PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting...

1

Transcript of PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting...

Page 1: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

PROJECT STATUS DECEMBER 2019

Page 2: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor
Page 3: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 1 and 2-Internal flooring work in progress

Villa 36-Plastering in progress, Villa 37-

Finishing work in progress

Page 4: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 39-Finishing work in progress

Villa 38-Internal flooring work in progress

Page 5: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 40-External primer completed, Villa 41-External Plastering

completed

Villa 42-Painting work in progress

Page 6: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 43-First floor slab work completed

Villa 44-First floor column work in progress

Page 7: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 45-Finishing work in progress

Villa 46-Block work completed

Page 8: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 48-External plastering completed

Villa 50-Block work in progress

Page 9: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 51-External landscape work in progress

Villa 52-Flooring in progress,53-Finishing in progress,54-Flooring in

progress,55-Primer completed

Page 10: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 56-Funder max cladding work in progress,

Villa 57-Flooring work in progress

Villa 58-External Primer work completed, Villa 59-Flooring work in progress

Page 11: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 60-External primer completed, Villa 61-

External primer completed

Villa 77-First floor roof slab & Bock work in

progress

Page 12: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 78-Flooring in progress, Villa 79-Primer

work in progress

Villa 80-Plastering completed, Villa 82-

Plastering in progress

Page 13: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 82-Primer work completed

Villa 83-Block work in progress

Page 14: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 84-External plastering completed

Villa 86-Block work in progress

Page 15: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 87-External plastering completed

Villa 88-Finishing work in progress

Page 16: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 89-Flooring work in progress

Villa 90-Finishing work in progress

Page 17: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 91-Internal plastering work completed

Villa 92-External primer completed

Page 18: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 93-Internal flooring work in progress

Villa 94-Internal flooring work in progress

Page 19: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 95-Internal flooring work in progress

Villa 96-Block work in progress

Page 20: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 98-External plastering completed

Villa 99-Primer work completed, Villa 100-

Flooring work in progress

Page 21: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 101-Block work in progress

Villa 102-First floor roof slab completed

Page 22: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 103-First floor roof slab in progress

Villa 106-Internal flooring in progress

Page 23: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 107-Block work completed

Villa 108-External plastering completed

Page 24: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 109-Primer work completed, Villa 110-Flooring in progress

Villa 111-First floor column work in progress

Page 25: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 115-Block work completed

Villa 116-External plastering completed

Page 26: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 117-External plastering work

completed

Villa 118-Flooring work in progress

Page 27: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 119

Villa 120-Block work completed

Page 28: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 122-Block work in progress

Villa 124-External primer work completed,

Villa 125-Block work completed

Page 29: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 127-Bedroom sloped roof work in

progress

Villa 128-First floor slab work completed

Page 30: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 129-Block work completed

Villa 130-Block work in progress

Page 31: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 139-Primer work completed

Villa 140 and 141-Flooring work in progress

Page 32: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor

Villa 142-First floor sloped roof slab in progress, Villa 143-SHR slab in progress

Villa 144-External plastering completed, Villa

145-Block work in progress

Page 33: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor