PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting...
Transcript of PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting...
PROJECT STATUS DECEMBER 2019
Villa 1 and 2-Internal flooring work in progress
Villa 36-Plastering in progress, Villa 37-
Finishing work in progress
Villa 39-Finishing work in progress
Villa 38-Internal flooring work in progress
Villa 40-External primer completed, Villa 41-External Plastering
completed
Villa 42-Painting work in progress
Villa 43-First floor slab work completed
Villa 44-First floor column work in progress
Villa 45-Finishing work in progress
Villa 46-Block work completed
Villa 48-External plastering completed
Villa 50-Block work in progress
Villa 51-External landscape work in progress
Villa 52-Flooring in progress,53-Finishing in progress,54-Flooring in
progress,55-Primer completed
Villa 56-Funder max cladding work in progress,
Villa 57-Flooring work in progress
Villa 58-External Primer work completed, Villa 59-Flooring work in progress
Villa 60-External primer completed, Villa 61-
External primer completed
Villa 77-First floor roof slab & Bock work in
progress
Villa 78-Flooring in progress, Villa 79-Primer
work in progress
Villa 80-Plastering completed, Villa 82-
Plastering in progress
Villa 82-Primer work completed
Villa 83-Block work in progress
Villa 84-External plastering completed
Villa 86-Block work in progress
Villa 87-External plastering completed
Villa 88-Finishing work in progress
Villa 89-Flooring work in progress
Villa 90-Finishing work in progress
Villa 91-Internal plastering work completed
Villa 92-External primer completed
Villa 93-Internal flooring work in progress
Villa 94-Internal flooring work in progress
Villa 95-Internal flooring work in progress
Villa 96-Block work in progress
Villa 98-External plastering completed
Villa 99-Primer work completed, Villa 100-
Flooring work in progress
Villa 101-Block work in progress
Villa 102-First floor roof slab completed
Villa 103-First floor roof slab in progress
Villa 106-Internal flooring in progress
Villa 107-Block work completed
Villa 108-External plastering completed
Villa 109-Primer work completed, Villa 110-Flooring in progress
Villa 111-First floor column work in progress
Villa 115-Block work completed
Villa 116-External plastering completed
Villa 117-External plastering work
completed
Villa 118-Flooring work in progress
Villa 119
Villa 120-Block work completed
Villa 122-Block work in progress
Villa 124-External primer work completed,
Villa 125-Block work completed
Villa 127-Bedroom sloped roof work in
progress
Villa 128-First floor slab work completed
Villa 129-Block work completed
Villa 130-Block work in progress
Villa 139-Primer work completed
Villa 140 and 141-Flooring work in progress
Villa 142-First floor sloped roof slab in progress, Villa 143-SHR slab in progress
Villa 144-External plastering completed, Villa
145-Block work in progress