New Ringgold Middle School
Project SlideshowAugust 26, 2017
Aerial Photo from West
Provided by Hudson Group – Taken 8.16.2017
Aerial Photo from North
Provided by Hudson Group – Taken 8.16.2017
Aerial Photo from East
Provided by Hudson Group – Taken 8.16.2017
Aerial Photo from South
Provided by Hudson Group – Taken 8.16.2017
Building Areas
Provided by Hudson Group – Taken 7.29.2017
1st Floor - Area A
Reception Desk Installation – Admin Area - 1st Floor – Area A
Final Cleaning– 1st Floor – Area A
Admin Area
Cafeteria
Corridor
Work Progress – 1st Floor - Area A
Remaining Work to Complete:• Reception Desk Installation in Admin Area• Food Service Equipment Remaining Installation Items• Architect/Engineer Punchlist (Wednesday, August 30, 2017)• Ansul System Inspection (Thursday, August 31, 2017)• Final Electrical Inspection (Thursday, August 31, 2017)• Final Plumbing Inspection (Thursday, August 31, 2017)• Final Cleaning
2nd Floor – Area A
Circulation Desk Installation – Media Center - 2nd Floor - Area A
Final Cleaning– 2nd Floor – Area A
STEM Classroom
Science Classroom
Corridor
Work Progress – 2nd Floor - Area A
Remaining Work to Complete:• Circulation Desk Installation in Media Center• Contractor Punchlist Items• Final Cleaning
1st Floor - Area B
Final Cleaning– 1st Floor – Area B
Classroom
Science Classroom
Corridor
Work Progress – 1st Floor - Area B
Remaining Work to Complete:• Architect/Engineer Punchlist (Wednesday, August 30, 2017)• Final Electrical Inspection (Thursday, August 31, 2017)• Final Plumbing Inspection (Thursday, August 31, 2017)• Final Cleaning
2nd Floor - Area B
Final Cleaning– 2nd Floor – Area B
Classroom
Corridor
Work Progress – 2nd Floor - Area A
Remaining Work to Complete:• Contractor Punchlist Items• Final Cleaning
1st Floor - Area C
Final Cleaning– 1st Floor – Area C
Classroom
Science Classroom
Corridor
Work Progress – 1st Floor - Area C
Remaining Work to Complete:• Architect/Engineer Punchlist (Wednesday, August 30, 2017)• Final Electrical Inspection (Thursday, August 31, 2017)• Final Plumbing Inspection (Thursday, August 31, 2017)• Final Cleaning
2nd Floor - Area C
Final Cleaning– 2nd Floor – Area C
Classroom
Science Classroom
Corridor
Work Progress – 2nd Floor - Area C
Remaining Work to Complete:• Contractor Punchlist Items• Final Cleaning
1st Floor - Area D
Mural & Ceramic Tile Installation – Area D
Ceramic Tile Installation – Area D
Casework Installation – Area D
Ceiling Grid Installation – Area D
Ceiling Tile Installation – Area D
Ceiling Tile Installation – Band & Choral Rooms – Area D
Acoustical Panel Installation – Area D
BandGym
Auditorium
Wood Panel Installation - Auditorium – Area D
Storefront Installation – Gym Entrance – Area D
VCT Installation – Area D
Gym Floor Installation – Area D
Light Fixture Installation – Area D
Duct Sock Installation – Gym - Area D
GRD Installation – Restrooms - Area D
Ductwork Insulation – Area D
Interior Work Progress – 1st Floor - Area DWork Completed• Electrical Rough In• Gym Speaker Installation• Gym Sound System Installation• Plumbing Rough In• Plumbing Piping Insulation• Plumbing Fixture Installation• HVAC Piping Installation• HVAC Ductwork Installation• Sprinkler Piping Installation• Rolling Grille Installation• Locker Bases• Locker Installation• Translucent Panel Installation• Window Installation• Cement Board InstallationWork in Progress• Light Fixture Installation• HVAC Insulation Installation• HVAC Controls• Sprinkler Head Installation• Stage Equipment Installation
• Support for Acoustical Panels• Auditorium Acoustical Panel Installation• Auditorium Chair Installation• Locker Installation• Bulkhead Installation• Interior Door Frame Installation• Block Filler• Drywall Installation• Toilet Partition Installation• Display Case Installation• Painting• Exterior Door Installation• Ceramic Tile Installation• Gym Equipment Installation• Toilet Accessory Installation• Ceiling Grid Installation
• Wood & Metal Door Installation• Auditorium Wood Panel Installation• Signage Installation• Ceiling Tile Installation• VCT Installation• Gym Floor Installation
EIFS Installation
Gym Entrance
Loading Dock
Concrete Sidewalk Installation
HS Entrance 2
Along West Roadway
Concrete Sidewalk at Retaining Walls 4A & 4B
Concrete Curbs
Placing Topsoil
Asphalt Binder Course
Guard Rail Installation
• Complete Countertop Sink Installation • Complete Casework Installation• Complete Countertop Installation• Complete Food Service Equip. Installation• Finish Ceiling Tile Installation – Area D• Complete Flooring Installation – Area D• Finish Gym Wood Floor Installation• Stage Floor Installation • Complete Metal Door Installation• Complete Wood Door Installation• Finish Site Concrete• Asphalt Paving • Continue Installing Topsoil• Site Landscaping
Scheduled Work for Next Few Weeks