Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

19
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status Proton Plan Status February February Eric Prebys

Transcript of Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Page 1: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 1

Proton Plan StatusProton Plan Status February February

Eric Prebys

Page 2: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 2

• Shutdown Preparations and Schedule – Prebys/Mau

• Operations – Prebys• Technical Progress - Prebys• Cost/Schedule Report – Baller

AgendaAgenda

Covered under shutdown prep.

Page 3: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 3

Proton Plan Shutdown ProjectsProton Plan Shutdown Projects

• Linac Low Level RF Upgrade Complications

• NTF Running• MTA beamline (not part of Proton Plan)

• Booster Long straight correctors

• Huge project Water supply upgrade

• Main Injector Ring Collimation System

• Two primary and four secondary collimators• Requires rerouting of power bus and water

RF upgrade• Transformer upgrade• Comb filter

Page 4: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 4

Linac LLRF StatusLinac LLRF Status

• Have design• Waiting on FPGA Board prototype• Will not drive shutdown

Page 5: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 5

Booster Corrector StatusBooster Corrector Status

• Magnets: Two Prototypes built and tested

• Look good• Second prototype will be put in Booster tunnel ~April

Vendor Deliveries• Cores: over half delivered• Coils: lots of start up problems, but now first couple of

magnets’ worth delivered Assembly

• Beginning assembly of first magnet from vendor-supplied components

• Power supplies 5 (4x40A + 1x65A) of the six power supply types in

procurement Remaining PS (2.5A skew quad) straightforward

Page 6: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 6

Corrector ScheduleCorrector Schedule

Page 7: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 7

Power Supply SchedulePower Supply Schedule

Page 8: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 8

Booster Water UpgradeBooster Water Upgrade

• Current system will not handle 15 Hz operation Already operating outside of specificiations

• Beginning staged upgrade this shutdown Will upgrade West gallery return from 2” to 4” and

6”. New manifolding. Will still tie into existing return via tunnel

• Estimate 4-6 weeks.• Preparing fixed price contract bid package.• We will not allow this project to drive

shutdown.

Page 9: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 9

Main Injector Collimator StatusMain Injector Collimator Status MI- Secondary Collimators cost and delivery.

1) Steel Plates and blocks, _______________________$182,776 May 1

2) Jacks_______________________________________$36,016 May 4 3) Bellows_____________________________________$13,424 May 25 4) Motor Brackets and shafts______________________ $10,000 May 4 5) LVDT, Switches, Thermocouples Brackets__________$6,000 May 1

6) Fasteners ( not ordered) __________expected cost $ 1,500 ( 2 weeks) 7) THK Bearings _____________________________ $600 received 8) Couplings (not ordered )_____________ expected cost $1,500 (2 weeks) 9) Hub City Gear Boxes___________________________$5,400 March 28 10) Vacuum Flanges, Machined __________________$11,000 May1 11) Vacuum Liner Blocks, Machining__________________$24,427 May 4 12) Marble ( not ordered )_______________expected cost $40,000 (6-8 weeks)

13) Electrical parts _______________________________$ 45,540 May 20

14) Marble frame ( not ordered) __________ expected cost $ 5,000 ( 4 -6 weeks)

15) Thermocouples, wire ___________________________$ 3,300 2 weeks

16) Ion vacuum pump _____________________________$ 35,664 4 weeks

Total: $381,086

Page 10: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 10

MI RF Upgrade ProjectsMI RF Upgrade Projects

• Solid state power supplies Ordered: ~4-8 weeks delivery Installation will take about 10 days

• Install spare anode transformer at MI Center • Will modify all three anode power supply

transformer slabs for new transformers, compatible with NOvA operation.

• Procuring new transformer for south anode power supply Will not be ready for shutdown

Page 11: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 11

• Linac LLRF Could be ready for July 1 shutdown Can be installed arount NTF schedule (total of ~2

days/station x 5) Will not be allowed to drive shutdown

• Booster Water

• Can be ready for July 1st shutown• 4-6 weeks installation• Will not drive shutdown

Correctors• Can not be ready until an August 1st shutdown at the earliest• 8 weeks installation, assuming no interference

• Main Injector Collimation

• Can be ready for a July 1st shutdown• Currently 16 weeks installation.• Hope to shorten to 12.

SummarySummary

Start date driver

Length driver

Page 12: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 12

Worries and CaveatsWorries and Caveats

• Correctors Production of cores and coils is proceeding, but we

have not yet built a production magnet from vendor-supplied parts.

We do not yet have a single vendor-supplied power supply

Installation schedule does not yet allow for interference with other projects, resource leveling, and does not include commissioning time (would ideally like two full weeks dedicated time).

• Main Injector Collimators Utility rerouting scheme still very preliminary No detailed installation plan

• Present time estimate (conservative) WAG

Page 13: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 13

Operations

Page 14: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 14

Operational HighlightsOperational Highlights

• MiniBooNE Still off All plates lowered without incident Waiting for stainless steel rods to lift back into out

position Scheduled to come back on ~mid April.

• NuMI No significant down time since last PMG

• Overall uptime since Feb. 1 = 94%!!– Design: 80%– Base: 70%

• Helps compensate for unrealistic cycle time Continue to push batch intensity Slip stacking studies continue

• Reached 4.05E13 protons to NuMI in tests Continue to work to reduce cycle time from 2.4->2.2

seconds

Page 15: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 15

Review: NuMI Cycle Time IssuesReview: NuMI Cycle Time Issues

• Because pBar and NuMI batches are accelerated together, the NuMI cycle time is locked to the pBar production cycle time.

• Original assumption: NuMI and pBar would run at 2 second cycle times during

2+5 operation (limited by minimum pBar rep. rate) Cycle time would change to 2.2 seconds for 2+9 operation

(limited by MI loading time)• In fact:

pBar has problems running below 2.4 seconds, significantly reducing beam to NuMI

The effect was originally largely cancelled by NuMI only cycles (during shot setup and “interleaved” mode when the accumulator had large stacks)

Now with fast transfers to Recycler, there are very limited NuMI-only cycles

• Present status: Working to optimize pBar for 2.2 cycle time Will lock complex to that time through end of collider

program Not yet accounted for in this year’s projections

Page 16: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 16

NuMI/pBar Cycle Time ProgressNuMI/pBar Cycle Time Progress

Page 17: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 17

NuMINuMI

Dotted lines are 2.4 second rep rate

Page 18: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 18

MiniBooNEMiniBooNE

• MiniBooNE still off• Will cross blue line ~May 1• Scheduled to come back on in mid-April

Page 19: Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.

Proton Plan PMG 3/22/07 E Prebys 19

Total Booster Output Total Booster Output

Mostly reflects loss of MiniBooNE