PS3: Protection & Control of Series Compensated Networks
description
Transcript of PS3: Protection & Control of Series Compensated Networks
![Page 1: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/1.jpg)
1
Australia
PS3: Protection & Control of Series Compensated Networks
Q8 b) What are the requirements of utilities in terms of certification tests for relays and/or protection systems before applying these to
series compensated lines?
![Page 2: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/2.jpg)
2
Australia
Electricity Supply Network
![Page 3: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/3.jpg)
3
Australia
Loy Yang
Red Cliffs
Kerang
Horsham
Portland
Bendigo
Ballarat
Wodonga Shepparton
Glenrowan
Hazelwood/Morwell
Mount Beauty
MelbourneMetro
Terang
Dederang
Yallourn
DartmouthMcKay Creek/West Kiewa
Eildon
Anglesea
Moorabool
GeelongPt. Henry
500 kV
330 kV
220 kV
275 kV
SP AusNet Network
• 1998
• 330KV
• Double Circuit
• 225km
![Page 4: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/4.jpg)
4
Australia
Project ObjectivesSM
TS
DDTS
No 1
line
No 2
line
Compensation: 50 % Compensation: 50 %
Transfer Capability restored to 1500 MW, Transfer Capability restored to 1500 MW, 36% improvement 36% improvement
Total project cost $A13.5 M Total project cost $A13.5 M
Completion period 14 monthsCompletion period 14 months
![Page 5: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/5.jpg)
5
Australia
Capacitor Arrangement
DDTSSMTS
Bypass Circuit Breaker
Spark Gap
MOV
DischargeReactor
![Page 6: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/6.jpg)
6
Australia
Distance Relay Problems
• Distorted Distance Measurement• Incorrect Directionality (Voltage & Current inversions)
• Transient over- and under-reach ( Sub- sychronous Transient Oscillations)
• Nonlinear & solid by-passing of capacitors initiate transient changes of :– Voltage magnitude and polarity– Impedance measured
![Page 7: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/7.jpg)
7
Australia
Incorrect Reach
AB
E
D
E
C
Line # 2
Line # 1
Line # 3
![Page 8: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/8.jpg)
8
Australia
Fault Simulations
![Page 9: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/9.jpg)
9
Australia
![Page 10: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/10.jpg)
10
Australia
Internal Fault
static
First cycleSecond cycleThird cycle
R
jX
dynamic
Reverse (blocking)
Z
Forward (operating) reach
SMTS, No 1 (Faulty) Line Relay, Fault on No 1 line, MOV, no Gap
![Page 11: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/11.jpg)
11
Australia
External Fault
First cycleSecond cycleThird cycle
R
jX
dynamic
Reverse (blocking)
Z
static
Forward (operating) reach
SMTS, No 2 (Healthy) Line Relay, Fault on No 1 line, MOV, no gap
![Page 12: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/12.jpg)
12
Australia
Relay Selection
• 2 x Distance + existing Power Line Carrierreliable Under/over reach transmission time 30ms
• 1 x Current Diff + new μWave Radiomany faults faster than distance schemes signal fading
![Page 13: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/13.jpg)
13
Australia
Operating Times
0
10
20
30
40
50
60
SMTS Loc 1 Loc 2 Loc 3 Loc 5 DDTS
X SEL/S
X SEL/D
X LFCB/S
X LFCB/D
Y ALPS/S
Y ALPS/D
1 2 3 5
![Page 14: PS3: Protection & Control of Series Compensated Networks](https://reader036.fdocuments.us/reader036/viewer/2022062802/56814548550346895db21763/html5/thumbnails/14.jpg)
14
Australia
Summary
• Transient fault studies essential for SC Lines
– Difficulty to gather data.
• Automatic Test Equipment extremely useful design
tool
• Derived from paper:“Fault simulation studies for protection of series compensated lines”
– Adam Klebanowski, GPU PowerNet, Victoria, Australia– Asia Pacific Regional ProTest (DOBLE) User Group Meeting, Melbourne,
Australia, 1999– [email protected]