New Ringgold Middle School Project Slideshow May 20, 2016

Transcript of Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from...

Page 1: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

New Ringgold Middle School

Project SlideshowMay 20, 2016

Page 2: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

Started Keyway

Page 3: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

Installation of Drain

Page 4: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

Keyway Construction

Page 5: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

Keyway Construction

Page 6: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

Compaction of Material

Page 7: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

Keyway

Page 8: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

Removal of Unsuitable Soil from Site

Page 9: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

Removal of Unsuitable Soil from Site

Page 10: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

Removal of Demo Materials from Gearing Rd. Residence

Page 11: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

Exterior Light Pole Removed

Page 12: Project Slideshow May 20, 2016 - Ringgold School District€¦ · Removal of Demo Materials from Gearing Rd. Residence. Exterior Light Pole Removed • Continue Keyway Construction.

• Continue Keyway Construction.• Continue with Removal of Unsuitable Soil

from Site.• Start Sitework for Building.

Scheduled Work for Next Few Weeks