Transcript of project report AKSHAY 1000 PARTNER.xlsx
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
1/47
PROJECT REPORT
OF
DIGVIJAY ENGINEERS
BUSSINESS ADDRESS
PLOT NO. G-39/7/2, MIDC WALUJ
AURANGABAD - 431006
ENGINEERING JOB WORKAREA : 1393 SQ MTRS
DIRECTOR
1. SHRIRAM SHAMRAO SHINDE
2. ANIL ATMARAM SHINDE
SCHEME AT:
MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION
( MIDC )
MIDC WALUJ
AURANGABAD
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
2/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
3/47
INTRODUCTION : -
a) Name of the Unit GOLDENDREAM BUILDCON PVT. LTD.
b) Constitution
c) Name of the Applicant 1. SANTOSH S. MUTHIYAN2. VINOD P. SHARMA
d) Communication Address D-5, API COMPOUND, MIDC CHIKALTHANA,
AURANGABAD - 431006
e) Address of location of unit PLOT NO. E-20,
MIDC CHIKALTHANA, AURANGABAD
f) Qualification
g) Age
h) Experience KNOWS THE LINE
i) Capacity 1000 p.w.
j) Power requirements 40 H.P.
k) Man Power requirements 50 ( 3 SHIFTS )
L) COST OF PROJECT 89.99975 ( IN LAKHS )
M) ACTIVITY TO BE STARTED TO SETUP INFORMATION TECHNOLOGY
UNIT
N) REMARKS GOOD SCOPE IN ABOVE LINE OF BUSINESS
O) SPECIAL FACTORS THIS LOCATION IS SELECTED AS IT IS
SURROUNDED BY FASTEST DEVLOPING
AREA IN INDUSTRIES WITH REQUIRED
INFRASTRUCTURES. SO REQUIREMENT
OF THE FACILITY WILL HAVE & SCOPE
OF BUSINESS WILL BE VERY HIGH.
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
4/47
7
DIRECT WAGES AND LABOUR CHARGES
PARTICULARS NOS. SALARY TOTAL SALARYSUPERVISOR 2 15000 30000
WORKS MANAGER 2 12000 24000
SKILLED WORKERS 10 8000 80000
UNSKILLED WORKERS 10 6000 60000
WATCHMEN 0 4000 0
TOTAL 24 45000 194000
ADD: 20% OTHER BENEFITS 38800
TOTAL 232800
TOTAL YEARLY 2793600
SO WAGES FOR NEXT 5 YEARS WILL BE WITH 10% INCREASE IN EVERY YEAR
Rs.
I st year 2793600
II nd year 3072960
III rd year 3380256
IV th year 3718282
V th year 4090110
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
5/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
6/47
10
STATEMENT OF FIXED ASSETS & DEPRECIATION
( DEPRECIABLE ASSETS )
YEARS PARTICULARS BUILDING FURNITU MACHINERY TOTAL
RATE @ RE @ @
10% 10% 15%
1 COST OF ASSETS/PROPER 40.00 1.06 22.00 63.06
Less : Depreciation 4.00 0.11 3.30 7.41
CLOSING BALANCES 36.00 0.95 18.70 55.65
2 COST OF ASSETS/PROPER 36.00 0.95 18.70 55.65
Less : Depreciation 3.60 0.10 2.81 6.50
CLOSING BALANCES 32.40 0.86 15.90 49.15
3 COST OF ASSETS/PROPER 32.40 0.86 15.90 49.15
Less : Depreciation 3.24 0.09 2.38 5.71
CLOSING BALANCES 29.16 0.77 13.51 43.44
4 COST OF ASSETS/PROPER 29.16 0.77 13.51 43.44
Less : Depreciation 2.92 0.08 2.03 5.02
CLOSING BALANCES 26.24 0.70 11.48 38.42
5 COST OF ASSETS/PROPER 26.24 0.70 11.48 38.42
Less : Depreciation 2.62 0.07 1.72 4.42
CLOSING BALANCES 23.62 0.63 9.76 34.01
6 COST OF ASSETS/PROPER 23.62 0.63 9.76 34.01
Less : Depreciation 2.36 0.06 1.46 3.89
CLOSING BALANCES 21.26 0.56 8.30 30.12
7 COST OF ASSETS/PROPER 21.26 0.56 8.30 30.12
Less : Depreciation 2.13 0.06 1.24 3.43
CLOSING BALANCES 19.13 0.51 7.05 26.69
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
7/47
OTHER PRODUCTION EXPENSES 8
REPAIRS & MAINTENANCE 100000
INSURANCE 1000000
CONSUMABLE & OTHER EXP. 100000
TOTAL 1200000
SO NEXT 5 YEARS THE OTHER PRODUCTION EXPENSES WILL BE AS BELOW WITH 10% INCREASE
IN EVERY YEAR
Rs.
I st year 1200000
II nd year 1320000
III rd year 1452000
IV th year 1597200
V th year 1756920
SELLING AND ADMINISTRATIVE EXPENSES
A) SALARIES TO ADMINISTRATIVE STAFF
PARTICULARS NOS. SALARY TOTAL SALARY
PER MONTH PER YEAR
ACCOUNTANT 1 20000 240000
CLERK 2 8000 192000
PEON 2 5000 120000
TOTAL 5 33000 552000
ADD: 20% OTHER BENEFITS 110400
TOTAL A) 662400
B) OTHER EXPENSES
RENT 500000
LEGAL & PROFESSIONAL CHARGES 200000
PRINTING & STATIONERY 30000
TRAVELLING & CONVEYANCE 50000
MISCELLANEOUS EXPENSES 36000
BANK COMMISSION & OTHER CHARGES 50000
TOTAL B 366000
TOTAL ( A + B ) 1028400
SO THE ADMINISTRATIVE EXPENSES FOR THE NEXT 5 YEARS WILL BE AS BELOW 10% INCREASE
IN EVERY YEAR Rs.
I st year 1028400
II nd year 1131240
III rd year 1244364
IV th year 1368800
V th year 1505680
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
8/47
1
SCHEDULE NO. 1
FINANCIAL VIABILITY
PARTICULARS TOTAL
COST OF PROJECT IN LAKHS
LAND 1393 M2 @ 1575 21.94
BUILDING 40
PLANT AND MACHINERY 22
FURNITURE 1.06
WORKING CAPITAL 5
TOTAL 90.00
MEANS OF FINANCE
DIRECTORS CAPITAL 25% 22.50
TERM LOAN FROM BANK 75% 67.50
TOTAL 100% 90.00
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
9/47
2
PROFITABILITY STATEMENT
SCHEDULE NO. 2
PRATICULARS I YEAR II YEAR III YEAR IV YEAR V YEAR
A) SALES REVENUE 731.5 1278.20 2022.79 2987.79 4218.27
SALES
TOTAL A 731.5 1278.20 2022.79 2987.79 4218.27
B) COST OF PRODUCTION
COST OF RAW MATERIAL 550.00 990.00 1573.00 2329.25 3294.23
LABOUR 27.94 30.73 33.80 37.18 40.90
POWER AND FUEL 27.94 30.73 33.80 37.18 40.90
OTHER PRODUCTION EXPENSES 12.00 13.20 14.52 15.97 17.57
SELLING & ADMIN. EXPENSES 10.28 11.31 12.44 13.69 15.06
INT. ON TERM LOAN 10.12 8.10 6.07 4.05 2.02
INT. ON UNSECURED LOAN 0.00 0.00 0.00 0.00 0.00
INT. ON WORKIG CAPITAL 0.75 0.90 1.05 1.20 1.35
DEPRECIATION 7.41 6.50 5.71 5.02 4.42
646.44 1091.47 1680.40 2443.55 3416.44
ADD. OPENING STOCK 0.00 38.50 69.30 110.11 163.05
646.44 1129.97 1749.70 2553.66 3579.49
LESS. CLOSING STOCK 38.50 69.30 110.11 163.05 230.60
TOTAL B 607.94 1060.67 1639.59 2390.61 3348.90
C) NET PROFIT 123.56 217.53 383.20 597.18 869.38
D) TAXATION 30.89 54.38 95.80 149.30 217.34
E) PROFIT AFTER TAX 92.67 163.15 287.40 447.89 652.03
ADD. DEPRECIATION 7.41 6.50 5.71 5.02 4.42
100.08 169.65 293.11 452.91 656.45
LESS. REPAYMENT OF TERM LOAN 23.62 21.60 19.57 17.55 15.52
SURPLUS AVAILABLE 76.45 148.05 273.53 435.36 640.92
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
10/47
3
DEBTS SERVICE COVERAGE RATIO
SCHEDULE NO. 3
PARTICULARS I YEAR II YEAR III YEAR IV YEAR V YEAR
A) NET PROFIT 92.67 163.15 287.40 447.89 652.03
DEPRECIATION 7.41 6.50 5.71 5.02 4.42
INTEREST ON TERM LOAN 10.12 8.10 6.07 4.05 2.02
TOTAL A 110.20 177.75 299.18 456.96 658.47
B) INTEREST ON TERM LOAN 10.12 8.10 6.07 4.05 2.02
REPAYMENT OF TERM LOAN 23.62 21.60 19.57 17.55 15.52
TOTAL B 33.75 29.70 25.65 21.60 17.55
DSCR ( A/B ) 3.27 5.98 11.66 21.16 37.52
AVERAGE OF DSCR 50
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
11/47
SCHEDULE NO. 4 4
CASH FLOW STATEMENT
PARTICULARS I YEAR II YEAR III YEAR IV YEAR V YEAR
A) SOURCE OF FUNDS:1)NET PROFIT BEFORE TAXES WITH INTEREST 107.34 202.43 369.33 584.65 858.27
ADDED BACK BUT AFTER DEPT.&INVEST ALLOW
2) PROMOTERS & FRIENDS CAPITAL INVEST. 0 0 0 0 0
3) DEPRECIATION 7.41 6.50 5.71 5.02 4.42
4) INVESTMENT ALLOWENCES 0 0 0 0 0
5) INCREASED IN LONG TERM LOAN 0 0 0 0 0
6) INCREASE IN DEFERRED PAYMENT FACILITIES 0 0 0 0 0
7)INCREASE IN UNSECURED LOANS & DEPOSITS 0 0 0 0 0
8) INCREASE IN BANK BORROWING FOR
WORKING CAPITAL 5 5.75 6.61 7.60 8.75
9) SALE OF FIXED ASSETS 0 0 0 0 0
10) OCTROI REFUND, SALES TAX REFUND 0 0 0 0 0
INCENTIVES
11) OTHERS 0 0 0 0 0
TOTAL A 119.75 214.68 381.65 597.28 871.43
PARTICULARS I YEAR II YEAR III YEAR IV YEAR V YEAR
B) UTILISATION OF FUNDS
1) INCREASE IN FUNDS 0 0 0 0 0
2) INCREASE IN CAPITAL EXPENSES 0 0 0 0 03) INCREASE IN CURRENT ASSETS 5 10 15 20 25
INVENTORIES & DEBTORS, ETC,
4) DECREASE IN LONG TERM LOAN 0.00 0.00 0.00 0.00 0.00
5) DECREASE IN UNSECURED LOAN &
DEPOSITS 0 0 0 0 0
6) WITHDRAWALS BY THE PROPRIETOR 2.25 2.59 2.98 3.42 3.94
7) INCREASE IN INVESTMENT
8) INTEREST 10.87 9.00 7.12 5.25 3.37
9) TAXATION 30.89 54.38 95.80 149.30 217.34
10) BORROWING
11) OTHERS EXPENSES
TOTAL B 49.02 75.97 120.90 177.97 249.65
C) OPENING BALANCE 0.00 38.50 69.30 110.11 163.05
D) NET SURPLUS ( A-B ) 70.73 138.71 260.75 419.31 621.77
E) CLOSING BALANCE 70.73 177.21 330.05 529.42 784.82
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
12/47
SCHEDULE NO. 5 5
PROJECTED BALANCE SHEET
PARTICULARS I YEAR II YEAR III YEAR IV YEAR V YEAR
LIABILITIES
OWN CAPITAL 22.50 25.87 29.76 34.22 39.35
TERM LOAN FROM BANK 23.62 21.60 19.57 17.55 15.52
CASH CREDIT FROM BANK 0.00 0.00 0.00 0.00 0.00
PROFIT & LOSS 0.00 0.00 0.00 0.00 0.00
PAYABLE 550.00 990.00 1573.00 2329.25 3294.23
TOTAL 596.12 1037.47 1622.33 2381.02 3349.10
ASSETS
FIXED ASSETS
NET BLOCK OF ASSETS 55.65 49.15 43.44 38.42 34.01
CURRENT ASSETS
RECEIVABLES 359.74 708.98 1170.74 1769.17 2532.54
STOCK 55.00 99.00 157.30 232.93 329.42
INVESTMENT & ADVANCES 55.00 99.00 157.30 232.93 329.42
CASH & BANK BALANCES 70.73 81.34 93.55 107.58 123.71
TOTAL 596.12 1037.47 1622.33 2381.02 3349.10
0.00 0.00 0.00 0.00 0.00
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
13/47
DETAILED PROJECT REPORT
1. INTRODUCTION
Aurangabad and surrounding is developing very fast due to fast industrialisation in this area viz.,Aurangabad estate, waluj, chikalthana & shendra. The said industrial area is already established
with many multinational like SCODA and automobile industries like BAJAJ AUTO and Auto ancillaries
unit like VERROC, ENDURANCE etc. beside there is also many pharma companies and Breveries
companies surrrounded in all this industrial area , hence opening a unit in this area is very much
benificery due to good infrastructure for growing new industries in this area.
2. PROMOTERS PROFILE
NAME OF APPLICANT AMIT MANGESH KULKARNI
ADDRESS AURANGABAD
PROPOSED LOCATION MIDC SHENDRA
EDUCATION GRADUATE
EXPERIENCE KNOWS THE LINE
PROPOSED ACTIVITY ENGINEERING PRODUCTS
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
14/47
DETAILED PROJECT REPORT ( DPR)
1. INTRODUCTION
Aurangabad and surrounding is devloping very fast Industrialisation in this
area viz. , Aurangabad estate, Waluj, Chikalthana & shendra. The said
industrial area is already established with many multinational like SCODA
and automobile industries lie BAJAJ AUTO and Auto ancillaries unit VERROC,
ENDURANCE etc, beside there is also many Pharma companies and Breveries
companies surrounded in all this industrial area, hence opening a unit in this
area is very much benificary due to good infrastructure for growing new
industries in this area.
2.PROMOTERS PROFILE
NAME OF PARTNERS 1.SHRIRAM SHAMRAO SHINDE
2. ANIL ATMARAM SHINDE
ADDRESS H-53, MIDC WALUJ, AURANGABAD
PROPOSED LOCATION PLOT NO. 39/7/2,
MIDC WALUJ, AURANGABAD
EDUCATION KNOWS THE LINE
EXPERIENCE KNOWS THE LINE
PROPOSED ACTIVITY ENGINEERING JOB WORK
3. CONSTITUTION OF THE COMPANY
PARTNERSHIP FIRM
4. REGISTRATION DETAILS
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
15/47
5. UNIT REGISTRATION DETAILS
The unit is registered in PART - I EM with
registration number as follows
6. EXISTING BUSINESS OF THE PROMOTERS AND DETAILS THEREOFThe proprietor is an men enterpreneurs and belonging to an business family having business in
engineering industries, many of the persons required various engineering material which is
used on the construction business etc so they own required various engineering material
which is used on construction site . As the promoter is itself in the engineering material manufacturing
business from last 5-10 yrs in manufacturing in slotted angles etc. so he need land to
start the engineering manufacturing material manufacturing business which will be suppliedto various engineering contractors etc.
7. LOCATION AND ITS SELECTION
Location of the unit is at MIDC WALUJ , Tq. Dist. Aurangabad the said location has been selected
as is ts surrounded by fastest developing area in construction , industries viz. five star Shendra
Industrial Area , Chikalthana Industrial Area etc. and in construction shopping center, appartments,
corporate office in short it in the new aurangabad zone. As all this construction sites are nearer to
the project so requirment of the product will be heavy and scope for business will very high.
8. DETAILS OF PRODUCTS WITH CAPACITIES
The unit will manufacture product which are required on engineering site as foolows :Slotted angles, etc. and related other engineering products the production
capacity of all this product will be a per order given by the contractors.
9. DETAILS OF RAW MATERIAL REQUIREDRaw material required for he products will be mainly bolts, head blocks, etc. as this material is easily
available in the local market and for bulk contract the raw material can be directly order from factory
from the nearest power plant and can also be purchased from local dealer as per requirment.
10. MARKETS AND ITS ANALYSIS
Our said product will be required in construction site where there is huge requirement of the productwhich are hughy required by manufacturing companies for making machines . Due to this various
merits of the product there is huge demand and at present there are very few manufacturer of this
product in this area.
11. IMPLEMENTION SCHEDULE WITH TIME CHART
As the proposal is a transfer case where already a prepared shed will be purchased.
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
16/47
9
INTEREST CHARGES & REPAYMENT OF LOAN
It's proposed to raise a sum of Rs. 903.44/- (IN LKHS) meet requirement Term Loan from Bank.
It is proposed to pay interest on Term Loan @ 15% p.a. and on Cash Credit Loan @ 15%p.a.
First year requested for a moratorium period, next six years shall be pay back period in qurterly interest
& principal also. The below mentioned table gives abstract of data of interest and installments payable
& expected outstanding balances at the end of each year, amount will be repaid within installmnts
five yearly equal and last installments are recovered out of fixed deposits with interest.
YEARS OPENING Interest Principal Total Closing Balances
Balances Amount Amount Repayment
I 67.50 10.12 Moratorium 10.12 67.50
II 67.50 10.12 13.50 23.62 54.00
III 54.00 8.10 13.50 21.60 40.50
IV 40.50 6.07 13.50 19.57 27.00
V 27.00 4.05 13.50 17.55 13.50
VI 13.50 2.02 13.50 15.52 0.00
INTEREST ON WORKING CAPITAL
YEARS LOAN AMOUNT INTEREST @
RS. IN LAKHS 15%
I 5 0.75
II 6 0.9
III 7 1.05
IV 8 1.2
V 9 1
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
17/47
0
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
18/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
19/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
20/47
133.1
25000
0
0
0
0
0
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
21/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
22/47
16000
10000
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
23/47
2000
1670
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
24/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
25/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
26/47
67.50
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
27/47
236.39 328.50 451.59 ### 816.57
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
28/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
29/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
30/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
31/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
32/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
33/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
34/47
6
SALES REVENUE STATEMENT
PARTICULARS I II III IV V
Total no. of production 1000 1100 1210 1331 1464.1
Cost of production/day 100000 150000 200000 250000 300000
Gross turnover in yr 100000000 165000000 242000000 332750000 439230000
Avg. rate of raw 85 85 85 85 85
material
SALES VALUE 140000000 231000000 338800000 465850000 614922000
SALES VALUE IN LAKHS 1400 2310.00 3388.00 4658.50 6149.22
PARTICULARS I II III IV V
UILISATION CAPACITY 55% 60% 65% 70% 75%
PRODUCTION 77000000 138600000 220220000 326095000 461191500
ADD: OPENING STOCK 0 3850000 6930000 11011000 16304750
77000000 134750000 213290000 315084000 444886750
LESS CLOSING STOCK 3850000 6930000 11011000 16304750 23059575
TOTAL SALES VALUE 73150000 127820000 202279000 298779250 421827175
TOTAL SALES VALUE 731.5 1278.20 2022.79 2987.79 4218.27
IN LAKHS
COST OF RAW MATERIAL CONSUMED
PARTICULARS I YEAR II YEAR III YEAR IV YEAR V YEAR
CAPACITY
UTILISATION 55% 60% 65% 70% 75%
COST OF 55000000 99000000 157300000 232925000 329422500
PRODUCTION
COST OF 550 990.00 1573.00 2329.25 3294.23PRODUCTION IN LAKHS
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
35/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
36/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
37/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
38/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
39/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
40/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
41/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
42/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
43/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
44/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
45/47
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
46/47
5.5 24000
1570000
314000
1256000
-
7/30/2019 project report AKSHAY 1000 PARTNER.xlsx
47/47
0