page 217: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 1 COMBINED COMPRESSIVE AND BENDING STRESS VS ADD-ON LENGTH

Page 218: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX V-3

TYPICAL BLOWCOUNT RECORD SHEET

FOR OFFSHORE USE TOGETHER

WITH A COMPLETED EXAMPLE FROM SBPT

Page 219: PTS (Conductor Design and installation manual for offshore platform)
Page 220: PTS (Conductor Design and installation manual for offshore platform)
Page 221: PTS (Conductor Design and installation manual for offshore platform)
Page 222: PTS (Conductor Design and installation manual for offshore platform)
Page 223: PTS (Conductor Design and installation manual for offshore platform)
Page 224: PTS (Conductor Design and installation manual for offshore platform)
Page 225: PTS (Conductor Design and installation manual for offshore platform)
Page 226: PTS (Conductor Design and installation manual for offshore platform)
Page 227: PTS (Conductor Design and installation manual for offshore platform)
Page 228: PTS (Conductor Design and installation manual for offshore platform)
Page 229: PTS (Conductor Design and installation manual for offshore platform)
Page 230: PTS (Conductor Design and installation manual for offshore platform)
Page 231: PTS (Conductor Design and installation manual for offshore platform)
Page 232: PTS (Conductor Design and installation manual for offshore platform)

CONTENTS

1 INTRODUCTION

2 TYPES OF MEASUREMENT

Hammer Efficiency Measurements

Stress and Acceleration Measurements

Background to the use of the measurements

Scope of offshore and onshore interpretation

3 THE BENEFITS OF INSTRUMENTATION

Guidance during pile installation

Providing information on piles as driven

Providing information relevant to subsequent installation of other platforms

Long term benefits

REFERENCES

Page 233: PTS (Conductor Design and installation manual for offshore platform)

1. INTRODUCTION

1.1 This Appendix sets out the potential advantages of making measurements on piles and

hammers to supplement high quality driving records made during pile installation.

1.2 Section 2 of this Appendix describes the recording and instrumentation procedures and

provides background data on the analytical techniques. Section 3 discusses the potential

uses and benefits of instrumentation.

1.3 Some group companies have either used instrumentation on projects or felt

instrumentation, if available) would have assisted them. Shell Expro installed

strain gauges on some of the piles at Brent 'A' and on the basis of the stress-time

measurements obtained information of overall hammer efficiency. SBPT used strain

gauges and accelerometers on a conductor pile at Maui A to obtain a better

understanding of driving behaviour and to monitor hammer performance. SOC have felt

that the premature refusal of some piles and conductors may have been due to hammers

operating inefficiently. However, without suitable instrumentation they had no way of

proving their suspicions.

Page 234: PTS (Conductor Design and installation manual for offshore platform)

2 TYPES OF MEASUREMENT

2.1 The following measurements can be made without difficulty on hammers and piles:

i) hammer efficiency

ii) stress and acceleration in followers or add-ens

On a research type of project, it is possible to make additional measurements on the

length of pile embedded in the soil, these are:

iii) stress and acceleration at various levels on the pile

iv) total stress measurements of the soil against the pile wall

v) pore water pressure measurements along the pile

vi) continuous monitoring of the plug level.

It is not recommended that measurements of the type listed in items (iii) to (vi) should be

made on routine projects. Such instrumentation requires structural modifications to any

pile on which it is placed. For this reason it is not described in this Appendix but full

details may be found in Ref. 1.

Hammer Efficiency Measurements

2.2 For hydraulic hammers instrumentations to measure performance is already built-in. To

date diesel hammers have proved impossible to instrument. Past experience on site has

shown the inadequacy of visual observations and high speed photography as a means of

assessing the performance of steam hammers. The importance whilst the particular pile

is being driven has led to the development ram velocity measuring devices for steam

hammers.

2.3 One such device for steam hammers involves mounting a small optical sensor and light

source on the cross head of the hammer using a support bracket. This is done on deck

and does not interfere with installation procedure. At the same time a small vane, the

only moving component, is mounted at the head of the hammer control bar. Immediately

prior to the ram striking the cushion the vane crosses the optical beam. The time for

which the beam is broken is measured and from the dimensions of the vane, the velocity

of the vane (and hence ram) is computed. Knowing the mass of the ram, its kinetic

energy and hence the hammer efficiency is determined.

Page 235: PTS (Conductor Design and installation manual for offshore platform)

2.4 This equipment can be mounted on the hammers at the outset of the installation period

and it can be used intermittently or continuously. In the unlikely event of a breakdown

(such as due to cable fracture) driving is not interrupted for repair. A new cable can be

easily fitted at the next driving interruption which may occur for hammer or chaser

changes or when making an add-on.

Stress and Acceleration Measurements

2.5 It is relatively easy to measure both stress and acceleration as functions of time at a

suitable point in the follower or pile. The results can be used to calculate.

(a) the total dynamic resistance (SRI))

(b) the distribution of the resistance

(c) the total energy entering the follower

(d) the influence of gravity connectors

The theoretical basis of such calculations are outlined in paras. 2.8 to 2.12.

Background to the use of the measurements

2.6 When a pile is driven into the soil the soil/pile interface is subjected to a failure condition

for each blow that achieves permanent set of the pile. It is apparent that this dynamic

condition is, in some way, related to the ultimate capacity that the pile would have if it

were tested immediately after the blow.

2.7 Considerable research has been carried out on relating the dynamic and static

conditions and on measuring the dynamic resistance (Refs. 2 & 3). The contributions by

the Goble group in Case Western University, Cleveland, Ohio and by TNO in Delft have

been substantiated by well documented full scale load tests. A combined plot of their

results is shown on Plate 1.

Page 236: PTS (Conductor Design and installation manual for offshore platform)

2.8 The passage down the pile of the stress wave generated by the hammer is resisted by

any external frictional or bearing forces and is also greatly influenced by discontinuities

in the pile. At any point in the pile material the stress wave generates acceleration,

velocity and displacement, and each of these are basic but inter-related parameters.

The accurate measurement of the stress, together with any one of the remaining three,

uniquely defines the wave motion. Discontinuities and external forces generate reflected

waves which return to the point of measurement after periods of time which are linear

functions of their distances from the point.

2.9 Wave theory indicates that force, and hence stress, are related to velocity by an

impedance function, see equation in Section 3. Thus measurements of stress and

velocity made at a point on the pile when a compression wave passes can each be used

to compute the "force-time" relationship. For a undirectional compressive wave the two

relationships should be identical. However, velocity is a vector (has magnitude and

direction) and stress is a scaler (has magnitude only). This means that any

compressive reflections of the wave arriving back at the point of measurement are

interpreted as "force increases" by the stress readings and "force decreases" by the

velocity. Therefore, by subtracting one force time relationship from the other, the

reflecting components can be identified. Intergration allows the total dynamic resistance

of the soil to be found. This method of analysis is called the impedance method. It

should be noted that the soil is not modelled in the analyses and hence the computed

soil resistance is "dynamic" rather than "static." to obtain the static resistance use has to

be made of the results of correlative studies with pile load test.

2.10 An alternative method of analysis which assesses the static soil resistance, involves the

use of a wave equation solution in an iterative cycle. The measured force-time profile

resulting from a hammer blow can be used as the (input to) wave equation program.

The iterative solution consists of progressive variation of the properties of the known soil

profile until the measured acceleration-time function is matched.

Page 237: PTS (Conductor Design and installation manual for offshore platform)

2.11 Both methods involve assumptions on pile behaviour which have been substantiated by

static load tests on piles elsewhere. This is the same situation which applies to all

design methods such as API, but dynamic methods have the advantage of using data

relating to the particular soil profile at the pile position. The impedance method, is

relatively simple mathematically. This is the type of analysis used by TNO and in the

CASE method. Dynamic pile capacity can, if required, be assessed on a per blow basis

by this method by using a small micro-processor on site. The wave equation approach

is more complex, requiring the use of extensive computing facilities, but it does permit

more accurate modelling of the pile configuration and the soil conditions. In this type of

solution consideration has to be given to the values of such soil parameters as quake

and damping defining the stress-deformation-time behaviour of the soil/pile interface.

However the analysis is relatively insensitive to these parameters and reasonable

solutions will be obtained provided values grossly in error are not used. Ref. 4.

2.12 Present practice is to use acceleration and force measurements as the basis of this

type of dynamic interpretation. The measurements are made by means of bolt-on

sensors. Installation involves the drill and tapping of three holes approximately I in

deep and 0.25 in diameter in the wall of the follower (or pile add-on). This is naturally

done whilst the follower or add-on is idle, as is the fitting of the senors. The use of bolt-

on sensors permits quick installation and their recovery on completion for post

measurement recalibration. "Stick-on" sensors are available for situations in which

drilling holes would have a detrimental effect on the structural integrity of a pile.

2.13 The sensors are connected to the conditioning and recording equipment by means of

free hanging cables. Experience has shown that such cables do not influence the

normal installation operations and have a lower risk of suffering significant damage than

do armoured cables or telemetric systems.

Page 238: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX V-4

INSTRUMENTATION FOR CONDUCTORS, PILES AND HAMMERS

Page 239: PTS (Conductor Design and installation manual for offshore platform)

2.14 All records are. stored on magnetic tape for subsequent analysis. During driving the

force and acceleration signals are also displayed on a storage oscilloscope and

facilities can be made available to make hard copies of individual records by means of

ultra violet records. These act as a check on the overall electronics since the input

signal for these devices could be derived from that stored on magnetic tape a fraction of

a second earlier.

Scope of offshore and onshore interpretation

2.15 The possible scope of the data interpretation will be controlled by the extent of the

measurements made and piling problems en-countered. The interpretation could include

the following:

(a) Offshore

- Presentation of driving records

- Presentation of force-time and acceleration time curves for some blows

- Hammer Efficiency as defined by hammer manufacturer on a per blow basis

- Impedance type analysis of some blows can be done by use of a small computer.

The results of such analyses could include:

(1) overall efficiency of hammer

(2) distribution of soil resistance

(3) end bearing component of resistance

(4) qualitative assessment of connector influence

(b) Onshore

- Production of a conventional post installation report including hammer efficiencyeffects, set up data etc.

- Supplementing of above report by detailed analyses of selected blows using both

the impedance and the wave equation based on analytical techniques.

- Assignation of design capacities to piles. - Conclusions on the piling and installation

techniques together with recommendations for possible future operations etc.

Page 240: PTS (Conductor Design and installation manual for offshore platform)

3 THE BENEFITS OF INSTRUMENTATION

3.1 The use of pile instrumentation is more likely to be justified

(a) in conditions in which hard driving is expected

(b) on the initial platform of a multi platform field development

(c) in "frontier areas" where there is little or no driving experience

(d) on untried hammers or on piles with new types of connectors

(e) on any very large project where potential savings on reduced installation time

or material costs for foundations may be substantial.

In the following paragraphs the benefits of instrumentation during and after driving are

described in detail.

Guidance during pile installation

3.2 In many situations piles are driven into a founding stratum, e.g. sand, hard clay or soft

rock, whose upper horizon may vary in depth over the general area. The presence of

this layer will be indicated by an increase in the blow count as the pile tip approaches

and then enters it. Since a considerable proportion of the ultimate compressive capacity

of the pile may be derived from end bearing it is reassuring to be able to prove that the

rise in blow count noted is due to the presence of the founding stratum rather than to

reduced hammer efficiency, increased cushion losses or high friction from the upper

layers. The combined use of pile and hammer instrumentation can establish the actual

situation. Shortly after completion of driving the measurements made on the pile could

enable an assessment to be made offshore of the end bearing component of the

dynamic soil resistance. This would prove whether or not the pile had penetrated into

the founding stratum.

3.3 In the event of a significantly long interuption to driving, e.g. resulting from bad weather,

set up may cause piles to refuse prematurely. In these circumstances the use of

instrumentation will contribute towards determining the pile capacity and deciding

whether it can be accepted.

Page 241: PTS (Conductor Design and installation manual for offshore platform)

The converse to this would arise if piles were to be driven to their maximum

penetration at blowcounts much lower than expected. Doubts would then be raised as

to the capacity of the piles. Re-drive tests would have to be performed after a suitable

delay to show whether or not the piles had set-up. Instrumenting the hammer and pile

will provide data before the set-up is broken. Without instrumentation it may not be

certain that the hammer has "warmed-up" and is working efficiently before the

blowcount starts decreasing.

3.4 Information on general hammer performance and in particular on cushion losses can

be obtained by comparing the energy available at the ram with that transmitted to the

follower.

Providing information on piles as driven

3.5 An assessment of the total resistance during the last few blows on a given pile will

enable a capacity predicition to be made. If this is based on redrive data or if during it

has been possible to assess set-up potential this must be at least as good as those

made on the basis of empirical design rules using "undisturbed" soil parameters from

adjacent locations, see paragraph 2.12. This would be particularly valuable in the event

of premature refusal if the tensile capacity (which can be predicted from the wave

equation type analysis of the pile measurements) governs the pile penetration. The

reassurance of another capacity assessment would also be valuable where no marked

increase in blow count is noted within the structural limit of driving range. Also revised

operational requirements sometimes result in increased platform loadings some time

after installation. If pile capacities higher than the original design capacities can be

confidently assigned future extensive foundation modifications may be avoided.

3.6 The hammer efficiency measurements allow improved back analysis of the pile driving

record to a soil resistance at the time of driving-depth profile. This provides a method

of checking the soil profile used for pile design and drivability studies.

Page 242: PTS (Conductor Design and installation manual for offshore platform)

3.7 Any measurements made before and after a reasonable delay in driving caused by

weather, mechanical breakdown etc, can be used to assess the set up behaviour. This

can be used to predict the eventual pile capacity and the likely time taken to achieve

this.

Providing information relevant to subsequent installation of other platform

3.8 The improved back analysis should allow much better predicitions to be made of the

drivability of piles on other platforms in the field. This should lead to cheaper and

quicker installation procedures than would otherwise be possible. This assumes that

soil conditions are fairly uniform over the field.

3.9 Data on hammers and on drivability will confirm suitability of the hammers used and the

general operating level of the hammers for use on future platforms.

Long term benefit

3.10 Data on hammers will eventually lead to improvements in their fatigue life, cushion

characteristics etc.

3.11 Better data for back analysis will eventually lead to a better understanding of soil

behaviour during driving and hence more accurate drivability predicitions.

3.12 The collection of basic data such as acceleration-time and stress-time can allow re-

analysis at any time in the future with the most advanced analytical tools available at

that time. This is particularly useful where jackets may be upgraded in the future to

accomodate additional facilities.

Page 243: PTS (Conductor Design and installation manual for offshore platform)

REFERENCE S

I SUTTON J.V.R. et al, " Full Scale Instrumented Pile Test in the North Sea " OTC (1979)

2 RAUSCHE, F.M. and GOBLE, G.G., "Soil Resistance Predictions from Pile Dynamics". Journal

of Soil Mechanics and Foundations Division, ASCE, September 1972.

3 Institute TNO for Building Materials and Building Structures, "A Simple Method to Determine the

Bearing Capacity of Foundation Piles". Report No. BI-78-2/64.1.2005, January 1978.

4 BOWLES, JE., "Analytical and computer methods in foundation engineering", Chapter 11,

Mgraw-Hill, Inc., 1974.

PLATES

Static Pile Capacity vs SRD .. .. .. Plate No. I

Page 244: PTS (Conductor Design and installation manual for offshore platform)

FIGURE 1

Page 245: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX V-5

CURVED CONDUCTOR AND GUIDE CONSIDERATIONS

GULF OF MEXICO

PREPARED BY SHELL OIL

Page 246: PTS (Conductor Design and installation manual for offshore platform)

CURVED CONDUCTOR & GUIDE CONSIDERATIONS

GULF OF MEXICO

1. To save field erection time in stabbing curved sections we preinstall precurved lead conductorsections in the jacket while in the fabrication yard to the extent launch weight and jacketbuoyancy will allow. Precurving should be carried out on the bottom part of the conductor overa length at least equal to the design penetration to minimize loss of angle while driving theconductor. In as much as the conductor must be overbent and yield in order to permanentlycurve it, it's D/t should not exceed 1300/Fy as per API RP 2A for a compact section. Wherelead sections are preinstalled in the jacket the guides supporting these must be designed forthe weight, buoyancy, and slamming loads imposed during loadout, transport, and launch. Thepreinstalled conductor sections are tied off at the top conductor guides so as to supportconductor weight once upended. This connection and supporting braces must be designed forthe maximum hanging weight at the top prior to the conductors being self-supporting in the soil.Care should be taken when lifting conductors to cut off support lugs that conductors are notpulled back out of bottom guide. A larger than normal bell may be appropriate at the bottomguide to facilitate re-stabbing should this occur. Where lead sections are preinstalled bells arenot normally required except as noted above unless desired to facilitate installing sections inthe fabrication yard.

2. Where conductor lead sections are not preinstalled or not preinstalled all the way to the mudlineconductor guides, larger than normal guide bells may be desired based on tolerance obtainedduring bending, misalignment, etc. The guides should also be designed for the appropriateweight plus impact as the conductors are stabbed through the guides, considering themaximum expected misalignment. Our guide sleeves for curved conductors are fabricated tothe same clearance as our guide sleeves for straight conductors, i.e., 0.500 inches all around.The guides are fabricated with the sleeve and bell at the angle build-up appropriate to itsdistance relative to the tangent point of the curve. Vertical gusset plates are provided totransfer any stabbing loads and friction loads along the axis of the sleeve into the supportarrangement.

3. Straight sections are normally added onto the precurved lead sections and lowered/driven intothe soil. Permanent loads are developed inforcing these straight add-ons into the alignment ofthe guides and must be resisted by the guides and their supports. An estimate of these loadsmay be obtained using moment-distribution (Hardy Cross) or some equivalent method. Whereappropriate a component of these loads should be applied along the direction of the sleeveaxis. Inasmuch as our driving experience (soft soils) indicate blow counts the same or slightlyhigher than straight conductors there appears to be no need to include an extraordinaryfrictional driving resistance type load on the guides so long as the guides are normally designedfor a reasonable vertical load.

Page 247: PTS (Conductor Design and installation manual for offshore platform)

4. The conductor guides should of course be designed for the normal wave force loads on theconductors in addition to the deflection compatability loads noted in 3 above.

5. Likewise, the deflection on compatibility loads (moment diagram) should be considered whendesigning the conductor.

M . P. Cornell

July, 1976

Page 248: PTS (Conductor Design and installation manual for offshore platform)

REFERENCES

CURVED CONDUCTORS

1. Coz, B.E., Drive Pipe Study for Shallow Hole Directional Drilling - 1970 General Lease Sale",Shell Oil Company, Southerneastern E&P Region, Construction Division, 1970.

2. Fischer, F. J., "Driving Analysis for Initially Curved Marine Conductors", Shell DevelopmentCompany, EPR 57-70-F, October, 1970.

3. Cox, B. E., "Curved Well Conductors and Offshore Hydrocarbon Development", Shell OilCompany, Southern E&P Region, Offshore Division, Informal Contribution for Presentation atthe 1974 Group Offshore Development Conference, September, 1974.

4. Bradley, W. B., and Fontenot, J. E., "Estimate Field Wear from Lab Data", OJG, February 24,1975. Although not specifically focused toward curved conductors this article discussesprocedures for estimating field-wear rates in casing.

5. Fischer, F. J., "Driving Analysis for Initially Curved Marine Conductors", Offshore TechnologyConference Paper OTC 2309, May, 1975.

6. Cox, B. E., and Bruha, W. A., "Curved Well Conductors and Offshore Platform HydrocarbonDevelopment", Offshore Technology Conference Paper .OTC 2621, May, 1976.

7. Cornell, M. R., Curved Conductor and Guide Considerations, Gulf of Mexico; unpublished,July, 1976.

Page 249: PTS (Conductor Design and installation manual for offshore platform)

APPENDIX V-6

USE OF WAVE EQUATION FOR CURVED CONDUCTORS

Page 250: PTS (Conductor Design and installation manual for offshore platform)

ENGINEERING REPORT

CURVED CONDUCTOR DRIVABILITY

NORTH CORMORANT FIELD

U.K. SECTOR, NORTH SEA

For: SHELL U.K. EXPLORATION AND PRODUCTION

Report No: U0227/A

Page 251: PTS (Conductor Design and installation manual for offshore platform)

Shell U.K. Exploration and

Production,

Shell Centre,

London, SEl 7NA

25 th September, 1978

Attention: Dr. A. Le Messurier

Dear Sirs,

Conductor Drivability North Cormorant

We have pleasure in submitting our Engineering Report concerning the drivability of curvedconductors at North Cormorant.

Mr. F.E. Toolan and Mr. M.R. Horsnell were Project Engineer and Staff Engineer respectively for thiswork.

We trust this report fulfills your requirements. If you have any questions do not hesitate to contact us.

Yours faithfully,

FUGRO LIMITED

D.W. BIDDLE

Director

Enc.

Page 252: PTS (Conductor Design and installation manual for offshore platform)

CONTENTS

LIST OF REPORTS

SUMMARY

1. INTRODUCTION

2. SCOPE OF WORK

3. SOIL CONDITIONS

4. APPLICATION OF SHELL'S 2-D WAVE EQUATION PROGRAM TO DRIVING CONDITIONS

AT NORTH CORMORANT

5. ANALYSIS OF CURVED CONDUCTORS

6. EFFECT OF CURVATURE TOLERANCE

7. INSTALLATION OF CURVED CONDUCTORS AT NORTH CORMORANT

8. REVIEW OF ANALYSES

9. CONCLUSIONS

LIST OF REFERENCES

APPENDIX A NOTES RELATING TO THE RUNNING OF SHELL'S 2-D WAVE EQUATION

PROGRAM

i

Page 253: PTS (Conductor Design and installation manual for offshore platform)

NORTH CORMORANT PROJECT

Bl LOCATION

This report is one of a set of reports concerning fieldwork, laboratory testing and engineering studies

for the above Location.

Reports submitted to date are:-

Reference Type of Report Date Submitted

and Description

U0227 Engineering Report, 20th Mar. 1978

Curved Conductor Installation,

North Cormorant Field,

U.K. Sector, North Sea.

U0227/A Engineering Report, 25th Sept. l978

Drivability of Curved Conductor,

North Cormorant Field,

U.K. Sector, North Sea.

U0283 Site Investigation Plan and 15th May, 1978

Preliminary Engineering Study

U0283/1 Field Report, May 1978 Survey 8th June 1978

U0283/2 Laboratory Testing Report 19th Aug. 1978

U0283/3 Engineering Report to be issued

Page 254: PTS (Conductor Design and installation manual for offshore platform)

SUMMARY

It is proposed to install curved conductors from a jacket which will be placed at the North Cormorant

location in the North Sea. This report presents the results of detailed drivability studies for the 30in. x

1in. curved conductors during installation using Shell's standard drill/drive techniques.

The work described within this Report was carried out under Phase II of the project to investigate the

installation of curved conductors at North Cormorant. It should be read in conjunction with the report

covering Phase I of the project, in which the general feasibility of installing the conductors was

assessed.

The principal conclusions of this report are that driving stresses will be in the order of 38 ksi and that

lateral forces on the guides will not exceed 20 kips. Discontinuities in the conductor string due to

curvature tolerance would induce an additional lateral force on the guides which is not expected to

exceed 6 kips.

The variation in soil conditions at the location is not expected to affect the conclusions and

recommendations made within either Phase I or Phase II of this project.

Page 255: PTS (Conductor Design and installation manual for offshore platform)

1. INTRODUCTION

1.1 At the request of Shell U.K. Exploration and Production, Fugro Limited have carried out

engineering analyses concerning the drivability of curved conductors from a proposed

production platform. The platform will be sited in the North Cormorant Field of the

North Sea and will be supported on piled foundations. This Report presents the results

of the analyses.

1.2 In this Report the terms Client and Shell refer to Shell U.K. Exploration and Production

Ltd.

1.3 This project has been carried out in two phases. The first phase was concerned with

the method of installing the curved conductors at North Cormorant with

recommendations being based upon analyses of straight conductors and driving

records from previous conductor installations carried out by Shell in the North Sea. This

work has been described in Report No. U0227, "Engineering Report - Curved

Conductor Installation - North Cormorant Field - U.K. Sector, North Sea", issued to

Shell on the 20th March, 1978 (Ref. 1). The second phase of the project, as reported

here, has been concerned with more detailed analyses of the drivability characteristics

of the curved conductors.

1.4 The majority of the analyses in this Report were made prior to soils information

becoming available from the site investigation carried out by Fugro in late May 1978. It

was agreed with the Client that the same soil data as in Phase 1 should be used, i.e.

the soils information from Borehole 2, Cormorant Bl location, and that the work should

be reviewed when additional soils data became available.

Page 256: PTS (Conductor Design and installation manual for offshore platform)

1.5 This report is based upon the following information supplied by the Client:-

a) Conductor pipes of 30in. outside diameter with wall thickness of 1.Oin.

b) Sixteen curved conductors would be floated out with the steel jacket. These

conductors would have a curvature of 2.3°/l00ft from mudline (-528.2 ft) to -

150.92 ft below mean sea lavel.

Above -150.92ft the conductors would be straight. The conductor guide

frames would be positioned during fabrication of the jacket on the same

curvature of the conductor. Straight add-ons would be used during conductor

installation.

c) Driving to be carried out with either a Delmag D-55 or D-60 diesel hammer.

d) Conductor guides at the following elevations relative to mean sea level:-

Guide 1 + 85.30ft (+ 26m)

Guide 2 + 32.81ft (+ l0m)

Guide 3 - 59.06ft (- 18m)

Guide 4 -150. 92ft (- 46m)

Guide 5 -242. 78ft (- 74m)

Guide 6 -334. 65ft (-102m)

Guide 7 -426. 51ft (-130m)

Guide 8 -518. 37ft (-158m)

e) Lateral stiffness of the guide frames of 720 kips/ft.

f) Curvature tolerance of +12mm over any 16m length of conductor.

Page 257: PTS (Conductor Design and installation manual for offshore platform)

2. SCOPE OF WORK

2.1 The scope of work was initially defined in a letter headed " Proposal for Drivability

Analyses of Curved Conductor Pipes on the North Cormorant Platform, British Sector,

North Sea", dated 2nd June, 1978. The order to proceed with the study was contained

in a Variation of Contract document, ref. 77.74/012 Variation A, dated 6th June, 1978.

2.2 The scope of work was as follows:-

i) Establish that Shell's computer program for analysing the drivability of

curved conductors could adequately model the following:-

a) diesel hammer characteristics

b) transmission of stress wave along the conductor

c) the dynamic soil/pile interaction for the soil conditions at the North

Cormorant location.

ii) For a 30in. diameter by lin. wall thickness conductor, having the design

curvature specified by the Client (see section 1.5 (b) ), determine its drivability

characteristics when driven by a Delmag D-55 diesel hammer operating at 90%

efficiency.

iii) Determine lateral forces induced on the conductor guide frames and the

maximum stresses during driving with the Delmag D-60 diesel hammer for the

following cases:-

a) Conductor having design curvature at refusal conditions.

Page 258: PTS (Conductor Design and installation manual for offshore platform)

b) Conductor having design curvature down to elevation -561ft (-171m) ,i.e. 30 ft below mudline, followed by a build up in curvature of 1°/l00ft atrefusal condition.

c) As (b) but with a curvature of -2° /l00ft below -561ft.

iv) Establish the effects that kinks, in the conductor string, due to the specified

curvature tolerance, may have on the drivability characteristics of the conductor.

v) Review all work carried out during Phase 1 and 2 in the light of the soils

information obtained from North Cormorant during the site investigation carried

out by Fugro Ltd during May 1978.

2.3 All computer analyses of curved conductors were carried out by Shell using their

own program and their computer system in the Hague. Input data and technical

support for the analyses was provided by Fugro Ltd.

2.4 The Client requested that details of all software modifications, and associated

problems, should be included in this report, to assist Shell personnel with future

analyses using their program. These details are contained in an appendix to this report.

2.5 It is Fugro' s normal practice to use SI units for calculations and for presenting results.

However, for this study some data was in Imperial units, some in metric units and some

in SI. For reasons of clarity, and to be consistent with previous reports the units in which

the data was provided have been maintained in this Report.

Page 259: PTS (Conductor Design and installation manual for offshore platform)

This has resulted in a mixture of units. When the term tons, ton force or tf are used they

always refer to metric tons of l000kgf.

Useful conversion factors are :-

1 tf = 9.81 kN

10 m = 33ft

1 tf = 2.205 kips

Page 260: PTS (Conductor Design and installation manual for offshore platform)

3. SOIL CONDITIONS

3.1 The soil conditions at Cormorant El location consist principally of overconsolidated

clays. The shear strength profile is presented on Plate 1 and a plot of Plasticity Index

versus depth is shown on Plate 2.

3.2 Using the shear strength profile shown on Plate 1 and the index properties of the soil,

values for soil resistance at time of driving (SRD) had been previously obtained in

Phase 1 of this project. Originally the SRD vs. depth relationship had been presented in

terms of accumulated SRD. For reasons which will be explained later in this report,

this relationship was converted into one of unit ultimate soil resistances vs. depth. This

relationship is shown on Plate 3.

Page 261: PTS (Conductor Design and installation manual for offshore platform)

4. APPLICATION OF SHELL's 2-D WAVE EQUATION PROGRAM TO DRIVING

CONDITIONS AT NORTH CORMORANT

4.1 It was agreed between Fugro and Shell that all drivability analyses of curved

conductors would be carried out using a two dimensional wave equation program

developed within Shell by F.J. Fishcher (Ref. 2 & 3).

4.2 Fugro have had considerable experience in predicting the drivability characteristics of

piles and conductors installed at a number of North Sea locations and in the

development of specialised computer software to assist in these predictions. Based on

this experience, Fugro have found that the main factors governing the effectiveness of

any drivability program based upon wave equation theory are:-

i) The ability of the program to model the peculiarities of the hammer type (i.e.

steam, diesel or hydraulic modes of operation).

ii) The way in which the dynamic soil/pile interaction is modelled.

iii) The formulation of the difference equations arising from the partial differential

equations describing the progress of the stress wave along the length of the pile.

In developing their own drivability program "WAVEQ", Fugro have carried out numerous

back analyses based on driving records to ensure that these three items are dealt with

realistically. Thus in assessing the potential of other drivability programs it is Fugro's

practice to systematically check the way in which a program handles these three factors

and to carry out comparative analyses with "WAVEQ".

Page 262: PTS (Conductor Design and installation manual for offshore platform)

4.3 Fischer's program has been written for the analysis of steam hammers, the driving force

of which is almost entirely due to the falling ram, with a small additional force due to the

steam up-lift pressure. The driving force of the diesel hammers to be used at North

Cormorant has two components, i) the falling ram and ii) the explosive force which

occurs due to compression of gases by the falling ram. It was agreed between Fugro

and the Client that before any analyses of curved conductors was carried out it should

be ensured that the program could realistically model the driving characteristics of a

diesel hammer.

4.4 Information available from the Client regarding the method of solution incorporated

within the program did not adequately describe the method by which dynamic

soil/structure interaction was modelled. Reference was made to a "viscous damping

coefficient", but no recommendations given as to how this coefficient could be obtained

from any available soils information. It was agreed between Fugro and the Client that

before any analyses of curved conductors were carried out it should be ensured that

realistic values for this coefficient could be determined from North Cormorant soils

information.

4.5 Fugro informed the Client that in addition to ensuring that both the hammer and the

dynamic soil/ pile interaction could be adequately modelled, the formulation of the

partial differential equations describing the behaviour of the stress wave along the

length of the curved conductor should be verified. It is not within the scope of this report

to detail the derivation of these equations, however the partial differential equations

describing both one-dimensional and two-dimensional wave equation theories are

shown, for comparison, on Plate 4.

Page 263: PTS (Conductor Design and installation manual for offshore platform)

4.6 No alternative two-dimensional wave equation program was readily available which

could be used to calibrate Shell's program for the factors listed in paragraph 4.2

and the input parameters of North Cormorant. However, Fugro had already carried out

drivability analyses for straight conductors, driven by a Delmag D55 diesel hammer,

during Phase 1 of the project using their own one-dimensional wave equation program

WAVEQ. It was therefore decided to repeat these analyses using Shell's two-

dimensional wave equation program, for a 30in. diameter by 1 in. wall thickness

conductor having a curvature of 0.6 x 10 -7 degrees/ 100ft ( Λ = 1.0 -10 ), i.e. over the

length considered the conductor could be considered to be virtually straight. The

conductor make-up is shown on Plate 5.

4.7 In the analyses using Fischer's program the diesel hammer was modelled using his

"Type III" hammer. The idealization of this hammer as a spring-mass system is shown

on Plate 6. It is Fugro's standard practice to model all offshore pile driving hammers as

a two mass, one spring system. The two masses model the ram and a combined pile

cap and cap-block. The spring models the stiffness of the pile cap. For diesel

hammers a buffer force equal to the explosive force of the hammer is applied

immediately after the ram strikes the cap-block.

4.8 To adapt Fischer's "Type III" hammer to model the Delmag D55 diesel hammer as

modelled by Fugro the following hammer characteristics were used:-

Weight of ram = 12.15 kips

Weight of helmet = 3.02 kips

Steam uplift force = 562.5 kips (i.e. the explosive force of the hammer)

Velocity at impact = 25.l6ft/sec.

Page 264: PTS (Conductor Design and installation manual for offshore platform)

Spring stiffness helmet to ram(AKHR) = 1.37 x 105 kips/ft.

Coefficient of restitution helmet to ram =

(E:HR)

0.75

Spring stiffness pile to helmet (AKPH) = 1.1 x 1019 kips/ft

The effectiveness of this hammer model can be seen from the results presented on

Plate 7. This shows the stress/time history immediately beneath the hammer computed

by both Fugro's and Shell's (i.e. Fischer's) programs. The comparison was such that It

was concluded that Shell's program could be adapted to model diesel hammers.

4.9 In the analyses carried out using Shell's program the dynamic soil/pile interaction was

modelled using the same soil damping coefficients as used in Fugro' s program during

the drivability analyses of Phase 1 of this project. These were:-

Side damping coefficient (CLAY) = 0.2 sec/ft.

Soil tip damping coefficient (CLAY) = 0.0l sec/ft.

The effectiveness of these parameters in Shell's program can be seen from the

results shown on Plates 8 to 10. Plates 8 and 9 show the comparison between the

stress/time histories obtained from both Shell's and Fugro's programs for conductor

elements located at the mudline and 90ft. below the mudline. Plate 10 shows the

comparison between the blow count resistance curves obtained from the two programs.

From these results it was concluded that Shell's program could effectively model

the dynamic soil/pile interaction at the North Cormorant location.

4.10 The comparison between the stress/time histories shown on Plates 7 to 9 also show

that the transmission of the stress wave along the conductor is being modelled

realistically by Shell's program.

Page 265: PTS (Conductor Design and installation manual for offshore platform)

4.11 Following discussions between Fugro and the Client, it was agreed that the results of

the analyses detailed in this section of the report indicated that Shell's program could

adequately model straight conductors at the North Cormorant location, and that there

was no reason to doubt that it would be able to adequately model curved conductors at

the same site.

Page 266: PTS (Conductor Design and installation manual for offshore platform)

5. ANALYSIS OF CURVED CONDUCTORS

5.1 In the first set of analyses the 3Oin. diameter by 1in. wall thickness conductor was

modelled with its design curvature and a Delmag D55 diesel hammer. The conductor

make-up is shown on Plate 11. The only section of the conductor string which has an

inbuilt curvature of 2.30/l00ft. is that which will be floated out with the structure i.e.

between guide frames 4 and 8. The length of conductor above this section is

considered to be made up of sections which are initially straight and are threaded

through the guide frames. Dynamic soil/pile interaction was modelled using the

parameters described in section 4.9. The soil resistances during driving were

obtained from the relationship shown on Plate 3.

5.2 For the analysis of curved conductors an important parameter is the lateral spring

stiffness of the soil. Only realistic modelling of these springs will ensure realistic

distribution of stresses and shear forces. To obtain these values, P-Y curves were

generated for the 3Oin. diameter pile, using the methods described in Ref 4. and 5 and

are tabulated on Plate 12. These curves represent the relationship between the soil

resistance experienced by a pile (P-values) for lateral movements of the pile (Y-

values).

5.3 In general, the lateral displacements of a curved conductor during the duration of one

blow of the hammer will be relatively small. It was assumed that this displacement

would not exceed the displacements at which peak soil resistances would occur. Using

this assumption, values for lateral spring stiffnesses were obtained from the slope of

the curve between zero and peak resistances. The relationship between lateral spring

stiffness and depth is shown on Plate 13.

Page 267: PTS (Conductor Design and installation manual for offshore platform)

5.4 The results of the drivability analyses are shown on Plate 14. This shows the

resulting drivability curve and compares it with the drivability curve of similar straight

conductors analysed in Phase 1 of this project. It can be seen that refusal occurs at a

soil resistance of 9000kN compared with l0000kN for the straight conductor.

5.5 To investigate the effects that the curvature would have on the guide forces and

stresses in the conductor, the analysis at refusal conditions was repeated with the

Delmag D55 hammer being replaced by a Delmag D60. Although this hammer would

give easier driving the resulting stresses and shear forces would be higher.

5.6 The results of this analysis are shown on Plates 15 and 16. Plate 15 shows the

distribution of shear force between the top of the conductor and the mudline. From

these results the forces on the guide frames were obtained by equating their values

to the change in shear force occurring across each guide. As can be seen from the

results, the maximum guide-frame force was found to be 12.05 kips occurring at the

5th guide. The maximum stress during driving was found to be a compressive stress

of 38.1 ksi occurring at the fourth guide frame, i.e. the transition point between

straight and curved sections of the conductor string. The stress/time history at this

point is shown on Plate 16.

5.7 To investigate the effects of deviation of the conductor from its designed curvature,

two further analyses were carried out. In the first of these analyses, the conductor

was considered to have its design curvature down to a depth of -561ft (30ft below

mudline) followed by a build up in curvature of 1º /l00ft. down to the tip of the

conductor. The analysis was carried out at refusal conditions for a Delmag D60

hammer.

Page 268: PTS (Conductor Design and installation manual for offshore platform)

The results of this analysis are shown on Plates 17 This shows the distribution of

shear force from the top of the conductor to the mudline. From this distribution it was

found that the maximum shear force was 17.2 kips occurring at the 8th guide. The

maximum stress was found to be 38.1 ksi occurring at the fourth guide frame. The

stress-time history for this location was found to be almost identical to that shown on

Plate 16.

5.8 In the second additional analysis the conductor was modelled with its design

curvature down to -561ft. (30ft below mudline) followed by a curvature of -2° /l00ft.

Again a D60 hammer at refusal conditions was modelled. The results of this analysis

are shown on Plate 18. This shows the distribution of shear force from the top of the

conductor to the mudline. From this distribution it was found that the maximum shear

force was 14.9 kips occurring at the 8th guide. The maximum stress was found to be

38.1 ksi occurring at the fourth guide frame. The stress-time history for this location

was found to be almost identical to that shown on Plate 16.

5.9 Following discussions with the Client, it was decided that the sensitivity of guide

forces to changes in guide frame stiffness should be investigated. Two analyses

were carried out in which the original guide frame stiffness of 720 kips/ft was

increased to 7200 and 72000 kips/ft. The results of these analyses showed that the

maximum guide force for each of these values were 17.2 kips and 18.2 kips

respectively, and that in both cases they occurred at guide 8. The shear force

distribution between top of conductor and mudline for the stiffness of 72000 kips/ft is

shown on Plate 19. The distribution for 7200 kips/ft was found to be almost identical.

Page 269: PTS (Conductor Design and installation manual for offshore platform)

6. EFFECT OF CURVATURE TOLERANCES

6.1 The Client informed Fugro that the tolerance for curvature of the pre-curved conductors

to be installed in the jacket prior to float-out would be ± 12mm over a 16m length of

conductor. The effect of this tolerance is shown on Plate 20. If the welding on of the

next conductor section is such that the overall curvature of the conductor string is

maintained a "kink" in the conductor will result.

6.2 During driving, the stress-wave will pass down the conductor and, as long as any

changes in curvature are achieved by a smooth transition, the resulting guide frame

forces will be as detailed in section 5.0. However, if a "kink" or sharp change in

curvature is encountered then an additional lateral force will be generated due to the

change in direction of the stress wave passing through the conductor.

6.3 For the curvature tolerance of paragraph 1 the angle of deviation (see Plate 20) is of

the order of 0.1º The maximum effect such a kink would have would occur when it was

located at the point of maximum stress. It has been shown that the maximum stress

during driving is 38.1 ksi i.e. an axial compressive force of 3473 kips for a 30in.

diameter by 1in. wall thickness conductor. The additional lateral force will be given by

the relationship :-

Thus for the conductors at North Cormorant one would expect an additional lateral

force of 6 kips due to a kink located at the fourth guide frame. The effect of the kink at

other elevations would be less than this value.

Page 270: PTS (Conductor Design and installation manual for offshore platform)

7. INSTALLATION OF CURVED CONDUCTORS AT NORTH CORMORANT

7.1 During Phase 1 of this project, a back analysis was carried out using driving records

from conductor installations at Dunlin, where similar soil conditions to those at North

Cormorant had been encountered. From the results of this back analysis it was

apparent that the drill-drive procedure adopted at Dunlin generally inhibited the

development of skin friction along the length of the conductors, and that the

generalised relationship between soil resistance at time of driving and depth of

penetration was as shown on Plate 21. It can be seen from this relationship that

beyond the initial drive into virgin soil (necessary to form a seal to avoid washout at the

mudline) no significant build up in soil resistance occurs with depth. Where resistance

has built up, it is due to tip resistance resulting from the conductor reaching the bottom

of the predrilled pilot hole. This resistance is destroyed on drilling out the next pilot

hole.

7.2 There are two possible explanations for the fact that soil friction on the side of the

conductor does not generally increase as the conductor is driven deeper These are:-

i) The conductor driving shoe opens up the pilot hole from 26in. diameter to a

diameter greater than that of the conductor. This is shown schematically on

Plate 22. Under these conditions side friction will be low even if the conductor

is curved, because both the conductor and the oversize hole will follow

identical paths.

ii) An oversize pilot hole is produced during the drilling operation. This is shown

schematically on Plate 23.

Page 271: PTS (Conductor Design and installation manual for offshore platform)

7.3 For curved conductors, the more critical situation will occur if friction is low because the

pilot hole is drilled oversize. A straight vertical oversize hole would offer no resistance

to a straight vertical conductor, but considerable resistance to a curved conductor. The

magnitude of the resistance would increase with curvature. Driving records from Dunlin

have shown that some of the straight conductors built up curvature during installation.

In some cases this curvature was as high as 2.2º /100ft resulting in a lateral movement

at the tip of the conductor of 4ins. over a length of pilot hole of 40ft. To achieve this

deviation without any significant build up in side resistance would require an oversize

pilot hole of at least 34in. diameter.

7.4 To achieve successful installation of the conductors at North Cormorant, it should be

ensured that the amount of soil resistance mobilised by the conductor at the required

setting depth does not cause hammer refusal. Drivability analyses carried out during

Phase 1 of this project had shown that a Delmag D-55 diesel hammer operating at 90%

efficiency could only drive a 30in. diameter by 1in. wall thickness straight conductor to

the required setting depth of 120m against 20% of available side resistance. The

available side resistance in the outside skin friction during driving which would be

experienced by the conductor if it was driven into virgin soil, i.e. no pilot hole. Thus

based on the analysis of straight conductors, the limiting criteria for installation of

curved conductors at North Cormorant is that during penetration down the pilot hole no

more than 20% of the available side resistance should be mobilised.

7.5 As discussed in paragraph 7.3, records from Dunlin had shown that the pilot hole

diameter could be opened up to as much as 34in. As a conservative approach a

32in. diameter pilot hole was considered, and it was shown that for a conductor

having a curvature of 2.30/100ft entering the pilot hole with a drop-off at 0º, 1º and

2°/100ft., 20% of the available side resistance would be mobilised at depths of 45.5ft.,

37ft., and 33.5ft. respectively (see Plates 23 to 25). It was therefore recommended

during Phase 1 of this project that to ensure successful installation of the curved

conductors at North Cormorant, drives should be limited to 30ft., and that drill-outs

lengths should be more than 30ft. but less than 35ft.

7.6 Results of the drivability analysis of conductors with the design curvature being driven

by a Delmag D55 hammer at 90% efficiency showed that refusal conditions would

occur at a soil resistance of 9OOOkN (see Plate 14). This represents 18% of

Page 272: PTS (Conductor Design and installation manual for offshore platform)

7.6 Results of the drivability analysis of conductors with the design curvature being driven

by a Delmag D55 hammer at 90% efficiency showed that refusal conditions would

occur at a soil resistance of 9000kN (see Plate 14). This represents 18% of available

soil resistance at the setting depth.

7.7 Reference to the results relating mobilised soil resistance to penetration down the pilot

hole (Plates 23 to 25) showed that for a 30in. diameter conductor having a curvature of

2.30/100ft with a drop-off of 0º, 1º and 2º /100ft the corresponding depths of penetration

to mobilised 18% of available soils resistance would be 42.5ft., 35ft and 31.5ft.

7.8 It is concluded that the recommendations regarding length of drives made during

Phase I of this project are still valid, i.e. drives should be limited to 30ft. All other

recommendations made during Phase I regarding installation procedure are

unaffected by the results of the analyses carried out during Phase II

Page 273: PTS (Conductor Design and installation manual for offshore platform)

8. REVIEW OF ANALYSES

8.1 All analyses carried out to date and reported in Sections 4 to 7 of this Report have

been based on soils data from Borehole 2 carried out at Cormorant B1 location. Soils

data available from the site investigation carried out during May 1978 has shown that

the soil conditions at Boreholes 3 and 4 at the B1 location are similar to those at

Borehole B2, all three profiles being composed principally of over-consolidated clays.

8.2 Both Borehole 3 and Borehole 4 were taken to a depth of 60m. It was therefore

impossible to calculate setting depths at the locations of these boreholes or to compute

soil resistances at time of driving below 60m. However, comparison of the soil

conditions at Boreholes 2, 3 and 4, based on the results of laboratory tests and field

observations, does not indicate that the driving recommendations, put forward in the

Report covering Phase 1 of this project, should be modified. The comparison has also

shown that the driving stresses and conductor guide forces presented in this report will

be unaffected by the variation in soil conditions between the boreholes.

Page 274: PTS (Conductor Design and installation manual for offshore platform)

9. CONCLUSIONS

9.1 The principal conclusions of this report are:-

1) The maximum driving stress encountered in driving curved conductors will be

in the order of 38 ksi.

2) Lateral forces on the guide frames are not expected to exceed 20 kips. The

effect of kinks in the conductor string due to the specified curvature tolerance

will produce an additional lateral force of the order of 6 kips.

3) The driving recommendations presented in the Report covering Phase 1 of this

project are unaffected by the variation in soil conditions between Borehole 2

and Boreholes 3 and 4, i.e. drives should be limited to 30ft and drill out lengths

should exceed 30ft but be less than 35ft.

Page 275: PTS (Conductor Design and installation manual for offshore platform)

REFERENCES

1. FUGRO LTD., "Engineering Report - Curved Conductor Installation - North Cormorant Field -

U.K. Sector, North Sea", March 1978.

2. FISCHER, F.J., "Driving Analysis for Initially Curved Marine Conductors," Shell Technical

Progress Report EPR 54-70-F, October 1970.

3. FISCHER, F.J., "Driving Analysis for Initially Curved Marine Conductors," Offshore

Technology Conference, Paper 2309, 1975.

4. MATLOCK, H., "Correlations for Design of Laterally Loaded Piles in Soft Clay", Offshore

Technology Conference, Paper 1204, 1970.

5. REESE, L.C., COX, W.R., and KOOP, F.D., "Field Testing and Analysis of Laterally Loaded

Piles in Stiff Clay", Offshore Technology Conference, Paper 2312, 1975.

Page 276: PTS (Conductor Design and installation manual for offshore platform)

Appendix A

NOTES RELATING TO THE RUNNING OF SHELL's 2-D WAVE EQUATION PROGRAM

A. 1 It was found that the value for lateral stiffness of the guide frames was not set to zero prior to

reading in its value from a new data. Thus when two analyses were carried out in the same

run file it was found that the stiffness accumulated from the first to the second. The program

was modified to set the stiffness to zero at the start of each analysis.

A.2 As written the program only produced values of stress, shear and torque at specified

locations, with a limitation of only six location and only if the variable NOWRIT was set to 2.

The program was modified to output shear forces for all modes at the end of the analysis.

This information enabled guide forces to be calculated.

A.3 The "transition point" referred to in the program documentation relates to the point in the

conductor string above which the conductors were originally straight. These conductors are

then bent to the specified curvature above the transition point in a static analysis carried out

prior to the drivability analyses.

The computed stresses due to bending plus stresses due to weight of hammer form the initial

stress conditions prior to driving.

A.4 It was found that if the transition point was located at the same mode as a guide, then the

lateral stiffness of the guide would be ignored.

A.5 The program as written could not be used to model small changes in curvature, such as those

due to kinks as any section of conductor had to be composed of at least 5 segments.

Page 277: PTS (Conductor Design and installation manual for offshore platform)

A.6 To obtain sufficient data to produce a plot of soil resistance at time of driving against depth

then the soil resistances along the length of the conductor had to be factored. This was

achieved by varying the perimeter lengths which forms part of the input data.

A.7 The program as written does not output the soil total resistance corresponding to the

blowcount output at the end of the analysis.

A.8 For the soil conditions at Cormorant B1 location, the forces induced on the guides were found

not to be sensitive to changes in lateral stiffness of the soil, even when these changes were in

the order of several magnitudes.

Page 278: PTS (Conductor Design and installation manual for offshore platform)

PLATE 1 VARIATION OF MEASURED SHEAR STRENGTH WITH DEPTH

Page 279: PTS (Conductor Design and installation manual for offshore platform)

PLATE 2 VARIATION OF PLASTICITY INDEX WITH DEPTH

Page 280: PTS (Conductor Design and installation manual for offshore platform)

PLATE 3 VARIATION OF UNIT SOIL RESISTANCE AT TIME OF DRIVING WITH DEPTH

Page 281: PTS (Conductor Design and installation manual for offshore platform)

PLATE 4 GOVERNING PARTIAL DIFFERENTIAL EQUATIONS FOR

1-D AND 2-D WAVE EQUATION THEORY

Page 282: PTS (Conductor Design and installation manual for offshore platform)

PLATE 5 CONDUCTOR MAKE-UP STRAIGHT CONDUCTORS

Page 283: PTS (Conductor Design and installation manual for offshore platform)

PLATE 6 HAMMER IDEALIZATION

Page 284: PTS (Conductor Design and installation manual for offshore platform)

PLATE 7

Page 285: PTS (Conductor Design and installation manual for offshore platform)

PLATE 8

Page 286: PTS (Conductor Design and installation manual for offshore platform)

PLATE 9

Page 287: PTS (Conductor Design and installation manual for offshore platform)

PLATE 10 SOIL RESISTANCE AT TIME OF DRIVING VS BLOW COUNT

Page 288: PTS (Conductor Design and installation manual for offshore platform)

PLATE 11 CONDUCTOR MAKE-UP FOR CURVED CONDUCTORS

Page 289: PTS (Conductor Design and installation manual for offshore platform)

PLATE 12 P-Y DATA FOR 30 INCH DIAMETER CONDUCTOR

Page 290: PTS (Conductor Design and installation manual for offshore platform)

PLATE 13 VARIATION OF LATERAL SOIL STIFFNESS WITH DEPTH

Page 291: PTS (Conductor Design and installation manual for offshore platform)

PLATE 14 SOIL RESISTANCE AT TIME OF DRIVING VS BLOWCOUNT

Page 292: PTS (Conductor Design and installation manual for offshore platform)

PLATE 15

Page 293: PTS (Conductor Design and installation manual for offshore platform)

PLATE 16

Page 294: PTS (Conductor Design and installation manual for offshore platform)

PLATE 17

Page 295: PTS (Conductor Design and installation manual for offshore platform)

PLATE 18

Page 296: PTS (Conductor Design and installation manual for offshore platform)

PLATE 19

Page 297: PTS (Conductor Design and installation manual for offshore platform)

PLATE 20 FORMATION OF 'KINK' IN CONDUCTOR STRING DUE TO CURVATURE TOLERANCE

Page 298: PTS (Conductor Design and installation manual for offshore platform)

PLATE 21 SOIL RESISTANCE DURING GENERALISED DRILL-DRIVE SEQUENCE

Page 299: PTS (Conductor Design and installation manual for offshore platform)

PLATE 22 MECHANISM DUE TO CONDUCTORS PRODUCING OVERSIZE PILOT HOLE

Page 300: PTS (Conductor Design and installation manual for offshore platform)

PLATE 23 MECHANISM DUE TO DRILLING OVERSIZE PILOT HOLE

Page 301: PTS (Conductor Design and installation manual for offshore platform)

PLATE 24 MOBILISED SRD VS DEPTH OF PENETRATION FOR VARIOUS DIAMETER PILOT

HOLES WITH 0º DROP-OFF

Page 302: PTS (Conductor Design and installation manual for offshore platform)

PLATE 25 MOBILISED SRD VS DEPTH OF PENETRATION FOR VARIOUS DIAMETER PILOT

HOLES WITH 1º DROP-OFF

Page 303: PTS (Conductor Design and installation manual for offshore platform)

PLATE 26 MOBILISED SRD VS DEPTH OF PENETRATION FOR VARIOUS DIAMETER PILOT

HOLES WITH 2º DROP-OFF