Protecting Workers on the Track Engineering Hours...accessing the track and providing protection for...
Transcript of Protecting Workers on the Track Engineering Hours...accessing the track and providing protection for...
Transport for LondonLondon Underground
MAYOR OF LONDON
Issue 3
Effective 1st March 2015
Learning information booklet
Protecting Workers on the Track Engineering Hours
Access
ContentsSection page
1 Introduction 42 Objectives 63 Responsibilities 74 Preparation 95 SiteAccessBookingforRailwayEngineering 216 SafetyAlertsandBulletins 307 Emergencyplans 318 Drawings 369 Liftingplansforliftingoperations 3710 Toolboxbriefingandcommunication 3811 EnvironmentalIssues 4012 WeedkillingTrain 4313 Planningtheprotectionforthework 4414 Sitefamiliar 4515 Tools,equipmentandmaterials 4916 Weatherconditions 5217 Tractioncurrentsupply 5318 NightlyEngineeringProtectionArrangementsMaps 5419 SpecifiedArea 5520 Workingwithanengineer’strainormechanisedvehicle 5721 Engineer’sCurrentArea 6122 NightlyEngineeringProtectionArrangements 6223 Signinginatthestation 6324 Communications 6725 BookingonwiththeTAC 6926 Workgroupsafetybriefing 71
ContentsSection page
27 Contactingthesignaller 7228 CurrentRailIndicatorDevice 7329 SwitchingOffTractionCurrent 7730 Goingonthetrack 7931 StartingandfinishingworkinTrafficHours 8032 LateSurrenderProtection 8133 Signingoutatthestation 8434 Possessions 8635 References 87
4
sect
ion IntroductionIntroduction1
1 IntroductionThislearninginformationbooklethasbeenproducedforindividualsaccessingthetrackandprovidingprotectionforthemselvesandothersduringEngineeringHours.ItcontainsinformationforProtectingWorkersontheTrack-EngineeringHours(PWT-EH).
TherearedifferentlevelsofPWT,youwillneedtobetrainedandsuitablycertificatedtoworkasaPWTin:
• EngineeringHours
• TrafficHours
• depots
• apossessionworksite
• SpecifiedAreas(SA)
• EngineersCurrentAreas(ECA).
ThislearninginformationbookletonlycoverstheactivitiesofthePWT-EH.Thefollowingactivitiesareseparatemodulesandarenotcoveredaspartofthistraining:
• securingandunsecuringofpoints
• definingSA’s/protectionofpossessions
• placingandremovingshortcircuitingdevices
• controllingthemovementofengineer’strainsandmechanisedvehicles.
5
section1Introduction
1.1 On successful completion of the training
OnsuccessfulcompletionofthistrainingyoumustarrangeanappointmentwiththeAccessteamandobtainatemporaryInternalVerification(IV)number,validforsixmonths.
ThetemporaryIVnumberenablestheholdertoworkwithinasingleplatformplus60metreseitherend;iftheindividualisbeingmentoredtheycanundertakethefulldutiesofaPWT-EH.
Onceyouhavebeenobservedsuccessfullycarryingouttheprotectionprocessontwoseparateoccasions,byanapprovedassessor,youwillobtainafullIVnumber.
6
sect
ion ObjectivesObjectives2 Responsibilities
2 ObjectivesOncompletionoftrainingthePWT-EHwillbeableto:
• statethedocumentationrequiredtoplantheworksafelyandeffectively
• demonstrateawarenessofcurrentfirelegislation
• demonstratethecorrectproceduresforsigninginandoutofastation
• statethekeycomponentsoftheNightlyEngineeringProtectionArrangement(NEPA)maps
• demonstratehowtocheckforallinformationusingtheNEPA
• statetheLineClear/LineSafeprocedures
• listtherequirementsforaccessingthetrack(sitefamiliar,SiteAccessBookingforRailwayEngineering(SABRE)number,certificationofworkgroup)
• demonstratehowtocheckforlasttraininformation
• listtheinformationrequiredtocompletetheLineClear/LineSafe(LC/LS)logbook
• demonstratethecorrectsafetycriticalcommunicationprotocols
• demonstratehowtobookonandoffwiththeTAC
• statetheinformationrequiredtoconductworkgroupsafetybriefing(s)
• demonstratehowtouseaCurrentRailIndicatorDevice(CRID)
• demonstratehowtouseaPermanentCurrentRailIndicatorDevice(P-CRID)
• statethecorrectproceduresforevacuationoftheoperationalrailway
• demonstrateawarenessofcontinuouslymonitoringtheprogressoftheworksagainstthecall-backtime
• statehowtoimplementLSParrangements.
Objectives
7
section3Responsibilities
3 ResponsibilitiesThePWT-EHwillberesponsiblefor:
Worksite: • theworkinprogress
• discipline
• theprogrammeofwork
• plant
• materials
• firstaidandemergencyprocedures
• generalhealth&safety.
Protection:• readingtherelevantpublications
• completingtheLC/LSlogbook
• bookingonandoffwiththeTAC
• confirmingtractioncurrentisoff
• conductingaworkgroupsafetybriefing
• ensuringstaffremainintheareaofprotection
• remainingincommunicationwithanyadditionalSitePerson(s)inCharge(SPC(s))/PWT-EH(s)
• monitoringthetimeforcallbackpurposes
• keepingamobilephone/handheldportableradioswitchedon,ifusingone
• ensuringpointsaresecuredifusingatracktrolley
• checkingthestatusofthecurrentoneachnewtractioncurrentsectionifprotectingamovingworksite
• makingsurestaffareawareofanyspecialfeatures,ifworkingadjacenttoNetworkRail(NR)infrastructure
• providingpersonnelwithadditionalbriefing(s)asrequired.
8
sect
ion ResponsibilitiesResponsibilities3 Preparation
Theremaybesituationsinvolvingasinglejob,multitaskormultijob,wherea‘Lead’PWT-EHisappointedfortheoverallaccountabilityforthewholeworksiteanddesignatedPWT-EH’saccountableforsinglespecialisttasks.
OncompletionoftheworkthedesignatedPWT-EHmust:
• reportbacktothe‘Lead’PWT-EHwiththeoverallaccountabilityfortheworksite
• confirmthespecifictaskareaissafeforpeoplewalkingandtoastandardrequiredfortrainstorun.
A‘Lead’PWT-EHwiththeoverallaccountabilityforaworksitemustensurethat:
• satisfactoryprotectionarrangementsareprovidedwhennecessary
• thepersonprovidingtheprotectiongivesafullworkgroupsafetybriefing,detailingtheprotectionarrangements
• communicationswiththepersonprovidingtheprotectionaremaintainedifnecessary,byappointingdesignatedPWT-EH’sinamultitaskworksite
• theoverallworksiteisleftsafeforpeoplewalkingandtoastandardrequiredfortrainstorun.
ItmustbeconsideredattheplanningstageifonePWT-EHcanundertaketheactivitiesofbothsafelymanagingtheworksiteandprovidetheprotectionorwhethertouseaseparatePWT-EHdedicatedtoprovidetheprotection.APWT-EHcanbeaworkingmemberoftheworkgroup,aslongasthisdoesnotinterferewiththeabilitytosafelymanagetheworksiteand/orcarryouttheprotectionduties.
Responsibilities
9
section4Preparation
4 PreparationTheequipmentorinformationthePWT-EHneedstohaveaccessto:
• sitefamiliarinformation
• timepiece
• LC/LSlogbook
• NEPAmapsandNEPAdocument
• CRIDorP-CRID.
4.1 Planning the work
Whenplanningthework,thefollowingmustbeconsidered:
• typeandlocationofwork
• SABREnumber
• documentation
• tools,equipmentandmaterials
• toolboxbriefingandcommunication
• environmentalaspects
• protectionarrangements.
Type and location of work
Youareonornearthetrack,ifyouare:
• withintwometresofanyrail
• onthepermanentway
• onaplatformramp.
Youarenotonornearthetrack,ifyouare:
• onastationplatform
• inanareaguardedbyaphysicalbarrier.Physicalbarriers
10
sect
ion PreparationPreparation4
Line Clear areas
LineClearareascoverallLUtrackinthesub-surfacesectionsandthetubesections,except:
• non-electrifiedtrack
• trackwithindepotsorsidingswheretractioncurrentisnormallyonatalltimes.
Line Safe areas
LineSafeareascoverallLUtracknotintheLineClearareas,except:
• non-electrifiedtrack
• trackwithindepotsorsidingswheretractioncurrentisnormallyonatalltimes.
SomeopensectionscanbeintheLineCleararea.
LineClear/LineSafeproceduresdoNOTcoverareasofnon-electrifiedtrack.
11
section4Preparation
4.2 Station platformsAsiteandtaskspecificriskassessmentmustbecarriedoutbeforeworkingonastationplatform.Itmustbeconsideredthattrainsarerunningandtractioncurrentis‘on’atalltimes,unlessotherwiseconfirmedthroughappropriateprotectionprocedures.
4.3 Stations fitted with Platform Edge DoorsWhenworkingatstationsfittedwithPlatformEdgeDoors(PEDs),itistheresponsibilityofthePWT-EHto:
• firstbookonwiththeTACasthestationsupervisorwillrequireconfirmationthePWT-EHhasdoneso
• arrangeaccesstoatunnelwiththestationsupervisor.
Ifthereisanengineer’strainworkingatastationfittedwithPEDsthePWT-EHmust:
• signthekeylogbook,takeresponsibilityfortheRKL220keyandtheplatformedgedoors
• bepresentontheplatformandstopanystaffwhoarenotworkingwiththetrainfromenteringthetrack.
12
sect
ion PreparationPreparation4
4.4 Certification
ItistheresponsibilityofthePWT-EHtoensurethatallpersonnelintheworkgrouparesuitablycertificatedforthetaskstheyareundertaking,toolsandequipmenttheyareusingandtheareasoftracktheyareworkingin.
13
section4Preparation
4.5 London Underground and Network Rail boundaries
PersonnelmustbecertificatedandcompetenttoNetworkRail(NR)standardsbeforeaccessinganyareaoftheoperationalrailwaywhichisdesignatedasbeingunderNRrules.
TheareaswhereNRcertificationisrequiredare:
• RichmondtowestofTurnhamGreen(ownedbyNR)
• HarrowandWealdstonetonorthofQueen’sPark(ownedbyNRbutLUcertificationisvalidwithinStonebridgeParkdepot)
• WimbledontowestofPutneyBridge(ownedbyLUbutNRrulesapplyduetoNRsignallingsystem).
Lines running close to Network Rail lines
AreaswhereLUandNRpropertyboundariesrunclosetogether:
Districtline:
• UpminstertoCampbellRoadJunctionWB
• aroundKensington(Olympia).
Centralline:
• WestRuisliptoNorthActonEB
• WestActontoEalingBroadwayWB.
MetropolitanandCircleline:
• KingsCrosstoFarringdonIR
• HarrowontheHilltoFinchleyRoadNBMetandNBFastMet.
LUcertificationisnotvalidforworkoneitherthetracksortheplatformsintheseareas.Ifyouneedtoentertheseareas,youmusthaveNRcertification.
14
sect
ion PreparationPreparation4
HammersmithandCityline:
• PaddingtontoWestbournePark
• BarkingtoCampbellRoadJunctionWB.
Victorialine:
• NorthumberlandParkdepotroad48.
Forworkingintheseareas,LUcertificationandprotectionappliesifpersonnel:
• remainonLUproperty
• donotgetcloserthan2metreslaterallytothenearestNRrunningrail.
NRcertificationandprotectionisrequiredif,atanytimeon:
• LUproperty,personnelareworkingwithin2metreslaterallyfromthenearestNRrunningrail
• NRproperty,personnelareworkingwithin3metreslaterallyfromthenearestNRrunningrail.
NRcertificationisalsorequiredwhenyourequireaccessthroughoracrossNRareastogettoLUassetsandcomewithin3metresofthenearestNRrunningrail.
15
section4Preparation
WhenworkingduringEngineeringHoursiftheworkisclosetothethroughrunningboundarywithNRandprotectionhastobeprovidedfromtheNRside,apossessionwillberequired.
4.6 Stations where Network Rail certification is required
Whenworkingonstationsbelongingtoothertrainoperatingcompanies(i.e.NR),whetherornotLUcertificationandprotectionarevaliddependsonthelocationoftheworksite.
Othertrainoperatingcompaniesstationlocations:
• Districtline:Barking,Upminster,Kensington(Olympia)
• Centralline:Stratford
• Bakerlooline:Queen’sPark.
ThestationsownedbyLUwhereothertrainoperatingcompaniesoperateare:
MetropolitanandCircleline:
• BarbicanandFarringdon.
Victorialine:
• HighburyandIslington.
Atthesestations,LUcertificationandprotectionarrangementsapplyon:
• LUtrack
• LUequipmentonplatforms-unlesstheworkiswithin1.25metresoftheNRplatformedge.
Ifyouarenotsureyourworkgroup’ssafetyonthetrackcertificationisvalidataparticularlocation,youshouldseekadvicefromyourmanager.
16
sect
ion PreparationPreparation4
Forworkwithin1.25metresoftheNRplatformedge,NRcertificationandprotectionarrangementsapply.
4.7 Overhead Line Equipment
WhenonasectionoflinewhichisadjacenttoorpassesoverNRlineselectrifiedby25kv(A.C.)OverheadLineEquipment(OLE)system,always:
17
section4Preparation
InanemergencyinvolvingOLEthefollowingproceduremustbefollowed:
• contacttheLUController
• givethelocationandstructurenumber
• givethenatureofemergency
• waitforfurtherinstructions.
WhenworkduringEngineeringHoursisnearNRtracksthefollowingmustbeconsideredduringplanning:
• whetherNRpossessionorprotectionisrequired
• anyadjacentOLEandifanisolationisrequired
• walkingroutestoandfromtheworksite
• thetrackcertificationoftheworkgroup
• anyotherrelevantfactors.
BeforeallowingpersonneltoworkorwalknearNRtracksthePWT-EHmustmakesurethattheyarebriefedonthehazardsspecifictotheareaandwhetheranyadditionalprotectionisinplace.
18
sect
ion PreparationPreparation4
4.8 Heathrow Express and London Overground
TheHeathrowExpressandLondonOvergroundhavebeenequippedbyNRwith25kvOLEfortractionsupplypurposes.
WhereLU’sinfrastructureisincloseproximityofthesetwolines,measureshavebeentakentoimmunisetheLU’sinfrastructureagainstanyelectricalhazardsthatcouldpossiblyemanatefromtheOLE,andthesetaketheformofred,greenandyellowbonds.
Warningsignsindicatethe‘immunised’areas.Intheseareasbondsareattachedtomanylinesandstructures:
• donotremove,cut,connectordisconnectanyofthebondsunlessauthorisedtodoso
• makesureyouarefamiliarwiththeareabeforeworkingthere.
ImmunisationbondsarefoundonLUlinesthatrunadjacenttocertainNRlines.
Yourmanagerorsupervisormustfullybriefyouonthesafetyproceduresthatyoumustfollowintheseareas.
19
section4Preparation
Theareasare:
Hammersmith&Citylines:
• WestbourneParktoPaddington(Suburban),bothroads.
Centralline
• EalingBroadwaytoBridgeD29,bothroads
• NRbridgewhichcrossesoverLUlinesatNorthActon.
Districtline:
• EalingBroadway,allroadsfromtheplatformbufferstopendtotheendsofNos.24and25sidingsroadseastofthestation
• WestendofEarl’sCourtstationtoKensington(Olympia)
• TurnhamGreentoGunnersbury,bothroads.
DistrictandPiccadillylines:
• BridgeD29atHangerLaneJunction.
MetropolitanandJubileelines
• BridgeMR10andMR10AbetweenWestHampsteadandKilburn.
Bakerlooline:
• AtQueen’sPark.
Iftheworkiscloserthan2.75metrestoOLE,oradamagedordisconnectedbondisdiscovered,orarrangingfortheisolationofOLE,theLUControllermustbecontacted.
PreparationSite Access Booking for Railway Engineering
20
sect
ion Preparation4
4.9 High voltage power lines (National Grid)
Ifanypersonnelseealineobstructedbyfallenwires,theymust:
• immediatelystopanytrainfromapproaching
• maintainasafedistancefromthelinesatalltimes
• contactandinformtheLUcontroller.
4.10 Special arrangements at Amersham and Harrow-on-the-Hill
SpecialarrangementsapplyatAmersham,southofthemaintenanceboundaryontheUpLineandatHarrow-on-the-Hill,northoftheboundaryontheNorthboundMainLine.
AtbothoftheselocationsthePWT-EHmustalsobecertificatedbyNRasaControllerofSiteSafety(COSS).
ForfurtherinformationrefertoleafletOSNoLF09availableontheNetworkImprovementwebsite.
Preparation
21
section5Site Access Booking for Railway Engineering
5 Site Access Booking for Railway Engineering
Whenaccessingthetrack,anapprovedSABREnumberfortheworkbeingcarriedout,isrequired:
• aSABREnumberisproducedfromthebookingsystemtocontrolaccesstoLUinfrastructure
• aPWT-EHwillbegivenavalidSABREnumberbythecompanytheyworkfor
• forurgentworkthePWT-EHmustcontacttheFaultReportingCentre(FRC)orDutyEngineer,Ifgranted,aFRCnumberwillbeissued.
5.1 Documentation
Method statement and work instructions
Thefollowingistheinformationthatcanbecontainedinamethodstatement:
• resources
• riskassessments
• controlmeasures
• PersonalProtectiveEquipment(PPE)
• emergencyrequirements
• monitoringandcompliance.
Themethodstatementshouldincludethenameandaddressofthedepartmentorcompanycarryingoutthework.
22
sect
ion Site Access Booking for Railway EngineeringSite Access Booking for Railway Engineering5
5.2 Risk assessments
Ariskassessmentissimplyacarefulexaminationofwhat,inyourwork,couldcauseharmtopeople,sothatyoucandecidewhetheryouhavetakenenoughprecautionsorshoulddomoretopreventharm.
Thefivestepstoariskassessmentare:
• identifythehazards
• decidewhomightbeharmedandhow
• evaluatetheriskanddecideonprecautions
• recordyourfindingsandimplementthem
• reviewtheriskassessment.
Specific risk assessments
SpecificriskassessmentsregardingmanualhandlingandControlofSubstancesHazardoustoHealth(COSHH)willalsoberequired,andwillbecontainedinthemethodstatement:
• allchemicals/substancesmusthaveaCOSHHassessmentpriortouse
• hazardousmaterialse.g.Asbestos,Lead,Anthrax,Polychlorinatedbiphenyl(PCB)andMercury.
5.3 Permits and licenses required for the work
Permit to work
IngeneralyoualwaysrequireaPermittoWorkforworkonLUpremises.Itspurposeistoensureworkcanbeundertakensafelyandthatallstaffcanbeaccountedforinanyemergencyevacuation.
23
section5Site Access Booking for Railway Engineering
ThePermittoWorkprocedureMUSTbeusedwhenworkingatheightonroofsorinareaswhichareconfinedspacessuchasplatforminverts.
Theonlyexceptionsare:
• emergencyworkarrangewiththeFRC
• workshownonaPossession,BusinessUnitorStationWorksPlan.
ThePWT-EH’smainresponsibilitiesconcerningthePermittoWorkareto:
• fillinaPermittoWorkformbeforearrivingatthelocationofwork
• beinpossessionoftheappropriatelicensestocarryoutthework
• superviseallstaffcoveredbythePermittoWorkform
• cleartheworksiteafterworkhasfinished
• makesuretheareaissafeandclear.
5.4 Fire legislation
AllpremiseswithinLUarecoveredbyoneofthefollowinglegislation:
• TheRegulatoryReform(FireSafety)Order2005
• TheFirePrecautions(Sub-surfaceRailwayStations)(England)Regulations2009.
Thefirelegislationcoveringsub-surfacerailwaystationsisTheFirePrecautions(Sub-surfaceRailwayStations)(England)Regulations2009.
Toensurethehigheststandards,stafftrainingisapriority.Anyonewhoisemployedtoworkonstationsotherthanamemberofthestationstaffmustbegiveninstructionsinthefireprecautionsto
24
sect
ion Site Access Booking for Railway EngineeringSite Access Booking for Railway Engineering5
beobservedinthecourseoftheirwork,andactiontobetakenbythemincaseoffirealertandevacuationofthepremises.
Regulation7states:
• allpartsofstationpremisesmustbekeptclearofanyaccumulationofcombustiblerefuseorothercombustiblematter
• anyareasetasideforstoringcombustiblerefuseinstationpremisespendingdisposalmustbeseparatedfromotherpartsofthepremisesbyfire-resistingconstruction.
TheRegulatoryReform(FireSafety)Order2005states:
• Wherenecessaryinordertosafeguardthesafetyofrelevantpersons,theresponsiblepersonmustensurethatroutestoemergencyexitsfrompremisesandtheexitsthemselvesarekeptclearatalltimes.
Contraventions of the Fire Regulations:
• rubbishbeingallowedtoaccumulate
• themeansofescapeisobstructed
• evidenceofsmoking
• smokedetectorbeingcovered
• firealarmnoticemissingordefaced
• holesknockedintocompartmentedwallsandnotfilledwithfireresistantmaterial
• doorclosersdisconnectedorfaulty
• firedoornoticemissing.
5.5 Permit for hot works
Anyworkinvolvingcutting,grinding,weldingorburningisnotallowedinanylocationotherthanaDepot,withoutapermitforhotworks:
25
section5Site Access Booking for Railway Engineering
• thepermitissubmittedbytheProjectManager,andauthorisedbytheaccountablemanager
• theprojectmanagermustsubmitpermitapplicationsatleastoneweekpriortothework
• thesinglelocationmustbesufficientlycompacttobeobservablebytheFireWatchpersonatalltimes
• thepermithasauniqueidentifyingnumber,andisvalidforonecalendarmonth
• isolationoffireprotectionequipmentdetailsmustbeindicatedonthepermit
• theauthorisedpermittopcopymustbeclearlydisplayedattheworksite.
ThepermitrequiresatrainedFireWatchpersonequippedwithappropriatefirefightingapparatus,tobeinattendanceatalltimeswhilstthehotworkingisbeingcarriedout.
5.6 Fire Watchperson
TheFireWatchpersonmust,beforework:
• beprovidedbywhoeverisdoingthework
• bookinseparatelywiththeStationSupervisorandthePWT-EH
• beawareofothersworkinginthearea
• carryahandheldradio
• advisetheadjacentstation(s)whenhotworkingintunnels
• carryoutsafetychecks
• haveatleast2x9litreAFFFplus1x2KgC02extinguishersand1fireblanket.
Isolationsoffiredetectionequipmentmayonlybecarriedoutbyqualifiedpersonnel.IsolationsduringEngineeringHoursareatarequestbytheprojectmanagertotheFRC.
26
sect
ion Site Access Booking for Railway EngineeringSite Access Booking for Railway Engineering5
Theworksite:
• mustbesufficientlycompacttoobserveeasily(anadditionalFireWatchpersonmaybeneeded)
• accesstotherearofthewallsandpartitionsisnecessaryinordertomonitorandcontroltheeffectsofhotworking(heat,fumes)
• flammablematerialsmustbeatleast15metresfromtheworksite
• fireextinguishersmustbeplacedinaprominentpositionontheexitroute.
DuringworktheFireWatchpersonmust:
• carrytheirtrainingcertificateatalltimeswhilstonduty
• bepresentthroughoutthedurationofthework(hotworkshouldceaseimmediatelyiftheyhavetoleave)
• notbecomedistracted.
AftertheworktheFireWatchpersonmust:
• remainattheworksiteforatleastonehourafterthehotworkingiscomplete,oruntilthefiredetectionequipmenthasbeenre-instated,whicheveristhelater
• ensurethatthesiteisleftcleanandtidy,aswellassafe
• bookoutwiththeStationSupervisorandthePWT-EH.
IfhotworkinginatunnelandtheFireWatchpersonisrequiredtoremainonsiteforaminimumofonehourandprotectionisrequiredtoberemoved,thePWT-EHmustensuretheFireWatchpersonisbriefedthattheymustremainontheplatformonceprotectionhasbeenremovedandifafireisdiscoveredorsuspected,theFireWatchpersonmustinformtheStationSupervisorimmediately.
27
section5Site Access Booking for Railway Engineering
5.7 Storage licence
Thereasonforstoragelicensingistoexercisecontroloverthetypesofmaterialsandthedurationofstorageatalocation,forsafetyreasons.ThereareverystrictconstraintsandpenaltiesinplaceonunauthorisedstorageatallLUpremises,therefore:
• allstoragemustbeinaccordancewithcurrentprocedures
• tostoreanyitemonstationpremisesyoumustfirstobtainastoragelicenceissuedbytheLandlord/Managerofthepremises
• storagelicencesmustshowitemsallowedtobestoredandmustbeclearlydisplayedatthelocation.
5.8 Stores for hazardous materials
Thethreestoragemethodsallowedare:
Permanent store
Isastorageareathatisdesignedtocontainafireandtopreventanexternalfirepenetratingit.Itmustbefittedwithautomaticsuppressionsystemandbecompartmentalised.ThedesignandconstructionmustmeetthespecificrequirementsoftheFirePrecautions(Sub-surfaceRailwayStations)(England)Regulations2009.
Temporary store
Anotherroomsetaside,onatemporarybasisthathassimilarfireresistingcapabilitiestoapermanentstorebutmightnotfullymeetlegislativerequirementsinallrespects,inwhichcaseanexemptionmustbesought.
Portable store
Acontainerdesignedforthestorageofflammableliquidsorsolids.Itmustmeetallofthefireresistingrequirementsofapermanentstorebutwillhavenofireprotectionorautomaticsuppressionsystemfittedwithinit.Itmustbelocatedinasprinkler-protectedarea.
28
sect
ion Site Access Booking for Railway EngineeringSite Access Booking for Railway Engineering5
Thestorageofflammablematerials:
• shouldbekepttoaminimumandrestrictedtoessentialsupplies
• canbestoredlooseinapermanentortemporarystore• canbestoredinaportablestoragebinprovideditdoesnotalso
containflammableliquids.
5.9 Storage of flammable liquids
Flashpointabove55oC(exceptDiesel):
• unlimitedstorageinmetalscrew-toppedcontainers.
Flashpointbetween55oCand21oC(includingDiesel):
• maximumof75litres,in3x25litrered,metalscrew-toppedcontainers.
Flashpointbetween21oCand0oC:
• maximum1litre,in2x½litreredmetalscrew-toppedcontainers.
5.10 Hazards associated with Liquefied Petroleum Gas (LPG)
ThereareverydangerouspropertiesassociatedwithLPG:
• heavierthanair,sinksintopits,platforminvertsandsumprooms
• extremelyflammable.
Flashpointbelow0oC:
• nostorageorusebelowground.
29
section5Site Access Booking for Railway Engineering
Using LPG
Theuseofdisposablecartridgesonblowlampsispermitted,subjecttothefollowingconditions:
• theblowlampmustbeofadesignapprovedbytheengineeringclientresponsibleforthework
• one,plusonesparecartridgemaybetakenunderground,andall,includingemptyonesmustberemovedfromundergroundafteruse.Blowlampsmustneverbeleftunattended
• theuseof4.5kgsizedrechargeablecylindersispermitted,butonlyonecanbeused,nospare.
Gas cylinders
Pressurisedgases(e.g.gascylinders)maybeusedunderground,butonlyduringEngineeringHoursandwithapermitforhotworks.
Movement of materials licence
Mostmaterialsusedinsiteworkatstationscandamageliftsandescalatorsifnottransportedcorrectly.Thisdamagemaynotbeimmediatelyapparent.ItisarequirementofLUtoobtainaMovementofMaterialslicence.
Undernocircumstancesmaygascylindersbestoredunderground.
TheserequirementsarelaiddownintheContractQUENCHconditions.
30
sect
ion Safety Alerts, Bulletins and Tube Lines HSE AlertsSafety Alerts, Bulletins and Tube Lines HSE Alerts6 Emergency plans
6 Safety Alerts and BulletinsHSEalertsareformajorfaultsthatcouldresultinseriousorfatalinjuryandwhereimmediateremedialactionisrequired.
HSEbulletinswillalertyoutosafetyissuesrelatedtohealthandsafetyintheworkplace.
Safety Alerts, Bulletins and Tube Lines HSE Alerts
31
section7Emergency plans
7 Emergency plans
7.1 Evacuation procedures
ThefollowinginformationappliestoallpersonnelworkingintheLineClearareaorrequiringaccessthroughittoreachlocationsoutsidetheLineCleararea.
ThePWT-EHshouldensuretheworkgroupisbriefedontheactionstotakeifanymemberofaworkgroupcausesordiscoversafire,theymustraisethealarmimmediatelybyshoutingorbyanyotherappropriatemeans.
ThePWT-EHmust:
• tellthecontrollerafirehasbrokenout,givingtheexactlocationandnearestentrypointandrequesttheattendanceofthefirebrigade
• followtheevacuationprocedure
• whenevacuatingasite,alertallmembersoftheworkgroupandproceedtotheStaffAssemblyPoint(SAP)bythequickestandsafestroute
• tellotherpersonsmet,forexample,mobilepersonneltoevacuatetothenearestSAP
• iftheevacuationrouteisblocked,usethenearestalternativesafeexitensureallpersonnelareaccountedfor.
ThePWT-EHmustbrieftheworkgroupontheactionsthattheyshouldtakeshouldtheybecomeseparatedduringtheevacuation.ThegroupwithoutthePWT-EHmustnominateapersontosupervisetheevacuationandthispersonmust:
• makesurethatallpersonnelinthisgroupleavethesiteinanorderlymannerbythenearestsaferoutetotheSAP
• tellthecontrollertocontacttheTACwhenallmembersoftheseparatedworkgroupareaccountedfor.
32
sect
ion Emergency plansEmergency plans7
Ifanymember(s)oftheworkgroupismissingthePWT-EHornominatedpersonmust:
• establishwhoismissing
• makesurethefirebrigadehavefulldetailsofanymissingpersonnel
• informtheTACthedetailsofanymissingpersonnel.
Ifanyoftheworkgroupisunaccountedforandthetrackisclear.ThePWT-EHmustnotpasstheSiteClearmessagetotheTACuntil:
• anypersonnelseparatedfromtheworkgrouphavebeenaccountedfor
• allpersonnelareinaplaceofsafety
• tools,materials,plantandequipmentareclearofthetrackanditissafefortrainstorun.
7.2 After an incident
AftertheincidentthePWT-EHshouldreviewthesituationanddecideonanyfurtheractionwiththeincidentofficerifonehasbeenappointed.ThePWT-EHshouldconsider:
• anyassistancethatmightberequiredimmediatelyattheSAP,includingfirstaid
• theneedtomakesurethatmissingpersonsareaccountedfor
• anyactionthatmightberequiredwhentheincidenthasbeendealtwithsothatthetrainservicecanberestored
IftheRendezvousPoint(RVP)islocatedatastaffedstation,amemberofthestationstaffwillmeetthefirebrigade.Ifthisisnotpossibleoritisanunstaffedstationornotastation,thePWT-EHmayhavetonominateamemberoftheworkgrouptomeetthefirebrigadeattheRVP.
33
section7Emergency plans
• anyunsafeconditiononthetrackordamagetoequipmentthatmighthaveoccurredorbeenleftasaresultoftheevacuation
• thelocationoftools,plantandequipmentthathadtobeleftwhenthesitewasevacuated
• anydisconnectionsmadethatmightpreventtheoperationsoftrains.Theabilitytoperformanyfurtherusefulworkduringthatshiftatthesameorotherlocations
• theeffectsontrackpatrollingandthenecessitytomakesurefurthertrackinspectionsarecarriedout,ifrequired
• theneedtobookprotectionagainwiththeTACbeforeenteringthetunnelsdepending,ifappropriate,onadviceoftheEmergencyServices
• therequirementtoprovideafullreportoftheincidenttothemanagerofthepersonsinvolved.
ThePWT-EHmustcomplywiththeincidentreportingprocedureandprovideanincidentreportasnecessary.
First aidersThePWT-EHmustensurethatfirstaidprovisionsareavailablefortheworksite.
Spill kits
Thepurposeofspillkitsistosoakupallspills,dripsorleaksandpreventpollutingtheenvironment:
• thetypeofspillkitrequiredwilldependonthematerialtobeused
• accesstothespillkitshouldbeprovidednearstorageareas,fillingpointsorportablekitsforuseonsite
Forotherseriousincidents(forexampleflooding,gasleak,toxicchemicalspillage,ortunnelcollapse)therequirementsofthissectionmustbefollowed.
34
sect
ion Emergency plansEmergency plans7
spillkitscomeindifferentsizecontainersorbagsandcontaintheinstructionsandanassortmentofabsorbentmaterials.
Thesecontainersarenotforthepurposeofdisposingthewastespillageonlyforstoringcleanspillkits.
Whenaspillageorleakoccurs:
• firstidentifythematerialandselectthecorrectspillkit
• wearappropriatePPE
• protectanydrains,soakawayoropenwaterwayswithabsorbentsockorboom
• soakupspillagewithabsorbentmatsorgranules
• whenthespillhasbeenabsorbed,theusedspillkitshouldbetemporarilydisposedofinthewastebagsprovidedreadytobestoredinanapprovedstoreawaitingcollection.Thespillmustbereportedasperthecompaniesincidentreportingprocess
• anewspillkitshouldbeordered.
Incident management & reporting
IfahazardisbroughttotheattentionofthePWT-EHtheymust:
• investigateandmakeanassessmentofthesituation
• arrangeremedialactionasrequired
• avoidargumentifatallpossible,butifnecessary,insistonsafetyandreporttheincidenttotheirmanager
• completetheircompaniesincidentreportingprocess
35
section7Emergency plans
Thefollowingaccidentsandincidentsmustbereported:
• allinjuries
• nearhits
• allhazards
• crime
• fires
• structuralfailures
• environmental.
Theonlyexceptionstothisareif:
• theareaisunsafe
• theareahastobeevacuated
• staffneedmedicalattention.
7.3 Emergency arrangements
Whenworkisplanned,thefollowingarrangementsforemergencysituationsmustbeincluded:
• whowillbethedesignatedpersontohandletheemergency
• whatthispersonmustdo(contacttheController,arrangeforfirstaid,meettheemergencyservices)
• howtheControlleristobecontacted.
ThereisalegaldutytoreportallincidentsimmediatelyandthePWT-EHmustensurethatpersonnelwhowitnesstheincidentstayattheworksiteuntiltheresponsiblemanagerorBritishTransportPolice(BTP)tellthemtheycanleave.
ItistheresponsibilityofthePWT-EHtoensurethatallincidentsarereportedasinstructedbytheircompanyincidentreportingprocedure.
Drawings
36
sect
ion Lifting plans for lifting operationsDrawings8
8 DrawingsThePWT-EHmuststudyandunderstandallclearanceapprovalandprojectdrawings.Drawingsandothermaintenanceinstructionsmustbekeptuptodateandmadeavailabletostafforcontractorsforguidance.
Drawings
37
section9Lifting plans for lifting operations
9 Lifting plans for lifting operationsHeavyliftsusingcranesandothercomplexliftsusingchainblocksrequireliftingplans,competentperson(s),appointedperson(s)andqualifiedbanksman/slinger.
Abanksman/slingerisdefinedasacompetentpersoncapableof:
• selectingandattaching/detachingliftingtackletoandfromtheload
• directingthemovementofloadsbycranepowerwithinthesafesystemofwork.
Thebanksman/slingershouldbeinpossessionofacertificateofcompetencewhichhasavalidityperiodoftwoyears.
38
sect
ion Tool box briefing and communicationTool box briefing and communication10
10 Tool box briefing and communicationTheworkgroupmustbebriefedonallaspectsoftheworkandthePWT-EHmustensurethatallpersonsintheworkgroupare:
• fitforworkandcompliantwiththeLUdrugsandalcoholpolicy
• wearingthecorrectPPE
• suitablycertificated
• awareoftheagreedcommunications.
10.1 LU drugs and alcohol policy
Ifamemberoftheworkgroupissuspectedofbeingundertheinfluenceofalcoholordrugs,thePWT-EHisresponsibleforinforming:
• theirmanager
• thestationsupervisor
• theBTP.
10.2 Personal Protective Equipment
PPEmustbeworninaccordancewiththemethodstatementanditistheresponsibilityofthePWT-EHtoensure:
• LUapprovedhighvisibilityclothingiswornatalltimeswhenonLUinfrastructure
• suitableworkclothingisprovidedandworncorrectly
• theworkgroupwearsturdyfootwearsuitableforthetask
• hardhatsarewornindesignatedareas
• gloves,eye,earprotectionanddustmasksareprovidedandworncorrectlyifrequired.
39
section10Tool box briefing and communication
10.3 Leptospiral Jaundice
LeptospiralJaundice(Weil’sdisease)transmittedbyratsurineandothervermin,inwater.Ifuntreateditcanbefatal:
• coverallcutsandabrasionswithwaterproofplasterspriortoworking
• wearsuitableprotectiveclothing
• nevertouchfacewithunwashedhandsorgloves
• ifscratchedwhilstworking,washandreporttodoctor
• washyourhandsbeforeyoueat,drinkorsmoke
• whenworkisfinished,washhandsthoroughlyincleanwater.
40
sect
ion Environmental IssuesEnvironmental Issues11
11 Environmental IssuesThePWT-EHandtheworkgroupmustbeawareofthefollowingenvironmentalissues:
11.1 Waste management
BeawarethatwastemanagementiscontrolledbylawandthePWT-EHmustensurethatalloftheworkgroupcomplyby:
• disposingofwasteinthecorrectsegregatedbins
• storingmaterialscarefullysotheydonotgetspoiled
• ensuringthatwasteisremovedbylicensedcontractorsandisaccompaniedbywastetransferdocumentation
• ensuringhomewasteisnotbroughtontotheLUinfrastructure
• ensuringwasteisremovedfromtheworksiteattheendoftheshift
• reportingillegalflytippingtotheirmanager.
11.2 Noise
Noisecanresultinpoorcommunityrelationsandpossiblynoiseabatementswhichcouldresultinworkbeingstopped.Wherereasonablypracticable:
• keepshoutingtoaminimum
• turnenginesoffwhenvehiclesandmachineryarenotinuse
• keepnoisyplantandactivitiesawayfromresidentialpropertieswherepossible
• considerlocalbusinessesandresidentswhenyoupark
• reportallcomplaintstoyourmanager.
41
section11Environmental Issues
11.3 Hazardous materials
HazardousmaterialsmustbestoredincontainersappropriateforthematerialaccordingtocurrentRegulations.Asaminimumthestoredmaterialmustbe:
• segregatedandsecure
• labelledashazardoustoindicatecontents
• unabletoescape,leakorproducefoulodourorattractpests
• storedordecantedatleast10metresawayfromsensitivereceptorse.g.drainsandsurfacewater.
11.4 Pollution prevention
Pollutingrivers,streamsandgroundwaterisillegal.Evensmallamountsofsomematerialscancauseseriouspollution.
ThePWT-EHmustbemadeawarethat:
• manyofourdrainsgodirectlytoriversorstreams
• drainsarenotadisposalrouteforwastes
• oil,fuel,antifreeze,siltandweedkillerarejustsomeofthepollutingmaterialsusedonLU.
ThePWT-EHmust:
• storematerialsinthecorrectareas
• reportspillageincidentsusingtheircompaniesincidentreportingprocedure.
Environmental Issues
42
sect
ion Weedkilling TrainEnvironmental Issues11
11.5 Wild life and habitat
LUinfrastructureishometomanylegallyprotectedspeciesandthatthePWT-EHmustensuretheworkbeingcarriedoutdoesnot:
• disturbnestingbirds
• disturbprotectedspecies,suchasbats,badgersandslowworms
• spreadJapaneseKnotweed.
Anyaccidentaldisturbanceofwildlifeandhabitatmustbereportedtotheirmanager.
Environmental Issues
43
section12Weedkilling Train
12 Weedkilling TrainTheweedkillingtraincancreateanothertypeofhazard,andspecialprecautionsmaybenecessarytoprotecttheworkgroupifenteringanareawithin24hoursofapplication.
TheoperationoftheweedkillingtrainispublishedintheTrafficCircularonaweeklybasisandontheNEPAonanightlybasis.Ifaworkgroupisjustpassingthroughatreatedarea,within24hoursofapplication,withoutcarryingoutwork,thentheydonotrequirespecialprecautions.
Ifworkinginatreatedareawithin24hoursofapplication,thePWT-EHmust:
• makesuretheywearapproveddisposableoveralls,andglovesifworkingincontactwithvegetationortrackcomponents
• ensurecontaminateddisposableclothingissealedintoplasticbagsanddisposedofcorrectly
• ensureworkgroupscrubandwashtheirbootsunderrunningwaterattheendoftheworkinatreatedarea
• advisetheworkgrouptowashtheirhandsbeforetouchingtheirfaceorbody,andespeciallybeforeeatingorsmoking.
Planning the protection for the work
44
sect
ion Site familiarPlanning the protection for the work13
13 Planning the protection for the workThefollowingmustbeconsideredandthePWT-EHmustdeterminewhatareasmustbebookedviatheLineClear/LineSafeprocesstoprotecttheworkgroup:
• tractioncurrentsectionstobeworkedon
• adjacentsections
• tractioncurrentswitchingtimes
• siteaccessandegress
• evacuationprocedures
• hazards
• relevantTACandSignallerscontactdetails
• generalcommunicationsavailable
• multiworkgroups
• equipmenttobeused.
Planning the protection for the work
45
section14Site familiar
14 Site familiar
14.1 Basic areas
Theseareasaredefinedassingleordoubletrackswithsomepointsandcrossingsbutnomajorjunctionsorrestrictivefeaturessuchasalongviaductorflyunder.
PWT-EHcanmakethemselvesfamiliarwithabasicareaby:
• takingacabrideinatrain
• studying‘placesofsafety’maps
• studyingthetrafficcontrollers’diagrams
• studyingothersourcesofavailableinformation
• walkingthesitebeforetakingaworkgroupontothetrack.
Platformgroundsaretreatedasbasicareasexceptwherethereis:
• multitrack
• locationswithotherrestrictivefeatures.
14.2 Complex areas
Theseareasaredefinedasmulti-tracksites,majorjunctionsandlocationswithrestrictivefeatures.Therisksaregreaterduetothephysicalconditionsontheground.Personsprovidingprotectionwhoareunfamiliarwitharea(s)thatareclassifiedascomplexmustmakeasitefamiliarisationvisit,accompaniedbyprotectionstafffamiliarwiththearea.Thiscouldinvolveanumberofvisitsbeforethepersonisfullyfamiliarwithallthelocalconditions.
DetailsofBasicandComplexareascanbefoundintheSiteFamiliarInformationdocumentavailablefromtheNetworkImprovementwebsite.
46
sect
ion Site familiarSite familiar14
14.3 Local conditions
Conditionsencounteredatindividuallocation(s)mightinclude:
• bi-directionalworking
• multi-trackareas
• parallelrunningorjoiningend-ontoNRorotherorganisations’linesobstructions
• accessroutesandwalkways
• depotsandsidings
• tractioncurrentarrangements
• tractioncurrentrailgaps.
14.4 Traction current sections to be worked on
ThetractioncurrentsectionstobeworkedoncanbefoundontheNEPAmaps.
14.5 Adjacent sections
Therewillbesituationswheretheadjacentsectionswillberequiredtobebookedforprotection,e.g.inLSareas.
14.6 Tractions current switching times
Areasindoubletracktunnels,tractioncurrentwillnormallybeswitchedonandoffatthesametimeontheadjacentsections.TheseareasarelistedinRuleBook16(GoingonthetrackinEngineeringHours).Alsoinsomelocations,tractioncurrentcanbeswitchedonandoffatdifferenttimesonadjacentroads.
47
section14Site familiar
14.7 Multi work groups
OnePWT-EHcanprotectseparatelylocatedworkgroupsworkingonstationplatformsaslongas:
• theworkispre-plannedandamethodstatementandriskassessmentincludingaprotectionplanisprovided
• two-waycommunicationsareprovidedwherepersonnelareworkingoutofdirectverbalcontactwitheachother,andeachworkgrouphasitsownPWT-EH
• personnelstaywithintheareadetailedintheprotectionplanandworkonlyontheplatformorthetrackareasofastationnotfittedwithPEDs,whichisuptoandincludingtheplatformrampsortheheadwalls
• theworklimitsaredefinedonsite,includingifnecessaryusingwarningnoticesorothervisibledemarcation(e.g.temporarybarriers).
48
sect
ion Site familiarSite familiar14 Tools, equipment and materials
OnePWT-EHcanprotectseparategroupsofpersonnelonthetrack,aslongas:
• theworkispre-plannedandamethodstatementandriskassessmentincludingaprotectionplanisprovided
• wherethereareseparategroupsofpersonnel,eachgrouphasitsownPWT-EH
• thepersonprovidingtheprotectioncanremainintwo-waycommunicationwitheachPWT-EH
• thepersonprovidingtheprotectionremainsintheareabookedwiththeTACandcanmaintaincontrolofthearrangementsonsiteatalltimes
• eachPWT-EHremainswiththepersonneltheyareresponsibleforthroughoutthework.
IfthedesignatedPWT-EHthatisnotprovidingtheprotectionisrequiredtoleavetheworksitetheymust:
• nominateasuitablycertificatedpersontotakeoverthedesignatedPWT-EHresponsibilities
• informthePWT-EHprovidingtheprotectionandprovidethenameofthedesignatedPWT-EHtakingover.
ThePWT-EHprovidingtheprotectionmustremainwiththeworkgroup(s)theyareprotecting.IfitisnecessaryforthePWT-EHprovidingtheprotectiontoleavetheworkgroup(s),theymusttaketheworkgroup(s)offthetrack.
IfthereismorethanonePWT-EH,thepersonprovidingtheprotectionmustdecidewhichPWT-EHwillcommunicatedirectlywiththem.
TheonlyexceptiontothisiswhenrequestingLSP.ThesafetyoftheworkgroupmustbeconsideredifthePWT-EHleavestheworkgroup.
Site familiar
49
section15Tools, equipment and materials
15 Tools, equipment and materialsWhenplanningtheworkthePWT-EHmustensurethatthefollowingrequirementsaremet:
• whatequipmentcanbeusedandwhere
• calibration
• fitforpurpose
• indate
• materials
• spares
• personnelaretrainedtousetools.
ThereareadditionalfactorstoconsiderwhenusingcertainequipmentduringEngineeringHours.
15.1 Diesel power packs and gas monitoring equipment
IftheworkisinaLineClearareaandtheuseofadieselpowerpackisrequired:
• gasmonitoringequipmentmustbeused
• itmustbepublishedwhenpossible
• onthenightofusetheTACincidentdeskmustbeinformedbefore23:00hours.
15.2 Track trolleys
AnytracktrolleyproposedtoworkonLUinfrastructuremustsatisfyLU’sdesignstandardsandisofatypeapprovedforuseonLU.AlltrolleysirrespectiveofownershipmustberegisteredonaPlantMaintenanceManagementSystemandmustbeallocatedaregistrationnumberwhichisuniquetoeachtracktrolleyandcontaintheassetholder’sreferencenumber.
Atwo-piecetracktrolleymusthavethesamereferencenumberpermanentlyfixedtoeachpartofthetracktrolley.
50
sect
ion Tools, equipment and materialsTools, equipment and materials15
Whentracktrolleysarebeingused,includingmotorisedtrolleysandrailcycletracktrolleys.
ThePWT-EHmust:
• setupasafesystemofworkcoveringthemovementoftrolleys
• atthestartoftheshift,telltheappropriatesignallertherequirementtosecurepoints
• ensurethatanytracktrolleyoperatorhasbeentrainedandcertificatedforthetypeoftrolleybeingused
• thetracktrolleyoperatortakesresponsibilityforplacingthetracktrolleyonthetrackandremovingitafteruse
• tellthetracktrolleyoperator(s)informationabouttrackcant,curvatureandgradientbeforethetracktrolley(s)isplacedonthetrack
• ensurethatacertificatedtracktrolleyoperatoraccompanieseachtrolley
• controlthemovementsoftracktrolleysbeingusedincloseproximitytoeachothertoensuresafetyismaintained
• briefallstaffonhowandwherethetracktrolley(s)istobeused
• ensurenobodyridesonatracktrolleyunlessitispurposebuilt
• oncompletionofthework,confirmtotheappropriatesignallerthatallpointsareun-secured.
Ifarailcycletracktrolleyisbeingused,theoperatormustbeacertificatedPWT-EH.
51
section15Tools, equipment and materials
15.3 Carrying scaffolding or towers
Whentracktrolleysareusedtotransportscaffoldingortowers,asafetyplanmustbedrawnupbytheresponsiblemanagerandmustinclude:
• thenumberoftrolleystobeused
• stabilityfactorsofthescaffoldingortowerwhenbeingusedandwhenbeingmoved,takingintoaccounttrackgradient,cantandcurvature
• clearancesfromoverheadstructuresorcables
• thecompetenceofthoseerectinganddismantlingthescaffoldingortower
• thesafetyofallpersonnelinvolvedinthetask.
15.4 Storage of track trolleys
ThePWT-EHisresponsibleforensuring:
• astoragelicenseisappliedfor
• thatwhenstorednearthetrackthetracktrolleyissecuredbychainandpadlockanddoesnotobstructthecess
• thatifthetrolleyiscapableofbeingdismantled,eachcomponentmustbesecuredbychainandpadlock.
15.5 Motorised trolleys and railcycles
WhenamotorisedorarailcycletracktrolleyisbeingusedintheLineClearorLineSafe(orboth)areaduringEngineeringHoursdetailsofitsworkingareamustbepublished.Inanemergencywhereithasnotbeenpossibletopublishdetails,theTACincidentdeskmustbeinformedbefore23:00.TheTAC’spermissionisrequiredforitsusefortheshiftconcerned.
52
sect
ion Weather conditionsWeather conditions16 Traction current supply
16 Weather conditionsLU’sdefinitionofwetweather:
• continuousrain,hailorsnowandperiodswhenthetrackiswetenoughtoincreasetheriskofelectrocution.
LUhasafirmpolicyonwetweather:
• livetrackmustnotbeworkedonduringperiodsofcontinuouswetweather
• thepolicyappliestoeveryone,LUandsupplieremployees
• staffhavetherighttorefusetoworkiftheyconsideritdangerous.
Whenworkingduringwetweather:
• thePWT-EHmakesthedecisionweatherworkwilltakeplace
• wetweathermightincreasetheunderfoothazardsinopensections
• ifthetrackislive,wetclothingcanincreasetheriskofelectrocution.
Weather conditions
53
section17Traction current supply
17 Traction current supplyTractioncurrentisfedtothetractioncurrentrailsfromanumberofsubstations.Eachtractioncurrentsectionhasasubstationateachend(inmostcases).Thereisarailgapattheendofeachtractioncurrentsection,wherethefeedchangestoanewsubstation(inmostcases).
SubstationgapsarenormallyindicatedbyarailgapindicatorandthesearenormallyonlyvisiblewhenapproachingasubstationgapintheDirectionofTravel(DOT).
ThenamingofthesectionsistakenfromthenamingofthesubstationsateachendofthesectionintheDOT.Thisnamingisoftentakenfromtheundergroundstationtheyarelocatedatornear.Insomecasesthesubstationsarenamedafterthestreetorroadtheyarelocatedin(e.g.CobourgStreettoCloudesleyRoadontheVictorialine).
WhenaccessisbookedwiththeTAC,inadditiontoknowingtheworksitelocation,thenamesofthetractioncurrentsectionstobeworkedonmustalsobeknown,andanysection(s)requiredforadditionalprotectionpurposesorforaccess.AllsectionsmustberecordedcorrectlyintheLC/LSlogbook.
TheTACmayaskthePWT-EHtoconfirmiftheyhavethecorrecttractioncurrentsection(s)recorded.TheTACwillrefuseaccessifthecorrecttractioncurentsection(s)arenotidentified.
Nightly Engineering Protection Arrangements Maps
54
sect
ion Specified AreaNightly Engineering Protection Arrangements Maps18
18 Nightly Engineering Protection Arrangements MapsThesemapsareprovidedforpersonsprovidingprotection.Theyshowthetractioncurrentsectionusingcolourcoding.
ThePWT-EHmustusetheNEPAmaps,toidentifytherelevanttractioncurrentsectionsrequiredforthework.
Nightly Engineering Protection Arrangements Maps
55
section19Specified Area
19 Specified AreaWhenanengineer’strainormechanisedvehicleisrequiredtoworkwithtractioncurrentoffinEngineeringHours,itmustdosoonlywithinaspecifiedareaorapossession.
56
sect
ion Specified AreaSpecified Area19 Working with an engineer’s train or
mechanised vehicle
SpecifiedareaswithinsingleboretunnelsinLineClearareasmustbedefinedfromonestationtoanother(includingdisusedstations)and,unlessotherwisepublished,theentirelengthofanyplatformsattheextremitiesofthespecifiedareamustbeincluded.Thiswillprovideaccesstoleavethetunnelinanemergency.ThisrequirementalsoappliestoallreductionsinlengthofspecifiedareaswithinLineClearareas.
SpecifiedareaswithinLineSafeareasanddoubletrackLineClearsectionsmustonlybedefinedfromthefollowinglocations:
• stationplatforms(whenincludingtheentireplatformlength)
• stationstarterfixedsignals(whennotincludingtheentireplatformlength)
• otherfixedsignals
• tunnelmouthsorbridges
• tractioncurrentrailgaps
• junctions(thelimitsofspecifiedareasdefinedatpointsorcrossoversmustalwaysincludethewholesetunlessotherwisestated).
Specified Area
57
section20Working with an engineer’s train or mechanised vehicle
20 Working with an engineer’s train or mechanised vehicleThePWT-EHmust:
• ensureallmembersoftheworkgrouparecertificatedtoworkwithmovingtrains
• briefeachpersoncontrollingthetrainmovement,andeachengineer’strainoperatorormechanisedvehicleoperator,toagreethecommunicationdetailsandtheuseofcabtelephonesorhand-heldradios(orboth)
• briefthepersoncontrollingthetrainmovementabouttheengineer’strainormechanisedvehiclemovementstheworkwillrequire
• ensuretheworkgroupmovetoasafeplacebeforeanyengineer’strainormechanisedvehiclemovement
• ensuretheloadingofanengineer’strainisalwayssupervisedbyacompetentperson.
20.1 Travelling on an engineer’s train
Engineer’strainsworkinginapossessionoraspecifiedareamustnotcarrypersonnelinthewagonsunlessitisnecessaryandsafetodoso,andthefollowingconditionshavebeenmet:
• tractioncurrentisoffatalltimes
• thereissufficientroomwithinthetrainandtrainloadsareproperlysecured
• thewagonsarefittedwithsidesorhandrails
• personnelcansafelygetonandoffthetrainfromaplatformorviatheapprovedwagon
• therearestepsandhandrails
• personnelmustnotgetonoroffwhilethetrainismoving
Working with an engineer’s train or mechanised vehicle
58
sect
ion Working with an engineer’s train or
mechanised vehicle Working with an engineer’s train or mechanised vehicle20• allpersonnelaregivenasafetybriefingontheproceduresto
follow,beforetheygetonthetrain
• personnelmustpositionthemselvessotheywillnotcomeintocontactwithanystructurewhichcouldcausetheminjury
• communicationwiththetrainoperatormustnotbeadverselyaffected
• thetrainisdrivenslowly
• whilethetrainismovingallpersonnelmustobservesafetyprocedures.Ifanunsafesituationarises,thetrainmustbestoppedassoonasitissafeandreasonablypractical
• personnelworkingwiththetrainmustnotgetonoroffthetrainuntilithasbeenconfirmedthatitissafeforthemtodoso.
20.2 Working with on-track plant
Whenworkingwithon-trackplantthePWT-EHmustbrieftheoperatoroftheon-trackplantandanybanksman/slingerworkingwithit.Thebriefingshouldinclude:
• thelimitsandscopeoftheworktobeundertakenattheworksite
• theemergency,safetyandfirstaidproceduresfortheworksite
• whatplantandequipmentwillbeinoperationattheworksite,andwhatprocesseswillbeundertaken
• theidentityandauthorityofthepersonappointedtocontroltheon-trackplant
• thelocationswheretheon-trackplantcanbeonandofftracked
• thelocationswheretheon-trackplantcanbestabled
• whatactionstotakewhenapproachingasetofpoints
• theactiontotakeiftheon-trackplantrunsoveradetonator
• themethodofwarningtousebeforemoving
Working with an engineer’s train or mechanised vehicle
59
section20Working with an engineer’s train or mechanised vehicle
• thehandsignalstobeused
• anyotherinformationrelevanttothesafemethodofworking.
20.3 Unrelated work in a specified area
Unrelatedworkinaspecifiedareacanonlybepermittedinanemergency,whenthereisurgentworkthatiscriticaltotheoperationoftrafficthenextday.
Unrelatedworkinaspecifiedareaisnotpermittedif:
• anengineer’strainisscheduledtouncoupleinthecourseofwork
• thereismorethanoneengineer’strainworkinginthespecifiedarea.
20.4 Conditions of unrelated work being permitted
TocarryoutunrelatedworkinaspecifiedareathePWT-EHmust:
• becertificatedforbothTrafficandEngineeringHoursprotection
• havetheagreementoftherelevantpersoncontrollingthetrainmovement
• makesurethatallpersonnelbeingprotectedarecertificatedtoworkwithtrainsmoving.
ThePWT-EHmustasktheTACforthedetailsofthepersoncontrollingthetrainmovementresponsibleforthespecifiedarea.
60
sect
ion Working with an engineer’s train or
mechanised vehicle Working with an engineer’s train or mechanised vehicle20 Engineer’s Current Area
ThePWT-EHmustagreethefollowinginformationwiththepersoncontrollingthetrainmovement:
• thenatureandlocationofthework
• thenumberofpersonnelinvolved
• movementoftheengineerstrain
• theprotectionarrangementsbeingapplied
• workingandcommunicationarrangementstobeused
• thetimeworkwillbefinished.
Specifiedareaagreementformsmustbecompletedwhenundertakingunrelatedworkinaspecifiedarea.Additionalprotectionfrommovingtrainsmightberequired.
Working with an engineer’s train or mechanised vehicle
61
section21 Engineer’s Current Area
21 Engineer’s Current AreaAnEngineer’sCurrentArea(ECA)isusedwhereatrainisworkingwithtractioncurrentonduringEngineeringHours.ThetractioncurrentsectionswithinthelimitsofanECAareknownas‘Active’tractioncurrentsections.Thismeansthesetractioncurrentsectionshavetractioncurrentswitchedonforthemovementofthetrain.
ToprotecttheECA,alltractioncurrentsectionsadjacenttothe‘Active’tractioncurrentsections,mustbeswitchedoff.Thesesectionsthatareswitchedoffareknownas‘Allied’tractioncurrentsections.TheyincludealltractioncurrentsectionswhereitisphysicallypossibleforatraintogainaccesstotheActivetractioncurrentsections.
StaffcanworkintheAlliedsectionsofanECAaslongastheyareprotectedbyLineClearorLineSafeprocedures.
Thearea,overwhichthetrainwillbeworking,definedbylampsanddetonators,istheECA.
SpecialarrangementswillhavetobemadeifpersonnelarerequiredtoworkinanECA;thiswillonlybedoneinanemergency,co-ordinatedbytheTAC.
62
sect
ion Nightly Engineering Protection Arrangements Nightly Engineering Protection Arrangements22 Signing in at the station
22 Nightly Engineering Protection Arrangements
TheNEPAprovidesalltheinformationfortheworkthatistakingplacethatnight.Itprovidesinformationinalogicalwayinasingledocumentfortheline(s)thePWT-EHisworkingon.
TheNEPAcontainsthefollowinginformation:
• IDcodes
• tractioncurrentsections
• tractioncurrentswitchingtimes
• lastservicetrainnumberandtimebyplatform
• engineer’s/servicetrainscausinglatecurrentandexpectedswitchofftime
• exclusiveandhazardousareas
• TACtelephonenumber
• relevantsignallerstelephonenumber.
OncethePWT-EHhasobtainedallrelevantinformation,theLC/LSlogbookcanbecompletedwiththedetailstheTACwillrequirewhenrequestingaccess.
Nightly Engineering Protection Arrangements
63
section23 Signing in at the station
23 Signing in at the stationAllstafforvisitorswhenworkingatorvisitingastationotherthantheirnormalplaceofworkmustsigninwiththestationsupervisoronarrivalandsignoutondeparture.Onarrivaltheymust:
• givetheirnameandshowtheiridentification
• explainthepurposeoftheirvisit
• giveallrelevantdetailsasnecessary.
Toworkonastationyoumusthaveeither:
• avalidSABREnumberandbelistedontheStationWorksPlanorGenericAccessPlan
• avalidrecognisedfaultnumber.
Thefollowingarenotrequiredtosigninwiththestationsupervisor:
• emergencyservicespersonnel
• LUoperationalstaffortheEmergencyResponseUnit,attendinganincident,unlesstheyremainonthestationaftertheincident
• signalandtraintechniciansattendingafaultorincident,unlesstheyremainonthestationaftertheincident
• policeofficersonpatrolduties
• revenuecontrolinspectorsorHMRevenue&Customspersonnelinplainclothes
• staffemployedorbookingonatengineeringdepots,forexampleatrackcabin,thatareanintegralpartofastation.
Staffwalkingthroughastationattracklevelarenotrequiredtoreporttothestationsupervisorofthatstation.Suchstaffmustreporttothestationsupervisorsatthestationswheretheystartandfinishtheirtrackwalks.
64
sect
ion Signing in at the station Signing in at the station23
23.1 Engineering Hours
ThePersoninChargeEvacuationRegister(PiCER)isthestationaccessprocess.ItiscompletedbythePWT-EH.ThePiCERisapplicabletoallpersonsorgroupsofpersonsattendingastationforworkontheLUinfrastructure.
WhenthePiCERformhasbeensignedoffthePWT-EHmust:
• signinandrecordthenumberofstaffintheworkgroupinthevisitor’sbook
• taketheappropriatenumberofvisitorspasses
• recordthepassnumbersinthevisitors’book.
InthecaseofEngineeringHoursandlargeworkgroups,thePWT-EHisresponsibleforconfirmingthevalidityoftheLUCAScards.
65
section23 Signing in at the station
23.2 Accessing unstaffed stations
IfaccesstoaclosedoranunstaffedstationisrequiredthePWT-EHmust:
• makearrangementsbeforehand
• agreewheretosigninandcollectanykeysifrequired.
WhensigninginatanystationthestationsupervisormustgivethePWT-EHdetailsof:
• theemergencyevacuationprocedureandSAP
• thefirealarmprocedure
• theavailabilityoffirstaidequipment(ifnoneprovidedunderthesafesystemofwork)
• anyoperationalsafetyrestrictionsonthestation
• anyadditionalhazards.
ThePWT-EHmustrepeatthebriefingtoallpersonsintheworkgroup.
Iftheunstaffedstationbecomesstaffedyoumustcanceltheoriginalpassorpassesandsigninthevisitorsbookatthatstation.
66
sect
ion Signing in at the station Signing in at the station23 Communications
23.3 When contractors arrive late
IfpersonnelarriveaftertheworkgrouphasbeensignedinthestationsupervisormustcontactthePWT-EHandaskthemtoattendtheofficetoassistwiththesigninginoftheadditionalmembersoftheworkgroup.ThePWT-EHcanappointacompetentdeputytoassistwiththis.
23.4 When a contractor wishes to leave early
ThePWT-EHmustmakesuretheworkgroupisawarethattheymustsignoutwiththestationsupervisoriftheywishtoleavebeforethePWT-EH.
23.5 Denied access
IfthestationsupervisorhasconcernswhichcannotberesolvedwiththePWT-EH,theymustnotdenyaccess.ThestationsupervisormustinformeithertheDutyOperationsEngineer,orDutyOperationsManagerengineeringviatheFRC.Deniedaccesscanonlybeimplementedwhenauthorisedtodoso.
Thestationsupervisormust:
• informthePWT-EHthataccesshasbeendenied
• completeadeniedaccessformdetailingthereasonforthedeniedaccessandissueittothePWT-EH
• askthePWT-EHtosignthedeniedaccessform.
Signing in at the station
67
section24 Communications
24 CommunicationsThefollowingareexamplesofthevariousmethodsofcommunicationusedonLU:
• connectradios
• handsignals
• mobilephones
• BTphones
• LUautonetwork
• verbal.
A Alpha J Juliet S Sierra
B Bravo K Kilo T Tango
C Charlie L Lima U Uniform
D Delta M Mike V Victor
E Echo N November W Whiskey
F Foxtrot O Oscar X X-Ray
G Golf P Papa Y Yankee
H Hotel Q Quebec Z Zulu
I India R Romeo
68
sect
ion Communications Communications24 Booking on with the TAC
24.1 Using Numbers
Numbers10andabovebeingusedinamessage,mustbestatedoneatatime.
Forexample,‘Train123’mustbespokenas‘Trainonetwothree’not‘Trainonehundredandtwentythree’
Thenumber‘0’as‘zero’
Whensignals,points,traindescriptionsorlocationshavesimilarnamesornumbers(forexample,signalsA114andA314onadjacentlines),caremustbeexercisedsoasnottocauseconfusion.
Numbersshouldnotbequotedseparatelywhentimesarebeingstated,forexample,thetime13.17hoursshouldbestatedas‘thirteenseventeen’.
Communications
69
section25 Booking on with the TAC
25 Booking on with the TACThePWT-EHmustbookonwiththeTACbeforegainingaccesstothetrack.TheTACdesksareopenforbookingsaspublishedeachnight.PersonsprovidingprotectiondonothavetowaittogettotheaccesspointbeforebookingonwiththeTAC,buttheymusthavepreparedtheirLC/LSlogbookwiththeinformationgatheredduringthepreparationstage.
WhenbookingonwiththeTACatalocationotherthantheaccesspoint,thepersonsprovidingprotectionmustgivetheTACacontactnumberincasetheyneedtobeinformedofanylatechanges.
OnoccasionsitmaybenecessarytobookonwithmorethanoneTACwhenthebookingcoversseparateTACcontrolareas
WhenbookingonwiththeTAC,thePWT-EHmustfollowthepromptsgivenbytheautomatedtelephonesystem.
Whenpromptedtheymustconfirmthat:
• theyhaveenteredtheirIVandSABRENumber(s)
• theyhavereadtherelevantpublications
• theyhaveaccesstoanapprovedCRID
• theSPCispresent,ifapplicable.
ThePWT-EHmustprovidetheTACwiththefollowinginformation:
• confirmationofnameandemployer
• locationofwork
• natureofwork
• numberofstaff
• equipmentbeingusedandwhetherthetrackisbeingmadeunsafe
• contactnumber.
70
sect
ion Booking on with the TAC Booking on with the TAC25 Work group safety briefing
TheTACmaygiveadditionalinformationthatmightaffectthebooking.Forexample:
• anengineer’straintravellingthroughtheareahasbeencancelled
• servicedisruption,laterunningtrainsoutofturn,changestolasttrainnumbers
• winterweatherarrangementsandadditionalhazards
• revisedtractioncurrentalterations.
ThisinformationmustberecordedintheLC/LSlogbook.
TheTACwillthenprovidethefollowinginformation:
• confirmationofbooking
• confirmationoftrainsholdinglatecurrent
• detailsofanymotorisedtracktrolley(s)
• dieselpowerpackuserspublishedoralreadybookedonintheLineCleararea.
ThefollowinginformationmustberepeatedbacktotheTACandrecordedintheLC/LSlogbook:
• TACreferencenumber
• callbacktime
• timecheck.
Ifworkingonmorethanonetractioncurrentsection,thecallbacktimegivenwillbeforthetractioncurrentsectionwhichwillbeswitchedonfirst.
Thecallbacktimeisnormally20minutes(10minutesfortheWaterlooandCityline)beforetheswitchingontimeforthetractioncurrentsection(s)thataccessisbeingbookedfor.
Booking on with the TAC
71
section26 Work group safety briefing
26 Work group safety briefingAfterbookingonwiththeTAC,thePWT-EHmustholdasafetybriefingwiththeworkgroupandinformthem:
• towearLUapprovedPPEwhenonthetrack
• oftherelevantdetailsoftheprotectionplan
• thelocationoftheworksite
• anyotherworkintheareawhichcouldaffecttheirwork
• ofanytracktrolleyworkings
• ofthetimetostopwork
• whenitisexpectedtobesafetogoonthetrack
• ofanyotherrelevantinformation.
Thisistheminimumcontentofasafetybriefing.
Contacting the signaller
72
sect
ion Contacting the signaller27
72
Current Rail Indicator Device
27 Contacting the signallerPWT-EHmustwitnessthepassageofthelasttrain.Ifthishasnotbeenpossible,theymustcontacttherelevantsignallertoensurealltrainmovementshaveceasedintheareabeingaccessed.TheNEPAwillshowanychangestothelasttrains.Thefrontandrearofatrainmustbecheckedtoconfirmthetrainrunningnumber.
Stationstaffwillnotbeabletoconfirmifthelasttrainhasdepartedtheirstation.
Contacting the signaller
73
section28 Current Rail Indicator Device
28 Current Rail Indicator Device
28.1 Prior to using a CRID
ThePWT-EHmustinspecttheCRIDforvisiblesignsofdamage,defectanddateofexpiry.
IftheCRIDappearstobedamaged,defectiveoroutofdate,itmustnotbeusedandareplacementmustbeobtained.
ThePWT-EHmustself-testtheCRIDby:
• connectingthetwounitstogether(basetobase)byaligningthearrows,usingtherailsecuringmagnetstoholdtheunitsinplace
• pressingandholdingthetestpushbuttonforatleastfiveseconds.Checktheredbatterystatusindicatorilluminates.Ifitdoesnot,theCRIDcanbeusedforthatshiftonly,providedtheLightEmittingDiodes(LEDs)functioncorrectly,asshownbelow.
CheckthestatusoftheLEDsasfollows:
74
sect
ion Current Rail Indicator Device Current Rail Indicator Device28
28.2 Using a CRID to check for traction current
Afterundertakingtheself-test,placetheCRIDonthetractioncurrentrailstocheckfortractioncurrent.
Makesurethebaseandcontactsontheterminalunitsarecleananddry.Thisistomakesureofagoodelectricalcontact.
28.3 Before placing a CRID
MakesurethatthesurfaceofthetractioncurrentrailswheretheCRIDwillbeplacedisflate.g.notrampends.
Thecheckingoftractioncurrentrailsinstationlimitsmustbecarriedoutatthenormaldepartureendoftheplatform.ThePWT-EHmustaccessthetrackbyfollowingtheLineClear/LineSafeprocedures.
28.4 Placing a CRID
Standinthefourfoot,betweentheconductorrails,facingtheDOTwherepossibleandplacetheterminalunitwithouttheLEDclustersonthenegativerailfirst,lettinggoofthatunitbeforeplacingtheotherunitonthepositiverailandlettinggo.Makesurethatbothunitsaresittingfullyontopofeachtractioncurrentrailandleavethereforatleastfiveseconds.
IftheLEDsilluminateatanytime,itmeansthattractioncurrentison.Inthissituation,removetheCRID,leavethetrackandgotoaplaceofsafety.
RuleBook16GoingonthetrackinEngineeringHoursreferstoalistoflocationswheretrainscanapproachaplatformfromeitherdirection.
75
section28 Current Rail Indicator Device
28.5 Removing a CRID
WhenremovingaCRIDfromthetractioncurrentrails,makesuretheunitisremovedfromthepositiverailfirstandthenremovetheotherunitfromthenegativerail.
AfterremovingtheCRIDfromthetractioncurrentrails,repeattheselftestingprocess.
EveryCRIDmustundergoaself-testbeforeandaftercheckingfortractioncurrenttomakesureitisworkingcorrectly.IftheCRIDfailseithertest,staffmustnotgoonthetrackuntilaproperlyfunctioningreplacementhasbeenfound.
ACRIDmustnotbeused:
• ifitisoutofdate(mustbevalidfortheentireshift)
• ifitisdamaged
• ifitfailstheselftest
• onrustytractioncurrentrails
• ontractioncurrentrailramps
• onoutofgaugetractioncurrentrails.
Alwaysbealerttothedangerfrommovingtrains.
28.6 P-CRID
TheP-CRIDisapermanentlyfixedtractioncurrentstatusindicationdevicedesignedtoimprovethesafetyofstaffaccessingthetrackorthosewhoseworkmightaffectthetrack.OnlythosestaffappropriatelytrainedorbriefedcanuseaP-CRIDastheprimarymethodfordeterminingtractioncurrentstatus.
LUapprovedhighvisibilityclothingmustbewornatalltimeswhenonornearthetrack.
76
sect
ion Current Rail Indicator Device Current Rail Indicator Device28 Switching Off Traction Current
ThefailsafemechanismoftheP-CRIDunitisdesignedtoremovetheriskofstaffaccessingthetrackwhentractioncurrentiseitherswitchedonoritsstatuscannotbedetermined.
WhenithasbeenestablishedthattheP-CRIDisfunctioningcorrectly,thefollowingproceduresmustbefollowed.
IftheP-CRIDdisplayseitheran:
“ON”indicationor
“OFF”indication
Thismeansthattheunitisfunctioningcorrectlyandcanbesafelyusedtoestablishthetractioncurrentstatus.
IfaFAULTindicationisshownthenthisunitmustnotbeusedandmustbereportedtoTubeLinesControlCentre(TLCC).
Current Rail Indicator Device
77
section29 Switching Off Traction Current
29 Switching Off Traction Current
29.1 Reasons why traction current might not be switched off at the published time
TractionCurrentswitchofftimemaybeamendeddueto:
• latelasttrain
• operationalincident
• amendmenttoexistingswitchofftimes
• engineerstrainscheduledtorun.
29.2 What to do if the traction current is still on after the published off time
Ifthetractioncurrentisstillswitchedonafterthepublishedofftime,thereasonforthisshouldbestatedintheNEPA.Ifthereasonisunscheduled,thecontrollerwouldknowthereasonandcommunicatethistotheTACandthePWT-EHwillbeadvised.IfthePWT-EHisunsurewhytractioncurrentisstillswitchedonafterthepublishedswitchofftime,theyshouldcontacttheTACincidentdesk.
29.3 What to do if traction current goes off early
IfthePWT-EHbecomesawarethattractioncurrenthasbeenswitchedoffbeforethepassageofthelasttrain,orpublishedtimeforswitchingtractionoff,theymustnotgoonthetrack.TheTACincidentdeskmustbecontactedimmediately.
78
sect
ion Switching Off Traction Current Switching Off Traction Current29
29.4 What to do if crossing into another traction current section
Iftheroutetakentotheworksiterequiresaccesstoanothertractioncurrentsection,thePWT-EHmustcheckfortractioncurrentusingtheproceduresforcheckingusingaCRID/P-CRID.TheworkgroupmustnotenterthesectionuntilinstructedbythePWT-EH.ItistheresponsibilityofthePWT-EHtoensuretheworkgroupareinaplaceofsafetybeforethecheckisconducted.
Switching Off Traction Current
79
section30 Going on the track
30 Going on the track
30.1 Going to the worksite
IfitisnecessaryfortheworkgrouptowalktoaworksitethePWT-EHmustleadtheworkgroupandmakesureeveryoneunderstandsthattheymustnotwalkinfrontofthePWT-EH.ThePWT-EHmayhavetodeliveranotherbriefingattheworksite,particularlyifcircumstanceshavechangedfromtheplatformbriefing.
30.2 Safety at the worksite
ThePWT-EHmustmonitortheprogressoftheworkagainstthecallbacktime.Theymustmakesuretheworkgroupremainswithintheprotectedarea.
IfusingTrackTrolley(s)orIronmen,pointsmustbesecuredformovementoverthem.
Starting and finishing work in Traffic Hours Late Surrender Protection
80
sect
ion Starting and finishing work in Traffic Hours31
31 Starting and finishing work in Traffic HoursIntheLineCleararea,workcanonlybecarriedoutduringEngineeringHours,unlessspecialarrangementshavebeenputinplace.IntheLineSafeareaworkcanbecarriedoutoutsideEngineeringHours,providedcertainconditionsaremet:
• allstaffaresuitablycertificatedforTrafficHoursandhaveTrafficHoursprotection
• thetrackisnotmadeunsafefortrainstorun.
31.1 Working into Traffic Hours
IfworkistocontinueintoTrafficHoursinaLineSafearea,theworkgroupmustbecertificatedforTrafficHoursandthetrackmustbesafefortrainstorun,ThePWT-EHmust:
• taketheworkgrouptoanareaoffthetrack
• identifytheProtectionMasterTrafficHours(PMTH)
• ensurethePMTHsetsupthesafesystemofworkandsetsupprotection
• ensurethePMTHbriefstheworkgroup
• recordthatworkistocontinueunderTrafficHoursprotection,intheirLC/LSlogbook
• passaSiteSafemessagetotheTACinformingtheTACthatworkiscontinuingunderTrafficHourprotection.
IftheworkgrouparenotcertificatedforTrafficHoursandthetrackisnotsafefortrainstorun,thenworkcanonlycontinueunderLSP.
Starting and finishing work in Traffic Hours
81
section32 Late Surrender Protection
32 Late Surrender ProtectionLSPisrequiredwhen:
• thePWT-EHinformstheTACthatworkwillnotbefinishedbythecall-backtimeandthetrackisunsafefortrainstorun
• thePWT-EHfailstopassaSiteClearorSiteSafemessagetotheTACbythecall-backtime.
LSPisintroducedtomaintainprotectionuntiltheworkisfinishedorthemissingpersonprovidingprotectionisfound,oranysearcherhasconfirmedthatthemissingpersonprovidingprotectionisnoton-siteandthetrackissafefortrainstorun.
LSPrequiresappropriatemeasurestopreventtrainsfromenteringtractioncurrentsection(s)wheretractioncurrentremainsswitchedoff,becauseSiteClearorSiteSafemessageshavenotbeenreceived.
32.1 Leaving the work group
ThePWT-EHmustconsiderwhattrackcertificationtheworkgrouphaveandtoappointthedeputyidentifiedattheplanningstagetoremainwiththeworkgroupattheworksite,ortotaketheworkgrouptoaplaceofsafety.
Indecidingthis,itshouldalsobeconsideredwhether:
• itisinanopensectionwithreadilyavailableplacesofsafety
• itisasingleboretunnel
• thereisastationnearby
• thereisaneedtowalktoatelephonetocontacttheTAC,andhowlongthiswilltake
• anyotherfactors.
IfthePWT-EHneedstoleavetheworkgroup,torequestLSP,thesafetyoftheworkgroupmustbeconsideredatalltimes.
82
sect
ion Late Surrender Protection Late Surrender Protection32
32.2 Informing the TAC
IfthePWT-EHbecomesawarethatworkwilloverrun,theTACmustbecontactedassoonaspossible,andthefollowinginformationprovided:
• name
• location
• TACreferencenumber
• thatthejobwillnotfinishontimeandthatLSPisrequired
• thereasonforLSP
• anapproximatetimewhentheworkwillfinish(ifknown)
• telephonenumberfromwheretheyarecalling.
ThePWT-EHmustalsoinformtheTAC:
• whichtractioncurrentsectionsrequireLSP
• wherepossiblegiveaSiteClearorSiteSafemessageforanytractioncurrentsection(s)whicharenolongerrequired.
Ifgivingupanytractioncurrentsections,asafeexitfortheworkgroupmustbeavailable.
TheTACwillgiveinstructions:
• towaitforconfirmationthatLSPhasbeenimplemented
• tocontactthemagainafter10minutesifitisnotconfirmedthatLSPhasbeenimplemented.
IftheconfirmationmessagethatLSPhasbeenimplementedisnotreceivedafter10minutes,theworkgroupshouldberemovedtoaplaceofsafetytoawaitfurtherinstructionsfromtheTAC.LSPisnotimplementeduntilconfirmedbytheTAC.
83
section32 Late Surrender Protection
32.3 On completion of work
WhentheworkhasbeencompletedthePWT-EHmustmakesurethattheworkgroupleavesthetrackandthattheworksiteisclearofmaterials,equipmentandanythingelsethatcouldendangerthetrainservice.Theymustalsomakesurethatanythinglefton-siteissecured.
32.4 Journey from the worksite
ThePWT-EHMust:
• leadtheworkgroupoffthetrack
• maintainprotectionwhilstleavingtheworksite
• makesuretheworkgroupremainwithintheareabookedwiththeTAC
• onceoffthetrack,instructtheworkgroupnottoreturntothetrackbecauseprotectionisbeingremoved.
32.5 Booking off with the TAC
ThePWT-EHmustthencontacttheTACstating:
• theirname
• theTACreferencenumber
• theSiteClear/SiteSafemessagestatingthatallstaffandequipmentareclearofthetrackanditissafefortrainstorun.
TheTACwillconfirmtheTACreferencenumberandtheSiteClear/SiteSafemessageandgivethePWT-EHthetimetheycleared.ThePWT-EHmustrepeatbackthetimeclearedtotheTACandrecordthetimeintheLC/LSlogbook.
84
sect
ion Signing out at the station33
33 Signing out at the stationWhentheworkiscompleteandbeforesigningout,thePWT-EHmustchecktheworksiteandconfirmithasbeen:
• clearedofallpersonsintheworkgroup
• clearedoftools,plant,equipment,materialsoranyotherobstructions
• leftinaclean,tidyandsafecondition.
33.1 Signing out of a staffed station
ThePWT-EHmust:
• signoutinthevisitorsbook
• signoutfortheirstaff(ifapplicable)
• returnallvisitorpasses.
InadditionthePWT-EHmust:
• makesureallmembersoftheworkgrouparesignedoutonthePiCERform
• signthe‘PersoninCharge’declaration-exitsectionofthePiCERform
• takethecopyofthePiCERformfromthestationsupervisor.
ThePWT-EHmustnowleavethestationandmakesurethatallmembersoftheworkgroup(ifapplicable)haveleftthestation.
85
section33Signing out at the station
33.2 Signing out of an unstaffed station
Ifthestationisunstaffed,thePWT-EHmustgotothenominatedlocationtosignoutwiththestationsupervisorresponsibleandreturnthekeys.
Ifavisitor’spasshasnotbeenreturned,thestationsupervisormust:
• arrangeforasearchofthepremises
• telltheperson’smanagerorsupervisor
• askforthepasstobereturned
• submitawrittenreporttothelandlordmanager.
Possessions References
86
sect
ion Possessions34
34 PossessionsApossessionisadesignatedareaoftracktakenoutofservice,protectedagainstunauthorisedtrains,underthecontrolofaPossessionMaster(POM)andaProtectionSupportManager(POSM).
AnypossessiononLU’sinfrastructuremustbeadequatelyprotectedbyanapprovedmethodsuchas:
• maintainingsignalsatdanger
• securingfacingpointstodiverttrainsawayfromthearea
• securingavehicle
• LineClear/LineSafeprocedurestocreatebufferzones
• operationofaprotectionkeyswitch.
Someoralloftheprotectionarrangementscanbedelegatedtosuitablyqualifiedstaff.
IfthepossessionisduringEngineeringHoursthePOSMisresponsibleforsettingupasafesystemofworkforeachworksitewiththePWT-EH.ThePWT-EHisthenresponsiblefor:
• managingthesafesystemofworkfortheworksiteincollaborationwiththePOSM
• liaisingwiththePOSMonmovementofengineer’strainsandmechanisedvehiclesintoandoutoftheirworksites
• co-ordinatingwiththepersoncontrollingthetrainmovement,themovementofengineer’strainsandmechanisedvehicleswithintheworksite.
Possessions
87
section35 References
87
35 References• RuleBook1Communications
• RuleBook3Tractioncurrentandhighvoltagesupply
• RuleBook10StationAccess
• RuleBook14PossessionPlanningandManagement
• RuleBook15PossessionProtectionMethods
• RuleBook16GoingonthetrackinEngineeringHours
• RuleBook17ManagingaccesstothetrackinEngineeringHours
• RuleBook18Engineer’sTrains,VehiclesandTrolleys
• TheRegulatoryReform(FireSafety)Order2005
• TheFirePrecautions(Sub-SurfaceRailwaysStations)(England)Regulations2009