ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position...
Transcript of ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position...
![Page 1: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/1.jpg)
Project Management
CE 447 -‐ PR
OJECT
MAN
AGEM
ENT
L-‐1
3
Project Planning
![Page 2: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/2.jpg)
2
![Page 3: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/3.jpg)
Human Resources: The RACI Matrix
CE 447 -‐ PR
OJECT
MAN
AGEM
ENT
L-‐1
3
Responsible-‐Accountable-‐Consulted-‐Informed
![Page 4: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/4.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 4
March 29, 2016
Responsibility charting The RACI technique has been designed to identify
functional areas, key activities and provides management with decision points where ambiguities exist.
The approach enables management to actively participate in the process of systematically describing: - activities - decisions to be accomplished - clarity of responsibilities
![Page 5: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/5.jpg)
RACI Overview
• The purpose of the RACI process is to answer the following questions . . .
• What functions, activities, and tasks must be performed • Who must perform them and what is their level of involvement
• RACI is a highly participative process that ensures ownership of the responsibilities
![Page 6: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/6.jpg)
Human Resources: The RACI Matrix
CE 447 -‐ PR
OJECT
MAN
AGEM
ENT
L-‐1
3
Responsible-‐Accountable-‐Consulted-‐Informed
![Page 7: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/7.jpg)
Type/Degree of Participation Can Be Defined
Individual(s) (Many) who perform an acIvity or take part in a decision—responsible for acIon/implementaIon. Responsibility can be shared. The degree of responsibility is determined by the individual with the “A”
Responsible “Doer”
Accountable “Buck Stops
Here”
Consulted “In the Loop”
Informed “FYI”
Individual (One!!) who has ulImate decision making and approval authority. Typically the owner of the budget.
Individual(s) (Many) who need to have input into a decision or acIon before it occurs. This incorporates two way communication Individual(s) (Many) who must be informed that a decision or acIon has taken place. This is one way communication.
![Page 8: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/8.jpg)
![Page 9: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/9.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 9
March 29, 2016
Guidelines • Place accountability (A) and responsibility (R) at the level
closest to the action • There can only be one accountability (A) per activity • Authority must accompany accountability • Minimise the number of consults (C) and informs (I) • All roles and responsibilities must be documented and
communicated RACI A – accountable The buck stops here – yes/no authority R – responsible The doer – working on the activity C – consult In the loop – involved prior to decision/action I – Inform Keep in the picture – needs to know of the
decision/action
![Page 10: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/10.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 10
March 29, 2016
Guidelines
![Page 11: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/11.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 11
March 29, 2016
Codes
![Page 12: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/12.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 12
March 29, 2016
Process Steps
![Page 13: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/13.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 13
March 29, 2016
The Output Matrix
![Page 14: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/14.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 14
March 29, 2016
RACI Charting
![Page 15: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/15.jpg)
I C A
A
C
I
C
R
A
I
C
R
R
C
I
R
A
C
I
A
R
I
A
RACI Charting Maps Roles with Activities
Functional Role: • A position assigned or assumed to
accomplish an activity or sub-activity
Activity: • An action or
decision that is one of several sequential steps in the completion of a business process. It should always result in a clear output
![Page 16: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/16.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 16
March 29, 2016
Activity or Decision List Guidelines
![Page 17: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/17.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 17
March 29, 2016
![Page 18: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/18.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 18
March 29, 2016
![Page 19: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/19.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 19
March 29, 2016
![Page 20: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/20.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 20
March 29, 2016
Vertical analysis
![Page 21: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/21.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 21
March 29, 2016
Horizontal analysis
![Page 22: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/22.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 22
March 29, 2016
Horizontal analysis
![Page 23: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/23.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 23
March 29, 2016
Horizontal analysis
![Page 24: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/24.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 24
March 29, 2016
Get Feedback
![Page 25: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/25.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 25
March 29, 2016
Benefits
![Page 26: ProjectManagement( · RACI Charting Maps Roles with Activities Functional Role: • A position assigned or assumed to accomplish an activity or sub-activity Activity: • An action](https://reader033.fdocuments.us/reader033/viewer/2022042316/5f04944d7e708231d40eab71/html5/thumbnails/26.jpg)
© D
et N
orsk
e Ve
ritas
AS
. All
right
s re
serv
ed
Slid
e 26
March 29, 2016
The RACI