PROPOSE ASIAN DEVELOPMENT BANK - adb.org · 0019254-0000566 ty:2432489.23 1 environmental and...

32
0019254-0000566 TY:2432489.23 1 ENVIRONMENTAL AND SOCIAL ISSUES COMPLIANCE REPORT NONG SAENG POWER PLANT PROJECT PROPOSE ASIAN DEVELOPMENT BANK GULF JP NS COMPANY LIMITED JULY - DECEMBER 2012

Transcript of PROPOSE ASIAN DEVELOPMENT BANK - adb.org · 0019254-0000566 ty:2432489.23 1 environmental and...

0019254-0000566 TY:2432489.23 1

ENVIRONMENTAL AND SOCIAL ISSUES COMPLIANCE

REPORT

NONG SAENG POWER PLANT PROJECT

PROPOSE

ASIAN DEVELOPMENT BANK

GULF JP NS COMPANY LIMITED

JULY - DECEMBER 2012

0019254-0000566 TY:2432489.23 2

ENVIRONMENTAL AND SOCIAL ISSUES COMPLIANCE REPORT

1. Mitigative Measures and Monitoring Programme

AIR QUALITY (STACK EMISSION)

Monitoring station : (Please indicate the location of the monitoring stations as indicated in the EMP such as 4 HRSG stacks of Nong Saeng Power Plant)

Item

Unit

Measured Value (Min.)

Measured Value (Max.)

Country’s Standards

Referred International

Standards

Remarks (Frequency, Method, etc.)

SO2 2000 Please refer to the methodology and frequency as indicated in the EMP construction and operation stage.

NO2 - CO - O2 - TSP 50 Gas Flow Rate

-

Note1 : For NOx the Thai standards will be applied.

AIR QUALITY (AMBIENT AIR QUALITY)

(Please indicate the location of the 4 monitoring stations/community areas as indicated in the EMP such as: (1) Ban Tamsinthusopa, (2) Ban Nong Lua, (3) Ban Nong-Ngu-Loem and (4) Ban Khok Daeng) Monitoring Station No. 1: Ban Tamsinthusopa, Tambon Nong-Namsai, Pachee District of Pra Nakhon Si

Ayutthaya.

Item

Unit

Measured Value (Min.)

Measured Value (Max.)

Country’s Standards

Referred International

Standards

Remarks (Frequency, Method, etc.)

SO2 (average 1-hour) ppb 1 6 3001/ - The continuous ambient air

quality monitoring for 24 hours using AAQMS. Analytical Method - TSP and PM-10 : Bata Ray

or Taper Element Oscillating Microbalance

- NO2 : Chemiluminescence Method

- SO2 : UV Fluorescence Method/Pararosaniline

- Wind speed and wind direction : Cup Anemometer/Anodized Aluminum Vane/Ultrasonic Anemometer

- Ambient Temperature : Temperature Sensor

Frequency 24 hours continuously

NO2 (average 1-hour) ppb 2 18 1703/ -

TSP (average 24-hour) mg/m3 0.014 0.100 0.3302/ 230

PM10 (average 24-hour) mg/m3 0.013 0.095 0.1202/ 150

Wind speed and wind direction m/s 0.6 3.1 - -

Ambient Temperature °C 22.7 29.6 - -

Remark : 1. The monitoring of ambient air quality during July to December 2012. 2. Country’s Standard according to :

1/ Notification of the National Environment Board No.21 (B.E. 2544). 2/ Notification of the National Environment Board No.24 (B.E. 2547).

3/ Notification of the National Environment Board No.33 (B.E. 2552).

0019254-0000566 TY:2432489.23 3

AIR QUALITY (AMBIENT AIR QUALITY)

Monitoring Station No. 2: Ban Nong-Lua, Tambon Nong-Kob, Nong-Saeng District of Saraburi.

Item

Unit

Measured Value (Min.)

Measured Value (Max.)

Country’s Standards

Referred International

Standards

Remarks (Frequency, Method, etc.)

SO2 (average 1-hour) ppb 1 4 3001/ - The continuous ambient air

quality monitoring for 24 hours using AAQMS. Analytical Method - TSP and PM-10 : Bata Ray

or Taper Element Oscillating Microbalance

- NO2 : Chemiluminescence Method

- SO2 : UV Fluorescence Method/Pararosaniline

- Wind speed and wind direction : Cup Anemometer/Anodized Aluminum Vane/Ultrasonic Anemometer

- Ambient Temperature : Temperature Sensor

Frequency 24 hours continuously

NO2 (average 1-hour) ppb 3 17 1703/ -

TSP (average 24-hour) mg/m3 0.013 0.113 0.3302/ 230

PM10 (average 24-hour) mg/m3 0.013 0.101 0.1202/ 150

Wind speed and wind direction m/s 0.4 3.2 - -

Ambient Temperature °C 23.8 29.4 - -

Remark : 1. The monitoring of ambient air quality during July to December 2012. 2. Country’s Standard according to :

1/ Notification of the National Environment Board No.21 (B.E. 2544). 2/ Notification of the National Environment Board No.24 (B.E. 2547).

3/ Notification of the National Environment Board No.33 (B.E. 2552).

0019254-0000566 TY:2432489.23 4

AIR QUALITY (AMBIENT AIR QUALITY)

Monitoring Station No. 3: Ban Nong-Ngu-Loem, Tambon Khok Muang, Pachee District of Phra Nakhon Si Ayutthaya.

Item

Unit

Measured Value (Min.)

Measured Value (Max.)

Country’s Standards

Referred International

Standards

Remarks (Frequency, Method, etc.)

SO2 (average 1-hour) ppb 1 7 3001/ - The continuous ambient air

quality monitoring for 24 hours using AAQMS. Analytical Method - TSP and PM-10 : Bata Ray

or Taper Element Oscillating Microbalance

- NO2 : Chemiluminescence Method

- SO2 : UV Fluorescence Method/Pararosaniline

- Wind speed and wind direction : Cup Anemometer/Anodized Aluminum Vane/Ultrasonic Anemometer

- Ambient Temperature : Temperature Sensor

Frequency 24 hours continuously

NO2 (average 1-hour) ppb 4 24 1703/ -

TSP (average 24-hour) mg/m3 0.022 0.118 0.3302/ 230

PM10 (average 24-hour) mg/m3 0.014 0.103 0.1202/ 150

Wind speed and wind direction m/s 0.4 2.8 - -

Ambient Temperature °C 24.3 29.3 - -

Remark : 1. The monitoring of ambient air quality during July to December 2012. 2. Country’s Standard according to :

1/ Notification of the National Environment Board No.21 (B.E. 2544). 2/ Notification of the National Environment Board No.24 (B.E. 2547).

3/ Notification of the National Environment Board No.33 (B.E. 2552).

0019254-0000566 TY:2432489.23 5

AIR QUALITY (AMBIENT AIR QUALITY)

Monitoring Station No. 4: Ban Khok Daeng, Tambon Khok-Toom, Nong-Saeng District of Saraburi. Item

Unit

Measured Value (Min.)

Measured Value (Max.)

Country’s Standards

Referred International

Standards

Remarks (Frequency, Method, etc.)

SO2 (average 1-hour) ppb 1 4 3001/ - The continuous ambient air

quality monitoring for 24 hours using AAQMS. Analytical Method - TSP and PM-10 : Bata Ray

or Taper Element Oscillating Microbalance

- NO2 : Chemiluminescence Method

- SO2 : UV Fluorescence Method/Pararosaniline

- Wind speed and wind direction : Cup Anemometer/Anodized Aluminum Vane/Ultrasonic Anemometer

- Ambient Temperature : Temperature Sensor

Frequency 24 hours continuously

NO2 (average 1-hour) ppb 5 36 1703/ -

TSP (average 24-hour) mg/m3 0.015 0.108 0.3302/ 230

PM10 (average 24-hour) mg/m3 0.015 0.108 0.1202/ 150

Wind speed and wind direction m/s 0.8 3.1 - -

Ambient Temperature °C 23.7 29.1 - -

Remark : 1. The monitoring of ambient air quality during July to December 2012. 2. Country’s Standard according to :

1/ Notification of the National Environment Board No.21 (B.E. 2544). 2/ Notification of the National Environment Board No.24 (B.E. 2547).

3/ Notification of the National Environment Board No.33 (B.E. 2552).

0019254-0000566 TY:2432489.23 6

WATER QUALITY (EFFLUENT QUALITY)

During Construction Stage

Monitoring Station: Holding Pond of Nong Saeng Power Plant

Item Measured Value (Min.)

Measured Value (Max.)

Country’s Standards

Referred International

Standards

Remarks (Frequency, Method, etc.)

Temperature - - - ≤ +3˚C Analytical Method - Temperature : Certified

Thermometer - pH : Electrometric Method - Total Dissolved Solids :

Dried at 103-105 °C, 180 °C

- Suspended Solids : Dried at 103-105 °C

- BOD5 : 5-Day BOD Test/Azide Modification Method

- COD : Open Reflux, Titrimetric Method

- Oil & Grease : Soxhlet Extraction Method/Partition Gravimetric Method

- TKN : Kjedahl Method - Heavy metals : Atomic

Absorption Spectrometric Method

- Fecal Coliform Bacteria : Multiple Tube Fermentation Technique

Frequency Once a month

BOD5 - - - -

COD - - - -

SS - - - 50

TDS - - - -

Oil & Grease - - - 10

pH - - - 6-9

TKN - - - -

Free Chlorine - - - -

Fecal Coliform Bacteria - - - -

Remark : Presently, the project does not discharge wastewater to the outside of the project area, therefore, the effluent quality in the holding pond is not measured. However, if the wastewater is discharged to the outside, the monitoring of effluent quality will be conducted and reported in the report on “Action on Environmental Measures” every 6 months.

0019254-0000566 TY:2432489.23 7

WATER QUALITY (EFFLUENT QUALITY)

During Operation Stage

Monitoring Station: Holding Pond of Nong Saeng Power Plant before Discharge

Note: Please include the online monitoring results in the report, kindly refer to the EMP. Item Measured

Value (Min.)

Measured Value (Max.)

Country’s Standards

Referred International

Standards

Remarks (Frequency, Method, etc.)

Temperature ≤ +3˚C Please refer to the methodology and frequency as indicated in the EMP.

BOD5 - COD - SS 50 TDS - Oil & Grease 10 pH 6-9 TKN - Free Chlorine - Heavy Metals - Fe √ - Zn √ 1.0 Cu √ 0.5 Pb √ - Ni √ - Mn √ - Cr+6 √ -

0019254-0000566 TY:2432489.23 8

SURFACE WATER QUALITY

During Construction Stage

Monitoring Stations: Klong Huaiba (Klong Nong-Ngu-Loem) area covering three monitoring stations: (i) 500 meters upstream of Nong Saeng Power Plant Site, (ii) Discharge point of the project, (iii) 500 meters downstream of the project’s discharge point.

Item Unit

Measured

Value (Min.)

Measured Value (Max.)

Country’s Standards

Referred International

Standards

Remarks (Frequency, Method,

etc.) Class 3 Class 4

BOD5 mg/l 1.0 2.0 2.0 4.0 - Analytical Method - pH : Electrometric Method - Total Dissolved Solids :

Dried at 103-105 °C, 180 °C

- Suspended Solids : Dried at 103-105 °C

- BOD5 : 5-Day BOD Test/Azide Modification Method

- COD : Open Reflux, Titrimetric Method

- Fecal Coliform Bacteria : Multiple Tube Fermentation Technique

Frequency Every 3 months

COD mg/l <40.0 50.0 - - -

SS mg/l 13 46 - - -

TDS mg/l 160 558 - - -

pH - 7.4 8.0 5.0-9.0 5.0-9.0 -

Fecal Coliform MPN/100 ml 220 7,900 4,000 - -

Remark : 1. The monitoring of surface water quality in September and December 2012. 2. *Country’s Standard according to Announcement of National Environment Board No.8 (B.E.2537)

0019254-0000566 TY:2432489.23 9

SURFACE WATER QUALITY

During Operation Stage

Monitoring Stations: Klong Huaiba (Klong Nong-Ngu-Loem) area covering three monitoring stations: (i) 500 meters upstream of Nong Saeng Power Plant Site, (ii) Discharge point of the project, (iii) 500 meters downstream of the project’s discharge point.

Note: Please include the online monitoring results in the report, kindly refer to the EMP.

Item Measured Value (Min.)

Measured Value (Max.)

Country’s Standards

Referred International

Standards

Remarks (Frequency, Method,

etc.)

Temperature - Please refer to the methodology and frequency as indicated in the EMP.

BOD5 - COD - SS - TDS - pH - Free Chlorine - Heavy Metals - Fe Zn Cr+6 Pb Ni Mn Cu

0019254-0000566 TY:2432489.23 10

NOISE

During Construction Stage

Measurement Station 1: Ban Tamsinthusopa, Tambon Nong-Namsai, Pachee District of Pra Nakhon Si Ayutthaya

Item Leq (24hr) Ldn L90 Country’s

Standard Referred

International Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

55.2-57.7 60.1-70.5 47.9-59.2 70 55 Measurement Method - Sound Pressure Level

Meter Noise level (Night-time)

52.9-65.1 60.1-70.5 47.9-59.2 70 45 Frequency - Twice a year for 5

consecutive days each (covering weekends and working days)

Remark : 1/ The measurement of sound pressure levels during September 21-26, 2012 2/The sound pressure level standard of 70 dB(A) notified by the Notification of the National Environment

Board, No.15, B.E.2540 (1997) Standard of Ldn and L90 are not specified yet.

3/No nearby communities were affected by the loud noise level during construction.

Measurement Station 2: Ban Nong-Tangbun, Tambon Nong-Kob, Nong-Saeng District of Saraburi

Item Leq (24hr) Ldn L90 Country’s

Standard Referred

International Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

58.1-60.7 61.6-71.2 48.0-59.5 70 55 Measurement Method - Sound Pressure Level

Meter Noise level (Night-time)

53.3-57.2 61.6-71.2 48.0-59.5 70 45 Frequency - Twice a year for 5

consecutive days each (covering weekends and working days)

Remark : 1/ The measurement of sound pressure levels during September 21-26, 2012 2/The sound pressure level standard of 70 dB(A) notified by the Notification of the National Environment

Board, No.15, B.E.2540 (1997) Standard of Ldn and L90 are not specified yet.

3/No nearby communities were affected by the loud noise level during construction.

0019254-0000566 TY:2432489.23 11

Measurement Station 3: Ban Nong-Ngu-Loem, Tambon Khok Muang, Pachee District of Phra Nakhon Si Ayutthaya

Item Leq (24hr) Ldn L90 Country’s

Standard Referred

International Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

57.4-59.6 64.4-72.2 52.9-60.7 70 55 Measurement Method - Sound Pressure Level

Meter Noise level (Night-time)

58.4-66.8 64.4-72.2 52.9-60.7 70 45 Frequency - Twice a year for 5

consecutive days each (covering weekends and working days)

Remark : 1/ The measurement of sound pressure levels during September 21-26, 2012 2/The sound pressure level standard of 70 dB(A) notified by the Notification of the National Environment

Board, No.15, B.E.2540 (1997) Standard of Ldn and L90 are not specified yet.

3/No nearby communities were affected by the loud noise level during construction.

Measurement Station 4: Ban Khok Daeng, Tambon Khok-Toom, Nong-Saeng District of Saraburi

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

57.1-60.1 62.9-67.3 48.1-55.5 70 55 Measurement Method - Sound Pressure Level

Meter Noise level (Night-time)

55.0-57.3 62.9-67.3 48.1-55.5 70 45 Frequency - Twice a year for 5

consecutive days each (covering weekends and working days)

Remark : 1/ The measurement of sound pressure levels during September 21-26, 2012 2/The sound pressure level standard of 70 dB(A) notified by the Notification of the National Environment

Board, No.15, B.E.2540 (1997) Standard of Ldn and L90 are not specified yet.

3/No nearby communities were affected by the loud noise level during construction.

0019254-0000566 TY:2432489.23 12

Measurement Station 5: The fence of the project or at the nearest house to the project

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

54.3-56.7 62.1-63.7 53.2-54.4 70 55 Measurement Method - Sound Pressure Level

Meter Noise level (Night-time)

55.8-57.3 62.1-63.7 53.2-54.4 70 45 Frequency - Twice a year for 5

consecutive days each (covering weekends and working days)

Remark : 1/ The measurement of sound pressure levels during September 21-26, 2012 2/The sound pressure level standard of 70 dB(A) notified by the Notification of the National Environment

Board, No.15, B.E.2540 (1997) Standard of Ldn and L90 are not specified yet.

3/No nearby communities were affected by the loud noise level during construction.

Measurement Station 6: A chicken farm within 1 km radius from the project site

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

54.6-57.2 58.5-60.4 47.3-50.7 70 55 Measurement Method - Sound Pressure Level

Meter Noise level (Night-time)

50.0-51.2 58.5-60.4 47.3-50.7 70 45 Frequency - Twice a year for 5

consecutive days each (covering weekends and working days)

Remark : 1/ The measurement of sound pressure levels during September 21-26, 2012 2/The sound pressure level standard of 70 dB(A) notified by the Notification of the National Environment

Board, No.15, B.E.2540 (1997) Standard of Ldn and L90 are not specified yet.

3/No nearby communities were affected by the loud noise level during construction.

0019254-0000566 TY:2432489.23 13

Measurement Station 7: A chicken farm within 1 to 2 km radius from the project site

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

63.0-66.0 60.5-66.6 47.1-57.8 70 55 Measurement Method - Sound Pressure Level

Meter Noise level (Night-time)

52.6-54.7 60.5-66.6 47.1-57.8 70 45 Frequency - Twice a year for 5

consecutive days each (covering weekends and working days)

Remark : 1/ The measurement of sound pressure levels during September 21-26, 2012 2/The sound pressure level standard of 70 dB(A) notified by the Notification of the National Environment

Board, No.15, B.E.2540 (1997) Standard of Ldn and L90 are not specified yet.

3/No nearby communities were affected by the loud noise level during construction.

NOISE

During Operation Stage

Measurement Station 1: Ban Tamsinthusopa

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

55 Please refer to the methodology and frequency as indicated in the EMP.

Noise level (Night-time)

45

Measurement Station 2: Ban Nong-Tangbun

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

55 Please refer to the methodology and frequency as indicated in the EMP.

Noise level (Night-time)

45

0019254-0000566 TY:2432489.23 14

Measurement Station 3: Ban Nong-Ngu-Loem

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

55 Please refer to the methodology and frequency as indicated in the EMP.

Noise level (Night-time)

45

Measurement Station 4: Ban Khok Daeng

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

55 Please refer to the methodology and frequency as indicated in the EMP.

Noise level (Night-time)

45

Measurement Station 5: The fence of the project or at the nearest house to the project

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

55 Please refer to the methodology and frequency as indicated in the EMP.

Noise level (Night-time)

45

Note2: Status of sound barriers (trees, greenbelt and physical wall) and double windows instalment should be followed up every month to ensure best efforts have been exercise together with regular monitoring.

Measurement Station 6: A chicken farm within 1 km radius from the project site

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

55 Please refer to the methodology and frequency as indicated in the EMP.

Noise level (Night-time)

45

0019254-0000566 TY:2432489.23 15

Measurement Station 7: A chicken farm within 1 to 2 km radius from the project site.

Item Leq (24hr) Ldn L90 Country’s Standard

Referred International

Standard

Remarks (Frequency, Method,

etc.)Noise level (Daytime)

55 Please refer to the methodology and frequency as indicated in the EMP.

Noise level (Night-time)

45

0019254-0000566 TY:2432489.23 16

FORESTRY AND WILDLIFE ECOLOGY

During Construction Stage

Wildlife

Parameter: Survey of wildlife around the project area including species, status and abundance.

Location: Within a radius of 5 km around the project site.

Duration: Six months from the beginning of the construction. The measure specified the survey of wildlife be conducted around the project area for

species, status and abundance in the area within 5 km radius of the project site for six months after the

project construction.

From the results of environmental impact surveillance on wildlife resources in the area

during this early part of the construction phase of Nong Saeng Power Plant Project, it was found that the

conditions of wildlife habitats and ecology in the area were changed very slightly and no impact was

imposed on the local wildlife resources and the associated diversity, abundance and status of wildlife in the

project area. The observed resultant change was found to be naturally seasonal-based, which was considered

as normal. Therefore, the results implied that the mitigative measures for wildlife resources were effectively

implemented as specified in the EIA report of Nong Saeng Power Plant Project. Details are presented in the

Environmental Measures Report, No.2/2011.

During Operation Stage

Parameter: Survey of wildlife around the project area for the study of their diversity, species, abundance

and all survival in the project area.

Location: Within a radius of 5 km around the project site.

Duration: At the beginning of the project operation and every 3 years thereafter with a survey in each

of the rainy and winter seasons of the year and for a total time period of 10 years. If the

findings do not indicate any tendency of the project-induced impact, the survey will be

determined.

0019254-0000566 TY:2432489.23 17

AQUATIC ECOLOGY AND FISHERY

During Construction Stage

Aquatic Ecology

Parameter: Phytoplankton, zooplankton, benthos

Location: Klong Huaiba (Klong Nong-Ngu-Loem); (i) 500 meters upstream of Nong Saeng Power Plant Project Site; (ii) Discharge point of the project and (iii) 500 meters downstream of the project’s discharge point.

Duration: Every three months throughout the construction period.

Sampling Method:

- Phytoplankton : Vertical plankton tow with plankton net mesh size 20-60 µm.

- Zooplankton : Vertical plankton tow with plankton net mesh size 100-200 µm for zooplankton and mesh size 300 µm for fish eggs and larvae.

- Benthos : Ekman Grab used to collect samples from the bottom layer of sediment.

The programme of aquatic ecology monitoring specified that the types and densities of

phytoplankton, zooplankton and benthos be monitored every 3 months during construction phase in the area

of Klong Huaiba (Klong Nong-Ngu-Loem) at 3 locations, i.e., 500 meters upstream of Nong Saeng Power

Plant Project Site, Discharge point of the project, and 500 meters downstream of the project’s discharge

point.

First Monitoring Results (September 3, 2012)

(1) Klong Huaiba at 500 meters upstream of Nong-Saeng Power Plant Project Site

- Phytoplankton : 11 species in 3 Divisions of phytoplankton were found, i.e., 1 species in

Cyanophyta, 7 species in Chlorophyta and 3 species in Chromophyta with the total density

of 40,320 cell/l. The predominant species was found to be Eudorina sp. and the diversity

index of phytoplankton was 0.9746

- Zooplankton : 4 species of Phylum Rotifera and 1 species of Phylum Arthropoda were

found. The total density was found to be 3,780 ind./litre. The predominant species was

found to be Polyarthra sp.. and the diversity index of zooplankton was 0.8378

- Benthos : Only one phylum was found to be Mollusca with 1 species, i.e., Pilsbryoconcha sp..

The total density was found to be 45 ind./m2. The diversity index could not be determined

since only one species was found.

(2) Klong Huaiba (Klong Nong-Ngu-Loem) at Discharge point of the project

- Phytoplankton : 8 species in 3 Divisions of phytoplankton were found, i.e., 1 species in

Cyanophyta, 4 species in Chlorophyta and 3 species in Chromophyta with the total density

0019254-0000566 TY:2432489.23 18

of 3,655 cell/l. The predominant species was found to be Strombomonas sp. and the

diversity index of phytoplankton was 1.9562.

- Zooplankton : Only 1 species in Phylum Arthropoda was found, i.e., Copepod naupil. The

density was found to be 430 ind./litre. The diversity index could not be determined since

only one species was found.

- Benthos : Three phyla of benthos were found, i.e., 1 species (Lumbriculidae) in Phylum

Annelida, 1 species (Chironomus sp. ) in Phylum Arthropoda and 1 species (Indonaia sp.) in

Phylum Mollusca with the density of 89, 134 and 45 ind./m2 respectively. The diversity

index of benthos was 1.0123.

(3) Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters downstream of the project’s discharge

point

- Phytoplankton : 12 species in 3 Divisions of phytoplankton were found, i.e., 1 species in

Cyanophyta, 7 species in Chlorophyta and 4 species in Chromophyta with the total density

of 16,400 cell/l. The predominant species was found to be Dictyosphaerium sp. and the

diversity index of phytoplankton was 1.8449.

- Zooplankton : Only 1 species in Phylum Protozoa was found, i.e., Coleps sp. with the

density of 200 ind./litre. The diversity index could not be determined since only one species

was found.

- Benthos : No benthos was found in this area.

Second Monitoring Results (December 20, 2012)

(1) Klong Huaiba at 500 meters upstream of Nong-Saeng Power Plant Project Site

- Phytoplankton : 16 species in 3 Divisions of phytoplankton were found, i.e., 3 species in

Cyanophyta, 10 species in Chlorophyta and 3 species in Chromophyta with the total

density of 56,945 cell/l. The predominant species was found to be Aulacoseira sp. and the

diversity index of phytoplankton was 2.0469.

- Zooplankton : Only 1 species in Phylum Rotifera was found, i.e., Polyarthra sp. with the

total density of 470 ind./litre. The diversity index was not determined since only one

species was found.

- Benthos : Two species in two phyla were found, i.e., Naididae in Annelida and Chironmus sp.

in Arthropoda. The density was found to be 45 and 445 ind./m2 respectively, and the diversity

index of benthos was 0.3068

(2) Klong Huaiba (Klong Nong-Ngu-Loem) at Discharge point of the project

- Phytoplankton : 17 species in 3 Divisions of phytoplankton were found, i.e., 2 species in

Cyanophyta, 10 species in Chlorophyta and 5 species in Chromophyta with the total

density of 136,515 cell/l. The predominant species was found to be Pandorina sp. and the

diversity index of phytoplankton was 1.1754.

0019254-0000566 TY:2432489.23 19

- Zooplankton : Only 1 species in Phylum Protozoa was found, i.e., Euglepha sp. with the

total density of 285 ind./litre. The diversity index was not determined since only one

species was found.

- Benthos : Only one phylum was found to be Arthropoda with 1 species, i.e., Chironomus sp.

with the total density of 89 ind./m2. The diversity index was not determined since only one

species was found.

(3) Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters downstream of the project’s discharge

point

- Phytoplankton : 19 species in 3 Divisions of phytoplankton were found, i.e., 2 species in

Cyanophyta, 12 species in Chlorophyta and 5 species in Chromophyta with the total

density of 52,877 cell/l. The predominant species was found to be Pandorina sp. and the

diversity index of phytoplankton was 2.1357.

- Zooplankton : No zooplankton was found in this area.

- Benthos : 4 species in 3 phyla were found, i.e., 1 species (Lumbriculidae) in Annelida,

1species (Chironomus sp.) in Arthropoda, and 2 species (Indonaia sp. and Scabies sp.) in

Mollusca. The total density was 268 ind./m2 and the diversity index of benthos was 1.3314.

Summary of Monitoring Results of Aquatic Ecology

- Phytoplankton : The monitoring results revealed that Divisions mostly found in all 3

monitoring areas were Division Cyanophyta (blue green algae), Division Chlorophyta

(green algae) and Division Chromophyta (diatom). These Divisions are generally found in

surface water resources or freshwater. The diversity index indicating the variety of lives

was found to be close to or more than 1 implied that the environmental conditions and

surface water quality were not imposed by any impacts. The results of diversity index were

mostly found to be more than 1 in all 3 monitoring areas, so the surface water quality was

considered to be good.

- Zooplankton : The monitoring results revealed that the phyla found in the monitoring areas

were Phylum Rotifera, Phylum Arthropoda and Phylum Protozoa. Only one species were

mostly found in the monitoring areas, thus the diversity index was not determined.

No zooplankton was found at Station No.3 on December 20, 2012.

- Benthos : The monitoring results revealed that Phylum Annelida, Phylum Arthropoda

(larvae), Phylum Mollusca (quahog) were mostly found in the sampling areas. Comparing

the monitoring results on September 3, 2012 and December 20, 2012, the density and

diversity index at Station No.1 and No.3 were found to be increased indicating better water

quality. However, the monitoring results at Station No.2 were decreased.

0019254-0000566 TY:2432489.23 20

Species and Density of Phytoplankton on September 3, 2012

Station Division Genus Density (Cell/l)

Total Density (Cell/l)

Diversity Index

Station No.1 Cyanophyta Oscillatoria sp. 630 40,320 0.9746

Chlorophyta Chlamydomonas sp. 210

Eudorina sp. 30,240

Euglena sp. 420 Lepocinclis sp. 420 Phacus sp. 420 Strombomonas sp. 210 Trachelomonas sp. 420

Chromophyta Aulacoseira sp. Cyclotella sp. Peridinium sp.

2,520 210

4,620

Station No.2 Cyanophyta Lyngbya sp. 645 3,655 1.9562

Chlorophyta Euglena sp. 215 Lepocinclis sp. 215 Phacus sp.

Strombomonas sp. 430 860

Chromophyta Aulacoseira sp. Gyrosigma sp. Surirella sp.

645 215 430

Station No.3 Cyanophyta Oscillatoria sp. 600 16,400 1.8449

Chlorophyta Crucigenia sp. Dictyosphaerium sp. Euglena sp. Geminella sp. Phacus sp. Strombomonas sp. Trachelomonas sp.

4,800 5,000 200 200 200

1,400 1,800

Chromophyta Aulacoseira sp. Eunotia sp. Navicula sp. Surirella sp.

1,600 200 200 200

Remark : Station No.1 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters upstream of Nong Saeng

Power Plant Project

Station No.2 : Klong Huaiba (Klong Nong-Ngu-Loem) at Discharge point of the project

Station No.3 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters downstream of the project’s

discharge point

0019254-0000566 TY:2432489.23 21

Species and Density of Phytoplankton on December 20, 2012

Station Division Genus Density (Cell/l)

Total Density (Cell/l)

Diversity Index

Station No.1 Cyanophyta Anabaena sp. Microcystis sp. Oscillatoria sp.

470 5,875 1,880

56,945 2.0469

Chlorophyta Actinastrum sp. Closterium sp.

2,115 470

Eudorina sp. 15,040 Euglena sp. 1,645 Geminella sp. 235 Lepocinclis sp. 705 Pandorina sp. 1,880 Pediastrum sp.

Scenedesmus sp. Strombomonas sp.

940 2,820 1,175

Chromophyta Aulacoseira sp. Navicula sp. Peridinium sp.

17,625 75

3,995

Station No.2 Cyanophyta Anabaena sp. Oscillatoria sp.

285 1,425

136,515 1.1754

Chlorophyta Eudorina sp. 31,920 Euglena sp. 570 Gloeocystis sp.

Lepocinclis sp. Pandorina sp. Pediastrum sp. Phacus sp. Scenedesmus sp. Strombomonas sp. Trachelomonas sp.

1,140 285

86,925 285 570

1,140 570

4,560

Chromophyta Aulacoseira sp. Gyrosigma sp. Navicula sp. Peridinium sp. Synedra sp.

1,425 285 285

4,560 285

Remark : Station No.1 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters upstream of Nong Saeng Power Plant Project

Station No.2 : Klong Huaiba (Klong Nong-Ngu-Loem) at Discharge point of the project Station No.3 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters downstream of the project’s

discharge point

0019254-0000566 TY:2432489.23 22

Species and Density of Phytoplankton on December 20, 2012

Station Division Genus Density (Cell/l)

Total Density (Cell/l)

Diversity Index

Station No.3 Cyanophyta Anabaena sp. Oscillatoria sp.

253 1,012

52,877 2.1357

Chlorophyta Chodatella sp. Coelastrum sp.

253 3,036

Closterium sp. Crucigenia sp. Eudorina sp.

253 4,048

12,144

Euglena sp. 253 Lepocinclis sp. 253 Pandorina sp. 16,192 Pediastrum sp.

Phacus sp. 759 759

Strombomonas sp. Trachelomonas sp.

1,012 5,060

Chromophyta Aulacoseira sp. Navicula sp. Peridinium sp. Surirella sp. Synedra sp.

2,530 506

3,795 506 253

Remark : Station No.1 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters upstream of Nong Saeng Power Plant Project

Station No.2 : Klong Huaiba (Klong Nong-Ngu-Loem) at Discharge point of the project Station No.3 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters downstream of the project’s

discharge point

0019254-0000566 TY:2432489.23 23

Species and Density of Zooplankton on September 3, 2012

Station Phylum Genus Density (ind./l)

Total Density (ind./l)

Diversity Index

Station No.1 Rotifera Anuraeopsis sp.

Filinia sp.

Polyarthra sp.

Trichocerca sp.

210

210

2,940

210

3,780 0.8378

Arthropoda Copepod nauplii 210

Station No.2 Arthropoda Copepod nauplii 430 430 0

Station No.3 Protozoa Coleps sp. 200 200 0

Remark : Station No.1 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters upstream of Nong Saeng Power

Plant Project

Station No.2 : Klong Huaiba (Klong Nong-Ngu-Loem) at Discharge point of the project

Station No.3 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters downstream of the project’s

discharge point

Species and Density of Zooplankton on December 20, 2012

Station Phylum Genus Density (ind./l)

Total Density (ind./l)

Diversity Index

Station No.1 Rotifera Polyarthra sp. 470 470 0

Station No.2 Protozoa Euglepha sp. 285 285 0

Station No.3 - Not found - - -

Remark : Station No.1 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters upstream of Nong Saeng Power

Plant Project

Station No.2 : Klong Huaiba (Klong Nong-Ngu-Loem) at Discharge point of the project

Station No.3 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters downstream of the project’s

discharge point

0019254-0000566 TY:2432489.23 24

Species and Density of Benthos on September 3, 2012

Station Phylum Taxa Density (ind./m2)

Total Density (ind./m2)

Diversity Index

Station No.1 Molussca Pilsbryoconcha sp. 45 45 0

Station No.2 Annelida Lumbriculidae 89 268 1.0123

Arthropoda Chironomus sp. 134

Molussca Indonaia sp. 45

Station No.3 - Not found. - - -

Remark : Station No.1 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters upstream of Nong Saeng Power

Plant Project

Station No.2 : Klong Huaiba (Klong Nong-Ngu-Loem) at Discharge point of the project

Station No.3 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters downstream of the project’s

discharge point

Species and Density of Benthos on December 20, 2012

Station Phylum Taxa Density (ind./m2)

Total Density (ind./m2)

Diversity Index

Station No.1 Annelida Naididae 45 490 0.3068

Arthropoda Chironomus sp. 445

Station No.2 Arthropoda Chironomus sp. 89 89 0

Station No.3 Annelida Lumbriculidae 89 268 1.3314

Arthropoda Chironomus sp. 45

Mollusca Indonaia sp. 89

Scabies sp. 45

Remark : Station No.1 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters upstream of Nong Saeng Power

Plant Project

Station No.2 : Klong Huaiba (Klong Nong-Ngu-Loem) at Discharge point of the project

Station No.3 : Klong Huaiba (Klong Nong-Ngu-Loem) at 500 meters downstream of the project’s

discharge point

0019254-0000566 TY:2432489.23 25

During Operation Stage

Parameter: Phytoplankton, zooplankton, benthos

Location: Pa-Sak River: (i) 200 m upstream of the water pumping point of Nong-Saeng Power Plant

Project, (ii) Water pumping point of the project and (iii) 200 meters downstream of the

project’s water pumping station.

Klong Huaiba (Klong Nong-Ngu-Loem); (i) 500 meters upstream of Nong Saeng Power

Plant Project; (ii) Discharge point of the project and (iii) 500 meters downstream of the

project’s discharge point.

Duration: Every 6 months.

0019254-0000566 TY:2432489.23 26

SOLID WASTES MANAGEMENT

During Construction Stage

Parameter: Types/quantities of solid wastes and the disposal method for each type of solid wastes.

Location: Project area.

Duration: Once a month during the construction period.

The measure specified that the types and quantities of solid wastes generated including solid wastes

disposal were recorded once a month during the construction phase.

The quantities of solid wastes (garbage only) transported outside the project by an environmental

officer of SI-NO Thai Engineering and Construction Public Co., Ltd. during July to December 2012 were

recorded and summarized below.

Month Quantity of Solid Wastes / Kilograms

July 21,791

August 26,901

September 36,211

October 45,072

November 25,123

December 26,074

During Operation Stage

Parameter: Types/quantities of solid wastes and the disposal method for each type of solid wastes.

Location: Project area.

Duration: Once a month during the operation period.

0019254-0000566 TY:2432489.23 27

OCCUPATIONAL HEALTH AND SAFETY

Operation Phase

Parameter Location/Person Duration Remarks Noise Dose Employees working in the

process of the power plant 4 times a year Please refer to the

measurement method as indicated in the EMP.

Noise Contour The electricity generating area of loud noise level

Every 5years

Heat-Wet Bulb Globe Temperature (WBGT)

heat sources , such as: (i) condenser exhaust unit, (ii) steam pipeline area, (iii) generator area, and (iv) combustion turbine area.

4 times a year.

Light Intensity Electrical and Control Building Administration Building Workshop

4 times a year.

Health examination for New Employees of Nong-Saeng Power Plant: (i) General Physical Examination, (ii) Lung X-rays and (iii) Basic blood test.

Before working within the specified period by the law.

Health examination for Employees of Nong-Saeng Power Plant: (i) lung x-rays, (ii) vision test, (iii) general physical examination and blood test. : complete blood cell, blood group and Hepatitis B immunity.

Once per year

Special examination: (i) hearing test for mechanical workers, (ii) lung function test for maintenance workers and (iii) vision test for every employee.

Once per year

Fire Prevention and Fire Fighting System

• The safety, occupational health and working environment section will have a meeting in order to summarize the problems, recommendations, and revise the safety manual and emergency plan by recording the details, statistics and comments from the employees and local fire fighting authority on the safety and occupational health of the project.

• Inspection of fire protection equipments, at least once a week.

• Evaluation of the emergency response drill in order to revise the emergency plan and practice skills.

0019254-0000566 TY:2432489.23 28

COMMUNITY HEALTH AND SAFETY

Construction Phase

Number of health safety and environment training and other training/orientation conducted for the workers/laborers, and general description of awareness.

- The project provided the following training and related document:

1. Occupational Health/Safety and Environment Induction (Nong Saeng Power Plant Project) was provided for new workers/employees before working in construction area.

2. Specific Training

The courses for new workers, scaffolding, lifting, working in confine space areas and working at high altitude areas.

3. Safety handbook for construction.

Various accidents/incidents involving workers/labourer (including clinic/hospital reports, nature of accidents/incidents), action undertaken to ensure accidents/incidents to be avoided.

- No accident/incident.

Various project related accidents/incidents affecting local communities (which may arise from traffic, dust, noise, vibration, or interaction with laborers), action undertaken to ensure accidents/incidents to be avoided.

- No accident/incident/injury. At present, the project has assigned personnel with responsibility to conduct surveillance and oversee the Project’s environment.

Number of contractor’s random alcohol and urine testing and description of general results

- The Project provided alcohol/drugs-related urine tests, by arranging personnel from the concerned governmental office to do the testing. The tests, performed on December 13, 2012 included 113 tested persons.

Number of health education programs conducted for workers/laborers (covering sanitation, family planning, and prevention of communicable diseases such as HIV/AIDS).

- The Project provided knowledge during the Safety talk, a morning session before starting to work on November 13, 2012 and December 11, 2012, along with the release of information relating to protection of personnel when working in dusty and glass wool area, health effect of dust and family planning.

Operation Phase

Various project related accidents/incidents or health problems affecting local communities (which may arise from activities during operation phase imposing impacts on environmental quality such as air and water quality which may affect the community), action undertaken to address the issue.

0019254-0000566 TY:2432489.23 29

SOCIO-ECONOMICS

1. Socio-economic survey and opinion

Implementation Phase

Parameter Location Duration/Frequency Methodology

Construction and Operation

Socio-economic survey and opinion of people, community leaders and representatives of concerned agencies on the timeliness and effectiveness of the environmental and social mitigative measures and the social programs being implemented by the Company.

Communities in the vicinity area of the Nong-Saeng Power Plant Representative of concerned agencies

Every 6-months talking and interviewing with community leaders One time-survey by questionnaires

Visiting, talking, interviewing with community leaders and representatives of concerned agencies Survey by questionnaires

The environmental measures specified a survey be conducted on socio-economic status and opinion

of households, community leaders in areas around the site of Nong Saeng Power Plant, and representatives

of the related governmental agencies. The survey shall be conducted by visiting as well as discussion, and in-

depth interviews with community leaders every 6 months, and using the questionnaires once.

For the meetings and interviews with community leaders and representatives of the concerned

government agencies recorded during July to December 2012, it was found that the project had held a

meeting of the Community Participation Committee about every month. The meetings involved community

leaders, and representatives of the locals and concerned government agencies.

Socio-economic surveys were conducted during December 10-12 and 24-25, 2011, and on January 17

and 25, 2012, using questionnaires as a tool to interview community leaders, household heads or representatives,

and the concerned authorities or representatives. The interviewed households were those in communities near the

project area (within a 5-km radius around the project site) and subject to the project-related impacts. The survey

results indicated that the upcoming power plant would bring about more advantages than disadvantages to

communities.

2. Grievance Registry

Relevant party

expressing grievance

Implementation Phase/Date

received

Parties likely to facilitate grievance resolution

Nature of Grievance

Responses/Actions from the Company

Further actions needed to settle grievance and

relevant timeline - - - - - -

Note: Grievance Registry report to be included in the project report is submitted to ADB-biannually during construction, and annually during operation stage.

No Grievance Registry report during July to December 2012.

0019254-0000566 TY:2432489.23 30

3. Corporate Social Responsibility Programs (CSR Programs)

Reporting of monthly CSR activities and beneficiaries

Month Activity Target Area Target Groups

Number of Beneficiaries (segregated by gender)

Approximate cost (Indicate if

the communities/ beneficiaries

have in-kind or cash counterpart

Remarks

July Buddhist Lent tradition Temples around 5 km radius of GNS

People, leaders

1,000 120,000

August Organizing the meeting and training for Power Development Fund knowledge

People around 5 km radius of GNS

Participation Community Committee and leaders

80 85,000

September Donate for scholarship Nong Num Sai sub-district

Children in primary education

200 250,000

Donate for rice Kotchasit sub-district

People in Kotchasit sub-district

100 18,000

Organzing Environmental inspectors meeting

Environmental inspectors around 5 km radius of GNS

Environ-mental inspectors

28 72,000

October Organize the GNS Community Participation Committee meeting

People around 5 km radius of GNS

Participation Community Committee

70 72,000

November Kratin Ceremony Temples around 5 km radius of GNS

People, leaders

1,000 1,120,000

Loy Kra Tong ceremony

Temples and local around 5 km radius of GNS

People, leaders

1,000 460,000

December New Year party People around 5 km radius of GNS

People, leaders

1,500 400,000

Note: CSR report to be included in the project report is submitted to ADB-biannually during construction, and annually during operation stage.

4. Report on the purchase of property at the entrance of the power plant complex

The Gulf Holding Co., Ltd. has purchased property at the entrance of the power plant.

0019254-0000566 TY:2432489.23 31

SOCIAL PROTECTION

1. General discussion on compliance with applicable Thai labor regulations and ADB’s Social Protection Strategy which requires compliance with core labor standards. The Company, its contractors and subcontractors are covered by and will comply with Thai labor regulations which has provisions that are consistent with core labor standards. The core labor standards are the elimination of all forms of forced or compulsory labor; the abolition of child labor; elimination of discrimination in respect of employment and occupation; and freedom of association and the effective recognition of the right to collective bargaining, as per the relevant conventions of the International Labor Organization.

1.1 The Company’s performance/operation is based on Thai laws.

1.2 The project has provided adequate personal protective equipment (PPE).

1.3 Employment of labor force: the Company has opened for job applications from 18-year-old (absolutely) persons, by respecting human rights and not employing illegal labor according to the law.

1.4 Foreign labor employment: the Company has contacted the labor through an import labor company(s) to prepare the foreign labor.

2. Statistics of workers/laborers, including Company (PGS), contractors and subcontractors office workers during the reporting period

Company Total Number of

Staff/Workers Type of Staff/Worker

Information on Daily/Weekly Wage for each type of Staff/Worker

Male Female Male Female PGS Staff 7 2 Management 1 - - - Technician 5 - - - Staff - 1 Contractors 205 51 Management 20 - - - Technician 161 9 - - Staff 24 42 Subcontractors - - Management - - - - Technician - -

3. Information on whether any of the staff, workers or laborers have expressed interest to form a workers association, trade union or any form of organized groups to discuss workers rights, compensation and benefits or any issue related to their well-being.

- Provisions are made according to the laws, including social security, compensation fund, labor protection welfare and wages of the workers.

.

0019254-0000566 TY:2432489.23 32

4. Report on Power Development Fund (PDF)

PGS to ensure copy of Annual PDF Report is shared with ADB. The ADB recognizes that the Company has no direct hand in the implementation, use, and selection of projects to be funded under the fund. Annual report is expected to be shared with ADB through out the project operation stage.

The Energy Regulatory Commission still has not started to put any money into the Power Plant Development Fund because the plant construction works is not commenced yet.

5. Lawsuits Situation

Monitoring Item Current Status and likely Outcomes of Ongoing Lawsuits

Lawsuit asking for Saraburi Comprehensive City Plan implementation

A plaint was filed against the government authorities by the protesters to the Central Administrative Court on March 23, 2010, claiming for the enforcement of the Ministerial Regulation on the Saraburi Provincial Town Planning. The protesters also filed a request for a temporary injunction for suspending any government authorities to issue permits for the Project. GNS was summoned by the Court as the interpleader. On July 14, 2011, the Court dismissed a request for a temporary injunction. Currently, GNS has completely submitted the testimonies as required by the Court’s procedures and the Court issued an order for cessation of fact finding procedure on August 14, 2012.

On January 15, 2013, the Court had an order striking the case from the docket, giving the reason that since the Ministerial Regulation on the Saraburi Provincial Town Planning has been enforced, it was unnecessary for the Court to examine the case.

Lawsuit to nullify the EIA approval

A plaint was filed against the government authorities by the protesters to the Central Administrative Court on September 21, 2010, claiming for the revocation of GNS’s Factory Operation Permit and the approval on GNS’s EIA. The protesters also filed a request for a temporary injunction for suspending any activities performed in the Project area. GNS was summoned by the Court as the defendant. On March 4, 2011, the Court dismissed a request for a temporary injunction. GNS has completely submitted the testimonies as required by the Court’s procedures and the Court issued an order for cessation of fact finding procedure on October 13, 2011.

On January 31, 2013, the Court dismissed the case based on the ground that considerations made by the governmental agencies were legitimate under existing laws and regulations.