Project Report 11

76
 PROJECT REPORT ON th  MONTH INDUSTRIAL TRAINING GODREJ BOYCE MFG. CO. LTD, APPLIANCES DIVISION, MOHALI, PUNJAB  SUBMITTED BY: PARMEET SINGH ROLL. NO. 11103335 B.TECH MECHANICAL ENGG.) GROUP- 4ME6 UNIVERSITY COLLEGE OF ENGINEERING PUNJABI UNIVERSITY PATIALA PUNJAB

description

na

Transcript of Project Report 11

  • 5/25/2018 Project Report 11

    1/76

    PROJECT REPORTON

    thMONTH INDUSTRIAL TRAININGGODREJ BOYCE MFG. CO. LTD,

    APPLIANCES DIVISION,MOHALI, PUNJAB

    SUBMITTED BY:PARMEET SINGH

    ROLL. NO. 11103335B.TECH MECHANICAL ENGG.)

    GROUP- 4ME6

    UNIVERSITY COLLEGE OF ENGINEERINGPUNJABI UNIVERSITY PATIALAPUNJAB

  • 5/25/2018 Project Report 11

    2/76

    INDEX

    Sr. No. DESCRIPTION

    1 DECLARATION

    2 ACKNOWLEDGEMENT3 INTRODUCTION OF THE ORGANIZATION

    4 PRODUCTS

    5 PARTICULARS OF THE MOHALI PLANT

    6 5S SYSTEM IN GODREJ

    7 KAIZEN

    8 INTRODUCTION ABOUT PLANT AND ALLOTED

    DEPARTMENT9 PROJECT NO 1

    10

    11

    PROJECT NO 2

    PROJECT NO 3

    12 REFERENCES

  • 5/25/2018 Project Report 11

    3/76

    DECLARATION

    I, Parmeet Singhstudent of B.Tech (Mechanical Engg)at University

    college of engg. Punjabi university, Patiala. hereby declare that the

    report on industrial training and project work entitled GODREJ &

    BOYCE MFG. CO. LTD is the result of my own work. I also

    acknowledge the other works / publications cited in the report.

  • 5/25/2018 Project Report 11

    4/76

    ACKNOWLEDGEMENT

    I am extremely grateful to Mr. Abhishek sharma (HOD, CMS & ST

    Dept.), Godrej And Boyce Mfg. Co. Ltd., and Mohali for providing this

    opportunity to carry out project work in the company.

    I would also like to thank, Mr. Gurpreet singh and Mr.Sudhir, for

    providing me infrastructural facilities to work with, without which this

    would not have been possible.

    I would like to express my deepest sense of gratitude to all members of

    Compressor Plant for their generous guidance, help and useful

    suggestions as a project guide, and showing faith in my work.

    Parmeet Singh

    UCOE, Punjabi university ,Patiala

    (11103335)

  • 5/25/2018 Project Report 11

    5/76

    Introduction of the organizationThe Godrej Group

    Inception

    Established in 1897, the Godrej group has grown in India from the days of the

    charkha to nights at the call centers. Our founder, Ardeshir Godrej, lawyer-turned-

    locksmith, was a persistent inventor and a strong visionary who could see the spark

    in the future. His inventions, manufactured by his brother Pirojsha Godrej, were

    the foundation of todays Godrej Empire. One of Indias most trustedbrand,

    Godrej enjoys the patronage and trust of around 500 million Indians every single

    day. Our customers mean the world to us. We are happy only when we see a

    delighted customer smile.

    With 7 major companies with interests in real estate, FMCG, industrial

    engineering, appliances, furniture, security and agri careto name a fewour

    turnover crosses 3.3 billion dollars*. You think of Godrej as such an integral part

    of Indialike the bhangara or the kurtathat you may be surprised to know that

    26% of our business is done overseas. Our presence in more than 60 countries

    ensures that our customers are at home with Godrej no matter where they go. Withbrands you can believe in, service excellence you can count on and the promise of

    brighter living for every customer, Godrej knows what makes India tick today.

    Today, we are at a point in Godrejs history when our amazing past is meeting up

    with its spectacular future head on. Godrej is learning and relishing being young

    again.

    A. PRODUCTS

    1. Godrej Appliances Division manufactures and markets, today; a range of

    refrigerators from 100 liters to jumbo sized 400 liters. The largest selling is the 170

    liters size. The 100 liters baby addresses the need of a small family or a second

    refrigerator for a growing family. It also addresses the needs of the Institutional

  • 5/25/2018 Project Report 11

    6/76

    and Hotel industry segment. The 300 liters size is the most suitable for the typical

    large Indian family.

    2. Each of the major sizes of the refrigerators is made in different models,

    primarily created to address the requirements of different segments of customerswith differing balance among taste, usage and cost considerations. Cold Gold and

    Ultra are designed with the taste of the up-market customers, whereas the Classic

    packs the best value for money for a customer with focus on economy with

    efficiency and no frills. All the models and sizes are made in a range of colors that

    reflect the choice of the different segment of customers.

    3. Keeping in tune with the changing technology and the distinct needs of the

    upwardly mobile urban market, GODREJ APPLIANCES DIVISION has launched

    four models of Frost - Free (165, 240, 260 and 400) refrigerators using indirectcooling technology. These models also are in tune with the latest styling and taste

    of softer looks and pastel colors, in harmony with the trend's worldwide.

    4. The range, colors and the models are never static and it is always the

    tradition of GODREJ APPLIANCES DIVISION to constantly upgrade the existing

    products, its range and bring to the market the latest to satisfy the ever changing

    expectations of customers. The latest model GODREJ APPLIANCES DIVISION

    introduced is the Jerry model.

    5. GODREJ APPLIANCES DIVISION also offers a range of washers from

    semi-automatic twin tub (5 kg & 3 kg) type to fully automatic or Fuzzy logic and

    Pulsate type single tub models. As with refrigerators, the washers are also made

    available in different colors to suit the taste of the customers. Washers are

    manufactured at Wing Works.

    6. GODREJ APPLIANCES DIVISION have introduced a range of ACs(manufactured and sourced) from 0.75 TR to 1.5 TR window AC's and 1.5 TR

    splits. The AC's are made available with trendy looks (grills) to enhance the

    interiors and in different colors.

  • 5/25/2018 Project Report 11

    7/76

    B. DESIGN AND DEVELOPMENT

    1. GODREJ APPLIANCES DIVISION understands that the quality is built

    into the product rather than just inspected at the end of the production. Towards

    this end, GODREJ APPLIANCES DIVISION has a well-qualified and experienced

    team of design engineers who convert the expectations of the customers into a

    concrete product. Their knowledge is constantly upgraded through training and

    exposure as well as access of technology from collaborators. The documented

    system for design development supports their knowledge, experience and

    creativity.

    2. GODREJ APPLIANCES DIVISION also out sources product designs,

    designing activities or aesthetics and styling concepts from experts in India or

    abroad. Although the specific designing activity may be done by such experts, the

    larger intent of the design and development requirements are supplemented /

    complemented by design verifications, design validations, design reviews and

    design changes through the in-house Design, Quality, PMQ and NBD teams. Such

    external experts / sources are approved by Design in consultation with the

    management with executive responsibility.

    C. QUALITY

    1. Throughout the design, manufacturing and testing of the appliances total

    attention is paid to the quality aspects of the product. Besides the incoming

    inspection co-ordinate by the Purchased Material Quality Cell (PMQ) and the in

    process monitoring by line function of manufacturing, the system has built in

    audits of the product and the processes at different stages by Quality Eng. Dept. to

    assure quality and provide fast feedback.

  • 5/25/2018 Project Report 11

    8/76

    2. The End-of-Line Audit (EOLA) offers feedback on continues basis to the

    manufacturing as regards the quality of the finished products. The Customer

    Acceptance Test and Customer Usage Test Laboratory give confidence that theproducts meet functional and reliability requirements. The Life Testing Laboratory

    for compressor and other appliances / components provides data and facts about

    the reliability under adverse operating conditions.

    3. The facilities are ably supported by a number of laboratories to analyze the

    material and other inputs. These consist of the Plastic Lab, the Oil and Fresno Lab,

    Powder Coating Lab, Metrology Lab, Metallurgy Lab, the Calibration Lab and

    Shipping test Lab.

    4. The data from the laboratories, tests and the audit feedback is constantly

    analyzed and corrective and preventive actions are taken to improve the

    performance of refrigerators in the field and processes that build them in house.

    5. The documented system in this Apex Quality Manual spells out, in the

    following chapters, in elaborate details, the procedures, processes and the system

    in place to support the quality aspects.

    D. MARKETING AND DISTRIBUTION

    1. GODREJ APPLIANCES DIVISION understands that availability and access to

    the consumers is critical for their satisfaction in this business. 19 branches in five

    regions with the dealership network of app. 1200 direct dealers and over 3000

    retailers support the marketing, selling and distribution across the whole country.

  • 5/25/2018 Project Report 11

    9/76

    The logistics department ensures the physical distribution to feed branches, and

    they in turn feed the dealer network.

    2. The branch and dealer network are also the channels of information to get the

    feedback on the consumer satisfaction, emerging expectation and the competitive

    offerings so that the product range and the introduction of varieties of models and

    colors are in tune with the changing market trends.

    E. SERVICE SUPPORT

    1. Product in the field, in the hands of the consumers, needs the support of

    education and training at the time of installation for deriving maximum benefits

    during use. It is equally essential for the consumers to understand the care and

    caution to minimize the inadvertent misuse that may lead to product malfunction

    and possible injury to the users.

    2. And should the need arise, the service back up is geared to diagnose and rectify

    the product problems during and even after the warranty period, either at the user's

    premises or if required, at the workshop with minimum disturbance to the

    customers. The service organization is adequately equipped to provide spare parts

    for the current and prior models in the use in the field through dealers and the

    branch network. The service set up also provides the training and education

    support to the dealer network so that they in turn can extend the same level of

    service to their customers.

    3. GODREJ APPLIANCES DIVISION believes that the field personnel are the

    important source of information and hence seek their feedback on the product

  • 5/25/2018 Project Report 11

    10/76

    performance on a regular basis, which forms the trigger for continuing

    improvements of the products and the processes.

    F. PURCHASING

    GODREJ APPLIANCES DIVISION understands that to be able to satisfy the

    ultimate consumers, it needs quality inputs from the vendors. Vendors are the

    partners in this process and therefore, GODREJ APPLIANCES DIVISION puts

    considerable emphasis on their development through clear communication,education and early involvement in product development stages, rather than just

    the monitoring and control through feedback from incoming inspection.

    G. PEOPLE

    People provide the inner strength to GODREJ APPLIANCES DIVISION. The

    organization takes pride in the fact that it has some of the best people in place to

    achieve the objectives of Technology leadership, quality and market presence. It

    has in place, a process of recruitment and training to groom the best talent. The

    welfare of the people is paramount for GODREJ APPLIANCES DIVISION,

    accordingly the company has invested substantially in the housing, medical and

    education support for the employees and their families.

  • 5/25/2018 Project Report 11

    11/76

  • 5/25/2018 Project Report 11

    12/76

  • 5/25/2018 Project Report 11

    13/76

  • 5/25/2018 Project Report 11

    14/76

  • 5/25/2018 Project Report 11

    15/76

  • 5/25/2018 Project Report 11

    16/76

    PRODUCTS

    AppliancesOfferings in the refrigerator, washing machine, air conditioner and microwave

    oven ranges.

    FMCG

    Cinthol, Good Knight mosquito repellent, Hair Color and Hair Dye.

    Agri

    Animal feed, oil palm plantations, agrochemicals and poultry.

  • 5/25/2018 Project Report 11

    17/76

    Batteries

    Godrej and GP Batteries offer a range of zinc chloride, alkaline & rechargeable

    batteries and a range of chargers.

    Construction

    Variety of construction services like real estate development, ready mix concrete,

    horticulture and enviro-tech.

    IT & Software Solutions

    Solutions for engineering and service industry.

  • 5/25/2018 Project Report 11

    18/76

    Material Handling

    Counter balance trucks, forklift trucks, tyre handlers, all terrain trucks, attachments

    and accessories.

    Precision Engineering

    Critical custom-built precision engineering equipments for multiple applications.

    Process Equipment

    High pressure vessels, heat exchangers, columns, heavy walled reactors and other

    custom.

  • 5/25/2018 Project Report 11

    19/76

    Storage Solutions

    Warehousing solutions, automation and consulting.

    Vending

    High quality table top beverage vending machines, services and beverages.

    Furniture

    Furniture for home, office, educational institutions, establishments, labs,

    hospitals, shipyard.

  • 5/25/2018 Project Report 11

    20/76

    Real Estate

    Residential, commercial and township developments.

    AV Solutions

    Display solutions, audio video conferencing solutions, electronic copy boards.

    Chemicals

    Oleo chemicals and surfactants.

  • 5/25/2018 Project Report 11

    21/76

    Electricals and Electronics

    Industrial automation, power distribution, compressed air solutions & green

    business commissioning.

    Locks

    Locking solutions for different security needs to ensure optimum safety.

    Motors

    Specialized custom built compressor motors.

  • 5/25/2018 Project Report 11

    22/76

    Precision Systems

    Machining & fabrication, heat & surface treatment, assembly, testing & supply of

    complex.

    Security Solutions

    Safes, lockers, banking automation products, electronic security systems, premises

    security & hi-tech doors.

    .

  • 5/25/2018 Project Report 11

    23/76

  • 5/25/2018 Project Report 11

    24/76

    PARTICULARS OF THE MOHALI PLANT

    PLOT SIZE : 75 ACRES

    CAPABILITY : 5 LACS

    PRODUCTIVITY : REFRIGERATORS

    INVESTMENT : Rs 120 CRORES

    MANPOWER : 1300

    INAUGRATED BY : S. HARCHARAN SINGH BRAR

    INAUGRATION ON : 28THFEBRUARY, 1996.

  • 5/25/2018 Project Report 11

    25/76

    5S SYSTEM IN GODREJ

  • 5/25/2018 Project Report 11

    26/76

    1. Sort (Organization)

    Clearly distinguish needed items from unneeded items and eliminate the latter.

    2. Set in order (Orderliness)

    Keep needed items in the correct place to allow for easy and immediate retrieval.

    3. Shine (Cleanliness)

    Keep the workshop swept and clean.

    4. Standardize (Standardize clean-up)

    This is the condition we support when we maintain the first four pillars.

    5. Sustain (Discipline)

    Make a habit of maintaining established procedure.

  • 5/25/2018 Project Report 11

    27/76

    KAIZENKaizen(

    ?), Japanese for "improvement", or "change for the better" refers to

    philosophy or practices that focus upon continuous improvement of processes in

    manufacturing, engineering, and business management.

    http://en.wikipedia.org/wiki/Help:Installing_Japanese_character_setshttp://en.wikipedia.org/wiki/Help:Installing_Japanese_character_setshttp://en.wikipedia.org/wiki/Help:Installing_Japanese_character_sets
  • 5/25/2018 Project Report 11

    28/76

    There are three plants in this division these are:

    1.COMPRESSORPLANT

    2.REFRIGERATOR PLANT

    3.WASHINGMACHINE

  • 5/25/2018 Project Report 11

    29/76

    ALLOTED DEPARTMENT

    COMPRESSOR PLANT

    COMPRESSOR

    A refrigerant compressor is a machine used to compress the vaporized

    refrigerant from the evaporator and to raise its pressure so that the corresponding

    saturation temperature is higher than that of cooling medium. It also continually

    circulates the refrigerant through the refrigerating system. Since the compressor of

    refrigerant requires some work to be done on it, therefore, a compressor must be

    driven by some prime mover.

    Since the compressor virtually takes the heat at low temperature

    from the evaporator and pump it at high temperature to the condenser, therefore, it

    often referred as Heat Pump.

    COMPRESSOR

  • 5/25/2018 Project Report 11

    30/76

    ASSEMBLEDCOMPERSSOR

  • 5/25/2018 Project Report 11

    31/76

    The various components of reciprocating compressor:-

    1. Shell

    2. Cover

    3. Body

    4. Stator

    5. Rotor

    6. Cylinder Head

    7. Piston

    8. Shaft/Crank

    9. Connecting Rod

    10.Gudgeon Pin

    11.Lock Pin

    12.Spring

    13.Oil Tube

    14.Muffler

    15.Valve plate

    16.Reed

    17.Retainer

    18.Suction Gasket

    19.Suction Reed

    20.Discharge Gasket

    21.MS Plug

    22.Oil Cup

    23.Relay Guard

    24.Glass Seal Terminal25.Discharge Tube

    26.Suction Tube

    27.Charging Tube

    28.Coil/Port Cover

    29.Nylon Ferrule

  • 5/25/2018 Project Report 11

    32/76

    30.Bolts

    31.Piston Washer

    32.Shaft Washer

    33.Copper bolt Washer

    34.Holding Rubber

    35.Stopper

    36.Stopper Plate

    37.Port Cover Washer

    38.Pedestal

    39.Muffler Rubber

    The compressor plant is divided into various departments

    Compressor Machine Shop

    Surface treatment

    Metrology Department

    Assembly Department

    Unit Shell Department

    Maintenance Department

    Tool Room

    Store

    Cutting Section

    Quality Department

  • 5/25/2018 Project Report 11

    33/76

    Layout of the Compressor Plant

  • 5/25/2018 Project Report 11

    34/76

    COMPRESSORMACHINESHOP

    In this department , there are various machines are used

    to perform various operations on mainly 6 parts of

    compressor. These parts are:

    COMPRESSOR BODY

    SHAFT

    VALVE PLATE

    CONNECTING ROD

    PISTON

    G PIN

  • 5/25/2018 Project Report 11

    35/76

    1. COMPRESSOR BODY:- It is made of cast iron material come

    from vendor NEWMAN & SATYAM.

    Machines in cms shop in body line :-

    Machine 1-EMT 682

    Machine 2-EMT 683

    Machine 3-EMT 684

    Machine 4-EMT 685

    Machine 5-EMT 686

    Machine 6-EMT 687

  • 5/25/2018 Project Report 11

    36/76

    Machine 1-EMT 682:- It is a SPM(special purpose machine) doing

    variety of different operatins on same workpiece. there are 14 stations onthis machine. The description of machine tool and its operation is as

    follows:

    s.no Station Tool description operation

    1 2H Insert:TCMT 110204 Hub facing and outer dia

    chamfer

    2 2V Insert:M 8065 1204 Head face rough milling

    3 3H Insert: OFKR 070408 Leg face rough milling

    4 4H CARTRIDGE:STSCL 10CA11

    Insert:TCMT 110204

    Shaft hole drill and outer dia

    turning

    5 4V Insert:M 8065 1204 Head face semi finish milling

    6 5V SOLID CARBIDE DRILL DIA24*134 Piston hole drilling

    7 6H STEPPED DRILL- M35 Leg hole centering

    8 7H CARTRIDGE:SCGCR12 CA 12

    INSERT:CCMT120408

    Leg face facing

    9 8H HSS DRILL DIA 4.5 MM

    COUNTER SINK TOOL

    Shaft hole chamfer and leg ho

    drilling

    10 9H CARBIDE BRAZED HOLE MILL Shaft hole milling and leg hole

  • 5/25/2018 Project Report 11

    37/76

    Fig-front view of machine EMT682

    Fig body after 1 machine

  • 5/25/2018 Project Report 11

    38/76

    Machine 2-EMT 683:-it is a second machine of body line.it do 11

    operations on the body. It is also a SPM. The description of machine tool and its

    operation is as follows:

    s.no Station Tool description operation

    1 2H CENTER DRILL M-35 Gas hole drilling

    2 2V INSERT:CCMT09T308

    INSERT:CCMT120408

    Seat facing and

    chamfering

    3 3H Insert:TCMT 060204

    HSS DRILL 5.1MM JOBBER

    SERIES

    Port hole drilling and

    conter boring

    4 4H TWIST DRILL M35

    HSS DRILL 4.5MM LONG SERIES

    Gas hole drilling

    5 5V HSSE SILVER CUT TOP M06 Port hole tapping

    6 6V END MILL CARBIDE BRAZED U slot milling

    7 7H HSS DRILL DIA 5.1MM JOBBER

    SERIES

    Leg relief hole drilling

    8 7V HSS MARKING TOOL Body marking

    9 8H HSS HOLE MILL REAMER Gas hole reaming

    Fig-front view of machine EMT683

  • 5/25/2018 Project Report 11

    39/76

    Machine 3-EMT 684:-it is a third machine in body line.it do 2

    operations on the body. It is also a SPM The description of machine tool and its

    operation is as follows:

    s.no Station Tool description operation

    1 HSS DRILL DIA 5MM LONG

    SERIES

    HSS COUNTER SINK TOOL

    DIA 33MM

    DRILLING AND CHAMFERING

    Fig-body after machine 3 Fig- machine EMT684

  • 5/25/2018 Project Report 11

    40/76

    Machine 4-EMT 685:-it is a third machine in body line.it do 5operations on the body. It is also a SPM It is also a SPM The description of

    machine tool and its operation is as follows:

    s.no Station Tool description operation1 2H FACE MILL DIA 80MM Head face finish milling

    2 3H INSERT:CCMT09T308 Piston hole semi finish bore

    3 3V Insert:CCMT 060204

    Insert:TCMT 110208

    Shaft hole semi finish bore

    4 4H Insert:CCMT 060204

    Insert:TCMT 090208

    CARTRIDGE:STSCR 08CA 09

    Piston hole finish bore

    5 4V Insert:TGCT 060104

    CARTRIDGE:STSCR 08CA 09

    Insert:TCMT 06T108KF

    CARTRIDGE:STSCR 08CA 09

    Shaft hole semi finish bore

    Fig- machine EMT68

  • 5/25/2018 Project Report 11

    41/76

    Machine 5-EMT 686:-It is a third machine in body line. It do 7operations on the body. It is also a SPM

    s.no Station Tool description operation

    1 2H CENTER DRILL Gas hole center drill

    2 2V STEPPED DRILL Head hole centering

    3 3H TWIST DRILL M-35 Gas hole drilling

    4 4H TWIST DRILL M-35 Head hole reaming

    5 5V REAMER M-35 Gas hole reaming

    6 6V HOLE MILL M-35 Head hole milling

    7 7H MACHINE TAP M-35 Head hole tapping

    Fig - Front view of machine EMT686

  • 5/25/2018 Project Report 11

    42/76

    Machine 6-EMT 687:-It is a third machine in body line.it do 1operation on the body. It is also a SPM.

    s. no Station no. Tool description Operation

    1 1 MACHINE TAP M-35 Legs tapping

    machine EMT687

    body after machine 6

  • 5/25/2018 Project Report 11

    43/76

    SHAFT CELL

    Machine 1kingsburry :It is a simple machine used for drilling

    operations. There are basically 4 stations on this machine. The kingsburry

    machine is used for drilling opretations.the description of machine is as follows:

    s.no Station no. operations1 2h Drill of 2mm at lower side

    of counter at large end

    Drill of

    2 3h Drill 3mm at upper side of

    counter at small end

    3 4h Small grooveat upper side

    of counter at small end

    4 5h Drill of 4mm at lower side

    of counter at large end

    In above table 2h,3h,4h.5h are various stations here H is direction in

    which machine works i.e horizontal.

    kingsburry machine

  • 5/25/2018 Project Report 11

    44/76

    Different models of shaft :-

    Fig-17 shaft model i8 Fig-18 shaft model i9 Fig-19 shaft model i10

    Machine 2:-deep hole drilling :

    This machine is second machine in shaft cell. This machine is used for drilling

    the hole of 5mm at the large end of shaft. There are basically two machines in

    this unit .the other machine will make the hole of 6mm at the top of small end

    of shaft. These shafts are differentiated according to their mdeli.e i8,i9,i10. The

    major difference is in the counter of the shaft. More heavier the counter more

    will be the suction and discharge capacity of the compressor.

  • 5/25/2018 Project Report 11

    45/76

    GRINDING ROOM

    MACHINE-1 WMW :

    It is a centreless cylindrical grinding machine

    with PLC panel installed with it. There are basically two grinding wheels which

    are to grind the large end of the shaft in microns. The different units installed

    are lubrication unit, hydraulic unit, electrical panel unit. The main grinding

    wheel rotate in clockwise direction while shaft large end rotate in anti clockwise

    direction and counter wheel rotate in clockwise direction. For safety of workers

    the safety gaurds are installed at the front of the machine.for checking the

    grinding cut in microns . There is bakers gauge installed for checking the

    finishing of shaft large end after grinding. 6 jet of air are located insinde thethrough which the finishing of shaft is checked.

  • 5/25/2018 Project Report 11

    46/76

    wmw centreless cylindrical grinding machine

    MACHINE-2 CNC MACROMATIC GRINDING

    MACHINE:-It is a CNC grinding machine with PLC panel installed withit.The different units installed are lubrication unit, hydraulic unit, electrical

    panel unit. There is only one grinding wheel for grind the small end of the shaft.

    The shaft is inserted into the jaws of adjustable chuck(adjusted according to the

    different models of compressor).The main grinding wheel and shaft rotate indifferent direction to each other.

    CNC MACROMATIC GRINDING MACHINE

  • 5/25/2018 Project Report 11

    47/76

    MACHINE-3 PISTON GRINDING:-The piston is the main part ofthe compressor. There is different piston for different compressor according to

    the size and capacity of compressor.

    PISTON

    Piston Grinding Machine

  • 5/25/2018 Project Report 11

    48/76

    OTHER COMPONENTS OF COMPERESSOR

    1.Oiltube: This is a metallic tube which is used to lubricate the shaft andother components like conn rod, piston, G pinEtc. As the rotor rotates the

    centrifigual force will be produced as oil tube is fitted in bottom end of shaft

    and it sucks oil to lubricate.

    Oil Tube

    2.Muffler cap:-Muffler cap is used for directioning the gas into thecompressor after the whole cycle completion. There is small restriction on oneside of this cap so that even a single particle of dust containing moisture will be

    eliminated.the one ond is attached to the cylinder head and a rubber cap is

    fitted at one lower end of muffler

    Muffler Cap

  • 5/25/2018 Project Report 11

    49/76

    3.Piston :-The piston is the main part of the compressor.There is differentpiston for different compressor according to the size and capacity of

    compressor.

    Piston

    4. stator and rotor : The stator is rotatory windning of aluminiumwiring. The rotor is fitted in stator with the help of hydraulic press in assembly

    shop. As the voltage of 170 watts is given to the comperessor the rotor rotates

    in stator and rotate other assembly with itself.

    Stator Rotor

  • 5/25/2018 Project Report 11

    50/76

    SURFACETREATMENT

    After machining of the component, the components are sent for a

    surface treatment. Surface treatment is done in order to prevent the

    component from the rust and coating of shaft. The components are

    treated with various chemicals like Nutrapon, Rustoken 25. In a

    surface treatment area, the small components like oil tube, spring etc

    are cleaned in a small component cleaning machine.

    I n sur face treatment, shaft is coming after al l

    maching operation coating is done in various steps.

    Wet tumbling

    This is a vibrater in which ceramic media is vibrating along with shafts .This is used to remove the burr on shafts.

  • 5/25/2018 Project Report 11

    51/76

    Dry tumbling

    After dry tumbling , shafts is again vibrating with dry media for polishing

    and finishing the shafts. Then shafts is degreasing in ultrasonic heater for

    removing some amount of dirt etc .

    Mn. PHOSPHATING COATING SYSTEM OF SHAFTS

    In the system , there are 12 no. of tanks . It provide coating on

    shafts . These Tanks are:

    1. DEGREASING 12. DEGREASING 23. DEGREASING 34. WATER RINSE5. ACTIVATION 16. ACTIVATION 27. PHOSPHATING18. PHOSPHATING 29. WATER RINSE 210.PASSIVATION11.OVEN 112.OVEN 2

  • 5/25/2018 Project Report 11

    52/76

    Chemical require in tanks to make Mn.

    Phospating system :

    TANK CHAMICAL QUANTITY CHANGE IN

    1. DEGREASING-1

    Nutrapon 1 Ltr. After 1 week

    2. DEGREASING-2

    Nutrapon 1 Ltr. After 1 week

    3. DeGREASING-3

    Nutrapon Ltr.

    After 1 week

    4. WATERRINSE-1

    D.M water Fully tank Over flow

    5. ACTIVATION ParocolinMn.(Powder) 1K.g After 3 days6 . PHOSPATING Parcolubricate+Nutralizer(Powder)

    20 Ltr.+20 cup(And checkpointage)

    After 15 days

    7.WATER RINSE-2

    D.M water Fully tank Over flow

    8. PASSIVATION Nutrapon 1 Ltr. After 3 days

    ACTUAL pointage,ph and temp. of tanks :SOURCE POINTAGE PH TEMP.

    DEGREASING-1 - 8-10 50-60

    DEGREASING-2 - 8-10 50-60

    DEGREASING-2 - 8-10 50-60

    PH.= 1. FA= 2.TA= iron point

    =grain size

    0.8-1.2 }6-8} ratio=6-10

    1-3

  • 5/25/2018 Project Report 11

    53/76

    Tank of Chemical require to make BODY LINE

    TANK CHAMICAL QUANTITY CHANGE IN

    1.HOT SPRYDEGRESING

    NUTRPON 2 LTR. IN EVERYPRT

    After 1 week

    2. HOTDEGRESING

    NUTRPON 1 Ltr. After 1 week

    3. WATERRINSE

    D.M water Fully tank After 1 days

    4. ACID TNK RESTOKAM 270 Ltr. After 4/5 days

    5. supprypssivtion

    WCI 02 1-1 ltr in evry prt One shift

    6DERUSTLK-1 DERUSTLK-1 30 LTR. After 1 week

    7 supprypssivtion

    supprypssivtion

    1-1 ltr in evry prt One shift

    8 Pssivtion WCI 02 1 Ltr. After 1 week

  • 5/25/2018 Project Report 11

    54/76

    UNITSHELL

    The process flow diagram for a compressor in the compressor unit

    shell department is shown below.

    Raw materialfrom supplier to

    PMQ

    Degreasing ofshell and cover

    Spot andProjectionWelding

    Shell and cover

    cleaning

    Assembly

    Feeding

    MAG Welding

    Leak Testing

    Dip PaintingDehydration

    loop1

    1stPurging

    Dehydrationloop 2

    2ndPurging Oil Charging

    Final Testing(P.D.I.)

    Storage andDispatch

  • 5/25/2018 Project Report 11

    55/76

    Raw Material From the Supplier

    There are two suppliers for the raw shell and cover namely Satyam and

    Newman.

    The material is first inspected for quality by the PMQ(Purchase Material

    Quality) Department before it is transferred to USD(Unit Shell and Dome)

    Department for processing. The defective or poor quality material is rejected

    by PMQ. Only the ok material is transferred to the USD.

    Raw material

  • 5/25/2018 Project Report 11

    56/76

    Degreasing of Shell and Cover (Pre Treatment)

    The raw shell and cover that arrive from the supplier are oily and dusty,

    so they need to be cleaned before they can be processed. So, they are

    passed through a shower of chemical known as Surfakleen 399X andthen the excess chemical is rinsed off through a shower of normal water.

    This all happens in a tunnel.

    The chemical and water are stored in tanks so that they can be

    recirculated as the process continues. The tanks are cleaned and refilled

    with chemical and fresh water after a week.

    After this, they pass through an oven known as Pre Treatment oven for

    drying of water. The temperature in the oven is set at 190oC.

    Degreasing of shell & cover

  • 5/25/2018 Project Report 11

    57/76

    Spot and Projection Welding

    Various child parts are welded on the shell and cover for proper functioning and

    ease of manufacturing.Child part on cover

    In cover, two hook type stoppers are welded in order to keep the internal

    compressor assembly in position.

    Following table shows the defects and there effects on compressor:-

    Defects Effects

    Poor weld

    strength

    1. Stopper broken2. Compressor motor damage

    Stopper

    height

    variation / tilt

    1. Compressor body touching

    2. Compressor jam

    All these lead to the absolute failure/rejection of compressor.

    Electrode material used is Be-Cu alloy because of its hardness. Previously Cu-Zn-Cr

    alloy was used but it was

    softer, so it weared out quickly.

  • 5/25/2018 Project Report 11

    58/76

    Child parts on shell

    In shell, various child parts like MS Pin, Oil Cup, Shell Mounting Bracket, GST

    (Glass seal Terminal) and Relay Guard are spot welded.

    Charging, Discharge and Suction tubes are projection welded.

    Below table shows various defects in child parts on shell and their effects on

    compressor and its working.

    Child

    Part

    Defects Effects

    MS Pin

    Poor weld strength.

    CD out

    Broken pin leading to instability of compressor

    assembly

    Compressor getting noisy

    Oil Cup

    Poor weld strength.

    Position out

    Broken oil cup

    Oil pin hits oil cup. Fitting of assembly not possible.

    Bracket

    Poor weld strength.

    Position out

    Broken bracket

    Problem in mounting on refrigerator

    GST

    Poor weld strength.

    Glass seal broken

    GST broken

    Leakage from GST. Leads to rejection of compressor

    Relay

    Guard

    Poor weld strength.

    Position out

    Relay Guard broken

    Problem in mounting on refrigerator.

    Tubes

    Poor weld strength

    Position out

    Tubes broken

    Leakage from tubes

    The welding temperature at various spot welding machines is in the range of 2000oCto 3000

    oC with current ranging from 20KA to 46KA.

  • 5/25/2018 Project Report 11

    59/76

    Shell and Cover CleaningThe shells and covers are installed on conveyers and they move through 10 different tanks

    as a cleansing process. Following table show the tanks in order from 1 to 10. The 11th

    tank

    is the air blower.

    Hot waterSurfakleen 399X

    Normal water

    Normal water

    Surfapickle-77

    Normal water

    Normal water

    Protobond 40/5

    Normal water

    Surfalyte 8M

    Air blower

  • 5/25/2018 Project Report 11

    60/76

    Functions of different chemicals:-

    Surfakleen 399X The major ingredient in this chemical is Caustic Soda. Itsfunction is to remove the grease and oil initially prevails on the shell and cover.

    Surfapickle 77 The major ingredient in this chemical is Phosphoric acid. Itsfunction is to avoid rusting and provide invisible pores on the surface of shells

    and covers so that the further chemical can form a coat on them.

    Protobond 40/5This chemical enters into the pores present on shell and cover.

    Surfalyte 8MIt is used as a passivation chemical so that the shells and coversdont react when come in contact with air or other particles.

  • 5/25/2018 Project Report 11

    61/76

    Assembly Feeding StationHere discharge tube is bent to 90

    oand the cover is punched with appropriate code

    according to the model before being fed to the assembly.

    After these operations, the operator cleans the surface of the shells and covers andputs them on the conveyer that takes it to the assembly.

    Cover Punching Machine

    It is used to punch the codes on the cover. These codes represent the models of the

    compressors.

    This is a hydraulically operated machine.

    Some of the punches with their models are shown below:-

    Punch Model

    A2 A1-1

    B2 B1-1

    Z I8CC

    Y I9CC

    X I10CC

    U I8AA

  • 5/25/2018 Project Report 11

    62/76

    MAG WeldingIt is a welding process in which an electric arc forms between a consumable wire

    electrode and the work piece metal, which heats the work piece, causing them to

    melt, and join.

    Along with the wire electrode, a shielding gas is fed through the welding gun, which

    shields the process from contaminants in the air. There are a total of 8 MAG

    Welding machines.

    Some important points-

    Shielding gasCO2

    ElectrodeCopper coated MS wire

    Overlap is done to prevent leakage

    Anti spatter gel is used to avoid the formation of spatters

    Properties of gel-

    Silicon free

    Non-toxic

    Inflammable

    Odourless

    Time taken by 8 MAG machines in welding a single compressor is shown

    below-

    MAG

    machinenumber

    Including lanter Excluding

    lanter

    Total

    production

    Lap 1 Lap

    2

    Lap 3 Average Only welding

    1 54.66 53.97 52.63 53.75 46.00 315(approx.)

  • 5/25/2018 Project Report 11

    63/76

    2 51.53 51.57 51.19 51.43 47.37 315(approx.)

    3 53.88 53.41 53.62 53.64 46.13 320(approx.)

    4 50.22 49.12 50.12 49.82 46.94 320(approx.)

    5 43.53 42.97 42.36 42.62 42.09 400(approx.)

    6 47.62 47.75 47.94 47.77 46.31 400(approx.)

    7 46.28 47.53 49.90 47.90 46.97 400(approx.)

    8 42.48 41.78 42.06 42.11 39.00 400(approx.)

    Leak Testing

    The welded compressors are then checked for leakages by immersing in water.

    If a leak is found it is repaired and then again leak tested.

    Dip PaintingRubber caps are applied on the tubes, the GST and the Relay Guard in order to

    prevent them from paint. Also to prevent the paint from entering inside the

    compressor through tubes. After that, it is loaded on the other conveyer which

    takes it to the paint tank for dip painting.

  • 5/25/2018 Project Report 11

    64/76

    Dip painting is done so that an even coat of paint is applied on the compressor

    and to ensure cost effectiveness.

    The paint is the normal door paint that is used at our homes.

    Immediately after that the compressor enters the P.D. (paint drying) ovenwhich heats the compressor at 250oC in order to dry off the paint.

    Dehydration Loop 1

    Immediately after drying of paint, an operator removes the rubber caps and

    the compressor enters the dehydration oven. This oven heats the compressor

    at 250oC in order to remove moisture from the inner assembly of the

    compressor.

    Removal of moisture from the compressor is necessary in order to prevent

    rusting or any kind of a chemical reaction of the inner parts because that

    would lead to improper functioning of the compressor and therefore would

    result in absolute rejection of the compressor.

  • 5/25/2018 Project Report 11

    65/76

    1st Purging

    In this process, dry air is made to pass through the compressor assembly in

    order to remove any amount of moisture left after dehydration loop 1. It is

    made to enter the compressor from charging tube and exits the compressorfrom discharge and suction tubes.

    Dehydration Loop 2

    The purged compressor enters dehydration oven 2 for dehydration again. The

    reason for dehydration again is the quality aspect of the compressor and to ensurean entirely moisture free compressor. The temperature in this oven is again set at

    250oC.

  • 5/25/2018 Project Report 11

    66/76

    2nd Purging

    Similar to 1stpurging, dry air is made to pass through the compressor assembly in

    order to remove any amount of moisture left in the compressor.

    Immediately after this rubber caps are applied on the tubes in order to preventexternal air from entering the compressor.

    Oil Charging

    When the dew point of the compressor becomes -38, it comes to the Oil

    Charging area where 2 different types of oils are charged depending upon the

    type of the compressor. These are shown below.

    R134a Compressor Saffson oil (250ml)

    Isobutane Compressor Freezol oil (170ml)

    Oil Cleaning Station

    The oil that comes from the supplier contains moisture quantity of 100ppm.

    This needs to be purified to an appropriate level (50-60ppm) in order to be

    charged in the compressor.

  • 5/25/2018 Project Report 11

    67/76

    1) CENTRIFUGAL PROCESS:

    It is used for removing the moisture and impurities present in oil.

    Firstly the oil is heated to a temperature of 100oC which removes most

    of the moisture present in the oil. Then it is made to fall on a rotating

    disc in which the impurity particles are removed. It is a 10 hour long

    process during which the oil is re circulated in the tank.

    2)CLEANTANK:

    Cleantank is used to remove the carbon and some other impurity

    particles that remain in the oil after the centrifugal process. In this

    process current is passed through the oil in a tank which is containing

    filters. During the process the impurity particles are collected on the

    filters due to the generation of magnetic field inside the tank.

    Final Testing (Pre Dispatch Inspection)

    The compressor is finally checked at this station for visual and internal

    defects.

    It is made to run at 200 volts at 2850 rpm.

    The operator checks for the discharge pressure and compressor efficiency at

    this station.

  • 5/25/2018 Project Report 11

    68/76

    Storage and Dispatch

    The OK compressors from PDI move to storage area from where they are

    dispatched to various customers.

  • 5/25/2018 Project Report 11

    69/76

    PROJECT 1:To Reduce The Residue of Body

    And Small Components.

    Residue level of body and small components .

    Components Qty. Ideal Residue Value Max. accept value

    BODY 5 9mg. 9mg.

    CYLINDER HEAD 25 12mg. 25mg.

    OIL TUBE 25 10mg. _

    SPRING 50 13mg. _

    PORT BOLTS 50 12mg. _

    STATOR BOLTS 50 15mg. _

    NYLON FERRUIE 100 12mg. _

    LOCK PIN 25 8mg. _

    Procedure to check the Residue level

    For testing the residue level of sub components . There are following

    steps:

    First of all measure the initial weight of filter paper .

  • 5/25/2018 Project Report 11

    70/76

    Take component in proper quantity and wash with

    Tetrachloroethylene (300mg.) in beaker .

    Attach filter paper in conical shape with funnel .

    After washing components chemical is filter by this filter paper Take 4-5 hours for dry the filter paper .

    Then take final weight of filter paper.

    So, Residue level = Final weightinitial weight (mg.)

    Chemical use in testing Tetrachloroethylene or Plorochloroethylene.

    How to clean bodyThere are 9 no. of tanks in body line for cleaning the body. These are:

    TANKS CHEMICALS

    1.HOT SPRAY DEGREASING NUTRAPON

    2.HOT DEGREASING NUTRAPON

    3.WATER RINSE D.M WATER

    4.ACID RESTOKAM

    5.SPRAY PASSIVATION WCI 02

    6.DERUSTALK-1 DERUSTALK-1

    7.SPRAY PASSIVATION WCI 028.PASSIVATION WCI 02

    9.HOT PASSIVATION WCI 02

  • 5/25/2018 Project Report 11

    71/76

    How to reduce body residue

    First of all, maintain the temp. of tank no.1, 2 & 3 at (50-60). Proper working of diaphragm pumps of tank no. 5 & 7.

    Proper level of chemical in tanks.

    Proper working of blowers.

    Attach new shower in tank no. 1, 5 & 7 for proper spray on body.

    Change chemical at particular day.

    How to reduce residue of small components

    There are 2 ultrasonic heaters for cleaning of small components.

    There are trays and hangers for attach components separately.

    Temp. Of heater at 50-60.

    Chemical uses are nutrapon and neutralizer.

    Always ON ultrasonic when dip the components.

    Dip these components at min. 120 sec.

    Improvement in residue

    After collecting the data, we obtain body residue 7.5mg. , 5.5mg. ,

    6.4mg. , 8.1mg. , spring 8.7mg. , oil tube 8.2mg. , cylinder head 15.2mg.

    etc.

  • 5/25/2018 Project Report 11

    72/76

    PROJECT2: Modification in stopper to reduce

    stopper defects.

    Modification in stopper

    The stopper currently being used prevents the spring out situations of the compressor

    assembly.

    Recently a large increase in rejection of the compressor was observed due to not pumping

    defect. This defect is a cause of broken discharge tube. The reason for breaking of

    discharge tube is still being searched. In order to reduce the rejection, something had to

    be made to prevent the body from touching the discharge tube.

    So, a new stopper design was made that would prevent both horizontal and vertical

    movement of the body in extreme conditions. This design is still in process of analysis

    and has yet not been finalised.

    BEFORE AFTE

  • 5/25/2018 Project Report 11

    73/76

    PROJECT3:Analysis of defects seen in components

    CRANK SHAFT

    Left out (operator mistake) under size (operator mistake)

    Casting defect Small groove (drill not working proper)

  • 5/25/2018 Project Report 11

    74/76

    Connecting rod

    Blow hole (casting defect) over size (large cut)

    Reamer step not clean Lining (honing not proper)

  • 5/25/2018 Project Report 11

    75/76

    Valve plate

    Seat damage Plate burnt (due to heating)

    Left out (grinding not proper) Seat burnt (due to heating)

  • 5/25/2018 Project Report 11

    76/76

    REFERENCES

    www.godrej.com

    www.wikipedia.com

    www.micromaticgrinding.com

    www.docstoc.com

    http://www.godrej.com/http://www.godrej.com/http://www.wikipedia.com/http://www.wikipedia.com/http://www.micromaticgrinding.com/http://www.micromaticgrinding.com/http://www.docstoc.com/http://www.docstoc.com/http://www.docstoc.com/http://www.micromaticgrinding.com/http://www.wikipedia.com/http://www.godrej.com/