PSB DUMP REPLACEMENT: STRATEGY & STATUS LIU-PSB Meeting 90 A. Sarrió, F. Loprete, A....

17
PSB DUMP REPLACEMENT: STRATEGY & STATUS LIU-PSB Meeting 90 A. Sarrió, F. Loprete, A. Perillo-Marcone 22 th November 2012 LIU-PSB

description

BTM- BHZ 10 BTY-BVT 101 EQUIPMENT TO BE DISMANTLED DUMP

Transcript of PSB DUMP REPLACEMENT: STRATEGY & STATUS LIU-PSB Meeting 90 A. Sarrió, F. Loprete, A....

PSB DUMP REPLACEMENT: STRATEGY & STATUS

LIU-PSB Meeting 90A. Sarrió, F. Loprete, A. Perillo-Marcone

22th November 2012

LIU-PSB

Pump BT-VPI23A

Pump BT-VPI23A

passage

BT-BHZ 10

BT-BHZ 10BTM-

BHZ 10 BTM-BHZ 10BTY-BVT

101

EQUIPMENT TO BE DISMANTLED DUMP

EQUIPMENT TO BE DISMANTLED

Elements to be disposed of and replacedEquipment to be temporarily dismantled

STRATEGY: STEPS

‘Plug’ against

radiation

STRATEGY: STEPS

Blocking system

‘Plug’ against

radiation

Clamping tool

Clamping system to pull the old beam pipe + dump core

STRATEGY: STEPS

Saw Container dump

Container beam pipe

Frame and adjustable support for

winch

Blocking system

‘Plug’ against

radiation

Clamping tool

System to cut the beam pipe

System to pull the beam pipe-dump core assembly: winch

The necessary equipment will be brought through the shaft by crane Length: 2.6m to 2.9m

Width: 1.5mSWL PR: 10t

BACK-UP

Most outer shielding block must be blocked

Shielded container for dump core

Lifting support

Adjustable height table