Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 –...

126
Prototype Field Tests. Test Results D6.2 Programme FP7 Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution level) Public Date of delivery May 31 st , 2013 Report number D6.2 Status and Version V 1.0 Number of pages 123 WP/Task related WP6 T6.3 WP/Task responsible KEMA / EDF-SA, Enel Distr., Iberdrola Author(s) Mathieu Caujolle, Luc Glorieux, Philippe Eyrolles, Julien Le Baut, Radouane Irhly, François-Xavier Toledo, Regine Belhomme, Francesco Naso, Olena Morozova, Giovanni Valtorta, Dominic Ectors, Pieter Kropman, Jitske Burger, Jan Maarten van der Valk, Ignacio Delgado, Roberto González Partner(s) Contributing EDF-SA, Enel Distribuzione, VITO, KEMA, Iberdrola Distribución. Document ID ADD-WP6-T6.3_Iberdrola_D6.2 Prototype Field Tests. Test Results ADD-WP6-T6.3_Iberdrola_D6.2 Prototype Field Tests. Test Results_v1.0.pdf proof

Transcript of Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 –...

Page 1: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests. Test Results

D6.2

Programme FP7 – Cooperation / Energy

Grant agreement number 207643

Project acronym ADDRESS

Type (distribution level) Public

Date of delivery May 31st, 2013

Report number D6.2

Status and Version V 1.0

Number of pages 123

WP/Task related WP6 – T6.3

WP/Task responsible KEMA / EDF-SA, Enel Distr., Iberdrola

Author(s)

Mathieu Caujolle, Luc Glorieux, Philippe Eyrolles, Julien

Le Baut, Radouane Irhly, François-Xavier Toledo, Regine

Belhomme, Francesco Naso, Olena Morozova, Giovanni

Valtorta, Dominic Ectors, Pieter Kropman, Jitske Burger,

Jan Maarten van der Valk, Ignacio Delgado, Roberto

González

Partner(s) Contributing EDF-SA, Enel Distribuzione, VITO, KEMA, Iberdrola

Distribución.

Document ID ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests.

Test Results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests.

Test Results_v1.0.pdf

proof

Page 2: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 2 of 126

Executive Summary

The figure one gives an overview of the ADDRESS project where the new functionalities that should

be implemented between the players involved in the Network System are depicted. During the project,

three field tests have been carried out in order to test and assess all these new functionalities: Spain,

Italy and France.

The Spanish field test is dedicated to the validation of the downstream part of the ADDRESS chain,

from aggregation platform to controllable appliances at consumers’ premises. The Italian test is

dedicated to the validation of the upstream part of the ADDRESS chain, from AD buyers to

aggregation platform, with a focus on DSO and grid operation on a large MV network, and to the effect

of Active Demand (AD) visible at HV level and the French site focuses on the validation of the whole

ADDRESS “chain”: from AD buyers to controllable appliances at consumers’ premises but on a

smaller scale, with several tens of consumers and with one MV feeder and several LV networks.

Pla

ye

rs o

r fu

nc

tio

ns

of

the

ele

ctr

icit

y

sy

ste

m

Aggregation platform

EB

Meter or equivalent

Washing machines

AC

Electric heating

Water heaters

Smart plugs

Maybe other

controlled usages

Retailer Other non

controlled usages Balancing

Responsible Party

Producer

Ma

rke

t, c

on

tra

cts

or

dir

ect

bila

tera

l re

latio

nsh

ips

Consumers

DSO

TSO

Italian Field Test

Spanish Field Test

French Field Test

Figure 1. Field tests at a glance.

This document is intended to provide a description of the results reached in the field test carried out in

three sites with the aim of validating the ADDRESS concepts and based on the different test cases

defined in previous Deliverables (Deliverable 6.1) [1]. In the following Deliverables (Deliverable 6.3

and Deliverable 6.4) [12], [13] the assessment and effectiveness of these results are presented

regarding the different objectives defined at the beginning of the ADDRESS project. The following

figure depicts this relationship.

D6.1 (Public) D6.2 (Public) D6.3 (Confidential) D6.4 (Confidential)

Field Tests scripts and description

Technical results of field tests

Assessment of field tests results+ KemaValidation

Evaluation of the effectiveness of the ADDRESS concepts

Figure 2. Relationship between Field Tests Deliverables

Page 3: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 3 of 126

Spanish Field Test

The location of the Spanish field test site is the city of Castellón de la Plana, a Mediterranean city

where Iberdrola is the main retail and distribution company, with more than 100.000 points of supply,

600 secondary substations and 7 primary substations. For this test site, Iberdrola recruited 263

consumers.

Six test cases have been carried out, one test case for each specific aspect of the ADDRESS chain to

be tested:

- Test case 1: Functionality of the Aggregator ToolBox. The focus is on the validation of the

functionality of the Aggregator Toolbox (ATB). The input to the ATB is the power to be increased

or reduced, the time and the duration of the signal; the output is the signals to send to each

Energy Box (EBox).

- Test case 2: Functionality of the EBox. The focus is on the analysis of the behaviour of the EBox

when Aggregator’s signal is received, how it is interpreted and which are the signals sent to the

smart plugs and smart loads.

- Test case 3: Functionality of the smart devices. The objective of this test is the analysis of the

communications between the EBox and the smart devices based on the output from the EBox

algorithm.

- Test Case 4: Global analysis. In these tests, the consumers’ response is analyzed from

Aggregator point of view. The objective of these tests is the assessment of the demand side

management and behaviour from all the consumers.

- Test Case 5: Consumers’ behaviour according to incentives. In these tests, the objective is to

analyze how the consumers’ behaviour varies for varying incentives.

- Test Case 6: Consumers’ behaviour according to duration. These tests have an objective similar

to the above set 5: to analyze the response of the consumers with respect to the duration of

price&volume signal.

Italian field test

The Italian test site is Carpinone (Molise Region, Centre of Italy), where there is a MV network with

several MV generation sources. In addition, the grid has over capacity which enables tests to be

performed without endangering the quality and availability of supply. A storage system is installed to

emulate demand increase by charging the battery and demand decrease by discharging the battery.

Tests developed to validate Italian field test have been grouped into four categories:

- Test case 1: The DSO as the AD product validator. In the test, the DSO receives AD bid

proposals large enough to push the network to some limit; so proposals have to be curtailed by

the DSO validation algorithms, and the curtailed bids should to be published in the MVCC

interface. Then, the curtailed AD products are be activated through emulation (by means of the

storage system or by modifying load/generation on the network and the real network operation will

be observed)

- Test case 2: The DSO as the buyer of AD products. In this case, a network constraint is simulated

by changing the thermal limit of a MV cable in the network under the test. The real network

operation that will be observed will have to comply with the DSO forecast.

Page 4: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 4 of 126

- Test case 3: limitation of the power flow rising to the transmission network. Localized AD products

to limit the power flow towards the transmission system. In this test, the AD contribution of specific

load areas are programmed within the day-ahead market.

- Test case 4: MVCC algorithms reaction to network changes.

French field test

This field tests took place on two islands (Houat & Hoëdic) where about 30 households were involved

with some of them acting as a reference (not participating in active demand process). These islands

are connected to the main land by one MV underwater cable. Distribution is done via 8 MV/LV

transformers.

In the French field tests different scenarios have been carried out to assess all the implemented

technology. Nearly all of them concern the complete ADDRESS architecture. The objectives of these

scenarios are mainly the following:

Assess the technical feasibility of the complete implemented ADDRESS system and

evaluate its performance on real field data.

Assess how Active Demand can meet the needs of the electricity system players using

bilateral contracts (SRP and/or CRP) or market offers. The provision of AD services was based on

the simulation of possible problems or needs identified by electricity system players (DSO, TSO,

BRP…) or by other players (retailer, RES producers – PV in our case…). The AD services such as

power reserve for imbalance management, load shaping (load increase or decrease) for technical

or economical optimizations, voltage control and power control to relief overloads or network

congestions were considered.

Simulate the market interactions of aggregation entities and other electricity system

players and assess the potential impact of AD on the prices of an electricity market.

Analyze the impact on the network of the delivered AD volumes. The effects of the AD product

volumes forecasted and submitted by the aggregation entity are compared with the actual ones

resulting from the load variations observed on the field.

Study the response of the consumer portfolio to the incentive signals defined by the

aggregation entities and sent to the Energy Boxes. This study performed on both local (consumer)

and global (cluster of consumers) levels allowed us to verify if, how and under which

conditions the initial AD need was fulfilled. The forecasted behaviours of the consumer

appliances and of the global cluster are compared to the ones measured on the field.

Finally, consumers’ acceptance and commitment were also assessed but this topic is out of the

scope of this deliverable. In this respect, the studies carried out and the result obtained are

described in ADDRESS Deliverable D5.2 [7].

The results of the three field tests are described in the present deliverable. Their main conclusions are

presented at the end of this report. Assessment and evaluation of all the tests are presented in the

Deliverable 6.3 [12].

Page 5: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 5 of 126

Table of contents

Executive Summary ........................................................................................... 2

Table of contents ................................................................................................ 5

List of figures ...................................................................................................... 6

List of tables ....................................................................................................... 9

1. Introduction ................................................................................................ 10

1.1. Scope of the document ................................................................................................ 10 1.2. Structure of the document ........................................................................................... 10 1.3. Notations, abbreviations and acronyms..................................................................... 10 1.4. Acknowledgements ...................................................................................................... 11

2. Prototype Field Tests. ................................................................................ 13

2.1. Introduction ................................................................................................................... 13

3. Spain ........................................................................................................... 14

3.1. Description of the test .................................................................................................. 14 3.1.1. Players involved and architecture of the system ....................................................... 14 3.1.2. Equipment installed .................................................................................................... 15 3.1.3. Exchanged messages between actors ...................................................................... 16

3.2. Results ........................................................................................................................... 17 3.2.1. Assessment of the ADDRESS technology ................................................................ 17 3.2.2. Problems encountered ............................................................................................... 38

4. Italy .............................................................................................................. 43

4.1. Description of the test .................................................................................................. 43 4.1.1. Location ...................................................................................................................... 43 4.1.2. Players involved ......................................................................................................... 44 4.1.3. Architecture of the system ......................................................................................... 45 4.1.4. Equipment installed .................................................................................................... 46 4.1.5. Exchanged messages between players .................................................................... 49

4.2. Results ........................................................................................................................... 49 4.2.1. Assessment of the ADDRESS technology ................................................................ 49

5. France ......................................................................................................... 63

5.1. Description of the test .................................................................................................. 63 5.1.1. Location ...................................................................................................................... 64 5.1.2. Players involved ......................................................................................................... 65 5.1.3. Architecture of the System ......................................................................................... 65 5.1.4. Equipment installed .................................................................................................... 66 5.1.5. Test conditions ........................................................................................................... 74

5.2. Results ........................................................................................................................... 87 5.2.1. Test execution ............................................................................................................ 87 5.2.2. Assessment of the technical performance on the consumer side ............................. 88 5.2.3. Provision of AD services at a cluster level ................................................................. 94 5.2.4. Market simulator....................................................................................................... 106 5.2.5. Complete scenario execution ................................................................................... 116

6. Conclusions .............................................................................................. 122

7. References ................................................................................................ 125

7.1. Project documents ...................................................................................................... 125 7.2. External documents .................................................................................................... 125

8. Revisions .................................................................................................. 126

8.1. Revision history .......................................................................................................... 126

Page 6: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 6 of 126

List of figures

FIGURE 1. FIELD TESTS AT A GLANCE. ......................................................................................... 2

FIGURE 2. RELATIONSHIP BETWEEN FIELD TESTS DELIVERABLES ................................................ 2

FIGURE 3. CONCEPTUAL ARCHITECTURE OF THE SPANISH FIELD TEST. ....................................... 15

FIGURE 4. FULLY EQUIPPED HOME. ........................................................................................... 16

FIGURE 5. EXCHANGED MESSAGES BETWEEN PLAYERS. ............................................................ 17

FIGURE 6. METHODOLOGY FOR DAILY CLUSTERING. .................................................................. 18

FIGURE 7. CONSUMERS’ CLASSIFICATION. MAIN VARIABLES. SPRING. ......................................... 20

FIGURE 8. PROTOTYPES FOR SPRING / WORKING DAYS. ............................................................. 20

FIGURE 9. LOAD PROFILE FROM SPANISH TESTS – SPRING WORKING DAY. .............................. 22

FIGURE 10. LOAD PROFILE FROM SPANISH TESTS – SPRING HOLIDAY ....................................... 23

FIGURE 11. SPANISH FIELD TEST - RESULTS OF TEST CASE 1. ................................................... 26

FIGURE 12. POWER REDUCTION REQUEST AT 19:00, WORKING DAY – DEMAND FROM SMART

PLUGS. ........................................................................................................................... 27

FIGURE 13. POWER REDUCTION REQUEST AT 19:00, HOLIDAY – DEMAND FROM SMART PLUGS. ... 28

FIGURE 14. POWER INCREASE REQUEST AT 16:00, HOLIDAY – DEMAND FROM SMART PLUGS. ..... 28

FIGURE 15 EBOX COMPARISON - OVERRIDE MODE. ................................................................ 29

FIGURE 16. SPANISH FIELD TEST - RESULTS FOR PLUGS FOR SHIFTABLE DEVICES. ...................... 30

FIGURE 17. SPANISH FIELD TEST – RESULTS FOR INTERRUPTIBLE DEVICES................................ 31

FIGURE 18. SPANISH FIELD TEST. MAXIMUM DURATION. ............................................................. 31

FIGURE 19. SPANISH FIELD TEST - MINIMUM DISTANCE BETWEEN OFF-PERIODS. ........................ 32

FIGURE 20. SPANISH FILED TEST - NUMBER OF OFF-PERIODS. ................................................... 32

FIGURE 21. SPANISH FILED TEST – MANAGEMENT OF SMART WASHING MACHINES ....................... 33

FIGURE 22. SPANISH FILED TEST – AD TO REDUCE CONSUMPTION BY 20 KW AT 13:00 TO 14:00

THE 26TH OF JUNE (SUMMER WORKING DAY) – CLUSTER 3 SELECTED ............................... 34

FIGURE 23. SPANISH FILED TEST – AD TO REDUCE CONSUMPTION BY 20 KW AT 13:00 TO 14:00

THE 26TH OF JUNE (SUMMER WORKING DAY) – CLUSTER 3 SELECTED – NORMALIZED

CURVES .......................................................................................................................... 34

FIGURE 24. SPANISH FILED TEST – AD TO INCREASE CONSUMPTION BY 20 KW AT 22:00 THE 25TH

OF APRIL (SPRING WORKING DAY) – CLUSTER 1 SELECTED ............................................... 35

FIGURE 25. SPANISH FILED TEST – AD TO INCREASE CONSUMPTION BY 20 KW AT 22:00 THE 25TH

OF APRIL (SPRING WORKING DAY) – CLUSTER 1 SELECTED – NORMALIZED CURVES ........... 35

FIGURE 26. SPANISH FILED TEST – DAILY POWER CONSUMPTION DURING DIFFERENT DAYS WITH

THE SAME POWER REDUCTION BUT DIFFERENT INCENTIVES. .............................................. 36

FIGURE 27. SPANISH FILED TEST – DAILY POWER CONSUMPTION OF DIFFERENT DAYS WITH THE

SAME POWER INCREASE BUT DIFFERENT INCENTIVES ........................................................ 37

FIGURE 28. SPANISH FILED TEST – DAILY POWER CONSUMPTION OF DIFFERENT DAYS WITH THE

SAME SIGNAL BUT WITH DIFFERENT DURATION. ................................................................. 38

FIGURE 29. INDICATORS USED FOR TESTING COMMUNICATIONS FUNCTIONALITY .......................... 39

FIGURE 30. NUMBER OF PACKAGES OF DATA RECEIVED FROM E-BOXES EVERY DAY ................... 39

Page 7: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 7 of 126

FIGURE 31. EBOXES THAT HAVE RECEIVED SIGNAL FROM AGGREGATOR, PER MONTH. ................ 40

FIGURE 32. SMART HOUSEHOLD DEVICES KEPT INTO THE DATABASE VS. THEORETICAL ONES. ..... 40

FIGURE 33. ACTUALLY RECEIVED SLOTS VS. THEORETICAL ONES. .............................................. 41

FIGURE 34. ACTUAL RECEIVED DEVICES VS. THEORETICAL ONES. .............................................. 42

FIGURE 35. THE TEST LOCATION AND THE STORAGE SYSTEM IN ITALY. ....................................... 43

FIGURE 36. CARPINONE ELECTRIC SYSTEM LAYOUT. ................................................................. 44

FIGURE 37. FIELD TEST OVERVIEW. ......................................................................................... 45

FIGURE 38. ADMS AND MVCC ARCHITECTURE. ....................................................................... 46

FIGURE 39. EQUIPMENT AND MEASUREMENTS IN THE HV/MV SUBSTATION. ................................ 47

FIGURE 40. EQUIPMENT IN THE MV/LV SUBSTATIONS. ............................................................... 48

FIGURE 41. EQUIPMENT IN THE MV PRODUCERS’ AND CUSTOMERS’ PREMISES. .......................... 48

FIGURE 42. THE WHOLE ADDRESS CHAIN TESTED IN FRANCE .................................................. 65

FIGURE 43 - OPERATION MODE OF THE ADDRESS ARCHITECTURE CONSIDERED IN THE FRENCH

FIELD TESTS.................................................................................................................... 66

FIGURE 44. MAIN COMPONENTS OF THE FRENCH DSO PLATFORM AND INTERACTIONS WITH

EXTERNAL ACTORS. ......................................................................................................... 68

FIGURE 45. MAIN COMPONENTS OF THE FRENCH ATB SYSTEM AND INTERACTIONS WITH EXTERNAL

ACTORS. ......................................................................................................................... 69

FIGURE 46. INTERACTION OF THE ATB SYSTEM WITH THE MARKET SIMULATOR. ........................ 70

FIGURE 47. AGGREGATION OF SUPPLY BIDS .............................................................................. 71

FIGURE 48. EQUIPMENT INSTALLED AT CONSUMER’S PREMISES. ................................................ 72

FIGURE 49. HOME SIDE SYSTEM AND EBOX DATABASE. ............................................................. 74

FIGURE 50 - CLUSTERING METHODOLOGY APPLIED TO THE FRENCH FIELD TESTS ........................ 75

FIGURE 51. SPRING CONSUMPTION PROTOTYPES FOR THE 3 DAY TYPES AND THE 2 CONSUMERS

TYPES. ........................................................................................................................... 76

FIGURE 52. CONTROL SYSTEM OF THE FRENCH ELECTRICAL WATER HEATERS. ......................... 81

FIGURE 53. CONTROL SYSTEM OF ELECTRICAL WATER HEATERS WITH ADDRESS. ................... 81

FIGURE 54. ILLUSTRATION OF DIFFERENT CONSUMPTION PROFILES. ........................................... 86

FIGURE 55. DAILY EWH CONSUMPTION PROFILE USED FOR THE TESTS. ..................................... 86

FIGURE 56. INTERRUPTIBLE LOADS – PEAK-SHAVING. .............................................................. 90

FIGURE 57. INTERRUPTIBLE LOADS – LIMITED PEAK-SHAVING. ................................................. 90

FIGURE 58. SHIFTABLE LOAD – EWH. ...................................................................................... 91

FIGURE 59. SHIFTABLE LOAD – SWM ....................................................................................... 92

FIGURE 60. COMMUNICATION ERRORS OBSERVED DURING THE FRENCH FIELD TESTS. ................ 93

FIGURE 61. RATE OF SUCCESS OF COMMUNICATION BETWEEN THE EBOXES AND THE ADDRESS

CONTROL CENTER. .......................................................................................................... 94

FIGURE 62. OVERRIDE RATES OBSERVED DURING THE FRENCH FIELD TESTS. ............................. 94

FIGURE 63. MAIN STEPS OF THE METHODOLOGY USED FOR COMPUTING THE CLUSTER BASELINES.97

FIGURE 64. RAW DISTRIBUTION OF THE MEDIAN OF THE CONSUMPTION PROFILE OF THE WEATHER

SELECTED GROUPS. ........................................................................................................ 98

FIGURE 65. EXAMPLE OF OFFSET OBSERVED BETWEEN THE MEAN LOAD CURVE OF THE DAILY

Page 8: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 8 of 126

GROUP AND THE LOAD CURVE OBSERVED OVER A DAY ....................................................... 98

FIGURE 66. EXAMPLE OF CLUSTER RESPONSES TO LOAD DECREASE REQUESTS. ....................... 99

FIGURE 67. EXAMPLE OF CLUSTER RESPONSES TO LOAD INCREASE REQUESTS. ....................... 100

FIGURE 68. EVENING PEAK-SHAVING - OK – SCENARIO NO. 2 OF TABLE 21. ............................ 101

FIGURE 69. EVENING PEAK-SHAVING - FAILED – SCENARIO NO. 4 OF TABLE 21. ....................... 102

FIGURE 70. TO SHIFT NIGHT PEAK - OK – SCENARIO NO. 15 OF TABLE 21. ............................... 102

FIGURE 71. TO SHIFT CONSUMPTION DURING WIND TURBINE PRODUCTION - FAILED – SCENARIO

NO. 17 OF TABLE 21. .................................................................................................... 103

FIGURE 72. STEPS FOR RUNNING THE MARKET SIMULATOR WITH AGGREGATION ENTITY’S OFFER108

FIGURE 73. ILLUSTRATION OF THE LOAD SHAPING OF EWH CONSUMPTION FOR THE FIRST

SCENARIO. .................................................................................................................... 109

FIGURE 74. ILLUSTRATION OF THE LOAD SHAPING OF EWH CONSUMPTION FOR THE SECOND

SCENARIO. .................................................................................................................... 109

FIGURE 75. SIGNALS CHOSEN FOR FOUR LOAD AREAS. ........................................................... 114

FIGURE 76. WIND PROFILE FOR THE BRITTANY AREA CONSIDERED IN THE SCENARIO (ACTUAL

PROFILE OF MAY 7TH 2012). ......................................................................................... 116

FIGURE 77. AD VOLUME PROFILES REQUESTED ON DIFFERENT LOAD AREAS. ........................... 117

FIGURE 78. LOAD AREAS (IN RED) COMPUTED BY THE ALGORITHM BASED ON THE LV NETWORK OF

THE BRITTANY ISLANDS ................................................................................................. 117

FIGURE 79. COMPARISON OF THE LOAD FORECASTS TO THE ACHIEVED PROFILES FOR 2 LOAD

AREAS OF THE BRITTANY ISLANDS. ................................................................................ 118

FIGURE 80. COMPARISON OF THE FORECASTED AND THE ACHIEVED PV PLANT INJECTED POWERS

(HOURLY DATA) USING ACHIEVED RADIANCE INFORMATION .............................................. 118

FIGURE 81. EVOLUTION OF THE UPPER AND LOWER FLEXIBILITY LIMITS (IN KW) COMPUTED FOR

SEVERAL LOAD AREAS .................................................................................................. 118

FIGURE 82. VALIDATION RESULT OF SOME OF THE SRP PRODUCTS SUBMITTED BY THE ATB

PLATFORM .................................................................................................................... 119

FIGURE 83. INCENTIVE SIGNALS SELECTED BY THE ATB ALGORITHMS TO MEET THE SRP VOLUMES119

FIGURE 84. CLUSTER RESPONSE TO THE SUBMITTED INCENTIVE SIGNAL OBSERVED ON THE FIELD.120

FIGURE 85. IMPACT OF AD LOAD INCREASE ON THE VOLAGE AND POWER FLOW AT THE ISLAND

CONNECTION ................................................................................................................ 120

FIGURE 86. IMPACT OF AD LOAD INCREASE ON THE VOLTAGE LEVELS OF THE ISLAND MV NETWORK121

Page 9: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 9 of 126

List of tables

TABLE 1. ABBREVIATIONS ........................................................................................................ 11

TABLE 2. PEAK PERIODS .......................................................................................................... 19

TABLE 3. CONSUMER CLUSTERING FOR SPRING WORKING DAYS - MAIN INDEXES ......................... 21

TABLE 4. SPANISH FIELD TESTS - TEST CASE 1, POWER SIGNAL 20 KW. .................................... 24

TABLE 5. SPANISH FIELD TEST - TEST CASE 1, POWER SIGNAL 10 KW. ....................................... 24

TABLE 6. SPANISH FIELD TEST. TEST CASE 2. ........................................................................... 27

TABLE 7. DEVICE COMMUNICATIONS. ........................................................................................ 41

TABLE 8. CARPINONE GRID CHARACTERISTICS. ......................................................................... 43

TABLE 9. INVOLVED GENERATORS. ........................................................................................... 44

TABLE 10. FIELD TEST DEVICES INSTALLED IN THE MV NETWORK. .............................................. 47

TABLE 11. TEST1: AD VALIDATION FOR THE INTRADAY MARKET. ................................................. 51

TABLE 12. TEST1BIS: AD VALIDATION FOR THE DAY-AHEAD MARKET. ......................................... 52

TABLE 13. AD VALIDATION FOR THE DAY-HEAD MARKET. ........................................................... 53

TABLE 14. DSO AS AN AD PRODUCT BUYER. ............................................................................ 56

TABLE 15. LOCALIZED AD PRODUCTS TO LIMIT THE POWER FLOW TOWARDS THE TRANSMISSION

SYSTEM – TEST 1 ............................................................................................................ 59

TABLE 16. LOCALIZED AD PRODUCTS TO LIMIT THE POWER FLOW TOWARDS THE TRANSMISSION

SYSTEM – TEST 2. ........................................................................................................... 61

TABLE 17. MVCC ALGORITHMS REACTION TO NETWORK CHANGES ............................................ 62

TABLE 18. CONTROLLABLE LOADS CONSIDERED DURING THE FRENCH FIELD TESTS. ................... 74

TABLE 19. FRENCH FIELD TESTS – OFF-PEAK PERIODS AND PREFERRED START AND END TIMES OF

THE EWH ....................................................................................................................... 82

TABLE 20. FRENCH FIELD TESTS SCENARIOS ............................................................................. 84

TABLE 21 - TEST EXECUTION OVERVIEW ................................................................................... 88

TABLE 21. FRENCH FIELD TESTS – TEST RESULTS. .................................................................. 101

TABLE 22. MEAN ENERGY CONSUMPTION OF ADDRESS AND REFERENCE GROUPS DURING THE

PERIOD OF THE FRENCH FIELD TEST (ALL FIGURES IN KWH) ............................................. 105

TABLE 23. VARIATION OF THE OFF-PEAK CONSUMPTION RATIO IN PRESENCE OF ADDRESS

SYSTEMS ...................................................................................................................... 105

TABLE 24. TEST RESULTS FOR THE SCENARIO OF THE FEBRUARY 9TH

, 2012. ............................ 111

TABLE 25. TEST RESULTS FOR THE SCENARIO OF THE DECEMBER 25TH

, 2012. ......................... 112

TABLE 26. COMPARISON OF THE RESULTS WITH THE REAL SPOT PRICES OF THE FEBRUARY 9TH

,

2012 ............................................................................................................................ 113

TABLE 27. COMPARISON OF THE RESULTS WITH THE REAL SPOT PRICES OF THE DECEMBER 25TH

,

2012 ............................................................................................................................ 113

TABLE 28. TEST RESULTS FOR THE SCENARIO OF MAY 24TH AND 25TH, 2013 .......................... 114

TABLE 29. TEST RESULTS FOR THE SCENARIO OF DECEMBER 24TH, 2012 ................................ 115

Page 10: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 10 of 126

1. Introduction

1.1. Scope of the document

The scope of this document is to provide a description of the results reached in the three field test

carried out in the ADDRESS project: Italian, French and Spanish. The field trials have been developed

in order to validate the concepts of ADDRESS through Active Demand (AD) products activated in the

trials. The document will present the different features of the three trials and the players involved in all

of them. For each site will be depicted:

- Players involved;

- Main result from the different test cases;

1.2. Structure of the document

The document comprises the following main sections:

Section 1 is the Introduction, highlighting the scope and structure of the document;

Section 2 describes the test cases that have been carried out in the different field tests in

order to assess and validate the developments carried out in the project and implemented in

the trials. This information refer to the updated definition presented in D6.1

Section 3, 4 and 5 details the main results obtained in the three filed test sites. Main results for

the different test scripts carried out during the last months of the project;

Section 6 concludes the document and summarises the main points.

1.3. Notations, abbreviations and acronyms

2PL Two-Phase Locking

AD Active Demand

ADMS Active Demand Management System

CRP Conditional Re-profiling

DB Database

DBMS Database Management System

DER Distributed Energy Resources

DG Distributed Generation

DMS Distribution Management System

DOW Description of Work

DSE Distribution System Estimator

DSM Distribution System Management

DSO Distribution System Operator

EBox Energy Box

Page 11: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 11 of 126

EC European Commission

EU European Union

FT Flexibility Table

GF Generation Forecast

HW Hardware

Java High-level, object-oriented, cross-platform programming language

Java COM. Java Communications API

LA Load area

LF Load Forecast

MVCC Multi-version Concurrency Control

MVCC Medium Voltage Control Center

OLV Off-Line Validation

OS Operating System

PC Project Coordinator

RTU Remote Terminal Unit

RTV Real time validation

SO System Operator

SOM Self-organizing Maps

SW Software

TB Technical Board

TM Technical Manager

TSO Transmission System Operator

USB Universal Serial Bus

WP Workpackage

XML Extensible Markup Language

Zigbee A low-cost, low-power, wireless mesh networking standard.

Table 1. Abbreviations

1.4. Acknowledgements

The following table gives the names and affiliations of the project participants who contributed at

different levels to the work leading to the results described in this report. Their contributions are

gratefully acknowledged.

PARTNER Contributors

ENEL Distribuzione Francesco Naso, Olena Morozova, Giovanni Valtorta

KEMA Pieter Kropman, Jitske Burger, Jan Maarten van der Valk

EDF SA Mathieu Caujolle, Luc Glorieux, Philippe Eyrolles, Julien Le Baut,

Radouane Irhly, François-Xavier Toledo, Regine Belhomme,

Page 12: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 12 of 126

Jonathan Reynaud, Didier Roland, Yann Pollet.

VITO Dominic Ectors

Iberdrola Distribución Roberto González, Ignacio Delgado

The careful and thorough reviews made by ADDRESS TB members (Arturo Losi, Regine Belhomme

and Giovanni Valtorta) are also gratefully acknowledged. Their comments have significantly

contributed to improve the text.

Page 13: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 13 of 126

2. Prototype Field Tests.

2.1. Introduction

ADDRESS project has divided the tests to be carried out into three field test locations where all the

functionalities of the equipment developed during the previous years of the project are checked.

The test scenarios and detailed test scripts for the three sites were defined and presented in

Deliverable D6.1 “Description of test location and detailed test program for (limited) prototype field

test, simulations and hybrid tests’’. [1]

This section will try to summarize the main objectives for each site that help us to identify the results in

the following sections of the Deliverable.

- Spain: tests are dedicated to the validation of the downstream part of the ADDRESS chain, from

aggregation platform to controllable appliances. Metering and appliances equipment have been

installed at 263 customers to put under real conditions the concepts of ADDRESS at a scale in

which tangible benefits can be studied.

- Italy: field tests are dedicated to the validation of the upstream part of the ADDRESS chain, from

AD buyers to aggregation platform, with a focus on DSO and grid operation on a large MV

network. The secure and reliable operation of the distribution network has been tested taking into

account AD together with distributed generation, energy storage systems and large customers

connected at the Medium Voltage (MV) level. The AD has been emulated by means of some DG

using RES (hydro) and a storage system.

- France: The tests are carried out on two French islands in Brittany with one MV feeder and 8 LV

networks. About 30 consumers are involved in the tests. The objective is to validate the whole

ADDRESS chain from AD buyers to controllable appliances at consumers’ premises. The

capability of AD to provide services to the different electricity players is studied, as well as the

impact of AD actions on the distribution grid. In particular the combination of Active Demand in

domestic installations and a small renewable (PV) power plant has been tested.

Additionally in Spain and France different climate conditions (warm in Spain, cold in France) have

ensured different equipment and usage patterns.

Page 14: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 14 of 126

3. Spain

3.1. Description of the test

The location for the Spanish field test for ADDRESS project is the city of Castellón de la Plana, a

Mediterranean city where Iberdrola is the main retail and distribution company with more than 100.000

points of supply, 600 secondary substations and 7 primary substations.

The aim of this test is to validate the interaction between the Aggregator (the new deregulated function

and key mediator between consumers, markets and power system participants which gathers the

flexibilities of the consumers to build Active Demand (AD) services and the consumers, through the

Energy Box (EBox). The EBox manages the appliances downstream according to signals received

from the Aggregator and the user’s preferences.

The main functionalities that have been tested refer to:

- HAN Communication;

- Validation of the EBox (remote user interface, optimization algorithm, interactions) and the rest

of equipment (smart plugs, measuring device, smart washing machines, air conditioning

management system);

- Validation of external communication EBox – Aggregator;

- Validation of consumers’ experience.

For this test, Iberdrola recruited 263 consumers; they signed a contract and received an incentive for

participating in the test.

All the information regarding the electricity use and the measurements have been sent everyday to the

Aggregator’s server, where data is collected, in order to assess and analyze the consumers’ response

to the AD events. With this information and the information gathered through questionnaires and

interviews carried out during the test (at the beginning, in the middle and at the end), the consumers

have been classified into different clusters and identified with a prototype load curve.

This study has allowed to identify the acceptance or rejection of residential consumers about AD and

help for future research from different points of view: technical, sociological, and also legal, concerning

the definition of tariffs and contracts with the consumers.

3.1.1. Players involved and architecture of the system

The actors involved in the Spanish field test are:

- Aggregator

- EBoxes

- Smart plugs

- Smart washing machines

- Air conditioning management systems

Figure 3 depicts the global architecture for the Spanish field test.

Page 15: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 15 of 126

Ebox

Air cond.

system

Additional

measuring

deviceSmart

Washing

machine

Smart

Plugsx5

Aggregator

House

Official Meter

DSO

Figure 3. Conceptual architecture of the Spanish field test.

In Figure 3, blue lines represent ADDRESS information exchanged, while red lines represent “official”

information exchanged through the smart meters installed in all the houses by the Distribution

Company.

3.1.2. Equipment installed

The equipment installed is:

- 263 EBoxes (ZIV) equipped with:

• Zigbee communication with smart appliances, smart plugs and measuring device.

• GPRS communication with the Aggregator toolbox.

- 263 sets of five smart plugs (Philips and ZIV) for the connection to the mains of various

appliances: water heater, washing machine, dishwasher, dryer…

- 263 additional measuring device that will be used to communicate with the EBox

- the Official smart meter, already installed.

In some houses (full HAN consumers), the following equipment is installed:

- Smart washing machines (25) from Electrolux.

- Air conditioning management system (14) from Intesis.

A fully equipped home, with all the devices and the communication technology used, is represented in

Figure 4.

Page 16: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 16 of 126

Figure 4. Fully equipped home.

3.1.3. Exchanged messages between actors

The relationships between the actors have been tested in different test scripts, intended to assess and

evaluate all their functionalities. The communication and message exchange between the actors is

depicted in Figure 5.

Page 17: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 17 of 126

Figure 5. Exchanged messages between players.

The steps are:

1. EBox receives the AD price&volume signal the day ahead from the Aggregator

2. EBox runs the optimization algorithm for the manageable loads based on the AD signal

3. EBox sends the orders to smart plugs and smart appliances

4. During the day, if the consumer switches on a new manageable appliance, this one sends its

request to the EBox

5. In the case of point 4. above, the EBox runs again its internal algorithm

6. In the case of point 4. above, EBox sends again activation signals to appliances

7. EBox records information received from the meter during the day (5’ slots).

8. EBox records information from smart plugs and smart loads during the day (5' slots).

9. EBox sends information from the measurements and status of all the appliances in the house

at the end of the day to the Aggregator.

3.2. Results

3.2.1. Assessment of the ADDRESS technology

Before depicting the results achieved with the test cases defined in [1], the consumers’ segmentation

is shown in order to present the consumer clusters defined to classify consumers in the Aggregator

ToolBox (ATB) and to select them for the test cases.

The data collected for the study cover a year, from December 2011 until December 2012; during this

Page 18: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 18 of 126

period, the hourly energy consumption for the selected consumers has been stored.

The days have been divided based on:

- Type of day: Working day / Holiday

- Season of the year: Winter / Spring / Summer / Autumn

The analysis was carried out through SOM algorithms [2], which allow getting different prototypes for

each combination; each consumer will be classified with 8 prototypes: winter working day, winter

holiday, spring working day, etc.

Figure 6 depicts the methodology used in the analysis.

Daily Curves

Se

aso

n

Clu

ste

rin

g

Typ

e o

f d

ay

clu

ste

rin

g

Working day Holiday

Prototypes

Winter Spring Summer Autumn

Figure 6. Methodology for daily clustering.

For each study, the following quantities have been taken into account to obtain the daily prototypes:

- Hourly energy consumption: 24 energy data

- Daily level consumption: Average hourly energy consumption in the day for each load curve

- Daily peaks: A daily peak occurs in an hour if the ratio of the energy in the hour to the average

hourly energy > 1.3

- Period of the day in which the daily peak is produced: Six periods in a day have been

considered, as in Table 2.

Period Hours

Early morning 1 – 6

Breakfast 7 – 10

Morning 11 – 13

Lunch 14 – 16

Evening 17 – 20

Page 19: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 19 of 126

Night 21 – 24

Table 2. Peak periods

A set of indexes were considered to identify the groups of consumers:

- Average hourly energy consumption in a day

- Number of peaks

The number of peaks for each prototype is computed as the average value of the number of peaks per

day of all the load profiles assigned to each prototype or pattern.

- Peak pattern

The objective of this index is to numerically describe when peaks are produced. With reference to the

six periods defined in Table 2, the index is defined as a binary six-digit number, such as 000000

- Maximum hourly consumption in a day, and hour

These two indexes register the maximum hourly value of energy consumption, and the corresponding

hour of the day.

- Peak/valley ratio

This index is obtained as the quotient of maximum and minimum consumptions in a day, and gives

information about the degree of variability of consumption.

With the SOM algorithm [2], four clusters have been identified. Figure 7, Figure 8 and Table 3 depict

the results of the clustering, for spring season and working days. These images depict the different

clusters divided into neurons or the minimum logical area used for analysing the information from

consumers. [2]

Load curve classification

Peaks pattern per neuron

Page 20: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 20 of 126

Average peak hours per neuron

Average Consumption per neuron

Figure 7. Consumers’ classification. Main variables. Spring.

0

500

1000

1500

2000

2500

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Wh

Spring - working days

Prototype 1

Prototype 2

Prototype 3

Prototype 4

Figure 8. Prototypes for spring / working days.

Page 21: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 21 of 126

C1 C2 C3 C4

Number of peaks 5.59 6.50 5.17 6.15 Hourly average consumption (Wh) 453.21 720.08 246.62 830.88

Peak pattern 000111 011101 000111 000011

Max consumption 912.31 988.36 441.10 2242.01

Max consumption, hour 23 24 23 23 Min consumption 188.71 393.87 133.30 271.58

Peak/valley ratio 4.83 2.51 3.31 8.26

Number of consumers 105 20 170 5

Table 3. Consumer clustering for spring working days - Main indexes

Based on the consumer cluster identified for the four seasons and the two types of day, tests have

been carried out during the last months of the projects.

Test Case 1. Functionality of the Aggregator ToolBox

The aim of these test case is the validation of the functionality of the ATB. The input to the ATB are

the power to be increased or reduced, the time and the duration of the signal; the output are the

signals to send to each cluster. This signal sent by the Aggregator concerns duration, power

threshold, start time and incentives.

The parameters considered to study the correctness of the operation of ATB are:

- Type of day: working day / holiday

- Hour of the day: peak hour / off-peak hour

- Power demand: increase / reduction

The peak hour is the hour of the day where there is regularly a high consumption; the off-peak hour is

the moment of day where the consumption is lower than the rest hours of the day. The peak hour and

off-peak hour selected to develop this case have been selected according to the hours when peak

demand or valley demand is presented in Spain.

The consumers of the Spanish field test site have different consumption behaviour depending on the

day of the week: working day and holiday. To obtain the power demand from all consumers in a

working day, power profiles “working day” of each cluster are multiplied by the total number of

consumers belonging to each cluster; the summation of these values depicts the whole power demand

available for the ATB. The load profile for holiday is calculated taking into account the power load

demand for “holidays” from each cluster and following the same procedure as for working days. Load

profiles are shown in Figure 9 and

Page 22: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 22 of 126

0

50

100

150

200

250

300

350

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

kWh

Power demand - Spring Holidays

Prototype 4

Prototype 3

Prototype 2

Prototype 1

Figure 10.

0

50

100

150

200

250

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

kWh

Power demand - Spring Working Days

Prototype 4

Prototype 3

Prototype 2

Prototype 1

Figure 9. Load profile from Spanish tests – Spring Working Day.

Page 23: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 23 of 126

0

50

100

150

200

250

300

350

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

kWh

Power demand - Spring Holidays

Prototype 4

Prototype 3

Prototype 2

Prototype 1

Figure 10. Load profile from Spanish tests – Spring Holiday

From Figure 9, it is possible to identify the peak and off-peak hour for working day:

- Peak-hour: 10, 16 and 22

- Off-peak hour: 6 and 19

For holiday

(

0

50

100

150

200

250

300

350

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

kWh

Power demand - Spring Holidays

Prototype 4

Prototype 3

Prototype 2

Prototype 1

Figure 10), the peak and off-peak hour identified are:

- Peak-hour: 15 and 22

- Off-peak hour: 6, 13 and 19.

The Aggregator has the prototypes of each cluster; to find a solution to accomplish a request, the

Aggregator needs to know the type of day when the signal is sent; in addition, in the tests two levels of

Page 24: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 24 of 126

power1 have been considered: 20 kW and 10 kW. The following table present these use cases:

Power 20 kW

signal hour

working day holiday

Peak hour & Decrease power

10 15

22 22

Peak hour & Increase power

10 15

22 22

Off-peak hour & Increase power

6 6

19 13

Off-peak hour & Decrease power

6 6

19 13

Table 4. Spanish field tests - Test Case 1, power signal 20 kW.

Power 10 kW

signal hour

working day holiday

Peak hour & Decrease power

10 10

22 22

Peak hour & Increase power

10 10

22 22

Off-peak hour & Increase power

6 6

19 19

Off-peak hour & Decrease power

6 6

19 19

Table 5. Spanish field test - Test Case 1, power signal 10 kW.

The response from the ATB for a power demand reduction of 20 kW, start time 22h, and duration 1h is

reported in Figure 11.

Cluster 1

Duration signal: 1 h

1 According to the total number of consumers, and in order to be able to achieve the AD requirements, the ATB

has defined two power thresholds in order to increase or reduce the demand from consumers.

Page 25: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 25 of 126

Start time: 22:00

Incentive: If power

consumption in

signal time is less

than 2 kW the user

benefit is 0.01

€/kWh.

Cluster 2

Duration signal: 1 h

Start time: 22:00

Incentive: If power

consumption in

signal time is less

than 2 kW the user

benefit is 0.01

€/kWh.

Cluster 32

Duration signal: 1 h

2 In order to achieve the AD requirement, the ATB sends two signals to different clusters to reduce the demand

and another signal to increase the demand in other moment of the day to try to shift some loads for other period of time.

Page 26: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 26 of 126

Start time: 23:30

Incentive: If power

consumption in

signal time is less

than 2 kW the user

benefit is 0.01

€/kWh.

Figure 11. Spanish field test - Results of test Case 1.

Test Case 2: Functionality of the EBox

The aim of this test case is the analysis of the behavior of the EBox when Aggregator’s signal is

received, how it is interpreted by the EBox and which are the signals that the EBox sends to the smart

plugs and smart devices.

The parameters considered in the test are:

- Power demand: increase / reduction

- Number of slots of the price&volume signal:

• Two slots (one power threshold and incentive)

• Three slots (two power thresholds and incentives)

- Hour of the day: peak / off-peak

- Duration of the signal:

• Two slots: 30m / 1h / 1h30m

• Three slots: 45m

Slots refer to the power levels. If the signal has two slots, there is a unique level power and two

incentives (xx € and 0 €). Depending on the nature of the signal (reducing or increasing the demand),

the power consumption should be above or below the limit. For a signal with 3 slots, there are two

levels power and three incentives (xx €, yy € and 0 €), receiving a different incentive depending on the

level consumption: above, below or between limits.

For the significance of the test, a reasonable number of EBoxes should be studied. The number

depends on the typology of the house and the equipments installed. Additionally, as explained in the

following sections, there is a limitation regarding the communications between EBoxes and

Aggregator. This has constrained the selection of EBoxes: for carrying out the test, the best EBoxes

from communications’ point of view have been selected. For selecting the Eboxes in order to be able

to analyze its behavior according to the information received:

1. different signals were sent in a specific day

2. for this day, information from the Eboxes is received at the end of the day.

After several days, we are able to receive information from all the Eboxes.

Studied cases are the result of the combination of input parameters and signal; they are summarized

in Table 6.

Peak hour Off-peak hour

2 slots 3 slots 2 slots 3 slots

Increase power Duration 30 min

45 min 30 min

45 min 1 h 1 h

Page 27: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 27 of 126

1 h 30 1 h 30

Decrease power Duration

30 min

45 min

30 min

45 min 1 h 1 h

1 h 30 1 h 30

Table 6. Spanish Field Test. Test case 2.

Figure 12, Figure 13, and Figure 14 depict the response from the smart plugs downstream of EBoxes

which received an AD signal from the Aggregator. In the Figures, the measurements from all the smart

plugs along the day are shown.

Figure 12. Power reduction request at 19:00, working day – Demand from smart plugs.

Page 28: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 28 of 126

Figure 13. Power reduction request at 19:00, holiday – Demand from smart plugs.

Figure 14. Power increase request at 16:00, holiday – Demand from smart plugs.

Page 29: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 29 of 126

The last test carried out in this case is aimed at checking the internal algorithms of the EBox to verify

that the Ebox does not intervene when an Aggregator’s signal is received and the global override is

selected by the user. To check for this, a specific Ebox in override mode was selected and its behavior

was analyzed in comparison with other Eboxes not in override mode that had received the AD signal.

The following image depicts the behaviour from two Eboxes, one of them in override mode and the

other one not in override mode. The figure depicts the daily energy consumption from both Eboxes

(normalized consumption load curves) which have received an AD signal to reduce the demand at

12:00h during one hour. The consumer’s Ebox not in override mode tries to reduce the demand during

the first quarter of hour whereas the consumer’s Ebox in override mode does not work and

consumer’s loads are switched on during this hour.

Figure 15 Ebox comparison - OVERRIDE mode.

Test Case 3: Functionality of the smart devices

The objective of this test case is the analysis of the communications between EBox and smart devices

according to the output s from the EBox algorithm.

To verify the functionality of smart plugs and smart appliances, it is necessary to select an adequate

number of devices and to analyze their functionally in different days. The total number of smart plugs

involved in the tests is 255 divided into 125 to power shiftable loads and 130 to power interruptible

loads. For shiftable devices, the specification is:

- the next start time is scheduled to occur during the user preferred time and according to the AD

signal.

For interruptible devices, the specifications are:

- max duration of the interruption: 2 slots (30 minutes)

- minimum distance between two off-periods: 6 slots (1,5 hours)

Page 30: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 30 of 126

- max number of off-periods: 8

The following paragraphs illustrate the main results of the tests and all the comments for all these

results will be presented in Deliverable6.3 [12]

Shiftable devices

Out of all the smart plugs involved in the tests, 51% have had their next start time in the preferred time

interval (Figure 16). The rest of the smart plugs did not fulfil the user’s preferences, for the following

reasons:

- Override option is selected in the smart plug the smart plug works correctly (18%)

- No override option selected in the smart plug the smart plugs does not work correctly (31%)

Figure 16. Spanish field test - Results for plugs for shiftable devices.

Interruptible devices

The 86% of the plugs for interruptible devices did fulfil specification during all the days, the 7%

between 80% and 100%, the 1% between 50% and 80% and 6% did do well in less than 50% of the

days (Figure 17).

Page 31: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 31 of 126

Figure 17. Spanish Field Test – Results for interruptible devices.

For each single specification, the analysis shows that :

- max duration of the interruption (2 slots = 30 minutes): fulfilled by 99.81 % of the smart plugs

(Figure 18);

Figure 18. Spanish field test. Maximum duration.

- min distance between interruptions (6 slots = 1,5 hours): 94.6% of interruptible smart plugs

(Figure 19);

Page 32: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 32 of 126

Figure 19. Spanish field test - Minimum distance between off-periods.

- max number of off-periods (8): all the smart plugs have presented less or 8 off-periods during

the day (Figure 20);

Figure 20. Spanish filed test - Number of off-periods.

Page 33: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 33 of 126

Smart washing machine

In the Spanish field test there are 25 Smart Washing Machines (SWMs) installed. The behaviour of the

SWM is similar to the one of shiftable devices: its start should be scheduled during the preferred

operation interval.

To evaluate the functionality of the SWM, it was verified that the power consumption occurred within

the operation interval set by the user. The result of the analysis is shown in the Figure 21.

Figure 21. Spanish filed test – Management of smart washing machines

Test Case 4: Global analysis

For these tests, the consumers’ response is analyzed from the Aggregator’s point of view. The focus is

on the behaviour of the consumers regarding the signals received, the day of the week and the hour

and the duration of these signals, for reducing consumption in peak hours and increasing it in off-peak

hour. To this extent:

1. The Aggregator defines the requirements to increase/reduce the demand during a specific day

and hour.

2. The Aggregator runs its internal algorithm and sends AD signals (price&volume signals) to the

most suitable clusters.

3. At the end of the day, the measurements from the selected consumers (all the consumers in

the selected clusters) are assessed in order to verify if the AD requirement from Aggregator’s

has been fulfilled.

Due to the limitation in communications, the number of EBoxes that received the AD signal was lower

than expected; then, it was necessary to extrapolate the data.

Based on the total consumption data received from the EBoxes, the average power consumption was

calculated for the selected cluster(s) and compared to the one of the rest of the ADDRESS

consumers. It is also interesting to represent the normalized load curves, obtained by dividing the load

curve by the maximum value of the load, to check the overall characteristics of the power

consumption.

Page 34: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 34 of 126

Figure 22 and Figure 23 depict the results of the tests for reducing consumption. The difference

between the consumption curves during the price&volume signal period of validity is apparent.

0

20000

40000

60000

80000

100000

120000

140000

160000

180000

0:0

00

:30

1:0

01

:30

2:0

02

:30

3:0

03

:30

4:0

04

:30

5:0

05

:30

6:0

06

:30

7:0

07

:30

8:0

08

:30

9:0

09

:30

10

:00

10

:30

11

:00

11

:30

12

:00

12

:30

13

:00

13

:30

14

:00

14

:30

15

:00

15

:30

16

:00

16

:30

17

:00

17

:30

18

:00

18

:30

19

:00

19

:30

20

:00

20

:30

21

:00

21

:30

22

:00

22

:30

23

:00

23

:30

0:0

0

kWh

Reduce -Load curve

Cluster 3

Without AD Signal

Figure 22. Spanish filed test – AD to reduce consumption by 20 kW at 13:00 to 14:00 the 26th of June (Summer working day) – Cluster 3 selected

0

0,1

0,2

0,3

0,4

0,5

0,6

0,7

0,8

0,9

1

0:0

0

0:3

0

1:0

0

1:3

0

2:0

0

2:3

0

3:0

0

3:3

0

4:0

0

4:3

0

5:0

0

5:3

0

6:0

0

6:3

0

7:0

0

7:3

0

8:0

0

8:3

0

9:0

0

9:3

0

10

:00

10

:30

11

:00

11

:30

12

:00

12

:30

13

:00

13

:30

14

:00

14

:30

15

:00

15

:30

16

:00

16

:30

17

:00

17

:30

18

:00

18

:30

19

:00

19

:30

20

:00

20

:30

21

:00

21

:30

22

:00

22

:30

23

:00

23

:30

0:0

0

Reduce Demand - Power consumption Normalized

Cluster 3

Without signal

Figure 23. Spanish filed test – AD to reduce consumption by 20 kW at 13:00 to 14:00 the 26th of June (Summer working day) – Cluster 3 selected – Normalized curves

Page 35: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 35 of 126

Figure 24 and Figure 25 depict the results of the tests for increasing consumption. Also in this case,

the difference between the consumption curves during the price&volume signal period of validity is

apparent; in particular, the load curve for the selected cluster (cluster 1) shows increases during the

period of the signal while the load curve of the rest of the consumers decreases.

Figure 24. Spanish filed test – AD to increase consumption by 20 kW at 22:00 the 25th of April (Spring working day) – Cluster 1 selected

Figure 25. Spanish filed test – AD to increase consumption by 20 kW at 22:00 the 25th of April (Spring working day) – Cluster 1 selected – Normalized curves

Page 36: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 36 of 126

Test Case 5: Consumers’ behavior according to incentives

In this test case, the analysis is focused on the difference of the consumers’ behavior when they

receive a similar price&volume signal but with different incentives. Most of the parameters in these

tests have been kept constant in order to give evidence only to the influence of the incentives; they are

day of the week, hour of the day to start the price&volume signal, power thresholds, duration of the

signal.

The analysis considers the aggregated response from the consumers after they receive the

Aggregator’s signal. These signals were sent manually from the ATB so as to be able to define the

incentives to decrease/increase consumption in a working day/holiday.

To develop this test, many signals were sent to the EBoxes, for each working day and holiday. After

sending these signals, the following weeks the same signals but with different incentives were sent,

with the idea of having two or more signals that only differ in the incentive. Due to communication

problems, the number of signals sent had to be bigger than required.

In the following figures, two examples are shown to ascertain the influence of the incentives. Two daily

load curves for the same day of the week during different weeks and with different incentives are

shown. Depending on the conditions of the day, the power demanded varies greatly from one day to

another; for this reason, these curves have been normalized for an easy comparison.

The first example (Figure 26) refers to a signal sent from the Aggregator to all the consumers (4

clusters) in order to reduce the demand at 19:00 for the same day of the week in different weeks and

compare the behaviour from consumers according to the incentives proposed. It is apparent that the

curve with the highest incentive has a more pronounced power reduction than the other. In the period

when the signal is activated, the energy consumption during the day with more incentive is lower than

the day with less incentive.

Figure 26. Spanish filed test – Daily power consumption during different days with the same power reduction but different incentives.

Page 37: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 37 of 126

In the example of Figure 27, which refers to the case of an increase of consumption, it is possible to

verify that the total energy demanded during the period of the signal has actually increased, and that

the increased consumption has a direct relation with the incentive of the signal.

Figure 27. Spanish filed test – Daily Power Consumption of different days with the same power increase but different incentives

Test Case 6: Consumers’ behavior according to duration

This test case has objectives similar to the test case 5; it is intended to analyse the response of the

consumers when they receive similar price&volume signals but the duration of the signal is different.

As in test case 5, the signals are sent manually from the ATB, this time in order to be able to define

different durations. Most of the parameters have been kept constant in order to give evidence only to

the influence of the incentives; they are day of the week, hour of the day to start the price&volume

signal, power thresholds, incentives. The analysis considers the aggregated response from the

consumers after they receive the Aggregator’s signal. These signals were sent manually from the ATB

so as to be able to define the duration of the signal intended to decrease/increase consumption in a

working day/holiday.

To develop this test, many signals were sent to the EBoxes, for each working day and holiday. After

sending these signals, the following weeks the same signals but with different durations were sent,

with the idea of having two or more signals that only differ in the duration. Due to communication

problems, the number of signals sent had to be bigger than required.

In Figure 28, an example is shown to ascertain the influence of the duration. Load curves are shown

for two different days; for each day, both the power demanded (darker line) and the trend line (lighter

line) are shown; the difference between the days is the duration of the signal. The trend line allows to

Page 38: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 38 of 126

see the behavior of the curve at the time of the signal. As it can be observed, the longer the duration

of the signal the more difficult to follow the signal. The signal with a duration of 30’ allows Ebox to

follow the AD requirement in an easier way than a signal with a duration of one hour and a half.

This can be justified by the specifications of controllable devices. The specifications of the interruptible

devices don’t allow interruptions with a duration bigger than fifteen minutes; moreover, the minumum

distance between two off-periods must be bigger than 1h 30’. Therefore, it is quite difficul to be able to

reduce consumption during all the period of the signal by disconnecting all devices at same time.

Figure 28. Spanish filed test – Daily power consumption of different days with the same signal but with different duration.

3.2.2. Problems encountered

3.2.2.1 Communications

During the deployment of the test, communications has been one of the main problems. Issues with

the reception and recording of information have caused difficulties into the processes of selection and

analysis of the results. Next, some indicators will be discussed to show the functionality of

communications in the Spanish field test.

Page 39: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 39 of 126

Figure 29. Indicators used for testing communications functionality

The first indicator is the number of EBoxes that send data about what had happened in the house the

day before. The correct operation in this case would be that every EBox sends every day data

packages with information about consumption, interruptions, etc. recorded the day before. However,

information is received with some day delay, or not received at all, as it is shown in Figure 30, where

the number of EBox data received (y axis) per day (x axis) according to the day the information is

checked (see the legend).

Figure 30. Number of packages of data received from E-boxes every day

The second indicator is aimed at checking if communications between Aggregator and EBoxes work

correctly. Figure 31 shows the average value and the percentage of EBoxes that have received

Aggregator’s signal per month versus the total number of EBoxes in the database.

In this figure, the different columns depict the average values of AD signals received by the different

Eboxes based on the daily information registered from these ones and collected in the ATB. It should

be taken into account that the communication from EBoxes to ATB varied every day and additionally

not always the EBoxes were able to communicate correctly with the ATB in order to receive the AD

signal the day before.

E- boxes

Aggregator

ADDRESS_036 ADDRESS_001 ADDRESS_300 …

Smart Plugs Smart washing machine

AACC

Data Packages from E-boxes to Aggregator

Signals from Aggregator to E-boxes

Consumptions from Smart devices to E-boxes

Page 40: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 40 of 126

0

20

40

60

80

100

120

January February March April

Communications from Aggregator to E-boxes

Av. Signal Received Av. Signal no received

0,00%

10,00%

20,00%

30,00%

40,00%

50,00%

60,00%

70,00%

80,00%

90,00%

100,00%

January February March April

Communications from Aggregator to E-boxes

% Signal Received % Signal no received

Figure 31. EBoxes that have received signal from Aggregator, per month.

Next, the communications between smart household devices and the EBoxes is verified. It is checked

which is the information about the household devices per each EBox in the database. Results about

this indicator are depicted in Figure 32.

0%

20%

40%

60%

80%

100%

January February March April

Smart Devices Communication

Received devices Non received devices

Figure 32. Smart household devices kept into the database vs. theoretical ones.

The last indicator about communications functionality is the performance of communications between

smart devices (plugs, washing machine and AACC) and the EBoxes. It is measured by the number of

slots actually received by the EBox from the smart devices compared with the expected value (Figure

33). The theoretical one is the result of the product between 288 slots per day and the number of

devices installed.

Page 41: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 41 of 126

0%

20%

40%

60%

80%

100%

January February March April

Smart Devices Communication

Received slots Non received slots

Figure 33. Actually received slots vs. theoretical ones.

Table 7 proposes a comparison between the number of slots received and the number of theoretical

slots, taking into account both the number of devices received (1) (see before) and the number of

EBox received (4). In the last case we have obtained the number of theoretical slots (6) taking into

account that every house has five smart devices (5) and each device stores information every five

minutes (288 slots per day).

Month Devices

received (1)

Theoretical

slots (2)

Received

slots (3)

E-box

received (4)

Theoretical

devices (5)

Theoretical

slots (6)

January 7.663 2.206.944 677.922 2.717 13.585 3.912.480

February 10.822 3.116.736 1.012.258 3.168 15.840 4.561.920

March 9.703 2.794.464 905.988 2.983 13.325 3.837.600

Table 7. Device communications.

Page 42: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 42 of 126

0%

20%

40%

60%

80%

100%

January February March April

Smart Devices Communication

Accepted Devices Failed Devices

Figure 34. Actual received devices vs. theoretical ones.

Page 43: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 43 of 126

4. Italy

4.1. Description of the test

The main objective of Italian field test is to validate the DSO algorithms and prototypes developed

within the ADDRESS project to enable and exploit AD products visible on the MV network. In this test,

AD products were emulated by means of a storage system and by modifying load/generation of some

MV customers/producers.

4.1.1. Location

The Italian test site location is Carpinone (Molise Region, Centre of Italy), where the grid has over

capacity which enables tests to be performed without endangering the quality and availability of

supply. At the location a storage system is installed to emulate demand increase of a load area by

charging the battery and demand decrease by discharging the battery.

Figure 35. The test location and the storage system in Italy.

Some of the major characteristics of the Carpinone test location are outlined in the Table 8 and a

graphical outline of the medium voltage network is depicted in the Figure 36.

340 km MV network (300 km overhead lines)

10 MV feeders

157 MV/LV substations

17 MV consumers (total power 13,2 MW)

11 MV DGs (13,25 MW: 5 hydro, 5 PV and 1 biogas)

1 Storage system (1000 kW - 500 kWh)

8110 LV consumers

63 LV DGs (total power 467 kW)

Table 8. Carpinone grid characteristics.

Page 44: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 44 of 126

Figure 36. Carpinone electric system layout.

As depicted in Figure 36, the storage system used to emulate AD in the test is installed on the Pesche

feeder.

4.1.2. Players involved

Some MV consumers and some of the generators connected on the Carpinone HV/MV substation

were involved in the field test. In particular, these generators have provided the generation curves

utilized by the Generation Forecast algorithm and some of them have become available to disconnect

their plants as required by the Test case 3 (section 4.2.1 Assessment of the results). Some of the

major characteristics of the involved generators involved are outlined in the Table 9.

Type of generator P (kW)

Biogas 771

PV 900

Hydro 2500

Hydro 1600

Hydro 2620

Hydro 1150

Hydro 1150

PV 82

Table 9. Involved generators.

Page 45: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 45 of 126

4.1.3. Architecture of the system

The field tests executed in Carpinone by ENEL Distribuzione refer to the left side of Figure 37.

Figure 37. Field Test Overview.

The Italian tests were focused on the so-called upstream of Active Demand: the DSO and TSO part.

The scope of the field tests addressed the functional components, which are to be used by the DSO in

an active grid environment. The DSO algorithms, Medium Voltage Control Centre (MVCC) prototypes

and SCADA functionality (Figure 38) are evaluated, using the requirements and criteria that have

already been defined in the design process and have been tested during the laboratory tests.

Measurements are set-up to capture the output of the said functions. Upon completion of the test the

measurements are compared with the original requirements.

The aim of the test effort is to:

- warrant the ability to maintain a secure & reliable network management

- ensure the usability of (software) functions.

Pla

ye

rs o

r fu

nc

tio

ns

of

the

ele

ctr

icit

y

sy

ste

m

Aggregation platform

EB

Meter or equivalent

Washing machines

AC

Electric heating

Water heaters

Smart plugs

Maybe other

controlled usages

Retailer Other non

controlled usages Balancing

Responsible Party

Producer

Ma

rke

t, c

on

tra

cts

or

dir

ect

bila

tera

l re

latio

nsh

ips

Consumers

DSO

TSO

Italian Field Test

Spanish Field Test

French Field Test

Page 46: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 46 of 126

Figure 38. ADMS and MVCC architecture.

4.1.4. Equipment installed

The MVCC developed in the ADDRESS project was installed on the AD Server component that runs

on a computer server that resides in the Campobasso Control Centre (see Figure 39). The SCADA

system of Campobasso Control Centre provides I/O data to support the DSO functionality.

Page 47: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 47 of 126

Figure 39. Equipment and measurements in the HV/MV substation.

Also the Remote Terminal Units (RTUs) and active/reactive power measurement devices were

installed in the HV/MV and in some MV/LV substation, in order to provide real measurements for

Distributor State Estimation. The RTU installed in the HV/LV substation transmits measurements to

SCADA via IP network. In the Table 10 devices installed in the MV network and their functions are

described.

SCADA System implementing

MVCC functions

Network Control Centre

(Campobasso)

DSO functions to enable and

exploit AD

TPT2000 (RTU) HV/MV “Carpinone” substation and

“Carovilli” remote MV busbar

Real time network

measurements for DSO

algorithms

RTU, P&Q

measurement

devices

MV/LV substations &

MV producers and consumers

premises

Table 11. Field test devices installed in the MV network.

The installation of the measurement devices in the MV/HV substation (storage included) and in the MV

producers and customer’s premises are illustrated in the Figure 40 and Figure 41.

Page 48: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 48 of 126

Figure 40. Equipment in the MV/LV substations.

Figure 41. Equipment in the MV producers’ and customers’ premises.

Due to the installed devices it was possible to collect the following measurements (in addition to

measures of current and voltage on the top of the MV lines, transmitted to the SCADA through

GSM/GPRS in real time):

- P, Q in 10 MV/LV substations (MV/LV transformer load)

- P, Q in 4 MV Producers premises

- P, Q in 2 MV Consumers premises (MV load)

- P, Q in 1 Storage system

Page 49: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 49 of 126

4.1.5. Exchanged messages between players

Most of the message exchanged between the MVCC and the external actors involved in the

architecture were simulated. In particular, the interactions with the market and the aggregators were

simulated by manually creating a total supply bid file (with the AD products characteristics offered to

AD market sent to SO for validation) and uploading it in the MVCC interface. The communication with

the producers involved in the tests took place via e-mail when it was necessary to require production

curves or some plants disconnection for the test execution.

4.2. Results

4.2.1. Assessment of the ADDRESS technology

Test Case 1: the DSO as an AD product validator

In this case the DSO receives bids of AD products, which aggregators traded in the market or directly

with other energy market players, to be validated. These bids should be curtailed or accepted by the

DSO by means of the validation algorithms, and the results of the validation (accepted or curtailed

bids) should be published in the MVCC interface. Then, the AD products will be activated by means of

emulation and the real network operation will be observed. The target of the test is to ensure that:

- The DSO algorithms run in a correct sequence without errors;

- The DSO validation algorithms detect and curtail correctly an unfeasible (too large) AD product

and publish the response on the MVCC interface.

The following scenarios were considered:

- Test 1 and Test 1bis: the DSO receives bids for the intraday market that should be curtailed or

accepted

- Test 2: the DSO receives bids for the day-ahead market that should be curtailed or accepted.

Test date/time

Objective Test procedure Expected result Result(OK/FAILED)

29/01/2013 14.00 - 15.00

To ensure that the DSO validation algorithms work properly

1. Run the GF, LF, FT

All the algorithms should run without errors

OK

2. Upload the Total SupplyBid file with SRP and CRP. The AD product 300 kW (250 kW SRP + 50 kW CRP UP + 90 kW CRP DOWN (100% curtaliled)) from 14.00 till 15.00 was offered on the LA DM602023612L001 (the LA where the storage system is connected)

TSB2013_01_29

intraday 300kw LA storage crp down da levare.xml

OK

Page 50: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 50 of 126

3. Run the OLV algorithm

The OLV correctly accepted the AD products (curtailment factor =0,001)

cim_ieee14_state_rdf

_OLV.xml

OK

4. Run the RTV (because we have also the CRP product in our TSB)

The RTV correctly accepted the CRP product

ValidationResponse_R

TV.xml

OK

5. Download the DSE outputs before the storage activation

The DSE output before the storage activation are realistic (the current and the voltage behaviors were checked and compared with the real measurements in some control points)

outputAdrress

13.41.xml

OK

6. Actuate the AD products with the storage system

The storage system is correctly activated (the P, Q values in the LV measurement xml file on the LA DM602023612L001 were compared with the previous situation, p. 4)

OK

7. Download the DSE outputs after the AD product activation (redo this every 15 min while the AD is activated)

The DSE output during the storage activation (at 14.20) is realistic (the current and the voltage behaviors were checked and compared with the real measurements in some control points)

outputAdrress

14.20.xml

OK

8. Verify the network operation by comparing the DSE outputs before, while and after the AD products

There are no network constraints in the network operation (the DSE outputs after the AD product activation must not exceed the

OK

Page 51: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 51 of 126

activation limits of the test line (+-10% of nominal voltage)

Table 12. Test1: AD validation for the intraday market.

Notes:

1. The VVC is tested implicitly because it always reacts to achieve the optimal network situation

2. The files related to the tests described above are available on the MVCC interface (for the

indicated date/time).

The first preliminary observations are:

1. All the algorithms run well and give realistic results.

2. Before the AD product activation, the DSO had no network problems to solve and after the AD

product activation by means of the storage system no network constraints appeared (DSE

results).

3. The interpretation of DSE results presents some difficulties due to the fact that they are

presented in .xml format. A user friendly visualization interface should be developed for the

product to be suitable for real applications.

4. The MVCC algorithms behavior was compliant with the expected one.

Test date/time

Objective Test procedure Algorithms behavior Result

(OK/FAILED)

29/01/2013 16.00-17.00

To ensure that the DSO validation algorithms works properly

1. Run the GF, LF, FT All the algorithms should run without errors

OK

2. Upload the TSB file with SRP = 300 kW on the LA DM602023612L001 form 16.00 till 17.00

TSB2013_01_29

intraday 300kw LA storage - scorta II cat.xml

OK

3. Run the OLV algorithm and RTV (because we have also the CRP product in our TSB)

OLV has to accept or to curtail the "big" bids (part of SRP and/or CRP), curtailed CRP/SRP have to be published on the MVCC interface

cim_ieee14_state_rdf

_OLV.xml

OK

4. Download the DSE outputs before storage activation

The DSE output before storage activation are not realistic

outputAdrress

15.20.xml

FAILED

5. Actuate the AD products with the storage system LVMeasurements2013

0129151545.xml

OK

Page 52: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 52 of 126

The P value on the LA DM602023612L001 is different respect to the P before storage activation

6. Download the DSE outputs after the AD product activation (redo this every 15 min while AD is activated)

The DSE gave an error FAILED

Table 13. Test1Bis: AD validation for the day-ahead market.

The first preliminary observations are:

1. All the algorithms (p.1) runs without errors.

2. Before the AD product activation the DSE gave an unrealistic result, not compliant with the

real network situation. This result could be due to the following reasons: significant differences

between field measurements and historic data or an unexpected reaction of the DSE to the

connection/disconnection of capacitor banks in HV/MV substation. This reliable DSE is

needed for real applications.

Test Date Objective Test procedure Expected result Results

(OK/FAILED)

12/12/2012

To validate the "memory function" of the OLV Algorithm. The memory function should read the results of the last OLV and, if the validated product is performed in the same hours and on the same LAof the new products, the latter will have to be curtailed consequently. This function is requested forthe evaluation of products of the intraday market, considering the results of the OLV of the day ahead market of the previous day.

1. run the GF 2. run the LF

All algorithms should run without problems and in the correct sequence. The algorithms output will be automatically updated to the OLV input folder and will appear in the OLV interface page

OK

The total supply bid has been prepared assuming a SRP load increase of 300 kW from 19:00 to 20:00 on the LA DM602023612L001

Run the OLV. Be sure there is no thick on the Enable button at the bottom of the "input" rectangle

The OLV should not receive any error message in updating the input files including the TSB already prepared in the previous step. The OLV should not curtail the SRP product assuming a typical load (observed from the real measurements), on the LA DM602023612L001, from -60 to -100 kW

TSB2012_12_14 LA storage -300.xml

Page 53: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 53 of 126

The log file should present the normal sequence of operation: Network model GF and LF input upload TSB upload Iterative calculation steps

The result of the curtailment matrix should be seen both on the interface and on the xml file

No curtailment has been applied

OK

The Total Supply Bid has been prepared assuming SRP load increase of 200 kW from 19:00 to 20:00 on the LA DM602023612L001 and a CRP down (load decrease) of 50 kW

Run the OLV. Be sure there is the thick on the Enable button at the bottom of the "input" rectangle

The OLV should not receive any error message in updating the input files comprising the TSB already prepared in the previous step. The OLV should curtail the SRP product with a curtailment factor value from 0,8 to 1 The OLV should curtail the CRP completely

OK (0,845 CF)

Table 14. AD Validation for the day-head market.

Test Case 2: the DSO as an AD product buyer

In this test case, the DSO has to buy AD products in order to solve some expected network

constraints. A network constraint is simulated by changing the thermal limit of a MV cable in the

network under test. The power flow variation to solve this network problem is calculated preliminarily

and the amount has to be equal to/larger than the AD bid that the DSO has to buy on the market.

Then, the DSO sends a request to the market and receives a response. In case of positive reply, the

AD product is activated by means of the storage system. The observed real network operation has to

be compliant with the DSO forecast (the current through the interested cable has to be lower than the

modified thermal limit).

server.log

cim_ieee14_state_rdf_OLV_20121214182736.xml

TSB2012_12_14 LA storage -200 + crp 50 con memoria.xml

cim_ieee14_state_rdf_OLV_20121214184144.xml

Page 54: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 54 of 126

Date Scope of the test

Test procedure Expected result Results (OK/FAILED)

19/02/2013

To verify that AD products could be used to solve network problems

1. Run the GF, LF, FT All algorithms run without problems and in the correct sequence

OK

2. A network constraint is created by setting a new (inferior) thermal limit of the MV cable between DM60-4027517 and DM60-2023541 in the MV equipment file. The DSO can solve the problem by means of a load reduction in the adjacent LA. The load reduction is simulated by the storage, which injects the energy in the network.

The changed parameters can be found in the attached file (row 20847-20853 related on the segment DM604027517_DM602023541_0

MVEquipment_20130

215093725m1.xml

OK

3. Upload the Total SupplyBid file with the AD product on Load Area where the storage is installed.

The created TSB contains SRP =50 kW, CRP UP = 50 kW and CRP DOWN = 5 kW products that correspondto a Load reduction = 95 kW on the LA 0001DM602023612L101 from 16.00 till 17.00

TSB2013_02_19

pom2 100kw LA storage crp da levare (1).xml

OK

4.The OLV has to curtail/accept and publish the validation response

The OLV accepted SRP and CRP because they do not exceed the power limit of MV/LV transformer of the LA 0001DM602023612L101 (where the AD product is simulated).

cim_ieee14_state_rdf

_OLV.xml

OK

Page 55: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 55 of 126

5. Run the RTV (on demand) because the TSB contains the CRP product.

The RTV accepted correctly the SRP and CRP

cim_ieee14_state_rdf

_OLV.xml

OK

6. Download and analyze the DSE output before the AD products activation

The current on the interested cable exceeds the 10 A (in this case it is equal to 16,5 A). It means that the DSO could have a network problem if the current on the interested cable is not reduced

outputAdrress

13.45.xml

OK

7. Activate the validated AD product with the storage (100 kW emission) and analyze the DSE output and LV measurements .xml file

The values of P, Q on the LA 0001DM602023612L101in the LV measurements .xml file has to change with respect to the normal state (before the storage activation)

LVMeasurements2013

0219153826 before storage.xml

LVMeasurements

after storage.xml

OK

Page 56: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 56 of 126

8. Download the DSE output while (every 15 min) and after the AD product activation. Verify the network operation by comparing the DSE output before and after the AD products activation

There are no network constraints in the real network operation after the AD products activation (the current in the indicated cable is less than 10 A (6,5 A) and the voltage does not exceed the limits of the test line (+-10% of nominal voltage)

outputAdrress

16.30.xml

OK

Table 15. DSO as an AD product buyer.

The observations are:

1. All the algorithms run well and give realistic results.

2. Before the AD product activation the DSO had an issue: the current in the interested cable was higher than 10 A (e.g. 17 A)

3. After the AD product activation by means of the storage system the current on the interested cable was less of 10 A (6,5 A) so the DSO problem

was solved by means of the AD products.

4. The MVCC algorithms behaviour was compliant with the expected one.

Page 57: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 57 of 126

Test Case 3: Localized AD products to limit the power flow towards the transmission system

The target of the test is to limit the power flow rising to the transmission network through the primary

substation using the localized AD product. In particular, the AD contribution of specific load areas will

be programmed within the day-ahead market.

During the test an analysis of historical data of consumption patterns of the primary substation

Carpinone was carried out (green busbar); in particular data from December 2011. Years 2012 and

2011 have similar weather and load conditions.

A significant reduction of power consumption occurs during the central hours of the morning. At the

same hours of Saturdays and Sundays there is also the reversal of power flow to the transmission

network. The maximum reverse flow is about 2,3 MW in the day December 26th (vacation day in

Italy), the reason for this behaviour is that the network has mainly industrial customers, which reduce

their load during the day off.

In this case the DSO is configured as:

• Distribution network manager: the DSO verifies if any network problems and congestions

occur, and verifies the technical possibility to solve the problems with an active demand

product

• Active Demand product buyer: the buys from the market the most suitable active demand

product from an aggregator.

The test steps are:

1. Creation of the total supply bid for the day-ahead market in order to have an AD product

from 11.00 to 12.00 of the day after

2. Launch of the online validation and verification

3. Emulation of the AD product the next day

4. Check the distribution state estimator if "network constraints" occur and if limitation of the

power flow towards the transmission network through the primary substation at Carpinone

does occur

Test 1: 19th December

This consumption profile is foreseen:

• 11:00 to 11:35 308 kW

• 11:35 to 11:45 150 kW

• 11:45 to 12:00 50 kW

19th December

Test procedure Expected result Notes

1. run the GF 2. run the LF

All algorithms can run without problems and in the correct sequence The algorithms output will be automatically updated on the OLV input folder and will appear in the OLV interface page

This test can be executed also for the day ahead

Weather_Isernia_2012_12_19.xml

Page 58: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 58 of 126

19th December

Test procedure Expected result Notes

The Total Supply Bid prepared assuming an SRP load increase of 250 kW from 11:00 to 12:00 on the following LA: DM602023612L001 DM602023541L001

If we simulate the AD products with the storage system, they have to be simulated in the LA DM602023612L001

TotalSupplyBid 2012_12_19 limitazione risalita.xml

Run the OLV. Be sure there is no thick on the Enable button at the bottom of the "input" rectangle

The OLV should not receive any error message in updating the input files comprising the TSB already prepared in the previous step. The OLV should not curtail the SRP product assuming a typical load (observed from the real measurements), on the LA DM602023612L001, from -60 to -100 kW

The log file should present the normal sequence of operation: Network model GF and LF input upload TSB upload Iterative calculation steps

The result of the curtailment matrix can be seen both on the interface and on the xml file

These curtailments were applied: DM602023612L001: 0% DM602023541L001: 77,2%

The curtailment factor on the very low value of the CRP up is 1.00 (totally curtailed); contemporarly the CF on the SRP product is not 0.This error is due to a bug of the iterative calculation process; the error is not fatal and do not compromise the test success

cim_ieee14_state_rdf_OLV.xml

In order to provide the planned AD product it is possible to use only the load area DM602023612L001 (Centro Squadre), where the storage is located. These are the following set points for the storage: 11:00-11:35 308 kW 11:35-11:45 150 kW 11:45-11:57 50 kW

Page 59: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 59 of 126

19th December

Test procedure Expected result Notes

The OLV should not receive any error message in updating the input files comprising the TSB already prepared in the previous step. The OLV should curtail the CRP completely

DistributionStateEstimator1200.zip

Table 16. Localized AD products to limit the power flow towards the transmission system – Test 1

The observations are:

1. a strong load reduction occurs from 11 to 12 in the morning, but only in some cases an

inversion of the power flow occurs.

2. in case of power flow inversion, the storage cannot always ensure enough power to limit the

flow rising to the transmission network through the primary substation Carpinone.

3. in case of storage activation, the connecting cable is not always able to support the

requested consumption. It becomes necessary to use also other load areas to provide the

requested AD product.

Test 2: 28th January

Tests carried on during December showed that the contribution of the storage only not always is

enough to limit the flow rising to the TSO network through the primary substation at Carpinone. It is

therefore necessary to use other load areas to provide the requested AD product. In particular a

production reduction will be requested to t

he generators on the network; so, the total supply bid must also include the contribution of AD

provided by them.

The total supply bid includes:

Load Area 0001DM602023612L001 W -250000

Load Area 0001DM602023541L001 W -250000

Load Area 0001DM602023503L001 W -150000

Load Area 0001DM602023541L001 W -150000

Load Area 0001DM602027506L001 W -100000

Load Area 0001DM602031519L001 W -100000

Load Area 0001DM602031518L001 W -200000

Load Area 0001DM602031517L001 W -150000

Load Area 0001DM602031514L001 W -100000

It corresponds to the following requirements for the generators on the network under test:

Generator Line Installed power

[kW]

AD foreseen

[kW]

Page 60: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 60 of 126

Biogas Pesche 700 300

PV Biogas Pesche 950 400

Storage (consumption) Pesche 500 500

TOTAL 1200

In order to provide the AD product, the storage on Load Area “Centro Squadre”

(DM602023612L001) is used.

The foreseen consumption profile is:

• 11:00-11:30 500 kW

• 11:30-12:00 0 kW

28th January

Test procedure Expected result Notes

1. run the GF 2. run the LF

All algorithms can run without problems and in the correct sequence The algorithms output will be automatically updated to the OLV input folder and will appear in the OLV interface page

This test can be executed also for the day ahead

Weather_Isernia_2013_01_28.xml

The Total Supply Bid was prepared assuming an SRP load increase of 1200 kW from 12:00 to 13:00 on the following LA: 0001DM602023612L001 kW250 0001DM602023541L001 kW250 0001DM602023503L001 kW150 0001DM602023541L001 kW150 0001DM602027506L001 kW100 0001DM602031519L001 kW100 0001DM602031518L001 kW200 0001DM602031517L001 kW150 0001DM602031514L001 kW100

TotalSupplyBid 2013_1_28 limitazione risalita new.xml

Run the OLV. Be sure there is no thick on the Enable button at the bottom of the "input" rectangle

cim_ieee14_state_rdf_OLV_20130128121515.xml

The log file should present the normal sequence of operation: Network model GF and LF input upload TSB upload

Page 61: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 61 of 126

28th January

Test procedure Expected result Notes

Iterative calculation steps

The result of the curtailment matrix can be seen both on the interface and on the xml file

In order to provide the planned AD product the following generators are involved: Biogas Pesche (kW700) kW300 requested PV Biogas Pesche (kW950) kW400 requested Storage Pesche (kW500) kW500 requested TOTAL 1200 kW

The OLV should not receive any error message in updating the input files including the TSB already prepared in the previous step. The OLV should curtail the CRP completely

DistributionStateEstimator1200.zip

Table 17. Localized AD products to limit the power flow towards the transmission system – Test 2.

The first preliminary analysis is:

1. a strong load reduction occurs in specific hours (11-12 in the morning), but only in some

cases an inversion of the power flow occurs. In case of a power flow inversion the storage

cannot always ensure enough power to limit the flow rising to the transmission network

through the primary substation at Carpinone.

2. in the case of storage utilization, the connecting cable is not always able to support the

requested consumption. It becomes necessary to use also other load areas to provide the

requested AD product

3. an economic analysis is required to quantify costs and benefits of the action taken:

- costs: penalties for the non-production of generators;

- benefits: avoided penalties for the resolution of congestion and / or flow towards the

TSO.

Page 62: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 62 of 126

Test Case 4: MVCC algorithms reaction to network changes

The aim of this test is to verify the algorithms reaction to the relevant network structure modification.

This test was carried out on purpose exploiting a “big” network configuration variation. In fact, this

test was performed while the Carovilli operative centre was disconnected due to scheduled

maintenance works.

Test date/time

Objective Test procedure Algorithms behavior Results

(OK/FAILED)

20/02/2013 16.00-17.00

To verify that the algorithms react correctly after modification of the network structure

1. Run the GF, LF, FT

All the algorithms should run without errors

OK

2. Download the Network model files and the DSE outputs after the Carovilli Operative Centre disconnection

The Carovilli Operative Centre disconnection is detectable in the MV topology .xml file

MVTopology_2013022

0003125.xml

The DSE output is realistic (the current and voltage values were checked in some control points)

output.xml

OK

Table 18. MVCC algorithms reaction to network changes

The observations are:

1. The MVCC correctly receives the measurements and the network model is correctly

updated.

2. The DSE reacts well in case of relevant network structure modification and it is able to give a

realistic evaluation of the new network state.

Page 63: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 63 of 126

5. France

5.1. Description of the test

Extensive tests were performed in EDF laboratory to prepare the French field tests. They were

conducted in conditions very near to those encountered on the field and allowed to assess the

technical feasibility and the performance of the ADDRESS chain components during individual and

interaction tests [6]. They also allowed to identify the limitations and the risks linked to the currently

implemented solutions.

Since these unitary and interactions tests were extensively carried out during the previous testing

stage, they are no longer performed in the field tests. The test cases carried out during the French

field tests are mostly global scenarios to which all the main components of the ADDRESS

architecture contribute.

The objectives of the French field tests were mainly the following:

Using the results of the laboratory tests as a basis, one of the aims was to evaluate the technical

feasibility and the performance of the complete ADDRESS chain.

During the field tests, it was assessed how AD can meet the needs of the electricity system

players using bilateral contracts (SRP and/or CRP). The provision of AD services was based on

the simulation of possible problems or actual needs identified by electricity system players (DSO,

TSO, BRP…) or by other players (retailer, RES producers – PV in our case…). These needs

resulted in appropriate AD requests tested on the field. The AD services such as power reserve

for imbalance management, load shaping (load increase or decrease) for technical or

economical optimizations, voltage control and power control to relieve overloads or network

congestions are considered.

The impact on the network of the obtained AD volumes was examined too. The effects

forecasted using the AD product volumes submitted by the aggregation entity and validated by

the DSO were compared with the effects caused by the load variations observed on the field.

In the field tests, we also studied the response of the consumer portfolio to the incentive signals

defined by the aggregation entities. This study performed on both individual (consumer) and

global (cluster of consumers) levels allowed us to verify if, how and under which conditions the

initial AD need was fulfilled. The forecasted behaviors of the consumer appliances and of the

global cluster were compared to the ones measured on the field.

In addition to the previous test cases, another objective was to test the simulated market

interactions of the aggregation entities and other electricity system participants (e.g. retailer, or

balancing responsible party). Several market scenarios were performed. We aimed at assessing

the impact AD could have on the prices of the simulated electricity market; different market

conditions were considered. The integration of the simulated electricity market inside of the

complete ADDRESS chain of process was also tested.

Finally, consumers’ acceptance and commitment were also assessed but this topic is out of the

scope of this deliverable. In this respect, the studies carried out and the result obtained are

described in ADDRESS Deliverable D5.2 [7].

Several cases were tested in order to cover these objectives of the French field tests. Most of them

Page 64: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 64 of 126

are about the complete ADDRESS chain of processes providing different service types. Others

concern the electricity market simulator and its interactions with the aggregation entity. All these

cases allow us to verify the capability of the implemented ADDRESS architecture to respond to the

envisioned situations and to test the performance of its modules on real data. Those involving all the

components of the ADDRESS architecture are the following:

Request from the DSO for reducing a local overload constraint,

Request from the TSO for reducing a congestion constraint,

Request from the BRP for managing the imbalance between production and consumption,

Requests in combination with RES for reducing a local voltage constraint anticipated by the DSO

or providing AD services to a RES producer,

Requests from the DSO for limiting the global consumption of the islands over a complete day,

Offers providing AD services to an electricity market.

It is to be noted that the proposed field test cases are generic enough to be illustrative of most of the

services that could be provided by the ADDRESS architecture. The AD requests that have been

considered and tested may indeed correspond to the needs of different players, or in other words

each of the 31 AD services defined in the Deliverable D1.1 [8] may be associated with at least one of

the cases played in the French field tests.

The description of the test cases and detailed test scripts performed in the French field tests can be

found in Chapter 8 and in the Appendix of Deliverable D6.1 [1].

5.1.1. Location

The field tests in France were performed on the two islands of Houat and Hoëdic in the South of the

Brittany region, in the West part of France.

The network considered is composed of 1 MV feeder and 8 MV/LV substations. The island of Houat

is connected to the continent through a 19 km long underwater MV cable, and a second 8.5 km long

underwater MV cable connects the island of Houat to the island of Hoëdic. On Hoëdic, one private

PV plant with a power of 100 kW peak is connected to the LV grid. At certain periods of the year

(e.g. May or June) the PV production may be very high with respect to the consumption of the island.

There are a total of 569 consumers for both islands, of which about 373 are permanent consumers.

Indeed, there is a high rate of secondary houses. Around 30 domestic consumers have taken part in

the tests, leading to a rate of 5 to 8 % of active consumers, which is quite significant for such a

demonstration.

On these islands a lot of the consumers use electricity for their water heaters (water tanks containing

between 150 and 300 litres) taking advantage of the off peak tariff (8 hours per day), and for heating

by means of electric heaters. This represents the major part of the electricity consumption for these

consumers.

The French field tests site is described in more detail in ADDRESS Deliverable D6.1 [1].

As already mentioned, the French field tests are dedicated to the validation of the whole ADDRESS

chain, i.e. from the AD buyers to controllable appliances at the consumers’ premises, which is shown

on Figure 42. The configuration of the chain and of its different components for the carrying out of

the French field tests are described in detail Sections 5.1.3, 5.1.4 and 5.1.5.

Page 65: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 65 of 126

Pla

yers

or

fun

cti

on

s o

f th

e e

lectr

icit

y

syste

m

Aggregation platform

EB

Meter or equivalent

Washing machines

Electric heating

Water heaters

Smart plugs

Retailer Other non controlled usages

Balancing Responsible

Party

Producer

Mark

et, c

ontr

acts

or

direct

bila

tera

l re

lationship

s

Consumers

DSO

TSO

Figure 42. The whole ADDRESS chain tested in France

5.1.2. Players involved

In order to conduct the field test cases described in the previous section, the complete ADDRESS

architecture is considered and tested. Depending on the scenario, different players are involved in

the tests. In every test script, at least the three following players are to be considered: the DSO, the

aggregation entity and the consumers (or more precisely their EBoxes and appliances). The Market

Simulator (MS), simplified representation of the Electricity system players and real local players are

also considered in some of them.

5.1.3. Architecture of the System

As already mentioned, during the laboratory tests, the modules composing the ADDRESS

architecture were validated and most of the limitations and risks they present were identified. Based

on these results, choices were made regarding the ADDRESS architecture implementation for the

French field tests in order to ensure that both the system performance and reliability are guaranteed.

Based on the results of the laboratory tests, a two-part system compliant with the ADDRESS

architecture and fit to the reliability requirements of a field test was retained for the French field tests.

This system is composed of two distinct parts (Errore. L'origine riferimento non è stata trovata.):

the upstream part of the architecture consisting of the DSO Platform, the ATB System, a

simplified modeling of the different electricity system players and the Market Simulator. It is

managed in off-line mode. Since significant risks of failures of the ATB optimization

processes were detected during the laboratory tests, the optimization results could not be

directly applied in the EBox database connected to the internet. The ATB and the DSO

platforms are run with a local copy of the EBox database (renamed ATB database). Using

the database, the whole day-ahead and intra-day sequences are run with the interactions

between the DSO and the ATB platforms being considered. If the sequences prove to come

to their end and succeed, they are approved for application.

the downstream part consisting of the ecosystem of the Energy Boxes. It is always run

connected to the internet in an online mode. The correct operation of the Energy Boxes

(EBox) highly depends on its availability and the robustness of the information present in the

Page 66: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 66 of 126

EBox database of the aggregation entity (where the EBoxes get the signals generated by

the ATB). In case a problem arises in this part, the consumers could be impacted. Special

care is thus taken so that no erroneous data is input in this database.

The link between both parts is ensured by the synchronization of the two EBox and ATB databases.

This synchronization occurs only when every precaution has first been taken to ensure that no

problem may arise on the field.

The strict separation between both parts was also useful to run some cases for which tweaks were

required. Indeed, some of the algorithm limitations identified during the laboratory tests required

manual interventions in order to by-pass some modules and run the considered test script (e.g. when

testing load increasing signals).

Detailed information on the system implementation deployed for the French field tests and on the

impact of these two separate operation modes on the management of the platforms included in the

ADDRESS system will be specified in the following section.

DSO Platform

Weather

websites

Historical Consumption

server SOAP

webservices

EBox Database

WebServer

ATB Database

2-way Synchronization

EBoxes

EBoxes

EBoxes

EBoxes

Internet

ATB

System

Up

stre

am

ch

ain

Do

wn

stre

am

ch

ain

Simulated Electricity

Market

Figure 43 - Operation mode of the ADDRESS architecture considered in the French field tests

5.1.4. Equipment installed

5.1.4.1 Upstream side of the ADDRESS chain: market, DSO and aggregation function

5.1.4.1.1 DSO platform

The DSO performs different activities depending on the considered test case

Page 67: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 67 of 126

(

LAC

GenF

FTC

LoadF

OLV RTV

Algorithm managing

engine

Consumption data database

AD flexibility data database

Weather data database

Weather

websites

Historical load data

server

Weather forecast manager

CIM network

converters

Historical

databases AXIS Server ATB

Network description

: Interactions of the DSO platform with external actors

: Interactions within the DSO platform

SOAP

DSO Platform

Figure 44.). All of its activities are run using the DSO platform developed by the EDF team and

where in particular the algorithms developed for the DSO by the project partners have been

integrated. Its specific components and GUIs are used.

The platform is used to anticipate the distribution network constraints and to define the DSO

needs in terms of AD products in regards to these constraints. These flexibility needs are

transmitted to the aggregation entity in order to adjust the local consumption of its

consumers’ portfolio.

The DSO platform operates automatically as the actor responsible for the technical

validation of the Active Demand programs. It communicates the flexibility information to

every aggregation entity, performs the technical validation of the submitted flexibility

programs and returns the curtailed volume to the appropriate aggregation entity.

The DSO platform enables assessing the impact of the real flexibility response of the

consumers on the evolution of the distribution network quantities and its constraints.

Page 68: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 68 of 126

LAC

GenF

FTC

LoadF

OLV RTV

Algorithm managing

engine

Consumption data database

AD flexibility data database

Weather data database

Weather

websites

Historical load data

server

Weather forecast manager

CIM network

converters

Historical

databases AXIS Server ATB

Network description

: Interactions of the DSO platform with external actors

: Interactions within the DSO platform

SOAP

DSO Platform

Figure 44. Main components of the French DSO platform and interactions with external actors.

5.1.4.1.2 Aggregation entity and ATB

The aggregation entity is the central component of the ADDRESS architecture. It interacts with

several actors depending on the considered case.

EBoxes. The main interaction of the aggregation entity with the consumers is through their

EBoxes. The aggregation entity defines and “sends” price and volumes signals to the

consumers’ EBoxes to obtain modifications of their consumption.

Regulated and deregulated players. The flexibility needs expressed by regulated and

deregulated actors are taken into account by the ATB platform algorithms. The signals sent

to the EBoxes depend on the requested flexibility volumes and timeslots.

DSO. The aggregation entity takes into account the local flexibility information defined by the

DSO in order to assess the offer volume it can respond to and to constrain the selection of

the signals that can be sent to the EBoxes. In the same way, the results of the technical

validation carried out by the DSO are integrated by the aggregation entity when choosing the

signals for the EBoxes.

Market. The aggregation entity can offer flexibility volumes on an external electricity market

and take into account the acceptance level of its offer proposal.

The management of its algorithms and their interactions with external actors is done by the two

platforms developed for the French field tests:

(i) the ATB prototype management software, used to generate the content of the ATB

database, and

(ii) the ATB platform, used to manage the day-ahead and intra-day optimization sequences.

Both platforms are part of the system of the aggregation entity, i.e. which will be called here the ATB

system (Figure 44)

Page 69: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 69 of 126

AXIS Server DSO

: Interactions of the ATB platform with external actors

: Interactions within the ATB platform

SOAP

ATB System

EB Database

WebServer

ATB Database

Consumer Samples

Generation

ATB prototype

management

Response Forecast

Signals Adjustment

Market Price Forecasting

ATB Platform

Optimization Algorithms

2-way Synchronization

EBoxes

EBoxes

EBoxes

EBoxes

Internet

Regulated /

deregulated actors

ESB

Orchestrator Market

Figure 45. Main components of the French ATB system and interactions with external actors.

5.1.4.1.3 Market simulator

The tests performed regarding the Market Simulator (MS) follow several objectives:

Assessing the impact of AD offers generated by the ATB or any aggregation entity on the

wholesale market prices,

Analyzing the market acceptance of these AD offers,

Evaluating the potential benefits for the aggregation entity.

It should be noticed that the market considered for the tests is the (French) SPOT national energy

market where different actors (DSO, TSO, aggregation entities, BRPs…) interact in order to sell or

buy volumes depending on their needs and their resource availability. These volumes are

aggregated in one global offer and one global demand coming from the forecasting tool (Figure 46.).

Other markets could have been considered assuming that they follow similar principles. The SPOT

market was favored since the data required for the studies are public.

Page 70: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 70 of 126

Figure 46. Interaction of the ATB system with the Market Simulator.

During the tests, two MSs have been used. The 1st one is the tool developed in Task 5.3 of WP5 and

the 2nd

one is a tool developed by the EDF team in order to run additional test cases not possible

with the 1st simulator.

1. Initial market simulator

The market simulator developed in Task5.3 is a JAVA program which operates similarly to a real

electricity market. It uses demand and supply bids as inputs and then clears the market. The tool

only accepts hourly and blocks bids for a single market area.

A bid creation tool was also developed in Excel in order to simplify the creation of the bid files for the

test cases.

The integration of the hourly bids is realized as follows:

The supply bids and demand bids are aggregated separately: the aggregated curve is the

sum, for each price, of the volumes from the different bids (Figure 47.). We thus obtain two

curves: the hourly total supply curve and the hourly total demand curve.

The two curves are then compared to find the temporary equilibrium, i.e. the price for which

the demand and supply volumes are equal (or intersect).

This allowed us to understand several wholesale price issues. But several problems were

encountered while integrating the AD offers and motivated the development of an alternative market

simulating tool.

Page 71: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 71 of 126

Figure 47. Aggregation of supply bids

2. Alternative market simulator

The alternative market simulator was developed in Excel by EDF in WP6 in order to run additional

test cases. In this new version, the equilibrium point is found by intersecting linearly the price-volume

curves of the total offer and total demand. This choice was made to simplify the computation

process.

However, when the AD offer of the aggregation entity is partially accepted by the market, the market

simulator will then use the usual starcase model. So, we are sure that the price of the equilibrium is

the price of the AD offer.

5.1.4.2 Downstream part of the ADDRESS chain: Energy Boxes

The equipment installed at each consumer’s premises consists of:

- one EBox composed of PC,

- up to 7 smart wall units to control the electric heaters and the water heater,

- up to 3 temperature sensors,

- 5 smart plugs to control other types of “classical” electric appliances,

- Smart washing machines developed in the project and able to communicate directly with the

EBox installed at 7 consumers.

The configuration is shown in Figure 48.

Bid 1 Bid 2

Total bid

Page 72: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 72 of 126

Meter EBox PC

ADDRESS

At consumers’

premises

ADDRESS

Control Center

(EDF Clamart)

Electric appliances connected

through smart plugs or wall units

• radiators

• water heater

• white goods…

Smart washing

machine

(7 consumers)

Temperature

sensors

Figure 48. Equipment installed at consumer’s premises.

The EBox is the computing device installed at the consumer’s premises that contains the energy

management software. It manages the controllable devices inside the house (Smart Plugs and Wall

Units, Temperature Sensors, Smart Washing Machine...) and communicates with the aggregation

platform through the so-called EBox database described in Section 5.1.4.1.2 (and

Page 73: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 73 of 126

AXIS Server DSO

: Interactions of the ATB platform with external actors

: Interactions within the ATB platform

SOAP

ATB System

EB Database

WebServer

ATB Database

Consumer Samples

Generation

ATB prototype

management

Response Forecast

Signals Adjustment

Market Price Forecasting

ATB Platform

Optimization Algorithms

2-way Synchronization

EBoxes

EBoxes

EBoxes

EBoxes

Internet

Regulated /

deregulated actors

ESB

Orchestrator Market

Figure 45.) to get the AD requests (Figure 49.).

The EBox is always operating in an online mode, i.e. it is always connected to the Internet. The

EBox database of the aggregation platform is remotely accessed every 15 minutes with this internet

connection using webservices. This remote access allows in particular to detect if a new incentive

signal has been added in the EBox database so that the optimization algorithm of the EBox is then

launched. During this optimization run the requested load modification operation is taken into

account. It is to be noticed that the incentive signals input in the EBox database are either selected

by the ATB platform algorithms or manually chosen.

During the French field tests, several types of devices have been managed by the EBox. Table 19

summarizes the loads that have been controlled.

Page 74: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 74 of 126

WebServer EBox

Database

Internet

Figure 49. Home side system and EBox database.

Category Device

Non-Controllable load Fridge, Freezer, Kettle, Micro Wave, Light, PC, TV…

Shiftable load Electrical Water Heater (EWH), Dryer, Washing Machine, Smart

Washing Machine, Dishwasher

Interruptible load Electrical Heaters

Table 19. Controllable loads considered during the French field tests.

5.1.5. Test conditions

In this Section, we give, for each platform (DSO, ATB, EBoxes...), a global description of the test

conditions and of the settings used when performing the field test cases.

5.1.5.1 ATB platform

5.1.5.1.1 ATB database adjustments

The laboratory tests showed that a new ATB database was necessary to be able to carry out some

of the French field tests. It was then built in accordance with the specificities needed. This database

has a better balance between the two types of incentive signals: 55% of the signals are meant for

load decrease and 45% of the signals are for load increase. This has to be compared to the

85% / 15% ratio of the initial test database. The parameters of the incentive signals and the cluster

prototypes as well as the prototype parameters have also been recalibrated following the lessons

learned from the laboratory tests.

5.1.5.1.2 Clustering methodology

The prototypes defined in the new database were constituted using the consumption data of the

Page 75: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 75 of 126

consumers taking part in the field experiments. Over a year of consumption data were used for this

purpose. After their analysis, several groups have been defined depending on:

the season of the year: Spring / Summer/ Autumn / Winter,

the day type: working days / Saturdays / Sundays or holidays...

For each of these groups, two distinct load curve prototypes have been determined. They result from

the classification performed on the consumer consumption profiles.

Figure 50 - Clustering methodology applied to the French field tests

An additional clustering level has also to be considered since the complete ADDRESS architecture is

tested in the French field tests: prototypes are defined depending on the Load Area attribution of

each consumer. It is to be noticed that the prototype load profiles do not change between the Load

Areas, only the number of associated consumers and specific characteristics change: some consist

of very few consumers while others are a little larger.

The methodology used for the prototype clustering is shown in Figure 50.

5.1.5.1.3 Constitution of the prototype consumption profiles

Different actions were performed in order to carry out the clustering of the French consumers taking

part in the ADDRESS field tests on the Brittany islands.

Consumer classification and consumer type identification

The consumption data measured during a period of more than one year were used in order to

classify the different consumers and calculate the average consumption of each prototype. A

software tool previously developed by EDF for its own studies was applied to this set of

consumption data. It allowed us to identify two main types of consumers. Three different day

types were also defined even if this 3-part separation was only required for one of the two

consumer classes.

Consumers’ Daily consumption Curves

Spring Summer Autumn Winter

Day type clustering

Working days

Saturdays Sundays

Season clustering

Profile 1 Profile 2

Profile clustering

Prototype (Load Area 1)

Load Area clustering

Prototype (Load Area i)

Prototype (Load Area N)

Page 76: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 76 of 126

The consumer recruitment was still going-on at the time of the classification and new consumers

continued to join. Classification criteria were provided in order to attribute these new consumers

to one of the two consumer classes without having to carry out again the whole classification

process.

It is to be noticed that more classes could have been defined but they were not created given the

limited number of consumers taking part in the French field tests.

Correction of the weather data influence

The analysis of the load curves showed a direct impact of the weather, and in particular of the

temperature, on the consumers’ consumption profiles. This load data was processed with

another tool previously developed by EDF for its own studies in order to correct the variability

induced by the temperature on the profiles and normalize them, i.e. estimate the consumption

that would have been observed for normalized weather conditions.

Generation of the prototype consumption profiles

Based on the previous results, 24 (4x3x2) prototype consumption profiles were computed for the

defined seasons, day types and consumer classes. Some of these prototypes are shown in

Figure 51..

0

500

1000

1500

2000

0 4 8 12 16 20 24

Po

we

r (w

)

Time (h)Working Day Saturday Holiday

0

200

400

600

800

1000

1200

0 4 8 12 16 20 24

Po

we

r (W

)

Time (h)Working Day Saturday Holiday

Figure 51. Spring consumption prototypes for the 3 day types and the 2 consumers types.

5.1.5.1.4 Appliance modeling

Some appliance types defined by default in the ATB database were not applicable to the context of

Page 77: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 77 of 126

the French field tests since all of them they were developed for the Spanish field tests. In particular,

the water heaters were first defined in the ATB database as interruptible devices of “low” power (less

than 300 W) working continuously. But, in France, the water heaters are of higher power (several

kW) and only work during short periods of time (those with off-peak prices) since remote signals sent

at the change between peak and off-peak time are used to control such devices. In order to take into

account these differences, the water heaters were defined as shiftable devices both in the database

and on the field. In the database, the statistical distribution of their starting times was also modified in

order to take into account the time intervals corresponding to the price change from peak (high

electricity price) to off-peak (low electricity price) periods: these intervals present the highest

probability for the water heaters to start their heating cycle.

But the adjustments carried out on the modeling of such loads could not fully solve the problem: the

statistical distribution of the starting times cannot compensate for the impact of the over-a-day price

variations implied by the remote tariff signals used in France. It is to be noted that the EBoxes

algorithms take this price information into account when managing their loads, i.e. when shifting or

interrupting their consumption following the user’s preferences and the price information.

5.1.5.1.5 ATB platform operation

The database generated with the previously defined clusters was used in all the test cases

performed for the French field tests described in Deliverable D6.1 [1]. Depending on the case, the

ATB platform interacted with the DSO platform or an external electricity market simulator.

It is to be noticed that the unitary and standalone tests of the ATB platform were already performed

during the laboratory tests. These tests were meant to:

Analyze the usage of the ATB database and evaluate the performance of the algorithms

used to build it (consumer prototype generation, cluster flexibility forecasting...),

Assess the capability of the ATB optimization algorithms to supply AD load increase and

decrease requests for different seasons, day types and day periods given a fixed database,

Check the interactions of the ATB with the DSO platforms during the validation sequence.

The test scripts associated with these lab tests can be found in the Appendix of Deliverable D6.1 [1].

5.1.5.1.6 Scaling the cluster flexibility

Some test cases imply that a large amount of flexibility is available in the aggregation function

portfolio. Such an amount is not possible given the limited number of consumers taking part in the

French field experiment. A scaling factor was applied to the ATB database for these cases in order

to simulate a larger presence of AD in the islands. This factor does not modify the flexibility profile

that could be offered: during the lab tests, it was assessed that the flexibility forecasted for a cluster

of 10 consumers was similar to the one forecasted for a cluster of 100 presenting the same

characteristics once scaled appropriately by a factor 10. This scaling property is linked to the

statistical method used for the forecasting.

The same factor was applied to the flexibility impact observed on the field when comparing the ATB

flexibility forecasting with the obtained flexibility.

5.1.5.1.7 Incentive signal selection

The ATB platform optimization algorithms are able, in most of the test cases, to select suitable

incentive signals to be sent to the associated clusters: in most cases, the chosen signals are directly

Page 78: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 78 of 126

supportive of the volumes of the AD request. This means that load decrease requests are supplied

by means of load decrease signals and load increase requests by load increase signals.

However, in some cases, the payback effect of the signals is used by the algorithms to supply the

request instead of its primary effect. For example, the payback effect of a load increase signal is

used to limit the consumption during the time interval associated with the load reduction request. In

this document, when used this way, the signals are referred to as “inverse signals”. The rate of

occurrence of this phenomenon is smaller than the one observed with the database used for the lab

tests, but it still remained. It is directly linked to the flexibility response forecasted by the algorithms

applied during the database generation phase. For example, the volumes that load decrease signals

can provide are sometimes smaller than those associated with the payback effect of a load increase

signal starting before.

The problem when using such “inverse signals” is that they rely on the quality of the forecast of the

payback effect, which is even harder to forecast than the direct effect of an incentive signal. The

measurement and assessment of this payback effect of AD requests at a cluster level is even more

complex (see subsection 5.2.3).

Thus since “inverse signals” are highly unreliable and may lead to possibly harmful effect at

consumers’ premises, when they are selected by the ATB optimization algorithms, they are not

applied on the field. The optimization processes are rerun after slightly adjusting the AD request

volumes and/or time interval until the signal selection is successful. All these adjustments were run

off-line using the ATB database. For some cases, such adjustments could not achieve the expected

result and the signal selection had to be performed manually by bypassing the ATB platform

algorithms.

5.1.5.1.8 ATB algorithm execution

As explained before, the ATB platform has to be bypassed in some cases, mainly because of some

limitations of the current ATB implementation. For instance, this happens in situations where the

payback effect of signals opposite to the request is used to respond to the expressed AD need, for

instance when intra-day load increases are requested.

In every other case, the ATB is implied to run the complete day-ahead and the intra-day sequences

to ensure that no error appears during one of the optimizations before applying the selected

incentive signals to the on-line EBox database.

5.1.5.2 DSO platform

The three operation modes of the DSO platform are described in [6]. In the field tests two of them

are used depending on the scenarios that are considered:

The accelerated-time mode is the one used in most of the field test cases. In this mode, the

platform operates in standalone, manages automatically the interactions with the ATB platform

and disregards any scheduling. For example, the AD requests sent by the ATB are considered

whenever they are submitted (no time limit or submission interval considered) and the responses

to these requests occur immediately at the end of the validation algorithm computation.

The off-line mode is used when the ATB has to be bypassed. In this situation, the DSO

algorithms are executed in sequence (sequential tests) with the interactions between the DSO

and the ATB platform simulated. The ATB requests are generated using the GUI embedded in

the DSO platform for this purpose.

NB: A third operation mode of the DSO platform, the scheduled mode, has been tested in laboratory

Page 79: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 79 of 126

but has not been used in the field tests due to communication issues.

The field test cases involving the DSO platform are very similar to some of the tests performed in the

laboratory (in particular tests scripts 7 and 8 of the DSO algorithms [1]). All these tests aimed at

assessing the performance and reliability of the algorithms on an individual level and integrated in

the ADDRESS architecture. The main differences between the lab and field tests rest in the context,

i.e. in the inputs linked to the tested field scenario.

Depending on the field test cases, the tests are performed:

Either on the real network of the Brittany islands operated in nominal or near-nominal conditions;

Or on a modified network constrained by one or more of the following actions: modification of

network components (line impedance, transformer rated power…), modification of the PV plant

characteristics, adjustments of the forecasted load curves…

5.1.5.3 Energy Boxes

5.1.5.3.1 Configuration of the loads

This section details the parameters that have been used to specify the different types of loads and

their parameters in the configuration file of the EBoxes. A special focus is given to the Interruptible

Loads and to the Electrical Water Heaters as shiftable loads.

5.1.5.3.2 Interruptible loads

During the field tests, most of the loads declared as Interruptible Loads were electrical heaters. This

is due to the fact that serious issues were met with the Thermal Load type in the laboratory tests [9].

Despite all the effort spent by the developers and EDF team, these issues could not be solved and

Thermal load type could not be tested on the field. Electric heaters were thus defined as interruptible

loads.

Electrical heaters represent an important part in the house consumption. This is why this section

focused on the described parameters for electrical heaters.

The Interruptible Loads are loads that can be interrupted by the EBox for a given duration. There are

four parameters that have to be defined in the configuration file of the EBox:

Duration: it is the maximum duration of each interruption (expressed in timeslots of 15 minutes);

Distance: it is the minimum distance between two consecutive interruptions (in timeslots of 15

minutes);

maxOFF: it is the maximum number of interruptions during one day;

onPower: it is the theoretical power which represents the consumption of the load (in Watt). This

parameter is used by the optimizer, but it was not the measured appliance consumption.

During the field tests, we initially used the same parameters for every Interruptible Load:

Duration=1, i.e. interruptions of 15 minutes duration to limit the impact on the consumer’s

comfort since we cannot control the temperature when electric heaters are defined as

interruptible loads;

Distance=6, i.e. a minimum duration of 1h30 between two interruptions;

maxOFF=4, i.e. 1h of interruption at maximum in a same day;

onPower=500 W;

Then, it was decided to increase the duration, the distance and the maxOFF. The parameters finally

Page 80: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 80 of 126

used are the following:

Duration=2, i.e. interruptions of 30 minutes duration (which prove to be acceptable from the

perspective of consumer’s comfort) ;

Distance=6 , i.e. a minimum duration of 1h30 between two interruptions;

maxOFF=8, i.e. 2h of interruption at the maximum if a same day;

onPower= value tuned using the power measured by the Smart Plug or the Wall-Unit.

5.1.5.3.3 Electrical Water Heater

During the French field test, the management of Electric Water Heaters (EWH) was a challenge.

Initially, the EWH were supposed to be operated by the EBox as Interruptible Loads. However, this

does correspond to the specific nature of the EWH in France (see Section 5.1 or Deliverable D6.1

[1]). So EDF decided to define them as Shiftable Loads which was more appropriate considering

their consumption behaviour.

More specifically, this change of the appliance modeling is motivated by several factors:

the EWH is a high power load (~2 or 3 kW depending on the family) consuming only during

specific day periods (off-peak periods typically) contrary to the EWH present in Spain that are

working continuously;

we could also shift a part of its consumption when the renewable production is high in order to

test the combination of AD with RES production.

Shifting these devices was a real challenge since in France a huge number of EWHs are already

remotely operated thanks to an electronic relay. This functioning is detailed in Figure 52..

Page 81: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 81 of 126

Figure 52. Control system of the French Electrical Water Heaters.

Both part of Figure 52. present the operation of the electric installation that allows to control the

EWHs during peak and off-peak periods. It consists in two circuits: a power circuit which feeds the

EWH and a control circuit which manages the power circuit thanks to an electronic relay (2).

During the off-peak period, a signal is sent to the contactor (1) which closes itself: the

electronic relay is then switched ON closing the power circuit and feeding the EWH.

During the on-peak period, another signal is sent to the contactor which opens itself: the

electronic relay is switched OFF opening the power circuit and switching off the power

supply of the EWH.

In order to enable the control of the EWH by the ADDRESS system, a Wall-Unit (3) was wired

downstream the control circuit and in series with the power part of the normal electrical installation.

This additional installation is presented in the Figure 53..

Figure 53. Control system of Electrical Water Heaters with ADDRESS.

Two problematic situations may occur with this implementation:

The starting time of the EWH calculated by the EBox happens during a peak period. The

Wall-Unit is switched on whereas the contactor is off.

the EWH will not be fed by the power circuit.

The starting time calculated by the EBox happens just before the end of an off-peak period.

The contactor is on and the EWH is fed only for a very short time till the end of the off-peak

period.

the water may not be warm enough when the relay is switched off.

Page 82: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 82 of 126

These two situations may cause a discomfort for the consumer (cold water!). Before declaring the

EWH as a Shiftable Load, it was therefore necessary to tune the parameters in the EBox in the

appropriate way. This was done in three steps.

First phase: EWHs declared as Non-Controllable loads

At first, after the EWH had been wired to a Wall-Unit, it was defined as a non-controllable load and

therefore it was not operated by the EBox. The objective was to measure the EWH consumption.

At the same time, laboratory tests were performed in the EDF laboratory to determine the best

parameters suited to the control of the EWH.

Second phase: EWHs declared as Shiftable loads

Declaring the EWHs as Shiftable Loads was not a simple matter since the parameters had to be

defined on a case by case basis for each consumer. Indeed, not every customer has the same

peak/Off-peak periods: on the two islands, four different types of tariff periods exist. The main

difficulty comes from the midday off-peak period because the water must be sufficiently heated

during this period. If this condition is not met, the water will not be hot enough by the evening.

Concerning the consumers whose off-peak period only happens during the night, the starting time

needed to be programmed at the middle of the night and not before midnight because of limitations

related with the implementation of the EBox optimization algorithm (one day non-sliding optimization

window). To guarantee this point, we used the same configuration for every EWH:

Default Consumption Profile:

Period=60 minutes

Power=1500 W

DetectionLevel=50 W

DetectionTime=7 seconds

DetectionOFFLevel=10 W

DetectionOFFTime=600 seconds

However, the preferred start and end times of the EWH had to be adapted to each consumer, taking

into account its peak/off-peak tariff periods. Table 20 summarizes these choices.

Off-Peak periods Preferred start and end times

01h30-07h30 12h30-14h30

01h45 – 13h45

02h00-07h00 14h00-17h00

02h15 – 15h30

23h30-07h30 00h15 – 03h00

22h30-06h30 00h15 – 03h00

Table 20. French field tests – Off-peak periods and preferred start and end times of the EWH

Despite these modifications, several problems still occurred (e.g. abnormal starting time calculated

by the EBox optimizer) causing a discomfort to some consumers. Furthermore, the EWH shifting

capability was limited during this phase: it was only possible to shift the EWHs during the Off-Peak

Page 83: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 83 of 126

period which is not necessarily the most interesting situation regarding the field tests cases

considered in France. All these reasons led EDF to change the position of the relay. Third phase: changing the position of the relay

For some EWHs, the position of the relay can be changed manually into a “forced operation”

position. In this mode, the EWH is no longer operated by the relay (it is always "ON") and starts as

soon as the water temperature is below a set point limit.

For a limited time during the French field tests the consumers were then asked to change the EWH

operation mode themselves to “forced operation”. After this intervention, AD requests have been

sent to their EBoxes in order to shift EWH load from off-peak to on-peak periods. This was

necessary to test cases where AD is combined with PV production.

5.1.5.3.4 Scenarios to test the provision AD Services

During the French Field Tests, the tested scenarios are listed in Table 21 below.

Scenario Request

Type

Number

of days

Dates (dd/mm/yyyy) Start

time

Duration

(min)

Evening peak-shaving Decrease 1 21/02/2013 18:15 15

Evening peak-shaving Decrease 3 27/02/2013 to 12/03/2013 18:30 15

Morning peak-shaving Decrease 4 14/03/2013 to 03/04/2013 07:45 30

Special evening peak

shaving (sport on TV)

Decrease 1 16/03/2013 21:15 30

DSO request Decrease 1 20/03/2013 09:45 30

DSO request Decrease 1 22/03/2013 11:00 30

DSO request Decrease 1 25/03/2013 10:00 30

DSO request Decrease 2 27/03/2013 to 28/03/2013 12:00 30

DSO request Decrease 2 28/03/2013 to 01/04/2013 17:00 30

Evening peak-shaving

in Spring time

Decrease 7 03/04/2013 to 10/04/2013 20:15 30

DSO request Decrease 8 11/04/2013 to 18/04/2013 11:15 30

Morning peak-shaving

at the end of Off-peak

period

Decrease 7 19/04/2013 to 25/04/2013 05:30 30

Night peak-shaving

(EWH)

Decrease 7 26/04/2013 to 02/05/2013 02:00 30

To shift consumption

during wind turbine

production

Increase 2 04/05/2013 to 09/05/2013 02:30 60

To shift night peak Increase 12 05/05/2013 to 31/05/2013 03:30 60

Night peak-shaving

(EWH)

Increase 5 06/05/2013 to 13/05/2013 03:00 60

Page 84: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 84 of 126

Scenario Request

Type

Number

of days

Dates (dd/mm/yyyy) Start

time

Duration

(min)

To shift consumption

during wind turbine

production

Increase 1 12/05/2013 04:00 60

To shift consumption

during PV production

Increase 6 17/05/2013 to 22/05/2013 13:30 60

To shift consumption

during PV production

Increase 9 23/05/2013 to 31/05/2013 11:00 60

Table 21. French field tests scenarios

5.1.5.4 Market simulator or MS

5.1.5.4.1 General assumptions

Several assumptions are made in order to test effective impact of AD on an electricity market. We

assume that:

- Each entity develops a consolidated portfolio strategy, has a good knowledge of his costs and is

able to forecast wholesale market prices efficiently. It is thus able to trade-off between his costs

and his potential gains using this information;

- We only focus on a global electricity market: the national exchange market. In fact, the rules for

the national power exchanges are clearly defined. It is also fully representative of the price

determination processes used in the power markets and all the data required for the simulation

are public. We did not consider local markets;

- When assessing AD provider’s costs, Task 5.4 assumes that the AD offers have a marginal

impact on the wholesale market, i.e. they do not affect the wholesale prices [9]. This is the

assumption used by the ATB platform when defining its AD offers. On the contrary, the main

objective of the market simulator is to illustrate the potential impacts of AD on these prices. Both

approaches are thus complementary.

- Each aggregation entity uses its internal market price forecasts, the flexibility available in its

consumers’ portfolio and the consumers’ preferences (focus on comfort, savings…) in order to

identify the optimal time slots for the AD volumes to be proposed to the market. Like in Task 5.1

and Task 5.4, we choose to adopt an “epsilon” margin around the forecasted market prices.

When testing the price sensitivity, several margin values were considered. They ranged from

10% to 40% below the forecasted market prices when offering AD products reducing demand

and from 10% to 40% above the forecasted prices when offering AD products increasing

demand3. Hence, this strategy aims at guaranteeing his AD products will be retained with a high

probability in the merit order when his forecasting are pertinent; in the other cases, losses are

limited thanks to the margins adopted.

- In the scenarios tested, we assume that only one aggregation entity is representing all the offers

from the different aggregators existing in the market. Using a price-volume signal, it is able to

manage the Electric Water Heaters (EWHs). The aggregation entity earns money by taking

3 In order to make the margin significant for market prices around zeros (0€), we have added (subtracted) one

euro (1€) to this margin. This is required since the margin is computed relative to the market price itself.

Page 85: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 85 of 126

advantage of appropriate load shifting on the Spot Market.

5.1.5.4.2 EWH scenarios

In these scenarios, we focus on a specific appliance, the “electric water heater” (EWH). This choice

was made for two reasons:

1. It is a common appliance in France: 9 millions of households are equipped and most of them

with thermal storage (see the description on Deliverable D6.1 [1]);

2. The French field tests showed positive results concerning the shifting of these devices.

The best time slots for EWHs activation are identified while ensuring comfort criteria.

First, we ran the market simulator in order to replay situations that were observed in the actual

French market. These tests were performed with the two market simulators, the one developed by

VTT (TS_MS_Java) and the one developed by EDF (TS_MS_Excel) as an alternative to bypass

some of the other tool limitations. We mainly focused on market situations characterized by unusual

market prices. Two different situations were considered in particular:

One with high market prices (9th February 2012 during the cold period where prices reached

1938€ / MWh in France). The corresponding test cases are TS_MS_Java – 1 to – 3 and

TS_MS_Excel – 1 to – 3 (described in D6.1 [1]).

One with negative market prices (25th December 2012 where the transitory situation caused

by high wind generation made prices drop to -50 €). The corresponding test cases are

TS_MS_Java – 4 to – 6 and TS_MS_Excel – 4 to – 6.

Then, we created an intermediate scenario using the field test flexibility and where the ATB was

bypassed (TS_MS_FRAD – 01). The incentive signals were selected manually on the basis on our

own specifications resulting from market forecast and put in the ATB database to be sent and

applied by the EBoxes. The resulting flexibility response observed in the field was introduced back

into the market simulator (with the appropriate scaling) in order to assess its impact on the market

prices.

The data we use for the EWH scenarios are public. They concern the electrical consumption of the

EWHs in France. The following simplified assumptions have been retained for illustrative purpose. It

is to be noticed that they correspond to a nearly ideal situation from the aggregation perspective.

The unit power of one EWH is around 2 kW and we have about 9 million EWHs controlled in

France. That gives us a global theoretical power of 18 GW. However, we apply a correction

(division) factor of two in order to take into account every constraint that acts on the EWH.

With this assumption, we get a global shiftable load of 9 GW in France.

Since the average heating time of an EWH is of about six hours, the maximum storage

capacity is 54 GWh. It leads us to a consumption of 20 TWh over a year.

In order to be coherent with the volumes treated in the French market and the ones

manipulated by the aggregation entities, the EWH volumes have been scaled (only 15.3%4

of the global volumes were considered for the scenarios)

From public data, we have been able to create a profile that depends on the month, the day

of the week and the hour. An overview of these profiles is given below (Figure 54.).

4 For a given day, MAX EWH power of the day / MAX national demand of the day. This ratio is then multiplied

by the MAX spot power of the day for estimating the EWH potential of the day.

Page 86: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 86 of 126

Figure 54. Illustration of different consumption profiles.

The minimum average sourcing cost can be reached using as much as possible the EWHs

heater at night, when the prices are low. It supposes that the storage is empty at the

beginning of the night. On the contrary, if the storage were at the maximum at night, we

should have to wait until the morning when the consumer begins to use hot water and the

individual prices are higher.

We assume that the aggregation entity has an exact knowledge of the D+1 market prices,

i.e. no error is made on the price forecast. Ideally, the aggregation entity would know the

D+2 and D+1 prices considering the daily profile consumption.

Two options were considered when choosing the reference power, Ptref., i.e. the quantity

used by the aggregation entity to prepare its offers.

o Using the load corresponding to the water consumption. We consider that the relay

controlling the load is always ON. So, the EWH is started as soon as the water

temperature becomes lower than the set point temperature limit.

o Using the load corresponding to the real energy consumption of the EWHs, i.e.

taking into account the control of the starting time thanks to the relay. This reference

is already optimized in order that the consumption of energy will be in the off peak

periods of the day (periods with individual lower prices).

The latter option was chosen because the prices we use for the tests (spot EPEX 2012) are

directly related with the EWH load controlled by the relay. The chart below (Figure 55.)

represents the average daily consumption profile (from 6:00 pm to 5:00 pm in D+1). It takes

into account the national repartition of the off-peak period (not every EWH is managed in the

same way). We will use this similar distribution for every day of the week to simplify our

cases.

Figure 55. Daily EWH consumption profile used for the tests.

Page 87: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 87 of 126

5.1.5.4.3 ATB and MS interaction

In day-ahead, the aggregation platform takes into account the flexibility requests expressed by

bilateral contracts (if any) and proposes the remaining flexibility volumes to the electricity market at

specific prices. The acceptance of the proposed flexibility is then taken into account by the

aggregation platform to define the signals to be sent to each consumer cluster. The optimization

algorithms of the ATB platform also take into account the flexibility constraints imposed by the DSO

for each Load Area in order to ensure the technical feasibility of the chosen signals.

Once the signal selection has ended, the chosen incentive signals are applied on the field.

It is to be noted that up-scaling factors are applied to the offered volumes proposed to the market in

order to make their impact more significant. The inverse scale is then applied to the accepted offer

volumes when the market responds to the aggregation platform. Because of limitations of the current

ATB implementation, the acceptance factor of the volumes corresponding to the payback effect of

the proposed offers cannot be taken into account by the ATB following optimization; only the offered

volume can be modulated by the market acceptance.

5.2. Results

As previously mentioned the field tests in France were mainly focused on assessing the operation

and the performance of the complete ADDRESS chain. The test cases and the detailed test scripts

are given in Chapter 8 and in the Appendix of Deliverable D6.1 [1].

In this Section, the main results of these tests are presented. A detailed description of a complete

test case is also given and the results obtained at each step are illustrated.

5.2.1. Test execution

The table below presents an overview of the tests execution performed during the French field tests

on the complete platform sequence. The column “Successful” indicates whether the successive

steps of the test scripts were carry out successfully or not but does not give any information on

regarding the effective delivery of AD flexibility. The results of the tests in terms of AD delivery are

given in Section Errore. L'origine riferimento non è stata trovata..

NB: For a detailed description of the test scripts, please refer to Deliverable D6.1 [1].

Function Code ID Objective Success

ful

Load decrease

services

TS_CAT3_Loa

d_Dec

1 AD request from the DSO for local overload reduction

OK

2 AD request from the TSO for global congestion reduction

OK

3 AD request from the BRP for imbalance management OK but

ATB

Page 88: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 88 of 126

Function Code ID Objective Success

ful

bypassed

5

Requests in

combination

with RES

TS_CAT3_Loa

d_Dec

1 AD request to avoid curtailment of a PV plant due to voltage constraint

OK

2 AD request for compensating the peak production of a mainland wind farm

OK

Over-a-day

global load

limitation

TS_CAT3_OA

D_Lim 1

AD requests from the DSO for an over-a-day global load limitation

OK

Market

Simulator

TS_MS_Java

1,3

4,6

Wholesale market prices estimation based on forecasted demand and supply

Evaluation of the MS accuracy given the number of

price/volume couples

OK

2,5 Estimation of the AD impact on the wholesale market prices using the EWH as a shiftable device

Failed6

TS_MS_Excel 1 to 6

Wholesale market prices estimation based on forecasted demand and supply

Estimation of the AD impact on the wholesale market prices using the EWH as a shiftable device

Estimation of the impact of the prices of AD offers

on the earnings / savings

OK

TS_MS_FRAD 1 Test of MS with AD offers related to the load shifting observed in the field tests

OK

Integration of

an electricity

market

TS_CAT3_MA

R_INT 1 Provision of AD services to an electricity market OK

Table 22 - Test execution overview

5.2.2. Assessment of the technical performance on the consumer side

5.2.2.1 Management of the consumption by the Energy Box

As previously mentioned, the management of the electrical heaters defined as Thermal Loads was

not possible due to technical issues: as a consequence, it was decided to declare the electrical

heaters as shiftable loads. Regarding the EBox specifications, it performs the consumption

management of the controlled devices even in the absence of request coming from the aggregation

platform, i.e. it optimizes the consumption of the house without any request:

Interruptions are carried out during peak periods so that the savings are maximum for the

consumers;

5 The ATB platform had to be bypassed because load increase signals were always selected by the ATB algorithm: instead

of using the direct effect of load decrease signals, the payback effect of load increase signals was selected. Load decrease signals were thus selected manually. 6 For several hours, the MS gives unrealistic results significantly different from the ones expected from a

theoretical point of view. The calculation of earnings/savings cannot be done without knowing the part of the aggregator's offer that has been accepted by the market.

Page 89: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 89 of 126

The optimization is done to save a maximum amount of energy, i.e. at the end of the day all

the interruptions allowed by the configuration specified in the EBox for the interruptible loads

have been made;

The distance between two consecutive interruptions is set so that the impact on the

consumer’s comfort limited;

When the priority is given to money savings, Shiftable Loads start during off-peak periods.

Moreover, several issues have been encountered during the field operation, such as:

- A default in a Wall-Unit.

- Stop in the execution of the EB software when a Smart Plug or a Wall-Unit is switched off. In

this situation, the load remained switched off until a remote manual action is undertaken to

restart the EBox software.

- Communication errors between the EBox and the Smart Plugs or the Wall Units. In that case

the EBox doesn't receive power measurements and is not able to send ON/OFF orders.

- The distance between the EBox and the Smart Washing Machine must be short in order to

ensure their communication.

NB: according to the privacy rules applicable in France, we are not allowed to present individual

results recorded in a consumer house, even if these results are anonymized. Consequently, in the

following sections, we will illustrate results obtained at consumers in the French field tests with

similar individual data recorded during the EDF lab tests in the multi-energie house and with

aggregated results obtained on the field.

5.2.2.2 Peak-Shaving using Interruptible Loads

After a signal is received, the EBox runs an optimization to calculate the interruptions of the

controlled appliances. If interruptions are still available (i.e. the total number of interruptions for the

day is not reached) and the economic incentive sent by the aggregation platform is high enough, the

appropriate interruptible loads are switched off at the requested time in order to reduce the

consumption below the required power.

AD request

Start (date & time) Duration (min) Limit (kW)

15-03-2013 07:45:00 30 0.05

The objective of this price-volume signal is to limit the power of the house below 0.05 kW during

30 minutes. The result is presented on Figure 56..

Page 90: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 90 of 126

0

200

400

600

800

1000

1200

1400

0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 0:00

Watts

P Heater 1 (W ) P Heater 2 (W ) P Heater 3 (W ) P Heater 4 (W ) P Heater 5 (W ) P Heater 6 (W )

Scheduled interruption

Figure 56. Interruptible Loads – Peak-Shaving.

The six electrical heaters (declared as interruptible loads) are switched to an OFF state by the EBox

between 7:45 and 8:15.

5.2.2.3 Limited Peak-Shaving using Interruptible Loads

In this second example of peak-shaving, the AD request is partially satisfied.

This price-volume signal requests a consumption below 0.1 kW between 20:00 and 20:30. As can be

seen in Figure 57., the four electrical heaters are interrupted from 20:00 to 20:15 and not until 20:30.

So the load decrease request is only partially satisfied. The reason is that one of the electrical

heaters is configured in the EBox with an interruption duration of 15 minutes only, for the comfort of

the users. Due to the request threshold at 0.1 kW, the EBox cannot find a solution for the second

half of the request.

AD request

Start (date & time) Duration (min) Limit (kW)

30-03-2013 20:00:00 30 0.1

0

200

400

600

800

1000

1200

0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 0:00

Watts

P Heater 1 (W ) P Heater 2 (W ) P Heater 3 (W ) P Heater 4 (W )

Scheduled interruption

Figure 57. Interruptible Loads – Limited Peak-Shaving.

Page 91: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 91 of 126

5.2.2.4 Shiftable Load: Electrical Water Heater

In this case, the EWH is declared as a shiftable load.

The applied AD requests are designed for shifting the consumption and are sent twice to the EBox

during the day first at 15:30 and then at 21:00. There are two power thresholds in order to be sure

that the request will be satisfied by the interruptible loads and by the shiftable loads. The results of

these requests are presented in Figure 58..

AD requests

Start (date & time) Duration (min) Limit (kW)

07-05-2013 15:30:00

&

07-05-2013 21:00:00

60

1.0

2.5

9999999.0

At 14:05, the EBox detects the start of the consumption measured by the Wall Unit of the EWH. The

EBox sets this Wall Unit into an OFF-state and calculates its next start time taking into account the

AD request, the user's preferences and the tariff. Then, at 15:30 (the request time), the EBox sets

the Wall Unit back into an ON-state: the EWH works until water temperature inside the EWH is hot

enough. At 18:15, as the water temperature is below the EWH temperature threshold, the EWH

starts again. This restart is detected by the EBox which sets the Wall Unit into an OFF-state again

and calculates the next start time at 21:00 according to the second AD request (Wall Unit back into

an ON-state).

0

500

1000

1500

2000

2500

00:

00

01:

00

02:

00

03:0

0

04:0

0

05:0

0

06:0

0

07:

00

08:

00

09:0

0

10:0

0

11:0

0

12:0

0

13:0

0

14:

00

15:

00

16:0

0

17:0

0

18:0

0

19:0

0

20:

00

21:

00

22:

00

23:0

0

Watts

Figure 58. Shiftable load – EWH.

Page 92: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 92 of 126

5.2.2.5 Shiftable Load: Smart Washing Machine

In this case, the shiftable load is the ADDRESS Smart Washing Machine (SWM). The applied AD

request is designed for shifting its consumption:

AD request

Start (date & time) Duration (min) Limit (kW)

25-04-2013 16:15:00 45 2.89

9999999.0

The power threshold (2.89 kW) is adjusted in order to be sure to shift the SWM because this EBox

manages also several interruptible loads.

The results of this request are presented in Figure 59..

At 14:45, the user starts his/her SWM, selects a washing program and sets the SWM in "remote

mode". Then, the EBox receives the consumption profiles from the SWM, calculates the next start

time for 16:15 (time of the AD request) and sends this start time to the SWM. At 16:15 on the clock

of the SWM, the washing program is started.

0

500

1000

1500

2000

2500

3000

3500

00:0

0

01:0

0

02:0

0

03:0

0

04:0

0

05:0

0

06:0

0

07:0

0

08:0

0

09:0

0

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

Watts

Figure 59. Shiftable Load – SWM

5.2.2.6 Unsuccessful or limited peak-shaving

During the French field tests, several scenarios of peak shaving were unsuccessful or limited. These

situations were a consequence of the EBox parameters concerning the interruptible loads:

When an AD request is set in intraday and late in the day, it could happen that there is no

solution: for instance for this day, all possible interruptions have already been used by

several or all the interruptible loads because of the normal behavior of the EBox as an

Energy Manager.

Page 93: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 93 of 126

When the power threshold of the price-volume signal is small and the number of possible

"available offs" is limited.

5.2.2.7 Energy Box communication errors

5.2.2.7.1 Between the EBoxes and the appliances (Smart Plugs or Wall Units)

The communication errors between the EBox and the Smart Plugs or Wall Units recorded during the

French Field Tests are given in Figure 60..

5.2.2.7.2 Between the EBoxes and the ADDRESS control center in Clamart

During the French field tests, a supervision system was designed so that the EBoxes installed in the

consumers’ house send all their data (data from the so-called IDM file) to the ADDRESS control

center (located in the EDF site of Clamart, close to Paris). This sending first occurred on a daily

basis and later on a 15 min basis. The rate of success of the communication between the EBoxes

and the ADDRESS control center is presented in Figure 61..

0,0%

5,0%

10,0%

15,0%

20,0%

25,0%

30,0%

February March April May General

Ave

rage

ap

plia

nce

co

mm

un

icat

ion

err

or

Figure 60. Communication errors observed during the French Field tests.

Page 94: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 94 of 126

Figure 61. Rate of success of communication between the EBoxes and the ADDRESS control center.

5.2.2.8 Overrides

With the User Interface of its EBox, each consumer can use the override whenever he/she needs it.

Figure 62. shows the override rates observed during the French Field tests.

0,0%

0,5%

1,0%

1,5%

2,0%

February March April May General

Ave

rage

ap

plia

nce

ove

rrid

e

Figure 62. Override rates observed during the French Field tests.

5.2.3. Provision of AD services at a cluster level

5.2.3.1 Evaluation of the obtained AD volumes at a cluster level

The precise evaluation of the AD flexibility delivered at the cluster level is very difficult. The issue

comes from the definition of the “baseline”, i.e. the reference curve representing what would have

been the behavior of the cluster without any incentive signals and to which the consumption curve in

Page 95: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 95 of 126

presence of incentive signals is compared to assess the delivery of the AD products. This issue is

even more complex in case of small clusters like the ones we have in the French field tests. Indeed

in case of large clusters, i.e. clusters composed of hundreds of consumers, the variability of their

consumption may be reduced and the baseline computation of the clusters would less sensitive.

The difficulties encountered when computing the baseline originate from several factors.

The consumption curve of individual consumers presents a high variability from one year to

another and even from one day to the next. This observation already holds for consumers

not using local energy managers or taking part into AD experiments. It is all the more

accentuated when devices influencing the appliance consumption are involved.

The EBoxes act as energy managing devices when no incentive signal is sent by the

aggregation entity. They automatically shift or interrupt some of the appliance consumption

depending on the consumers’ preferences. This standalone operating mode introduces new

modifications to the “natural” consumption curve.

The incentive signals sent by the aggregation entity for increasing or decreasing the global

load of the household modify the initial placement of the appliance consumption. The

response of the AD devices will depend on the remaining flexibility available at the time of

the request and on the consumer’s preferences.

All this variability remains at the cluster level when it only consists of a reduced number of

consumers.

It is to be noticed that the baseline can be either defined as the consumption of the cluster without

any automated influence (cluster without ADDRESS-like systems) or its consumption when no

incentive signal is sent (cluster with ADDRESS-like systems acting only as energy managers). This

definition will have to be addressed by the regulation. The TSOs, DSOs, AD providers and retailers

should work together in order to agree on this definition, but also on a method for measuring and

computing the delivered AD for each load area (LA) and macro load area (MLA) regarding the AD

products which have been previously submitted and validated.

Many methods are currently studied in order to compute a reliable baseline that can be used for

assessing, controlling and remunerating the flexibility provided by AD at consumer or cluster levels:

forecasting based methods, control groups based methods...

The methodology used for the French field tests is presented in the following paragraphs. In our

study, we considered that the baseline is the cluster consumption without any automated influence

(1st possibility). This choice was motivated by the data available for the analysis.

5.2.3.1.1 Methodology for the baseline computation

The methodology applied for this analysis uses simplified processes because of the limited data

available: reduced number of observations with a same incentive, limited number of consumers in

the clusters… It should also be noted that the proposed method may no longer be appropriate if AD

requests were to be applied over a long time, i.e. if they affect both the reference and the

observation intervals.

Two data sources were available for assessing the AD flexibility provided by the incentive signals:

the consumption data collected by the smart meters installed by the French DSO (ERDF) and the

data regularly sent by the EBoxes. We mainly used the consumption measured by the smart meters

since the consumption data measured by the EBoxes were not available for an as long period as

Page 96: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 96 of 126

those collected by the meters and additionally they were corrupted over some time periods. The

metered data cover the period from December 2011 to May 2013, i.e. to the end of the French

experiment.

The construction of the baselines is based on the historical consumption and weather data from

December 2011 to June 2012. This interval is referred to as the “comparison interval”. An individual

reference profile is computed for each consumer and each day where an incentive signal was sent

by the aggregation entity to the EBoxes. These references are then aggregated to compute the

baseline of the cluster.

The methodology used consists of several steps (Figure 63.). They are applied to each day when an

AD request was submitted. Let explain the process for a specific day referred to as the “studied day”.

(1) First selection of equivalent days regarding weather data

A first characterization quantity, i.e. the average wind chill7 temperature, is computed for the

studied day. It is compared with those computed for all the days of the comparison interval.

The days with similar average wind chill temperatures are kept for further analysis. A two

degree difference is allowed.

7 The wind chill is the air temperature perceived by the body on exposed skin due to the flow of cold air.

Page 97: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 97 of 126

Figure 63. Main steps of the methodology used for computing the cluster baselines.

(2) Consumption profile sorting based on median value

The median value of the consumption profiles observed for the days selected with the

temperature information is then computed. This second characterization quantity allows us

to discriminate the profiles whose median values are very different from the one calculated

during the studied day. These medians are not computed with the consumption curve

considered over a whole day; the time interval is chosen in order to improve the probability

of finding matching curves. Figure 64. illustrates the distribution of the differences observed

between these two medians before any corrective measure is applied. These differences

come from different factors such as days where the consumers are absent, etc.

Only the consumption profiles whose median difference is small are kept. These profiles are

referred to as the “daily group”. They are weighted depending on their similarity with the

profile observed over the studied day. Those matching the most are preponderant.

Selection of

equivalent days

Median based

sorting

Daily reference

computation

Median bias

correction

Series reference

computation

Cluster reference

computation

Historical wind-chill data

D-day wind-chill profile

Historical consumption profile

D-day consumption profile

D-day

C-consumer

Consumer

Level

Cluster

Level

D-day is the last

of the series?

C-consumer is the

last of the cluster?

Yes

Yes

No

No

Page 98: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 98 of 126

Figure 64. Raw distribution of the median of the consumption profile of the weather selected groups.

(3) Median bias correction of the “daily group” at consumer level

When studying the load curves of daily groups, it was noticed that many of them presented a

similar behavior but could not be used as such as a reference because the load profile was

shifted by a few hundred watts (Figure 65). In order to compensate this shifting, the median

values of the consumption profiles are used again. The offset observed between the studied

day and each curve of the daily group is brought back to zero.

7500

12500

17500

22500

27500

32500

0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00

Po

we

r (W

)

Time (h)Realized Baseline Raw Baseline

Figure 65. Example of offset observed between the mean load curve of the daily group and the load curve observed over a day

(4) Daily reference computation at consumer level

The average consumption curve of the daily group profiles is computed once their median

has been corrected. This average profile can be used as a comparison reference with the

consumption profile observed during the studied day in order to assess the load decreases

or increases induced by the incentive signals sent by the aggregation entity, as well as their

payback effect. The profile is referred to as the “daily reference”.

At the end of these 4 steps, we have constructed a reference consumption profile for each

consumer and for each day where AD requests were submitted by the aggregation entity.

(5) Series reference computation at consumer level

On the field, series of identical AD requests were applied, i.e. incentive signals with the

same characteristics (timeslots, volumes and prices) were sent to all the consumers of a

Page 99: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 99 of 126

cluster several days in a row. These series are meant to assess the variability of the

response of a consumer to the same signals as well as the average response of the

consumers to these signals. For this purpose, two additional consumption curves are

computed using previous data as a basis.

(1) The “average series reference” is calculated using the consumption profile of every

daily reference determined for the days composing the series.

(2) The “average series response” is calculated using the consumption profiles

submitted to AD requests of the N days composing the series. It corresponds to the

average response profile of the consumer to a specific AD flexibility request.

Both curves can be compared to evaluate the mean load increase or decrease that can be

expected for each active consumer when submitted to the same signal characteristics.

(6) Series reference computation at cluster level

The two references previously computed at a consumer level are aggregated to constitute

the comparison references of the cluster. They are used to assess the cluster response to

specific AD requests.

5.2.3.1.2 Examples of computed baselines and associated consumption profiles

The methodology was applied to all the incentive signals applied on the field. In Figure 66. and

Figure 67. are represented the baselines computed using this method and the average consumption

profile obtained during the considered series.

It can be seen that whereas in some cases the increase or decrease clearly appears and can be

quantified in other cases it is much more difficult. Only a thorough analysis might say if this is due to

the baseline which is not appropriate for this day or to the absence of response (or very limited

response) of the cluster.

32500

37500

42500

47500

52500

15:30 16:30 17:30 18:30 19:30 20:30 21:30 22:30

Po

we

r (W

)

Time (h)

Realized Baseline

17500

22500

27500

32500

37500

42500

18:15 19:15 20:15 21:15 22:15 23:15 0:15 1:15

Po

we

r (W

)

Time (h)Realized Baseline

Figure 66. Example of cluster responses to load decrease requests.

Load decrease

signal

Load decrease

signal

Page 100: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 100 of 126

7500

12500

17500

22500

27500

8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00

Po

we

r (W

)

Time (h)

Realized Baseline

7500

12500

17500

22500

0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00

Po

we

r (W

)

Time (h)Realized Baseline

Figure 67. Example of cluster responses to load increase requests.

5.2.3.2 Impact of AD on the consumption profile of a cluster

5.2.3.2.1 AD requests carried out

The results of the tested scenarios in the French Field tests are listed in Table 23.

Scenario Request

Type

Start

time

Duration

(min)

Result

1 Evening peak-shaving Decrease 18:15 15 OK

2 Evening peak-shaving Decrease 18:30 15 OK

3 Morning peak-shaving Decrease 07:45 30 Limited

4 Special evening peak

shaving (sport on TV)

Decrease 21:15 30 Failed

5 DSO request Decrease 09:45 30 Limited

6 DSO request Decrease 11:00 30 OK

7 DSO request Decrease 10:00 30 OK

8 DSO request Decrease 12:00 30 Limited

9 DSO request Decrease 17:00 30 OK

10 Evening peak-shaving in

summer time

Decrease 20:15 30 Failed

11 DSO request Decrease 11:15 30 OK

12 Morning peak-shaving at the

end of Off-peak period

Decrease 05:30 30 OK

13 Night peak-shaving (Water

Heaters)

Decrease 02:00 30 Failed

14 To shift consumption during

wind turbine production

Increase 02:30 60 OK

15 To shift night peak Increase 03:30 60 OK

16 Night peak-shaving (Water

Heaters)

Increase 03:00 60 OK,but

Limited

Load increase

signal

Load increase

signal

Page 101: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 101 of 126

Scenario Request

Type

Start

time

Duration

(min)

Result

17 To shift consumption during

wind turbine production

Increase 04:00 60 Failed

18 To shift consumption during

PV production

Increase 13:30 60 Limited

19 To shift consumption during

PV production

Increase 11:00 60 OK

Table 23. French field tests – Test results.

The meaning of the column "Results" is the following:

OK: the actions decided by the EBoxes had significantly modified the aggregated

consumption of the cluster of consumers.

Failed: there was no measurable effect on the cluster consumption.

Limited: there was a small or limited effect on the cluster consumption.

5.2.3.2.2 Examples of cluster responses to AD requests

The next four figures present examples curves of the average consumption per consumer of the

French Field test cluster for different scenarios listed in Table 23.

2000

2100

2200

2300

2400

2500

2600

2700

2800

2900

3000

15

:30

16

:00

16

:30

17

:00

17

:30

18

:00

18

:30

19

:00

19

:30

20

:00

20

:30

21

:00

21

:30

22

:00

22

:30

Watts

Realized Baseline

Figure 68. Evening peak-shaving - OK – Scenario No. 2 of Table 23.

Page 102: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 102 of 126

1000

1200

1400

1600

1800

2000

2200

2400

18

:15

18

:45

19

:15

19

:45

20

:15

20

:45

21

:15

21

:45

22

:15

22

:45

23

:15

23

:45

0:15

0:45

1:15

Watts

Realized Baseline

Figure 69. Evening peak-shaving - Failed – Scenario No. 4 of Table 23.

500

600

700

800

900

1000

1100

1200

1300

1400

1500

0:3

0

1:0

0

1:3

0

2:0

0

2:3

0

3:0

0

3:3

0

4:0

0

4:3

0

5:0

0

5:3

0

6:0

0

6:3

0

7:0

0

7:3

0

Watts

Realized Baseline

Figure 70. To shift night peak - OK – Scenario No. 15 of Table 23.

Page 103: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 103 of 126

200

400

600

800

1000

1200

1400

1600

1:0

0

1:3

0

2:0

0

2:3

0

3:0

0

3:3

0

4:0

0

4:3

0

5:0

0

5:3

0

6:0

0

6:3

0

7:0

0

7:3

0

8:0

0

Watts

Realized Baseline

Figure 71. To shift consumption during wind turbine production - Failed – Scenario No. 17 of Table 23.

5.2.3.3 Impact of AD on the energy consumption

5.2.3.3.1 Methodology

In this paragraph, we present the methodology used for assessing, at a global level, the possible

changes in the energy consumption that may result from the installation of the EBoxes.

Context and data available

The period considered for this analysis covers the period of the French field tests, i.e. from

December 2012 to May 2013. For comparison purpose, the same period is considered for the year

2011/2012 when no EBox was installed in the Brittany islands.

Several issues had to be solved when conducting this study. Some of them are explained below:

Most of the consumption data sent by the EBoxes are not reliable enough during the period from

the beginning of the experiment to mid-February because of erroneous data measurement

(which was solved later) and communication issues. These problems persisted for some boxes

after February. Consumption data measured by the smart meters installed by ERDF are

therefore used instead. In fact, even if their measurements also present some missing data, they

are far more reliable.

The measured consumption is very dependent on the outside temperature: a large part of the

consumers’ consumption increases with decreasing temperatures and vice versa.

The variability typical of the studies focusing on single consumers, such as consumer

absenteeism, induced additional variability. Such discrepancies are not taken into account in this

study.

Constitution of the consumer panel

A selection of consumers had to be carried out in order to obtain comparable results. The

methodology used to separate the “ADDRESS” group from the “reference” one stands as follows.

Page 104: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 104 of 126

The two resulting groups of consumers are used for assessing the impact of AD on the energy

consumption.

Consumers with an EBox installed (“ADDRESS” group) and those without the ADDRESS

system are distinguished (“reference” group). When an EBox is installed but cannot control

any appliance during the whole period, the consumer is also attributed to the “reference”

group.

Only domestic consumers are considered. The consumption data are removed from the

study when the EBox is installed in public facilities.

A consumer is removed from the study when too many consumption data are missing during

the whole period or any of its sub-periods.

Normalization of the consumption curves against wind chill temperatures

The first treatment applied consists in correcting the power measurements with the outside

temperature, i.e. in taking into account the impact of weather changes on the consumption. The used

data are the wind chill temperature data from the Belle-Ile island weather station. It is the closest

weather station to the Houat and Hoëdic islands.

The treatment correcting the consumption data makes the following assumption: when daily

temperatures are equal, a consumer always displays the same consumption of electricity. Thus,

when two corresponding days present different temperatures, a correction is made according to the

wind chill temperature. In order to estimate this correction, we consider that a part of the domestic

electricity consumption is correlated with the outside temperature (heating appliances…) while the

other part is constant and does not depend on this parameter. Based on this assumption, a linear

relationship is established between the energy consumed per day and the day temperature.

We also reckon that temperatures over 16°C have a lesser impact on the consumption: over this

temperature, only the constant part of the consumption remains.

The average daily heating degree and the average wind chill are then computed on both considered

periods and based on this information, the 2013 consumption is corrected. This correction is

computed separately on peak hours and on off-peak hours and the results are then aggregated for

the whole cluster.

Assessing the changes in energy consumption on each sub-period of the field tests

The field test time is split into several parts related to the stages of the field deployment of the

EBoxes and of the testing scenarios. For each test period, the consumption is compared with the

consumption over the same period of the year before. Temperature and data corrections are

performed so that both periods can be compared and the volumes of the load variations can be

estimated. The comparison starts from December 1st 2012 since there is no observation before

December 1st 2011 and ends on May 31

st.

1st period: After the start of the EBox installation and before the incentive signals are sent on

a regular basis (from December 1st until February 14

th);

2nd

period: From the start of the regular sending of load decrease incentive signals to the

EBoxes (February 14th to May 3

rd);

3rd

period: Load increase incentive signals sent during off-peak hours (May 4th to May 22

nd);

4th period: Load increase incentive signals sent during peak hours (May 23

rd to May 31

st).

Page 105: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 105 of 126

5.2.3.3.2 Results

Table 24 presents the consumption of the two groups of consumers considered during the French

field tests: the “ADDRESS” group consisting of all the consumers whose appliances are controlled

by EBoxes and the “Reference” group where no ADDRESS system was installed. For each group

and each year, the mean consumption (raw) observed during the periods of the day with low

electricity price (LP), i.e. the off-peak periods, and the one observed during high price (HP – peak

period) is presented. The result of the volume correction performed with previous method is

illustrated and the resulting energy consumption variation between 2012 and 2013 is expressed.

Group raw

2012 HP raw

2012 LP raw

2013 HP raw

2013 LP corrected 2013 HP

corrected 2013 LP

Mean Consumption Variation

ADDRESS 3306.73 2208.03 3734.75 2393.26 3161.19 2096.43 257.13

Reference 2319.98 1645.20 2449.10 1752.41 2074.94 1632.42 196.55

Table 24. Mean energy consumption of ADDRESS and Reference groups during the period of the French field test (all figures in kWh)

Table 25 presents the variations of the off-peak consumption ratio (LP/Total ratio where

Total=LP+HP) in presence of the ADDRESS systems: the off-peak consumption ratio (raw) is

presented for both groups and years and the corrected ratio for 2013.

Group Raw

LP/Total ratio 2012 Raw

LP/Total ratio 2013 Corrected

LP/Total ratio 2013

ADDRESS 0.407 0.395 0.403

Reference 0.545 0.552 0.558

Table 25. Variation of the off-peak consumption ratio in presence of ADDRESS systems

Both for the ADDRESS group and the Reference group, the mean variations between 2012 and

2013 in Table 24 correspond to energy reductions. So the EBoxes as well as the actions they trigger

when performing standalone optimizations or when responding to flexibility requests do not seem to

have a negative effect on the global energy consumption since the energy reductions observed for

the ADDRESS group is of the same order of magnitude (around 5%) as the one obtained for the

Reference group. They do not seem to have an impact on the share between LP and HP energy

consumptions either. The differences between the two groups are not significant enough to be able

to conclude to a positive effect of the EBoxes on the energy consumption.

NB: it should be recalled that the objective of ADDRESS at the consumer level is not to reduce the

energy consumption but rather to shift the consumption to times that more beneficial for the

electricity systems as a whole [10], [11].

The above results should be considered with great care because:

the energy consumption between the two groups is not equivalent in terms of total energy

consumption even though both categories of consumers have the same types of electric

equipment. The size of the two groups is too small to avoid having a few consumers with a large

influence on the results for the whole group.

Possible changes in the consumers’ individual behavior (holidays…) can also greatly influence

the results considering the size of the groups and the limited historical data available.

Page 106: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 106 of 126

The duration of the field tests is too short to allow to derive more conclusive results on such

topics.

5.2.4. Market simulator

5.2.4.1 EWH scenarios

5.2.4.1.1 Methodology

The whole process applied when running the Market Simulator (MS) in the EWH scenarios is

presented in Figure 72..

In the first step, we run the MS with only global forecasted data (offer and demand). These volumes

originate from exchanges between different actors (DSO, TSO, aggregation entities, BRPs…) that

sell or buy volumes depending on their needs and their resource availability. All of these volumes are

aggregated into one global offer and one global demand.

The purpose of this 1st step is to determine the forecasted market equilibrium without any AD offers.

In real life, the global demand and offer volumes are forecasted based on the historical values.

However, in our scenarios, the bids are read from the public historical curves. Using this information,

we construct a reference (SPOT prices) to compare the results of MS with.

In a second step, load shaping is performed. For the scenarios of December 25th and February 9

th, it

consists in changing the daily EWH reference consumption that has been shown in Figure 55. in

order to optimize the purchasing expenses. This shifting isn’t totally free as it highly depends on the

consumers’ usage. The challenge is to find the best shifting that satisfies the following points:

- The new load positioning has to satisfy comfort constraints;

- The shifting appreciation regarding the spot price is maximum.

It is to be noticed that the initial placement of the French EWH’s consumption is already statically

optimized from a consumer-only point of view. However the aggregation entity, by having accurate

price forecasts, can improve this optimization and be rewarded for providing additional services.

The output of this load shaping step is summarized in Figure 73. and Figure 74. where:

The green curve represents the normal energy consumption for EWH during this day.

The blue one represents the forecasted EPEX spot prices8.

The grey curve represents the usage of hot water;

The red curve represents the optimized placement of energy consumption for the EWH

considering the constraints discussed above.

The difference between the optimized consumption and the reference consumption is considered as

the volume of the AD offer. Negative AD Volumes mean that the aggregator proposes a load

decrease for the concerned period, and positive ones mean that the aggregator/retailer will purchase

this extra volume compared to the reference placement (load increase).

NB: the sum of the optimized consumptions over the day is equal to the one of the reference

consumptions; thus the total of AD volumes is equal to 0.

In the third step, we adopt a 20% margin around the real market prices in order to introduce

uncertainty in our calculations: 20% below the market prices when offering AD products reducing

demand and 20% above the forecasted prices when offering AD products increasing demand. The

impact of the value of this margin on the results is also studied here.

8 The real EPEX Spot prices of the considered day are used for the simulations.

Page 107: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 107 of 126

The MS is then run a second time after integrating the AD offers to obtain the new equilibrium points.

The fourth step, i.e. the exploitation of the results given by the MS, will be presented and discussed

in the Deliverable D6.3 Errore. L'origine riferimento non è stata trovata..

Page 108: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 108 of 126

Figure 72. Steps for running the Market Simulator with aggregation entity’s offer9

9 For the tests, the AD prices will be calculated using the real SPOT market prices instead of the forecasted ones as shown Errore. L'origine riferimento non è

stata trovata..

Page 109: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 109 of 126

Figure 73. Illustration of the load shaping of EWH consumption for the first scenario.

Figure 74. Illustration of the load shaping of EWH consumption for the second scenario.

5.2.4.1.2 Results

The following tables (Table 26 and Table 27) summarize the results obtained when running the

whole MS processes on the considered EWH scenarios.

As we can see, the equilibrium prices decrease when the aggregator offers a load decrease and

increase when it consumes more than it is supposed to. The average difference between the two

Page 110: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 110 of 126

equilibrium prices (Equilibrium Price 2 – Equilibrium Price 1) over the 24 periods is -1,1 €/MWh for

the first scenario and +0.5 €/MWh for the second one. This indicator shows that the AD offers

globally implied a decrease in the market prices. However, the real impact on the purchasing

expenses should rather be weighted by hourly volumes depending on the part of the AD volumes

that has been accepted by the market. This impact will be discussed in the report D6.3 [12].

In order to assess the functioning of the MS, the prices for the equilibrium 1 were compared to the

real SPOT prices that were observed during this day. The purpose is to validate the equilibrium

calculation algorithm that allows obtaining the equilibrium points.

As we can see in Table 28 and Table 29, the results are satisfactory and the relative difference is

lower than 1%. However, for some periods (the 8th and 13th periods in Table 28 for example), the

difference becomes significant. It is related to the sampling of the demand and offer’s data for some

specific periods where these two curves are similar around the SPOT price10

. This shows that the

MS is very sensitive to the input data: for each hour, the more offer and demand points we have

around the forecasted equilibrium the more effective and reliable the results of the equilibrium

calculation algorithm will be.

10

This constraint is explained and illustrated in the methodology paragraph (§5.2.1.3.1.15.2.4.1.1).

Page 111: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 111 of 126

Table 26. Test results for the scenario of the February 9th

, 2012.

Page 112: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 112 of 126

Table 27. Test results for the scenario of the December 25th

, 2012.

Page 113: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 113 of 126

Table 28. Comparison of the results with the real SPOT prices of the February 9

th , 2012

Table 29. Comparison of the results with the real SPOT prices of the December 25

th , 2012

5.2.4.2 Electric water heaters from the field test

5.2.4.2.1 Methodology

In this case, the methodology is quite the same as the one of the two previous EWH scenarios. The

only change occurs in the load shaping step: since we use the load shifting that has been obtained in

the French field tests rather than the consumption whose placement was optimized, we no longer

need to run the placement optimization tool.

On the field we succeeded to shift the consumption of 10 water heaters (2 kW each): 5 of them were

shifted from May 24th at 11:00pm to May 25th at 4:00 am and 5 were shifted from May 25th at 1:00

am to may 25th at 5:00 am.

Since the real clusters are supposed to be much bigger than the one considered in the French field

tests, the shifted consumption of the EWH was simply multiplied by 500 in order to have more

significant AD offers to propose to the market (10 MWh).

5.2.4.2.2 Results

Compared to the 2 first scenarios, the volumes for AD offers are considerably lower. The impact on

the market prices is thus not as significant as they are in the 2 first scenarios. However we can

notice that, for the 7th period, the 10 MWh load increase has changed the market price by a value of

0.334 €/MWh.

Page 114: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 114 of 126

Table 30. Test results for the scenario of May 24th and 25th, 2013

5.2.4.3 ATB and MS interaction (simulation day: December 24th 2012)

5.2.4.3.1 Methodology

The volumes of AD offers are calculated in two different situations for the scenario of December 24th:

1. The first one is the load shifting of the French EWH (same global volume and different

consumption hours),

2. The second one is the output of the Aggregation Tool Box (ATB) that has been run with the

French field tests parameters.

In Figure 75, the AD flexibility volumes proposed by the ATB platform for two of the four Load Areas

considered are presented. The reduced volumes available in each cluster (a few kW) explain why

the volumes had to be up-scaled before being sent to the MS.

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

-6

-4

-2

0

2

4

6

Time (h)

Fle

xib

ility

(kW

)

s 2013-06-25 17-09-58 DayAhead-0001F NODE 0258L001

16298[19]

33005[67]

offers

total

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

-20

-15

-10

-5

0

5

10

15

Time (h)

Fle

xib

ility

(kW

)

s 2013-06-25 17-09-28 DayAhead-0001F NODE 0013L001

16022[18]

32660[66]

offers

total

Figure 75. Signals chosen for four Load Areas.

Even if the volumes of the AD offers proposed by the ATB were up-scaled, the impact on the market

prices remains low.

Page 115: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 115 of 126

5.2.4.3.2 Results

Table 31. Test results for the scenario of December 24th, 2012

Page 116: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 116 of 126

5.2.5. Complete scenario execution

In this subsection, we present the results obtained at each step of a complete field test case. The case

TS_CAT3_RES_Req – 2 presented in Deliverable D6.1 [1] is considered here.

The situation considered in the scenario is the following. Based on wind forecasts (Figure 76.), a

production peak coming from the wind farms connected to the mainland grid is anticipated by the TSO

during the night around 3:00 AM. A load increase request is emitted at a global level in order to

compensate this high RES production. We consider that the Brittany islands also contribute to

compensate this peak with their available flexibility (since they are connected to the continent through

a submarine cable).

It is to be noticed that the flexibility considered in the ATB portfolio is much larger than the one actually

available on the islands during the field tests. The effects of AD products on the distribution network

are thus scaled up in the same way. This is done to make the scenario more realistic.

0

5

10

15

20

0:00 3:00 6:00 9:00 12:00 15:00 18:00 21:00 0:00

Win

d S

pe

ed

(m/s

)

Time (h)

Wind Speed

Max Wind Speed

Figure 76. Wind profile for the Brittany area considered in the scenario (actual profile of May 7th 2012).

5.2.5.1 AD need definition

The AD need expressed by the TSO is formulated in terms of SRP products. These products impact

the Load Areas of the Brittany islands during the constrained time interval. Since the flexibility request

considered here is global and the ATB algorithms cannot perform an optimization over multiple Load

Areas, the requested volumes are split manually between the Load Areas depending on the available

flexibility (Figure 77.).

Since intra-day SRP are not implemented in the ATB, the product type considered here (SRP)

imposes that the AD volumes cannot be adjusted in intra-day in order to fit to more precise forecasts.

This could have been achieved using CRP products, but the choice of product type was imposed by

another limitation of the ATB: CRP products cannot be used to meet load increase requests in the

ATB implemented, only SRP ones can.

Page 117: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 117 of 126

00:00 02:00 04:00 06:00 08:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 00:00

-1

-0.5

0

0.5

1

time

Curt

aile

men

t (P

U)

LoadArea 0258L001 - srp

LoadArea 0010L001 - srp

LoadArea 0294L001 - srp

LoadArea 0013L001 - srp

00:00 02:00 04:00 06:00 08:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 00:00

-2.5

-2

-1.5

-1

-0.5

0

x 104

time

Pow

er

(W)

LoadArea 0258L001 - srp

LoadArea 0010L001 - srp

LoadArea 0294L001 - srp

LoadArea 0013L001 - srp

Figure 77. AD volume profiles requested on different Load Areas.

5.2.5.2 DSO forecasting and flexibility computation

The DSO has to perform several actions at the beginning of the scenarios in order to initialize the

different platforms taking part in the scenario.

FFiirrsstt, the Load Areas of the MV network are computed based on the description of the LV network of

the Brittany islands (Figure 78).

Figure 78. Load Areas (in red) computed by the algorithm based on the LV network of the Brittany islands

TThheenn, the forecasting algorithms embedded in the DSO platform forecast the evolution of the

consumption profile of each Load Area as well as the production profile of the PV power plant installed

on Hoëdic island.

In Figure 79., the forecasted consumption profiles of two Load Areas are compared with the achieved

ones. In Figure 80., the forecasted and achieved production profiles are compared. It is to be noticed

that the curves presented in Figure 80. are generic curves because of confidentiality issues with the

actual data from the PV plant. So they are not measurements from the PV plant installed on the

Brittany islands, but they illustrate behaviours similar to the ones observed during the field tests with

the actual PV plant data.

LLaasstt, the flexibility limits of each Load Area, i.e. the flexibility table, is computed based on previous

information: MV network description, defined Load Areas and forecasts (Figure 81.). This flexibility

table is then sent to the ATB platform to be used as constraints by its optimization algorithms when

selecting the incentive signals to be sent to the EBoxes.

Page 118: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 118 of 126

-20 40 60 80

100 120 140 160 180

00:00:00 04:48:00 09:36:00 14:24:00 19:12:00 00:00:00

Po

we

r in

kW

Time in hRealized (10min) Forecasted (15min) Forecasted (1h)

-20 40 60 80

100 120 140 160

00:00:00 04:48:00 09:36:00 14:24:00 19:12:00 00:00:00

Po

we

r in

kW

Time in h

Realized (10min) Forecasted (15min) Forecasted (1h)

Figure 79. Comparison of the load forecasts to the achieved profiles for 2 Load Areas of the Brittany islands.

0

10

20

30

40

50

60

70

0 5 10 15 20

Pro

du

ced

Po

we

r (k

W)

Time (h)

Measure - Pprod (10min) Measure - Pprod (1h) Forecast - Pprod (1h)

0

10

20

30

40

50

60

70

0 5 10 15 20

Pro

du

ced

Po

we

r (k

W)

Time (h)

Measure - Pprod (10min) Measure - Pprod (1h) Forecast - Pprod (1h)

0

10

20

30

40

50

60

70

0 5 10 15 20

Pro

du

ced

Po

we

r (k

W)

Time (h)

Measure - Pprod (10min) Measure - Pprod (1h) Forecast - Pprod (1h)

Figure 80. Comparison of the forecasted and the achieved PV plant injected powers (hourly data) using achieved radiance information

00:00 04:00 08:00 12:00 16:00 20:00 00:00

0

0.5

1

1.5

2

2.5

3

x 105

time / 2012-08-22T00:00:00+01:00

FT

LA - 0001F NODE 0006L001 - lower

LA - 0001F NODE 0258L001 - lower

LA - 0001F NODE 0010L001 - lower

LA - 0001F NODE 0294L001 - lower

LA - 0001F NODE 0013L001 - lower

00:00 04:00 08:00 12:00 16:00 20:00 00:00

2

2.5

3

3.5

4

4.5

5

x 105

time / 2012-08-22T00:00:00+01:00

FT

LA - 0001F NODE 0006L001 - upper

LA - 0001F NODE 0258L001 - upper

LA - 0001F NODE 0010L001 - upper

LA - 0001F NODE 0294L001 - upper

LA - 0001F NODE 0013L001 - upper

00:00 04:00 08:00 12:00 16:00 20:00 00:00

0

0.5

1

1.5

2

2.5

3

x 105

time / 2012-08-22T00:00:00+01:00

FT

LA - 0001F NODE 0006L001 - lower

LA - 0001F NODE 0258L001 - lower

LA - 0001F NODE 0010L001 - lower

LA - 0001F NODE 0294L001 - lower

LA - 0001F NODE 0013L001 - lower

00:00 04:00 08:00 12:00 16:00 20:00 00:00

2

2.5

3

3.5

4

4.5

5

x 105

time / 2012-08-22T00:00:00+01:00

FT

LA - 0001F NODE 0006L001 - upper

LA - 0001F NODE 0258L001 - upper

LA - 0001F NODE 0010L001 - upper

LA - 0001F NODE 0294L001 - upper

LA - 0001F NODE 0013L001 - upper

Figure 81. Evolution of the upper and lower flexibility limits (in kW) computed for several Load Areas

5.2.5.3 DSO technical validation

The SRP product volumes are submitted by the ATB to the DSO for technical validation. The Off-Line

Validation algorithm embedded in the DSO platform is launched on message reception and the result

(Figure 82.) is sent back to the ATB for integration. Here, the total AD volumes are accepted since no

constraints were detected on the network.

Page 119: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 119 of 126

00:00 02:00 04:00 06:00 08:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 00:00

-1

-0.5

0

0.5

1

time

Curt

aile

men

t (P

U)

LoadArea 0258L001 - srp

LoadArea 0010L001 - srp

LoadArea 0294L001 - srp

LoadArea 0013L001 - srp

00:00 02:00 04:00 06:00 08:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 00:00

-2.5

-2

-1.5

-1

-0.5

0

x 104

timeP

ow

er

(W)

LoadArea 0258L001 - srp

LoadArea 0010L001 - srp

LoadArea 0294L001 - srp

LoadArea 0013L001 - srp

Figure 82. Validation result of some of the SRP products submitted by the ATB platform

5.2.5.4 ATB optimization result

The optimization algorithms of the ATB platform consider the accepted SRP product volumes and

select suitable incentive signals depending on the flexibility limits imposed to each Load Area and the

forecasted flexibility response of each cluster (Figure 83.).

0 2 4 6 8 10 12 14 16 18 20 22 24-40

-30

-20

-10

0

10

20

Time (h)

Pow

er

(kW

)

s 2013-06-21 17-29-39 DayAhead-0001F NODE 0294L001

33349[68]

reserve

0 2 4 6 8 10 12 14 16 18 20 22 24

-40

-30

-20

-10

0

10

20

Time (h)

Pow

er

(kW

)

s 2013-06-21 17-29-18 DayAhead-0001F NODE 0013L001

32659[66]

reserve

0 2 4 6 8 10 12 14 16 18 20 22 24-40

-30

-20

-10

0

10

20

Time (h)

Pow

er

(kW

)

s 2013-06-21 17-29-05 DayAhead-0001F NODE 0010L001

32291[65]

reserve

0 2 4 6 8 10 12 14 16 18 20 22 24

-40

-30

-20

-10

0

10

20

Time (h)

Pow

er

(kW

)

s 2013-06-21 17-32-07 DayAhead-0001F NODE 0258L001

32981[67]

reserve

Figure 83. Incentive signals selected by the ATB algorithms to meet the SRP volumes

5.2.5.5 On-field application

As explained in the test conditions, the database used by the ATB platform and the one used by the

EBoxes are separated (see Errore. L'origine riferimento non è stata trovata.). At the end of the

ATB optimization sequence, a signal similar to the one selected by the ATB is entered in the EBox on-

line database.

5.2.5.6 Obtained cluster response

The global response of the cluster to the selected incentive signal was then assessed. As seen in

Figure 84, a maximum load increase of a little less than 5kW was achieved during the first half hour

following the start time of the signal (at 3:00 AM).

Page 120: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 120 of 126

7500

12500

17500

22500

0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00

Po

we

r (W

)

Time (h)Realized Baseline

Figure 84. Cluster response to the submitted incentive signal observed on the field.

5.2.5.7 Effect of AD on the distribution network

The effect of the power variations induced by the AD product delivery on the MV network voltage at

the island connection as well as on the power flowing towards the islands is illustrated in

(a) Without AD (b) With AD

Figure 85.. The distribution of the voltage on the MV network of the island is shown in (a)

Without AD (b) With AD

Figure 86..

In the present case, an impact of the load increase due to AD delivery can indeed be observed but it is

very limited.

0 5 10 15 200.94

0.96

0.98

1

time (h)

voltage (

PU

)

NODE 0008

0 5 10 15 20

300

400

500

600

700

time (h)

Active P

ow

er

(kW

)

voltage

reference

-5%

0 5 10 15 20

0.94

0.96

0.98

1

time (h)

voltage (

PU

)

NODE 0008

0 5 10 15 20

300

400

500

600

700

time (h)

Active P

ow

er

(kW

)

voltage

reference

-5%

0 5 10 15 200.94

0.96

0.98

1

time (h)

voltage (

PU

)

NODE 0008

0 5 10 15 20

300

400

500

600

700

time (h)

Active P

ow

er

(kW

)

voltage

reference

-5%

0 5 10 15 20

0.94

0.96

0.98

1

time (h)

voltage (

PU

)

NODE 0008

0 5 10 15 20

300

400

500

600

700

time (h)

Active P

ow

er

(kW

)

voltage

reference

-5%

(a) Without AD (b) With AD

Figure 85. Impact of AD load increase on the volage and power flow at the island connection

Load increase

signal

Page 121: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 121 of 126

1.000

0.998

0.999 0.997

0.992 0.989

0.999

0.993

0.992

0.987

0.998

0.998

0.987

1.000 0.973

0.998

0.992 0.991

0.992 0.991

0.999

0.999

0.999

0.988

0.963

0.998

0.992

0.999

0.996

0.999

0.998

0.998

0.998

0.9980.992

0.999

1.0001.000

0.998

0.998

0.998

0.998

0.998

0.999 0.999

0.999

0.999

1.000

0.999

0.998

0.996

0.999

0.999

0.999

0.999

0.999

0.992 0.992

0.998

1.000 0.999

0.999

0.998

0.998

0.9990.999

0.991

0.998 0.998

0.998

1.000

0.991 0.991

1.000

0.9930.998

0.999

0.991

0.998

0.998

0.971

0.996

0.996

0.995

0.997

0.997

0.972

0.972

0.992

0.971

0.972

0.971

0.971

0.996

0.993

0.972

0.996

0.994

0.993

0.994

0.971

0.989

0.992

0.988

0.987

0.972

0.971

0.963

0.971

0.987

0.996

0.991

0.991

0.972

0.993

Time stamp : 3h

net

Transformers

Loads

Generators

1.000

0.998

0.999 0.997

0.991 0.988

0.998

0.991

0.990

0.985

0.998

0.998

0.985

1.000 0.973

0.998

0.991 0.990

0.991 0.990

0.999

0.999

0.999

0.986

0.961

0.998

0.991

0.999

0.995

0.999

0.998

0.998

0.998

0.9970.991

0.999

1.0001.000

0.998

0.998

0.998

0.998

0.998

0.999 0.999

0.999

0.999

1.000

0.999

0.998

0.996

0.999

0.999

0.999

0.999

0.998

0.991 0.991

0.998

1.000 0.999

0.998

0.998

0.998

0.9990.999

0.990

0.998 0.998

0.998

1.000

0.990 0.990

1.000

0.9910.997

0.999

0.990

0.998

0.998

0.971

0.996

0.996

0.995

0.997

0.997

0.971

0.972

0.992

0.971

0.972

0.971

0.971

0.996

0.993

0.972

0.996

0.993

0.993

0.993

0.971

0.988

0.990

0.986

0.985

0.972

0.971

0.961

0.971

0.985

0.996

0.990

0.990

0.972

0.993

Time stamp : 3h

net

Transformers

Loads

Generators

(a) Without AD (b) With AD

Figure 86. Impact of AD load increase on the voltage levels of the island MV network

a) b)

Page 122: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 122 of 126

6. Conclusions

The ADDRESS project developed three field tests where all the technology was tested and assessed

according to the specifications and requirements defined during the project.

Based on these specifications, the technology was implemented and divided into the three field tests

each focussing on different targets:

- Spain: tests on a LV network with demand side management (DSM) from consumers’ point of

view.

- In Italy: tests on a MV network with several MV generation sources to study the interactions of

several DG connection points on the MV network.

- French Islands: tests on LV networks connected to a MV feeder network with DSM and with

RES connected to the LV level.

During the last months of the ADDRESS project, different test cases have been carried out in the

three field tests. The main conclusions follow.

Spanish field test

The Spanish field test is dedicated to the validation of the downstream part of the ADDRESS chain, to

verify the interactions between the Aggregator and the consumers.

To develop the tests, at first a consumers’ segmentation was carried out by different seasons and type

of day in order to classify them in the Aggregator Toolbox. According to this classification, different

clusters were defined in order to categorize the 263 consumers participating to the test. Each cluster

has a different load profile according to the type of day (working day or holiday) and the season of the

year (winter, spring, summer and autumn). In the end, one consumer is defined with 8 different

clusters during all the year.

The tests covered a period of 8-10 months, from the middle of September 2012 to the end of May

2013 and beyond. The recruitment and installation process of the equipment was developed during

the different months of the pilot. Not all the consumers were participating all the time;. some

participated since September, and others from Feb-March 2013 till the end of the test.

During the execution of the test, communications have been the main issue. This has hindered

developing all tests and obtaining the results. For this, it was necessary to carry out more tests to

validate functionality of all the players involved. Due to the communications issue, some test cases

defined in previous deliverables [1] could not be developed. The communication with some specific

EBoxes was not possible, so most of the results have been analysed in an aggregated way.

Despite of it, the analysis of all appliances and players involved in the Spanish field test was achieved.

In some cases the results were not as expected but different tests were carried out in order to be able

to validate or not the technology implemented. In some tests, in order to achieve a representative

value as result of the test, an extrapolated answer from consumers involved in the use case was

needed in order to analyse the achieved results. The evaluation of these results is acquainted in the

Deliverable 6.3

Italian field test

The objective of Italian test was to validate the upstream part of the ADDRESS chain, from AD buyers

to aggregation platform, with a focus on DSO and grid operation on a large MV network, and on the

effect of AD visible at HV level. The AD was emulated by means of some DG using RES (hydro) and a

Page 123: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 123 of 126

storage system.

The Italian field test cases and scripts were divided into four categories:

- Test case 1: The DSO as the AD product validator

- Test case 2: The DSO as the buyer of AD products

- Test case 3: Localized AD products to limit the power flow towards the transmission system

- Test case 4: MVCC algorithms reaction to network changes

The observations are:

- Most of the tests were carried out successfully.

- All the algorithms run well and give realistic results.

- The MVCC algorithms behave as expected.

Therefore it was possible to test on field the management of the distribution network in

presence of Active Demand, allowing the DSO to play both the technical and the commercial

roles foreseen in the ADDRESS architecture.

The assessment of the results achieved is presented in ADDRESS Deliverable6.3

French field test

The main objective of the French field Test was to evaluate the performance and the technical

feasibility of the whole ADDRESS chain. A two-part system compliant with the ADDRESS architecture

and fit to the reliability requirements of a field test was retained for the French field tests. This system

is composed of:

the upstream part of the architecture consisting of the DSO platform, the aggregation platform,

a simplified modeling of the different electricity system players and the electricity market

simulator;

the downstream part consisting of the ecosystem of the Energy Boxes (and the controlled

appliances). It is always run connected to the internet in an online mode.

Standardized links were used between some actors (DSO / aggregation functions…) so that they

could communicate automatically and perform on their own with a limited manual intervention.

Several cases were tested in order to cover the objectives of the French field tests. Most of them are

about the complete ADDRESS chain of processes providing different AD service types to the

electricity system players: voltage control, balancing services, load shaping, combination of AD with

RES (Renewable Energy Sources)… Other cases concern the electricity market simulator and its

interactions with the aggregation entity. All these cases allow to verify the capability of the

implemented ADDRESS architecture to respond to the envisioned situations and to test the

performance of its modules on real data. Depending on the scenario, different players are involved in

the tests.

The main cases considered are the following:

Request from the DSO for reducing a local overload constraint,

Request from the TSO for reducing a congestion constraint,

Request from the BRP for managing the imbalance between production and consumption,

Requests in combination with RES for reducing a local voltage constraint anticipated by the DSO

or providing AD services to a RES producer,

Requests from the DSO for limiting the global consumption of the islands over a complete day,

Page 124: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 124 of 126

Offers providing AD services to an electricity market.

During the French field test, several issues have been encountered both in the downstream and

upstream parts of the ADDRESS chain and should be taken into account to analyse the results:

one refers to the development of the Energy Box and their installation in the households. This

issue has already been discussed in previous deliverables [9]. The solution adopted allowed

to test most of the functionalities regarding the management of the loads by the EBox system.

the electric heating could not be managed as thermal loads due to blocking issues in the

EBox software optimisation,

the management of Electric Water Heaters (EWH) also met difficulties. Initially, the algorithms

were developed so that the EWH can be operated by the EBox as Interruptible Loads.

However, this doesn’t correspond to the specific way the EWH are operated in France. So it

was decided to define them as Shiftable Loads which was more appropriate considering their

consumption behaviour. So appropriate modifications and delicate parameter tuning were

necessary,

The integration of the different components of the ADDRESS chain needed additional

developments in particular to compensate for missing functionalities.

Some issues were also encountered in the ATB system (failed ATB optimizations, selection of

non-adapted incentive signals...). In a few cases, this led in particular to bypass the

aggregation platform in order to run the complete field scenarios concerned by these

problems.

Despite of all the above issues, we were able to carry out all the tests planned and to validate the

complete ADDRESS chain in the French field tests as expected. Indeed the complete automated

sequence (from market simulator, DSO platform and aggregator platform up to the Energy Boxes)

could be performed on the field for the designed test cases. The effective impact of AD requests on

the consumer consumption could be assessed and compared with the forecasts provided by the

aggregation platform. The impact of up-scaled AD requests on the distribution network was also

studied.

In other words the technical feasibility and performance of the provision of AD services to electricity

system players could be assessed and the objective of the French field tests were reached.

As it has already been mentioned above, the assessment of the results obtained in the French field

tests will be presented in the following deliverables [12], [13].

Page 125: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 125 of 126

7. References

7.1. Project documents

List of reference document produced in the project or part of the grant agreement

[DOW] – Description of Work

[GA] – Grant Agreement

[CA] – Consortium Agreement

[1] D6.1 - Description of test location and detailed test program for (limited) prototype field test,

simulations and hybrid tests.

[2] WP1 Subtask 1.2.3ADD-Task1_2-IBD-Subtask123_V3.1.doc

[3] Validation of integrated field tests in Spain (Id. ADD-WP6-T6.3)

[4] IR6.2. Validation of Italy Field Test (6.2)

[5] ADDRESS: Validation of lab and field tests in France (Id. ADD-WP6-T6.3)

[6] Internal report I6.1 - Laboratory tests results

[7] D5.2 – Key societal factors influencing the adoption of the ADDRESS SmartGrids architecture.

Report on the results of WP5 verified by the experience obtained in the field tests (WP6).

[8] D1.1 – Conceptual architecture including description of: participants, signals exchanged, markets

and market interactions, overall expected system functional behaviour

[9] D2.2 - Development of Local Energy Management equipment and integration of algorithms for

load, generation and storage control

[10] D5.4 - Report outlining business cases for Customers, Aggregators and DSOs in the scenarios

detailed in WP1

[11] IR5.1 - Evaluation of Benefits of Active Demand

[12] D6.3 – Assessment to what extent the objectives of the field test are met, what prototype

(application) performs best.

[13] D6.4 - Evaluation of the effectiveness of the ADDRESS concepts in promoting active demand

and the large scale integration of DER

7.2. External documents

List of reverence documents not produced in the project (articles, books,….)

Page 126: Prototype Field Tests. Test Results...Prototype Field Tests. Test Results D6.2 Programme FP7 – Cooperation / Energy Grant agreement number 207643 Project acronym ADDRESS Type (distribution

Prototype Field Tests, test results

ADD-WP6-T6.3_Iberdrola_D6.2 – Prototype Field Tests. Test Results

Final v1.0

Copyright ADDRESS project page 126 of 126

8. Revisions

8.1. Revision history

Version Date Author Notes

0.1 31/05/13 Ignacio Delgado First release

0.2 14/06/2013 TB members comments

0.3 24/06/13 Ignacio Delgado Updated version with comments from

Arturo and Regine

0.4 01/07/13 EDF-SA, Enel

Distr,Iberdrola

comments

0.5 8/07/13 Ignacio Delgado Updated version

0.6 15/07/2013 PC Comments

0.7 22/07/2013 Iberdrola Updated after PC review

1.0 31/07/2013 PC-QMO Final Approval